REC327-4346 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: establish a fleet maintenance framework to ensure regular update of District Service Agreements with local councils. |
REC327-4347 | 36 - Volunteers | By December 2023, the Rural Fire Service should: develop a strategy to ensure that local brigade volunteers are adequate in numbers and appropriately trained to operate fleet appliances in the RFS Districts where they are required. |
REC327-4350 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: develop a fleet enhancement framework and strategy that is informed by an assessment of current fleet capability to respond to fire incidents, and research into the most appropriate technologies and appliances to address emerging and future fire risks across NSW. |
REC327-4345 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: review and improve processes for timely recording of fleet asset movements, locations, and maintenance status. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4320 | 12 - EM agency and authority | Knowledge resources to support flood management: That, to provide more accurate and complete data for flood threat identification, warning and modelling systems, Government through the proposed new NSW Reconstruction Authority (NSWRA) work with the Australian Government to: |
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
REC324-4314 | 8 - Communications and warnings | PIFAC function: That, to ensure the community can better understand the threat of flood, storm and tsunami activity, the Department of Customer Service (DCS) be made accountable for PIFAC in all emergencies. This will improve access to clear, reliable and consistent messaging prior to and during emergencies. This transfers the PIFAC role from NSW Police Force to Service NSW. Under this PIFAC function, DCS would be responsible for: |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4315 | 36 - Volunteers | The Community First Responders Program: That, to better coordinate community efforts to save life and property during a disaster, Government create a ‘Community First Responders Program’, funding appropriate community equipment and training, particularly in high-risk catchments along the east coast of NSW. This training would be delivered by combat and/or other appropriate government agencies. This program could support and empower community led initiatives such as disaster response, evacuation centres and the provision of services such as psychological first aid. |
REC324-4307 | 9 - Community education | Flood education: That, to build disaster resilience in future generations as floods and other natural disasters are a fact of Australian life, the Department of Education should design, implement and deliver an evidence-based, targeted education campaign (like sun exposure) in schools (new disaster curriculum). |
REC324-4298 | 37 - Funding | Housing and development funding options: That, to empower vulnerable people and communities to avoid significant impacts from flood as well as drive broader investment in adaptation, Government through NSWRA: |
REC324-4316 | 12 - EM agency and authority | Resilience NSW and recovery: That, in order to enhance NSW disaster preparedness, response and recovery, and meet the needs of the people of NSW prior to, during and after a disaster, and provide clarity on agency roles and responsibilities, Resilience NSW be reshaped to ‘Recovery NSW’. The new agency will be more streamlined and agile to drive recovery in the first 100 days post disaster. To achieve this, Resilience NSW’s functions should be reallocated as follows: |
REC324-4309 | 12 - EM agency and authority | SES and RFS back-office merger: That, to help protect life and property across NSW in storm and flood events, and to improve resourcing and NSW State Emergency Service (SES) frontline capability, Government implement, before the next storm season, a merger of the SES and NSW Rural Fire Services (RFS) back-office and corporate service functions, while maintaining their separate legislative identity, brand, uniform and volunteer membership. This ‘joined-up’ RFS/SES corporate support structure would be under the command of the RFS given its corporate and operational maturity and would be responsible for: |
REC324-4301 | 32 - Doctrine, standards, and reform | Floodplains as assets: That, to establish the capacity and maximise the economic, social and environmental potential and consequently unlock the value of NSW floodplains, Government adopt the following guiding principles for floodplain management: |
REC324-4317 | 32 - Doctrine, standards, and reform | Flood rescue capability: That, to help improve the protection of life across NSW in flood events: |
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
REC324-4302 | 32 - Doctrine, standards, and reform | Disaster adaptation plans for all towns: That, to establish realistic expectations of safe spaces to live and deliver much needed housing quickly, Government through NSWRA working with local government: |
REC324-4318 | 12 - EM agency and authority | Permanent SEOCON: That, to improve NSW’s ability to prepare and respond to floods and other disasters, Government establish a new Deputy Commissioner of NSW Police Force to take on permanently the SEOCON role. This role, in addition to current SEOCON functions, would be responsible for: |
REC324-4313 | 8 - Communications and warnings | NSW disaster app: That, to improve community confidence in government messaging and warnings, the SEOCON and DCS develop a single ‘NSW disaster app’. This: |
Rec-ID | Code | Recommendation | |
---|---|---|---|
REC323-4287 | 34 - Local knowledge | That the NSW State Emergency Service, in partnership with the Bureau of Meteorology, investigate ways in which local communities and local media with local knowledge can play a stronger role in flood predictions and warnings. |
|
REC323-4264 | 34 - Local knowledge | That the NSW Government work in partnership with key Aboriginal stakeholders, including the Jali Local Aboriginal Land Council, to prioritise the rebuild of Cabbage Tree Island, and ensure a safe and resourced evacuation plan is in place. |
|
REC323-4275 | 34 - Local knowledge | That the NSW Government, in partnership with community groups, including First Nations groups, develop initiatives to build community resilience, particularly in regions at high risk of future natural disaster events. |
|
REC323-4288 | 8 - Communications and warnings | That the NSW Government work with the Commonwealth to develop a national cross-agency app to integrate all community services and agencies into a single platform so that everyone can receive accurate and timely information from one source during emergencies. |
|
REC323-4265 | 34 - Local knowledge | That the NSW Government work with First Nations peoples to support Aboriginal organisations in their capacity to operate and respond in times of natural disasters. |
|
REC323-4281 | 37 - Funding | That the NSW Government allocate funding to the improvement of the Pitt Town Evacuation Route and other key possible evacuation routes in Sydney's northwest. |
|
REC323-4276 | 34 - Local knowledge | That the NSW Government ensure that community groups, both existing and emerging, including First Nations groups, are well integrated into disaster recovery, by incorporating them into state recovery plans and engaging with them in between and in the lead up to natural disasters. |
|
REC323-4290 | 20 - Role of police | That the NSW Government embed into its emergency plans the appointment of a senior police officer with combat experience to lead recovery efforts following natural disasters. |
|
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
|
REC323-4282 | 16 - Training and behaviour | That the NSW Government invest in the required personnel, training and vessels to ensure that all agencies involved in flood rescue can be mobilised to their fullest potential. |
|
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
|
REC323-4291 | 12 - EM agency and authority | That the NSW Government consider abolishing Resilience NSW if it is unable to ensure: |
|
REC323-4270 | 37 - Funding | That the NSW Government consider entering into a service agreement with an organisation that has the resources and capacity to manage donations and activate quickly during natural disasters. |
|
REC323-4283 | 8 - Communications and warnings | That the NSW Government work with the community broadcasting sector to identify ways in which community broadcasters could be better supported to provide critical services during natural disasters, with a view to providing them adequate long term funding. |
|
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
|
REC323-4279 | 37 - Funding |
|
|
REC323-4292 | 12 - EM agency and authority | That the NSW Government consider a restructure of the NSW State Emergency Service with consideration to: realigning the focus of the organisation to harness local knowledge and networks; coordinating more closely with other rescue agencies to bolster its capacity to respond; and increasing salaried staff and resources, and driving volunteer recruitment. |
|
REC323-4272 | 37 - Funding | That the NSW Government ensure that flood affected individuals can continue to access financial assistance for as long as there is demonstrated need. |
|
REC323-4284 | 8 - Communications and warnings | That the NSW Government review its public awareness and communication strategies in relation to natural disasters. |
|
REC323-4261 | 37 - Funding | That the NSW Government advocate through the National Cabinet to widen eligibility under the Disaster Funding Recovery Arrangements to allow local councils to build back better. |
|
REC323-4280 | 37 - Funding | That the NSW Government work with local governments to identify alternative routes to vulnerable roads, and that the NSW and Australian Governments fund the construction of these important routes to improve evacuation and access options in times of disaster. |
|
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3841 | 12 - EM agency and authority | That, in order to ensure suitably skilled and experienced personnel operate as Divisional Commanders during major fire incidents, Bush Fire Management Committees identify appropriate personnel as part of their plan of operations. |
REC315-3871 | 11 - Evacuation and shelters | That, in order to ensure equitable access to evacuation centres and associated support services for people in border communities, Resilience NSW ensure cross-border access arrangements are reflected in evacuation centre management guidelines. |
REC315-3805 | 32 - Doctrine, standards, and reform | That, to strengthen cross-agency accountability and deliver improved bush fire risk management outcomes: |
REC315-3854 | 7 - Inter-agency communication | That, in order to ensure emergency response agencies can communicate across state and territory borders, the Commonwealth Government allocate 10 + 10 MHz as a dedicated spectrum for Public Safety Mobile Broadband (PSMB) at no cost to states and territories. |
REC315-3814 | 11 - Evacuation and shelters | That the NSW RFS identifies remote bush fire prone areas that do not already have an indoor Neighbourhood Safer Place (NSP) and upgrades the relevant NSW RFS Stations to meet NSP guidelines. These stations would require adequate Asset Protection Zones and active/passive protection systems to provide short-term protection. |
REC315-3832 | 8 - Communications and warnings | That, in order to improve the provision of evidence-based public health messaging about air quality during bush fire events, Government develop a public education campaign and supporting systems before the next bush fire season. This should include: |
REC315-3863 | 15 - Inter-service cooperation | That, in order to provide real-time information on evacuation doorknocking during emergency events, Government explore a shared data gateway for NSW agencies based on the NSW State Emergency Service Collector app and a common mapping and analytics platform. |
REC315-3840 | 29 - Operational Health and Safety | That, in order to ensure firefighter sustenance is of sufficient volume and quality, the NSW RFS reviews food standards and procedures in consultation with volunteers. The review should include catering service standards, including food safety, as well as the viability of sourcing commercial contracts and providing 12-hour food packs to firefighters. |
REC315-3870 | 11 - Evacuation and shelters | That, in order to ensure the safety and wellbeing of vulnerable people during an evacuation, Resilience NSW: |
REC315-3804 | 32 - Doctrine, standards, and reform | That the NSW RFS Commissioner consult with the Fire and Rescue NSW Commissioner and other emergency services to develop a protocol in the event that simultaneous emergency events necessitate the re-allocation of resources while a Section 44 declaration is in place. |
REC315-3853 | 7 - Inter-agency communication | That, in order to ensure the State Emergency Operations Centre (SEOC) can maintain communications during emergencies, the Government provide the SEOC with independent Public Safety Network functionality. |
REC315-3811 | 8 - Communications and warnings | That in order to provide greater consistency in public information and warnings, especially in border areas: |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3862 | 8 - Communications and warnings | That, in order to improve information flows and increase public awareness of ABC emergency broadcasts, Government: |
REC315-3839 | 29 - Operational Health and Safety | That, to ensure firefighters can access mental health support through GPs, Government work with the Commonwealth Government to: |
REC315-3867 | 11 - Evacuation and shelters | That, in order to ensure evacuation centres are fit-for-purpose, Resilience NSW work with Local Emergency Management Committees (LEMCs) to: a) update the guidelines for LEMCs identifying evacuation centres to require a risk assessment of potential locations, which should include identifying alternate sources of power for use by evacuation centres and recording these appropriately |
REC315-3803 | 16 - Training and behaviour | That Government support training initiatives to increase the capacity of fire authorities to fight the kind of megafires seen in the 2019-20 season. The training initiatives should include: |
REC315-3852 | 7 - Inter-agency communication | That, in order to improve fireground communications between NSW agencies and interstate personnel: a) Government ensure all NSW fire authority personnel and vehicles can access and utilise the Public Safety Network (PSN). This should include access to NSW RFS Private Mobile Radio networks where PSN coverage is not yet available. |
REC315-3809 | 37 - Funding | That Government work with other Australian governments to provide long-term funding certainty to AFAC, including the National Resource Sharing Centre (NRSC) and the National Aerial Firefighting Centre (NAFC). |
REC315-3828 | 9 - Community education | That, in order to improve bush fire planning and protection of road infrastructure and to ensure communities, freight movers and fire fighting agencies have appropriate access and egress in a bush fire event, Government, working with local government as needed: |
REC315-3861 | 16 - Training and behaviour | That, in order to expand the pool of trained personnel able to undertake the Public Information Functional Area Coordinator (PIFAC) role, Resilience NSW and the NSW Police Media Unit (PIFAC) develop and deliver a training package for Emergency Management Media Liaison Officers. |
REC315-3838 | 29 - Operational Health and Safety | That, in order to ensure all NSW RFS members can access the mental health support they need, the NSW RFS expands in-house mental health support for members. |
REC315-3866 | 11 - Evacuation and shelters | That, in order to ensure evacuation arrangements can be scaled up when needed, Resilience NSW: |
REC315-3799 | 9 - Community education | That at the start of each fire season, based on advice from the Bush Fire Coordinating Committee, Government provide a public statement with an evaluation of the likely fire season risk and the effectiveness of the planning and preparation for the upcoming season. This should be based on sophisticated monitoring of the key risk factors and signals for an extreme fire season. It should form the basis for clear public communication about these risks on a regional basis and the actions that Government proposes in preparation. |
REC315-3846 | 12 - EM agency and authority | That, in order to maximise the efficiency and effectiveness of heavy plant used in dry fire fighting techniques, the NSW RFS expand and introduce the following in respect to heavy plant: |
REC315-3807 | 16 - Training and behaviour | That, in order to expand NSW’s specialist aviation personnel safety and capacity, Government expand simulator capabilities at the NSW RFS Training Academy. |
REC315-3857 | 12 - EM agency and authority | That, in order to ensure timely payment and maintain positive ongoing supplier relationships during large-scale bush fires, the NSW RFS implements an automated logistics solution, informed by the outcomes of the Emergency Logistics Project. |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3835 | 15 - Inter-service cooperation | That, in order to ensure the safety of local landholders on firegrounds, the NSW RFS emphasises the importance of local landholders using protective clothing while fire fighting as part of the RFS’ ‘Farm Fire Unit Integration’ priority for 2020-21. |
REC315-3865 | 8 - Communications and warnings | That the NSW RFS include the following priorities in the Fires Near Me improvements roadmap: |
REC315-3844 | 32 - Doctrine, standards, and reform | That, in order to enhance fire fighting strategies in severe conditions, the NSW RFS implements the following in respect to backburning: |
REC315-3872 | 11 - Evacuation and shelters | That, in order to improve support for people evacuating with animals, the Department of Primary Industries: |
REC315-3806 | 15 - Inter-service cooperation | That the NSW RFS work with AFAC to analyse the impact of changing fire seasons on inter- jurisdictional resource sharing agreements, both domestic and international, and determine any flow-on effects for NSW fire fighting personnel capacity. |
REC315-3855 | 7 - Inter-agency communication | That, in order to ensure all agencies have a clear understanding of cross-border communication channels during bush fires, all MoUs between state or territory agencies include an agreed protocol about how agencies will communicate across borders and that these are reflected in Incident Action Plans. |
REC315-3820 | 32 - Doctrine, standards, and reform | That Government amend the Rural Fires Act 1997 so that all public land management agencies be required to forward complaints received about bush fire hazards to the Commissioner of the NSW RFS. As an interim measure, heads of agencies should commence this practice immediately. |
REC315-3834 | 12 - EM agency and authority | That, in order to ensure all firefighters understand how local situational awareness reflects (or may not reflect) the broader scale situation presented by a large/extreme bush fire and the implications this may have on asset protection and fire suppression strategies, the NSW RFS: |
REC315-3864 | 9 - Community education | That, in order to ensure people can access clear information on cross-border fires, the NSW RFS: |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2393 | 15 - Inter-service cooperation | In recognising the success of the work of both the volunteer based Rural Fire Service and the full time Fire and Rescue NSW (FRNSW) members in joint operations – both agencies should be represented at major briefings or press conferences to reinforce successful integrated collaborative efforts rather than individual agency achievements |
REC302-2400 | 15 - Inter-service cooperation | Until a single call centre is developed, continue deployments of a senior RFS officer to Fire and Rescue NSW ComCen on a 24/7 day basis. This arrangement should determine the quickest most suitable resource and who is ‘in charge’ of an incident |
REC302-2397 | 12 - EM agency and authority | Use the model and system in place at the Ambulance Service of NSW as a benchmark for call taking, dispatch and the provision of situational awareness when deploying resources. This will overcome the lack of a feedback loop in current bushfire operations |
REC302-2396 | 15 - Inter-service cooperation | The Commissioners of Fire and Rescue NSW (FRNSW) and the RFS issue an instruction to FRNSW ComCen that while AVL capability is being made available to the RFS vehicle fleet, no offers of assistance by one agency to the other in combatting a fire is rejected or delayed if what is being offered is appropriate |
REC302-2404 | 8 - Communications and warnings | Review the effectiveness of emergency public information arrangements, and give consideration to embedding an ABC Manager (not a journalist) into the RFS headquarters during emergencies to broadcast warnings to the community that can be pooled to commercial media outlets |
REC302-2395 | 32 - Doctrine, standards, and reform | Remove those policies, guidelines, memoranda of understanding and committees that are made redundant as a result of adopting recommendation #2 while updating any remaining policies that are considered to still be relevant |
REC302-2403 | 12 - EM agency and authority | Take steps to ensure that both fire commissioners are seeking opportunities to engender a culture in their respective organisations that seeks to attract and foster the volunteer ethos and experience |
REC302-2394 | 15 - Inter-service cooperation | Take immediate steps to eliminate fire boundaries for call and dispatch purposes to create an agnostic approach to the threat of fires from both a departmental and organisational perspective |
REC302-2401 | 12 - EM agency and authority | While the proposal to establish an integrated call and dispatch centre is being implemented, Fire and Rescue NSW should take steps to civilianise ComCen and maintain experienced senior officers from both agencies as supervisors similar to how the NSW Police Force and Ambulance Service of NSW operate |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1395 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service reassess the protection of pastoral assets during bush fires to ensure that priority for protection is not simply afforded to the homestead, and that land holders are, within reason, able to request which of their own assets are protected. |
REC280-1389 | 32 - Doctrine, standards, and reform | That the NSW Government, as a matter of urgency, amend the Rural Fires Act 1997 to codify the current interim arrangements for command and notification requirements for class 1 and class 2 fires, which clarify that the NSW Rural Fire Service or Fire and Rescue NSW: |
REC280-1394 | 12 - EM agency and authority | That the Minister for Police and Emergency Services examine the feasibility of relocating the NSW Rural Fire Service headquarters to a rural or regional location. |
REC280-1387 | 12 - EM agency and authority | That the NSW Rural Fire Service: |
REC280-1393 | 36 - Volunteers | That the NSW Rural Fire Service formally recognise the Volunteer Fire Fighters Association as a legitimate advocacy organisation representing volunteer bush fire fighters, and duly consult with it on policy and operational matters. |
REC280-1384 | 12 - EM agency and authority | That the NSW National Parks and Wildlife Service examine its staffing policy for periods of extreme and catastrophic weather conditions to ensure that sufficient staff are available on site on fire watch. |
REC280-1392 | 36 - Volunteers | That the NSW Rural Fire Service, in order to ensure greater respect for volunteer fire fighters’ knowledge and experience in the management of fires: |
REC280-1403 | 32 - Doctrine, standards, and reform | That the Ministry for Police and Emergency Services urgently review its policies for the provision of disaster welfare services to ensure that in the event of a bush fire emergency and the declaration of a fire under section 44 of the Rural Fires Act 1997, adequate funding and services, especially recovery centres and mental health services, are provided for an adequate length of time, with gradual transition to normal service delivery when those services are no longer required. |
REC280-1379 | 9 - Community education | That the NSW Rural Fire Service develop and implement a comprehensive community education campaign aimed at increasing community understanding of and support for hazard reduction burns. |
REC280-1391 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service review its procedures, systems and infrastructure for notifying community members of bush fires, both when a fire has broken out and as it proceeds, to ensure the provision of timely and adequate information. |
REC280-1397 | 32 - Doctrine, standards, and reform | That the NSW National Parks and Wildlife Service adopt an interim fencing agreement in the immediate aftermath of a fire. This will enable emergency and interim works to commence, but features such as length, fencing components and site of the fence line are not binding. A final fencing agreement would be negotiated no earlier than six months following a major national park fire. |
REC280-1390 | 32 - Doctrine, standards, and reform | That the NSW Government consider enabling the default position during catastrophic and extreme fire danger periods to be the same as for section 44 fires, so that fire control centres have the same systems and resources ready to deploy should a fire break out. |
Rec-ID | Code | Recommendation |
---|---|---|
REC279-1231 | 16 - Training and behaviour | Training Strategy: By April 2015, develop a training strategy that identifies volunteer training priorities and provides for ongoing review to ensure operational currency, flexibility of delivery and evaluation |
REC279-1230 | 36 - Volunteers | Volunteer Retention: By April 2015, develop strategies and resources to improve volunteer retention, including: a) induction and development of leaders b) health checks for units to identify and address areas for improvement c) pathways for volunteers to take on greater responsibility d) consultation and communication e) recognition for volunteers and their employers |
REC279-1229 | 12 - EM agency and authority | Recruitment Guidelines and Resources: By April 2015, update its recruitment guidelines and resources, and support units in better targeting recruitment |
REC279-1228 | 36 - Volunteers | Volunteer Workforce Plan: By December 2014, develop a volunteer workforce plan to focus resources for recruitment and retention on areas of greatest need. The plan should be based on regional capability plans that assess in a consistent way: a) how many volunteers they have and need b) the gaps and risks around volunteer numbers, skills and training |
REC279-1227 | 36 - Volunteers | Improve Analysis and Reporting: By December 2014, improve analysis and reporting on management information about volunteers, including: a) numbers, contribution, skills, profile, availability and turnover b) reasons for joining and leaving c) gaps in data completeness and quality This should enable SES to demonstrate an improvement in the completeness and accuracy of management information by April 2015 |
REC279-1232 | 16 - Training and behaviour | Volunteer Charter: by December 2014, agree a charter with volunteers that clarifies roles and expectations including commitments by: a) SES to support volunteers to prepare for and respond to emergencies b) SES to make the best use of volunteers’ time by introducing user-friendly systems and reducing the administrative burden on them c) volunteers to turn-out when called to respond to emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1497 | 8 - Communications and warnings | That the NSW Rural Fire Service investigate mechanisms to enhance the predictability of megafires and how this information is communicated easily to the public. |
REC261-1510 | 36 - Volunteers | That the NSW Rural Fire Service formally recognise the Volunteer Fire Fighters Association as a legitimate advocacy organisation representing volunteer bush fire fighters, and duly consult with it on policy and operational matters. |
REC261-1496 | 9 - Community education | That the NSW Rural Fire Service develop and implement a comprehensive community education campaign aimed at increasing community understanding of and support for hazard reduction burns. |
REC261-1509 | 34 - Local knowledge | That the NSW Rural Fire Service, in order to ensure greater respect for volunteer fire fighters’ knowledge and experience in the management of fires: |
REC261-1492 | 37 - Funding | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
REC261-1506 | 32 - Doctrine, standards, and reform | That the NSW Government, as a matter of urgency, amend the Rural Fires Act 1997 to codify the current interim arrangements for command and notification requirements for class 1 and class 2 fires, which clarify that the NSW Rural Fire Service or Fire and Rescue NSW: |
REC261-1516 | 32 - Doctrine, standards, and reform | That the NSW National Parks and Wildlife Service remove from its boundary fencing policy and standard contract the condition that requires adjoining land owners to maintain a fence that has been damaged by trees falling from national park land. |
REC261-1504 | 12 - EM agency and authority | That the NSW Rural Fire Service: |
REC261-1512 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service reassess the protection of pastoral assets during bush fires to ensure that priority for protection is not simply afforded to the homestead, and that land holders are, within reason, able to request which of their own assets are protected. |
REC261-1501 | 12 - EM agency and authority | That the NSW National Parks and Wildlife Service examine its staffing policy for periods of extreme and catastrophic weather conditions to ensure that sufficient staff are available on site on fire watch. |
REC261-1511 | 12 - EM agency and authority | That the Minister for Police and Emergency Services examine the feasibility of relocating the NSW Rural Fire Service headquarters to a rural or regional location. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1051 | 8 - Communications and warnings | That the Rural Fire Service consider redrafting the disclaimer in its fire predictions to make abundantly clear where the potential errors or omissions may affect the prediction and how to detect them if they are there (for example, by comparing them with linescans) and what other factors (such as VLS) may affect the predictions and in what way. |
REC260-1069 | 32 - Doctrine, standards, and reform | That NPWS conduct a review of its hazard reduction policies to ensure all assets within and on the boundary of the Park are clearly identified and an adequate policy or management plan exists for the protection of all assets, including a procedure pursuant to which progress in meeting hazard reduction targets is regularly and comprehensively assessed. |
REC260-1056 | 32 - Doctrine, standards, and reform | That the Rural Fire Service and National Parks and Wildlife Service consider adopting the approach to fire classification suggested by Mr Conway that “classification and resourcing of the fire ground response and incident management capability should reflect the potential of the fire rather than observed fire behaviour. |
REC260-1062 | 16 - Training and behaviour | That the National Parks and Wildlife Service consider incorporating “worst-case scenario” training, as proposed in Mr Conway’s report, in its suite of fire-fighting protocols, exercises and training packages for senior incident controllers and other senior managers. |
REC260-1068 | 16 - Training and behaviour | That the National Park and Wildlife Service review its fire weather training regime and consider adopting or adapting the fire weather training courses introduced in Victoria following the 2009 bushfire disaster. |
REC260-1055 | 34 - Local knowledge | That the Rural Fire Service together with other land managers develop a program whereby local stakeholders come together regularly (every 2 months during non-fire season and monthly during the fire season) to share intelligence and to consider hazard and incident management measures for implementation. |
REC260-1061 | 18 - Access to fire ground | That the National Parks and Wildlife Service, in consultation with the relevant local Council(s), devise a policy that enables the John Renshaw Parkway to be closed at either end of the Warrumbungle National Park during a bush fire in such a way that its closure would not impede access by emergency services vehicles into the park. |
REC260-1067 | 15 - Inter-service cooperation | That as part of the adoption of such a posture in ‘severe’ or worse fire conditions, the National Parks and Wildlife Service consider alerting, at an early stage, all relevant persons and organisations, such as shire councils, heavy plant operators, the local RFS captains, Fire & Rescue NSW and other emergency services, that it is doing so, and that their assistance may be required at short notice. |
REC260-1054 | 2 - Emergency powers | That the Rural Fire Service consider extending pre-emptive section 44 to whole of Castlereagh RFS/Warrumbungle Shire area. |
REC260-1060 | 7 - Inter-agency communication | That the Rural Fire Service and National Parks and Wildlife Service review the procedures for requesting aerial support in ‘severe’ or worse fire conditions to ensure that delays in providing it are reduced to the minimum time possible. |
REC260-1066 | 14 - Incident Mgt Teams | That during periods of ‘severe’ or worse fire conditions, that the National Parks and Wildlife Service consider adopting a posture of pre-emptive planning and deployment of incident management teams in national parks similar to the manner in which the Rural Fire Service does. |
REC260-1053 | 14 - Incident Mgt Teams | That in Class 3 fire-fighting operations, the Rural Fire Service consider including a fire behaviour analyst in the incident management team if feasible. |
REC260-1059 | 8 - Communications and warnings | That the Rural Fire Service and National Parks and Wildlife Service consider amending their protocols for upgrading advices to higher levels to emphasise the significance and urgency of raising warning levels as soon as the potential dangers of fire to lives or property materially increase. |
REC260-1065 | 32 - Doctrine, standards, and reform | That the National Parks and Wildlife Service review its procedures for monitoring Class 1 fires occurring in ‘severe’ or worse fire conditions that cannot be reconnoitred at ground level adequately due to terrain or dangerous conditions, and consider including aerial surveillance (if reasonably practicable) as a standard procedure in such circumstances. |
REC260-1052 | 14 - Incident Mgt Teams | That the Rural Fire Service consider amending its fire prediction reports to include a checklist of significant factors that have not been able to be considered in the prediction model and a warning to be alert for them and seek intelligence on them from fire ground managers. |
REC260-1057 | 16 - Training and behaviour | That the Rural Fire Service and National Parks and Wildlife Service introduce training, exercises or information packages, or other suitable forms of professional development, for operational fire fighters and analysts concerning the potential effects of atmospheric instability and vorticity-driven lateral spread on fire behaviours in severe-catastrophic fire danger conditions. |
REC260-1064 | 32 - Doctrine, standards, and reform | That the National Parks and Wildlife Service review its protocols for control of Class 1 fires under its control to ensure that incident controllers managing fires in ‘severe’ or worse fire conditions receive as much incident management planning support as is reasonably practicable in the circumstances. |
Rec-ID | Code | Recommendation |
---|---|---|
REC259-1048 | 8 - Communications and warnings | That State and Local Government agencies maximise communication to the residents owning bushfire prone properties to be aware of their level of exposure by having access to the BAL relevant to their property. |
REC259-1045 | 9 - Community education | That recovery policy incorporates the need for regular public meetings which give access to officials and representatives of agencies, as required |
REC259-1044 | 9 - Community education | That where, in the future a similar process for land clearing is adopted, the rationale and process is better explained and widely promulgated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0798 | 32 - Doctrine, standards, and reform | Optimise the configuration of a raised Warragamba Dam for flood mitigation of the full range of flood events and water supply, with due consideration of upstream impacts. |
REC238-0811 | 9 - Community education | Monitor, investigate and address community response to flood warnings |
REC238-0797 | 32 - Doctrine, standards, and reform | Determine the appropriateness and the steps required to allow the reduction of full supply level by up to five metres and/or the implementation of alternative gate operation at Warragamba Dam for the mitigation of minor to moderate flood events in the short-term. |
REC238-0810 | 9 - Community education | Undertake, coordinate and evaluate community education programs on flood risk and response. |
REC238-0809 | 9 - Community education | Ensure the SES has the long-term capacity to plan and exercise for the full range of flood events in the Hawkesbury-Nepean Valley |
REC238-0803 | 32 - Doctrine, standards, and reform | Ensure effective flood gauging arrangements in the Hawkesbury-Nepean Valley |
REC238-0799 | 18 - Access to fire ground | Develop and implement a program of cost-effective road improvement works that can enhance flood evacuation capacity in the short-medium term. |
REC238-0812 | 9 - Community education | Develop mechanisms and arrangements to promote and provide greater access to flood risk information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0821 | 32 - Doctrine, standards, and reform | That the definition of “bush fire hazard reduction work” in the Dictionary of the Rural Fires Act 1997 be amended to include the establishment or maintenance of fire trails. |
REC237-0827 | 32 - Doctrine, standards, and reform | The Panel notes and endorses the NSW bush fire management system based on a multi-agency, tenure blind approach using locally focused Bush Fire Management Committees, Bush Fire Management Plans and the Bush Fire Environmental Assessment Code as best practice. |
REC237-0832 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service investigate use of appropriate modelling, such as PHOENIX RapidFire and the Bayesian Network analysis, to quantify the level of bush fire risk to critical values and assets. |
REC237-0820 | 32 - Doctrine, standards, and reform | That the Rural Fires Act 1997 be amended to allow the Commissioner of the NSW Rural Fire Service to carry out hazard reduction on land without the consent of the owner after reasonable attempts to contact the landowner have failed, without serving a notice under section 66 of the Rural Fires Act. |
REC237-0826 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service hold discussions with the Commonwealth Department of Sustainability, Environment, Water, Population and Communities about hazard reduction and roadside vegetation, including potential changes to the NSW Bush Fire Environmental Assessment Code. |
REC237-0831 | 32 - Doctrine, standards, and reform | That Bush Fire Management Committees be required to take into account fuel age and fire frequency thresholds when developing Bush Fire Risk Management Plans |
REC237-0819 | 32 - Doctrine, standards, and reform | That section 56 of the Rural Fires Act 1997 be amended to give the Commissioner of the NSW Rural Fire Service the power to direct a Bush Fire Management Committee to amend its Bush Fire Risk Management Plan if it is inadequate, in the opinion of the Commissioner. |
REC237-0824 | 32 - Doctrine, standards, and reform | That section 100I of the Rural Fires Act 1997 be amended to allow hazard reduction certificates to be issued for annual low impact works for a period of three years, where appropriate. |
REC237-0830 | 9 - Community education | That Bush Fire Risk Management Plans be tabled at Local Emergency Management Committees for comment. |
REC237-0818 | 32 - Doctrine, standards, and reform | That section 9(4)(b) of the Rural Fires Act 1997, which sets out the functions of the NSW Rural Fire Service, be amended to include protecting infrastructure, environmental, economic, cultural, agricultural and social assets from damage. |
REC237-0823 | 32 - Doctrine, standards, and reform | That section 74 of the Rural Fires Act 1997 be amended to require public authorities to report monthly to the Commissioner of the NSW Rural Fire Service on activities undertaken to reduce bush fire hazards on managed land during the preceding month and the reasons why any planned activities did not take place. |
REC237-0829 | 9 - Community education | That Bush Fire Risk Management Plans be posted on the NSW Rural Fire Service website. |
REC237-0817 | 32 - Doctrine, standards, and reform | That section 3(c) of the Rural Fires Act 1997, which sets out the objects of the Act, be extended to include protecting infrastructure, environmental, economic, cultural, agricultural and social assets from damage. |
REC237-0834 | 37 - Funding | That the NSW Rural Fire Service apply for funding from the NSW Treasury for the development of a multi-agency business case for a BRIMS replacement that includes internal management, risk communication, community engagement capability and publishing activities on websites. |
REC237-0822 | 32 - Doctrine, standards, and reform | That section 74 of the Rural Fires Act 1997 be amended to require public authorities to report to the Commissioner of the NSW Rural Fire Service within one month of the end of the financial year on activities undertaken to reduce bush fire hazards on managed land during the preceding financial year. |
REC237-0828 | 9 - Community education | That the NSW Rural Fire Service develop a strategy to better inform the community and NSW Rural Fire Service members about the NSW bush fire management system and its components. |
REC237-0833 | 37 - Funding | That the NSW Rural Fire Service and the NSW Treasury explore ways to ensure that unspent hazard reduction funds be carried over to the next financial year in a timely manner and to ensure that hazard reduction funding has a seamless transition from one financial year to the next. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0072 | 32 - Doctrine, standards, and reform | SERCon consider that the proposed State Recovery Committee review the recommended considerations arising from |
REC164-0071 | 32 - Doctrine, standards, and reform | SERCon consider the establishment of a body, such as a State Recovery Committee, with responsibility for the |
REC164-0077 | 32 - Doctrine, standards, and reform | SERCon consider the continued development of a State Recovery Sub-Plan (including complementary local and district |
REC164-0076 | 32 - Doctrine, standards, and reform | SERCon consider meeting with the State Emergency Management Committee, Directors General and agency heads to |
REC164-0075 | 16 - Training and behaviour | SERCon consider development of an education program for other government and non-government agencies (with |
REC164-0074 | 9 - Community education | SERCon consider a review of existing community-based educational programs, with a view to informing the community |
Rec-ID | Code | Recommendation |
---|---|---|
REC163-1939 | 2 - Emergency powers | That the Rural Fires Act 1997 be amended to provide to designated Fire Investigation Officers of the Rural Fire Service the power to enter any land upon which a bushfire has occurred for the purposes of investigation for a period of up to 24 hours after a fire has been declared out. |
REC163-1938 | 12 - EM agency and authority | That appropriate officers of the Rural Fire Service be granted the same powers as granted to officers of NSW Fire Brigades under section 19 of the Fire Brigades Act 1989. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
REC129-3628 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test the capability of its contact tracing system to deal with a public health emergency. |
REC129-3621 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and establish a time table to finalise all emergency and contingency plans. |
REC129-3627 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test its surveillance systems for early detection of infectious diseases. |
REC129-3632 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and develop distinct surge capacity plans within each Area Health Service to manage emergency staffing needs, isolation facilities, intensive care units, assisted ventilation services, hospital beds and medical supplies. |
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3631 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and continue to develop plans to respond to the surge in demand for diagnostic tests and for laboratory personnel. |
REC129-3624 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and formally establish and oversight a comprehensive program of training, testing and evaluation of plans at the state, area and facility level. |
REC129-3630 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and continue to develop systems to bring all the information relevant to the surge in demand for health resources together in real time. |
REC129-3623 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and apply the lessons learnt from Exercise Cumpston to further improve preparedness for major infectious disease emergencies. |
REC129-3629 | 8 - Communications and warnings | We recommend that NSW Health continue with its good work and continue to improve communication mechanisms with those, such as GPs, likely to be affected in major infectious disease outbreaks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3600 | 34 - Local knowledge | The Department of Primary Industries continue to consult local community about emergency planning and sites for disposal to retain confidence in the event of a genuine emergency. |
REC128-3609 | 16 - Training and behaviour | That the Department of Primary Industries be conscious of its responsibilities in maintaining the continued enthusiasm of Industry Liaison Officers and offer training and refresher training as required. |
REC128-3614 | 37 - Funding | The Committee encourages the Department and the Rural Land Protection Boards to discuss the need for funding of poultry surveillance activities in the context of reviewing the Memorandum of Understanding between the two parties. |
REC128-3599 | 32 - Doctrine, standards, and reform | In order to improve the response to animal health emergencies, that the Department of Primary Industries prioritise the finalisation of Memoranda of Understanding with the four jurisdictions bordering New South Wales. |
REC128-3608 | 16 - Training and behaviour | That emergency animal health training be included in induction programs for newly recruited District Veterinarians and all District Veterinarians be encouraged to maintain their skills by attending regular refresher training as appropriate. |
REC128-3613 | 9 - Community education | That the Department of Primary Industries and Rural Lands Protection Boards employ outreach activities to alert these small producers to their responsibilities and improve their awareness of animal and plant pests and diseases. |
REC128-3618 | 32 - Doctrine, standards, and reform | That the Department of Primary Industries should complete a review of the Memorandum of Understanding and ensure the roles of the Department and Rural Lands Protection Boards are more clearly identified outlined for effective delivery of animal health programs. |
REC128-3607 | 16 - Training and behaviour | That the Department of Primary Industries should continue efforts to develop the skills of private sector veterinarians to increase the level of resources available in emergency responses. |
REC128-3612 | 12 - EM agency and authority | That the Department of Primary Industries should ensure that it retains the services of a specialist poultry industry liaison officer in the future. |
REC128-3617 | 37 - Funding | That the Department of Primary Industries should provide specific information on levies to contributing producers through a separate document, rather than rely on standard audit documents and annual reporting requirements. |
REC128-3604 | 37 - Funding | That the Department of Primary Industries restore the level of discretionary testing funds provided to District Veterinarians to previous levels and maintain these in the future in real terms. |
REC128-3611 | 12 - EM agency and authority | That the Department of Primary Industries should endeavour to improve its knowledge and skills base in the pig industry by recruiting a specialist pig industry liaison officer. |
REC128-3616 | 37 - Funding | That the Department of Primary Industries continue to pursue improvements to consultation with industry and accountability mechanisms to further build trust between industry and government, thereby enhancing the effectiveness of the OJD Program. |
REC128-3603 | 37 - Funding | That the Department of Primary Industries consider applying discretion to the use of user charging policies for testing in times when farm incomes are affected by external circumstances such as widespread drought. |
REC128-3610 | 32 - Doctrine, standards, and reform | That the Minister for Primary Industries consider amending the Stock Diseases Act 1923 to ban the supply of waste swill to pig owners by food retailing businesses such as bakeries, restaurants and supermarkets. |
REC128-3615 | 9 - Community education | That the Department of Primary Industries should continue to raise awareness among producers of OJD risks and the operation of Sheep Health Statements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3645 | 32 - Doctrine, standards, and reform | It is recommended that the Board: |
REC119-3647 | 32 - Doctrine, standards, and reform | It is recommended that the Board: |
REC119-3646 | 32 - Doctrine, standards, and reform | It is recommended that the Board develop response time standards for metropolitan and rural rescue services to guide committees in determining the number, type and location of rescue units (page 25). |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3966 | 12 - EM agency and authority | Each member of the Board to act in an honorary capacity. |
REC013_3977 | 8 - Communications and warnings | To arrange with settlers who live on hills or have a clear view, and are connected by telephone, to act as " look-outs ", and to communicate with the brigade in the case of fire. |
REC013_3965 | 12 - EM agency and authority | The Minister to have power to make regulations for the purpose of all proceedings of the Board, including the summoning and attendance of members, and the enforcement of orders of the Board. |
REC013_3973 | 40 - Equipment and consumables | To arrange for uniform water facilities, where possible, by having large taps attached to elevated tanks, suitable approaches made to dams for filling carts, and convienient gates to approach same. |
REC013_3964 | 12 - EM agency and authority | The Board shall consist of a Chairman and four other members, one member to be nominated each by the Graziers', Farmers and Settlers' and Agricultural Bureau Associations, one by the Fire Underwriters' Association, and one by the Government. |
REC013_3972 | 40 - Equipment and consumables | To recommend to shire councils the purchase of fire carts and necessary equipment for fire fighting. |
REC013_3963 | 12 - EM agency and authority | The establishment of a Board, to be called "The Bush Fires Control Board" which shall operate in conjunction with the shire councils in connection with the prevention of bush fires and control of bush-fire organisations. |
REC013_3971 | 12 - EM agency and authority | To elect necessary officers. |
REC013_3970 | 12 - EM agency and authority | The Board may, at any time, require the Bush Fire Committees to report on the condition of their fire-fighting equipment, and on any other matter, which in their opinion, will tend to greater efficiency in their operations. |
REC013_3979 | 32 - Doctrine, standards, and reform | That burning off by "occupiers" on any lands be regulated by permit or by regulation. |