Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4336 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services, in consultation with the Queensland Police Service, incorporate into the workflow of the current Emergency Alert system a process that ensures the inclusion of an ‘urgent approval and distribution without delay’ process for Emergency Alert messages by 1 November 2022. |
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4337 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an urgent multi-agency (including but not limited to the Queensland Police Service and Brisbane City Council) review of the workflow, of the current Emergency Alert system, including requesting, composing, authorising and issuing of Emergency Alerts by 1 November 2022. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
REC325-4329 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services implement the Australian Warning System for all nationally agreed hazards by 1 November 2023. Implementation should include guidance and training to all local governments and agencies operationally involved in disaster management, with emphasis on those agencies with hazard specific responsibility. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that do not have pre-formatted messages and polygons engage with Queensland Fire and Emergency Services and determine whether their local disaster management group capability could be improved through the development of pre-formatted polygons and messages. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that currently use pre-formatted messages within the Emergency Alert system review and, where necessary, redraft messages using the principles of Clear Explicit Translatable Language (CETL). |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4320 | 12 - EM agency and authority | Knowledge resources to support flood management: That, to provide more accurate and complete data for flood threat identification, warning and modelling systems, Government through the proposed new NSW Reconstruction Authority (NSWRA) work with the Australian Government to: |
REC324-4313 | 8 - Communications and warnings | NSW disaster app: That, to improve community confidence in government messaging and warnings, the SEOCON and DCS develop a single ‘NSW disaster app’. This: |
REC324-4314 | 8 - Communications and warnings | PIFAC function: That, to ensure the community can better understand the threat of flood, storm and tsunami activity, the Department of Customer Service (DCS) be made accountable for PIFAC in all emergencies. This will improve access to clear, reliable and consistent messaging prior to and during emergencies. This transfers the PIFAC role from NSW Police Force to Service NSW. Under this PIFAC function, DCS would be responsible for: |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4316 | 12 - EM agency and authority | Resilience NSW and recovery: That, in order to enhance NSW disaster preparedness, response and recovery, and meet the needs of the people of NSW prior to, during and after a disaster, and provide clarity on agency roles and responsibilities, Resilience NSW be reshaped to ‘Recovery NSW’. The new agency will be more streamlined and agile to drive recovery in the first 100 days post disaster. To achieve this, Resilience NSW’s functions should be reallocated as follows: |
REC324-4308 | 26 - Research | Compound mental helath studies: That, to inform Government policies and programs for mental health and disasters, Government commission a longitudinal study on the effect of consecutive disasters on community mental health. |
REC324-4318 | 12 - EM agency and authority | Permanent SEOCON: That, to improve NSW’s ability to prepare and respond to floods and other disasters, Government establish a new Deputy Commissioner of NSW Police Force to take on permanently the SEOCON role. This role, in addition to current SEOCON functions, would be responsible for: |
REC324-4309 | 12 - EM agency and authority | SES and RFS back-office merger: That, to help protect life and property across NSW in storm and flood events, and to improve resourcing and NSW State Emergency Service (SES) frontline capability, Government implement, before the next storm season, a merger of the SES and NSW Rural Fire Services (RFS) back-office and corporate service functions, while maintaining their separate legislative identity, brand, uniform and volunteer membership. This ‘joined-up’ RFS/SES corporate support structure would be under the command of the RFS given its corporate and operational maturity and would be responsible for: |
REC324-4319 | 26 - Research | Climate and weather research: That, to enable effective mitigation and adaptation measures in response to changing climate risks, Government establish NSW as a world centre of disaster research and technology development. This should include: |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
REC323-4288 | 8 - Communications and warnings | That the NSW Government work with the Commonwealth to develop a national cross-agency app to integrate all community services and agencies into a single platform so that everyone can receive accurate and timely information from one source during emergencies. |
REC323-4291 | 12 - EM agency and authority | That the NSW Government consider abolishing Resilience NSW if it is unable to ensure: |
REC323-4283 | 8 - Communications and warnings | That the NSW Government work with the community broadcasting sector to identify ways in which community broadcasters could be better supported to provide critical services during natural disasters, with a view to providing them adequate long term funding. |
REC323-4292 | 12 - EM agency and authority | That the NSW Government consider a restructure of the NSW State Emergency Service with consideration to: realigning the focus of the organisation to harness local knowledge and networks; coordinating more closely with other rescue agencies to bolster its capacity to respond; and increasing salaried staff and resources, and driving volunteer recruitment. |
REC323-4284 | 8 - Communications and warnings | That the NSW Government review its public awareness and communication strategies in relation to natural disasters. |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1267 | 8 - Communications and warnings | That emergency management authorities react with heightened awareness and action when BoM issues flood watches and related warnings. |
REC297-1266 | 8 - Communications and warnings | That Government supports the anticipated SES State Flood Warning proposals aimed at improving public warnings and communication, and that the proposed warning system is consistent with the National Frameworks. |
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2348 | 17 - Assets and technology | I recommend that if it has not already done so, the New South Wales Police Force acquires the audio surveillance technology that in similar circumstances would allow a device to be monitored in the Police Forward Command Post and/or the Police Operations Centre and that the organisation ensures that its capacity in this regard keeps pace with technological advances in the area. |
REC292-2357 | 12 - EM agency and authority | I recommend that the New South Wales Police Force review its policy of requiring negotiators to relinquish that role when they are promoted to commissioned officer rank |
REC292-2346 | 12 - EM agency and authority | I recommend that the New South Wales Police Force investigate the development of an integrated intelligence system that allows selected officers secure access to all information platforms and to record and share operational decisions. |
REC292-2356 | 12 - EM agency and authority | I recommend that the New South Wales Police Force review the number, rank and function of the officers comprising the Negotiation Unit |
REC292-2345 | 12 - EM agency and authority | I recommend that the New South Wales Police Force establish procedures and the technical capability to ensure that phone calls from hostages in sieges or the victims of other ongoing high-risk situations are expeditiously transferred to officers involved in responding to the incident. |
REC292-2355 | 12 - EM agency and authority | I recommend that the New South Wales Police Force review its procedures to ensure that handovers between negotiation teams are staggered so that a fully briefed officer is always available to receive a call from the stronghold. |
REC292-2354 | 12 - EM agency and authority | I recommend that the New South Wales Police Force consider expanding the panel of psychological advisers it retains and the range of disciplines it consults. |
REC292-2349 | 12 - EM agency and authority | I recommend that the New South Wales Police Force review its personnel arrangements and structures for the monitoring of surveillance devices, including the number of officers allocated to a listening or viewing post for monitoring purposes, and the demarcation of roles, including primary monitor, scribe/log keeper, and disseminator. I also recommend that clear communication channels be established for reporting data captured during such surveillance, including via integrated electronic intelligence sharing platforms or applications. |
REC292-2369 | 26 - Research | I recommend that the New South Wales Police Force evaluate whether the use of noise-attenuation devices should be mandated when explosive distraction devices are used. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1529 | 8 - Communications and warnings | As part of the above, both the Banana Shire Council and SunWater ensure Emergency Alert messages are pre-formatted, consistent, polygons are identified according to risk, and that they are tested and practiced with the State Disaster Coordination Centre. |
REC271-1528 | 8 - Communications and warnings | Prior to September 2015, SunWater and the Banana Shire Council jointly develop a multi-channel, common warning strategy, including common language and consistent messaging, for residents downstream of |
REC271-1527 | 8 - Communications and warnings | Prior to September 2015, the Banana Shire Council develops a multi-channel warning strategy and associated public information campaign, including common language and consistent messaging, for the Banana Shire. |
REC271-1522 | 26 - Research | Banana Shire Council investigate means to prioritise the commissioning of a fit-for-purpose flood study for high-risk areas across the Banana Shire to better inform flood risk management, including improved town planning. The outcomes of such a study should be available to the public and inform flood awareness campaigns, flood warnings, and building approvals. |
REC271-1521 | 26 - Research | The Department of Energy and Water Supply and SunWater, undertake the necessary studies to determine whether or not it is feasible to operate Callide Dam as a flood mitigation dam. Such studies should include matters in relation to, but not limited to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0792 | 8 - Communications and warnings | The Department of Human Services should develop an improved model for communication for future disasters that provides a single point of information and contact for disaster affected communities |
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0804 | 26 - Research | Clarify roles, responsibilities and consider funding options for post-event collection of data and flood intelligence. |
REC238-0813 | 26 - Research | Develop and maintain a comprehensive flood model and flood modelling framework for the Hawkesbury-Nepean Valley. |
REC238-0807 | 26 - Research | Develop a comprehensive road evacuation network model for floods in the Hawkesbury-Nepean floodplain to inform evacuation capacity assessments and strategic transport and land use planning, and to assist with the real-time operational management of evacuation during floods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2823 | 8 - Communications and warnings | The Australian Government, in consultation with consumers and other relevant federal, state and territory agencies, develop a national communication strategy for consumers to be used in the event of an infectious disease outbreak. |
REC232-2821 | 26 - Research | The National Health and Medical Research Council, in conjunction with key stakeholders, work collaboratively to provide more support for initiatives to increase international infectious disease research collaborations and build research capacity, particularly with neighbouring countries in the Asia-Pacific region. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1836 | 26 - Research | Flood studies will be undertaken to determine the flood extent on the basis of a greater than 1 in 100 ARI, where appropriate: |
REC217-1825 | 22 - Role of local Gvt | When developing flood mitigation options in lowland areas, local governments should give consideration to the use of temporary levees as an alternative or addition to permanent structures. To maximise the use of these structures and limit flood damage, and aid affordability, consideration should be given by local governments to the sharing of temporary levees among different townships and different council areas. |
REC217-1819 | 22 - Role of local Gvt | In consultation with local communities, local councils will develop flood response plans as subplans to their current Municipal Emergency Management Plans. As part of the flood risk assessment process, these plans will be informed by the best available flood mapping and modelling, and will identify agreed activities to be undertaken during floods including, where appropriate, the construction of temporary levees. The condition of levees will be incorporated into such plans to enable improved emergency response. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2871 | 22 - Role of local Gvt | Efficient and effective supporting tools and processes: high-quality local/municipal planning. |
REC216-2870 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: streamlining the authorisation processes for urgent warnings. |
REC216-2869 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: developing tools and workflows to quickly and reliably transform technical data into intelligence that can be used to construct messages for community information that are timely, relevant, tailored and effective. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0731 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directives it develops in relation to these matters. |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0730 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop clear directives about: • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the process for dealing with requests for assistance that exceed an SES unit’s capacity to respond them • the process for seeking extra support for an SES unit that has been overwhelmed by a disaster (whether by way of Emergency Management Queensland or the disaster management arrangements or both) • the role of SES liaison officers in communications with disaster managers about SES disaster operations • the role of incident controllers, and their teams, relative to those SES (or Emergency Management Queensland) personnel charged with the command of SES operations. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0729 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directive when it is developed. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0728 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop a directive that makes clear the authority of an officer of that agency to command a major SES operation. This could be expected to occur when a deployment of additional SES members is made to a region because the response needed is beyond the capacity of its local units. The directive should make clear the powers of the officer and his or her reporting responsibilities to disaster managers in these circumstances. Emergency Management Queensland must also ensure that any officer who assumes such a role has adequate training and skills in the conduct of disaster operations. |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0725 | 12 - EM agency and authority | The fire service should ensure that station officers are familiar with the procedure for contacting management when requesting the calling in of additional staff; and, in particular, that they have available to them the names and current telephone numbers of the officers to be contacted in the first instance, with alternative contact details in the event that those officers prove unavailable. |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0433 | 8 - Communications and warnings | the state develop and implement standards for Emergency Alert to ensure consistent use, training and application by accredited operators within agencies across ‘all hazards’. |
REC199-0438 | 8 - Communications and warnings | the state investigate the ability to refine the Flood and Storm Information Line to enable it to receive as well as provide information. |
REC199-0471 | 8 - Communications and warnings | the state and the commonwealth, during a flood event, make information available on providers who have capacity to accommodate patients and residents who require evacuation. |
REC199-0432 | 8 - Communications and warnings | the state develop and implement a single web portal as a means of providing emergency information to communities and local government on an ‘all hazards’ basis, including the information referred to in recommendations 74, 89 and 92. |
REC199-0437 | 8 - Communications and warnings | the state engage with local government to ensure emergency services’ public information and warnings reflect the community demographic. |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0416 | 26 - Research | the state establish appropriate arrangements to ensure the capacity to maintain technical expertise for flood intelligence is initiated, including appropriate agreements with commercial experts. |
REC199-0436 | 8 - Communications and warnings | the state develop a standard approach to the provision of emergency warnings and information in formats – spoken and written – that recognise diverse community needs, including language and disability |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0435 | 8 - Communications and warnings | the state put in place appropriate measures to inform the community of the intended purpose of the Emergency Alert warning system. |
REC199-0440 | 8 - Communications and warnings | the state actively pursue the use of social media as part of its emergency warning and public information system. |
REC199-0402 | 8 - Communications and warnings | the state develop a flood warning system for each basin and location with community input and make relevant documents publicly available. Each warning system should include key performance indicators. |
REC199-0434 | 8 - Communications and warnings | the state require that agencies operate in compliance with the guidelines of the Victorian Warning Protocol to ensure efficacy of warning messages. |
REC199-0439 | 8 - Communications and warnings | the state review its Memoranda of Understanding with official emergency broadcasters to take account of increased usage of internet based information, including social media and the ability to broadcast community meetings |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3177 | 12 - EM agency and authority | That the officer responsible for the importation of horses ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3629 | 8 - Communications and warnings | We recommend that NSW Health continue with its good work and continue to improve communication mechanisms with those, such as GPs, likely to be affected in major infectious disease outbreaks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3612 | 12 - EM agency and authority | That the Department of Primary Industries should ensure that it retains the services of a specialist poultry industry liaison officer in the future. |
REC128-3611 | 12 - EM agency and authority | That the Department of Primary Industries should endeavour to improve its knowledge and skills base in the pig industry by recruiting a specialist pig industry liaison officer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3900 | 12 - EM agency and authority | That agencies integrate condition information into their asset management decision-making practices and use it as the basis for validating asset valuations and depreciation calculations. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3923 | 12 - EM agency and authority | That DPI negotiates access, as and when required, to an AQIS PC4- accredited laboratory. |
REC112-3921 | 17 - Assets and technology | That the recommendations of the 2000 DPI report into the reference collection’s storage facility be implemented, to secure the collection in a purpose-built facility. |
REC112-3917 | 12 - EM agency and authority | That DPI improves monitoring and surveillance of high priority threats and improves the quality of information provided to the Commonwealth. |
REC112-3915 | 12 - EM agency and authority | That DPI makes arrangements to use contract labour for fruit fly trap monitoring and surveillance before the predicted fruit fly outbreak season. |
REC112-3914 | 12 - EM agency and authority | That DPI develops a consistent approach to recording and enforcing breaches of the certification and verification system. |
REC112-3909 | 12 - EM agency and authority | That PSB’s enforcement procedures are consistent with those of the rest of the department. |