Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4335 | 16 - Training and behaviour | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services update and deliver training on the workflow reviewed (as per Recommendation 3) of the current Emergency Alert system to all persons responsible at a local, district and state level by 1 November 2022. Training should address system constraints and system complexities in addition to the process of requesting, composing (including Clear Explicit Translatable Language [CETL]), authorising and issuing Emergency Alerts. |
REC325-4323 | 7 - Inter-agency communication | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services adopt measures to achieve a common operating picture between deployed Queensland Fire and Emergency Services assets in disaster management operations by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4282 | 16 - Training and behaviour | That the NSW Government invest in the required personnel, training and vessels to ensure that all agencies involved in flood rescue can be mobilised to their fullest potential. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1530 | 16 - Training and behaviour | Local Disaster Coordination Centre capability and capacity should be reviewed to ensure adequate staffing arrangements are in place to fill key positions, and that operational protocols are known and practiced across all functions to provide redundancy. Assistance for review and necessary training should be sought from key Local Disaster Management Group member agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2818 | 16 - Training and behaviour | The Royal Australian College of General Practitioners provide resources and training to general practitioners on the complex health needs of migrants and refugees, with a focus on identifying infectious diseases which are notifiable in Australia, or diseases which are of specific concern to refugee and migrant communities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0775 | 16 - Training and behaviour | The Department of Environment and Resource Management should conduct periodic dam safety information and education sessions with emergency management personnel including those from Emergency Management Queensland, local and district disaster management groups and local councils. Priority should be given to sessions if the Bureau of Meteorology forecasts a wet season with a greater than 50 per cent chance of above median rainfall. |
REC210-0766 | 16 - Training and behaviour | Wide Bay Water should, in addition to its usual wet season preparations and maintenance, undertake the following activities in advance of each wet season: Queensland Floods Commission of Inquiry | Final Report 29 Complete list of Final Report recommendations • conduct training for personnel on dam operation, including contingency plans for the situation in which one or more of the gates is inoperable • hold meetings of key personnel of Wide Bay Water involved in the operation of the dam during floods, which: – in addition to any other matters, inform staff about the current status of the gates, dam operation strategies and contingency plans for the situation in which one or more of the gates is inoperable – are recorded in minutes which document the information provided and are made available to all operational staff. |
REC210-0734 | 16 - Training and behaviour | Emergency Management Queensland should simplify the process by which SES members gain recognition for prior qualifications so that unnecessary duplication of training can be avoided. |
REC210-0681 | 19 - Offences | Councils and distributor-retailers should agree to protocols for the exchange of information about suspected illegal connections, the steps being taken to investigate them or the basis for concluding that no investigation is required, and the results of any investigations or enforcement actions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0447 | 7 - Inter-agency communication | the state ensure that common and interoperable resource management systems are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0463 | 16 - Training and behaviour | the state: • ensure an appropriate regime of regular emergency management training and exercising is introduced. This must be ‘all hazards’ and multi-agency focused and include all relevant stakeholders • designate an accountable officer to hold ongoing responsibility for conducting such exercises; and • designate the Emergency Services Commissioner as holding ongoing responsibility for auditing and reviewing this training and exercising. |
REC199-0446 | 7 - Inter-agency communication | the state commit to securing effective multi-agency interoperable communications as a high level priority and that all future communications projects and upgrades incorporate compliance provisions mandating interoperability requirements. |
REC199-0462 | 16 - Training and behaviour | the state introduce a joint emergency management leadership training program that will deliver critical core competencies for all levels of management of major emergencies. Future appointments to senior operational emergency management positions should require successful accreditation at the appropriate level. |
REC199-0418 | 7 - Inter-agency communication | the state develop an efficient process to ensure that, during flood events, temporary construction of flood mitigation works, such as levees, is controlled so as not to unacceptably impact on flood intelligence. |
REC199-0448 | 16 - Training and behaviour | the state ensure that sector wide familiarity and understanding of the various systems for incident management is developed and maintained. Primarily, this should be achieved through multi-agency emergency management training and exercising involving usage of the various agency incident management systems. |
REC199-0458 | 7 - Inter-agency communication | the state ensure: • a common, functional and accessible system be introduced to enable effective Municipal Emergency Coordination Centre and Incident Control Centre communications • a regime of regular Municipal Emergency Coordination Centre exercising is introduced with oversight by an appropriate independent body. Such exercising should include testing of systems utilised for Incident Control Centre and Municipal Emergency Coordination Centre communications • those required to perform Emergency Management Liaison Officer roles have undertaken appropriate training; and • resource requesting arrangements are clarified and documented so that control and coordination functions do not overlap. |
REC199-0415 | 16 - Training and behaviour | the state ensure that all personnel who are likely to become involved in incident management teams for floods receive basic flood awareness training prior to such involvement. |
REC199-0449 | 7 - Inter-agency communication | the state ensure that interoperable information management practices are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0414 | 16 - Training and behaviour | the state ensure that all personnel who, because of their particular flood expertise, are likely to be potential participants in an Incident Control Centre are familiar with the requirements of the Australasian Inter-service Incident Management System structure |
REC199-0475 | 16 - Training and behaviour | the Department of Planning and Community Development review the volunteer register and examine additional options to support councils in volunteer management, including the development of tools and staffing support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0075 | 16 - Training and behaviour | SERCon consider development of an education program for other government and non-government agencies (with |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3608 | 16 - Training and behaviour | That emergency animal health training be included in induction programs for newly recruited District Veterinarians and all District Veterinarians be encouraged to maintain their skills by attending regular refresher training as appropriate. |
REC128-3607 | 16 - Training and behaviour | That the Department of Primary Industries should continue efforts to develop the skills of private sector veterinarians to increase the level of resources available in emergency responses. |
REC128-3609 | 16 - Training and behaviour | That the Department of Primary Industries be conscious of its responsibilities in maintaining the continued enthusiasm of Industry Liaison Officers and offer training and refresher training as required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3931 | 16 - Training and behaviour | That DPI ensures that AIIMS training includes information to ensure that everyone understands their role, and how information will be managed internally and externally, in the event of an incursion. |
REC112-3930 | 16 - Training and behaviour | That DPI provides plant incursion-specific AIIMS training for anyone who might be involved in, or providing resources for, an incursion response. This includes senior management, field and research staff, contractors and industry participants. |
REC112-3916 | 16 - Training and behaviour | That DPI reviews the work of entry level graduates to ensure career paths are clear and encourage the retention of staff. |