Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4336 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services, in consultation with the Queensland Police Service, incorporate into the workflow of the current Emergency Alert system a process that ensures the inclusion of an ‘urgent approval and distribution without delay’ process for Emergency Alert messages by 1 November 2022. |
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4337 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an urgent multi-agency (including but not limited to the Queensland Police Service and Brisbane City Council) review of the workflow, of the current Emergency Alert system, including requesting, composing, authorising and issuing of Emergency Alerts by 1 November 2022. |
REC325-4323 | 7 - Inter-agency communication | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services adopt measures to achieve a common operating picture between deployed Queensland Fire and Emergency Services assets in disaster management operations by 1 November 2023. |
REC325-4329 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services implement the Australian Warning System for all nationally agreed hazards by 1 November 2023. Implementation should include guidance and training to all local governments and agencies operationally involved in disaster management, with emphasis on those agencies with hazard specific responsibility. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that do not have pre-formatted messages and polygons engage with Queensland Fire and Emergency Services and determine whether their local disaster management group capability could be improved through the development of pre-formatted polygons and messages. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that currently use pre-formatted messages within the Emergency Alert system review and, where necessary, redraft messages using the principles of Clear Explicit Translatable Language (CETL). |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4308 | 26 - Research | Compound mental helath studies: That, to inform Government policies and programs for mental health and disasters, Government commission a longitudinal study on the effect of consecutive disasters on community mental health. |
REC324-4313 | 8 - Communications and warnings | NSW disaster app: That, to improve community confidence in government messaging and warnings, the SEOCON and DCS develop a single ‘NSW disaster app’. This: |
REC324-4314 | 8 - Communications and warnings | PIFAC function: That, to ensure the community can better understand the threat of flood, storm and tsunami activity, the Department of Customer Service (DCS) be made accountable for PIFAC in all emergencies. This will improve access to clear, reliable and consistent messaging prior to and during emergencies. This transfers the PIFAC role from NSW Police Force to Service NSW. Under this PIFAC function, DCS would be responsible for: |
REC324-4319 | 26 - Research | Climate and weather research: That, to enable effective mitigation and adaptation measures in response to changing climate risks, Government establish NSW as a world centre of disaster research and technology development. This should include: |
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
REC323-4290 | 20 - Role of police | That the NSW Government embed into its emergency plans the appointment of a senior police officer with combat experience to lead recovery efforts following natural disasters. |
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
REC323-4283 | 8 - Communications and warnings | That the NSW Government work with the community broadcasting sector to identify ways in which community broadcasters could be better supported to provide critical services during natural disasters, with a view to providing them adequate long term funding. |
REC323-4275 | 34 - Local knowledge | That the NSW Government, in partnership with community groups, including First Nations groups, develop initiatives to build community resilience, particularly in regions at high risk of future natural disaster events. |
REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
REC323-4284 | 8 - Communications and warnings | That the NSW Government review its public awareness and communication strategies in relation to natural disasters. |
REC323-4276 | 34 - Local knowledge | That the NSW Government ensure that community groups, both existing and emerging, including First Nations groups, are well integrated into disaster recovery, by incorporating them into state recovery plans and engaging with them in between and in the lead up to natural disasters. |
REC323-4264 | 34 - Local knowledge | That the NSW Government work in partnership with key Aboriginal stakeholders, including the Jali Local Aboriginal Land Council, to prioritise the rebuild of Cabbage Tree Island, and ensure a safe and resourced evacuation plan is in place. |
REC323-4287 | 34 - Local knowledge | That the NSW State Emergency Service, in partnership with the Bureau of Meteorology, investigate ways in which local communities and local media with local knowledge can play a stronger role in flood predictions and warnings. |
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
REC323-4265 | 34 - Local knowledge | That the NSW Government work with First Nations peoples to support Aboriginal organisations in their capacity to operate and respond in times of natural disasters. |
REC323-4288 | 8 - Communications and warnings | That the NSW Government work with the Commonwealth to develop a national cross-agency app to integrate all community services and agencies into a single platform so that everyone can receive accurate and timely information from one source during emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1267 | 8 - Communications and warnings | That emergency management authorities react with heightened awareness and action when BoM issues flood watches and related warnings. |
REC297-1266 | 8 - Communications and warnings | That Government supports the anticipated SES State Flood Warning proposals aimed at improving public warnings and communication, and that the proposed warning system is consistent with the National Frameworks. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1529 | 8 - Communications and warnings | As part of the above, both the Banana Shire Council and SunWater ensure Emergency Alert messages are pre-formatted, consistent, polygons are identified according to risk, and that they are tested and practiced with the State Disaster Coordination Centre. |
REC271-1528 | 8 - Communications and warnings | Prior to September 2015, SunWater and the Banana Shire Council jointly develop a multi-channel, common warning strategy, including common language and consistent messaging, for residents downstream of |
REC271-1527 | 8 - Communications and warnings | Prior to September 2015, the Banana Shire Council develops a multi-channel warning strategy and associated public information campaign, including common language and consistent messaging, for the Banana Shire. |
REC271-1522 | 26 - Research | Banana Shire Council investigate means to prioritise the commissioning of a fit-for-purpose flood study for high-risk areas across the Banana Shire to better inform flood risk management, including improved town planning. The outcomes of such a study should be available to the public and inform flood awareness campaigns, flood warnings, and building approvals. |
REC271-1521 | 26 - Research | The Department of Energy and Water Supply and SunWater, undertake the necessary studies to determine whether or not it is feasible to operate Callide Dam as a flood mitigation dam. Such studies should include matters in relation to, but not limited to: |
REC271-1533 | 14 - Incident Mgt Teams | State Disaster Coordination Centre considers requesting a representative from critical infrastructure owners be present as a liaison officer in the State Disaster Coordination Centre during activations for events that may impact on their assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0792 | 8 - Communications and warnings | The Department of Human Services should develop an improved model for communication for future disasters that provides a single point of information and contact for disaster affected communities |
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0813 | 26 - Research | Develop and maintain a comprehensive flood model and flood modelling framework for the Hawkesbury-Nepean Valley. |
REC238-0807 | 26 - Research | Develop a comprehensive road evacuation network model for floods in the Hawkesbury-Nepean floodplain to inform evacuation capacity assessments and strategic transport and land use planning, and to assist with the real-time operational management of evacuation during floods. |
REC238-0804 | 26 - Research | Clarify roles, responsibilities and consider funding options for post-event collection of data and flood intelligence. |
REC238-0799 | 18 - Access to fire ground | Develop and implement a program of cost-effective road improvement works that can enhance flood evacuation capacity in the short-medium term. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2826 | 21 - Role of Commonwealth Government | The Australian Government coordinate the development of a highly skilled workforce which can respond effectively to a sustained pandemic in Australia. |
REC232-2825 | 21 - Role of Commonwealth Government | The Commonwealth Government support the growth of vaccine development and production capacity for vaccines in Australia, to enhance Australia’s preparedness to respond to outbreaks of infectious disease in Australia, and in particular, pandemic influenza. |
REC232-2823 | 8 - Communications and warnings | The Australian Government, in consultation with consumers and other relevant federal, state and territory agencies, develop a national communication strategy for consumers to be used in the event of an infectious disease outbreak. |
REC232-2821 | 26 - Research | The National Health and Medical Research Council, in conjunction with key stakeholders, work collaboratively to provide more support for initiatives to increase international infectious disease research collaborations and build research capacity, particularly with neighbouring countries in the Asia-Pacific region. |
REC232-2820 | 21 - Role of Commonwealth Government | Having regard to the terms of the Torres Strait Treaty, the Department of Health and Ageing, Queensland Health, AusAID and the Papua New Guinea Government: |
REC232-2817 | 21 - Role of Commonwealth Government | The Australian Government work with the state and territory governments to assess the viability of providing a centralised refugee and migrant health service in each state and territory, which would automatically refer people who move from immigration detention into the wider Australian community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1836 | 26 - Research | Flood studies will be undertaken to determine the flood extent on the basis of a greater than 1 in 100 ARI, where appropriate: |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
REC217-1816 | 21 - Role of Commonwealth Government | That the Department of Sustainability and Environment continue to invest in the auditing of Victoria’s levee systems, both public and private, so that the Victoria Flood Database contains reliable and up to date data, including information on levees’ location, height, condition and ongoing viability for flood protection. |
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2870 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: streamlining the authorisation processes for urgent warnings. |
REC216-2869 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: developing tools and workflows to quickly and reliably transform technical data into intelligence that can be used to construct messages for community information that are timely, relevant, tailored and effective. |
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0696 | 21 - Role of Commonwealth Government | Carriers, councils and the Australian Communications and Media Authority should take into account the risk of flooding when considering the placement of telecommunications facilities. |
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0449 | 7 - Inter-agency communication | the state ensure that interoperable information management practices are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0402 | 8 - Communications and warnings | the state develop a flood warning system for each basin and location with community input and make relevant documents publicly available. Each warning system should include key performance indicators. |
REC199-0434 | 8 - Communications and warnings | the state require that agencies operate in compliance with the guidelines of the Victorian Warning Protocol to ensure efficacy of warning messages. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0439 | 8 - Communications and warnings | the state review its Memoranda of Understanding with official emergency broadcasters to take account of increased usage of internet based information, including social media and the ability to broadcast community meetings |
REC199-0418 | 7 - Inter-agency communication | the state develop an efficient process to ensure that, during flood events, temporary construction of flood mitigation works, such as levees, is controlled so as not to unacceptably impact on flood intelligence. |
REC199-0447 | 7 - Inter-agency communication | the state ensure that common and interoperable resource management systems are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0458 | 7 - Inter-agency communication | the state ensure: • a common, functional and accessible system be introduced to enable effective Municipal Emergency Coordination Centre and Incident Control Centre communications • a regime of regular Municipal Emergency Coordination Centre exercising is introduced with oversight by an appropriate independent body. Such exercising should include testing of systems utilised for Incident Control Centre and Municipal Emergency Coordination Centre communications • those required to perform Emergency Management Liaison Officer roles have undertaken appropriate training; and • resource requesting arrangements are clarified and documented so that control and coordination functions do not overlap. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0433 | 8 - Communications and warnings | the state develop and implement standards for Emergency Alert to ensure consistent use, training and application by accredited operators within agencies across ‘all hazards’. |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0438 | 8 - Communications and warnings | the state investigate the ability to refine the Flood and Storm Information Line to enable it to receive as well as provide information. |
REC199-0416 | 26 - Research | the state establish appropriate arrangements to ensure the capacity to maintain technical expertise for flood intelligence is initiated, including appropriate agreements with commercial experts. |
REC199-0446 | 7 - Inter-agency communication | the state commit to securing effective multi-agency interoperable communications as a high level priority and that all future communications projects and upgrades incorporate compliance provisions mandating interoperability requirements. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0432 | 8 - Communications and warnings | the state develop and implement a single web portal as a means of providing emergency information to communities and local government on an ‘all hazards’ basis, including the information referred to in recommendations 74, 89 and 92. |
REC199-0471 | 8 - Communications and warnings | the state and the commonwealth, during a flood event, make information available on providers who have capacity to accommodate patients and residents who require evacuation. |
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0437 | 8 - Communications and warnings | the state engage with local government to ensure emergency services’ public information and warnings reflect the community demographic. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0444 | 2 - Emergency powers | the state, as a matter of urgency, develop a multi-agency Incident Control Team capability to be readily available for statewide deployment to establish incident control or to relieve functioning control structures. |
REC199-0453 | 20 - Role of police | Victoria Police revise coordinator arrangements to ensure: • a coordinator presence is maintained at the place where incident control is being exercised • effective control is established and is maintained until the response phase has concluded • key control roles may be performed by personnel from agencies other than the designated control agency • that the timely compilation and distribution of an appropriate Incident Action Plan is recognised as a fundamental component of establishing effective control • those performing the coordinator role at an Incident Control Centre be suitably trained, skilled and experienced in emergency management and where possible possess a degree of local knowledge of the relevant area; and • that the revised coordinator arrangements are reflected within the State Emergency Response Plan |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
REC199-0436 | 8 - Communications and warnings | the state develop a standard approach to the provision of emergency warnings and information in formats – spoken and written – that recognise diverse community needs, including language and disability |
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
REC199-0451 | 15 - Inter-service cooperation | the state ensure, as a matter of priority, that the State Control Centre is able to function as a fit for purpose, multi-agency emergency management centre. Necessary works to achieve this outcome should have an overarching focus on the implementation of common agency systems and processes to the fullest extent possible. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
REC199-0435 | 8 - Communications and warnings | the state put in place appropriate measures to inform the community of the intended purpose of the Emergency Alert warning system. |
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0440 | 8 - Communications and warnings | the state actively pursue the use of social media as part of its emergency warning and public information system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2946 | 21 - Role of Commonwealth Government | That a national agency sponsored by the Commonwealth Government be established to undertake national coordination of flood risk management and to operate the system of premium discounts and the flood risk reinsurance facility. The Agency would: |
REC187-2918 | 21 - Role of Commonwealth Government | That an agency sponsored by the Commonwealth Government be created to manage the national coordination of flood risk management and to operate a system of premium discounts and a flood risk reinsurance facility, supported by a funding guarantee from the Commonwealth. |
Rec-ID | Code | Recommendation |
---|---|---|
REC154-3461 | 24 - Govt responsibility | DPI should develop an Memorandum of Understanding (MOU) with the Department of Human Services that capitalises on and strengthens the current good working relationship to support joint forward planning and risk management and mitigates against relationship failure in the event of leadership change. The MOU should clarify: |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3166 | 21 - Role of Commonwealth Government | That, in the absence of other satisfactory government controlled and operated post-arrival quarantine stations becoming available before the options to renew the leases of Eastern Creek and Spotswood Quarantine Stations expire, those options be exercised. |
REC148-3152 | 21 - Role of Commonwealth Government | That the person holding the position of Inspector General of Horse Importation may be removed in the following circumstances only: |
REC148-3165 | 21 - Role of Commonwealth Government | That there continue to be in Australia government controlled and operated post-arrival quarantine stations for horses. |
REC148-3151 | 21 - Role of Commonwealth Government | That the person holding the position of Inspector General of Horse |
REC148-3164 | 21 - Role of Commonwealth Government | That there be similar facilities for the unloading and transfer of horses at any other airport in Australia that might receive horses imported from places other than New Zealand. |
REC148-3148 | 21 - Role of Commonwealth Government | That the Secretary of the Department of Agriculture, Fisheries and Forestry designate, without delay, a Senior Executive Service officer to be primarily responsible and accountable for the importation of horses into Australia and to that end to have the power to exercise all necessary authority. |
REC148-3163 | 21 - Role of Commonwealth Government | That there be provided without delay at Sydney (Kingsford Smith) and Tullamarine Airports facilities to enable people who might have had contact with imported horses to shower and change their clothes, under supervision, before leaving the airport. |
REC148-3162 | 21 - Role of Commonwealth Government | That facilities for the unloading and transferring of horses at Tullamarine Airport in Melbourne be constructed urgently, upon advice of experts in biosecurity containment, to enable adequate biosecurity precautions to be taken effectively and to minimise the risk of injury to horses and those handling them. |
REC148-3168 | 21 - Role of Commonwealth Government | That each government controlled and operated quarantine station have sufficient staff to carry out properly all activities and measures required by the current operating procedures dealing with the quarantine of horses. |
REC148-3161 | 21 - Role of Commonwealth Government | That the facilities for unloading and transferring of horses at Sydney (Kingsford Smith) Airport be upgraded without delay, following the advice of experts in biosecurity containment, so as to enable appropriate biosecurity precautions to be taken effectively and to minimise the risk of injury to horses and those handling them. The facilities should include at least one padded box or stall sound-proofed to the extent that it is reasonable to do so. |
Rec-ID | Code | Recommendation |
---|---|---|
REC134-3520 | 21 - Role of Commonwealth Government | To improve the management of the National Medical Stockpile, the ANAO recommends that the Department of Health and Ageing incorporate into its governance framework: |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3629 | 8 - Communications and warnings | We recommend that NSW Health continue with its good work and continue to improve communication mechanisms with those, such as GPs, likely to be affected in major infectious disease outbreaks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3606 | 24 - Govt responsibility | That the Department of Primary Industries address the forthcoming potential shortage of veterinary pathologists and agronomists within its testing facilities by positive recruitment actions over the next five years such as offering scholarships or training existing professional staff to develop skills in pathology. |
REC128-3600 | 34 - Local knowledge | The Department of Primary Industries continue to consult local community about emergency planning and sites for disposal to retain confidence in the event of a genuine emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3891 | 15 - Inter-service cooperation | That Melbourne Water and councils explore opportunities for working collaboratively to address the management of flooding risks with a view to optimising the efficient and effective use of their flood mitigation resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3933 | 15 - Inter-service cooperation | That DPI formalises agreements between divisions and groups that allow staff to be involved in incursion responses and reflects this requirement in individual duty statements. |
REC112-3920 | 15 - Inter-service cooperation | That better use be made of Primary Industries Research Victoria's (PIRVIC) facilities by strengthening links with relevant groups of expertise, such as the Forest Science Centre. |