Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4227 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the membership of the K’gari Locality Specific Fire Management Group be expanded to include representatives of the Butchulla people, community associations from each township and tourism and business operators with interests on the island. |
REC322-4230 | 34 - Local knowledge | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services engages with land managers and other stakeholders on K’gari to source data to inform Predictive Services products. |
REC322-4250 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the Locality Specific Fire Management Group for K’gari meet at least twice per year, in person or virtually. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4186 | 34 - Local knowledge | Supporting local recovery: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department work with councils and communities before, during and after emergencies to strengthen: |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2407 | 39 - Disaster Risk Management | Discontinue the automatic allocation of Fire Warden powers to Council and Committee members and substitute an option for members to be appointed as Fire Wardens. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1213 | 34 - Local knowledge | Structures to incorporate local knowledge and situational awareness into the fire response |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0865 | 34 - Local knowledge | That Tasmania Fire Service reviews its position on using local experienced officers on the fire ground in the command model in a structured and systemic way. |
REC247-0863 | 34 - Local knowledge | That Tasmania Fire Service considers measures to bring local knowledge into Incident Management Team operations. |
REC247-0875 | 34 - Local knowledge | That Tasmania Fire Service reviews its integration of rural local knowledge and volunteer brigades into fire operations, develops and maintains appropriate strategies, and aims to be a best-practice fire service in this regard. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0561 | 34 - Local knowledge | Suitably experienced local representatives should be engaged to provide advice to the IMT in all Level 2 and Level 3 incidents at the earliest opportunity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0519 | 34 - Local knowledge | The Department of Environment and Conservation review its practices and procedures in the undertaking of prescribed burns so as to fully utilise the skills available to it in a seamless way including but not limited to: · volunteer bushfire brigades, especially in regard to use as a source of local advice; and · staff of the Fire and Emergency Services Authority of Western Australia. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1675 | 39 - Disaster Risk Management | PowerWater Corporation be consulted with the intention of establishing a Memorandum Of Understanding for the maintenance of PowerWater land for the purpose of coordinated fire reduction. |
REC209-1674 | 39 - Disaster Risk Management | That the concession holder of the rail corridor be approached to formalise a Memorandum of Understanding for the maintenance of the railway corridor for the purposes of fuel load reduction. |
REC209-1667 | 39 - Disaster Risk Management | Prepare a formal proposal for the creation of pastoral/Indigenous Lands Fire Management Teams. |
REC209-1666 | 39 - Disaster Risk Management | Investigate the application and cost of the creation of District Coordination Officers to key high demand brigade districts. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0293 | 34 - Local knowledge | Suitably experienced personnel with local knowledge should be connected to the Operations and Planning section in all Level 3 incidents in the vicinity of substantial settlements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0234 | 34 - Local knowledge | Ensure that local knowledge, local flavour and local language is used where possible in the development of all community bushfire warnings. |
REC196-0238 | 34 - Local knowledge | Encourage ICCs to use local knowledge to review templates prior to release. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0038 | 34 - Local knowledge | The ISU should be provided with a person with local knowledge at Level 3 incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2246 | 34 - Local knowledge | That DSE undertake community consultation on policies relating to roads and access tracks on public land, particularly in respect to fire management. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2233 | 34 - Local knowledge | That communities, public land managers, Water Authorities and Catchment Management Authorities jointly identify and implement local and environmentally sound solutions to improve the availability of water for firefighting through the Municipal Fire Management Planning process. |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |