Rec-ID | Code | Recommendation |
---|---|---|
REC326-4343 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures a communications plan is in place, including the communication of guidelines to potential applicants. |
REC326-4344 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: establishes and follows guidelines that align with relevant good practice guidance including accountabilities, key assessment steps and clear assessment criteria. |
REC326-4340 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: documents all key decisions and approvals in line with record keeping obligations. |
REC326-4341 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures regular monitoring is in place as part of funding deeds. |
REC326-4342 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4041 | 9 - Community education | The ESA Community Education and Engagement program be adapted to include an expanded role for RFS volunteers and include a wider set of stakeholders who are more vulnerable to the impact of bushfire. A plan would require wider involvement across stakeholder organisations such as Directorates who have existing relationships with vulnerable groups. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
REC316-4040 | 41 - Emergency Management exercises | The PICC be exercised in conjunction with any and all Emergency Plan exercises to test and refine strengthened arrangements. |
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4046 | 33 - Relief and recovery | Emergency Plan and Recovery sub-plans should be amended to better define recovery mechanisms and responsibilities, including hand over points to recovery authorities and community engagement for the delivery of long term recovery mechanisms. |
REC316-4028 | 41 - Emergency Management exercises | Any changes to the ECC structure and role be exercised both within ESA and across a WHoG exercise and testing program. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
REC316-4045 | 42 - Culture and Heritage | WHoG desktop exercise should be conducted to test and support relocation and evacuation planning. |
REC316-4023 | 41 - Emergency Management exercises | An opportunity to exercise and test the formation and functioning of a Management Executive through desktop and/or limited scenario-based exercises be provided. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4032 | 41 - Emergency Management exercises | Concurrent and/or non–standard emergencies such as energy supply impacts be included in future exercise programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3813 | 35 - Business and Industry in relation to industry | That, in order to ensure tourism businesses are prepared for natural disasters including bush fires, Resilience NSW work with NSW RFS and Destination NSW to develop bush fire preparedness support for tourism businesses, based on research into existing models. Over time, this support could be expanded to include other natural hazards. |
REC315-3833 | 3 - Biodiversity | That Government invest in long-term ecosystem and land management monitoring, modelling, forecasting, research and evaluation, and harness citizen science in this effort. This will include, among other things: |
REC315-3869 | 42 - Culture and Heritage | That, in order to ensure Aboriginal people can access appropriate support during evacuation, Resilience NSW work with Local Emergency Management Committees and Aboriginal Affairs to ensure: |
REC315-3821 | 4 - Fire season preparation | That government agencies managing land (at all levels and through all agencies) be the best neighbours possible by considering their neighbours when undertaking activities related to bush fire preparation and having clear, two-way communication about these activities, with the aspiration that government landholders will be seen as highly desirable neighbours. |
REC315-3847 | 17 - Assets and technology | That, in order to ensure Australia’s fire fighting aerial capacity capitalises on existing assets and is made up of the right mix, Government: |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3812 | 25 - Inquiry, audit, lessons management and after action review | That Government commit to: |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3868 | 33 - Relief and recovery | That, in order to ensure people only need to tell their story once to access government agency support following an emergency, Resilience NSW and Service NSW jointly design an inclusive, person-centred approach to information collection at evacuation centres. This should be supported by an opt-in scheme enabling personal information to be shared between NSW government agencies, local councils and non-governmental organisations administering support services for disaster-affected people. |
REC315-3843 | 17 - Assets and technology | That, in order to improve early fire suppression, the NSW RFS trial initial aerial dispatch in areas of high bush fire risk. The trial should identify the most appropriate and cost-effective mix of aircraft, and any associated infrastructure improvements that would be required. |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3810 | 24 - Govt responsibility | That, to ensure updated resource-sharing arrangements are in place, the NSW and Victorian Governments progress and finalise a multi-agency Memorandum of Understanding before the 2020-21 fire season commences. |
REC315-3829 | 4 - Fire season preparation | That, in order to ensure outcomes-based roadside vegetation management to reduce roadside tree fall and grass ignitions in planning and preparing for bush fire, Transport for NSW, working with local government and NSW RFS, establish a consistent framework for roadside vegetation management that analyses road priority, utility, amenity, strategic value and risk. The framework should: |
REC315-3864 | 9 - Community education | That, in order to ensure people can access clear information on cross-border fires, the NSW RFS: |
REC315-3817 | 5 - Hazard reduction burns | That Government, noting that hazard reduction targeted in proximity to assets is on balance more likely to provide help than hinder, should: |
REC315-3842 | 24 - Govt responsibility | That, in order to prioritise early suppression and keep fires small: |
REC315-3824 | 1 - Land-use and building regs | That Government commit to shifting to a strategic approach to planning for bush fire, and develop a new NSW Bush Fire Policy similar to the NSW Flood Prone Land Policy in order to accommodate changing climate conditions and the increasing likelihood of catastrophic bush fire conditions; to build greater resilience into both existing and future communities; and to decrease costs associated with recovery and rebuilding. |
REC315-3850 | 3 - Biodiversity | That Government develop and implement a policy on injured wildlife response, rescue and rehabilitation including: |
REC315-3808 | 22 - Role of local Gvt | That, in order to strengthen the capability of local councils in future emergency events: |
REC315-3860 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure the guiding principles and approval processes are contemporary, streamlined and more flexible, the NSW and Commonwealth Governments review the Defence Assistance to the Civil Community (DACC) arrangements. This review should include the circumstances in which the State can request Commonwealth assistance, and the level of information provided by the ADF to the State on available resources and capabilities. |
REC315-3816 | 5 - Hazard reduction burns | That Government re-commit to the current, regionally based approach to planning and coordinating hazard reduction activities across all tenures through Bush Fire Management Committees but ensure that it is actually being implemented at a high-level of quality across NSW. Getting it to a high-level of quality requires: |
REC315-3837 | 17 - Assets and technology | That, in order to improve firefighter safety, Government fire authorities: |
REC315-3823 | 42 - Culture and Heritage | That, in order to increase the respectful, collaborative and effective use of Aboriginal land management practices in planning and preparing for bush fire, Government commit to pursuing greater application of Aboriginal land management, including cultural burning, through a program to be coordinated by Aboriginal Affairs and Department of Planning, Industry and Environment working in partnership with Aboriginal communities. This should be accompanied by a program of evaluation alongside the scaled-up application of these techniques. |
REC315-3849 | 17 - Assets and technology | That, in order to enhance NSW’s fire fighting capacity, Government trial aerial fire fighting at night in the 2020-21 season with a view to full implementation if successful. |
REC315-3799 | 9 - Community education | That at the start of each fire season, based on advice from the Bush Fire Coordinating Committee, Government provide a public statement with an evaluation of the likely fire season risk and the effectiveness of the planning and preparation for the upcoming season. This should be based on sophisticated monitoring of the key risk factors and signals for an extreme fire season. It should form the basis for clear public communication about these risks on a regional basis and the actions that Government proposes in preparation. |
REC315-3828 | 9 - Community education | That, in order to improve bush fire planning and protection of road infrastructure and to ensure communities, freight movers and fire fighting agencies have appropriate access and egress in a bush fire event, Government, working with local government as needed: |
REC315-3859 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure State Emergency Operations Centre (SEOC) interoperability during all natural disasters, Resilience NSW review the current SEOC arrangements and location including responsibilities for ongoing resourcing and maintenance. |
REC315-3815 | 17 - Assets and technology | That, in order to equip NSW RFS with comprehensive information on all structures and assets at risk of bush fire, Government ensures that: |
REC315-3836 | 17 - Assets and technology | That, in order to ensure frontline personnel have appropriate personal protective clothing during bush fires: |
REC315-3873 | 25 - Inquiry, audit, lessons management and after action review | That Resilience NSW review existing functional area arrangements to ensure they are closely aligned to agencies responsible for direct service delivery. |
REC315-3822 | 42 - Culture and Heritage | That Government adopt the principle that cultural burning is one component of a broader practice of traditional Aboriginal land management and is an important cultural practice, not simply another technique of hazard reduction burning. |
REC315-3848 | 17 - Assets and technology | That, in order to enhance NSW’s ability to improve situational awareness, Government expand FRNSW’s Remotely Piloted Aerial Systems (RPAS) capability (both capital assets and trained operators) to major regional centres and ensure the NSW RFS and other NSW government agencies can access this capability as required. |
REC315-3798 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure recommendations accepted by the Government are implemented in a timely and transparent manner, Government establish a central accountability mechanism to track implementation of recommendations from bush fire-related reviews and inquiries and consider expanding this to other policy areas. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3858 | 25 - Inquiry, audit, lessons management and after action review | That, in order to improve cross-agency communication and coordination during bush fires, the NSW RFS review Fire Control Centres (FCCs) in areas that were heavily affected by fire. The results should be combined with the Emergency Operations Centre (EOC) Facilities Review to identify areas that would benefit from a purpose-built FCC, enabling co-location with the EOC. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3261 | 24 - Govt responsibility | Consider amending the Fire and Emergency Services Act 2005 to align SAFECOM Board operations with accepted governance standards with the Minister appointing an Independent Chair of the SAFECOM Board. The SAFECOM Chief Executive (CE) should report to the Board and maintain SAFECOM’s role at the direction of the Board. Alternatively, SAFECOM could be abolished, moving to a model of a Department of Fire and Emergency Services where the departmental head reports to the Minister but the value proposition of any such machinery of government change would need to be thoroughly examined. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3270 | 17 - Assets and technology | Review the use of aviation assets including facilities to operate them given the increased pressure from extended fire seasons on northern and southern hemisphere resources. Review line scanning capability with a view to providing real time data to the IMTs on where fires are burning using aviation assets as an intelligence tool rather than just a fire suppression capability. |
REC314-3264 | 6 - Insurance and legal liability | Consider removing stamp duty from home insurance to encourage a wider section of the community to take out insurance. South Australian government agencies should share their risk modelling data with the Insurance Council of Australia. |
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2402 | 17 - Assets and technology | Explore better options for call and dispatch, telecommunications and information sharing capability across the emergency management portfolio including the adoption of a multi-agency emergency management operations complex |
REC302-2399 | 24 - Govt responsibility | Implement a fully integrated civilianised single call and dispatch centre, that includes a redundancy option outside the Sydney CBD, which will adopt an agnostic approach to deploy the quickest most suitable resource to an emergency. Such a centre should be managed by either a non uniformed public servant staffed organisation like the Office for Emergency Management, or the NSW Police Force |
REC302-2398 | 17 - Assets and technology | As a matter of priority commence the roll out of AVL capability for the Rural Fire Service fleet, completing as much work as possible before the 2018/19 bushfire season, capitalising where necessary on current and future work undertaken with the NSW Government Radio Network to ensure both officer safety and situational awareness |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2385 | 25 - Inquiry, audit, lessons management and after action review | TFS should initiate a policy review (seeking support from government as appropriate) to clearly identify what body or agency is responsible for planning, carrying out and enforcing fuel management on private property at a township level. If current arrangements are unclear or ineffective, TFS should request government to consider making this a statutory responsibility of TFS and provide any additional funding required to support this function. |
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
REC291-1249 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Premier and Cabinet to conduct an independent review of the current arrangement for the management and distribution of the Emergency Services Levy. The review will have the specific purpose of: · seeking input from key entities including the Departments of Treasury, Finance, Fire and Emergency Services, Lands, and Parks and Wildlife, WA Local Government Association, and the Office of Bushfire Risk Management. · ensuring the arrangement has the flexibility and agility to deal with emerging bushfire risk priorities. · establishing a budget process that enables a shift in investment towards prevention, mitigation and building community resilience and capability. |
REC291-1233 | 25 - Inquiry, audit, lessons management and after action review | The State Government to explore options for streamlining the functions and the independence of the State Emergency Management Committee Secretariat and the Office of Bushfire Risk Management with a view to including an inspectorate function, and appointing a person who is dedicated to that role. The purpose is to provide assurance and reporting, and to inquire into, monitor and report transparently on emergency management standards, preparedness, capability, service delivery and investment performance outcomes. Within two years of the establishment of this arrangement the State Government to review and assess whether it is meeting the desired outcomes. |
REC291-1248 | 24 - Govt responsibility | The State Emergency Management Committee to establish a State Bushfire Coordinating Committee as a sub-committee of SEMC. The State Bushfire Coordinating Committee will be chaired by the Director of the Office of Bushfire Risk Management and will have the primary responsibility to: · develop a State Bushfire Management Policy and a set of long term bushfire risk management objectives; · provide a forum for key bushfire risk management stakeholder agencies; · advise the SEMC on matters pertaining to bushfire, in particular, to report against the investment in, and achievement of the bushfire risk management objectives; · provide advice and support to the proposed Chief Officer of the Rural Fire Service on bushfire risk management matters; and · report to SEMC and to the community on bushfire risk management matters on at least an annual basis. |
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1184 | 24 - Govt responsibility | The Tasmanian fire agencies think more broadly about how staff who are already employed by Government could support the management of future emergencies. |
REC287-1188 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies commission a review into the efectiveness of aerial firefghting in the 2016 fires, in order to better understand and to document for future reference the cost-efectiveness of specifc fire suppression strategies and tactics in different vegetation types. The Review should include a comparative analysis of fire suppression options whether aerial or ground-based. |
REC287-1186 | 9 - Community education | The Tasmanian fire agencies review: • their pre-season engagement with groups such as (but not limited to) environmental groups who might beneft from a greater understanding of fire management tactics, in order to inform them of and receive feedback on intended approaches to firefghting and fire management the work of the Public Information Section at incident management, regional and State level, to develop an increased appreciation of what information management might be most appropriate to serve the public interest in understanding the progress of the incident and to identify ways of providing surge capacity to resource effective information management in protracted and signifcant incidents. |
REC287-1185 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies take steps at a national level to share learnings from the 2016 fires about the administration of interstate assistance and support the codifcation of the workings, structure and reporting lines of an Interstate and International Liaison Unit for future complex deployments within Australia and New Zealand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1141 | 21 - Role of Commonwealth Government | SACFS and the BoM review current weather, fuel loads and curing rates to determine the most appropriate and accurate forecast is prepared, issued and validated against current conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1083 | 9 - Community education | The State, led by Emergency Management Victoria, develop a community engagement model for emergency management to ensure all State agencies and local governments engage with communities and already identifed trusted networks as an integral component of emergency management planning. |
REC264-1072 | 25 - Inquiry, audit, lessons management and after action review | The State empower and require the Auditor-General or another appropriate agency, to: • oversee the implementation of these recommendations and the commitments made by the State and GDF Suez during this Inquiry; and • report publicly every year for the next three years on the progress made in implementing recommendations and commitments. |
REC264-1087 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • practice and ensures that, by taking a risk management approach, it is suitable for fire prevention, mitigation and suppression in all parts of the Hazelwood mine; and review its ‘Mine Fire Service Policy and Code of Practice’ so that it refects industry best • work plan for the Hazelwood mine. incorporate the revised ‘Mine Fire Service Policy and Code of Practice’ into the approved |
REC264-1086 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • consequences of fire in the worked out areas of the Hazelwood mine, and an assessment of the most effective fre protection for the exposed coal surfaces; conduct, assisted by an independent consultant, a risk assessment of the likelihood and • controls are in place to eliminate or reduce the risk of fre; and prepare an implementation plan that ensures the most effective and reasonably practicable • implement the plan |
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1539 | 25 - Inquiry, audit, lessons management and after action review | Defence Security Authority conduct an investigation into the whereabouts of items of anaccounted explosive ordnance issued to Defence Explosive Ordnance Training School Exercise Marrangaroo. |
REC257-1548 | 25 - Inquiry, audit, lessons management and after action review | The Regional Director-Defence Support-Northern NSW, make contact with Deputy Commissioner ~~~~~ Director of Operational Services Rural Fire Service, to arrange a headquarters driven bipartite review of the events of 16 October 2013 with a review to mitigation of future fire events generally, and with specific reference to: |
REC257-1546 | 25 - Inquiry, audit, lessons management and after action review | Defence undertake a review of its ability to respond to a fire within Marrangaroo Training Area, whether bushfire or structural. The underlying assumption should be that the only response available to fight a fire within Marrangaroo Training Area will be provided by Defence. Further, such response must occur while a fire is in its initial stages. A review must either acknowledge the risk of fire occurring in th future, or upgrade Defence's firefighting capability at Marrangaroo Training Area. |
REC257-1544 | 17 - Assets and technology | Defence should not procure any firefighting vehicle for Marrangaroo Training Area without first consulting relevant personnel within the Rural Fire Service on an appropriate type of vehicle, and obtaining training for the personnel proposed to use it. Alternatively, Defence should explore contracted firefighitng support during periods of live-fire on Marrangaroo Training Area. |
REC257-1542 | 17 - Assets and technology | Firefighitng capability at Marrangaroo Training Area be upgraded so that Australian Defence Force members are not placed in situations of unacceptable risk. Specifically, those participating in range practices must have access to a firefighting vehicle close by and easily deployed, and capable of throwing a large quantity of water an appreciable distance into areas adjacent to the ranges, should a fire occur. |
REC257-1541 | 17 - Assets and technology | A Stryker unit, or an upgraded firefighting unit, be present at the range sentry point, remain manned and ready to deploy during range activites, with its driver in direct radio contact with the Range Safety Officer. Upon the range being declared clear by the Safety Officer inspecting the range after a demolition serial, the firefighting unit must proceed forward to the range wile the periphery of the range continues to be inspected by the Safety Officer, and remain on the range until the Safety officer declares that the area is clear of fire or that it is otherwise appropriate for the fireghting unit to leave the range area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0894 | 17 - Assets and technology | That the police and other emergency service organisations discuss their resource issues for emergency operations with the Government. |
REC247-0937 | 19 - Offences | That the legislation and enforcement arrangements are reviewed to ensure there are suitable offences and penalties, investigation and enforcement capabilities, and a rigorous approach is taken to breaches of the law. |
REC247-0907 | 33 - Relief and recovery | That the State Emergency Management Committee ensures that a program of debriefing on recovery issues is completed by all relevant agencies and organisations, and detailed plans and operating procedures are established ready for implementation. |
REC247-0943 | 9 - Community education | That a bushfire community education and information strategy be professionally developed and coordinated across the fire authorities by Tasmania Fire Service. |
REC247-0878 | 17 - Assets and technology | That bushfire agencies evaluate the use and effectiveness of fixed wing water bombing aircraft. |
REC247-0927 | 25 - Inquiry, audit, lessons management and after action review | That an accountability process be established for managing improvement in the emergency management arrangements, including annual State of Readiness Reports by relevant departments and agencies and on the overall emergency management arrangements. |
REC247-0893 | 17 - Assets and technology | That further options to appropriately supplement the resources available for emergency management operations be examined. |
REC247-0935 | 4 - Fire season preparation | That the State Emergency Management Committee includes in its planning, the development of contingency emergency management plans for areas of high risk due to local conditions. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0942 | 1 - Land-use and building regs | That the Government makes land use planning and building construction to prevent and mitigate bushfire risk a high priority and establishes a means to progress improvements in this area, such as a designated body or group, as soon as possible. |
REC247-0873 | 25 - Inquiry, audit, lessons management and after action review | If it is considered more information is required on action to suppress the fires in Dunalley and why fire operations did not continue, the Department of Justice should conduct an independent examination of this matter. |
REC247-0926 | 25 - Inquiry, audit, lessons management and after action review | That membership of the State Emergency Management Committee, and other processes to link in appropriate agencies and organisations to emergency management, be included in the recommended review of the emergency management arrangements. |
REC247-0892 | 17 - Assets and technology | That a review be conducted of the resource capacity and capability to provide effective and efficient emergency operations, including approved improvements. |
REC247-0934 | 4 - Fire season preparation | That the State Fire Management Committee considers developing a structured, systemic and proactive bushfire hazard reduction program with municipal councils and Tasmania Fire Service; and advises the Government on any legislative or other changes required to implement such a program. |
REC247-0903 | 25 - Inquiry, audit, lessons management and after action review | That the role of Red Cross in emergency management plans and procedures for the activation of Red Cross be reviewed. |
REC247-0941 | 25 - Inquiry, audit, lessons management and after action review | That the Strategic Fuel Management Plan includes measurable targets and they are actively monitored and reported on to the community. |
REC247-0855 | 17 - Assets and technology | That a structure and facilities be established for the State Controller or other person managing multi-agency response and recovery operations. |
REC247-0923 | 25 - Inquiry, audit, lessons management and after action review | That a process be established for the timely implementation of approved recommendations from the 2009 Victorian Bushfires Royal Commission. |
REC247-0891 | 9 - Community education | That emergency management plans specifically include processes for effectively engaging with local communities and using community resources, including volunteers. |
REC247-0933 | 4 - Fire season preparation | That the Government considers whether a peak body should be established, with authority to effectively implement a bushfire mitigation plan. |
REC247-0896 | 33 - Relief and recovery | That the state level structural arrangements for managing recovery operations are reviewed. |
REC247-0939 | 5 - Hazard reduction burns | That Tasmania Fire Service conducts a review of the fire permit system in the Fire Service Act 1979, and implements change to improve the efficiency and effectiveness of the system by: • considering whether it is appropriate to authorise persons or organisations to conduct fuel reduction burning during a permit period • providing a better match between the period, area and fire risk • maintaining a timely and efficient process for issuing permits • naming the period in a way that draws attention to bushfire risk • establishing a reporting and accountability process. |
REC247-0910 | 33 - Relief and recovery | That suitable facilities are established from which to effectively control and coordinate immediate recovery operations. |
REC247-0951 | 25 - Inquiry, audit, lessons management and after action review | That an independent means of monitoring and reporting on the implementation of approved recommendations is established. |
REC247-0880 | 17 - Assets and technology | That bushfire agencies develop, implement and maintain air operations procedures. |
REC247-0931 | 4 - Fire season preparation | That a specific risk prevention and mitigation advisory body be established for the State Emergency Management Committee. |
REC247-0895 | 6 - Insurance and legal liability | That action be taken as a priority to resolve any legal issues on mutual assistance arrangement for fire services. |
REC247-0938 | 5 - Hazard reduction burns | That Tasmania Fire Service or another suitable agency provides information to the community which shows, in simple form, the legislation applicable to approvals for lighting fires on private property and the various relationships between that legislation. |
REC247-0909 | 25 - Inquiry, audit, lessons management and after action review | That the plans for social recovery be reviewed, and plans and procedures are established ready for implementation. |
REC247-0944 | 9 - Community education | That the State Emergency Management Committee develops and coordinates a whole-of-government community resilience strategy for emergencies in a form that can be practically implemented, as a priority. |
REC247-0879 | 17 - Assets and technology | That bushfire agencies develop procedures for the automatic activation of aircraft to fires at pre-determined trigger points on high fire risk days. |
REC247-0928 | 24 - Govt responsibility | That the Government take into account demographic change in its assessment of the consequences of climate change on emergency events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-0970 | 17 - Assets and technology | That RFSQ retain responsibility for Air Operations and re-evaluate avenues for cost recovery when aircraft are used by other agencies. The coordination of incendiary tasking to support mitigation should sit with the RFSQ in coordination with other agencies |
REC241-1024 | 17 - Assets and technology | That the Rural Fire Service Queensland revoke its current 20 year maximum age policy on volunteer Brigade vehicles to allow Brigades wanting to retain their vehicle to do so, providing the vehicle has an annual mechanical certificate. A 30 year maximum age policy for vehicles will replace the 20 year policy. |
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-1029 | 17 - Assets and technology | That a policy be developed around the ownership, insurance and safe use and operation of All Terrain Vehicle 4WD vehicles by brigades for fire fighting purposes. |
REC241-0999 | 28 - Personal responsibility | That on all land where fuel load creates a fire risk, the owner shall be responsible for the construction and maintenance of effective firebreaks. Failure to provide effective and accessible firebreaks will result in the cost of firebreak construction to control a wildfire on this land being debited to the land owner |
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1016 | 6 - Insurance and legal liability | That a volunteer shall not be liable for any act or omission made in good faith provided it is not proven to be reckless, negligent or malicious. This protection is to be afforded in both Criminal and Common law. |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
REC241-1028 | 17 - Assets and technology | That vehicles are fit for the purpose and the Brigade locality for which they are intended. A group of two volunteers, in conjunction with the Rural Fire Brigades Association Queensland, should be charged with reviewing current models and providing Recommendations on vehicle suitability. |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-1042 | 17 - Assets and technology | The issue of red and blue lights for RFSQ and SES vehicles be further pursued by the Department of Community Safety |
REC241-0954 | 24 - Govt responsibility | That a Ministerial Advisory Council be established to inform the Minister of matters relating to Rural Fire Service and SES volunteers. |
REC241-1012 | 17 - Assets and technology | Use of private aircraft to be at the discretion of District Inspector or Incident Control and reimbursement of fuel to be authorised accordingly. |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
REC241-1027 | 17 - Assets and technology | That Rural Fire Service Queensland, in consultation with Primary Producer Brigade volunteers, redesign and reconfigure slip-on units to bring the total cost below the level required for asset registration. The redesign should allow for the foam system to be optional. |
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-1039 | 17 - Assets and technology | That the State Government supply and logistics for Personal Protective Equipment and other equipment be urgently reviewed with a focus on timely and cost effective delivery to volunteer members. |
REC241-1009 | 17 - Assets and technology | That the reflective livery on Rural Fire Service Queensland staff vehicles be kept to a minimum of a light bar and affixed Rural Fire Service Queensland logo. These vehicles are to be appropriate to the task and location. |
REC241-0979 | 24 - Govt responsibility | That the Queensland Government liaise with the Federal Government with a view to securing incentives for employers that recognise loss of income and employee time for emergency operations. |
REC241-1026 | 17 - Assets and technology | That the Rural Fire Service Queensland catalogue accurately reflects the range of equipment available. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-1036 | 17 - Assets and technology | That each District Inspector prepare a report on vehicles required over the next ten years based on current age of fleet. |
REC241-1001 | 24 - Govt responsibility | That the extent of forest and plantation fuel load fire risk in South East Queensland requires a designated government resources fire team to manage this risk and proactively conduct fuel mitigation burning; and provide a wildfire response to government land. |
REC241-0973 | 17 - Assets and technology | That all land on which rural fire brigade sheds are located be re-evaluated to formalise enforceable lease agreements. |
REC241-1025 | 17 - Assets and technology | That an ‘Options Paper’ be developed by District Inspectors on the suitability and supply of PPE and equipment to volunteers for their district. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
REC223-0523 | 25 - Inquiry, audit, lessons management and after action review | The Government consider enacting legislation to facilitate the review of all future major incidents, including but not limited to fire, earthquake, storm and marine inundation, and the emergency response to them. |
REC223-0522 | 25 - Inquiry, audit, lessons management and after action review | The response operation to the Margaret River bushfire in November 2011 be the subject of a review with independent oversight. |
REC223-0521 | 9 - Community education | The Department of Environment and Conservation develop and implement a strategy to better inform the community about the complexities and decisions surrounding prescribed burns when they are undertaken in the rural urban area. |
REC223-0516 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Conservation review its implementation of the findings of the Ferguson Review conducted in 2010. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0249 | 17 - Assets and technology | FRS fire appliance allocation and training needs to be reviewed to enhance offensive bushfire capability within the metropolitan area. |
REC201-0247 | 28 - Personal responsibility | Local residents must take a degree of shared responsibility to prepare their properties by reducing the risk of bushfire around their properties and planning for a bushfire emergency. |
REC201-0256 | 22 - Role of local Gvt | Noting existing legislative and policy arrangements, there is merit in considering options for the future management of Level 3 fires in Local Government areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1718 | 35 - Business and Industry in relation to industry | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-0345 | 22 - Role of local Gvt | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-0375 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. This program should be implemented and managed under the Bush Fires Act 1954 in a manner similar to the fire break inspection program. |
REC200-1686 | 9 - Community education | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-1726 | 41 - Emergency Management exercises | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. |
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-0384 | 25 - Inquiry, audit, lessons management and after action review | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-1694 | 24 - Govt responsibility | The State Government give its full support to the Western Australian Local Government Association's Send to Solve initiative. |
REC200-1701 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
REC200-1717 | 24 - Govt responsibility | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-0344 | 9 - Community education | The Fire and Emergency Services Authority (FESA) review its distribution of information material, including Prepare. Act. Survive. FESA should also consider including the community in pre-season exercising, in consultation with the Department for Child Protection and local governments. |
REC200-0373 | 33 - Relief and recovery | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-1685 | 9 - Community education | The Fire and Emergency Services Authority (FESA) review its distribution of information material, including Prepare. Act. Survive. FESA should also consider including the community in pre-season exercising, in consultation with the Department for Child Protection and local governments. |
REC200-1724 | 6 - Insurance and legal liability | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-0349 | 9 - Community education | The Fire and Emergency Services Authority work in partnership with Main Roads Western Australia and local governments to develop and implement a comprehensive strategy for the use of mobile variable message boards to alert the community to the declaration of a total fire ban and what it means. |
REC200-0379 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-1732 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry's recommendations in two years. |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-1716 | 24 - Govt responsibility | State and locals governments: |
REC200-0343 | 9 - Community education | The Fire and Emergency Services Authority, in partnership with local governments, conduct more focused pre-season bushfire education, which emphasises: Water supply is not guaranteed during a bushfire Power supply is not guaranteed during a bushfire Saving life will be a priority over saving property so expect to be evacuated Once evacuated, access to affected areas may not be possible for several days Water ‘bombing’ by aircraft cannot be guaranteed in bushfire SMS warnings are advice only and may not be timely. |
REC200-0367 | 22 - Role of local Gvt | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-1684 | 9 - Community education | The Fire and Emergency Services Authority, in partnership with local governments, conduct more focused pre-season bushfire education, which emphasises: |
REC200-1723 | 24 - Govt responsibility | The State Government restructure the Fire and Emergency Services Authority as a Department. As part of this restructure, Emergency Management Western Australia should either |
REC200-0348 | 9 - Community education | The Fire and Emergency Services Authority consider alternative wording to Total Fire Ban that ensures people gain a more complete understanding of what actions are prohibited. |
REC200-0378 | 17 - Assets and technology | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-1729 | 22 - Role of local Gvt | The Fire and Emergency Services Authority and local governments ensure that Community Emergency Service Managers are physically based in local government. |
REC200-0354 | 22 - Role of local Gvt | Local governments consider increasing the number of green waste collections carried out each year to encourage a more proactive approach to property (and vegetation) maintenance by residents. |
REC200-0392 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry’s Recommendations in two years. |
REC200-1699 | 24 - Govt responsibility | The State Government ensure that the continued development of the Fire and Emergency Service Authority's Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost-effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-1715 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. |
REC200-0342 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. Local Government provide information to residents on any changes to the Australian Standard relating to tethering gas tanks and encourage property owners to take action to comply with the Standard. |
REC200-0365 | 17 - Assets and technology | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA’s own policy of ‘Use of Private Vehicles in Fires’. |
REC200-1683 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-0347 | 9 - Community education | The Department of Education oversee the provision of bushfire education in schools that are located in bushfire prone areas, ensuring that all schools in these areas incorporate key bushfire messages in their curriculum. |
REC200-0377 | 1 - Land-use and building regs | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-1688 | 9 - Community education | The Department of Education oversee the provision of bushfire education in schools that are located in bushfire prone areas, ensuring that all schools in these areas incorporate key bushfire messages in their curriculum. |
REC200-1728 | 24 - Govt responsibility | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-0353 | 22 - Role of local Gvt | The State Government give its full support to the Western Australian Local Government Association’s Send to Solve initiative. |
REC200-0388 | 17 - Assets and technology | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0340 | 1 - Land-use and building regs | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-0364 | 17 - Assets and technology | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-1682 | 24 - Govt responsibility | The State Government give legislative effect to the Planning for Bush Fire Protection Guidelines. |
REC200-1719 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-0346 | 1 - Land-use and building regs | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-0376 | 1 - Land-use and building regs | State and locals governments: a) recognise that regardless of future declarations of bushfire prone areas, the existing planning and building problems in the Perth Hills related to bushfire risk will persist; b) urge residents in these areas to retrofit their homes and evaporative air conditioners in compliance with AS 3959 - 2009; c) examine options to retrospectively bring these areas into compliance with Planning for Bushfire Protection Guidelines. |
REC200-1687 | 9 - Community education | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-1727 | 24 - Govt responsibility | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
REC200-0387 | 17 - Assets and technology | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the Recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-1695 | 22 - Role of local Gvt | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-1707 | 1 - Land-use and building regs | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0361 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. This session should include open discussion and explain the decisions of all parties – including how the incident controllers determined priorities, and why residents chose not follow their advice to evacuate. The learning outcomes should be promulgated across all agencies and incorporated in future level 3 incident controller training programs. |
REC200-1681 | 24 - Govt responsibility | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0120 | 17 - Assets and technology | Maintaining the DEC fleet of tankers, bulldozers and low loaders is crucial to DEC’s fire management and control capability. |
REC183-0119 | 17 - Assets and technology | The development of a three year aerial firefighting strategy for W.A. would ensure optimal development of a joint air capability. |
REC183-0109 | 1 - Land-use and building regs | It is sensible that, in considering planning development proposals on land adjacent to the DEC estate, that development authorities invite comment from DEC on the fire management consequences of development proposals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0126 | 9 - Community education | FESA promotes a whole-of-community approach, involving FESA, Local Governments and the community, in fire prevention functions, activities and planning. |
REC182-0135 | 33 - Relief and recovery | FESA revises its standard operating procedures to provide guidance on the format and timing of post-incident community meetings. |
REC182-0134 | 17 - Assets and technology | FESA reviews its air reconnaissance capability and determines if multiple multi-sensor air reconnaissance aircraft or unmanned aerial vehicles are required for managing concurrent and/or complex incidents. |
REC182-0127 | 9 - Community education | FESA strengthens its planning process to ensure learnings are incorporated and communicated, levels of preparedness are linked to threat analyses and public awareness and education activities are sustained. |
REC182-0132 | 9 - Community education | FESA implements an education and awareness campaign to promote the purpose and utility of community information systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3546 | 22 - Role of local Gvt | Local Government to be maintained as an important component of bushfire management in South Australia because of the link with the community. |
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |