Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4273 | 33 - Relief and recovery | That the NSW Government overhaul the way in which it conducts its grants process as it frustrated applicants and further traumatised them by repeatedly re-interviewing them and making them prove that they were flooded. |
REC323-4277 | 33 - Relief and recovery | That the NSW Government develop a more proactive, rapid response to manage animal welfare following natural disasters which includes improved collaboration and communication with local veterinarians and animal welfare organisations. |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4262 | 33 - Relief and recovery | That the NSW Government provide an increased level of targeted support to flood affected communities contending with widespread mould. |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
REC323-4269 | 33 - Relief and recovery | That the NSW Government address the mental health needs of local communities following the February-March 2022 floods by: • embedding within state emergency and recovery plans a strategy that provides surge capacity for mental health and social workers by: • prioritising funding for community groups that are currently providing social and mental health support to their local communities • ensuring all flood-impacted communities receive the mental health support they need to fully recover. |
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4289 | 33 - Relief and recovery | That the NSW Government ensure that all emergency and recovery plans, including state plans, local emergency management plans and functional area plans, are reviewed and updated regularly and provide clarity on the role of non-government partners. |
REC323-4271 | 33 - Relief and recovery | That Service NSW establish teams of assessors that can be on the ground to assess and approve grant applications. |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1261 | 28 - Personal responsibility | That heightened awareness and action is needed by communities when BoM issues flood watches and related warnings. Councils and SES need to facilitate this. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1302 | 28 - Personal responsibility | That the State Emergency Service together with the Local Government Association and Country Fire Service establish a plan for coordinated provision of sandbags to the public, including options for what is provided, where and when, and the process for effective communication of availability to the public. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1207 | 33 - Relief and recovery | Communicating in Recovery: The Office of Emergency Management: · considers the development of a communications and engagement strategy for major disaster events · progresses the development of the ‘Communicating In Recovery’ Guideline in the Local Recovery Toolkit. |
REC281-1206 | 33 - Relief and recovery | Transition from Response to Recovery: That Region Emergency Management Committees meet post event to: · consider available impact data · determine the need to establish a Recovery Committee · document the rationale for the decision · advise the Office of Emergency Management of the decision. |
REC281-1204 | 33 - Relief and recovery | Transition from Response to Recovery That the Office of Emergency Management, in consultation with the NSW Police Force Emergency Management Unit develops a template for handover of the Response to Recovery Phase of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1533 | 14 - Incident Mgt Teams | State Disaster Coordination Centre considers requesting a representative from critical infrastructure owners be present as a liaison officer in the State Disaster Coordination Centre during activations for events that may impact on their assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1160 | 33 - Relief and recovery | Transition from Response to Recovery |
REC267-1156 | 33 - Relief and recovery | Streamlining NDRRA Grants Processes |
REC267-1155 | 33 - Relief and recovery | MP Recovery Reference Group |
REC267-1148 | 33 - Relief and recovery | Planning for Recovery Centres Recovery Centres are a proven means of providing support to affected communities. More comprehensive recovery planning is needed at local levels, including the identification of potential Recovery Centre sites in Local EM Plans to help facilitate streamlined establishment of the Centres in future events. Consideration should be given to developing a clear set of standard messaging regarding |
REC267-1163 | 33 - Relief and recovery | Corrections Volunteer Labour Teams |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1161 | 33 - Relief and recovery | VIP Visits |
REC267-1158 | 28 - Personal responsibility | Farm Management Deposits |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2548 | 17 - Assets and technology | The Civil Aviation Safety Authority shares the risk assessment outputs of Sky Sentinel, its computerised risk assessment system, with the applicable authorisation holder. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0805 | 33 - Relief and recovery | Develop a Hawkesbury-Nepean Flood Recovery Plan, which identifies strategies and arrangement for recovery from severe floods in the Hawkesbury-Nepean Valley. |
REC238-0806 | 33 - Relief and recovery | Review the adequacy of current arrangements for infrastructure reconstruction following a major flood event in the Hawkesbury-Nepean Valley. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2850 | 17 - Assets and technology | I recommend that the AFP be provided with a search and rescue vessel which is suitable to the specific conditions of Christmas Island. I further recommend that steps be taken to ensure that if for any reason the search and rescue vessel is not available, there is a replacement vessel on Christmas Island capable of providing an emergency response in difficult sea conditions. |
REC227-2848 | 17 - Assets and technology | I recommend that the AFP take steps to determine whether access can be obtained to the National Search and Rescue Council endorsed SARMAP program covering the Australian Search and Rescue Region as well as adjoining tiles for Indonesia. Steps should be taken to ensure that if possible coverage would include high traffic areas where SIEVs enter the Australian Search and Rescue region allowing timely search and rescue plans to be drawn up for any potential incidents. |
REC227-2846 | 17 - Assets and technology | I recommend that Border Protection Command continues to examine ways of improving its surveillance capability around Christmas Island so that the risk of SIEVs arriving undetected is reduced. |
REC227-2859 | 17 - Assets and technology | I recommend that the issue of RHIB jet intake protection be allocated a high priority and that there be ongoing investigation of possible solutions to reduce the problem. |
REC227-2851 | 17 - Assets and technology | I recommend that consideration should be given to acquiring two personal water craft for deployment by appropriately trained and equipped staff of the AFP or the VMRS or both on Christmas Island. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0724 | 28 - Personal responsibility | Councils should consider making available to business owners locality specific information that would assist them to develop evacuation plans for commercial premises, for example, any evacuation sub-plan created under Emergency Management Queensland’s disaster evacuation guidelines. |
REC210-0679 | 28 - Personal responsibility | If the Queensland Development Code is amended to include provisions requiring homeowners to install sewage reflux valves, the Queensland Government should develop and make available to homeowners appropriate guidance material to assist them in meeting their responsibilities to maintain reflux valves. |
REC210-0723 | 28 - Personal responsibility | Councils should support and encourage business owners to develop private flood evacuation plans by providing the following to business owners in areas known to be affected by flood: • information about the benefits of evacuation plans • contact details of relevant council and emergency service personnel for inclusion in evacuation plans. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC188-2917 | 33 - Relief and recovery | The committee recommends that relevant Commonwealth agencies continue to monitor the wellbeing of their personnel and that counselling and support services should be provided for as long as necessary. |
REC188-2916 | 33 - Relief and recovery | The committee recommends that the Department of Regional Australia and DIAC liaise with the Christmas Island community to explore options for a permanent memorial to be erected on the island, at a site of the residents' choosing, for the victims of the tragedy. |
REC188-2915 | 33 - Relief and recovery | The committee recommends that Department of Immigration and Citizenship (DIAC) and its relevant contractors continue to monitor the wellbeing of the survivors and that counselling and support services should be provided for as long as is necessary. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3432 | 17 - Assets and technology | That port/channel managers are required to ensure, through service agreements, licensing, direct acquisition or other means as appropriate, the availability of the critical Level 1declared assets. |
REC158-3431 | 17 - Assets and technology | That port/channel managers are required to identify in the declared asset system (in conjunction with the emergency services) critical Level 1 declared assets and other Level 2 declared assets, that may be required in support of a marine emergency within the port, and that identified resource availability, accessibility and call out time is recorded. |
REC158-3430 | 17 - Assets and technology | That the nominated marine safety authority is responsible for development of a declared asset system and is required to ensure that port/channel managers utilise and maintain the declared asset system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
REC004-3996 | 17 - Assets and technology | That the standard pattern of cinder arrester be affixed to the ash-pans in all locomotives during the summer months. |
REC004-3994 | 17 - Assets and technology | That the Railway Department, while gradually reducing the number of different types of locomotives, should steadily keep in view the adoption of English and American railway practice, by providing engines with larger boilers, fire boxers, and smoke-boxes, and with wide blast-pipes, in order to insure ample steaming power with a minimum of forced draught. |
REC004-3992 | 17 - Assets and technology | That the use of a spark-arrester and cinder-arrester by the Railway Department shall not constitute a defence to an action for damage caused by fire escaping from a locomotive, unless the Department proves that such spark-arrester and cinder-arrester were in a thoroughly efficient condition when the fire took place. |