REC327-4348 | 38 - Agency/Department Reporting | By December 2023, the Rural Fire Service should: report annually on fleet allocations to RFS Districts, and identify the ways in which fleet resources align with district-level fire risks |
REC327-4349 | 38 - Agency/Department Reporting | By December 2023, the Rural Fire Service should: develop performance measures to assess the performance and capabilities of the fleet in each RFS District by recording and publicly reporting on: fire response times and fire response outcomes; and, completions of fire hazard reduction works. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3266 | 14 - Incident Mgt Teams | Engage with the Australian Defence Force (ADF) once or twice a year to understand the capabilities that could potentially be deployed. Educate IMTs about how to deploy ADF assistance effectively and develop a streamlined ‘call out’ procedure. |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3265 | 14 - Incident Mgt Teams | Prepare to ‘scale up’ capability during major bushfire events with senior representatives (including BoM staff) in the SEC 24/7, ensure adequate facilities for IMTs, base camps (e.g. Humanihuts) and recovery centres. Consider the resource implications of providing firefighters to interstate operations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2512 | 38 - Agency/Department Reporting | Documenting results and recommendations from disaster recovery tests. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4007 | 40 - Equipment and consumables | A measure of safety may be found in the use of high explosives combined with wet tamping, or, still better, water cartridges, instead of powder under any of its modifications. Encouragement ought also to be given to the use of patent multiple wedges and applicances of a like nature, for supplanting the use of explosives. Under all circumstances and conditions some provision should be adopted for compelling workmen to thoroughly undercut, shear, or nick, and generally to work the coal as directed by the Manager. |
REC002-4012 | 38 - Agency/Department Reporting | Complete sets of daily-report books should be provided, and kept in the mine or office, to be overlooked by the Inspector during his periodical visits. |
REC002-4005 | 40 - Equipment and consumables | Where safety-lamps are used the lock should be of such a character as to prevent any workman opening it. If the "Protector" type of lamp be employed the necessity for a lock is the less necessary, as the unscrewing of this type of lamp extinguishes the light. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1261 | 28 - Personal responsibility | That heightened awareness and action is needed by communities when BoM issues flood watches and related warnings. Councils and SES need to facilitate this. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1302 | 28 - Personal responsibility | That the State Emergency Service together with the Local Government Association and Country Fire Service establish a plan for coordinated provision of sandbags to the public, including options for what is provided, where and when, and the process for effective communication of availability to the public. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-2053 | 40 - Equipment and consumables | Personal protective equipment (masks, gowns, gloves, goggles) – enhance stocktake methods. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2021 | 40 - Equipment and consumables | Review temporary bridge stockpile for adequacy (DSG). |
REC286-1443 | 14 - Incident Mgt Teams | Build capacity to enable Incident Management Teams to manage the likely increased frequency and intensity of major fire events. |
REC286-2054 | 40 - Equipment and consumables | Personal protective equipment (masks, gowns, gloves, goggles) – review supply/distribution arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2525 | 38 - Agency/Department Reporting | The report recommends that Ambulance Tasmania outline what KPIs are measured and provide targets or benchmarks to define what is good or poor performance. |
REC285-2518 | 38 - Agency/Department Reporting | The report recommends that regional summary reports of clinical reviews be standardised to facilitate review and comparison across regions. |
REC285-2517 | 38 - Agency/Department Reporting | The report recommends that Ambulance Tasmania collects data to allow regular and meaningful comparison of clinical outcomes at the regional level, to better allocate resources and to rapidly identify problems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1138 | 14 - Incident Mgt Teams | Review the communication and request procedures within SACFS to ensure that the most effective chain of command and line of communications are established between the Incident Management Team, region and state. |
REC273-1135 | 14 - Incident Mgt Teams | That SACFS conduct a review of SIMT with a view to increasing the number of teams from four to six, aligning them with each of the six regions within SA. |
REC273-1139 | 14 - Incident Mgt Teams | SACFS appoint the Regional Controller and/or Coordinator as the IC for any Level 3 incident occurring within their Region to provide better continuity and improved coordination. The position of the regional controller and/or coordinator could then be backfilled by a suitably qualified individual as required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1158 | 28 - Personal responsibility | Farm Management Deposits |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1066 | 14 - Incident Mgt Teams | That during periods of ‘severe’ or worse fire conditions, that the National Parks and Wildlife Service consider adopting a posture of pre-emptive planning and deployment of incident management teams in national parks similar to the manner in which the Rural Fire Service does. |
REC260-1053 | 14 - Incident Mgt Teams | That in Class 3 fire-fighting operations, the Rural Fire Service consider including a fire behaviour analyst in the incident management team if feasible. |
REC260-1058 | 28 - Personal responsibility | That NPWS and the RFS consider developing a land management policy that requires active engagement with property owners adjoining the Park to ensure that hazard reduction and asset protection is encouraged and undertaken before the bush fire season commences |
REC260-1052 | 14 - Incident Mgt Teams | That the Rural Fire Service consider amending its fire prediction reports to include a checklist of significant factors that have not been able to be considered in the prediction model and a warning to be alert for them and seek intelligence on them from fire ground managers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0911 | 14 - Incident Mgt Teams | That emergency management plans specifically include processes and resources for effectively engaging with and using local communities, including volunteers |
REC247-0862 | 14 - Incident Mgt Teams | That Tasmania Fire Service and its partner agencies establish a means of monitoring and reviewing the effectiveness of centralising the location of Incident Management Teams. |
REC247-0861 | 14 - Incident Mgt Teams | That Tasmania Fire Service examines options for developing and issuing fire management objectives and tactics from Incident Management Teams in a more timely way, including ‘quick’ plans. |
REC247-0853 | 14 - Incident Mgt Teams | That the State Controller (or an alternate if they are not available) be expected to personally take an active role in controlling and coordinating response and recovery operations, depending on the nature and scale of the emergency, and until other identified arrangements for ongoing operations are established. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0786 | 14 - Incident Mgt Teams | TFS develop written guidelines for the use of IMTs about the use of evacuation in a bushfire context, and triggers for decision-making. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1799 | 14 - Incident Mgt Teams | That the South Australian Country Fire Service establish preplanned Level 2 Incident Management Teams in each Region for deployment to Level 2 incidents. |
REC153-1791 | 14 - Incident Mgt Teams | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service consider the creation of a position within an Incident Management Team of a Landowner Liaison Officer the duties and responsibilities of whom is to establish contact with and liaise with the owner and/or occupiers of rural land on which a fire is situated. |
REC153-1806 | 40 - Equipment and consumables | That the Minister for Emergency Services and the Minister for Local Government cause local council plant and equipment that is suitable for use in bushfire fighting be fitted with radios connected to the Government Radio Network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3574 | 38 - Agency/Department Reporting | Formation of a subcommittee of the DHHS Tasmanian Medical Retrieval Services Committee to identify risk exposures, system problems and potential solutions. The subcommittee should review data, problem cases, system issues and generate a risk register. Meetings should occur at least quarterly. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3625 | 38 - Agency/Department Reporting | We recommend that NSW Health continue with its good work and establish a performance management framework with targets and indicators to assess progress in preparing for infectious disease emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3619 | 38 - Agency/Department Reporting | That the Department of Primary Industries should ensure the roles and capacities of Rural Lands Protection Boards and industry are effectively monitored to enable assessment of the effectiveness of animal health programs. |
REC128-3605 | 38 - Agency/Department Reporting | That the Department of Primary Industries make every effort to meet its targets for the TSE program and encourage public and private sector veterinarians across the State to submit samples. The Department should include reports on its performance against these targets in annual reports. |
REC128-3602 | 38 - Agency/Department Reporting | That the Department’s performance against tactical and strategic benchmarks be regularly reported in annual reports or animal and plant health emergency evaluation reports and compared to other jurisdictions where possible. |
REC128-3601 | 38 - Agency/Department Reporting | That, as a matter of principle, the NSW Government provide public reports on the lessons learned from emergency exercises which it manages or in which it participates. If necessary, such reports should exclude material which might jeopardise security. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3723 | 38 - Agency/Department Reporting | All ATSB accident investigation reports should be made public. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3722 | 38 - Agency/Department Reporting | The ATSB should deliver any report of any such rail accident which it investigates to the Board of any rail organisation involved in the accident, ITSRR and the Minister for Transport Services. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3776 | 38 - Agency/Department Reporting | The Minister for Transport Services should retain, independently of ITSRR, safety auditors to provide a report to the Minister confirming or qualifying the contents of each such ITSRR quarterly report. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3712 | 38 - Agency/Department Reporting | RailCorp and ITSRR should co-operate with national programs for the collection, collation, trend analysis and dissemination of safety critical information. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3775 | 38 - Agency/Department Reporting | The Minister for Transport Services must table in Parliament, each such quarterly report by ITSRR. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3697 | 38 - Agency/Department Reporting | All train drivers’ defects reports should be entered by RailCorp into a computerised record and tracked to finalisation. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3774 | 38 - Agency/Department Reporting | The ITSRR must provide a quarterly report to the Minister for Transport Services on the progress made by RailCorp in implementing these recommendations, including: |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3729 | 38 - Agency/Department Reporting | All reports of the Chief Investigator of OTSI should be delivered, upon completion and without being reviewed, to ITSRR and the Minister for Transport Services. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3648 | 38 - Agency/Department Reporting | It is recommended that providers supply data to the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3973 | 40 - Equipment and consumables | To arrange for uniform water facilities, where possible, by having large taps attached to elevated tanks, suitable approaches made to dams for filling carts, and convienient gates to approach same. |
REC013_3972 | 40 - Equipment and consumables | To recommend to shire councils the purchase of fire carts and necessary equipment for fire fighting. |
Rec-ID | Code | Recommendation |
---|---|---|