Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2481 | 22 - Role of local Gvt | Greater clarity about responsibilities for recovery at the community, local, and district levels should be considered in any future review of the Disaster Management Act (2003). |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1262 | 13 - Mapping and data quality | That the Flood Warning Consultative Committee considers the merits of delineating the Ouse River as a separate catchment from the Derwent River Basin. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1254 | 13 - Mapping and data quality | That Government: |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
REC297-1253 | 13 - Mapping and data quality | That agencies undertaking flood studies adopt a standardised approach, based on Australia Handbook 7, maintain public ownership of underlying data sets to support future modelling, and ensure open access to these studies. |
REC297-1252 | 13 - Mapping and data quality | That SES uploads current flood studies and plans to the Common Operating Platform as a flood plan layer and that councils, subject to resolving licence restrictions, arrange to have appropriate access. |
REC297-1265 | 13 - Mapping and data quality | That BoM and the Flood Warning Consultative Committee, in consultation with gauge owners, review flood gauges and develop a program to update data used to support hydrologic modelling. This should include reviewing gauge maintenance before and after floods. |
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1263 | 13 - Mapping and data quality | Subject to funding, that the Flood Warning Consultative Committee investigates the hydrological matters and advice received during this Review and detailed in this Report in Sections 4.1.9 and 4.1.11. |
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
Rec-ID | Code | Recommendation |
---|---|---|
REC294-1364 | 24 - Govt responsibility | The Chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services recommend implementing the Mackay District Improvement Strategy (refer to page 53 of the inquiry). |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2067 | 24 - Govt responsibility | Improve integration of health information systems. |
REC286-1473 | 13 - Mapping and data quality | Develop a statewide flood hazard map for use within the Tasmanian Planning System. |
REC286-2097 | 13 - Mapping and data quality | Extend current tsunami maritime hazard modelling project to deliver coastal inundation modelling. |
REC286-2063 | 24 - Govt responsibility | Review Tas Govt interoperability arrangements. |
REC286-1459 | 13 - Mapping and data quality | Improve beach morphology mapping to understand coastal inundation, including post-event surveys. |
REC286-2094 | 13 - Mapping and data quality | Deliver updated inundation mapping. |
REC286-1436 | 4 - Fire season preparation | Continue the development and implementation of community level Bushfire Mitigation Plans. |
REC286-2059 | 24 - Govt responsibility | Enhance business continuity planning by the Tasmanian Health Service. |
REC286-2052 | 22 - Role of local Gvt | Undertake local level emergency management planning for areas at risk of debris flow. |
REC286-1458 | 13 - Mapping and data quality | Make coastal mapping available to public. |
REC286-2058 | 24 - Govt responsibility | Clarify the relationship between the DHHS and THS in the establishment of flu services. |
REC286-2043 | 22 - Role of local Gvt | Assessment of council’s capacity to manage land effectively. |
REC286-2069 | 24 - Govt responsibility | Implement a database management approach for notifiable disease record systems. |
REC286-2033 | 24 - Govt responsibility | Incorporate heatwave surge response planning into business continuity planning. |
REC286-2041 | 22 - Role of local Gvt | Development mechanisms to support small councils to manage treatment across the PPRR spectrum (across all hazards). |
REC286-2068 | 24 - Govt responsibility | Develop a disaster client record system. |
REC286-2019 | 24 - Govt responsibility | Assess water supply resilience in the case of an interruption. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1526 | 13 - Mapping and data quality | In accordance with recommendations of the BMT WBM report, the Banana Shire Council, SunWater, and the Bureau of Meteorology, under the stewardship of the Department of Natural Resources and Mines, jointly identify the requirements for a suitable gauge network for the Callide Valley to allow meaningful and timely flood warnings. The review should identify key stakeholders, examine potential funding sources and include a cost benefit analysis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1429 | 2 - Emergency powers | A dynamic online list of positions and contact details is published for those able to authorise Emergency Alert, and made accessible to local government. |
REC268-1423 | 22 - Role of local Gvt | The State Disaster Coordination Centre Notification Matrix is reviewed to ensure local governments are notified of any event affecting, or likely to affect, their local government area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1567 | 24 - Govt responsibility | State and territory governments should: |
REC256-1566 | 24 - Govt responsibility | State and territory governments should prioritise and accelerate implementation of the Enhancing Disaster Resilience in the Built Environment Roadmap, including reviewing the regulatory components of vendor disclosure statements. The Land Use Planning and Building Codes Taskforce should be tasked to identify and consider options for regular, low-cost dissemination of hazard information to households by governments and insurers. |
REC256-1561 | 24 - Govt responsibility | State and territory governments should be required to report on the following accountability requirements: |
REC256-1565 | 13 - Mapping and data quality | Governments should task the Australia–New Zealand Emergency Management Committee with leading the development of guidelines for the collection and dissemination of natural hazard mapping, modelling and metadata. Guidelines should be developed for all hazards that need to be modelled and mapped at the local/regional level and where consistency across regions is desirable. |
REC256-1575 | 24 - Govt responsibility | State and territory governments should develop benchmark prices for the reconstruction of essential public assets and submit these to the Australian Government for approval within one year. In developing these prices, they should consult with local governments and relevant experts, and draw on asset management plans. The prices should be reviewed and updated over time. |
REC256-1563 | 13 - Mapping and data quality | Governments at all levels should make new and currently held natural hazard data publicly available in accordance with open public sector information principles. When collecting new natural hazard data or undertaking modelling, all levels of government should: |
REC256-1571 | 24 - Govt responsibility | State and territory taxes and levies on general insurance should be phased out and replaced with less distortionary taxes. |
REC256-1568 | 24 - Govt responsibility | State governments, where they have not already done so, should provide local governments with statutory protection from liability for releasing natural hazard information and making changes to local planning schemes where such actions have been taken ‘in good faith’ and in accordance with state planning policy and legislation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2598 | 24 - Govt responsibility | That government considers the establishment of a separate unit to implement and operate a Whole of Government network if existing stakeholders fail to make significant progress toward an agreed Whole of Government solution. |
REC245-2596 | 24 - Govt responsibility | That the Whole of Government project’s objectives should include meeting entity requirements and the consultant be asked to reevaluate the revised set of objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
REC244-2606 | 22 - Role of local Gvt | The Act be amended to require the mandatory appointment of Authorised Officers by each rural council or council that has within its area a Designated Urban Bushfire Risk Area(s) with an option for the CFS Chief Officer to exempt council from this requirement (similar to Section 105B). |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0836 | 24 - Govt responsibility | That the Government explore as a matter of priority the transitioning to St John Ambulance SA Ltd providing non-emergency ambulance carriage services in South Australia, and be appropriately funded for doing so. |
REC243-0847 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2649 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
REC242-2646 | 24 - Govt responsibility | That the State Government give high priority to liaising with interstate and Federal processes, and offer to take a lead, on changing the climatic and fire rating arrangements to ensure these match the conditions that can create dangerous bushfire conditions at short notice. |
REC242-2639 | 24 - Govt responsibility | That the Government’s Workers Rehabilitation and Compensation (SAMFS Firefighters) Amendment Bill be amended to include Country Fire Service firefighters alongside Metropolitan Fire Service firefighters. |
REC242-2638 | 24 - Govt responsibility | That the Government explore as a matter of priority the transitioning to St John Ambulance SA Ltd providing non-emergency ambulance carriage services in South Australia, and be appropriately funded for doing so. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2651 | 13 - Mapping and data quality | That the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomesThat the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2721 | 24 - Govt responsibility | That the Chief Executive Officer Portfolio Business collaborate with the two portfolio Commissioners to: |
REC239-2662 | 24 - Govt responsibility | That responsibility for prisoner transport and non-managerial roles within the larger watch-houses is transferred to Queensland Corrective Service. |
REC239-2687 | 24 - Govt responsibility | That funding, staffing and responsibility associated with administration of the NDRP be transferred from Emergency Management Queensland to the Department of Local Government, Community Recovery and Resilience. |
REC239-2712 | 24 - Govt responsibility | That Emergency Management Queensland be integrated with the current Queensland Fire and Rescue to become the Department of Fire and Emergency Services. |
REC239-2661 | 24 - Govt responsibility | That Queensland Corrective Service remains a separate program within the Department of Justice and Attorney-General so that while opportunities for improved services and efficacy can be realised, there is a clear separation from the youth justice services. |
REC239-2782 | 24 - Govt responsibility | That transparency of the Ministerial direction be achieved through publishing and monitoring for effectiveness. |
REC239-2686 | 24 - Govt responsibility | That primacy of control should rest with the State Disaster Coordinator. This position should, by default, be the Deputy Commissioner, Regional Operations, Queensland Police Service. |
REC239-2708 | 24 - Govt responsibility | That the role of the Inspector General Emergency Management not extend to conducting reviews on behalf of agencies and that the role consider the effectiveness of all agencies and how their work contributes to a whole of Government response. |
REC239-2660 | 24 - Govt responsibility | That Queensland Corrective Services be transferred to the Department of Justice and Attorney-General by a machinery-of-Government change as soon as is practicable. |
REC239-2759 | 24 - Govt responsibility | That the new Chief Executive Officer Portfolio Business be accountable for delivering the reformed Communications Centre arrangement by the 2017–18 financial year in time for the Commonwealth Games of 2018. |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2685 | 24 - Govt responsibility | That primacy of control for disaster operations remains with the Queensland Police Service and be reinforced. |
REC239-2701 | 24 - Govt responsibility | That the Inspector General Emergency Management provide continuing advice to Government on the level of interoperability in disaster management arrangements, as well as the level of interoperability being achieved within the new portfolio. |
REC239-2657 | 24 - Govt responsibility | That negotiation takes place between Queensland Health and the Queensland Ambulance Service to determine the broad governance requirements of any such arrangements. |
REC239-2749 | 24 - Govt responsibility | That the Prostitution Licensing Authority be moved to the Department of Justice and Attorney General Office of Fair Trading. |
REC239-2679 | 24 - Govt responsibility | To remove the Queensland Ambulance Service and Queensland Corrective Services from the Department of Community Safety—we recommend that it be renamed the Department of Fire and Emergency Services and be led by a Commissioner. |
REC239-2710 | 13 - Mapping and data quality | That all agencies participating in these activities should, as far as legally possible, share data sets whether or not the relevance is immediately obvious. |
REC239-2700 | 24 - Govt responsibility | That the position of Inspector General Emergency Management (in addition to some of the responsibilities of the chief executive officer under the current Disaster Management Act 2003) will: |
REC239-2655 | 24 - Govt responsibility | That the Queensland Ambulance Service is transferred to Queensland Health by a machinery-of-Government change as soon as is practicable and that the Commissioner report directly to the Director General Queensland Health. |
REC239-2732 | 24 - Govt responsibility | There be a formation of an Office of Portfolio Business, providing support and governance across a range of corporate functions, which are essential to the delivery of frontline services. The Review team considers that the functions of the Operations Business and Strategy Directorate should become part of that Office and that any exception should be carefully considered by those charged with implementation of approved recommendations. |
REC239-2678 | 24 - Govt responsibility | That probation and parole should continue to work together with the Queensland Police Service to reduce the risk of reoffending and reduce crime. |
REC239-2699 | 24 - Govt responsibility | That the Minister establish a public sector office to be headed by an Inspector General of Emergency Management. The Inspector General of Emergency Management will be responsible for most of the functions listed under part 16A of the current Disaster Management Act 2003. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2845 | 24 - Govt responsibility | The committee recommends that the Commonwealth government works with state and territory governments to continue to implement the recommendations of the Productivity Commission report, where possible, to improve coordination in relation to climate change adaptation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1855 | 22 - Role of local Gvt | Local government authorities incorporate into their Local Emergency Management Plans their procedures for dealing with any trauma experienced by bushfire brigade volunteers, having regard to best practice in managing trauma. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1825 | 22 - Role of local Gvt | When developing flood mitigation options in lowland areas, local governments should give consideration to the use of temporary levees as an alternative or addition to permanent structures. To maximise the use of these structures and limit flood damage, and aid affordability, consideration should be given by local governments to the sharing of temporary levees among different townships and different council areas. |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1819 | 22 - Role of local Gvt | In consultation with local communities, local councils will develop flood response plans as subplans to their current Municipal Emergency Management Plans. As part of the flood risk assessment process, these plans will be informed by the best available flood mapping and modelling, and will identify agreed activities to be undertaken during floods including, where appropriate, the construction of temporary levees. The condition of levees will be incorporated into such plans to enable improved emergency response. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2871 | 22 - Role of local Gvt | Efficient and effective supporting tools and processes: high-quality local/municipal planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0683 | 13 - Mapping and data quality | All councils should, resources allowing, map the overland flow paths of their urban areas. |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0665 | 13 - Mapping and data quality | Councils should make their flood and overland flow maps and models available to applicants for development approvals, and to consultants engaged by applicants. |
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0664 | 13 - Mapping and data quality | Councils should, resources allowing, maintain flood maps and overland flow path maps for use in development assessment. For urban areas these maps should be based on hydraulic modelling; the model should be designed to allow it to be easily updated as new information (such as information about further development) becomes available. |
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0755 | 13 - Mapping and data quality | CS Energy should supplement physical monitoring of Splityard Creek Dam with visual monitoring by installing surveillance cameras or similar devices. |
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0746 | 13 - Mapping and data quality | Seqwater should consider engaging a technical writer to develop completely new manuals after the operational strategies for Wivenhoe, Somerset and North Pine dams are set by the Queensland Government. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2885 | 13 - Mapping and data quality | Increased automation and outsourcing of observations |
Rec-ID | Code | Recommendation |
---|---|---|
REC206-1888 | 24 - Govt responsibility | The Committee recommends that the Australian Government empower the Australian Securities and Investments Commission to regulate claims handling and settlement of financial service providers. This can be achieved by the Treasurer introducing legislation by 1 July 2012 to give effect to the measures contained in Schedule 1, Part 1 of the lapsed Insurance Contracts Amendment Bill 2010, so that breaches of the duty of utmost good faith in relation to claims handling constitute a breach of the Insurance Contracts Act. |
REC206-1885 | 24 - Govt responsibility | The Committee recommends that the Australian Government introduce legislative changes required to remove the exemption for general insurers to unfair contract terms laws, and ensure its enactment by the end of 2012. |
REC206-1884 | 24 - Govt responsibility | The Committee recommends that the Australian Parliament pass the Insurance Contracts Amendment Bill 2011 and ensure its enactment by 1 July 2012. The Committee further recommends that the standard definition of ‘flood’ be included in the definition of Standard Cover in the Insurance Contracts Regulations 1985. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1898 | 24 - Govt responsibility | To help clarify roles and responsibilities of local government for climate change adaptation, the state and Northern Territory governments should publish and maintain a comprehensive list of laws that delegate regulatory roles to local governments. This would assist both state and local governments to assess whether local governments have the capacity to discharge their roles effectively. |
REC205-1896 | 24 - Govt responsibility | Australian governments should implement policies that help the community deal with the current climate by improving the flexibility of the economy. This would also build adaptive capacity to deal with future climate change. This includes reforms to: |
REC205-1904 | 24 - Govt responsibility | State and territory taxes and levies on general insurance constitute a barrier to effective adaptation to climate change. State and territory governments should phase out these taxes and replace them with less distortionary taxes. |
REC205-1899 | 24 - Govt responsibility | Local governments’ uncertainty about their legal liability is a barrier to effective climate change adaptation. State governments should clarify the legal liability of councils with respect to climate change adaptation matters and the processes required to manage that liability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0420 | 13 - Mapping and data quality | the state establish standards for flood mapping to ensure they are kept contemporary and meet the purposes of landuse risk planning and emergency response. In doing so, maps should extend where appropriate to include Probable Maximum Flood, over a range of Annual Exceedence Probability levels and be explicitly linked to a stream gauge. |
REC199-0444 | 2 - Emergency powers | the state, as a matter of urgency, develop a multi-agency Incident Control Team capability to be readily available for statewide deployment to establish incident control or to relieve functioning control structures. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0417 | 13 - Mapping and data quality | the state ensure that regional and local flood plans incorporate all available flood mapping and intelligence, including assessments of levees and flood consequence information. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0408 | 13 - Mapping and data quality | the state, in consultation with Bureau of Meteorology and Melbourne Water, take the necessary action to ensure that all flood warnings issued are linked to the geographical location of the gauge the data was derived from. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0429 | 13 - Mapping and data quality | the state take into account any outcomes from the Commonwealth Government’s flood mapping reviews in the continual development of the Victorian flood database and to incorporate into the database flood data currently held by Melbourne Water. |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1928 | 24 - Govt responsibility | That the Queensland Reconstruction Authority finalise the value for money policies and procedures, particularly those that take into account the role and responsibilities of the external service providers. |
REC190-1927 | 24 - Govt responsibility | That the Queensland Reconstruction Authority agree on and finalise the work plan and attach it as a Schedule to the Agreement as required in section 15 of the Agreement. |
REC190-1926 | 24 - Govt responsibility | That the Queensland Reconstruction Authority clarify and communicate the roles of the Lines of Reconstruction sub-committees to the Chairs of each committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC180-2969 | 22 - Role of local Gvt | Councils should strengthen governance arrangements for business continuity by: |
REC180-2973 | 22 - Role of local Gvt | Local Government Victoria should, further to its work on strengthening the oversight role of audit committees, assist councils to develop good practice approaches to implementing, overseeing and continuously improving business continuity management. |
REC180-2972 | 22 - Role of local Gvt | Councils should strengthen their continuous improvement frameworks by: |
REC180-2971 | 22 - Role of local Gvt | Councils should improve the structure, format and content of their business continuity plans to provide greater clarity on roles and responsibilities for emergencies, more specificity on continuity and recovery responses, and better integration with other council disaster recovery and emergency plans. |
REC180-2970 | 22 - Role of local Gvt | Councils should improve assessments of business continuity risks by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2983 | 24 - Govt responsibility | The Department of Human Services should work with the State Emergency Recovery Planning Committee, regions, and other partners to facilitate understanding and ownership of roles and responsibilities for common recovery services. |
REC179-2980 | 24 - Govt responsibility | The Department of Human Services should work with regions and partner agencies at the state level to create consistent, streamlined impact assessment processes and systems. |
REC179-2979 | 24 - Govt responsibility | The Department of Human Services should communicate strategic priorities to achieve state and regional level alignment in building recovery capacity and capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0054 | 22 - Role of local Gvt | SEMC and EM WA should: work with local government to ensure up-to-date, comprehensive local arrangements are in place |
REC170-0050 | 24 - Govt responsibility | SEMC and EM WA should: assess the state’s level of preparedness at least annually, identifying gaps and significant risks |
REC170-0049 | 24 - Govt responsibility | SEMC and EM WA should: formally and regularly assess which hazards the state should prepare for |
REC170-0055 | 22 - Role of local Gvt | SEMC and EM WA should: monitor and take action to ensure local plans are in place and cover areas where the hazard could occur |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0086 | 2 - Emergency powers | Suggested escalation trigger points be discussed with District Disaster Coordinators and Local Disaster Coordinators, and if considered practical and useful, be incorporated in Local, District and State Disaster Management Plans. |
REC165-0098 | 24 - Govt responsibility | The SDMG take into account key improvement initiatives and change processes suggested when deciding on an effective implementation strategy for agreed recommendations. |
REC165-0081 | 2 - Emergency powers | District and State levels utilise the current Act to make pre-emptive declarations of a disaster event (likely disasters) so as to be proactive in leading and controlling disaster events. All levels of the system should immediately notify other levels if they activate the Disaster Management arrangements. The Public Safety Preservation Act 1986 be amended to provide powers for Police Officers to provide an immediate response in the event of a rapid onset disaster event such as a landslide. |
REC165-0097 | 24 - Govt responsibility | Revised governance arrangements be implemented involving Disaster Management Groups at the three levels supported by EMQ as outlined in this report to achieve continuous improvement in the Disaster Management arrangements in the State. A new provision in Section 5 emphasise the discretion available to all involved in the Disaster Management system to take action to prevent impending loss of life even if contrary to the agreed arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3035 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources liaise with Ministers with environmental and planning responsibilities, and if necessary Council of Australian Governments, to ensure that environmental requirements for oil and gas projects are not imposed subsequent to safety assessments and do not increase the risk of major accident events. |
REC161-3028 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources continue to support a duty of care safety case regime for best practice offshore petroleum industry regulation augmented to include regulation of integrity. Since the safety case is at the centre of the duty of care co-regulatory regime, we consider that the requirement for the implementation of the safety case at facilities involved in the exploitation of petroleum resources should be provided for within the Offshore Petroleum and Greenhouse Gas Storage Act 2006 itself. |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3095 | 24 - Govt responsibility | SAFECOM re-evaluate and determine a more meaningful definition of fire districts. |
REC151-3071 | 24 - Govt responsibility | The comprehensive prevention, preparedness, response and recovery (PPRR) approach to the management of bushfires as recommended by the Ministerial Review of Bushfire Management in South Australia is supported: its implementation should consider issues raised by councils and should also be considerate of the recommendations of the Wangary Coronial Inquest. |
REC151-3107 | 2 - Emergency powers | Immunity be prescribed for persons (including volunteers) using force in the exercise of a power or function under the FES Act or carrying out any direction or requirement given or imposed at the scene of a fire or other emergency. |
REC151-3079 | 2 - Emergency powers | Crown Law opinion be obtained to determine whether the FES Act gives the Minister power to direct and control individual Chief Officers and if that provision does not exist then the FES Act be amended to include that power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3218 | 13 - Mapping and data quality | The Committee recommends that the Australian Government, through the Australian Bureau of Statistics, ensure that: |
REC145-3219 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3230 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3204 | 13 - Mapping and data quality | The Committee recommends that the Australian Government establish a National Coastal Zone Database to improve access to and consistency of information relevant to coastal zone adaptation. The National Coastal Zone Database should be an online portal that allows ready access to: |
REC145-3217 | 24 - Govt responsibility | The Committee recommends that the Australian Government, through the Council of Australian Governments process, examine the establishment of a system of national coastal zone environmental accounts, employing the model developed by the South East Queensland Healthy Waterways Partnership. |
REC145-3226 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3201 | 13 - Mapping and data quality | The Committee recommends that the Department of Climate Change share all data collected through vulnerability assessments undertaken as part of the Australian Government Local Adaptation Pathways Program on the proposed National Coastal Zone Database (see also recommendation 42). |
REC145-3224 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3223 | 24 - Govt responsibility | The Committee recommends that the Australian Government urgently commission a detailed climate change vulnerability assessment for Kakadu National Park, in consultation with the park’s traditional owners and other stakeholders and drawing on the results of the ‘first pass’ National Coastal Vulnerability Assessment of the park. This assessment should specifically focus on the vulnerability of Kakadu’s freshwater wetland systems to saltwater intrusion. A key outcome of the assessment should be the development of a Climate Change Action Plan for Kakadu National Park, with coordinated input from the Australian Government and Northern Territory Government, Indigenous land owners, researchers and other stakeholders. |
REC145-3239 | 24 - Govt responsibility | The Committee recommends that the Australian Government establish a National Coastal Advisory Council to: |
REC145-3231 | 22 - Role of local Gvt | The Committee recommends that the Australian Government request that the Centre for Excellence for Local Government ensure a particular focus on capacity building for coastal local councils. Capacity building should focus on addressing issues relating to: |
REC145-3235 | 13 - Mapping and data quality | The Committee recommends that the National Coastal Zone Database be expanded over time to include information on environmental data and management and planning information relevant to the coastal zone. |
REC145-3221 | 24 - Govt responsibility | The Committee recommends that the Australian Government, in considering its response to the Independent Review of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act), take into account concerns about the EPBC Act and coastal zone management raised as part of this inquiry—in particular, the need to address the cumulative impacts of coastal development. This could be achieved by numerous means, including: |
REC145-3237 | 24 - Govt responsibility | The Committee recommends that the Australian Government, in cooperation with state, territory and local governments, and in consultation with coastal stakeholders, develop an Intergovernmental Agreement on the Coastal Zone to be endorsed by the Council of Australian Governments. The intergovernmental agreement should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3388 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government re-investigate the suitability of the Fairbairn site as a proposed centralised accommodation facility for emergency services. |
REC144-3386 | 24 - Govt responsibility | The Committee considers that the ACT Government should table in the ACT Legislative Assembly the cost-benefit analysis and business plan for Fairbairn as a central site for emergency services in the ACT. |
REC144-3382 | 24 - Govt responsibility | The Committee recommends that responsibility for oversighting the progress of the implementation of agreed recommendations of the Coroner be undertaken by a truly independent body and not by the Bushfire Council. |
REC144-3390 | 24 - Govt responsibility | If the ACT Government decides to proceed with the site as the emergency services headquarters, that it accord a high priority to the finalisation of the site preparations for the ESA at Fairbairn as a matter of urgency. |
REC144-3389 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government make a public announcement about the future accommodation plans for the Emergency Services Agency and its component parts so that both the ESA and the ACT public are informed about current proposals and timeframes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3575 | 24 - Govt responsibility | The preferred model for the Tasmanian Medical Retrieval Services is to have TMRS and NETS staff based in RHH. The fixed wing would remain based in Launceston (for the present) with the helicopter to remain based in Hobart. |
REC140-3573 | 13 - Mapping and data quality | Databases with a common minimum data set complete with incident monitoring should be established for TAS Air Ambulance, TMRS and NETS missions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2109 | 24 - Govt responsibility | The Working Group recommends that participants in the exercises designed to test continuity of executive government plans and procedures should be the office holders themselves. |
REC116-2108 | 24 - Govt responsibility | The Working Group recommends that all States/Territories and the Australian Government should regularly (annually) test their continuity of executive government plans and contingencies. |
REC116-2126 | 24 - Govt responsibility | The Working Group recommends the Australian Emergency Management Committee note that: |
REC116-2105 | 24 - Govt responsibility | The Working Group recommends that the adequacy of existing national mortuary capability to meet the likely demands of a catastrophic disaster be assessed by State/Territory Coroners. This assessment should also consider the need for a mobile mortuary capability and involve discussions with the Australian Federal Police. |
REC116-2125 | 24 - Govt responsibility | The Working group recommends that the Australian Government take a leadership role with regard to addressing the national capability issues identified within this review. Further, that the States/Territories recognise and accept the collaborative nature of developing national capability and commit through engagement and consultation to assisting the Australian Government in this task. |
REC116-2123 | 24 - Govt responsibility | The Working Group recommends that the Australian Government consider developing an overarching whole of government disaster plan that clearly articulates authority, roles and responsibilities of agencies, inter-departmental committees and key officials, to link the range of existing Australian Government disaster plans. |
REC116-2118 | 24 - Govt responsibility | The Working Group recommends that State/Territory Recovery Committees review their membership to ensure that it is reflective of community needs, including representation from the Insurance Disaster Response Organisation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3935 | 24 - Govt responsibility | To provide the strategic leadership and governance required to implement the Disaster Management Act 2003, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable governance framework for disaster management which includes the establishment of — |
REC111-3936 | 24 - Govt responsibility | To enhance the governance of the Queensland disaster management system, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services ensure that — |