Rec-ID | Code | Recommendation |
---|---|---|
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
REC325-4324 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the tasking protocols used to manage State Emergency Service (SES) tasks undertaken in the response phase of a disaster to enable more complete recording of details for all ‘jobs of opportunity’ (including the personal details of those assisted and/or rescued) to enable better coordination of tasks and reflect outcomes of activities by 1 November 2023. |
REC325-4325 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review and implement State Emergency Service (SES) protocol by 1 November 2023 outlining procedures to be undertaken to ensure persons uplifted from places of immediate danger or risk are transferred to a place of safety. |
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4334 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services develop and publish an operationally based quick reference guide that complements the training offered (as per Recommendation 5) by 1 November 2022. The guide will identify key and critical aspects of the Emergency Alert system in relation to the development, composition, request for and authorising of Emergency Alerts and will include a template and an example of ‘good’ messaging using concise, minimal language and Clear Explicit Translatable Language (CETL). |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2488 | 33 - Relief and recovery | The basic capacity needs of each functional recovery group and how this can be scaled up should be identified. Plans for functional recovery groups should reflect this in clear statements for every level of the system, for all relevant entities about their required function, role and responsibilities during recovery. |
REC310-2485 | 33 - Relief and recovery | Recovery plans at all levels should include transition arrangements. They should be implemented during recovery. The arrangements should: |
REC310-2484 | 33 - Relief and recovery | There remains a need to maximise the effect of all offers of assistance to recovering communities. This recommendation presents an opportunity to resolve any outstanding aspects of Recommendation 4 and Actions in Response from the Cyclone Debbie Review Action Plan: |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC294-1364 | 24 - Govt responsibility | The Chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services recommend implementing the Mackay District Improvement Strategy (refer to page 53 of the inquiry). |
Rec-ID | Code | Recommendation |
---|---|---|
REC293-1336 | 32 - Doctrine, standards, and reform | The chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services, implement the Mackay Disaster District capability improvement strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC289-1226 | 32 - Doctrine, standards, and reform | IGEM recommends that Emergency Management Victoria continue to lead the development and application of a comprehensive sector wide preparedness model for integration within and across emergency management arrangements in Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1404 | 15 - Inter-service cooperation | That the Department of Health & Human Services and the Department of Justice & Regulation, in consultation with their portfolio emergency service agencies that have response time measures, determine relevant targets for these. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1531 | 32 - Doctrine, standards, and reform | Banana Shire Council completes business continuity planning as a matter of priority, including documentation and testing of the plan. |
REC271-1526 | 13 - Mapping and data quality | In accordance with recommendations of the BMT WBM report, the Banana Shire Council, SunWater, and the Bureau of Meteorology, under the stewardship of the Department of Natural Resources and Mines, jointly identify the requirements for a suitable gauge network for the Callide Valley to allow meaningful and timely flood warnings. The review should identify key stakeholders, examine potential funding sources and include a cost benefit analysis. |
REC271-1525 | 6 - Insurance and legal liability | The Department of Energy and Water Supply, in conjunction with SunWater, seek clarification of the dam owners’ legal obligation to comply with Emergency Action Plans and, if required, investigate how a more flexible approach may be adopted. |
REC271-1522 | 26 - Research | Banana Shire Council investigate means to prioritise the commissioning of a fit-for-purpose flood study for high-risk areas across the Banana Shire to better inform flood risk management, including improved town planning. The outcomes of such a study should be available to the public and inform flood awareness campaigns, flood warnings, and building approvals. |
REC271-1521 | 26 - Research | The Department of Energy and Water Supply and SunWater, undertake the necessary studies to determine whether or not it is feasible to operate Callide Dam as a flood mitigation dam. Such studies should include matters in relation to, but not limited to: |
REC271-1532 | 32 - Doctrine, standards, and reform | The evacuation sub-plan component of the Local Disaster Managment Plan should be reviewed, including any identified triggers for activation. Ideally, the plan should be tested in a live, multi-agency exercise prior to next summer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC269-1167 | 32 - Doctrine, standards, and reform | That Queensland’s disaster management arrangements are reviewed to enhance integration. Specifically: · to address the disparity between functions and structure of local government and disaster groups · to integrate hazard specific agency planning at all levels of the arrangements (This may include legislative, policy and procedural considerations). |
REC269-1171 | 32 - Doctrine, standards, and reform | State agencies with disaster management roles and responsibilities assess their performance by including a disaster management performance measure in chief executive officers’ performance agreements. This measure should reinforce an obligation for agencies to participate in the arrangements at all levels. |
REC269-1170 | 32 - Doctrine, standards, and reform | Responsibilities of functional lead agencies and hazard-specific primary agencies are clearly articulated in state level doctrine, including the Queensland State Disaster Management Plan. |
REC269-1169 | 32 - Doctrine, standards, and reform | An integrated risk-based approach to disaster management planning for Queensland is developed that is consistent with the Standard for Disaster Management in Queensland and applicable at all levels of the arrangements. |
REC269-1168 | 32 - Doctrine, standards, and reform | The Local and District Disaster Management Guidelines are reviewed to align with the Standard for Disaster Management in Queensland. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1430 | 26 - Research | Formal research is commissioned or meta-analysis is undertaken to provide a better understanding of the effectiveness of warnings and other relevant message testing. The outcomes are disseminated to all disaster management entities and learnings used to inform practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1095 | 15 - Inter-service cooperation | CFA and VICSES should: explore further opportunities to collaborate with each other. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1488 | 32 - Doctrine, standards, and reform | That the Emergency Services Telecommunications Authority, assisted by Ambulance Victoria, reviews the business rules to be applied by the Emergency Services Telecommunications Authority ambulance dispatchers in selecting appropriate resources for dispatching to events, taking account of meal-break procedures. |
REC262-1482 | 15 - Inter-service cooperation | That Emergency Management Victoria be responsible for facilitating the interoperability of all organisations involved in emergency response, including the Emergency Services Telecommunications Authority and Ambulance Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2654 | 26 - Research | That the Department of Health determines the underlying causes for the rapid growth in demand for Queensland Ambulance Service emergency responses and implements strategies to address these causes and reduce the cost per head of population to service this demand. |
REC240-2651 | 13 - Mapping and data quality | That the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomesThat the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2678 | 24 - Govt responsibility | That probation and parole should continue to work together with the Queensland Police Service to reduce the risk of reoffending and reduce crime. |
REC239-2705 | 32 - Doctrine, standards, and reform | That the Inspector General Emergency Management assess the effectiveness of plans and policy in relation to SES deployment and command and control. |
REC239-2762 | 15 - Inter-service cooperation | That the Chief Executive Officer Portfolio Business in consultation with the Police Commissioner and the Commissioner Fire & Emergency Services should provide the direction for future information and communication technology strategies and acquisitions. |
REC239-2693 | 32 - Doctrine, standards, and reform | That the presence of police in State Disaster Coordination Centre response teams is mandated and formalised through documented standard operating procedures. |
REC239-2717 | 32 - Doctrine, standards, and reform | That the ‘Functions of Chief Executive’ under the Disaster Management Act 2003 are amended to remove those functions that will become the role of the proposed Inspector General of Emergency Management. |
REC239-2662 | 24 - Govt responsibility | That responsibility for prisoner transport and non-managerial roles within the larger watch-houses is transferred to Queensland Corrective Service. |
REC239-2699 | 24 - Govt responsibility | That the Minister establish a public sector office to be headed by an Inspector General of Emergency Management. The Inspector General of Emergency Management will be responsible for most of the functions listed under part 16A of the current Disaster Management Act 2003. |
REC239-2735 | 32 - Doctrine, standards, and reform | That the new Department of Fire and Emergency Services develop a common doctrine to protect people from fire and emergencies. |
REC239-2676 | 32 - Doctrine, standards, and reform | That any changed arrangements to the operations of Queensland Corrective Service ensure anti-corruption, prisoner management, and accountability processes are defined and established. |
REC239-2704 | 32 - Doctrine, standards, and reform | That the current SES memoranda of agreement between the Department of Community Safety and local governments be revised to include a clear statement as to the command and control arrangements between State and respective local governments. These arrangements should also be reflected in the local disaster management plans. |
REC239-2761 | 15 - Inter-service cooperation | That systems development in the Queensland Police Service capitalises on the advances made by the Queensland Fire and Rescue Service in recent years. |
REC239-2687 | 24 - Govt responsibility | That funding, staffing and responsibility associated with administration of the NDRP be transferred from Emergency Management Queensland to the Department of Local Government, Community Recovery and Resilience. |
REC239-2712 | 24 - Govt responsibility | That Emergency Management Queensland be integrated with the current Queensland Fire and Rescue to become the Department of Fire and Emergency Services. |
REC239-2782 | 24 - Govt responsibility | That transparency of the Ministerial direction be achieved through publishing and monitoring for effectiveness. |
REC239-2661 | 24 - Govt responsibility | That Queensland Corrective Service remains a separate program within the Department of Justice and Attorney-General so that while opportunities for improved services and efficacy can be realised, there is a clear separation from the youth justice services. |
REC239-2697 | 32 - Doctrine, standards, and reform | That the Queensland Police Service Disaster Management Unit work with emergency management staff in the new portfolio to produce the State disaster management plan. |
REC239-2732 | 24 - Govt responsibility | There be a formation of an Office of Portfolio Business, providing support and governance across a range of corporate functions, which are essential to the delivery of frontline services. The Review team considers that the functions of the Operations Business and Strategy Directorate should become part of that Office and that any exception should be carefully considered by those charged with implementation of approved recommendations. |
REC239-2668 | 32 - Doctrine, standards, and reform | That as part of reviewing its legislation, Queensland Corrective Service should ensure that amendments be made to ensure a stronger onus is placed upon a more efficient process to receive prisoners with a view to reducing the time spent in police watch houses. |
REC239-2703 | 15 - Inter-service cooperation | That the protocols developed by the Queensland Police Service and SES for operations define the respective roles and responsibilities as well as recognise the varying capabilities of SES units across the State. |
REC239-2759 | 24 - Govt responsibility | That the new Chief Executive Officer Portfolio Business be accountable for delivering the reformed Communications Centre arrangement by the 2017–18 financial year in time for the Commonwealth Games of 2018. |
REC239-2686 | 24 - Govt responsibility | That primacy of control should rest with the State Disaster Coordinator. This position should, by default, be the Deputy Commissioner, Regional Operations, Queensland Police Service. |
REC239-2710 | 13 - Mapping and data quality | That all agencies participating in these activities should, as far as legally possible, share data sets whether or not the relevance is immediately obvious. |
REC239-2781 | 34 - Local knowledge | That the current provisions enabling there to be a Ministerial Direction be maintained and actioned as the Minister sees fit. |
REC239-2660 | 24 - Govt responsibility | That Queensland Corrective Services be transferred to the Department of Justice and Attorney-General by a machinery-of-Government change as soon as is practicable. |
REC239-2696 | 32 - Doctrine, standards, and reform | That the Queensland Police Service Disaster Management Unit be given responsibility for production of the State disaster management plan for the State Disaster Management Group’s approval. |
REC239-2728 | 32 - Doctrine, standards, and reform | That the Fire and Rescue Act 1990 be amended so that Commissioner’s position is not limited to a “person with professional experience in fire prevention and fire fighting”. |
REC239-2667 | 15 - Inter-service cooperation | That Queensland Corrective Service, the Queensland Police Service and Queensland Health should work together to develop a position that enables prisoners to have timely access to their prescribed medication despite travel between facilities and without the need for costly re-prescription. |
REC239-2702 | 32 - Doctrine, standards, and reform | That the Queensland Police Service and SES develop clear operational protocols to ensure that SES assistance is not exploited. |
REC239-2756 | 32 - Doctrine, standards, and reform | That the Chief Executive Officer Portfolio Business consider ‘big data’ problems and solutions in line with the outcome of the efficiency review into the Queensland Police Service and ensure alignment with whole of government solutions. |
REC239-2685 | 24 - Govt responsibility | That primacy of control for disaster operations remains with the Queensland Police Service and be reinforced. |
REC239-2709 | 17 - Assets and technology | That the information and communication technology solution being developed to provide situational awareness, decision support, event management and that logs critical decisions receives urgent attention to ensure timely completion. |
REC239-2778 | 17 - Assets and technology | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative ANPR models should form part of the design architecture considerations. |
REC239-2657 | 24 - Govt responsibility | That negotiation takes place between Queensland Health and the Queensland Ambulance Service to determine the broad governance requirements of any such arrangements. |
REC239-2695 | 32 - Doctrine, standards, and reform | That the Disaster Management Act 2003 be amended to: |
REC239-2721 | 24 - Govt responsibility | That the Chief Executive Officer Portfolio Business collaborate with the two portfolio Commissioners to: |
REC239-2666 | 32 - Doctrine, standards, and reform | That a system should be designed so that the prisoner and the prisoner’s prescribed drugs are treated as one and therefore travel together through the system for whatever purpose. |
REC239-2701 | 24 - Govt responsibility | That the Inspector General Emergency Management provide continuing advice to Government on the level of interoperability in disaster management arrangements, as well as the level of interoperability being achieved within the new portfolio. |
REC239-2755 | 32 - Doctrine, standards, and reform | That the Queensland Police Service bring this practice to the attention of the Privacy Commissioner and discuss a new service wide policy on the retention of data to ensure that their officers are not acting in breach of the law. |
REC239-2679 | 24 - Govt responsibility | To remove the Queensland Ambulance Service and Queensland Corrective Services from the Department of Community Safety—we recommend that it be renamed the Department of Fire and Emergency Services and be led by a Commissioner. |
REC239-2708 | 24 - Govt responsibility | That the role of the Inspector General Emergency Management not extend to conducting reviews on behalf of agencies and that the role consider the effectiveness of all agencies and how their work contributes to a whole of Government response. |
REC239-2775 | 17 - Assets and technology | That efforts by the courts, the Director of Public Prosecutions, the legal profession, Queensland Corrective Services and the Queensland Police Service to adopt technology for court processes should be supported through Government funding in so far as they create efficiencies, result in lower costs and produce better human rights outcomes. |
REC239-2655 | 24 - Govt responsibility | That the Queensland Ambulance Service is transferred to Queensland Health by a machinery-of-Government change as soon as is practicable and that the Commissioner report directly to the Director General Queensland Health. |
REC239-2694 | 15 - Inter-service cooperation | That Queensland enters into a similar arrangement with Bureau of Meteorology to have an experienced forecaster seconded to Kedron State Disaster Coordination Centre for at least the duration of fire and storm seasons. |
REC239-2718 | 32 - Doctrine, standards, and reform | That the Department of Fire and Emergency Services be created through the renaming and amendment to the existing Fire and Rescue Service Act 1990 including: |
REC239-2664 | 17 - Assets and technology | That Queensland Corrective Service should increase the use of technology as an alternative to court appearances and ensure the provision of appropriate number and level of facilities under its control. |
REC239-2700 | 24 - Govt responsibility | That the position of Inspector General Emergency Management (in addition to some of the responsibilities of the chief executive officer under the current Disaster Management Act 2003) will: |
REC239-2749 | 24 - Govt responsibility | That the Prostitution Licensing Authority be moved to the Department of Justice and Attorney General Office of Fair Trading. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1834 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop clear policy for the coordinated management of rural drainage, clarifying the legal framework, and identifying authorities with responsibility for the management and ongoing maintenance of formal schemes, and their development: |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
REC217-1838 | 32 - Doctrine, standards, and reform | That statements of obligations, issued under the Water Industry Act 1994 for water authorities, be amended to include a provision whereby managing authorities must: |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1830 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop a code of practice on the removal of vegetation around critical public assets, in consultation with councils, CMAs and asset managers. Regional Flood Strategies will support this code of practice as part of shared flood risk management planning. |
REC217-1837 | 32 - Doctrine, standards, and reform | The state government give consideration to enacting legislation to provide protection from legal liability for public authorities conducting works on priority levees in good faith, acting reasonably and responsibly in the public interest, and in accordance with standards agreed to under approved schemes. Public authorities should not be excluded from liability if they have acted negligently. |
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1829 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment should develop guidelines for streamlining the permitting system for works on waterways for incorporation in the revised Victoria Flood Management Strategy. An exemption process will be introduced, with particular application to identified reaches of rivers and streams that require ongoing vegetation management and maintenance: |
REC217-1836 | 26 - Research | Flood studies will be undertaken to determine the flood extent on the basis of a greater than 1 in 100 ARI, where appropriate: |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1820 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop guidelines for the management of levees in emergencies, during and after a flood event, which can be incorporated into local flood response plans. The department will also provide, as part of these guidelines, a set of criteria for assessing the ongoing viability of ad hoc levees post‐flood. The Emergency Management Act 1986 will be amended to support the implementation of these guidelines. A more effective means for councils to remove illegal levees will also be examined by the Department of Sustainability and Environment. |
REC217-1828 | 32 - Doctrine, standards, and reform | The revised Victoria Flood Management Strategy should clearly articulate the policy guidelines for the management of vegetation and debris in Victorian waterways, for the purposes of flood protection and mitigation, taking into account the localised potential flooding effects of in‐stream vegetation in townships. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0700 | 6 - Insurance and legal liability | Insurers should review their existing systems and processes and implement any improvements necessary to ensure that accurate and complete records of conversations with policy-holders are made. |
REC210-0717 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 to provide a definition of the term ‘emergency’ for the purposes of section 468 of that Act. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0683 | 13 - Mapping and data quality | All councils should, resources allowing, map the overland flow paths of their urban areas. |
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0760 | 32 - Doctrine, standards, and reform | CS Energy should amend its business procedure to remove any ambiguity as to the establishment of communications with Seqwater and to acknowledge the formal communications protocol regarding releases. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0747 | 6 - Insurance and legal liability | Seqwater should ensure a legal review of the Wivenhoe manual and the North Pine manual is completed before the manual is submitted for approval. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
REC210-0759 | 32 - Doctrine, standards, and reform | CS Energy should review its emergency action plan and business procedures to ensure they are wholly consistent and give appropriate consideration to flooding as a possible emergency event. |
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0746 | 13 - Mapping and data quality | Seqwater should consider engaging a technical writer to develop completely new manuals after the operational strategies for Wivenhoe, Somerset and North Pine dams are set by the Queensland Government. |
REC210-0770 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to oblige each owner of a referable dam to have an emergency action plan approved by the appropriate Queensland Government agency. Such plans should be reviewed periodically |
REC210-0665 | 13 - Mapping and data quality | Councils should make their flood and overland flow maps and models available to applicants for development approvals, and to consultants engaged by applicants. |
REC210-0703 | 6 - Insurance and legal liability | The Insurance Council of Australia should amend clause 3.4.3 of the General Insurance Code of Practice so that it requires insurers to inform policy-holders of their right to request a review of an insurer’s decision to refuse to provide access to information on which it relied in assessing claims. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0714 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 so that it allows for the relaxation of environmental authority conditions, by transitional environmental program or otherwise, as to discharge of water: • pre-emptively, in advance of rainfall or flooding events, or • for all mines in a catchment that is flooding. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
REC210-0664 | 13 - Mapping and data quality | Councils should, resources allowing, maintain flood maps and overland flow path maps for use in development assessment. For urban areas these maps should be based on hydraulic modelling; the model should be designed to allow it to be easily updated as new information (such as information about further development) becomes available. |
REC210-0702 | 6 - Insurance and legal liability | The Insurance Council of Australia should consider an amendment to Part 3 of the code which requires insurers to notify policy-holders of the information on which they relied in assessing claims. |
REC210-0719 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Environmental Protection Act 1994 so as to permit an emergency direction to be given orally where it is not practicable to provide the direction in writing, with provision for its subsequent confirmation in writing |
REC210-0750 | 32 - Doctrine, standards, and reform | The assessment of flood mitigation manuals should be completed by a person with appropriate expertise who has had no involvement in its development, at any stage, and who can be seen to be independent of all individuals who were so involved. |
REC210-0699 | 6 - Insurance and legal liability | When a policy-holder makes a claim, the insurer should ascertain the policy-holder’s preferred method of contact and ensure that it is used (with other modes of communication if necessary) to keep the policyholder informed about the progress of the claim. However, important decisions regarding the claim – for example, determinations about the outcome of the claim and settlement sums – should always be confirmed in writing. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0735 | 6 - Insurance and legal liability | The Crime and Misconduct Commission should investigate whether the conduct of Mr Tibaldi, Mr Ayre and Mr Malone relating to: • preparation of documents surrounding the January 2011 flood event, including the 17 January 2011 brief to the Minister, the 2 March 2011 flood event report, and statements provided to the Commission • oral testimony given to the Commission evidences offence/s against the Criminal Code, and/or official misconduct under the Crime and Misconduct Act 2001 committed by any, or all, of them. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0701 | 6 - Insurance and legal liability | Letters notifying policy-holders that their claims have been denied should, at a minimum, state the information upon which the insurer has relied in making the decision. These letters should also advise policy-holders that copies of the information will be made available upon request (in accordance with clause 3.4.3 of the General Insurance Code of Practice) and indicate how policy-holders can make a request. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0749 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Water Supply (Safety and Reliability) Act 2008 to designate the Minister as the person who must approve a flood mitigation manual. |
REC210-0686 | 6 - Insurance and legal liability | SunWater and the Central Highlands Regional Council should determine the issues of ownership and responsibility for maintenance of the LN1 drain system in Emerald. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0733 | 32 - Doctrine, standards, and reform | Emergency Management Queensland should pursue the execution of the ‘Local Arrangements’ with councils where a Memorandum of Agreement is in place. The contents of the arrangements should be reviewed and updated regularly |
REC210-0755 | 13 - Mapping and data quality | CS Energy should supplement physical monitoring of Splityard Creek Dam with visual monitoring by installing surveillance cameras or similar devices. |
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0712 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to clarify the purposes for which a transitional environmental program can be granted. In particular, if the government considers the transitional environmental program the appropriate regulatory mechanism to deal with the discharge of water from mines during flood, section 330 of the Environmental Protection Act 1994 should be clarified to make it clear that it extends to that use. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0456 | 32 - Doctrine, standards, and reform | the state: • ensure an ‘all hazards, all agencies’ approach to Incident Action Plan compilation is developed and implemented to enable the timely issue of functional Incident Action Plans. All agency incident action planning processes should be standardised to the fullest extent possible, including consideration of a library of pro-forma Incident Action Plans; and • develop and implement mechanisms to test and ensure that agencies possess satisfactory incident action planning capability and capacity for ‘all hazards’ at all levels of operations. |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0464 | 32 - Doctrine, standards, and reform | the state develop and implement a strategy that maximises the flexibility and united capacity of the Country Fire Authority and Victoria State Emergency Service to respond to emergencies. |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0416 | 26 - Research | the state establish appropriate arrangements to ensure the capacity to maintain technical expertise for flood intelligence is initiated, including appropriate agreements with commercial experts. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0442 | 32 - Doctrine, standards, and reform | the state appoint a state emergency controller who is ultimately accountable for all major emergencies. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0461 | 32 - Doctrine, standards, and reform | the state ensure: • water rescue/swift water rescue definitions, roles and responsibilities are clarified and communicated to all stakeholders to ensure common understanding • appropriate training, equipment and support is provided to those required to perform water rescue/swift water rescue. Common training programs, standards and accreditation should be utilised wherever possible to increase potential for joined up operations and maximised capability • that based upon the experiences of these flood events, an appropriate level of water rescue capacity and capability is established and maintained • flood plans (all levels) and flood emergency response planning incorporate consideration of pre-positioning of appropriate water rescue capability in the event that such services should be required; and • that revised water rescue roles, responsibilities and arrangements are clearly defined in the Emergency Management Manual Victoria and such definitions are replicated in all individual agency planning and operational documents |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0469 | 32 - Doctrine, standards, and reform | the state update the current fire specific guidelines and resources for evacuation planning to take an ‘all hazards’ approach |
REC199-0429 | 13 - Mapping and data quality | the state take into account any outcomes from the Commonwealth Government’s flood mapping reviews in the continual development of the Victorian flood database and to incorporate into the database flood data currently held by Melbourne Water. |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0454 | 32 - Doctrine, standards, and reform | the State Emergency Response Coordinator further develop the Strategic Emergency Management Assurance Team process by involving subject matter experts from relevant emergency management control agencies who are the subject of Strategic Emergency Management Assurance Team focus. |
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
REC199-0487 | 32 - Doctrine, standards, and reform | the state develop and incorporate into emergency management planning regimes plans based on geographic risk, such as sub-regional plans |
REC199-0408 | 13 - Mapping and data quality | the state, in consultation with Bureau of Meteorology and Melbourne Water, take the necessary action to ensure that all flood warnings issued are linked to the geographical location of the gauge the data was derived from. |
REC199-0467 | 32 - Doctrine, standards, and reform | the state review and align all policies and procedures for evacuation, such as the interim evacuation guidelines and the State Health Emergency Response Plan, to ensure consistency and to clarify roles and responsibilities. |
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0459 | 32 - Doctrine, standards, and reform | the state undertake a complete review of emergency management legislation. This should include agencyspecific emergency management legislation and should focus on service interoperability and securing an ‘all hazards, all agencies’ capability |
REC199-0484 | 32 - Doctrine, standards, and reform | the state: • assess current risk and risk mitigation strategies for essential services, with a focus on ensuring that risks are appropriately identified at all levels of emergency planning; and • ensure that the responsible authority or owner/ operator of essential services put in place appropriate strategies to mitigate any risk to service continuity |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0420 | 13 - Mapping and data quality | the state establish standards for flood mapping to ensure they are kept contemporary and meet the purposes of landuse risk planning and emergency response. In doing so, maps should extend where appropriate to include Probable Maximum Flood, over a range of Annual Exceedence Probability levels and be explicitly linked to a stream gauge. |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0451 | 15 - Inter-service cooperation | the state ensure, as a matter of priority, that the State Control Centre is able to function as a fit for purpose, multi-agency emergency management centre. Necessary works to achieve this outcome should have an overarching focus on the implementation of common agency systems and processes to the fullest extent possible. |
REC199-0457 | 32 - Doctrine, standards, and reform | the state: • revise the Emergency Management Team Practice Note to include a template to ensure an appropriate and consistent approach to Emergency Management Team operations • provide the revised Emergency Management Team Practice Note to all stakeholders to enable familiarisation; and • ensure that there is regular exercising of Emergency Management Teams with an `all hazards’ focus. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0417 | 13 - Mapping and data quality | the state ensure that regional and local flood plans incorporate all available flood mapping and intelligence, including assessments of levees and flood consequence information. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0443 | 32 - Doctrine, standards, and reform | the state reconfigure the Victorian Emergency Management Council and the supportive committee arrangements to ensure a comprehensive, accountable, effective and integrated approach to the development of emergency management arrangements is in place for Victoria. The process should also include consideration of the Security and Emergencies Committee and Central Government Response Committee roles, functions, reporting arrangements and relationships with other state level emergency management groups. Settled arrangements must be clearly articulated to ensure stakeholder understanding. |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1924 | 32 - Doctrine, standards, and reform | That the Queensland Reconstruction Authority review and approve the draft organisational policies and procedures, in the areas of human resources, finance, communications and information technology. |
REC190-1928 | 24 - Govt responsibility | That the Queensland Reconstruction Authority finalise the value for money policies and procedures, particularly those that take into account the role and responsibilities of the external service providers. |
REC190-1927 | 24 - Govt responsibility | That the Queensland Reconstruction Authority agree on and finalise the work plan and attach it as a Schedule to the Agreement as required in section 15 of the Agreement. |
REC190-1926 | 24 - Govt responsibility | That the Queensland Reconstruction Authority clarify and communicate the roles of the Lines of Reconstruction sub-committees to the Chairs of each committee. |
REC190-1925 | 32 - Doctrine, standards, and reform | That the Queensland Reconstruction Authority develop and implement policies and procedures to ensure the adequate management and security of public records in accordance with the Public Records Act 2009. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2974 | 32 - Doctrine, standards, and reform | The Department of Human Services should develop practical, operational guidelines for implementing recovery at the state level. |
REC179-2983 | 24 - Govt responsibility | The Department of Human Services should work with the State Emergency Recovery Planning Committee, regions, and other partners to facilitate understanding and ownership of roles and responsibilities for common recovery services. |
REC179-2980 | 24 - Govt responsibility | The Department of Human Services should work with regions and partner agencies at the state level to create consistent, streamlined impact assessment processes and systems. |
REC179-2979 | 24 - Govt responsibility | The Department of Human Services should communicate strategic priorities to achieve state and regional level alignment in building recovery capacity and capability. |
REC179-2975 | 32 - Doctrine, standards, and reform | The Department of Human Services should improve regional recovery plans through: |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0078 | 32 - Doctrine, standards, and reform | The basic tenet of a local community response as the foundation of Queensland's Disaster Management framework, with a clear description of the relationships between the levels and description of the phases of Disaster Management, needs to be more strongly emphasised in the "objects" of the legislation and "how objects are to be achieved". |
REC165-0092 | 32 - Doctrine, standards, and reform | Executive Officers to DDCs be serving Police Officers. Regional and Area officers of EMQ be members of Local and District Disaster Management Groups to enable them to fulfil their Statewide support and governance roles. |
REC165-0083 | 32 - Doctrine, standards, and reform | The Chairperson of SDMG (where leadership is not already defined in relevant National Plans) nominate a senior officer to assume overall responsibility for control and coordination of each disaster event to ensure a decisive and effective response. At Local level the Act provide for the CEO in consultation with the LDMC to appoint a public official/s with required training and competence as Local Controller. |
REC165-0098 | 24 - Govt responsibility | The SDMG take into account key improvement initiatives and change processes suggested when deciding on an effective implementation strategy for agreed recommendations. |
REC165-0091 | 32 - Doctrine, standards, and reform | EMQ resources be directed to continually improving, monitoring and regularly evaluating the State's Disaster Management system with a priority focus on providing support to Local Government levels including interlinking exercises involving District and State arrangements. |
REC165-0097 | 24 - Govt responsibility | Revised governance arrangements be implemented involving Disaster Management Groups at the three levels supported by EMQ as outlined in this report to achieve continuous improvement in the Disaster Management arrangements in the State. A new provision in Section 5 emphasise the discretion available to all involved in the Disaster Management system to take action to prevent impending loss of life even if contrary to the agreed arrangements. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
REC165-0096 | 15 - Inter-service cooperation | The Department of Community Safety and Councils develop MOUs to reflect the genuine partnership that exists in present arrangements including an emphasis on the use of the agreed State disaster arrangements to task and deploy SES units following State/Local consultation. |
REC165-0080 | 32 - Doctrine, standards, and reform | The State Disaster Management Plan incorporate linkages with all Lead Agencies and officers in control of National Plan or Agreement response. All of these Plans and Agreements should have a formal requirement to ensure officers in charge work within the State's Disaster Management framework to deliver Disaster Management responses. |
REC165-0088 | 32 - Doctrine, standards, and reform | The State Disaster Management Act be strengthened by a description of the phases of Disaster Management with emphasis on the key elements within each phase including the recovery phase; Lead Agencies and nominated leaders in each area of Queensland for each of the four key elements of recovery be identified and provided with the appropriate training and familiarisation of their role to ensure the adequacy of planning at District and Local level throughout Queensland; Lead Agencies be responsible for maintaining strong relationships with counterparts at the Federal Government level to ensure necessary Federal support for State and Local recovery initiatives after disaster events; Response arrangements remain in place until the State Controller is satisfied that recovery leadership arrangements are in place at Local, District and State levels; Recovery leadership and support from State level remain in place until local recovery is substantially completed. |
REC165-0094 | 32 - Doctrine, standards, and reform | The Act be amended to make it clear that Disaster Controllers/Coordinators at all levels are to be authorised public officials with the necessary training and authority to properly discharge the role and provide an effective direct line of support, coordination and control of disaster events. The Act and State Plan provide guidance about appropriate role and functions of elected representatives during all disaster event phases. The Major Incidents Group and State Security Committee be merged to become the State Disaster and Security Council with role as suggested in this report. |
REC165-0079 | 32 - Doctrine, standards, and reform | The Act be amended (Sections 45, 46, 47) to enable verbal directions in times of disaster responses from a State Controller to DDC to Local Controller, which must be committed to writing promptly to formalise the record. |
REC165-0084 | 32 - Doctrine, standards, and reform | The State Disaster Management Group focus on Disaster Management strategy and policy with sub-committees or appropriate levels in the Disaster Management system assigned detailed disaster planning or risk management assessment roles. New group members be provided with an induction briefing about the State's Disaster Management arrangements by the Executive Officer prior to attending their first meeting. |
REC165-0093 | 32 - Doctrine, standards, and reform | The Department of Community Safety (through EMQ) be assigned in the Act with the responsibility to develop, maintain, monitor and continuously improve the State's Disaster Management arrangements and systems. The Executive Director, EMQ, be a member of SDMG with the Director-General, Department of Community Safety. The position of Executive Officer, SDMG, be assigned appropriate support roles to SDMG. An officer other than the Executive Director, EMQ, or the State Controller of a disaster event, perform the role of Executive Officer to the SDMG. A dedicated Assistant Commissioner of Police be assigned the role of control, coordination and overall responsibility for Queensland's response to disaster events other than those subject to National Plans and Agreements. |
REC165-0099 | 32 - Doctrine, standards, and reform | The suggested summary of legislative changes guide the legislative response to the report incorporating consultation with key stakeholders at State, District and Local levels. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3051 | 32 - Doctrine, standards, and reform | ACTAS should: |
REC159-3061 | 32 - Doctrine, standards, and reform | ACTAS should develop and implement policies and guidance to staff on how complaints should be assessed and actioned, including timeliness targets. |
REC159-3060 | 32 - Doctrine, standards, and reform | ACTAS should develop a policy that provides direction on what type of feedback it will seek, from whom it will seek the feedback, and how this feedback will be used to improve the patient care experience. |
REC159-3057 | 32 - Doctrine, standards, and reform | ACTAS should conduct formal reviews of its clinical procedures manuals in consultation with its Clinical Advisory Committee, and develop guidance to oversight these reviews. |
REC159-3056 | 32 - Doctrine, standards, and reform | ACTAS should specify and document the role of each of its various clinical governance processes, how they relate to each other, and how these will be managed, measured and monitored within an overarching clinical framework. |
REC159-3053 | 32 - Doctrine, standards, and reform | ACTAS should develop policies and guidelines to assist ambulance officers’ decisions on whether or not to transport a patient to hospital. This guidance might include appropriate responses when a mentally impaired patient declines transport or treatment, and when to call on management or clinical guidance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3395 | 15 - Inter-service cooperation | The Committee recommends that the ACT Emergency Services and the Rural Fire Service in particular institute regular meetings with the NSW Rural Fire Service and other appropriate authorities, such as environment |
REC144-3381 | 32 - Doctrine, standards, and reform | The Committee recommends that the Bushfire Council consultative requirements under the Emergencies Act 2004 be reviewed, with a view to removing the requirement to consult with the Bushfire Council on operational matters, such as staff appointments and matters prescribed by regulation. |
REC144-3394 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government develops a joint strategic bushfire management plan with the NSW Government and the NSW Rural Fire Service in relation to those areas which have the potential to impact on both jurisdictions. |
REC144-3380 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government develop and publish an operational policy document which spells out the command and control structures and procedures should an emergency event arise. |
REC144-3388 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government re-investigate the suitability of the Fairbairn site as a proposed centralised accommodation facility for emergency services. |
REC144-3392 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government finalise Version 2 of the Strategic Bushfire Management Plan as required under the Emergencies Act. |
REC144-3386 | 24 - Govt responsibility | The Committee considers that the ACT Government should table in the ACT Legislative Assembly the cost-benefit analysis and business plan for Fairbairn as a central site for emergency services in the ACT. |
REC144-3391 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government explain its reasons to the Legislative Assembly for not proceeding with the release of Version 2 of the Strategic Bushfire Management Plan in July 2005. |
REC144-3383 | 32 - Doctrine, standards, and reform | The Committee recommends that, if the Bushfire Council is to have an advisory role generally in emergency management, it should be renamed to reflect a general emergency role rather than a role specifically in relation to bushfires. |
REC144-3390 | 24 - Govt responsibility | If the ACT Government decides to proceed with the site as the emergency services headquarters, that it accord a high priority to the finalisation of the site preparations for the ESA at Fairbairn as a matter of urgency. |
REC144-3382 | 24 - Govt responsibility | The Committee recommends that responsibility for oversighting the progress of the implementation of agreed recommendations of the Coroner be undertaken by a truly independent body and not by the Bushfire Council. |
REC144-3389 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government make a public announcement about the future accommodation plans for the Emergency Services Agency and its component parts so that both the ESA and the ACT public are informed about current proposals and timeframes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
REC125-3895 | 32 - Doctrine, standards, and reform | That all agencies develop drainage asset management plans, consistent with best practice, and that these incorporate: |
REC125-3891 | 15 - Inter-service cooperation | That Melbourne Water and councils explore opportunities for working collaboratively to address the management of flooding risks with a view to optimising the efficient and effective use of their flood mitigation resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3879 | 32 - Doctrine, standards, and reform | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan, to consider the use of alternative locations for staging, evacuation, assembly and incident coordination, to increase separation of emergency operations from non emergency activity be adopted. |
REC123-3878 | 32 - Doctrine, standards, and reform | Melbourne Airport management, the emergency services and airlines develop risk based tactical plans that, where safe and appropriate, allow the staged or progressive closure or re-opening of terminal space to support continuity of airport operations during emergencies. |
REC123-3876 | 15 - Inter-service cooperation | Metropolitan Fire Brigade and Aviation Rescue Fire Fighting service review and enhance the existing mutual response Memorandum of Agreement to provide more timely notification and therefore immediate access to appropriate resources to respond to emergencies. |
REC123-3875 | 15 - Inter-service cooperation | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan to ensure the capabilities of agencies are adequately documented and understood by all stakeholders, and that all agencies including airlines are represented at the appropriate organisational level on the Airport Emergency Planning Committee. |
REC123-3881 | 32 - Doctrine, standards, and reform | Reference to the Aviation Rescue and Fire Fighting service in Part 6 of the Emergency Management Manual Victoria, table of control and support agencies, be extended to include its responsibility for hazardous materials emergencies at the airport. |
REC123-3874 | 32 - Doctrine, standards, and reform | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan to confirm that planning and response arrangements appropriately consider the protection of public safety, the current security environment and the timely restoration of airport operations, and that it is consistent with state emergency response planning arrangements. |
REC123-3880 | 32 - Doctrine, standards, and reform | Victoria Police, Melbourne Airport management, airlines and emergency services develop a Memorandum of Understanding for media coordination and public communications at Melbourne Airport that documents the responsibility for media coordination during emergencies to Victoria Police. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3942 | 32 - Doctrine, standards, and reform | It is recommended that public sector entities establish frameworks which will provide for more effective governance over business continuity management. |
REC111-3938 | 32 - Doctrine, standards, and reform | To ensure an effective and co-ordinated approach to communication throughout the Queensland disaster management system, it is recommended that — |
REC111-3936 | 24 - Govt responsibility | To enhance the governance of the Queensland disaster management system, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services ensure that — |
REC111-3935 | 24 - Govt responsibility | To provide the strategic leadership and governance required to implement the Disaster Management Act 2003, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable governance framework for disaster management which includes the establishment of — |