Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4335 | 16 - Training and behaviour | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services update and deliver training on the workflow reviewed (as per Recommendation 3) of the current Emergency Alert system to all persons responsible at a local, district and state level by 1 November 2022. Training should address system constraints and system complexities in addition to the process of requesting, composing (including Clear Explicit Translatable Language [CETL]), authorising and issuing Emergency Alerts. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
REC323-4290 | 20 - Role of police | That the NSW Government embed into its emergency plans the appointment of a senior police officer with combat experience to lead recovery efforts following natural disasters. |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4282 | 16 - Training and behaviour | That the NSW Government invest in the required personnel, training and vessels to ensure that all agencies involved in flood rescue can be mobilised to their fullest potential. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
REC308-2465 | 29 - Operational Health and Safety | Fatigue management strategies and guidance should be improved to ensure sustainable staffing practices are incorporated into disaster management planning. |
REC308-2464 | 16 - Training and behaviour | The provision of system-wide education, guidance and testing to enhance requests for Assistance is strengthened. |
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1269 | 35 - Business and Industry in relation to industry | That Government engages with non-government organisations that may provide services during emergency events to clarify the terms and conditions for support through a written arrangement (MOU or similar). |
REC297-1257 | 35 - Business and Industry in relation to industry | That in the event that Hydro Tasmania decides to start cloud seeding again, water managers, represented by DPIPWE, work with Hydro Tasmania to ensure appropriate, best practice application of the guidelines issued by the Agricultural and Resource Management Council of Australia and New Zealand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1530 | 16 - Training and behaviour | Local Disaster Coordination Centre capability and capacity should be reviewed to ensure adequate staffing arrangements are in place to fill key positions, and that operational protocols are known and practiced across all functions to provide redundancy. Assistance for review and necessary training should be sought from key Local Disaster Management Group member agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2818 | 16 - Training and behaviour | The Royal Australian College of General Practitioners provide resources and training to general practitioners on the complex health needs of migrants and refugees, with a focus on identifying infectious diseases which are notifiable in Australia, or diseases which are of specific concern to refugee and migrant communities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0734 | 16 - Training and behaviour | Emergency Management Queensland should simplify the process by which SES members gain recognition for prior qualifications so that unnecessary duplication of training can be avoided. |
REC210-0775 | 16 - Training and behaviour | The Department of Environment and Resource Management should conduct periodic dam safety information and education sessions with emergency management personnel including those from Emergency Management Queensland, local and district disaster management groups and local councils. Priority should be given to sessions if the Bureau of Meteorology forecasts a wet season with a greater than 50 per cent chance of above median rainfall. |
REC210-0708 | 35 - Business and Industry in relation to industry | The Queensland Government should work collaboratively with the Commonwealth Government and mine operators to ensure co-ordinated and effective monitoring of salts, metals and other contaminants in marine environments that may be affected by mine discharges. |
REC210-0766 | 16 - Training and behaviour | Wide Bay Water should, in addition to its usual wet season preparations and maintenance, undertake the following activities in advance of each wet season: Queensland Floods Commission of Inquiry | Final Report 29 Complete list of Final Report recommendations • conduct training for personnel on dam operation, including contingency plans for the situation in which one or more of the gates is inoperable • hold meetings of key personnel of Wide Bay Water involved in the operation of the dam during floods, which: – in addition to any other matters, inform staff about the current status of the gates, dam operation strategies and contingency plans for the situation in which one or more of the gates is inoperable – are recorded in minutes which document the information provided and are made available to all operational staff. |
REC210-0763 | 35 - Business and Industry in relation to industry | Seqwater should ensure that the Somerset Dam gallery is not susceptible to flooding during overtopping events. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0424 | 35 - Business and Industry in relation to industry | the state require dam owners and operators to review storage operating manuals to incorporate lessons from the 2010–11 floods and make this information publicly available. The manuals should include a clear policy on dam surcharging and pre-release. |
REC199-0451 | 15 - Inter-service cooperation | the state ensure, as a matter of priority, that the State Control Centre is able to function as a fit for purpose, multi-agency emergency management centre. Necessary works to achieve this outcome should have an overarching focus on the implementation of common agency systems and processes to the fullest extent possible. |
REC199-0475 | 16 - Training and behaviour | the Department of Planning and Community Development review the volunteer register and examine additional options to support councils in volunteer management, including the development of tools and staffing support. |
REC199-0415 | 16 - Training and behaviour | the state ensure that all personnel who are likely to become involved in incident management teams for floods receive basic flood awareness training prior to such involvement. |
REC199-0448 | 16 - Training and behaviour | the state ensure that sector wide familiarity and understanding of the various systems for incident management is developed and maintained. Primarily, this should be achieved through multi-agency emergency management training and exercising involving usage of the various agency incident management systems. |
REC199-0463 | 16 - Training and behaviour | the state: • ensure an appropriate regime of regular emergency management training and exercising is introduced. This must be ‘all hazards’ and multi-agency focused and include all relevant stakeholders • designate an accountable officer to hold ongoing responsibility for conducting such exercises; and • designate the Emergency Services Commissioner as holding ongoing responsibility for auditing and reviewing this training and exercising. |
REC199-0414 | 16 - Training and behaviour | the state ensure that all personnel who, because of their particular flood expertise, are likely to be potential participants in an Incident Control Centre are familiar with the requirements of the Australasian Inter-service Incident Management System structure |
REC199-0427 | 35 - Business and Industry in relation to industry | the state require dam owners and operators provide regular situational reports to the relevant control agency where dam issues may impact incident management. |
REC199-0462 | 16 - Training and behaviour | the state introduce a joint emergency management leadership training program that will deliver critical core competencies for all levels of management of major emergencies. Future appointments to senior operational emergency management positions should require successful accreditation at the appropriate level. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0426 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform people situated downstream of water storages if the owners/operators become aware of an immediate threat arising from the dam to the safety of those people. The owner/operators should provide this information as soon as the owner/operators become aware of the threat. |
REC199-0453 | 20 - Role of police | Victoria Police revise coordinator arrangements to ensure: • a coordinator presence is maintained at the place where incident control is being exercised • effective control is established and is maintained until the response phase has concluded • key control roles may be performed by personnel from agencies other than the designated control agency • that the timely compilation and distribution of an appropriate Incident Action Plan is recognised as a fundamental component of establishing effective control • those performing the coordinator role at an Incident Control Centre be suitably trained, skilled and experienced in emergency management and where possible possess a degree of local knowledge of the relevant area; and • that the revised coordinator arrangements are reflected within the State Emergency Response Plan |
REC199-0425 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform the control agency and the Bureau of Meteorology about the management and operation of dams and weirs consistent with the flood warning requirements of the relevant river systems, including providing telemetry at sites as necessary. This may require the state proactively liaising with other states to ensure equivalent obligations are placed on interstate dam operators where the dam may impact Victorian communities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0075 | 16 - Training and behaviour | SERCon consider development of an education program for other government and non-government agencies (with |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3502 | 35 - Business and Industry in relation to industry | The Emergency Services Telecommunications Authority in partnership with Telstra should develop testing regimes that will ensure the integrity of the call queue arrangements and correct configuration of the Recorded Voice Announcements. |
REC156-3495 | 16 - Training and behaviour | The Department of Primary Industries should work through the appropriate Ministerial Councils to seek alignment of competency standards for line workers across jurisdictions. |
REC156-3493 | 35 - Business and Industry in relation to industry | The electricity distribution businesses and retailers work with the Department of Human Services and hospitals to review the registration, notification and removal process for those on life support machinery. |
REC156-3485 | 15 - Inter-service cooperation | The integrated Emergency Coordination Centre be utilised during all significant multi-agency or multi-incident events with effective liaison with the State Emergency Response Coordinator. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
REC129-3620 | 35 - Business and Industry in relation to industry | We recommend that NSW Health continue with its good work and conclude agreements with private health providers specifying roles, and expectations in the case of an infectious disease pandemic. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3607 | 16 - Training and behaviour | That the Department of Primary Industries should continue efforts to develop the skills of private sector veterinarians to increase the level of resources available in emergency responses. |
REC128-3609 | 16 - Training and behaviour | That the Department of Primary Industries be conscious of its responsibilities in maintaining the continued enthusiasm of Industry Liaison Officers and offer training and refresher training as required. |
REC128-3608 | 16 - Training and behaviour | That emergency animal health training be included in induction programs for newly recruited District Veterinarians and all District Veterinarians be encouraged to maintain their skills by attending regular refresher training as appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
REC125-3893 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures that stakeholders (and especially local councils) are fully consulted before and during the development of drainage strategies and plans. These plans should consider councils’ drainage systems. |
REC125-3892 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures stakeholder expectations are fully considered when setting flood risk reduction targets. |
REC125-3891 | 15 - Inter-service cooperation | That Melbourne Water and councils explore opportunities for working collaboratively to address the management of flooding risks with a view to optimising the efficient and effective use of their flood mitigation resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3916 | 16 - Training and behaviour | That DPI reviews the work of entry level graduates to ensure career paths are clear and encourage the retention of staff. |
REC112-3930 | 16 - Training and behaviour | That DPI provides plant incursion-specific AIIMS training for anyone who might be involved in, or providing resources for, an incursion response. This includes senior management, field and research staff, contractors and industry participants. |
REC112-3913 | 35 - Business and Industry in relation to industry | That DPI works with industry to develop a training module on the certification and verification system for inclusion in industry quality assurance programs. |
REC112-3929 | 35 - Business and Industry in relation to industry | That DPI develops a comprehensive strategy for communicating to industry their rights and responsibilities in relation to threats, incursions, outbreaks and post-outbreak; and also for communicating internally. |
REC112-3921 | 17 - Assets and technology | That the recommendations of the 2000 DPI report into the reference collection’s storage facility be implemented, to secure the collection in a purpose-built facility. |
REC112-3920 | 15 - Inter-service cooperation | That better use be made of Primary Industries Research Victoria's (PIRVIC) facilities by strengthening links with relevant groups of expertise, such as the Forest Science Centre. |
REC112-3933 | 15 - Inter-service cooperation | That DPI formalises agreements between divisions and groups that allow staff to be involved in incursion responses and reflects this requirement in individual duty statements. |
REC112-3918 | 35 - Business and Industry in relation to industry | That DPI effectively communicates to all sectors of the industry their responsibilities to report new threats, and how to report them. |
REC112-3931 | 16 - Training and behaviour | That DPI ensures that AIIMS training includes information to ensure that everyone understands their role, and how information will be managed internally and externally, in the event of an incursion. |