REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4337 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an urgent multi-agency (including but not limited to the Queensland Police Service and Brisbane City Council) review of the workflow, of the current Emergency Alert system, including requesting, composing, authorising and issuing of Emergency Alerts by 1 November 2022. |
REC325-4323 | 7 - Inter-agency communication | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services adopt measures to achieve a common operating picture between deployed Queensland Fire and Emergency Services assets in disaster management operations by 1 November 2023. |
REC325-4329 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services implement the Australian Warning System for all nationally agreed hazards by 1 November 2023. Implementation should include guidance and training to all local governments and agencies operationally involved in disaster management, with emphasis on those agencies with hazard specific responsibility. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that do not have pre-formatted messages and polygons engage with Queensland Fire and Emergency Services and determine whether their local disaster management group capability could be improved through the development of pre-formatted polygons and messages. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that currently use pre-formatted messages within the Emergency Alert system review and, where necessary, redraft messages using the principles of Clear Explicit Translatable Language (CETL). |
REC325-4336 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services, in consultation with the Queensland Police Service, incorporate into the workflow of the current Emergency Alert system a process that ensures the inclusion of an ‘urgent approval and distribution without delay’ process for Emergency Alert messages by 1 November 2022. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4298 | 37 - Funding | Housing and development funding options: That, to empower vulnerable people and communities to avoid significant impacts from flood as well as drive broader investment in adaptation, Government through NSWRA: |
REC324-4313 | 8 - Communications and warnings | NSW disaster app: That, to improve community confidence in government messaging and warnings, the SEOCON and DCS develop a single ‘NSW disaster app’. This: |
REC324-4314 | 8 - Communications and warnings | PIFAC function: That, to ensure the community can better understand the threat of flood, storm and tsunami activity, the Department of Customer Service (DCS) be made accountable for PIFAC in all emergencies. This will improve access to clear, reliable and consistent messaging prior to and during emergencies. This transfers the PIFAC role from NSW Police Force to Service NSW. Under this PIFAC function, DCS would be responsible for: |
Rec-ID | Code | Recommendation | |
---|---|---|---|
REC323-4264 | 34 - Local knowledge | That the NSW Government work in partnership with key Aboriginal stakeholders, including the Jali Local Aboriginal Land Council, to prioritise the rebuild of Cabbage Tree Island, and ensure a safe and resourced evacuation plan is in place. |
|
REC323-4288 | 8 - Communications and warnings | That the NSW Government work with the Commonwealth to develop a national cross-agency app to integrate all community services and agencies into a single platform so that everyone can receive accurate and timely information from one source during emergencies. |
|
REC323-4275 | 34 - Local knowledge | That the NSW Government, in partnership with community groups, including First Nations groups, develop initiatives to build community resilience, particularly in regions at high risk of future natural disaster events. |
|
REC323-4265 | 34 - Local knowledge | That the NSW Government work with First Nations peoples to support Aboriginal organisations in their capacity to operate and respond in times of natural disasters. |
|
REC323-4290 | 20 - Role of police | That the NSW Government embed into its emergency plans the appointment of a senior police officer with combat experience to lead recovery efforts following natural disasters. |
|
REC323-4281 | 37 - Funding | That the NSW Government allocate funding to the improvement of the Pitt Town Evacuation Route and other key possible evacuation routes in Sydney's northwest. |
|
REC323-4276 | 34 - Local knowledge | That the NSW Government ensure that community groups, both existing and emerging, including First Nations groups, are well integrated into disaster recovery, by incorporating them into state recovery plans and engaging with them in between and in the lead up to natural disasters. |
|
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
|
REC323-4283 | 8 - Communications and warnings | That the NSW Government work with the community broadcasting sector to identify ways in which community broadcasters could be better supported to provide critical services during natural disasters, with a view to providing them adequate long term funding. |
|
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
|
REC323-4270 | 37 - Funding | That the NSW Government consider entering into a service agreement with an organisation that has the resources and capacity to manage donations and activate quickly during natural disasters. |
|
REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
|
REC323-4284 | 8 - Communications and warnings | That the NSW Government review its public awareness and communication strategies in relation to natural disasters. |
|
REC323-4279 | 37 - Funding |
|
|
REC323-4272 | 37 - Funding | That the NSW Government ensure that flood affected individuals can continue to access financial assistance for as long as there is demonstrated need. |
|
REC323-4261 | 37 - Funding | That the NSW Government advocate through the National Cabinet to widen eligibility under the Disaster Funding Recovery Arrangements to allow local councils to build back better. |
|
REC323-4287 | 34 - Local knowledge | That the NSW State Emergency Service, in partnership with the Bureau of Meteorology, investigate ways in which local communities and local media with local knowledge can play a stronger role in flood predictions and warnings. |
|
REC323-4280 | 37 - Funding | That the NSW Government work with local governments to identify alternative routes to vulnerable roads, and that the NSW and Australian Governments fund the construction of these important routes to improve evacuation and access options in times of disaster. |
|
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2479 | 34 - Local knowledge | Local groups should plan for and establish clear arrangements to effectively manage offers of assistance including the management of goods, services and volunteers. |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
REC309-2475 | 15 - Inter-service cooperation | Greater emphasis be placed on pre-planned and pre-determined arrangements between the Australian Defence Force and State and local agencies. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
REC306-2423 | 37 - Funding | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning as a matter of priority, establish what funding is reasonably required and complete all elements of the Brisbane River Catchment Flood Studies. |
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1267 | 8 - Communications and warnings | That emergency management authorities react with heightened awareness and action when BoM issues flood watches and related warnings. |
REC297-1266 | 8 - Communications and warnings | That Government supports the anticipated SES State Flood Warning proposals aimed at improving public warnings and communication, and that the proposed warning system is consistent with the National Frameworks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1304 | 20 - Role of police | That SA Police, as the control agency for search and rescue, and State Emergency Service who have the responsibility for providing search and rescue services under the State Emergency Management Plan, develop a swiftwater rescue capability plan that describes key swiftwater risk locations, roles and responsibilities of emergency services, State swiftwater resources and dispatch arrangements. |
REC295-1316 | 24 - Govt responsibility | That the position of Deputy Director, Office for Digital Government is dedicated to the Office for Digital Government; and that people throughout DPC are identified and trained to perform appropriate roles within the State Crisis Centre |
REC295-1278 | 20 - Role of police | That SA Police develop an evacuation plan for the Adelaide Central Business District (CBD) which includes: |
REC295-1296 | 8 - Communications and warnings | That the SES in collaboration with MFS Communications Centre (Comcen) investigate and implement options to reduce the number of calls coming into the Comcen, (particularly on 132500). Options could include better utilisation of the available options on the Interactive Voice Recording and community education to increase community resilience. |
REC295-1312 | 24 - Govt responsibility | That the Department of Education and Child Development be included as a member of State Emergency Management Council and represented in the State Emergency Centre. |
REC295-1329 | 8 - Communications and warnings | Review and update Part 3, Annex C, of the SEMP ‘Public Information and Warnings’ to: a) clarify the role and responsibilities of the Public Information Functional Support Group and control agencies in relation to public information b) define requirements and processes for liaising with the community, including holding community meetings |
REC295-1291 | 24 - Govt responsibility | That the Flood Reform Task Group, as proposed by the Department |
REC295-1308 | 24 - Govt responsibility | That the Department of the Premier and Cabinet revise the ministerial documents relating to emergency management. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1288 | 24 - Govt responsibility | That Attorney General’s Department explore options to overcome fatigue and welfare issues of SAGRN staff associated with emergency events of extended duration. |
REC295-1307 | 20 - Role of police | That, as with earthquake, SA Police be designated the Control Agency under the State Emergency Management Plan for black system events or other major power outages. |
REC295-1319 | 24 - Govt responsibility | That a single emergency service multi-agency control centre be established with sufficient capacity and capability to deal with all types of emergency incidents in SA. Also consider Police and State Emergency Centre. |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1305 | 18 - Access to fire ground | That the annexure to the State Emergency Management Plan, ‘Traffic management during emergencies’, be updated to include: responsibilities and processes for road closures; and, Department of Planning, Transport and Infrastructure requirements in regards to provision of road closure information, notification of changes in road closure status and publishing of that information. |
REC295-1318 | 24 - Govt responsibility | That the recommendation made following the Pinery bushfire, ‘to review control facilities at State, region and incident level’, be expanded to include all emergency services facilities that will be utilised for major incidents other than bushfire e.g. flood and earthquake and to also be extended into metropolitan areas, and implemented. |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1203 | 22 - Role of local Gvt | Impact Assessment Data Sharing The Office of Emergency Management: · with the SEOCON, jointly provides further guidance to Regional Emergency Management Officers about their role in facilitating local council access to the Impact Assessment Data Base · with REMOs and the SEOCON jointly provides further information to local councils about Impact Assessment Data Sharing Arrangements and the data available through this mechanism · includes information about the Impact Assessment Data Sharing Arrangements in the Local Recovery Toolkit · develops a mechanism to allow local councils to have direct access to the collated impact data. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1416 | 24 - Govt responsibility | A state-wide strategy, including a common definition, is developed for identifying and engaging vulnerable people in emergencies. |
REC272-1420 | 24 - Govt responsibility | The Department of Housing and Public Works should consider preparing an annual communique to asset owners of, and local governments with access to public cyclone shelters, outlining the maintenance and certification process and pre-season status. |
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
REC272-1418 | 24 - Govt responsibility | A state-wide engagement strategy is coordinated to ensure community messaging is consistent across all levels of Queensland’s disaster management arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1529 | 8 - Communications and warnings | As part of the above, both the Banana Shire Council and SunWater ensure Emergency Alert messages are pre-formatted, consistent, polygons are identified according to risk, and that they are tested and practiced with the State Disaster Coordination Centre. |
REC271-1528 | 8 - Communications and warnings | Prior to September 2015, SunWater and the Banana Shire Council jointly develop a multi-channel, common warning strategy, including common language and consistent messaging, for residents downstream of |
REC271-1527 | 8 - Communications and warnings | Prior to September 2015, the Banana Shire Council develops a multi-channel warning strategy and associated public information campaign, including common language and consistent messaging, for the Banana Shire. |
REC271-1533 | 14 - Incident Mgt Teams | State Disaster Coordination Centre considers requesting a representative from critical infrastructure owners be present as a liaison officer in the State Disaster Coordination Centre during activations for events that may impact on their assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1149 | 15 - Inter-service cooperation | PES External Surge Program The success of the PES External Surge Program and the willingness of participants to deploy at short notice to support the recovery effort is commendable, as is the readiness of their supervisors to release them from their duties to enable deployment. The Program, supported by an appropriate training program, is one that should be sustained as part of the whole of Government recovery readiness effort. |
REC267-1153 | 4 - Fire season preparation | Planning for Access to Potentially Isolated Communities |
REC267-1151 | 24 - Govt responsibility | Government Communications Coordination |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2561 | 24 - Govt responsibility | The Australian Government amends regulations so that background checks and the requirement to hold an Aviation Security Identification Card are only required for unescorted access to Security Restricted Areas, not for general airside access. This approach would align with international practice. |
REC258-2559 | 15 - Inter-service cooperation | The Civil Aviation Safety Authority’s Director of Aviation Safety meet with industry sector leaders to jointly develop a plan for renewing a collaborative and effective Standards Consultative Committee. |
REC258-2530 | 24 - Govt responsibility | The Australian Government appoints an additional Australian Transport Safety Bureau Commissioner with aviation operational and safety management experience. |
REC258-2526 | 24 - Govt responsibility | The Australian Government develops the State Safety Program into a strategic plan for Australia’s aviation safety system, under the leadership of the Aviation Policy Group, and uses it as the foundation for rationalising and improving coordination mechanisms. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
REC250-0792 | 8 - Communications and warnings | The Department of Human Services should develop an improved model for communication for future disasters that provides a single point of information and contact for disaster affected communities |
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0799 | 18 - Access to fire ground | Develop and implement a program of cost-effective road improvement works that can enhance flood evacuation capacity in the short-medium term. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2791 | 37 - Funding | The committee recommends that the government develop a process by which the ATSB can request access to supplementary funding via the minister. |
REC236-2783 | 2 - Emergency powers | The committee recommends that the Australian Transport Safety Bureau retrieve VH-NGA flight data recorders without further delay. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2812 | 37 - Funding | In order to further build on the value for money review work being undertaken by the National Disaster Recovery Taskforce (on behalf of the Australian Government Reconstruction Inspectorate), the Australian National Audit Office (ANAO) recommends that the Taskforce: |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2823 | 8 - Communications and warnings | The Australian Government, in consultation with consumers and other relevant federal, state and territory agencies, develop a national communication strategy for consumers to be used in the event of an infectious disease outbreak. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2847 | 15 - Inter-service cooperation | I recommend that Border Protection Command implement a surveillance strategy, possibly with the assistance of other Commonwealth authorities and organisations on the island such as the AFP, which heightens its coverage at times when the weather and sea conditions are rough. |
REC227-2849 | 20 - Role of police | I recommend that the AFP takes steps to ensure that there are on Christmas Island at all times appropriately trained AFP officers who have completed the National Police Search and Rescue Manager’s Course and that upskilling should be ongoing to establish a cadre of trained search and rescue personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1845 | 37 - Funding | The state government should provide core, ongoing funding to the responsible authority for the FloodSafe community education program. Funding should be provided for education about prevention, response and recovery phases and include information on rates notices about the height of particular floods. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1819 | 22 - Role of local Gvt | In consultation with local communities, local councils will develop flood response plans as subplans to their current Municipal Emergency Management Plans. As part of the flood risk assessment process, these plans will be informed by the best available flood mapping and modelling, and will identify agreed activities to be undertaken during floods including, where appropriate, the construction of temporary levees. The condition of levees will be incorporated into such plans to enable improved emergency response. |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1842 | 37 - Funding | The state government review the current funding approach used for the operation, maintenance and upgrade of river gauges, with a view to improving the river gauge network. |
REC217-1814 | 37 - Funding | The funding model for works on levees and their ongoing maintenance be revised, to be primarily based on the beneficiary pays principle. The state government should give consideration to wholly funding, or contributing to, the initial upgrade of high priority levees to an agreed standard. The construction of any new public levees will be the subject of a cost‐benefit analysis to be undertaken by DSE and the public authority, and be supported by a floodplain management study. Levees deemed low priority will be wholly the responsibility of the beneficiaries. |
REC217-1825 | 22 - Role of local Gvt | When developing flood mitigation options in lowland areas, local governments should give consideration to the use of temporary levees as an alternative or addition to permanent structures. To maximise the use of these structures and limit flood damage, and aid affordability, consideration should be given by local governments to the sharing of temporary levees among different townships and different council areas. |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2869 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: developing tools and workflows to quickly and reliably transform technical data into intelligence that can be used to construct messages for community information that are timely, relevant, tailored and effective. |
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
REC216-2871 | 22 - Role of local Gvt | Efficient and effective supporting tools and processes: high-quality local/municipal planning. |
REC216-2870 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: streamlining the authorisation processes for urgent warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0732 | 37 - Funding | Emergency Management Queensland should develop and implement a new formula for the distribution of its recurrent SES subsidy, which takes into account relevant factors including the size of a local SES contingent and the population, area and natural hazard risk profile of the local government area concerned. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
REC208-0524 | 8 - Communications and warnings | That the Premier issue clear and unambiguous guidelines to all Government Ministers specifying the timing of notifications to the public of any matters that may affect public health or safety. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0439 | 8 - Communications and warnings | the state review its Memoranda of Understanding with official emergency broadcasters to take account of increased usage of internet based information, including social media and the ability to broadcast community meetings |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0447 | 7 - Inter-agency communication | the state ensure that common and interoperable resource management systems are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0433 | 8 - Communications and warnings | the state develop and implement standards for Emergency Alert to ensure consistent use, training and application by accredited operators within agencies across ‘all hazards’. |
REC199-0458 | 7 - Inter-agency communication | the state ensure: • a common, functional and accessible system be introduced to enable effective Municipal Emergency Coordination Centre and Incident Control Centre communications • a regime of regular Municipal Emergency Coordination Centre exercising is introduced with oversight by an appropriate independent body. Such exercising should include testing of systems utilised for Incident Control Centre and Municipal Emergency Coordination Centre communications • those required to perform Emergency Management Liaison Officer roles have undertaken appropriate training; and • resource requesting arrangements are clarified and documented so that control and coordination functions do not overlap. |
REC199-0438 | 8 - Communications and warnings | the state investigate the ability to refine the Flood and Storm Information Line to enable it to receive as well as provide information. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0402 | 8 - Communications and warnings | the state develop a flood warning system for each basin and location with community input and make relevant documents publicly available. Each warning system should include key performance indicators. |
REC199-0446 | 7 - Inter-agency communication | the state commit to securing effective multi-agency interoperable communications as a high level priority and that all future communications projects and upgrades incorporate compliance provisions mandating interoperability requirements. |
REC199-0432 | 8 - Communications and warnings | the state develop and implement a single web portal as a means of providing emergency information to communities and local government on an ‘all hazards’ basis, including the information referred to in recommendations 74, 89 and 92. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0437 | 8 - Communications and warnings | the state engage with local government to ensure emergency services’ public information and warnings reflect the community demographic. |
REC199-0471 | 8 - Communications and warnings | the state and the commonwealth, during a flood event, make information available on providers who have capacity to accommodate patients and residents who require evacuation. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0444 | 2 - Emergency powers | the state, as a matter of urgency, develop a multi-agency Incident Control Team capability to be readily available for statewide deployment to establish incident control or to relieve functioning control structures. |
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
REC199-0453 | 20 - Role of police | Victoria Police revise coordinator arrangements to ensure: • a coordinator presence is maintained at the place where incident control is being exercised • effective control is established and is maintained until the response phase has concluded • key control roles may be performed by personnel from agencies other than the designated control agency • that the timely compilation and distribution of an appropriate Incident Action Plan is recognised as a fundamental component of establishing effective control • those performing the coordinator role at an Incident Control Centre be suitably trained, skilled and experienced in emergency management and where possible possess a degree of local knowledge of the relevant area; and • that the revised coordinator arrangements are reflected within the State Emergency Response Plan |
REC199-0436 | 8 - Communications and warnings | the state develop a standard approach to the provision of emergency warnings and information in formats – spoken and written – that recognise diverse community needs, including language and disability |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0418 | 7 - Inter-agency communication | the state develop an efficient process to ensure that, during flood events, temporary construction of flood mitigation works, such as levees, is controlled so as not to unacceptably impact on flood intelligence. |
REC199-0451 | 15 - Inter-service cooperation | the state ensure, as a matter of priority, that the State Control Centre is able to function as a fit for purpose, multi-agency emergency management centre. Necessary works to achieve this outcome should have an overarching focus on the implementation of common agency systems and processes to the fullest extent possible. |
REC199-0435 | 8 - Communications and warnings | the state put in place appropriate measures to inform the community of the intended purpose of the Emergency Alert warning system. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0440 | 8 - Communications and warnings | the state actively pursue the use of social media as part of its emergency warning and public information system. |
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0449 | 7 - Inter-agency communication | the state ensure that interoperable information management practices are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0434 | 8 - Communications and warnings | the state require that agencies operate in compliance with the guidelines of the Victorian Warning Protocol to ensure efficacy of warning messages. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3433 | 24 - Govt responsibility | That Harbour Masters are employed by a government body and remain geographically located at the port. |
REC158-3448 | 24 - Govt responsibility | That the Director of Marine Safety works with the Australian Maritime Safety Authority to ensure that State and port emergency arrangements interface appropriately with the National Maritime Emergency Response Arrangements. |
REC158-3447 | 15 - Inter-service cooperation | That emergency services are required to work directly with port/channel managers and the nominated marine safety authority to ensure that a training and exercise regime is established to enable emergency services personnel to develop and maintain the skills and knowledge relevant to marine emergency management. |
REC158-3454 | 24 - Govt responsibility | That the Department of Transport ensures that key stakeholders are engaged during the implementation of the approved Review recommendations. |
REC158-3446 | 15 - Inter-service cooperation | That emergency services are required to work directly with port/channel managers and the nominated marine safety authority to identify and ensure availability of marine resources necessary for emergency services to meet their statutory obligations in responding to marine emergencies (this recommendation should be read in conjunction with recommendation 26 & 27). |
REC158-3451 | 37 - Funding | That port/channel managers should be able, within the general context of the pricing/cost recovery arrangements established under the Port Services Act 1995 and pricing determinations made by the Essential Services Commission, to recover the reasonable costs of meeting their statutory obligations (as per recommendation 26) through charges for prescribed service applied to port users. |
REC158-3445 | 15 - Inter-service cooperation | That emergency services are required to work directly with ports and the nominated marine safety authority when ports are preparing marine emergency response arrangements. |
REC158-3450 | 37 - Funding | That emergency services are responsible for funding the development of the emergency services marine emergency response capacity/capability to meet their statutory obligations. |
REC158-3444 | 15 - Inter-service cooperation | That the Office of the Emergency Services Commissioner ensures that an emergency services multi-agency working group is established to develop a specialist marine emergency response capability for Victoria based on the multi-agency Urban Search and Rescue (USAR) model. The specialist personnel should be required to have: |
REC158-3449 | 37 - Funding | That port/channel managers are responsible for funding the preparation of marine emergency risk assessments and marine emergency response arrangements and ensuring the availability of identified marine resources in support of response to a marine emergency, to meet their statutory obligations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC154-3461 | 24 - Govt responsibility | DPI should develop an Memorandum of Understanding (MOU) with the Department of Human Services that capitalises on and strengthens the current good working relationship to support joint forward planning and risk management and mitigates against relationship failure in the event of leadership change. The MOU should clarify: |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3185 | 37 - Funding | That, until the review of those fees has been completed, the fee charged by the government controlled and operated quarantine stations for thoroughbred stallions temporarily imported into Australia be not be less than $165.00 plus GST a day and the fee for all other horses be not less than $65.00 plus GST a day. No discount is to be allowed for the number of horses in a consignment. |
REC148-3184 | 37 - Funding | That the fees charged in relation to the importation and quarantining of horses be reviewed and fixed without delay having regard to the following factors: |
REC148-3169 | 37 - Funding | That the budgets for airport reception of horses and government controlled and operated quarantine stations be determined so as to be sufficient to fund the operations of the Quarantine Stations in accordance with these recommendations and any further procedures and requirements that are laid down from time to time. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3629 | 8 - Communications and warnings | We recommend that NSW Health continue with its good work and continue to improve communication mechanisms with those, such as GPs, likely to be affected in major infectious disease outbreaks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3616 | 37 - Funding | That the Department of Primary Industries continue to pursue improvements to consultation with industry and accountability mechanisms to further build trust between industry and government, thereby enhancing the effectiveness of the OJD Program. |
REC128-3614 | 37 - Funding | The Committee encourages the Department and the Rural Land Protection Boards to discuss the need for funding of poultry surveillance activities in the context of reviewing the Memorandum of Understanding between the two parties. |
REC128-3606 | 24 - Govt responsibility | That the Department of Primary Industries address the forthcoming potential shortage of veterinary pathologists and agronomists within its testing facilities by positive recruitment actions over the next five years such as offering scholarships or training existing professional staff to develop skills in pathology. |
REC128-3604 | 37 - Funding | That the Department of Primary Industries restore the level of discretionary testing funds provided to District Veterinarians to previous levels and maintain these in the future in real terms. |
REC128-3603 | 37 - Funding | That the Department of Primary Industries consider applying discretion to the use of user charging policies for testing in times when farm incomes are affected by external circumstances such as widespread drought. |
REC128-3617 | 37 - Funding | That the Department of Primary Industries should provide specific information on levies to contributing producers through a separate document, rather than rely on standard audit documents and annual reporting requirements. |
REC128-3600 | 34 - Local knowledge | The Department of Primary Industries continue to consult local community about emergency planning and sites for disposal to retain confidence in the event of a genuine emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
REC125-3891 | 15 - Inter-service cooperation | That Melbourne Water and councils explore opportunities for working collaboratively to address the management of flooding risks with a view to optimising the efficient and effective use of their flood mitigation resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3664 | 20 - Role of police | The location of the command post for site control at the scene of any rail accident should be identified by NSW Police by a distinctive flashing light. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3934 | 37 - Funding | That DPI prepares guidelines, both internally and externally with Treasury, about funding arrangements for an outbreak. |
REC112-3933 | 15 - Inter-service cooperation | That DPI formalises agreements between divisions and groups that allow staff to be involved in incursion responses and reflects this requirement in individual duty statements. |
REC112-3920 | 15 - Inter-service cooperation | That better use be made of Primary Industries Research Victoria's (PIRVIC) facilities by strengthening links with relevant groups of expertise, such as the Forest Science Centre. |