Rec-ID | Code | Recommendation |
---|---|---|
REC314-3273 | 26 - Research | Collate data and research the impact of bushfires upon communities, firefighters and animals (both native and domestic) to identify appropriate medium and long-term welfare and support requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2508 | 25 - Inquiry, audit, lessons management and after action review | Regularly reviewing these plans to ensure that they reflect the current operating environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2385 | 25 - Inquiry, audit, lessons management and after action review | TFS should initiate a policy review (seeking support from government as appropriate) to clearly identify what body or agency is responsible for planning, carrying out and enforcing fuel management on private property at a township level. If current arrangements are unclear or ineffective, TFS should request government to consider making this a statutory responsibility of TFS and provide any additional funding required to support this function. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1315 | 25 - Inquiry, audit, lessons management and after action review | That a review of the role and effectiveness of the State Emergency Management Committee (SEMC) including: the legislative functions; membership including the chair; roles and responsibilities; and, SEMC Advisory Groups be undertaken. |
REC295-1305 | 18 - Access to fire ground | That the annexure to the State Emergency Management Plan, ‘Traffic management during emergencies’, be updated to include: responsibilities and processes for road closures; and, Department of Planning, Transport and Infrastructure requirements in regards to provision of road closure information, notification of changes in road closure status and publishing of that information. |
REC295-1297 | 25 - Inquiry, audit, lessons management and after action review | Engage an independent business analyst to review the current call, receipt and dispatch process for emergency services i.e. the Metropolitan Fire Service, Country Fire Service and State Emergency Service, from the initial call for assistance through to response of emergency service resources, including the allocation and coordination of multiple taskings. |
REC295-1276 | 25 - Inquiry, audit, lessons management and after action review | That SA Health undertake a review of their emergency management arrangements. Health State Controllers should be consulted during this review and arrangements should be consistent throughout the department and across the State and compatible with State emergency management arrangements and information systems |
REC295-1328 | 25 - Inquiry, audit, lessons management and after action review | Update the SEMP Part 3, Annex F ‘Debriefs’ to provide more guidance regarding the types of debriefs, when they are required to be undertaken and at what level and guidance for undertaking and recording debriefs, and implementing lessons identified. |
REC295-1327 | 25 - Inquiry, audit, lessons management and after action review | Establish a lessons management capability across the SA emergency management sector to collect, analyse and track lessons identified during debriefs and reviews following events and other sources such as interstate and oversees reviews and inquiries. |
REC295-1317 | 25 - Inquiry, audit, lessons management and after action review | Review representation in the State Emergency Centre including: a) determining if there is a more suitable functional support group e.g. the Procurement Functional Support Group, to replace the Logistics Functional Support Group, and if so, Chief Procurement Officer, DPC, has responsibility for the management of this role within the State Emergency Centre. b) That when the State Crisis Centre is not operating from a physical location, a State Crisis Centre liaison officer is attached to the State Emergency Centre. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1246 | 18 - Access to fire ground | The State Emergency Management Committee to review the policy for traffic management at emergency incidents so it reflects national ‘best practice’. This includes the production and issuing of an aide-memoire to guide traffic management, emergency and incident management personnel. |
REC291-1249 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Premier and Cabinet to conduct an independent review of the current arrangement for the management and distribution of the Emergency Services Levy. The review will have the specific purpose of: · seeking input from key entities including the Departments of Treasury, Finance, Fire and Emergency Services, Lands, and Parks and Wildlife, WA Local Government Association, and the Office of Bushfire Risk Management. · ensuring the arrangement has the flexibility and agility to deal with emerging bushfire risk priorities. · establishing a budget process that enables a shift in investment towards prevention, mitigation and building community resilience and capability. |
REC291-1245 | 18 - Access to fire ground | The Department of Fire and Emergency Services to issue a photo identification card to DFES members, members of Bush Fire Brigades, volunteer emergency services, Incident Management Teams, forestry industry brigade members and Networked Government Emergency Agency members. DFES also to consider temporary windscreen signage to identify vehicles carrying such personnel. |
REC291-1233 | 25 - Inquiry, audit, lessons management and after action review | The State Government to explore options for streamlining the functions and the independence of the State Emergency Management Committee Secretariat and the Office of Bushfire Risk Management with a view to including an inspectorate function, and appointing a person who is dedicated to that role. The purpose is to provide assurance and reporting, and to inquire into, monitor and report transparently on emergency management standards, preparedness, capability, service delivery and investment performance outcomes. Within two years of the establishment of this arrangement the State Government to review and assess whether it is meeting the desired outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1194 | 37 - Funding | The Committee recommends the State Fire Commission be fully reimbursed for the costs of the State Emergency Service transfer in years 2014 to 2017. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1188 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies commission a review into the efectiveness of aerial firefghting in the 2016 fires, in order to better understand and to document for future reference the cost-efectiveness of specifc fire suppression strategies and tactics in different vegetation types. The Review should include a comparative analysis of fire suppression options whether aerial or ground-based. |
REC287-1185 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies take steps at a national level to share learnings from the 2016 fires about the administration of interstate assistance and support the codifcation of the workings, structure and reporting lines of an Interstate and International Liaison Unit for future complex deployments within Australia and New Zealand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2079 | 26 - Research | Develop capacity to utilise the new high-resolution satellite products now available. |
REC286-1442 | 25 - Inquiry, audit, lessons management and after action review | Review legislation relating to Fuel Stove only areas, Fire Permit System and Total Fire Bans to ensure appropriate incentives to modify individuals’ behaviour. |
REC286-2091 | 37 - Funding | Investigate the costs and benefits in enhancing the current Tsunami detection buoy network. |
REC286-2048 | 26 - Research | Conduct research into changes of owners’ and occupiers stated and revealed risk tolerance and preference for treatment measures before and after natural hazard events. |
REC286-1438 | 25 - Inquiry, audit, lessons management and after action review | Consider outcomes of national review of warnings and review resilience of warning systems’ infrastructure. |
REC286-2045 | 26 - Research | Investigate the potential effectiveness of economic and financial mechanisms to manage the risk appetites of land owners. |
REC286-2070 | 25 - Inquiry, audit, lessons management and after action review | Test the Biosecurity Act 2015. |
REC286-1480 | 26 - Research | Deliver Flood Studies. |
REC286-2032 | 26 - Research | Quantify the effect of heatwaves on vulnerable people. |
REC286-2095 | 37 - Funding | Investigate the costs and benefits of delivering a public education and awareness program. |
REC286-2092 | 26 - Research | Investigate usefulness of satellite data for PPRR (prevention, preparedness, response, recovery) planning. |
REC286-1457 | 26 - Research | Improve understanding of how coastal inundation events interact with riverine flood events. |
REC286-2024 | 26 - Research | Improve knowledge and understanding of the effect heatwaves coinciding with other hazard events have on the effectiveness and capability of response and recovery capabilities |
REC286-2093 | 37 - Funding | Investigate the costs and benefits in enhancing the current Tsunami warning arrangements with signage and audible warning systems at key exposed locations (e.g. Port Arthur and Kingston Beach). |
REC286-2090 | 26 - Research | Increase understanding of the Puysegur Trench dynamics to improve certainty around the likelihood and magnitude of future Tsunamis. |
REC286-1456 | 26 - Research | Improve understanding of the weather systems that cause storm surge events to improve predictability and warnings. |
REC286-1460 | 25 - Inquiry, audit, lessons management and after action review | Review seismic monitoring network alert systems to ensure emergency managers are on the contact lists. |
REC286-2092 | 37 - Funding | Ensure sufficient investment in controls across the PPRR spectrum with a focus on Prevention and Mitigation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2524 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate why the level of multiple responses had increased. |
REC285-2520 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate whether the additional resources in the North and North West regions were effective in reducing average response times. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1142 | 18 - Access to fire ground | That SACFS consider the Traffic Management Procedures and guiding principles adopted in Tasmania as a model that could be implemented within SA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1121 | 18 - Access to fire ground | A Restricted Access Permit system for the entry/ re-entry of residents, based on the one developed for the Parkerville Stoneville Mt Helena Bushfire should be finalised. |
REC265-1102 | 25 - Inquiry, audit, lessons management and after action review | SEMC Secretariat Community Emergency Management Officers should work with the Shire to document the Shire of Mundaring’s learnings from the Parkerville Stoneville Mt Helena fire with a view to sharing this with other local authorities particularly those facing similar situations in order to extend the range of tools available to assist local governments to understand their roles and responsibilities in future emergencies. |
REC265-1122 | 18 - Access to fire ground | DFES, in consultation with bushfire volunteers should develop a procedure for the controlled entry and exit of volunteers to the fire ground |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2564 | 37 - Funding | Western Australia Health should collate and centrally monitor financial data including the cost to government of IHPT |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2563 | 37 - Funding | Western Australia Health should develop and agree with St John Ambulance a new funding model for emergency ambulance services focusing on standards, performance and allocation of risk |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0923 | 25 - Inquiry, audit, lessons management and after action review | That a process be established for the timely implementation of approved recommendations from the 2009 Victorian Bushfires Royal Commission. |
REC247-0932 | 37 - Funding | That the resources available to the Parks and Wildlife Service, to manage bushfire risk following the recent increase in land under its tenure, is reviewed. |
REC247-0921 | 26 - Research | That Tasmania Fire Service promotes a structured approach to research across Australia, to provide a shared understanding and the capacity to benchmark and judge performance. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0909 | 25 - Inquiry, audit, lessons management and after action review | That the plans for social recovery be reviewed, and plans and procedures are established ready for implementation. |
REC247-0866 | 26 - Research | That fire agencies continue to develop their predictive modelling capability for use in actively managing fires. |
REC247-0951 | 25 - Inquiry, audit, lessons management and after action review | That an independent means of monitoring and reporting on the implementation of approved recommendations is established. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
REC247-0903 | 25 - Inquiry, audit, lessons management and after action review | That the role of Red Cross in emergency management plans and procedures for the activation of Red Cross be reviewed. |
REC247-0849 | 26 - Research | That Tasmania Fire Service supports the relevant authorities to continue developing methodologies to forecast and simulate fire risk. |
REC247-0941 | 25 - Inquiry, audit, lessons management and after action review | That the Strategic Fuel Management Plan includes measurable targets and they are actively monitored and reported on to the community. |
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0873 | 25 - Inquiry, audit, lessons management and after action review | If it is considered more information is required on action to suppress the fires in Dunalley and why fire operations did not continue, the Department of Justice should conduct an independent examination of this matter. |
REC247-0927 | 25 - Inquiry, audit, lessons management and after action review | That an accountability process be established for managing improvement in the emergency management arrangements, including annual State of Readiness Reports by relevant departments and agencies and on the overall emergency management arrangements. |
REC247-0937 | 19 - Offences | That the legislation and enforcement arrangements are reviewed to ensure there are suitable offences and penalties, investigation and enforcement capabilities, and a rigorous approach is taken to breaches of the law. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0926 | 25 - Inquiry, audit, lessons management and after action review | That membership of the State Emergency Management Committee, and other processes to link in appropriate agencies and organisations to emergency management, be included in the recommended review of the emergency management arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0788 | 25 - Inquiry, audit, lessons management and after action review | TFS seek to address the following outstanding items from the recommendations of the Victorian Bushfires Royal Commission. § 45 out of 53 Community Bushfire Response Plans for “at risk” communities have been finalized. The remaining eight should be completed as a priority action. § That TFS progress the development of Community Bushfire Mitigation Plans for the 53 at risk communities, possibly as an action for reactivated Fire Management Area Committees. § TFS, together with other ESOs and local government, should develop a common comprehensive approach to the option of planned evacuation from dangerous or potentially dangerous areas to safer areas and eventual return. § TFS should include factors for consideration for evacuation during a bushfire into their training doctrine for Incident Controllers. § The IAP Template and its application be reinforced as an important operational requirement for IMT’s during the 2013-14 pre-season briefing program. 10 § That TFS review their use of IRMS to ascertain if either its full potential is not being realized through a lack of operator training or it is in fact not providing the required functionality and there is a need to research an improved resource management system which enhances interoperability. § The TFS Publication: Guidelines for Development in Bushfire Prone Areas of Tasmania http://www.fire.tas.gov.au/userfiles/stuartp/file/Publications/BushDeve… s2012.pdf requires an update to reflect the provisions of Planning Directive #5 Bushfire-Prone Areas Code. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2592 | 37 - Funding | That duplication of infrastructure be costed and taken into account when considering whether to proceed with the Whole of Government network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2600 | 25 - Inquiry, audit, lessons management and after action review | An external audit of shared services performed by SAFECOM and services now provided by the three ESOs which have the potential to be shared, be undertaken to determine the most efficient and cost effective way such services can be delivered to the sector. The three ESO Chiefs need to have input into this process. |
REC244-2631 | 25 - Inquiry, audit, lessons management and after action review | Review Section 134 to ensure that it is not a deterrent to a group of farm fire units operating at an incident. |
REC244-2620 | 25 - Inquiry, audit, lessons management and after action review | Review employment conditions under the F&ES Act to align with those under the Public Sector Act unless there is a compelling reason to the contrary. |
REC244-2617 | 25 - Inquiry, audit, lessons management and after action review | When judging major incidents in the future, consideration be given to Eburn and Dover’s proposal to establish processes with a statutory basis that sufficiently balance the community’s interests in ensuring that true lessons, including lessons of error or neglect, are identified, whilst also protecting members of the emergency services. Processes need to be developed for emergency services such as those used in aviation and medicine, to facilitate open and honest disclosure of errors. |
REC244-2601 | 25 - Inquiry, audit, lessons management and after action review | That an independent review of the operational and geographic boundaries of the ESOs be conducted recognising the limitations of the current governance structures to adequately address such issues. Such a review needs to be performed periodically, but not less than every 8 years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0838 | 37 - Funding | That the Government cease drawing from South Australia Police or other Community safety and emergency service budgets to fund the Directorate and instead merge its work and functions with the pre-existing South Australia Fire and Emergency Services Commission for zero total State and other Community safety and emergency service budget impact. |
REC243-0835 | 37 - Funding | That the Government increase the budgets of all emergency services and community safety organisations, including: i. seeking Federal funding where appropriate (and assisting at no cost volunteer organisations with the grants application process); and ii. considering, with full public and cost benefit analysis, reviewing the effectiveness and efficiency of the Emergency Services Levy; and iii. consider including St John Ambulance Australia SA Ltd in the bodies to benefit from the Emergency services Levy if the funding of other Community Safety and Emergency services providers is improved in line with this recommendation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2643 | 25 - Inquiry, audit, lessons management and after action review | That the Government consult broadly upon and review impediments to volunteering in the community and establish a taskforce to assist in removing barriers to volunteering, particularly with respect to: |
REC242-2650 | 37 - Funding | That the Government resume funding for the helicopter surveillance service rather than by fixed-wing aircraft along Adelaide, South Coast and other high-risk coastlines during summer recreational periods for monitoring shark and other rescue situations, to bring the State back into line with interstate best practice. |
REC242-2648 | 37 - Funding | That the Government adequately fund Community Safety and Emergency Services budgets so that fire-bombing aircraft are available on call for rapid deployment throughout Autumn and Spring at short notice to bomb fires at the earliest and safest possible opportunity. |
REC242-2640 | 37 - Funding | That the Government cease drawing from South Australia Police or other Community safety and emergency service budgets to fund the Directorate and instead merge its work and functions with the pre-existing South Australia Fire and Emergency Services Commission for zero total State and other Community safety and emergency service budget impact. |
REC242-2637 | 37 - Funding | That the Government increase the budgets of all emergency services and community safety organisations, including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0545 | 26 - Research | Improved understanding of fire behaviour in coastal heathlands would support sound risk management through the southwest of W |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0540 | 25 - Inquiry, audit, lessons management and after action review | : In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0523 | 25 - Inquiry, audit, lessons management and after action review | The Government consider enacting legislation to facilitate the review of all future major incidents, including but not limited to fire, earthquake, storm and marine inundation, and the emergency response to them. |
REC223-0522 | 25 - Inquiry, audit, lessons management and after action review | The response operation to the Margaret River bushfire in November 2011 be the subject of a review with independent oversight. |
REC223-0516 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Conservation review its implementation of the findings of the Ferguson Review conducted in 2010. |
REC223-0517 | 26 - Research | The Department of Environment and Conservation be supported to conduct further research into the fuel management of coastal heath in the south west of Western Australia exploring alternatives to burning as well as best practice for burning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1869 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments include provisions for regular external audits of invoices for payment in their next round of Employee Assistance Program contract negotiations. |
REC222-1862 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services request the State Emergency Management Committee to review by June 2013 the sharing of data between the State’s emergency response agencies using the WebEOC software and any further enhancements that can be made to this process. |
REC222-1847 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments undertake a formal review by 30 June 2013 of the welfare services addressing stress and trauma provided to both their career and volunteer members. |
REC222-1856 | 37 - Funding | The Ministers for Emergency Services, Environment and Police provide additional funds in the 2013-14 Budget so that the State’s emergency response agencies can implement a Psychological First Aid approach to preparing staff to deal with critical incidents and disasters, as is used in other Australian jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC221-2860 | 19 - Offences | Housing should ensure it has sound systems, processes and controls in place that minimise the opportunity for fraud and gives it the best chance of detecting it by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1916 | 25 - Inquiry, audit, lessons management and after action review | Local Emergency Management Committee (LEMC) processes should be reviewed to ensure that: |
REC204-1913 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Attorney General consider conducting a review of the Civil Liability Act 2002 (WA) in light of the 2011 Kimberley Ultramarathon. Such a review should consider issues such as the effectiveness given to competitor waivers under the Act and the potential difficulties of establishing proceedings and enforcing a judgement against foreign‐based providers of recreational activities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0291 | 18 - Access to fire ground | Local knowledge should be accessed to inform the placement and operation of VCPs. |
REC203-0290 | 18 - Access to fire ground | VCPs are one of the instruments by which the Incident Controller manages the emergency. VCPs without communications cannot be fully effective in their role. Determine and implement an appropriate communications platform for emergency management |
REC203-0289 | 18 - Access to fire ground | There needs to be a better appreciation of the role of Vehicle Control Points (VCPs) and how they are managed in bushfire emergencies by all key agencies and the community |
REC203-0292 | 18 - Access to fire ground | There is a need for community education on how road-blocks and VCPs operate in the event of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0493 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services report to Parliament every six months on the progress made in completing all of the outstanding Recommendations of the Keelty Report. |
REC202-0497 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Local Government have urgent discussions with the Western Australian Local Government Association (WALGA) as to why they are not supporting the full Recommendations addressed to local government in the Keelty Report. The Minister ensure that by May 2012 WALGA and its member councils have the resources to fully implement theimplementation of the Recommendations. |
REC202-0495 | 25 - Inquiry, audit, lessons management and after action review | At the conclusion to the 2011-12 bushfire season, the Minister for Emergency Services institute a thorough review of the operations of FESA, the Police and DEC in protecting the State from bushfires and other natural disasters, with a primary focus on: · staffing levels; · equipment levels and coordination; and · training needs. The Minister report to Parliament by June 2012 on any changes that need to be made to the current departmental structures to optimise the State’s preparedness for the 2012-13 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0392 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry’s Recommendations in two years. |
REC200-1697 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-0384 | 25 - Inquiry, audit, lessons management and after action review | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-1732 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry's recommendations in two years. |
REC200-0361 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. This session should include open discussion and explain the decisions of all parties – including how the incident controllers determined priorities, and why residents chose not follow their advice to evacuate. The learning outcomes should be promulgated across all agencies and incorporated in future level 3 incident controller training programs. |
REC200-0369 | 18 - Access to fire ground | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
REC200-0385 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-1725 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-1701 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. |
REC200-0357 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0221 | 37 - Funding | Funding be sought to enable the State Fire Management Council to take a greater coordination role for bushfire risk management and mitigation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC192-1922 | 37 - Funding | The Committee recommends the provision of substantial funds to improve road infrastructure in the Mitcham Hills to be spent over the 2010/11, 2011/12, 2012/13 and 2013/14 budgets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0105 | 19 - Offences | That the Department of the Attorney General, in consultation with FESA and Western Australia Police (WAPOL), consider options for legislative amendments to extend criminal liability to all damage, injury or death directly caused by arson. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0016 | 18 - Access to fire ground | Full briefings of traffic management personnel should be provided prior to dispatch to work areas – why road closed, what their authority level is, level of current risk etc |
REC172-0014 | 18 - Access to fire ground | The Interagency Guidelines for Road closure needs to be reviewed to incorporate a mechanism to identify bone-fide local landholders to facilitate their movement in and out of cordoned areas in sympathy with the Stay and Defend requirements. |
REC172-0013 | 18 - Access to fire ground | In preparing traffic management plans consideration should be given to which VCP’s are critical and need to be resourced with uniformed Police Officers and which VCP’s can be manned with civilian contractors. |
REC172-0012 | 18 - Access to fire ground | Main Roads Western Australia, Police and LGA’s be encouraged via State emergency arrangements to establish a distributed cache of “hard” road barriers for deployment to major incidents |
REC172-0039 | 18 - Access to fire ground | Dedicated information packages should be made available to personnel operating Vehicle Control Points at the shift briefing. |
REC172-0011 | 18 - Access to fire ground | At Level 3 incidents the position of ‘Traffic Operations Officer’ –be established and filled by a WAPOL officer. A role description for this position is required and should be included in the “Guidelines for the Operations of Road Closures During Bushfires 2008”. This officer is to be supported by a suitably qualified officer from MRWA that is capable of developing Traffic Management Plans that address risk and are cognisant of considerations associated with road type, appropriate speed limitations, signage requirements, traffic volumes, detours for local traffic and heavy haulage etc. This role should report to the IC and have strong links to the Operations Section, Planning Section (particularly the Situation Unit) and the Information Unit. |
REC172-0017 | 18 - Access to fire ground | Information packs to be provided to road traffic personnel to assist with enquiries by public or provision to members of public and landholders who are defending homes/stock etc |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0062 | 25 - Inquiry, audit, lessons management and after action review | Agencies should: annually assess their capability to respond to emergencies and take measures to address any shortfalls |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3009 | 25 - Inquiry, audit, lessons management and after action review | That the Tasmania Fire Service conduct an audit of all shopping centres to ensure that there exists within those centres adequate fire protection and evacuation systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1775 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to identify the effects of continuous cropping, minimum tillage, direct drilling seeding practices and of the retention of cropping stubble, in respect of bushfire risk and prevention. |
REC153-1776 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to establish means by which risk of bushfires, as created by continuous cropping, minimum tillage, direct drilling seeding practices and the retention of cropping stubble across the landscape, can be minimised. |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3092 | 19 - Offences | Expiation fees be reviewed so as to be consistent with the seriousness of the offences. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3576 | 37 - Funding | That Fire and Emergency Services Authority of Western Australia and Main Roads Western Australia, in consultation with the Western Australian Local Government Association, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs. In particular consideration should be given to regulations applying in the eastern states i.e. Queensland. |
REC143-3589 | 37 - Funding | That consideration be given to the establishment of a ‘Heritage Reserve Fund’ that might underwrite urgent initial repairs to private heritage listed properties. |
REC143-3586 | 37 - Funding | That the ‘opportunity cost’ for Local Authorities in meeting the 25% contribution to the restoration of eligible public assets damaged by a natural disaster event be considered when FESA and Main Roads Western Australia, in consultation with Western Australian Local Government Authority, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs as recommended in Recommendation 1. |
REC143-3582 | 37 - Funding | That the Department of Treasury and Finance, in consultation with FESA, consider alternative funding arrangements to alleviate the need for FESA to ‘underwrite’ NDRA costs during the year. |
REC143-3581 | 37 - Funding | That, in tandem with their consideration of local government cost sharing arrangements under WANDRA (refer Recommendation 1), the Fire and Emergency Services Authority and Main Roads Western Australia also establish ‘exceptional circumstances’ criteria to provide for additional assistance to local government where it may be warranted in order to avoid undue financial pressure caused by delays to secure reimbursement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3552 | 37 - Funding | Department of Health and Human Services (DHHS) to fund 3 Full-Time Equivalent (FTE) Senior Registrar positions at the Royal Hobart Hospital (RHH) for the Tasmanian Medical Retrieval Service (TMRS). One registrar in the Anaesthesia Department, one in the Intensive Care Unit and one in Emergency Department is proposed. |
REC140-3568 | 37 - Funding | The State Medical Retrieval Cost Centre (TMRS and NETS) be formed and be supported by the appropriate administrative and resource accountant expertise. This cost centre should be placed with those responsible for its management. |
REC140-3567 | 37 - Funding | A uniform retrieval charge to the region of referral should be considered. This should be independent of the mode of transport used. |
REC140-3554 | 37 - Funding | DHHS fund the equivalent of 2 FTE Consultant positions for retrieval duties (1.5 FTE existing, 0.5 FTE new) |
REC140-3553 | 37 - Funding | RHH Neonatal Emergency Transport Service receive DHHS funding for a Senior Registrar to assume the responsibilities of retrieval staffing, quality assurance, data collection and reporting demands. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3778 | 37 - Funding | The Committee recommends that government consider options for assistance (including cost sharing) for farmers to fence native vegetation areas on private property affected by the Wangary fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4139 | 19 - Offences | Local authorities prosecute in all cases of deliberate breaches of the provisions of the Bush Fires Act and thay failing this the Bush Fires Board take appropriate action to initiate such prosecutions. |
REC019-4145 | 37 - Funding | A fund be established to subsidise the purchase of equipment for bush fire brigades but that the granting of subsidies depend upon a certificate being received from the Bush Fires Board that the brigade in question is of a standard that will be available at all times for effective use and that adequate facilities are available for its storage and maintenance at a centre suitable for the brigade. |
REC019-4156 | 26 - Research | A fire control research advisory committee be formed to co-operate with the Forests Department in carrying out scientific research into fire control. |
REC019-4151 | 26 - Research | The Forests Department carry out more research into both the technical and practical side of fire control as a necessary accompaniment to the expenditure of money on other forest works and that forest fire control officers be sent overseas at intervals to gain information regarding the latest developments in this work. |
REC019-4157 | 18 - Access to fire ground | Local authorities and if necessary the Minister take active steps to enforce the removal of fire hazards from the vicinity of buildings in rural areas and that special attention be given to the removal of dead trees on the edges of pasture land and on firebreaks in timbered country. |