Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
REC316-4046 | 33 - Relief and recovery | Emergency Plan and Recovery sub-plans should be amended to better define recovery mechanisms and responsibilities, including hand over points to recovery authorities and community engagement for the delivery of long term recovery mechanisms. |
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1249 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Premier and Cabinet to conduct an independent review of the current arrangement for the management and distribution of the Emergency Services Levy. The review will have the specific purpose of: · seeking input from key entities including the Departments of Treasury, Finance, Fire and Emergency Services, Lands, and Parks and Wildlife, WA Local Government Association, and the Office of Bushfire Risk Management. · ensuring the arrangement has the flexibility and agility to deal with emerging bushfire risk priorities. · establishing a budget process that enables a shift in investment towards prevention, mitigation and building community resilience and capability. |
REC291-1248 | 24 - Govt responsibility | The State Emergency Management Committee to establish a State Bushfire Coordinating Committee as a sub-committee of SEMC. The State Bushfire Coordinating Committee will be chaired by the Director of the Office of Bushfire Risk Management and will have the primary responsibility to: · develop a State Bushfire Management Policy and a set of long term bushfire risk management objectives; · provide a forum for key bushfire risk management stakeholder agencies; · advise the SEMC on matters pertaining to bushfire, in particular, to report against the investment in, and achievement of the bushfire risk management objectives; · provide advice and support to the proposed Chief Officer of the Rural Fire Service on bushfire risk management matters; and · report to SEMC and to the community on bushfire risk management matters on at least an annual basis. |
REC291-1233 | 25 - Inquiry, audit, lessons management and after action review | The State Government to explore options for streamlining the functions and the independence of the State Emergency Management Committee Secretariat and the Office of Bushfire Risk Management with a view to including an inspectorate function, and appointing a person who is dedicated to that role. The purpose is to provide assurance and reporting, and to inquire into, monitor and report transparently on emergency management standards, preparedness, capability, service delivery and investment performance outcomes. Within two years of the establishment of this arrangement the State Government to review and assess whether it is meeting the desired outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1219 | 17 - Assets and technology | Live resource tracking system that can be used by all response agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1112 | 17 - Assets and technology | Radio infrastructure in the Perth Hills should be reviewed to assess whether it is practicable for radio and/or mobile phone coverage to be improved to achieve better coverage across the area. |
REC265-1125 | 33 - Relief and recovery | Consultation with the Board of the Lord Mayor’s Distress Relief Fund and other disaster appeal organisers should be undertaken to determine the potential for software development to consolidate the application and approval process, including provision of templates and application forms; |
REC265-1102 | 25 - Inquiry, audit, lessons management and after action review | SEMC Secretariat Community Emergency Management Officers should work with the Shire to document the Shire of Mundaring’s learnings from the Parkerville Stoneville Mt Helena fire with a view to sharing this with other local authorities particularly those facing similar situations in order to extend the range of tools available to assist local governments to understand their roles and responsibilities in future emergencies. |
REC265-1123 | 17 - Assets and technology | Every effort should be made to enhance the ability of communications personnel to cope with fast moving and time critical fire events by providing and maintaining: ongoing extensive communications training; advanced vehicle capability for clear communication within areas of radio coverage dead spots; ability to receive Air intelligence live streaming; map production facilities; deployment of multiple Incident Control Vehicles when required; all Incident Control Vehicles with access to DFES Information Technology Systems. |
REC265-1119 | 24 - Govt responsibility | Relevant policies and Westplans should be amended to require that full consultation occurs between the Controlling Agency and the Department for Child Protection and Family Support regarding the location of the evacuation centre(s) in a bushfire incident. |
REC265-1117 | 17 - Assets and technology | Automatic Vehicle Location technology should be adopted to enable a better appreciation of the deployment and location of appliances at an incident, in order to increase situational awareness |
REC265-1127 | 33 - Relief and recovery | Consultation should be undertaken with agencies and organisations that are engaged in emergency welfare provision to identify more effective ways to provide a consistent message to the community that non-cash donations are not required. |
REC265-1116 | 17 - Assets and technology | Procedures should be established to monitor the use of heavy plant during a bushfire incident, including the tasking of support appliances. Procedures should provide for the appointment of a dedicated Machinery Supervisor as prescribed within the Australasian Interservice Incident Management System. |
REC265-1126 | 33 - Relief and recovery | Development of a template contract for the clean-up of affected properties to speed-up the process; |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1582 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1614 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the ACT Bushfire Council, should conduct a review of the ACT Bushfire Council against its recently developed terms of reference (July 2013) within two years. |
REC228-1610 | 24 - Govt responsibility | The Emergency Services Agency should annually review fire management zones and the Territory and Municipal Services Directorate should subsequently update the Regional Fire Management Plans. |
REC228-1609 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency should undertake audits to meet the requirements in the Strategic Bushfire Management Plan for the preparation, sharing and publication of annual progress reports. Annual progress reports should be made available to the ACT Bushfire Council. |
REC228-1620 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the Territory and Municipal Services Directorate, should review the Farm FireWise Program, including: |
REC228-1605 | 24 - Govt responsibility | The Justice and Community Safety Directorate should continue to review its strategic and accountability indicators and the Territory and Municipal Services Directorate should commence a review of its strategic and accountability indicators. The directorates should consult to develop complementary measures which better assess their bushfire management activities. |
REC228-1619 | 1 - Land-use and building regs | The Territory and Municipal Services Directorate, in consultation with the Emergency Services Agency, should improve its management of Land Management Agreements, with respect to rural leaseholders’ fire management responsibilities, by: |
REC228-1618 | 24 - Govt responsibility | The Emergency Services Agency, the Environment and Sustainable Development Directorate and the Territory and Municipal Services Directorate should strengthen across-Government delivery of major projects in the Strategic Bushfire Management Plan and Regional Fire Management Plans by collectively: |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2846 | 17 - Assets and technology | I recommend that Border Protection Command continues to examine ways of improving its surveillance capability around Christmas Island so that the risk of SIEVs arriving undetected is reduced. |
REC227-2858 | 13 - Mapping and data quality | I recommend that the Commonwealth prioritise completion of a hydrographic survey of Christmas Island and ensure that such a survey is completed in the near future. |
REC227-2851 | 17 - Assets and technology | I recommend that consideration should be given to acquiring two personal water craft for deployment by appropriately trained and equipped staff of the AFP or the VMRS or both on Christmas Island. |
REC227-2850 | 17 - Assets and technology | I recommend that the AFP be provided with a search and rescue vessel which is suitable to the specific conditions of Christmas Island. I further recommend that steps be taken to ensure that if for any reason the search and rescue vessel is not available, there is a replacement vessel on Christmas Island capable of providing an emergency response in difficult sea conditions. |
REC227-2848 | 17 - Assets and technology | I recommend that the AFP take steps to determine whether access can be obtained to the National Search and Rescue Council endorsed SARMAP program covering the Australian Search and Rescue Region as well as adjoining tiles for Indonesia. Steps should be taken to ensure that if possible coverage would include high traffic areas where SIEVs enter the Australian Search and Rescue region allowing timely search and rescue plans to be drawn up for any potential incidents. |
REC227-2859 | 17 - Assets and technology | I recommend that the issue of RHIB jet intake protection be allocated a high priority and that there be ongoing investigation of possible solutions to reduce the problem. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0546 | 13 - Mapping and data quality | Maps prepared for prescribed burns should address the fuel type and burn history of the burn area as well as surrounding areas. Predicted rates of spread under prescribed and other conditions should recognise the complexity of coastal heathlands. |
REC226-0581 | 24 - Govt responsibility | Increased acceptance of mutual obligations will be fundamental to the management of fire risk across the state |
REC226-0596 | 33 - Relief and recovery | An early decision on relief funding enables timely responses. D CP should review their communication of relief arrangements to ensure that they are clear. |
REC226-0545 | 26 - Research | Improved understanding of fire behaviour in coastal heathlands would support sound risk management through the southwest of W |
REC226-0576 | 13 - Mapping and data quality | Better maps are required for urban/rural interface fires |
REC226-0595 | 33 - Relief and recovery | Shire experiences in managing these traumatic events should be captured and passed into emergency management procedures. |
REC226-0571 | 24 - Govt responsibility | A review of the manner in which resourcing is conducted across all agencies needs to occur with a review identifying the best manner to ensure all agencies adapt to the same process. |
REC226-0594 | 33 - Relief and recovery | Procedures to resolve issues surrounding financial assistance need to be reviewed to ensure they are as smooth, fast and transparent as possible possible. Review and streamline current financial relief procedures. |
REC226-0568 | 24 - Govt responsibility | State-wide all agency reporting should be established to facilitate the interactions of emergency management agencies, support agencies and governments. |
REC226-0583 | 17 - Assets and technology | The state should converge on a single communications platform for all emergency management and support agencies. |
REC226-0547 | 13 - Mapping and data quality | Fuel loads on private property need to be identified and included in understanding fire behaviour in determine the contribution they make to the burn risk assessment. |
REC226-0582 | 17 - Assets and technology | The state should progressively align on a shared platform, such as WebEOC, to establish a COP [Common Operating Picture or Platform?]. |
REC226-0598 | 33 - Relief and recovery | When communities are grieving there is a need to provide special forms of support to affected residents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0540 | 25 - Inquiry, audit, lessons management and after action review | : In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
REC225-0533 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1630 | 13 - Mapping and data quality | The Minister for Emergency Services ensure that a Statewide fuel load database that includes data from Western Power, the Department of Fire and Emergency Services and the Department of Environment and Conservation be established before the 2013-14 bushfire season. |
REC224-1629 | 24 - Govt responsibility | The Minister for Emergency Services must ensure that future post-incident analyses are completed and made public within eight weeks of a natural disaster. |
REC224-1631 | 24 - Govt responsibility | The State Government prepare a strategy before the 2013-14 bushfire season on how the main firefighting agencies should deal with a drier South West region where fewer prescribed burns can be completed each year. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0517 | 26 - Research | The Department of Environment and Conservation be supported to conduct further research into the fuel management of coastal heath in the south west of Western Australia exploring alternatives to burning as well as best practice for burning. |
REC223-0516 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Conservation review its implementation of the findings of the Ferguson Review conducted in 2010. |
REC223-0523 | 25 - Inquiry, audit, lessons management and after action review | The Government consider enacting legislation to facilitate the review of all future major incidents, including but not limited to fire, earthquake, storm and marine inundation, and the emergency response to them. |
REC223-0522 | 25 - Inquiry, audit, lessons management and after action review | The response operation to the Margaret River bushfire in November 2011 be the subject of a review with independent oversight. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1869 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments include provisions for regular external audits of invoices for payment in their next round of Employee Assistance Program contract negotiations. |
REC222-1862 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services request the State Emergency Management Committee to review by June 2013 the sharing of data between the State’s emergency response agencies using the WebEOC software and any further enhancements that can be made to this process. |
REC222-1847 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments undertake a formal review by 30 June 2013 of the welfare services addressing stress and trauma provided to both their career and volunteer members. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1913 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Attorney General consider conducting a review of the Civil Liability Act 2002 (WA) in light of the 2011 Kimberley Ultramarathon. Such a review should consider issues such as the effectiveness given to competitor waivers under the Act and the potential difficulties of establishing proceedings and enforcing a judgement against foreign‐based providers of recreational activities. |
REC204-1911 | 24 - Govt responsibility | As part of the review of its due diligence processes, Tourism WA should ensure that: |
REC204-1919 | 1 - Land-use and building regs | Tourism WA must give specific regard as to whether land use approvals need to be sought, particularly from Department of Regional Development and Lands, when conducting due diligence for event sponsorship proposals that require sign off by both departments. |
REC204-1909 | 35 - Business and Industry in relation to industry | Eventscorp should ensure that organisers of events its sponsors are directed to all appropriate authorities and stakeholders to ensure the responsible, safe and efficient planning and conduct of the event. |
REC204-1918 | 1 - Land-use and building regs | Department of Regional Development and Lands and Department of Environment and Conservation should consider how their respective land use approval processes can incorporate the input of Local Emergency Management Committees (LEMCs) as part of risk assessments for high risk events and adventure sport activities. |
REC204-1916 | 25 - Inquiry, audit, lessons management and after action review | Local Emergency Management Committee (LEMC) processes should be reviewed to ensure that: |
REC204-1915 | 24 - Govt responsibility | The Department of Regional Development and Lands should ensure that event organisers and government agencies responsible for sponsoring and approving events have a greater level of awareness about the requirements of section 91 licences under the Land Administration Act 1977 (WA). |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0308 | 33 - Relief and recovery | Early resolution and clear communication of the financial and other support measures that will be available to affected residents is an important contributor to community resilience. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0493 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services report to Parliament every six months on the progress made in completing all of the outstanding Recommendations of the Keelty Report. |
REC202-0500 | 24 - Govt responsibility | In implementing the Keelty Report’s Recommendation 42, the Ministers for Emergency Services and Environment jointly report to Parliament by May 2012 on the likely impacts on, and implications for, the future bushfire operations of the State Government of the drying climate in the State’s South West region. |
REC202-0498 | 24 - Govt responsibility | The Minister for Planning report to Parliament by May 2012 on the urgent actions undertaken by the Department of Planning and the Western Australian Planning Commission (WAPC) to transfer responsibility for declaring bushfire prone areas to the WAPC. |
REC202-0497 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Local Government have urgent discussions with the Western Australian Local Government Association (WALGA) as to why they are not supporting the full Recommendations addressed to local government in the Keelty Report. The Minister ensure that by May 2012 WALGA and its member councils have the resources to fully implement theimplementation of the Recommendations. |
REC202-0507 | 13 - Mapping and data quality | The Minister for Emergency Services, with advice from the Interagency Bushfire Management Committee Fuel Load Management sub-committee, report to Parliament by May 2012 on the estimated cost of developing one fuel load information system across all lands in Western Australia, no matter who manages it. This system’s information should be readily accessible and easily understood by all stakeholders, including the public. |
REC202-0496 | 17 - Assets and technology | The Minister for Emergency Services ensure that a whole-of-government equipment register of the firefighting equipment held by FESA, DEC and local government authorities is in place for the 2012-13 bushfire season. |
REC202-0506 | 17 - Assets and technology | The Minister for Emergency Services ensure that FESA has the funds to implement the installation and use of WebEOC for use during the 2011-12 bushfire season and immediately put in place common protocols with the Police and DEC to record significant events during a bushfire. |
REC202-0495 | 25 - Inquiry, audit, lessons management and after action review | At the conclusion to the 2011-12 bushfire season, the Minister for Emergency Services institute a thorough review of the operations of FESA, the Police and DEC in protecting the State from bushfires and other natural disasters, with a primary focus on: · staffing levels; · equipment levels and coordination; and · training needs. The Minister report to Parliament by June 2012 on any changes that need to be made to the current departmental structures to optimise the State’s preparedness for the 2012-13 bushfire season. |
REC202-0503 | 24 - Govt responsibility | The Minister for Police and Emergency Services and the Minister for the Environment report to Parliament by December each year as to the state of readiness of the main State Government agencies tasked with fighting bushfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0249 | 17 - Assets and technology | FRS fire appliance allocation and training needs to be reviewed to enhance offensive bushfire capability within the metropolitan area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0355 | 13 - Mapping and data quality | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-1699 | 24 - Govt responsibility | The State Government ensure that the continued development of the Fire and Emergency Service Authority's Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost-effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-0364 | 17 - Assets and technology | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-1718 | 35 - Business and Industry in relation to industry | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-0378 | 17 - Assets and technology | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-1732 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry's recommendations in two years. |
REC200-0352 | 13 - Mapping and data quality | The Fire and Emergency Services Authority and local governments ensure that the ability to: measure and map fuel loads maintain fuel load databases draw up prescriptions for, and oversee controlled burns are included as key competencies in any future recruitment of Chief Bushfire Control Officers and Community and Emergency Services Managers. |
REC200-0392 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry’s Recommendations in two years. |
REC200-1697 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-0361 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. This session should include open discussion and explain the decisions of all parties – including how the incident controllers determined priorities, and why residents chose not follow their advice to evacuate. The learning outcomes should be promulgated across all agencies and incorporated in future level 3 incident controller training programs. |
REC200-1717 | 24 - Govt responsibility | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-0377 | 1 - Land-use and building regs | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-1728 | 24 - Govt responsibility | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-0346 | 1 - Land-use and building regs | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-0388 | 17 - Assets and technology | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-1694 | 24 - Govt responsibility | The State Government give its full support to the Western Australian Local Government Association's Send to Solve initiative. |
REC200-0359 | 13 - Mapping and data quality | The State Government ensure that the continued development of the Fire and Emergency Service Authority’s Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-1716 | 24 - Govt responsibility | State and locals governments: |
REC200-0376 | 1 - Land-use and building regs | State and locals governments: a) recognise that regardless of future declarations of bushfire prone areas, the existing planning and building problems in the Perth Hills related to bushfire risk will persist; b) urge residents in these areas to retrofit their homes and evaporative air conditioners in compliance with AS 3959 - 2009; c) examine options to retrospectively bring these areas into compliance with Planning for Bushfire Protection Guidelines. |
REC200-1727 | 24 - Govt responsibility | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-0340 | 1 - Land-use and building regs | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-0387 | 17 - Assets and technology | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the Recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-1682 | 24 - Govt responsibility | The State Government give legislative effect to the Planning for Bush Fire Protection Guidelines. |
REC200-0358 | 13 - Mapping and data quality | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. The system should enable public access to allow members of the community to access information about the fuel load in a given locality. |
REC200-1707 | 1 - Land-use and building regs | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0373 | 33 - Relief and recovery | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-1723 | 24 - Govt responsibility | The State Government restructure the Fire and Emergency Services Authority as a Department. As part of this restructure, Emergency Management Western Australia should either |
REC200-0384 | 25 - Inquiry, audit, lessons management and after action review | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-1681 | 24 - Govt responsibility | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-0357 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-1701 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. |
REC200-0365 | 17 - Assets and technology | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA’s own policy of ‘Use of Private Vehicles in Fires’. |
REC200-1719 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-0379 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0109 | 1 - Land-use and building regs | It is sensible that, in considering planning development proposals on land adjacent to the DEC estate, that development authorities invite comment from DEC on the fire management consequences of development proposals. |
REC183-0120 | 17 - Assets and technology | Maintaining the DEC fleet of tankers, bulldozers and low loaders is crucial to DEC’s fire management and control capability. |
REC183-0119 | 17 - Assets and technology | The development of a three year aerial firefighting strategy for W.A. would ensure optimal development of a joint air capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0135 | 33 - Relief and recovery | FESA revises its standard operating procedures to provide guidance on the format and timing of post-incident community meetings. |
REC182-0134 | 17 - Assets and technology | FESA reviews its air reconnaissance capability and determines if multiple multi-sensor air reconnaissance aircraft or unmanned aerial vehicles are required for managing concurrent and/or complex incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0104 | 1 - Land-use and building regs | That FESA assess the cost and other implications of proposed changes to bushfire prone zone declarations which would allow the whole State to be declared bushfire prone. |
REC173-0103 | 24 - Govt responsibility | That the Minister for Emergency Services consider the appointment of the Chief Executive Officer, Department of Environment and Conservation as a member of the State Emergency Management Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0028 | 17 - Assets and technology | Ensure the S61 helicopter has all appropriate channels for water bombing operations throughout the State by including this requirement on a pre-deployment checklist. |
REC172-0029 | 17 - Assets and technology | Provide a photocopier in the Mobile Communications Facility or the mobile equipment cache that is capable of large volume production of collated documents. |
REC172-0027 | 13 - Mapping and data quality | Add an ‘Aviation’ map to the standard set of incident maps. The standard for this map will need to be developed by subject matter experts from the Air Ops group. |
REC172-0026 | 17 - Assets and technology | At large incidents a communications bus should be provided for the use by Air Ops and a designated work space should be provided for the Air Ops management group. |
REC172-0047 | 17 - Assets and technology | There is an established need to develop mobile accommodation and accommodation facility support solutions that allows an acceptable standard of accommodation to be provided to fire fighters in close proximity to the incident. |
REC172-0025 | 17 - Assets and technology | Suppression resources should be ordered and mobilised as 2 truck Strike Teams with a STL and consistently deployed to the fire ground as a unit. |
REC172-0019 | 17 - Assets and technology | A centralised, regional, multi-agency resource coordination and tracking system/facility be established to accommodate and coordinate the movement of resources from all agencies within and between regions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0069 | 17 - Assets and technology | That in any consideration being given to the allocation of responsibility for control of operations in respect of major fires, consideration be given to the availability of technology and other resources, particularly when particular skills are required to make best use of such technology or resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0050 | 24 - Govt responsibility | SEMC and EM WA should: assess the state’s level of preparedness at least annually, identifying gaps and significant risks |
REC170-0049 | 24 - Govt responsibility | SEMC and EM WA should: formally and regularly assess which hazards the state should prepare for |
REC170-0062 | 25 - Inquiry, audit, lessons management and after action review | Agencies should: annually assess their capability to respond to emergencies and take measures to address any shortfalls |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3058 | 25 - Inquiry, audit, lessons management and after action review | ACTAS should improve patient care processes by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3388 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government re-investigate the suitability of the Fairbairn site as a proposed centralised accommodation facility for emergency services. |
REC144-3386 | 24 - Govt responsibility | The Committee considers that the ACT Government should table in the ACT Legislative Assembly the cost-benefit analysis and business plan for Fairbairn as a central site for emergency services in the ACT. |
REC144-3382 | 24 - Govt responsibility | The Committee recommends that responsibility for oversighting the progress of the implementation of agreed recommendations of the Coroner be undertaken by a truly independent body and not by the Bushfire Council. |
REC144-3393 | 1 - Land-use and building regs | The Committee recommends that the responsibility for land management issues lie within a single portfolio, specifically the Minister for Territory and Municipal Services. |
REC144-3379 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that a thorough review be undertaken of the communications and coordination between the separate agencies which make up the Emergency Services Agency, to assess the extent to which cultural factors are detrimental to the effective operation of the ESA. |
REC144-3390 | 24 - Govt responsibility | If the ACT Government decides to proceed with the site as the emergency services headquarters, that it accord a high priority to the finalisation of the site preparations for the ESA at Fairbairn as a matter of urgency. |
REC144-3389 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government make a public announcement about the future accommodation plans for the Emergency Services Agency and its component parts so that both the ESA and the ACT public are informed about current proposals and timeframes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3583 | 33 - Relief and recovery | That the newly proposed index linked limits for Personal Hardship and Distress Relief Payments as outlined in the paper “National Disaster Relief Arrangements - An Analysis and Recommendations for Personal Hardship Distress Measures” be accepted by government. |
REC143-3580 | 17 - Assets and technology | That FESA investigate the use of new technologies such as Voice over Internet Protocol (VoIP) for supplementing the dissemination of WANDRA information in cases where landlines have been disrupted. |
REC143-3588 | 33 - Relief and recovery | That, in line with recommendations contained in the 2004 Report to the Council of Australian Governments, greater flexibility should be introduced to WANDRA to enable damaged infrastructure to be upgraded to a more resilient standard where that is both feasible and cost-effective. |
REC143-3585 | 33 - Relief and recovery | That the Professional Assistance Grant is formally extended by WANDRA to include non rural businesses and that it be made available to assist with the clean up of disaster related damage to farms and businesses. (The Committee recognises that the amendments to WANDRA as of March 2007 address this recommendation). |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1985 | 24 - Govt responsibility | That the Emergency Services Agency, with the suport of the ACT Government, seek to establish with the NSW Department of Environment and Conservation and the NSW Rural Fire Service a protocol that will provide for the establishment of a joint incident management team as part of unified control arrangements based on adoption of the following principles: |
REC126-1942 | 24 - Govt responsibility | That the ACT Attorney-General and the ACT Government - in consulation with the Chief Justice of the ACT and the ACT Chief Magistrate - take legislative action that would have the effect of funds being directly appropriated annually to the courts, preferable along the lines of the Commonwealth model as it applies to the High Court of Australia, the Federal Court of Australia, the Family Court of Australia and the Federal Magistrates Court. Alternatively, the funds could be appropriated in accordance with the South Australian model, which has a seperate Courts Administartion Authority. |
REC126-2009 | 24 - Govt responsibility | That a taskforce be established to give effect to the recommendations in this report |
REC126-1960 | 13 - Mapping and data quality | That an appropriate geographic information systems capability be maintained to enable the production of fire-specific maps as the need arises and that personnel from the Emergency Services Agency and other agencies be trained in the operation of map production systems, so that 9maps can be modified to include fire-specific information as required |
REC126-1984 | 24 - Govt responsibility | That the Emergency Services Agency, with the support of the ACT Government, develop a single, new memorandum of understanding with the NSW Department of Environment and Conservation and the NSW Rural Fire Service, providing for liaison and joint operations as soon as it becomes apparent to whichever jurisdiction is managing a fire that the fire will probably affect the other jurisdiction. Joint operations should not be limited to when an incident occurs on both sides of the border, as is the current arrangement |
REC126-2006 | 24 - Govt responsibility | I recommend that, as appropriate, the ACT cooperate with the Commonwealth in the implementation of the committee's recommendations and, in particular, give careful consideration to adoption of the following recommendations: |
REC126-1959 | 13 - Mapping and data quality | That the Emergency Services Agency introduce a program with land management agencies in the ACT to ensure that maps of all public and private land in the ACT are subjected to regular review and amendment as required. Maps of a scale sufficient to facilitate fire management operations should be available in printed form and maintained on an electronic database capable of modification to add relevant features during a firefighting operation |
REC126-1979 | 24 - Govt responsibility | That the policy and practice just recommended be the subject of a memorandum of understanding between the Emergency Services Agency and the Department of Territory and Municipal Services (previously the Department of Urban Services) or other relevant department or agency, so as to ensure that the land management agency on whose land a fire starts has responsibility to respond immediately to that fire in accordance with the applicable standards for weight of response. Further, the land management agency should be responsible for efforts to suppress fire until such time as it becomes clear that the suppression task is beyond capacity of the agency, at which point the ACT Rural Fire Service should assume direct responsibility for coordinating the ongoing response |
REC126-2004 | 35 - Business and Industry in relation to industry | That the ACT Government and ActewAGL jointly develop and implement protocols that will create a procedure whereby each of the water and sewerage, electricity and gas distribution networks, or parts thereof, can safely and promptly be manipulated, controlled, shut off, isolated or disconnected under emergency conditions. |
REC126-1952 | 25 - Inquiry, audit, lessons management and after action review | That regular periodic reviews be undertaken of changes made to the operational and management arrangements for dealing with wildfires and other emergencies in the ACT, to ensure that those arrangements continue to comply with the Australian Inter-Agency Incident Management System Incident Control System |
REC126-2012 | 24 - Govt responsibility | If they are willing and available to participate, that the taskforce's membership include Mr Phil Cheney, Mr Tony Bartlett, Mr Val Jeffery and Mr John Lowe |
REC126-1976 | 24 - Govt responsibility | That the Emergency Services Agency have authority over the land management agencies and other landholders in order to implement preparedness and prevention measures – including fuel-reduction works where there are failures in compliance |
REC126-2002 | 1 - Land-use and building regs | That consideration be given when building to the positioning of outbuildings around residential structures such that their potential impact on the main structure is reduced |
REC126-1948 | 24 - Govt responsibility | That the Emergency Services Agency be removed from the Department of Justice and Community Safety and transformed into an independent statutory authority reporting directly to the responsible Minister. Note in this regard that Mr McLeod made a similar recommendation, and I endorse it unequivocally. Placing the agency within a government department puts unnecessary layers of bureaucracy between the agency and the responsible Minister, and the bureaucrats concerned usually have no special knowledge of or experience in emergency management, regardless of their seniority in the bureaucracy |
REC126-2011 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the recommendations of the seven reviews of the Emergency Services Bureau carried out before the McLeod inquiry and ensure implementation of any of those recommendations that remain relevant but have not been implemented |
REC126-1970 | 35 - Business and Industry in relation to industry | That the Emergency Services Agency reconsider and revise the arrangement that exists between the ACT Fire Brigade and Canberra airport in relation to the provision of assistance |
REC126-2000 | 1 - Land-use and building regs | That the ACT Government consider taking measures to implement the provisions of Australian Standard 3959, Construction of Buildings in Bushfire Prone Areas, for the ACT urban area |
REC126-1947 | 25 - Inquiry, audit, lessons management and after action review | That the ACT Government commission a review of coroners’ jurisdiction in order to determine whether that jurisdiction ought to be limited or expanded and, if so, to what extend |
REC126-2010 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the extent to which the recommendations in the McLeod report have been implemented in order to ensure implementation of those not yet implemented |
REC126-1962 | 24 - Govt responsibility | That, because of the small jurisdiction of the ACT (equivalent to one fire district in NSW) the ACT Government consider all possible options for the provision of fire services to the ACT, among them: |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4156 | 26 - Research | A fire control research advisory committee be formed to co-operate with the Forests Department in carrying out scientific research into fire control. |
REC019-4153 | 17 - Assets and technology | No opportunity be lost by the Forests Department to improve the efficiency of their fire fighting gangs, radio and other equipment in the light of the latest practical and scientific developments. |
REC019-4151 | 26 - Research | The Forests Department carry out more research into both the technical and practical side of fire control as a necessary accompaniment to the expenditure of money on other forest works and that forest fire control officers be sent overseas at intervals to gain information regarding the latest developments in this work. |