Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2513 | 33 - Relief and recovery | Assessing the availability and skillsets of the resources needed to respond to a major disaster recovery event. |
REC313-2509 | 33 - Relief and recovery | Developing detailed recovery procedures. |
REC313-2516 | 33 - Relief and recovery | Documenting disaster recovery risks in agency risk registers, along with controls and treatment plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1278 | 20 - Role of police | That SA Police develop an evacuation plan for the Adelaide Central Business District (CBD) which includes: |
REC295-1298 | 12 - EM agency and authority | That the State Emergency Service, in consultation with key stakeholders, identify and implement a robust system and procedures for prioritising, allocating and coordinating multiple tasks. |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1325 | 12 - EM agency and authority | Review and reinstate the State Emergency Management Training Officer and State Emergency Management Planning Officer (capability development) positions to operate with a broad, strategic and leadership focus. |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
REC295-1322 | 12 - EM agency and authority | Consider opportunities to identify synergies between the incident management systems used in SA being the, Australasian Interservice Incident Management System (AIIMS) and ICCS Plus. This might include joint training and exercising in roles that are common across both systems. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1307 | 20 - Role of police | That, as with earthquake, SA Police be designated the Control Agency under the State Emergency Management Plan for black system events or other major power outages. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1304 | 20 - Role of police | That SA Police, as the control agency for search and rescue, and State Emergency Service who have the responsibility for providing search and rescue services under the State Emergency Management Plan, develop a swiftwater rescue capability plan that describes key swiftwater risk locations, roles and responsibilities of emergency services, State swiftwater resources and dispatch arrangements. |
REC295-1335 | 12 - EM agency and authority | Explore alternative emergency management models including the alternative model proposed above to establish a South Australian Emergency Management Office and State Relief and Recovery Office within the South Australian Fire and Emergency Services Commission, to ensure that all the objects and guiding principles of the Emergency Management Act 2004, and State Emergency Management Plan are addressed efficiently and effectively. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2522 | 12 - EM agency and authority | The report recommends that Ambulance Tasmania reinforce the requirement to record factors contributing to response time outliers and the remedial action undertaken to address the contributing factors. |
REC285-2519 | 12 - EM agency and authority | The report recommends that Ambulance Tasmania develop strategies to improve response times to those of other jurisdictions and undertake cost benefit analysis of those strategies before deciding on implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
Rec-ID | Code | Recommendation |
---|---|---|
REC279-1229 | 12 - EM agency and authority | Recruitment Guidelines and Resources: By April 2015, update its recruitment guidelines and resources, and support units in better targeting recruitment |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1406 | 12 - EM agency and authority | That the Department of Health & Human Services and Ambulance Victoria focus emergency response time reporting on highest priority cases. |
REC274-1412 | 20 - Role of police | That Victoria Police assesses and where practical addresses limitations to available data and trials the use of response times for internal performance measurement. |
REC274-1411 | 12 - EM agency and authority | That the Country Fire Authority, Victoria State Emergency Service and Metropolitan Fire and Emergency Services Board improve controls over response time data collection and reporting. |
REC274-1410 | 12 - EM agency and authority | That the Department of Justice & Regulation applies a consistent approach to emergency response time measures including data capture, calculation and reporting. |
REC274-1409 | 12 - EM agency and authority | That the Department of Health & Human Services and Department of Justice & Regulation verify that response time data used in their reports on output performance measures is accurate and auditable. |
REC274-1407 | 12 - EM agency and authority | That the Department of Health & Human Services' and the Department of Justice & Regulation's public reporting of response time measures clearly attribute accountability for each phase of emergency response, including call-taking time involving the Emergency Services Telecommunications Authority. |
REC274-1413 | 12 - EM agency and authority | That Ambulance Victoria, Country Fire Authority, Metropolitan Fire and Emergency Services Board and Victoria State Emergency Service improve the transparency of public reporting on response times by including regional performance, times, trends and analysis of the factors affecting performance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1418 | 12 - EM agency and authority | Queensland Fire and Emergency Services should consider examining regulatory provisions to improve disaster management and business continuity planning for aged care providers. |
REC272-1414 | 12 - EM agency and authority | Queensland Fire and Emergency Services coordinate the development of an integrated risk based approach to disaster management planning for Queensland that is consistent with the Standard and applicable at all levels of the arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1099 | 12 - EM agency and authority | VicSES should: align ERAS-e profiles with its planning cycle |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1563 | 13 - Mapping and data quality | Governments at all levels should make new and currently held natural hazard data publicly available in accordance with open public sector information principles. When collecting new natural hazard data or undertaking modelling, all levels of government should: |
REC256-1572 | 6 - Insurance and legal liability | Insurers should provide additional standardised information to households regarding their insurance policies, the natural hazards they face and indicative costs of rebuilding after a natural disaster. This work should be led by the Insurance Council of Australia developing guidelines, within one year, to ensure consistency in the provision and presentation of this information across insurers. |
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
REC256-1565 | 13 - Mapping and data quality | Governments should task the Australia–New Zealand Emergency Management Committee with leading the development of guidelines for the collection and dissemination of natural hazard mapping, modelling and metadata. Guidelines should be developed for all hazards that need to be modelled and mapped at the local/regional level and where consistency across regions is desirable. |
REC256-1564 | 6 - Insurance and legal liability | State and territory governments, local governments and insurers should explore opportunities for collaboration and partnerships. Partnerships, for example, could be formed through the Insurance Council of Australia and state-based local government associations (or regional organisations of councils). Consideration could be given to the Trusted Information Sharing Network model. Partnerships could involve: |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2572 | 12 - EM agency and authority | St John Ambulance should explore opportunities for extending the community paramedic model to other areas of identified need |
REC252-2568 | 12 - EM agency and authority | Western Australia Health should develop criteria with St John Ambulance for the allocation of paramedics across the state |
REC252-2567 | 12 - EM agency and authority | Western Australia Health should re-engage with St John Ambulance at a senior level to address strategic and complex issues including long term solutions to ramping |
REC252-2573 | 12 - EM agency and authority | St John Ambulance should build on its regionalisation model and improve engagement with local services in the Kimberley and Pilbara regions |
Rec-ID | Code | Recommendation |
---|---|---|
REC248-2578 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should review the impact of its enterprise agreements on the efficiency of frontline management, and on the implementation of audit recommendations, in preparation for enterprise agreement discussions in 2013 |
REC248-2583 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should review and strengthen controls over staff fulfilling their evidence to support personal unplanned leave |
REC248-2577 | 12 - EM agency and authority | Ambulance Victoria should closely monitor in rural regions the outcomes of its strategy to strengthen team management and adjust the strategy to address gaps or underperformance. |
REC248-2582 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should provide one comprehensive source of information on leave |
REC248-2576 | 12 - EM agency and authority | Ambulance Victoria should review processes for managing personal unplanned leave evidence to reduce the risk that personal unplanned leave is incorrectly recorded |
REC248-2581 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should improve specialised human resources support to frontline managers |
REC248-2586 | 12 - EM agency and authority | Victoria Police should monitor the use of online tools for accessing unplanned leave data, to make sure that the tools are accessible and meet the needs of police managers |
REC248-2575 | 12 - EM agency and authority | Ambulance Victoria should review support for team managers who also perform paramedic duties and implement improvements to maximise team managers’ ability to perform their roles |
REC248-2580 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should provide operational commanders, senior station officers the personal unplanned leave of firefighters in their teams |
REC248-2585 | 12 - EM agency and authority | Victoria Police should improve the management of police members undergoing performance and discipline procedures |
REC248-2579 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should strengthen performance management of firefighter effectively manage personal unplanned leave |
REC248-2584 | 12 - EM agency and authority | The Metropolitan Fire and Emergency Services Board should continue to strengthen human resource management processes and controls to reduce avoidable overtime costs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2590 | 12 - EM agency and authority | That: |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2616 | 6 - Insurance and legal liability | That once the review of the Emergency Management Act has been finalised, any reference to the liability of councils should be mirrored in both the EM Act and the F&ES Act. |
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
REC244-2634 | 12 - EM agency and authority | If possible the terms of election for CFS Health and Safety Representatives be aligned with group elections. |
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
REC244-2619 | 12 - EM agency and authority | Should the SES be given the power ‘to register suitable organisations’, then the ‘other person’ in Section 127 – Protection from liability, could be defined to include members of organisations affiliated to emergency service organisations. |
REC244-2618 | 12 - EM agency and authority | SES be given a power ‘to register, subject to any conditions the Chief Officer SES considers appropriate, suitable organisations (such as Volunteer Marine Rescue Associations) as affiliated organisations of the State Emergency Service’. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2651 | 13 - Mapping and data quality | That the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomesThat the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2765 | 12 - EM agency and authority | That the Chief Executive Officer Portfolio Business promote innovation and drive cultural change in terms of business practice. |
REC239-2691 | 39 - Disaster Risk Management | That the Commissioners of Police and the Queensland Fire and Rescue Service review the current district disaster boundaries as a matter of urgency in-line with the findings and recommendations of the Auditor–General’s report into the Queensland disaster management system. |
REC239-2730 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service actively progress initiatives for flexible employment including: |
REC239-2710 | 13 - Mapping and data quality | That all agencies participating in these activities should, as far as legally possible, share data sets whether or not the relevance is immediately obvious. |
REC239-2743 | 12 - EM agency and authority | That where practicable, the consideration for new or enhanced facilities include an assessment of the viability of creating a Rural Fire Service /SES common user facility. |
REC239-2750 | 20 - Role of police | That the Queensland Police Service: |
REC239-2669 | 12 - EM agency and authority | That specific business cases should be developed for contestability of correctional services in Queensland, including: |
REC239-2716 | 12 - EM agency and authority | That the remainder of the current Emergency Management structure transition to the Commissioner, Fire and Emergency Services for further consideration regarding the most appropriate reporting alignment giving due consideration to existing capacity. This should be done in consultation with the Commissioner, the Queensland Police Service to ensure proper collaboration with the Queensland Police Service Disaster Management Unit staff. |
REC239-2760 | 12 - EM agency and authority | That a suitably qualified Chief Information Officer with whole of portfolio responsibility is appointed to oversight corporate support and capability development |
REC239-2689 | 20 - Role of police | That, where appropriate, the Commissioner of Police appoints appropriately trained and experienced public service officers to appropriate roles in the disaster management system to support District Disaster Coordinators in their vital roles. |
REC239-2726 | 20 - Role of police | That the Queensland Fire and Rescue Service enters into discussion with the Queensland Police Service regarding the possibility for the Queensland Police Service to assist with prosecutions that may arise out of fire safety matters. |
REC239-2707 | 12 - EM agency and authority | That the Inspector General Emergency Management ensures that improvement strategies identified are acted upon and improvement strategies embedded within agencies as standard practice. |
REC239-2742 | 12 - EM agency and authority | That the recommendations of The Malone Review in relation to Criminal History checks, so far as supported, by the Review team in this report be progressed inclusive of SES issues. |
REC239-2748 | 20 - Role of police | That the Queensland Police Service considers adopting the broader use of ANPR in line with other Australian jurisdictions in consultation with the Privacy Commissioner. |
REC239-2665 | 12 - EM agency and authority | That planning, especially for infrastructure, must take into account the service delivery model (e.g. the fact that prisoners have high level health needs). |
REC239-2715 | 12 - EM agency and authority | That the Disaster Management Standards Branch element of Standards Improvement, transition to the Inspector General Emergency Management. |
REC239-2757 | 20 - Role of police | That the Queensland Police Service executive team reassesses its preparedness to collaborate with other agencies to deliver a whole of Government approach to delivering community safety. |
REC239-2680 | 12 - EM agency and authority | That the fire service takes a broader view of its role as an emergency management organisation. |
REC239-2723 | 1 - Land-use and building regs | That the Queensland Fire and Rescue Service examine alternative contractual arrangements with building owners which would reduce the need for physical attendance at alarm activations. |
REC239-2706 | 12 - EM agency and authority | The establishment, management, support and education of the State Emergency Service (SES) become the responsibility of a Deputy Commissioner, Fire and Emergency Services and this person should also be responsible for Rural Fire Service Queensland. |
REC239-2734 | 12 - EM agency and authority | That a new Deputy Commissioner position be created to manage volunteer emergency services including the Rural Fire Service and the State Emergency Service. |
REC239-2663 | 12 - EM agency and authority | That the Commissioner of Queensland Corrective Service report directly to the Director-General the Department of Justice and Attorney-General. |
REC239-2714 | 12 - EM agency and authority | That the following units of Emergency Management Queensland transition to the control of the position of Deputy Commissioner Rural Fire Service Queensland and State Emergency Services: |
REC239-2747 | 20 - Role of police | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative automated number plate recognition models should form part of the design architecture. |
REC239-2754 | 12 - EM agency and authority | That the Chief Executive Officer Portfolio Business should overhaul portfolio information and communication technology and appoint a Chief Information Officer with appropriate qualifications and significant industry experience as a first priority. |
REC239-2677 | 12 - EM agency and authority | That biometric tools be leveraged for other demands (e.g. bail reporting). |
REC239-2722 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service should introduce alternative means of response to automatic alarms such as small first response investigative crews e.g. two fire–fighters in a sedan (not responding under lights and siren). |
REC239-2774 | 39 - Disaster Risk Management | Those final determinations of disaster management districts include consultation with the Local Government Association Queensland, the Queensland Fire and Rescue Service and other Government departments. |
REC239-2698 | 12 - EM agency and authority | That the Deputy Commissioner, Operations (of the proposed new Department of Fire and Emergency Services) should be responsible for ensuring the readiness of the disaster operations system, including the State Disaster Coordination Centre, enabling seamless transition to police control when required. |
REC239-2733 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service reduce the number of communication centres to two, with one being a primary site and the other site providing redundancy and business continuity functionality. |
REC239-2658 | 12 - EM agency and authority | That the Queensland Ambulance Service maintains its own identity to: |
REC239-2713 | 12 - EM agency and authority | That the following units of Emergency Management Queensland transition to the control of the Deputy Commissioner of Regional Operations (Department of Fire and Emergency Services): |
REC239-2745 | 12 - EM agency and authority | That the Emergency Service Cadet Program take a full spectrum approach to emergency services |
REC239-2752 | 20 - Role of police | That the roll-out of the Queensland Police Service digital technology should take into consideration adopting and facilitating new processes including the police response to domestic violence. |
REC239-2672 | 12 - EM agency and authority | That Queensland Corrective Service conduct business analysis and planning to clearly identify its customers and its contribution to the Government’s priorities |
REC239-2720 | 12 - EM agency and authority | That a reduced regional model for fire and emergency services be generally aligned to that of the Queensland Police Service with a district structure that accords with disaster districts. |
REC239-2766 | 12 - EM agency and authority | Recommendation: |
REC239-2692 | 39 - Disaster Risk Management | That the Queensland Police Service Disaster Management Unit is to be permanently located at the State Disaster Coordination Centre to work on a day to day basis with the proposed new Department of Fire and Emergency Services. |
REC239-2731 | 12 - EM agency and authority | That the CEO Portfolio Business and the Commissioner Queensland Fire and Rescue Service find a more appropriate method of accounting for part time and volunteer staff when considering the support required to raise, train and sustain this very large part of the workforce. |
REC239-2656 | 12 - EM agency and authority | That the Queensland Ambulance Service is maintained as a state-wide service into the future. |
REC239-2711 | 39 - Disaster Risk Management | That the Inspector General Emergency Management be empowered to provide an assurance to Government that the disaster management system is both appropriate and capable of dealing with complex events. |
REC239-2744 | 12 - EM agency and authority | That the revitalised PCYC Emergency Service Cadet Program continue to be supported by government. |
REC239-2751 | 12 - EM agency and authority | That collaboration on new initiatives such as the co-responder model in Cairns continue and if successful, initiatives should be considered for state wide or service wide adoption. |
REC239-2670 | 12 - EM agency and authority | That prisoner transport and non-managerial roles within watch-houses should be a priority for contestability. |
REC239-2719 | 12 - EM agency and authority | That the current Queensland Fire and Rescue Service model of functional management be expanded, shifting line management responsibility for community safety operations and professional development from Regional Assistant Commissioners to the State Commanders. Regional Assistant Commissioners become responsible for operations and coordination of departmental support within geographic locations and report to the Deputy Commissioner operations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0825 | 1 - Land-use and building regs | That the NSW Rural Fire Service hold discussions with the Department of Planning and Infrastructure and Local Government NSW on ways to improve compliance with development consents under section 76A of the Environmental Planning and Assessment Act 1979. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2885 | 13 - Mapping and data quality | Increased automation and outsourcing of observations |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
REC205-1906 | 6 - Insurance and legal liability | Governments should not subsidise household or business property insurance, whether directly or by underwriting risks. |
REC205-1905 | 6 - Insurance and legal liability | The Australian Government should only proceed with reforms that require all household insurers to offer flood cover if it can be demonstrated that the benefits to the wider community would exceed the costs. |
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2976 | 41 - Emergency Management exercises | The Department of Human Services should regularly test recovery plans with partner agencies. |
REC179-2982 | 12 - EM agency and authority | The Department of Human Services should base targets for staff in emergency roles on regional needs and develop a staff deployment strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
REC165-0085 | 20 - Role of police | The Commissioner of Police, through a dedicated Assistant Commissioner (supported by a cohort of Assistant Commissioners to ensure adequate coverage), be assigned responsibility for overall control of each natural Disaster Management event in Queensland as the preferred arrangement. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3034 | 12 - EM agency and authority | That National Offshore Petroleum Safety Authority critically review its regulatory manning levels based on its current workload and the recommendations for additional areas of focus and increased auditing presented in this Report. To meet these requirements, we estimate that National Offshore Petroleum Safety Authority requires up to 50 inspectors in total plus associated support staff to bring overall staffing from about 55 to 75. RET should help facilitate the necessary ongoing levy funding in consultation with industry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3048 | 12 - EM agency and authority | ACTAS should enhance its approach to risk management by: |
REC159-3046 | 12 - EM agency and authority | ACT Ambulance Service (ACTAS) should revise its Business Plan to address key priorities and activities for each key service delivery function. This would include clearer expected outputs to be delivered annually and their prioritisation. |
REC159-3054 | 12 - EM agency and authority | ACTAS should improve systems to manage its non-emergency transport services, provide training and guidance to staff on use of these systems, and implement a quality assurance process. |
REC159-3052 | 12 - EM agency and authority | ACTAS should develop and implement as a matter of priority, appropriate strategies to address declining response times. |
REC159-3049 | 12 - EM agency and authority | ACTAS should enhance its approach to demand modelling in order to better guide current and future ambulance resourcing by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3077 | 12 - EM agency and authority | The presiding member of the Advisory Board appointed under Section 18(4) be also appointed as a member of the SAFECOM Board. |
REC151-3099 | 12 - EM agency and authority | The selection procedures in the Regulations for SACFS officer positions be reviewed in terms of ensuring that appropriate skills and experience are considered. |
REC151-3067 | 12 - EM agency and authority | Fresh consideration be given to the title of Commissioner of Fire and Emergencies so as to ensure it does not give the impression that it is operationally superior to the Chief Officers of the emergency service agencies. |
REC151-3098 | 12 - EM agency and authority | Nominations for candidates for SACFS group elections be received both by written nomination and by oral nomination. |
REC151-3066 | 12 - EM agency and authority | Accountability for matters of policy, strategy and resource allocation for the emergency services sector, currently the province of the Board, be given to the position created in Recommendation 3 above. |
REC151-3083 | 12 - EM agency and authority | Provisions remain in the FES Act relating to the emergency service organisations being separate legal entities. |
REC151-3080 | 12 - EM agency and authority | The United Firefighters Union of Australia – SA Branch (UFU) be given full voting rights on the Advisory Board. |
REC151-3078 | 12 - EM agency and authority | All members of the proposed reconstituted SAFECOM Board be given full voting rights. |
Rec-ID | Code | Recommendation |
---|---|---|
REC147-3188 | 12 - EM agency and authority | The ANAO recommends that EMA maintain the Internet site to ensure that material is appropriate, current and readily accessible for users. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3571 | 12 - EM agency and authority | A senior, experienced, clinically trained ambulance officer to be based in TAS Communications in Hobart for at least 14 hours a day. |
REC140-3557 | 12 - EM agency and authority | Royal Flying Doctor Service fixed wing to remain in Launceston for the duration of the current contract. |
REC140-3570 | 12 - EM agency and authority | The fragmentation and duplication of fixed wing and helicopter clinical coordination should be eliminated through centralisation to TAS Communications. |
REC140-3569 | 12 - EM agency and authority | A senior Tasmanian NETS representative be confirmed on the Tasmanian Medical Retrieval Services Committee. |
REC140-3566 | 12 - EM agency and authority | Launceston General and Burnie Hospital’s Emergency Departments require sufficient equipment, monitors and human resources to provide occasional safe local retrieval in their region. |
REC140-3562 | 12 - EM agency and authority | A rapidly responsive helicopter and road retrieval capability to be developed out of RHH. |
REC140-3573 | 13 - Mapping and data quality | Databases with a common minimum data set complete with incident monitoring should be established for TAS Air Ambulance, TMRS and NETS missions. |
REC140-3558 | 6 - Insurance and legal liability | DHHS need to confirm adequate accident insurance coverage for staff working in retrieval medicine. Coverage specific to helicopter and fixed wing duties is required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |