Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC327-4345 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: review and improve processes for timely recording of fleet asset movements, locations, and maintenance status. |
REC327-4346 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: establish a fleet maintenance framework to ensure regular update of District Service Agreements with local councils. |
REC327-4350 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: develop a fleet enhancement framework and strategy that is informed by an assessment of current fleet capability to respond to fire incidents, and research into the most appropriate technologies and appliances to address emerging and future fire risks across NSW. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4234 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science review its suite of operational doctrine to ensure arrangements for situational reporting and requests for assistance are aligned to recognised multi-agency practices used in disaster management. |
REC322-4236 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the arrangements and requirements for situational reporting when an incident is under the control of the Department of Environment and Science be detailed in the Queensland Bushfire Plan. These arrangements should also be outlined in relevant joint entity agreements and operational doctrine. |
REC322-4237 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science develop and implement a Wildfire Response Plan for Queensland Parks and Wildlife Service Coastal and Islands Region, to be included in the region’s Disaster Management Operations Plan. |
REC322-4238 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science ensure that all Queensland Parks and Wildlife Service regions develop a Disaster Management Operations Plan based on a standardised format. The plans should include provision for annual review to ensure they remain contemporary, interoperable with relevant disaster management plans and aligned to the Department of Environment and Science Emergency Management Plan. |
REC322-4241 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services consider expanding specialist Remote Area Firefighting Team capability to assist in responding to significant bushfire events which occur in rugged or inaccessible terrain. |
REC322-4233 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science review the current description of Level 1, 2, and 3 bushfire incidents and the implied meaning of property in the Queensland Bushfire Plan. This review should identify and agree on clear criteria and decision points for the transfer of control and develop a standard process and templates. |
REC322-4247 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends a collaborative review of firelines, tracks and trails on K’gari be undertaken by the Department of Environment and Science, in collaboration with the Locality Specific Area Fire Management Group and the Butchulla people, to ensure an adequate network is agreed by relevant stakeholders, and roles and responsibilities for maintenance are agreed and documented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4173 | 32 - Doctrine, standards, and reform | The Inspector-General for Emergency Management recommends that in conjunction with Inquiry Recommendation 2, the State establish or assign responsibility to a single body or entity to lead and coordinate the implementation of evidence-based fuel management policy, practice and assurance and reporting on activities on both public and private land in Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3269 | 32 - Doctrine, standards, and reform | Develop and practice procedures for the CFS, DEW and local governments to access and deploy heavy plant and machinery for fuel reduction operations both before and during bushfires. |
REC314-3261 | 24 - Govt responsibility | Consider amending the Fire and Emergency Services Act 2005 to align SAFECOM Board operations with accepted governance standards with the Minister appointing an Independent Chair of the SAFECOM Board. The SAFECOM Chief Executive (CE) should report to the Board and maintain SAFECOM’s role at the direction of the Board. Alternatively, SAFECOM could be abolished, moving to a model of a Department of Fire and Emergency Services where the departmental head reports to the Minister but the value proposition of any such machinery of government change would need to be thoroughly examined. |
REC314-3260 | 32 - Doctrine, standards, and reform | Align risk assessment tools and processes to Risk Management Standard ISO 31000 and the National Emergency Risk Assessment Guidelines (NERAG) and communicate these on public-facing platforms. Make Bushfire Management Area Plans (BMAP) accountable for managing and reporting on region-specific risk and identifying critical infrastructure such as mobile phone towers as key risks. |
REC314-3259 | 32 - Doctrine, standards, and reform | Implement previous review recommendations for bushfire management including those relating to the 2009 amendments to the Fire and Emergency Services Act 2005, State Bushfire Coordination Committee operation, State Bushfire Management Plan, as well as urgent completion of Codes of Practice for fuel hazard reduction on all land tenures, and redevelopment of Bushfire Management Area Plans accompanied by effective community engagement to build an understanding of risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2426 | 32 - Doctrine, standards, and reform | Queensland's plans and arrangements for heatwave should be reviewed to provide for an intergrated multi-agency approach to their management. A single agency should lead and oversee this process. |
REC307-2441 | 32 - Doctrine, standards, and reform | Hazard-specific and disaster management guidelines and plans should explain the circumstances and process for hazard-specific activation of the disaster management arrangements in support of an incident. They should be relevant to local authorities and local and district groups, and used during events. |
REC307-2434 | 32 - Doctrine, standards, and reform | Given an increasing risk of intense fires, the framework of legislation relating to vegetation management, bushfire mitigation and preparation priorities should be re-assessed. The re-assessment should aim to enable more appropriate and flexible means at the local level for the reduction of intense fires. |
REC307-2433 | 24 - Govt responsibility | To make planned burning and land clearing easier to understand and implement for landholders, a single point of contact for all bushfire mitigation inquiries and permits should be established. |
REC307-2432 | 32 - Doctrine, standards, and reform | Legislation at state and local level requiring landholders to reduce fire risk on their property should be actively applied |
REC307-2443 | 32 - Doctrine, standards, and reform | Planning for response to bushfire risk should identify all stakeholders to be engaged in the response phase and their roles and responsibilities should be clearly documented. |
REC307-2427 | 32 - Doctrine, standards, and reform | Wherever possible, the antecedents that will lead to catastrophic fire weather conditions existing for a particular area should be identified and documented within fire management plan relevant to the area. |
REC307-2442 | 32 - Doctrine, standards, and reform | Hazard-specific plans and guidelines should be published on external websites for access by relevant stakeholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2415 | 32 - Doctrine, standards, and reform | Define formal bushfire management regimes for areas with different bushfire management requirements and define bushfire management responsibilities in those areas. One category will provide for areas that warrant provision of a wildfire response capacity, another will allow for the declaration of temporary fire management arrangements for the duration of identified high-risk circumstances. |
REC304-2409 | 32 - Doctrine, standards, and reform | Formalise and clearly define the powers and duties of Bushfires NT personnel, including volunteers, thereby clarifying Bushfires NT’s role in bushfire management in the Northern Territory. |
REC304-2421 | 32 - Doctrine, standards, and reform | Include a detailed description of the role, responsibility and accountability of |
REC304-2408 | 32 - Doctrine, standards, and reform | Introduce clear Terms of Reference for the Bushfires Council and Regional Bushfires Committees, and introduce a requirement for the Minister to consider advice and recommendations from the Council. |
REC304-2420 | 32 - Doctrine, standards, and reform | Enshrine the broader fire management principles, including coordination, strategic planning, mitigation, monitoring and control within the Act. |
REC304-2405 | 24 - Govt responsibility | Retain the Bushfires Council as a Ministerial advisory body. |
REC304-2418 | 32 - Doctrine, standards, and reform | Amend the object to provide for ‘The mitigation, management, and suppression of bushfires’. Definitions of these terms should be included in the Act, and should include clarification that bushfire suppression can include emergency response activities in certain circumstances |
REC304-2417 | 32 - Doctrine, standards, and reform | Amend the Act title to ‘Bushfires Management Act’. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2399 | 24 - Govt responsibility | Implement a fully integrated civilianised single call and dispatch centre, that includes a redundancy option outside the Sydney CBD, which will adopt an agnostic approach to deploy the quickest most suitable resource to an emergency. Such a centre should be managed by either a non uniformed public servant staffed organisation like the Office for Emergency Management, or the NSW Police Force |
REC302-2395 | 32 - Doctrine, standards, and reform | Remove those policies, guidelines, memoranda of understanding and committees that are made redundant as a result of adopting recommendation #2 while updating any remaining policies that are considered to still be relevant |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2387 | 32 - Doctrine, standards, and reform | TFS, PWS and STT agree an updated version of the Interagency Fire Management Protocol which maintains the principle that there will be one state-wide point of command for major unwanted fires burning in the State of Tasmania, explicitly recognises the right of each of TFS, PWS and STT to have their objectives prioritised in incident action planning and adequate resources applied to those objectives, and provides a mechanism for executive decision-makers from TFS, PWS and STT to come together and agree objectives and resourcing levels that will then be operationalised by whole-of-State control structures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1248 | 24 - Govt responsibility | The State Emergency Management Committee to establish a State Bushfire Coordinating Committee as a sub-committee of SEMC. The State Bushfire Coordinating Committee will be chaired by the Director of the Office of Bushfire Risk Management and will have the primary responsibility to: · develop a State Bushfire Management Policy and a set of long term bushfire risk management objectives; · provide a forum for key bushfire risk management stakeholder agencies; · advise the SEMC on matters pertaining to bushfire, in particular, to report against the investment in, and achievement of the bushfire risk management objectives; · provide advice and support to the proposed Chief Officer of the Rural Fire Service on bushfire risk management matters; and · report to SEMC and to the community on bushfire risk management matters on at least an annual basis. |
REC291-1247 | 32 - Doctrine, standards, and reform | The State Government to create a Rural Fire Service to enhance the capability for rural fire management and bushfire risk management at a State, regional and local level. The proposed Rural Fire Service will: · be established as a separate entity from the Department of Fire and Emergency Services or, alternatively, be established as a sub-department of the Department of Fire and Emergency Services; · have an independent budget; · be able to employ staff; · have a leadership structure which, to the greatest degree possible, is regionally based and runs the entity; · be led by a Chief Officer who reports to the responsible Minister on policy and administrative matters; and to the Commissioner for Fire and Emergency Services during operational and emergency response; · have responsibilities and powers relating to bushfire prevention, preparedness and response; and · operate collaboratively with the Department of Fire and Emergency Services, the Department of Parks and Wildlife, Local Government and volunteer Bush Fire Brigades. In creating the Rural Fire Service, the State Government to consider whether back office and corporate support services could be effectively provided by an existing Department, such as the Department of Fire and Emergency Services or the Department of Parks and Wildlife. The State Government to review the creation of the Rural Fire Service two years after its establishment, to assess whether its structure and operations are achieving the intended outcome. |
REC291-1238 | 32 - Doctrine, standards, and reform | The State Emergency Management Committee to adopt, across all hazards, the doctrine of: · the primacy of life; · the ‘Strategic Control Priorities’ (as documented by the Department of Fire and Emergency Services); and · community warnings that are timely, tailored and relevant. Agencies will reinforce amongst emergency management personnel the importance of this doctrine through briefings and intent statements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1211 | 32 - Doctrine, standards, and reform | Review of institutional arrangements in the fire sector |
REC290-1218 | 7 - Inter-agency communication | Cross-agency resource management system |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1184 | 24 - Govt responsibility | The Tasmanian fire agencies think more broadly about how staff who are already employed by Government could support the management of future emergencies. |
REC287-1182 | 32 - Doctrine, standards, and reform | The fire agencies consider how the Regional Fire Operations Centre (RFOC) as a concept adds value once a level 3 IMT is up and running in a region. |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1166 | 7 - Inter-agency communication | Develop an integrated inter-agency resource management system: Large and complex fire incidents require resources from multiple agencies. Developing an integrated inter-agency resource management system will have three main benefits: identifying potential resources will be more straightforward • the status and location of resource deployments can be tracked • planning of deployments can take into account all relevant information |
REC277-1165 | 32 - Doctrine, standards, and reform | Clarify the role of the ROC and SOC and their reporting relationships: The ROC and SOC have important coordination roles under the State Emergency Management Arrangements to support both the incident and the broader region and state. Clarifying the role of the ROC and SOC, their reporting relationships, and how the command structures of other agencies are integrated, will have three main benefits: the ROC and SOC can perform their functions effectively • no inconsistencies, gaps or duplication in the activities of the IMT, ROC and SOC • transparency of incident management |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1128 | 32 - Doctrine, standards, and reform | Incorporate in operational doctrine the ability for the State Controller to determine the operational readiness levels of the state or regions based on either the predicted and/or actual risk and/or activity to some or all of the regions. |
REC273-1145 | 32 - Doctrine, standards, and reform | Review relevant Legislation associated Acts and Plans to establish a consistent approach to fire and emergency management to minimise duplication and risk of contradiction. That the Hazard and Functional area plans be amalgamated and establish a SA Bushfire Plan, under the SEMP, which clearly define role of SACFS. |
REC273-1144 | 7 - Inter-agency communication | That SACFS consider a review to develop an effective interagency messaging system and agency resource management system. |
REC273-1143 | 32 - Doctrine, standards, and reform | That SACFS in consultation with SAMFS consider adopting common terminology and capability requirements for strike teams being ‘4-5 appliances and a group officer’ in line with other jurisdictions. |
REC273-1133 | 32 - Doctrine, standards, and reform | That a complete review of current naming conventions of personnel and centres, in accordance with the outcomes of the Victorian Bushfire Royal Commission is undertaken, to ensure clarity around command, control and coordination within SA. |
REC273-1129 | 32 - Doctrine, standards, and reform | Incorporating ‘triggers’ within Chief Officers Standing Orders No. 17, which requires the escalation of the State Controller role to the rank of Assistant Chief Officer or greater, depending on the increased risk or activity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1107 | 32 - Doctrine, standards, and reform | Standard Operating Procedure 1 (Mobilisation Zone 2, Perth Hills area) should be reviewed to ensure that appropriate escalation triggers and levels of operational readiness are in place for future periods when severe fire weather conditions are forecast. |
REC265-1124 | 32 - Doctrine, standards, and reform | EMP 4.4 and Westplan – Recovery Coordination should be amended to: clarify the wording around handing over control of the incident from the Controlling Agency to local government and the transition from response to recovery; include principles and criteria that will assist the Controlling Agency and local government to determine the best time to effect a hand over of control of the incident; make explicit the roles and responsibilities of the parties involved in the handover of control of the incident; specify the information required in the needs and impact assessments provided to local government by the Controlling Agency so that local government is given sufficient information to take control of incidents; clarify the roles, responsibilities and the title of the State Recovery Controller and ensure that the appropriate wording is reflected in Westplans and State Emergency Management Policies; Hazard Management Agencies, combat and support agencies and local governments need to fully inform themselves of the role of the State Recovery Controller and implement a more effective approach to communicating |
REC265-1100 | 32 - Doctrine, standards, and reform | The forthcoming review by SEMC of SEMP 4.4 Recovery Coordination and Westplan – Recovery Coordination and SEMP 4.1 Incident Management should include consideration of: |
REC265-1119 | 24 - Govt responsibility | Relevant policies and Westplans should be amended to require that full consultation occurs between the Controlling Agency and the Department for Child Protection and Family Support regarding the location of the evacuation centre(s) in a bushfire incident. |
REC265-1114 | 32 - Doctrine, standards, and reform | Procedures should be reviewed to address the risks associated with response aircraft all working from one forward operating base, including the need for a designated fire protection unit to be available in the event of an aircraftrelated fire or other emergency incident |
REC265-1113 | 32 - Doctrine, standards, and reform | The role of the Ground Controller should be reaffirmed in operational doctrine and reinforced in Incident Management Team training. During incidents involving aircraft the appointment of a Ground Controller should be confirmed by the Incident Controller |
REC265-1110 | 32 - Doctrine, standards, and reform | Whenever a Bush Fires Act 1954 section 13 transfer of control is invoked, the Incident level of an event should also be reviewed and any changes documented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1079 | 32 - Doctrine, standards, and reform | The State review and revise the Bushfre Smoke Protocol and the PM Health Protection Protocol, to: 2.5 • ensure both protocols are consistent with each other; and • ensure both protocols include assessment methods and trigger points for specifc responses. |
REC264-1078 | 32 - Doctrine, standards, and reform | The State review and revise the community carbon monoxide response protocol and the firefghter carbon monoxide response protocol, to: |
REC264-1077 | 32 - Doctrine, standards, and reform | The State take the lead in advocating for a national compliance standard for PM |
REC264-1088 | 32 - Doctrine, standards, and reform | GDF Suez adopt and apply the firefghter carbon monoxide response protocol. |
REC264-1075 | 32 - Doctrine, standards, and reform | The State: • bring forward the commencement date of s.16 of the Mineral Resources (Sustainable Development) Amendment Act 2014 (Vic), to facilitate the requirement that approved work plans specifcally address fre prevention, mitigation and suppression; and • acquire the expertise necessary to monitor and enforce compliance with fre risk measures adopted by the Victorian coal mining industry under both the mine licensing and occupational health and safety regimes. |
REC264-1084 | 32 - Doctrine, standards, and reform | GDF Suez revise its Emergency Response Plan, to: • require an increased state of readiness on days of Total Fire Ban; • require pre-establishment of an Emergency Command Centre; • require pre-positioning of an accredited Incident Controller as Emergency Commander; and • require any persons nominated as Emergency Commander to have incident controller accreditation and profciency in the use of the Australasian Inter-service Incident Management System. |
REC264-1074 | 32 - Doctrine, standards, and reform | The State enact legislation, to: • require Integrated Fire Management Planning; and • authorise the Emergency Management Commissioner to develop and implement regional and municipal fire management plans. |
REC264-1080 | 32 - Doctrine, standards, and reform | The State develop and widely disseminate an integrated State Smoke Guide, to: • incorporate the proposed State Smoke Plan for the management of public health impacts from large scale, extended smoke events; • include updated Bushfre Smoke, carbon monoxide and PM protocols; and 2.5 • provide practical advice and support materials to employers, communities and individuals on how to minimise the harmful effects of smoke. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1538 | 32 - Doctrine, standards, and reform | Commanding Officer Defence Explosive Ordnance Training School amend relevant instructions, both generally and specifically, so as to ensure that explosive ordnance used in training serials is logged in real time, in accordance with extant doctrine. |
REC257-1552 | 32 - Doctrine, standards, and reform | Authority be given to the regional Environmental Officer to close a range or impose live-firing restriction in addition to any set out in Range Standing Orders if circumstances so warrant. |
REC257-1537 | 32 - Doctrine, standards, and reform | Commanding Officer Defence Explosive Ordnance Training School review and enforce Standard Operating Procedures to ensure that appropriate explosive ordnance accounting and handling practices, in accordance with Defence doctrine, are adhered to during all training activities. |
REC257-1551 | 32 - Doctrine, standards, and reform | The use of Internal and External ranges at MTA for patrolling activities be prohibited. |
REC257-1550 | 32 - Doctrine, standards, and reform | Defence engage with both the Bureau of Meteorology and the Rural Fire Service to determine a more suitable index system. In the interim, Range Standing Orders be amended so that live-firing on the ranges on Marrangaroo Training Area not be permitted where the Forest Fire Danger Index for either the Central Ranges District or Greater Sydney Region is 12, it being the threshold for HIGH Fire Danger Rating or above. put another way, and in a practical sense, Range Standing Orders should, as an interim measure, require the Officer in Charge Practice and the Range Control Officer to consider the Forest Fire Danger Index for both Central Ranges District AND Greater Sydney Region on the day of any given serial. If either index is as 12 or above, live-firing should not be permitted. Any indication in Range Standing Orders or elsewhere that live-firing is permitted on Marrangaroo Training Area when the Fire Danger rating is HIGH should be rescinded. |
REC257-1549 | 32 - Doctrine, standards, and reform | Marrangaroo Training Area Range Standing Orders should be reviewed to impose a requirement that the Officer in Charge of any live-firing practice ascertain and consider current weather parameters, temperature, humidity, wind strength and direction, registered at Mt Boyce immediately prior to any demolition serial. The setting of those parameters and their limits should be decided in consulation with the Bureau of Meteorology and Rural Fire Service and inserted into Range Standing Orders. |
REC257-1554 | 32 - Doctrine, standards, and reform | All documents be reviewed to remove ambiguity and perceived inconsistencies. Marrangaroo Training Area Range Standing Orders be subject to further examination, with particular consideration of the bushfire mitigation strategies referred to in the Bushfire Management Plan 2011-2014 before amendments to Chapter 10 are made. the basis upon which Range Standing Orders might fix a cut-off point for live-firing exercises should depend on continued bushfire strategies. Range Standing orders and Marrangaroo Training Area Bushfire Management Plan be reviewed annually. if hazard reduction has not occurred or the fire trails degraded, Range Standing Orders should take into account of heightened risk. |
REC257-1543 | 32 - Doctrine, standards, and reform | Range Standing Orders be amended to include a direction that no Defence vehicle is to leave the administration area of Marrangaroo Training Area during a bushfire, except to leave Marrangaroo Training Area itself through the main gate, unless it is a properly equipped bushfire fighitng vehicle havig at least four wheel drive capabiliy and self-protection equipment. |
REC257-1553 | 32 - Doctrine, standards, and reform | On matters relating directly to safety or risk, or when live-firing may occur, where there is ambiguity or apparent inconsistency, the most conservative or restrctive order should be followed until formal clarification has been provided. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1567 | 24 - Govt responsibility | State and territory governments should: |
REC256-1574 | 32 - Doctrine, standards, and reform | The Australian Government should establish a framework for the development of benchmark prices for the reconstruction of essential public assets. This should set out the broad parameters that state and territory governments should follow, without prescribing particular prices to be used. |
REC256-1558 | 37 - Funding | Funding to state and territory governments for community recovery should be provided as untied grants, with a transition period pending the development of a framework to assess community recovery costs. During the transition period, the Australian Government should continue to provide funding for community recovery through a reimbursement model. |
REC256-1566 | 24 - Govt responsibility | State and territory governments should prioritise and accelerate implementation of the Enhancing Disaster Resilience in the Built Environment Roadmap, including reviewing the regulatory components of vendor disclosure statements. The Land Use Planning and Building Codes Taskforce should be tasked to identify and consider options for regular, low-cost dissemination of hazard information to households by governments and insurers. |
REC256-1571 | 24 - Govt responsibility | State and territory taxes and levies on general insurance should be phased out and replaced with less distortionary taxes. |
REC256-1557 | 37 - Funding | Where asset management plans at the local, state or territory level pre-identify and cost betterment of assets (improving asset resilience to natural disasters), the Australian Government should share 50 per cent of the betterment component of reconstruction costs following damage from a (eligible) natural disaster. |
REC256-1562 | 32 - Doctrine, standards, and reform | The Australian Government should: |
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
REC256-1556 | 37 - Funding | The Australian Government should fund natural disaster recovery by: |
REC256-1561 | 24 - Govt responsibility | State and territory governments should be required to report on the following accountability requirements: |
REC256-1569 | 32 - Doctrine, standards, and reform | The provisions in the Queensland Sustainable Planning Act 2009 for injurious affection should be repealed. |
REC256-1577 | 37 - Funding | The Australian Government should develop a formula for allocating mitigation funding to state and territory governments on the basis of where such funding is likely to achieve the greatest net benefits, taking into account the future risks of natural disasters. This should be completed within five years and in consultation with state and territory governments. |
REC256-1560 | 37 - Funding | The Australian Government should: |
REC256-1568 | 24 - Govt responsibility | State governments, where they have not already done so, should provide local governments with statutory protection from liability for releasing natural hazard information and making changes to local planning schemes where such actions have been taken ‘in good faith’ and in accordance with state planning policy and legislation. |
REC256-1575 | 24 - Govt responsibility | State and territory governments should develop benchmark prices for the reconstruction of essential public assets and submit these to the Australian Government for approval within one year. In developing these prices, they should consult with local governments and relevant experts, and draw on asset management plans. The prices should be reviewed and updated over time. |
REC256-1559 | 37 - Funding | The Australian Government should gradually increase the amount of annual mitigation funding it provides to state and territory governments to $200 million. Initially, this funding should be distributed to state and territory governments in accordance with the allocation under the National Partnership Agreement on Natural Disaster Resilience. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1588 | 32 - Doctrine, standards, and reform | WA fire agencies adopt a common set of standing orders, operational procedures, training and competencies for rural firefighting that are produced in hard copy, leading to integrated multi-agency training, IMTs, Regional and State coordination/control centres. |
REC254-1584 | 32 - Doctrine, standards, and reform | DFES or DEC (depending on land tenure) is mandated to take over control of emergency incidents from Local Government once they have been declared Level 2 incidents. WESTPLAN BUSHFIRE and legislation to be amended accordingly. |
REC254-1580 | 32 - Doctrine, standards, and reform | Critical operational procedures such as ‘Red Flag Warnings’, on a common fireground need to be consistent across DFES, DEC and Local Government. In particular, the operational procedure of Red Flag Warnings needs to be adopted by all WA fire agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0882 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service documents and publishes its operational policies and procedures so they are accessible to and suitable for operational personnel. |
REC247-0950 | 32 - Doctrine, standards, and reform | That resources are committed to developing and implementing approved reforms to the emergency management arrangements. |
REC247-0859 | 7 - Inter-agency communication | That police and other emergency services examine options for achieving radio interoperability between them in the absence of an integrated radio system. |
REC247-0908 | 32 - Doctrine, standards, and reform | That the State Emergency Management Committee examine whether there are any legal issues associated with continuing recovery operations where the overarching emergency management arrangements have ceased. |
REC247-0871 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service critically reviews the operation of the Six Operational Priorities to determine whether they are appropriate and effective. |
REC247-0929 | 32 - Doctrine, standards, and reform | That the State Emergency Management Committee considers structuring the Tasmania Emergency Management Plan in a way that provides more specific guidance, commitment to and accountability for action to be taken. |
REC247-0881 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service establishes sufficient resources and expertise to research, develop, implement and review its policies and operations. |
REC247-0949 | 32 - Doctrine, standards, and reform | That following any review, the Emergency Management Act 2006 be amended. |
REC247-0858 | 7 - Inter-agency communication | That all agencies and the Government support moving to an integrated communications technology for police and the emergency services. |
REC247-0902 | 7 - Inter-agency communication | That evacuation centres and other centres have a standard operating procedure for communications. |
REC247-0870 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service considers adopting a primary tactic of an aggressive first attack on fires. |
REC247-0928 | 24 - Govt responsibility | That the Government take into account demographic change in its assessment of the consequences of climate change on emergency events. |
REC247-0877 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service reviews its approach to fire management operations at night, and develop and effectively implement unambiguous policy and operating procedures. |
REC247-0942 | 1 - Land-use and building regs | That the Government makes land use planning and building construction to prevent and mitigate bushfire risk a high priority and establishes a means to progress improvements in this area, such as a designated body or group, as soon as possible. |
REC247-0852 | 32 - Doctrine, standards, and reform | That the role and expected duties of the State Controller be clearly defined in the Emergency Management Act 2006. |
REC247-0898 | 32 - Doctrine, standards, and reform | That the State Special Emergency Plan–Recovery and the emergency management structure for recovery be reviewed. |
REC247-0869 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service ensures that planning for active fires includes a proactive approach wherever possible. |
REC247-0914 | 32 - Doctrine, standards, and reform | That the Tasmanian Emergency Management Plan includes a comprehensive all hazards communications policy and plan. |
REC247-0876 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service reviews its approach to blacking out and mopping up, including its policies, operating procedures and training. |
REC247-0940 | 32 - Doctrine, standards, and reform | That the Government actively support the timely development and implementation of an ongoing Strategic Fuel Management Plan. |
REC247-0897 | 32 - Doctrine, standards, and reform | That a standing plan is developed to manage the transition from immediate recovery to medium and long-term recovery, and arrangements are made to ensure this plan can be effectively implemented in a timely way. |
REC247-0867 | 7 - Inter-agency communication | That Tasmania Fire Service reviews the communication systems used for all emergency management operations, ensures operators are qualified, and ensures there is appropriate accountability. |
REC247-0913 | 32 - Doctrine, standards, and reform | That the State Fire Commission structures its Tasmania Bushfire Safety Policy so policy outcomes are identifiable and progress in achieving outcomes can be evaluated. |
REC247-0874 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service reviews operational practices to ensure there is continuity of fire operations when fire suppression action is required. |
REC247-0932 | 37 - Funding | That the resources available to the Parks and Wildlife Service, to manage bushfire risk following the recent increase in land under its tenure, is reviewed. |
REC247-0883 | 32 - Doctrine, standards, and reform | That Tasmania Police ensures planning for emergency operations includes a proactive approach wherever possible. |
REC247-0864 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service reviews its position on fire ground management to determine whether a unified command model at the fire ground should be adopted. |
REC247-0912 | 32 - Doctrine, standards, and reform | That the State Fire Commission finalise its position on the Tasmania Bushfire Safety Policy without further delay. |
REC247-0872 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service considers what adjustments may be necessary to the promotion and use of the Six Operational Priorities to ensure plans are suitable for the circumstances of each fire. |
REC247-0930 | 32 - Doctrine, standards, and reform | That the State Emergency Management Committee determine suitable risk management tools, such as the Bushfire Risk Assessment Model, and encourages their use in assessing bushfire risk in a consistent manner. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2599 | 32 - Doctrine, standards, and reform | That the MFS, CFS and SES be incorporated into a departmental structure under the direction of a Chief Executive based on interstate developments over the past two decades, which establishes this arrangement as the benchmark for the governance of Emergency Services in Australia. The MFS, CFS and SES would operate as separate units under the ultimate direction of the CEO. |
REC244-2626 | 32 - Doctrine, standards, and reform | Section 70 (5) be amended to preclude a person from being elected as a group officer, brigade captain or brigade lieutenant if he or she is an employee of the CFS. |
REC244-2609 | 32 - Doctrine, standards, and reform | That the proposed ‘Permit Information Management System’ (PIMS) be implemented as soon as possible and incorporated into the Call Receipt and Dispatch process. Following implementation, amend Regulation 33 (5) (d) and (10) (c) in line with the automated notification process. |
REC244-2633 | 32 - Doctrine, standards, and reform | Amend Section 143 to strengthen the capacity of the ESOs to recover outstanding debts (e.g. penalty for late payment provisions). |
REC244-2614 | 32 - Doctrine, standards, and reform | Consider the amendment of Section 82 (2) to include the power to order the cessation of harvesting or any other actions (including the lighting of fires authorised under Section 81) that because of the weather conditions, may cause a fire, if ignited, to get out of control. |
REC244-2625 | 32 - Doctrine, standards, and reform | Sections 42 and 97 be amended to provide greater flexibility in the engagement of contractors by Senior MFS and CFS Officers. Consideration be given to providing similar powers in Section 118 to enable the SES to engage contractors. |
REC244-2608 | 32 - Doctrine, standards, and reform | Consider whether Regulation 71 be amended to extend the range of offences for which expiation fees apply to include a breach of any permit condition imposed by an authorised officer. |
REC244-2632 | 32 - Doctrine, standards, and reform | Section 142 be amended to include the SES |
REC244-2613 | 32 - Doctrine, standards, and reform | Should the State Bushfire Coordination Committee continue to exist under the F&ES Act amend Section 94 (4) (c) to refer to the ‘State Bushfire Coordination Committee’. |
REC244-2624 | 32 - Doctrine, standards, and reform | The F&ES Act be amended to clarify the meaning of ‘closure’ in Section 38 and that provisions relating to the extension and rescission of closure orders be reviewed. |
REC244-2607 | 32 - Doctrine, standards, and reform | Amend Regulation 41 to exempt the use of prescribed appliances when a Hot Work Permit compliant with AS1674.1 has been issued. |
REC244-2630 | 32 - Doctrine, standards, and reform | Clarify that Section 128 of the F&ES Act is not compromised by any other legislation. |
REC244-2612 | 32 - Doctrine, standards, and reform | Develop a code of practice which is referenced by the F&ES Act for burning off including the option to issue seasonal permits for relevant purposes throughout the State. |
REC244-2623 | 32 - Doctrine, standards, and reform | That the F&ES Act be amended to enable fire safety inspections in and outside fire districts. |
REC244-2603 | 32 - Doctrine, standards, and reform | Should the State Bushfire Coordination Committee continue to exist under the F&ES Act, then Section 71 of the Act be amended to provide for the appointment of an independent presiding member of the committee. |
REC244-2629 | 32 - Doctrine, standards, and reform | The power of the Chief Officer to appoint officers from the staff of the SES as well as appoint volunteer officers of the SES be clarified. A command structure section (similar to Section 70) be incorporated into the Act and include the power to register, appoint, disqualify and terminate volunteer members. |
REC244-2611 | 32 - Doctrine, standards, and reform | Review the format and necessity for Schedules 9 and 10 of the Regulations |
REC244-2636 | 32 - Doctrine, standards, and reform | Amend the F&ES Act to provide for the operation of interstate fire and emergency service workers in South Australia. The issue of liability may need to be considered. |
REC244-2622 | 32 - Doctrine, standards, and reform | Amend Sections 28, 61 and 110 to provide the Chief Officers greater flexibility over organisational structure. |
REC244-2602 | 32 - Doctrine, standards, and reform | That South Australia’s Hazard Leader Plan for Rural Fire, prepared in accordance with the State Emergency Management Plan, replace the F&ES Act requirement for a separate State Bushfire Management Plan. |
REC244-2628 | 32 - Doctrine, standards, and reform | Amend the F&ES Act to reflect the SES expanded responsibilities as Hazard Leader for ‘Extreme Weather’ including their community education role. |
REC244-2610 | 32 - Doctrine, standards, and reform | Amend Regulation 33 (6) and (8) to include respectively ‘notice given’ and ‘permit application’ using the online medium. |
REC244-2635 | 32 - Doctrine, standards, and reform | The requirement to consult with members of the unit and the SESVA before an SES Unit is dissolved should remain but the need for public meetings be removed from the regulations. |
REC244-2615 | 32 - Doctrine, standards, and reform | In consultation with stakeholders including CFA, develop a Forest Industry Brigade standard for inclusion in the Fire and Emergency Services Regulations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2759 | 24 - Govt responsibility | That the new Chief Executive Officer Portfolio Business be accountable for delivering the reformed Communications Centre arrangement by the 2017–18 financial year in time for the Commonwealth Games of 2018. |
REC239-2678 | 24 - Govt responsibility | That probation and parole should continue to work together with the Queensland Police Service to reduce the risk of reoffending and reduce crime. |
REC239-2704 | 32 - Doctrine, standards, and reform | That the current SES memoranda of agreement between the Department of Community Safety and local governments be revised to include a clear statement as to the command and control arrangements between State and respective local governments. These arrangements should also be reflected in the local disaster management plans. |
REC239-2718 | 32 - Doctrine, standards, and reform | That the Department of Fire and Emergency Services be created through the renaming and amendment to the existing Fire and Rescue Service Act 1990 including: |
REC239-2685 | 24 - Govt responsibility | That primacy of control for disaster operations remains with the Queensland Police Service and be reinforced. |
REC239-2735 | 32 - Doctrine, standards, and reform | That the new Department of Fire and Emergency Services develop a common doctrine to protect people from fire and emergencies. |
REC239-2660 | 24 - Govt responsibility | That Queensland Corrective Services be transferred to the Department of Justice and Attorney-General by a machinery-of-Government change as soon as is practicable. |
REC239-2696 | 32 - Doctrine, standards, and reform | That the Queensland Police Service Disaster Management Unit be given responsibility for production of the State disaster management plan for the State Disaster Management Group’s approval. |
REC239-2756 | 32 - Doctrine, standards, and reform | That the Chief Executive Officer Portfolio Business consider ‘big data’ problems and solutions in line with the outcome of the efficiency review into the Queensland Police Service and ensure alignment with whole of government solutions. |
REC239-2676 | 32 - Doctrine, standards, and reform | That any changed arrangements to the operations of Queensland Corrective Service ensure anti-corruption, prisoner management, and accountability processes are defined and established. |
REC239-2702 | 32 - Doctrine, standards, and reform | That the Queensland Police Service and SES develop clear operational protocols to ensure that SES assistance is not exploited. |
REC239-2782 | 24 - Govt responsibility | That transparency of the Ministerial direction be achieved through publishing and monitoring for effectiveness. |
REC239-2683 | 37 - Funding | That the Office of Portfolio Business follows the same budget processes as other agencies. |
REC239-2717 | 32 - Doctrine, standards, and reform | That the ‘Functions of Chief Executive’ under the Disaster Management Act 2003 are amended to remove those functions that will become the role of the proposed Inspector General of Emergency Management. |
REC239-2732 | 24 - Govt responsibility | There be a formation of an Office of Portfolio Business, providing support and governance across a range of corporate functions, which are essential to the delivery of frontline services. The Review team considers that the functions of the Operations Business and Strategy Directorate should become part of that Office and that any exception should be carefully considered by those charged with implementation of approved recommendations. |
REC239-2657 | 24 - Govt responsibility | That negotiation takes place between Queensland Health and the Queensland Ambulance Service to determine the broad governance requirements of any such arrangements. |
REC239-2695 | 32 - Doctrine, standards, and reform | That the Disaster Management Act 2003 be amended to: |
REC239-2755 | 32 - Doctrine, standards, and reform | That the Queensland Police Service bring this practice to the attention of the Privacy Commissioner and discuss a new service wide policy on the retention of data to ensure that their officers are not acting in breach of the law. |
REC239-2668 | 32 - Doctrine, standards, and reform | That as part of reviewing its legislation, Queensland Corrective Service should ensure that amendments be made to ensure a stronger onus is placed upon a more efficient process to receive prisoners with a view to reducing the time spent in police watch houses. |
REC239-2701 | 24 - Govt responsibility | That the Inspector General Emergency Management provide continuing advice to Government on the level of interoperability in disaster management arrangements, as well as the level of interoperability being achieved within the new portfolio. |
REC239-2780 | 37 - Funding | That should the Westgate project proceed, that consideration must be given to opportunities to partner the investment with the private and public sectors. The business case should also consider alternative facilities such as Australian Defence Force sites. |
REC239-2682 | 37 - Funding | That a budget based on the desired functional accountabilities should be appropriated to the Portfolio Business as part of the Government budget process. |
REC239-2712 | 24 - Govt responsibility | That Emergency Management Queensland be integrated with the current Queensland Fire and Rescue to become the Department of Fire and Emergency Services. |
REC239-2728 | 32 - Doctrine, standards, and reform | That the Fire and Rescue Act 1990 be amended so that Commissioner’s position is not limited to a “person with professional experience in fire prevention and fire fighting”. |
REC239-2655 | 24 - Govt responsibility | That the Queensland Ambulance Service is transferred to Queensland Health by a machinery-of-Government change as soon as is practicable and that the Commissioner report directly to the Director General Queensland Health. |
REC239-2693 | 32 - Doctrine, standards, and reform | That the presence of police in State Disaster Coordination Centre response teams is mandated and formalised through documented standard operating procedures. |
REC239-2753 | 37 - Funding | That the proposed Chief Executive Officer Portfolio Business be responsible for developing a cost attribution model for portfolio agencies, including the Queensland Police Service, as a priority. |
REC239-2666 | 32 - Doctrine, standards, and reform | That a system should be designed so that the prisoner and the prisoner’s prescribed drugs are treated as one and therefore travel together through the system for whatever purpose. |
REC239-2700 | 24 - Govt responsibility | That the position of Inspector General Emergency Management (in addition to some of the responsibilities of the chief executive officer under the current Disaster Management Act 2003) will: |
REC239-2779 | 37 - Funding | That a new business case for Westgate project should be prepared by an independent party. |
REC239-2681 | 37 - Funding | That the funding model for the Portfolio Business is not based on fee- for-service arrangements or notional contributions from the operational services. |
REC239-2708 | 24 - Govt responsibility | That the role of the Inspector General Emergency Management not extend to conducting reviews on behalf of agencies and that the role consider the effectiveness of all agencies and how their work contributes to a whole of Government response. |
REC239-2723 | 1 - Land-use and building regs | That the Queensland Fire and Rescue Service examine alternative contractual arrangements with building owners which would reduce the need for physical attendance at alarm activations. |
REC239-2687 | 24 - Govt responsibility | That funding, staffing and responsibility associated with administration of the NDRP be transferred from Emergency Management Queensland to the Department of Local Government, Community Recovery and Resilience. |
REC239-2749 | 24 - Govt responsibility | That the Prostitution Licensing Authority be moved to the Department of Justice and Attorney General Office of Fair Trading. |
REC239-2662 | 24 - Govt responsibility | That responsibility for prisoner transport and non-managerial roles within the larger watch-houses is transferred to Queensland Corrective Service. |
REC239-2699 | 24 - Govt responsibility | That the Minister establish a public sector office to be headed by an Inspector General of Emergency Management. The Inspector General of Emergency Management will be responsible for most of the functions listed under part 16A of the current Disaster Management Act 2003. |
REC239-2679 | 24 - Govt responsibility | To remove the Queensland Ambulance Service and Queensland Corrective Services from the Department of Community Safety—we recommend that it be renamed the Department of Fire and Emergency Services and be led by a Commissioner. |
REC239-2705 | 32 - Doctrine, standards, and reform | That the Inspector General Emergency Management assess the effectiveness of plans and policy in relation to SES deployment and command and control. |
REC239-2721 | 24 - Govt responsibility | That the Chief Executive Officer Portfolio Business collaborate with the two portfolio Commissioners to: |
REC239-2686 | 24 - Govt responsibility | That primacy of control should rest with the State Disaster Coordinator. This position should, by default, be the Deputy Commissioner, Regional Operations, Queensland Police Service. |
REC239-2661 | 24 - Govt responsibility | That Queensland Corrective Service remains a separate program within the Department of Justice and Attorney-General so that while opportunities for improved services and efficacy can be realised, there is a clear separation from the youth justice services. |
REC239-2697 | 32 - Doctrine, standards, and reform | That the Queensland Police Service Disaster Management Unit work with emergency management staff in the new portfolio to produce the State disaster management plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0832 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service investigate use of appropriate modelling, such as PHOENIX RapidFire and the Bayesian Network analysis, to quantify the level of bush fire risk to critical values and assets. |
REC237-0818 | 32 - Doctrine, standards, and reform | That section 9(4)(b) of the Rural Fires Act 1997, which sets out the functions of the NSW Rural Fire Service, be amended to include protecting infrastructure, environmental, economic, cultural, agricultural and social assets from damage. |
REC237-0823 | 32 - Doctrine, standards, and reform | That section 74 of the Rural Fires Act 1997 be amended to require public authorities to report monthly to the Commissioner of the NSW Rural Fire Service on activities undertaken to reduce bush fire hazards on managed land during the preceding month and the reasons why any planned activities did not take place. |
REC237-0831 | 32 - Doctrine, standards, and reform | That Bush Fire Management Committees be required to take into account fuel age and fire frequency thresholds when developing Bush Fire Risk Management Plans |
REC237-0817 | 32 - Doctrine, standards, and reform | That section 3(c) of the Rural Fires Act 1997, which sets out the objects of the Act, be extended to include protecting infrastructure, environmental, economic, cultural, agricultural and social assets from damage. |
REC237-0822 | 32 - Doctrine, standards, and reform | That section 74 of the Rural Fires Act 1997 be amended to require public authorities to report to the Commissioner of the NSW Rural Fire Service within one month of the end of the financial year on activities undertaken to reduce bush fire hazards on managed land during the preceding financial year. |
REC237-0827 | 32 - Doctrine, standards, and reform | The Panel notes and endorses the NSW bush fire management system based on a multi-agency, tenure blind approach using locally focused Bush Fire Management Committees, Bush Fire Management Plans and the Bush Fire Environmental Assessment Code as best practice. |
REC237-0821 | 32 - Doctrine, standards, and reform | That the definition of “bush fire hazard reduction work” in the Dictionary of the Rural Fires Act 1997 be amended to include the establishment or maintenance of fire trails. |
REC237-0826 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service hold discussions with the Commonwealth Department of Sustainability, Environment, Water, Population and Communities about hazard reduction and roadside vegetation, including potential changes to the NSW Bush Fire Environmental Assessment Code. |
REC237-0834 | 37 - Funding | That the NSW Rural Fire Service apply for funding from the NSW Treasury for the development of a multi-agency business case for a BRIMS replacement that includes internal management, risk communication, community engagement capability and publishing activities on websites. |
REC237-0820 | 32 - Doctrine, standards, and reform | That the Rural Fires Act 1997 be amended to allow the Commissioner of the NSW Rural Fire Service to carry out hazard reduction on land without the consent of the owner after reasonable attempts to contact the landowner have failed, without serving a notice under section 66 of the Rural Fires Act. |
REC237-0825 | 1 - Land-use and building regs | That the NSW Rural Fire Service hold discussions with the Department of Planning and Infrastructure and Local Government NSW on ways to improve compliance with development consents under section 76A of the Environmental Planning and Assessment Act 1979. |
REC237-0833 | 37 - Funding | That the NSW Rural Fire Service and the NSW Treasury explore ways to ensure that unspent hazard reduction funds be carried over to the next financial year in a timely manner and to ensure that hazard reduction funding has a seamless transition from one financial year to the next. |
REC237-0819 | 32 - Doctrine, standards, and reform | That section 56 of the Rural Fires Act 1997 be amended to give the Commissioner of the NSW Rural Fire Service the power to direct a Bush Fire Management Committee to amend its Bush Fire Risk Management Plan if it is inadequate, in the opinion of the Commissioner. |
REC237-0824 | 32 - Doctrine, standards, and reform | That section 100I of the Rural Fires Act 1997 be amended to allow hazard reduction certificates to be issued for annual low impact works for a period of three years, where appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0552 | 7 - Inter-agency communication | Communications planning for geographic regions with recognised black spots and specific communications challenges should be prepared in advance of an emergency in order to support the IMT Communications Planning Officer |
REC226-0579 | 32 - Doctrine, standards, and reform | Legislative change may be needed to enable FES A to better manage fire- fighting resources across the state. |
REC226-0577 | 7 - Inter-agency communication | A system of vehicle tracking should be fitted to all fire appliances and linked to the common operating picture. Good communications planning is essential for good command and control. |
REC226-0571 | 24 - Govt responsibility | A review of the manner in which resourcing is conducted across all agencies needs to occur with a review identifying the best manner to ensure all agencies adapt to the same process. |
REC226-0569 | 32 - Doctrine, standards, and reform | Section 13 arrangements need to be clarified across key agencies. |
REC226-0581 | 24 - Govt responsibility | Increased acceptance of mutual obligations will be fundamental to the management of fire risk across the state |
REC226-0568 | 24 - Govt responsibility | State-wide all agency reporting should be established to facilitate the interactions of emergency management agencies, support agencies and governments. |
REC226-0580 | 32 - Doctrine, standards, and reform | The role of district and local emergency management committees should be reviewed to ensure they are appropriately engaged in the active management of emergencies across the PPR R continuum |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0539 | 32 - Doctrine, standards, and reform | WA fire agencies adopt a common set of standing orders, operational procedures, training and competencies for rural firefighting that are produced in hard copy, leading to integrated multi-agency training, IMTs, Regional and State coordination/control centres. |
REC225-0537 | 7 - Inter-agency communication | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
REC225-0536 | 32 - Doctrine, standards, and reform | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
REC225-0534 | 32 - Doctrine, standards, and reform | Once Recommendation 1 has been actioned, all agencies give greater priority to the promulgation of Red Flag warnings in order to enhance situational awareness on the fireground. |
REC225-0531 | 32 - Doctrine, standards, and reform | Critical operational procedures such as ‘Red Flag Warnings’, on a common fireground need to be consistent across DFES, DEC and Local Government. In particular, the operational procedure of Red Flag Warnings needs to be adopted by all WA fire agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1670 | 32 - Doctrine, standards, and reform | Bushfires NT create a bushfire management strategy and emergency response procedures framework including the criteria that define the escalation and response requirements for all incidents up to and including the establishment of an EOC, applicable for all regions across the Territory. |
REC209-1662 | 37 - Funding | Identify where Australian Government funding is available and apply for funding for integrating weed management, controlled burning, bushfire management and carbon farming initiatives. |
REC209-1660 | 24 - Govt responsibility | Better alignment between divisions within DNRETAS be achieved through the development of an integrated strategy that addresses the combined objectives of weed management, land management, carbon farming and biodiversity management using fire across the Territory. |
REC209-1659 | 32 - Doctrine, standards, and reform | Regional Fire Management Plans be reviewed for all regions prior to the start of each fire season. |
REC209-1678 | 32 - Doctrine, standards, and reform | That the Bushfires Act and Regulations be reviewed and modernised after the implementation of the recommendations of this review. |
REC209-1654 | 24 - Govt responsibility | That the Director Bushfires NT NOT be appointed as a member of Council. |
REC209-1677 | 37 - Funding | A specialist investigation be conducted, using expertise from NT Treasury, to identify more appropriate ways to optimise the use of available funding for bushfire management. |
REC209-1642 | 37 - Funding | That a cost benefit analysis of an integrated ICT desktop and portable capability including iPads and iPhones for all operational personnel be conducted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2883 | 32 - Doctrine, standards, and reform | Start a project to introduce organisational process thinking with a view to standardising processes and product specifications. |
REC207-2874 | 32 - Doctrine, standards, and reform | Formalise and standardise service levels provided to emergency services. |
REC207-2893 | 37 - Funding | Explore options to obtain revenue from advertising on the Bureau’s website |
REC207-2880 | 32 - Doctrine, standards, and reform | Ensure the Bureau puts in place necessary planning and governance arrangements to develop its bid for capital funding to maintain its critical supercomputing capacity |
REC207-2892 | 37 - Funding | Apply a consistent cost-recovery model to all services delivered to state/territory fire agencies. |
REC207-2879 | 37 - Funding | Firm up approval processes and funding for any departures from provision of the basic product set |
REC207-2890 | 37 - Funding | Review and rebalance relative investment in long term climate modelling and medium-term seasonal outlook. |
REC207-2877 | 37 - Funding | Explore opportunities to re-phase investments in large scale projects and programs such as the Strategic Radar Enhancement Program, the NexGen Forecast and Warning System Products and the Improving Water Information Program. |
REC207-2889 | 37 - Funding | Review level of investment in research activities to free up budget and reduce pressure on computing capacity |
REC207-2875 | 32 - Doctrine, standards, and reform | Agree clear allocation of responsibilities to state and local government for flood management, with defined boundaries on the Bureau’s role and: |
REC207-2884 | 32 - Doctrine, standards, and reform | Focus leadership practices to re-orient culture away from customisation and experimentation and towards reliable, efficient and consistent documented processes |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1899 | 24 - Govt responsibility | Local governments’ uncertainty about their legal liability is a barrier to effective climate change adaptation. State governments should clarify the legal liability of councils with respect to climate change adaptation matters and the processes required to manage that liability. |
REC205-1898 | 24 - Govt responsibility | To help clarify roles and responsibilities of local government for climate change adaptation, the state and Northern Territory governments should publish and maintain a comprehensive list of laws that delegate regulatory roles to local governments. This would assist both state and local governments to assess whether local governments have the capacity to discharge their roles effectively. |
REC205-1896 | 24 - Govt responsibility | Australian governments should implement policies that help the community deal with the current climate by improving the flexibility of the economy. This would also build adaptive capacity to deal with future climate change. This includes reforms to: |
REC205-1904 | 24 - Govt responsibility | State and territory taxes and levies on general insurance constitute a barrier to effective adaptation to climate change. State and territory governments should phase out these taxes and replace them with less distortionary taxes. |
REC205-1895 | 32 - Doctrine, standards, and reform | Reforms to address barriers to effective climate change adaptation should be assessed on a case-by-case basis to determine whether they are likely to deliver net benefits to the community. This should include consideration of any risks to their implementation. |
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0297 | 32 - Doctrine, standards, and reform | The role of district and local emergency management committees should be reviewed to ensure they are appropriately engaged in the active management of emergencies across the PPR R continuum |
REC203-0296 | 32 - Doctrine, standards, and reform | Legislative change may be needed to enable FES A to manage fire-fighting resources across the state. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0252 | 7 - Inter-agency communication | FESA must actively manage the transition to WAERN and provide alternative means for regional crews to communicate when in areas where WAERN is not operated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1719 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-0341 | 32 - Doctrine, standards, and reform | The State Government give legislative effect to the Planning for Bush Fire Protection Guidelines. |
REC200-1727 | 24 - Govt responsibility | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-0376 | 1 - Land-use and building regs | State and locals governments: a) recognise that regardless of future declarations of bushfire prone areas, the existing planning and building problems in the Perth Hills related to bushfire risk will persist; b) urge residents in these areas to retrofit their homes and evaporative air conditioners in compliance with AS 3959 - 2009; c) examine options to retrospectively bring these areas into compliance with Planning for Bushfire Protection Guidelines. |
REC200-1694 | 24 - Govt responsibility | The State Government give its full support to the Western Australian Local Government Association's Send to Solve initiative. |
REC200-1704 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-0385 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-1717 | 24 - Govt responsibility | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-0340 | 1 - Land-use and building regs | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-1725 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-0372 | 7 - Inter-agency communication | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-1682 | 24 - Govt responsibility | The State Government give legislative effect to the Planning for Bush Fire Protection Guidelines. |
REC200-1703 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority develop formal procedures for mandating the completion of Incident Action Plans, ensuring the documents are detailed and that they record critical decision making. |
REC200-0382 | 32 - Doctrine, standards, and reform | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-1716 | 24 - Govt responsibility | State and locals governments: |
REC200-0339 | 32 - Doctrine, standards, and reform | Emergency Management Western Australia establish an inter-agency working group to continue the development of the new single emergency services Act. |
REC200-1723 | 24 - Govt responsibility | The State Government restructure the Fire and Emergency Services Authority as a Department. As part of this restructure, Emergency Management Western Australia should either |
REC200-0363 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority develop formal procedures for mandating the completion of Incident Action Plans, ensuring the documents are detailed and that they record critical decision making. |
REC200-1681 | 24 - Govt responsibility | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-1702 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority immediately comply with the provisions of WESTPLAN BUSHFIRE and formally declare incidents at their appropriate level and document and communicate those decisions in a similar way to the systems used by the Department of Environment and Conservation and the Western Australian Police. |
REC200-0380 | 32 - Doctrine, standards, and reform | The State Emergency Management Committee amend State Emergency Management Policy 4.1 (Operational Management) to: give clear and explicit direction about when and how an incident should be declared clearly articulate the actions to be taken clearly define accountabilities provide detailed criteria for elevating issues and engaging other agencies. |
REC200-1713 | 7 - Inter-agency communication | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-1721 | 32 - Doctrine, standards, and reform | The State Government amend section 50 of the Emergency Management Act 2005 to allow the Chair of the State Emergency Coordination Group to declare an emergency situation. |
REC200-0362 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority immediately comply with the provisions of WESTPLAN BUSHFIRE and formally declare incidents at their appropriate level and document and communicate those decisions in a similar way to the systems used by the Department of Environment and Conservation and the Western Australian Police. |
REC200-0379 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-1699 | 24 - Govt responsibility | The State Government ensure that the continued development of the Fire and Emergency Service Authority's Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost-effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-1709 | 32 - Doctrine, standards, and reform | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
REC200-1720 | 32 - Doctrine, standards, and reform | The State Emergency Management Committee amend State Emergency Management Policy 4.1 (Operational Management) to: |
REC200-0346 | 1 - Land-use and building regs | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-1728 | 24 - Govt responsibility | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-0377 | 1 - Land-use and building regs | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-1696 | 32 - Doctrine, standards, and reform | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-1707 | 1 - Land-use and building regs | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0313 | 32 - Doctrine, standards, and reform | The Fire Services expedite programmed work on joint operational command and control, including standards, procedures and training |
REC195-0312 | 32 - Doctrine, standards, and reform | The Fire Services Commissioner ensures that joint fireground command and control, integration and escalation procedures are developed, particularly for ‘fastrunning’ fires |
REC195-0311 | 32 - Doctrine, standards, and reform | The Fire Services ensure that agency specific operational procedures fully align with the arrangements. |
REC195-0322 | 7 - Inter-agency communication | The Fire Services investigate the reported technical communication issues for this fire |
REC195-0321 | 7 - Inter-agency communication | The Fire Services move towards a common and more disciplined approach to fireground communications. |
REC195-0319 | 7 - Inter-agency communication | The Fire Services introduce systems, procedures and operational training that promote information sharing and consistent situational awareness at every level, including to and from the fireground. This should include agencies such as police members on duty at roadblocks |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0109 | 1 - Land-use and building regs | It is sensible that, in considering planning development proposals on land adjacent to the DEC estate, that development authorities invite comment from DEC on the fire management consequences of development proposals. |
REC183-0108 | 32 - Doctrine, standards, and reform | DEC should consider publishing a new reference document that describes policy, doctrine and key systems of work of the fire management system. This document would be a “brief case” or “back pack” reference and would be reviewed annually and issued to all senior staff and fire management personnel. |
REC183-0107 | 32 - Doctrine, standards, and reform | The DEC Fire Management Policy should be reviewed and updated. |
REC183-0115 | 32 - Doctrine, standards, and reform | The Hazard Management Agency for bushfire has not been defined. Defining the HMA for bushfire should be addressed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0123 | 32 - Doctrine, standards, and reform | FESA implements measures that will ensure unity and clarity of command. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0103 | 24 - Govt responsibility | That the Minister for Emergency Services consider the appointment of the Chief Executive Officer, Department of Environment and Conservation as a member of the State Emergency Management Committee. |
REC173-0100 | 32 - Doctrine, standards, and reform | The prioritising of the critical amendments to the Bush Fires Act 1954 recommended by the Community Development and Justice Standing Committee that relate to fire management, ie: a. Fire and Emergency Services Authority (FESA)‘s ability to assume control of a fire in specific circumstances b. Amendments to the definition of property c. Providing FESA with the authority to declare a total fire ban |
REC173-0102 | 32 - Doctrine, standards, and reform | That further amendments be made to the Bush Fires Act 1954 be drafted to provide fire response agencies with the necessary authorisation and statutory protection to respond to a fire on private property, or land that Local Government, Department of Environment and Conservation (DEC) or FESA is responsible for, until such time as the responsible agency is able to attend and take control. The amendments to be drafted, in conjunction with the urgent progression of critical amendments as recommended by the Community Development and Justice Standing Committee. |
REC173-0104 | 1 - Land-use and building regs | That FESA assess the cost and other implications of proposed changes to bushfire prone zone declarations which would allow the whole State to be declared bushfire prone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0003 | 32 - Doctrine, standards, and reform | All incidents where the HMA delegates the authority to manage suppression operations to another agency on its behalf, should be achieved via a written delegation setting out the scope, limitations and duration of the delegation. |
REC172-0002 | 32 - Doctrine, standards, and reform | The Emergency Management Act 2005 is amended to provide a mechanism for one HMA to transfer responsibility to another HMA and ensure that both HMA’s are provided the powers and protection necessary under that Act. |
REC172-0001 | 32 - Doctrine, standards, and reform | The Emergency Management Regulations 2006 be urgently amended to determine a HMA(s) for bushfire. |
REC172-0043 | 7 - Inter-agency communication | There needs to be a system that allows laptop computers brought to an incident to be configured at the start of the season and allow them to be easily activated to the correct configuration when they arrive at the incident. |
REC172-0021 | 32 - Doctrine, standards, and reform | Unassigned resources arriving at incidents should be encouraged to make themselves known and to undertake alternate duties. |
REC172-0042 | 7 - Inter-agency communication | Portable, reliable mobile repeaters are required to provide radio communications into areas not covered by existing repeater networks. These repeaters need the capacity to be linked. |
REC172-0018 | 32 - Doctrine, standards, and reform | The Interagency Guidelines need to be amended to reflect what is operationally possible with regard to risk management rather than what is required to achieve an absence of risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0084 | 32 - Doctrine, standards, and reform | The State Disaster Management Group focus on Disaster Management strategy and policy with sub-committees or appropriate levels in the Disaster Management system assigned detailed disaster planning or risk management assessment roles. New group members be provided with an induction briefing about the State's Disaster Management arrangements by the Executive Officer prior to attending their first meeting. |
REC165-0092 | 32 - Doctrine, standards, and reform | Executive Officers to DDCs be serving Police Officers. Regional and Area officers of EMQ be members of Local and District Disaster Management Groups to enable them to fulfil their Statewide support and governance roles. |
REC165-0099 | 32 - Doctrine, standards, and reform | The suggested summary of legislative changes guide the legislative response to the report incorporating consultation with key stakeholders at State, District and Local levels. |
REC165-0083 | 32 - Doctrine, standards, and reform | The Chairperson of SDMG (where leadership is not already defined in relevant National Plans) nominate a senior officer to assume overall responsibility for control and coordination of each disaster event to ensure a decisive and effective response. At Local level the Act provide for the CEO in consultation with the LDMC to appoint a public official/s with required training and competence as Local Controller. |
REC165-0091 | 32 - Doctrine, standards, and reform | EMQ resources be directed to continually improving, monitoring and regularly evaluating the State's Disaster Management system with a priority focus on providing support to Local Government levels including interlinking exercises involving District and State arrangements. |
REC165-0098 | 24 - Govt responsibility | The SDMG take into account key improvement initiatives and change processes suggested when deciding on an effective implementation strategy for agreed recommendations. |
REC165-0080 | 32 - Doctrine, standards, and reform | The State Disaster Management Plan incorporate linkages with all Lead Agencies and officers in control of National Plan or Agreement response. All of these Plans and Agreements should have a formal requirement to ensure officers in charge work within the State's Disaster Management framework to deliver Disaster Management responses. |
REC165-0090 | 7 - Inter-agency communication | The SDMG lead an initiative to integrate and/or inter-connect all of the control centres involved at all levels of the Disaster Management system in Queensland as part of the project to integrate State communications. |
REC165-0097 | 24 - Govt responsibility | Revised governance arrangements be implemented involving Disaster Management Groups at the three levels supported by EMQ as outlined in this report to achieve continuous improvement in the Disaster Management arrangements in the State. A new provision in Section 5 emphasise the discretion available to all involved in the Disaster Management system to take action to prevent impending loss of life even if contrary to the agreed arrangements. |
REC165-0079 | 32 - Doctrine, standards, and reform | The Act be amended (Sections 45, 46, 47) to enable verbal directions in times of disaster responses from a State Controller to DDC to Local Controller, which must be committed to writing promptly to formalise the record. |
REC165-0088 | 32 - Doctrine, standards, and reform | The State Disaster Management Act be strengthened by a description of the phases of Disaster Management with emphasis on the key elements within each phase including the recovery phase; Lead Agencies and nominated leaders in each area of Queensland for each of the four key elements of recovery be identified and provided with the appropriate training and familiarisation of their role to ensure the adequacy of planning at District and Local level throughout Queensland; Lead Agencies be responsible for maintaining strong relationships with counterparts at the Federal Government level to ensure necessary Federal support for State and Local recovery initiatives after disaster events; Response arrangements remain in place until the State Controller is satisfied that recovery leadership arrangements are in place at Local, District and State levels; Recovery leadership and support from State level remain in place until local recovery is substantially completed. |
REC165-0094 | 32 - Doctrine, standards, and reform | The Act be amended to make it clear that Disaster Controllers/Coordinators at all levels are to be authorised public officials with the necessary training and authority to properly discharge the role and provide an effective direct line of support, coordination and control of disaster events. The Act and State Plan provide guidance about appropriate role and functions of elected representatives during all disaster event phases. The Major Incidents Group and State Security Committee be merged to become the State Disaster and Security Council with role as suggested in this report. |
REC165-0078 | 32 - Doctrine, standards, and reform | The basic tenet of a local community response as the foundation of Queensland's Disaster Management framework, with a clear description of the relationships between the levels and description of the phases of Disaster Management, needs to be more strongly emphasised in the "objects" of the legislation and "how objects are to be achieved". |
REC165-0093 | 32 - Doctrine, standards, and reform | The Department of Community Safety (through EMQ) be assigned in the Act with the responsibility to develop, maintain, monitor and continuously improve the State's Disaster Management arrangements and systems. The Executive Director, EMQ, be a member of SDMG with the Director-General, Department of Community Safety. The position of Executive Officer, SDMG, be assigned appropriate support roles to SDMG. An officer other than the Executive Director, EMQ, or the State Controller of a disaster event, perform the role of Executive Officer to the SDMG. A dedicated Assistant Commissioner of Police be assigned the role of control, coordination and overall responsibility for Queensland's response to disaster events other than those subject to National Plans and Agreements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3032 | 32 - Doctrine, standards, and reform | That the Offshore Petroleum and Greenhouse Gas Storage Act 2006 and its subsidiary regulations be amended to enable National Offshore Petroleum Safety Authority to have a broader range of graduated compliance tools including the ability to impose a civil fine on an operator per day of non compliance with an improvement or prohibition notice. Legislation should also be considered that would enable National Offshore Petroleum Safety Authority to make public, with appropriate safeguards, specific information concerning its enforcement actions including the name of the operator, the breach, and the enforcement action required including potential penalties. |
REC161-3038 | 32 - Doctrine, standards, and reform | We recommend that the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations (MOSO) be amended to ensure that the safety case for a floating facility specifically identifies when command structure changes occur (which may be well before departing the site and associated zone). We also recommend that the OPGGS Act be amended so that a vessel becomes a facility when any part of it comes within 500 metres of the site and continues to be a facility until no part of the vessel remains within 500 metres of the site. |
REC161-3025 | 32 - Doctrine, standards, and reform | That Australian Maritime Safety Authority should have a role in assuring continuing marine standards that are not inconsistent with Offshore Petroleum and Greenhouse Gas Storage Act 2006 provisions and that Australian Maritime Safety Authority needs defined powers to assist National Offshore Petroleum Safety Authority (NOPSA) in minimising risk in the offshore petroleum industry. Potential mechanisms for achieving this outcome include: providing Australian Maritime Safety Authority with defined powers and obligations under the Offshore Petroleum and Greenhouse Gas Storage Act 2006, thereby ensuring that the Authority becomes an effective inspector/regulator of vessels while they are deemed to be facilities; or revising the current Commonwealth maritime legislation disapplication provisions of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 with the aim of achieving the same goal. If it can be readily achieved and is an efficient regulatory option, we believe the first option is preferable. |
REC161-3031 | 32 - Doctrine, standards, and reform | That National Offshore Petroleum Safety Authority develop a robust risk assessment matrix for use in assessing and responding to the changing risk associated with each facility and the operator. Further, we recommend that National Offshore Petroleum Safety Authority increase auditing frequency and duration to audit each manned facility on average twice per year (covering each staff swing), but more often if the risk matrix indicates this is necessary; and that audits should average several days actually on major facilities. |
REC161-3037 | 32 - Doctrine, standards, and reform | We recommend that the Commonwealth undertake legislative change that will ensure that when any floating facility reverts to a ‘navigable form’, the relevant provisions of the Navigation Act and the OHSMI Act will apply regardless of any voyage criteria. This will help to ensure that all Australian seafarers are covered. |
REC161-3024 | 32 - Doctrine, standards, and reform | That the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations 1996 Regulations be amended to ensure that the safety case for a floating facility specifically identifies when command structure changes occur (which may be well before departing the site and associated zone). We also recommend that the Offshore Petroleum and Greenhouse Gas Storage Act 2006 be amended so that a vessel becomes a facility when any part of it comes within 500 metres of the site and continues to be a facility until no part of the |
REC161-3029 | 32 - Doctrine, standards, and reform | In relation to safety case development and compliance overall, that National Offshore Petroleum Safety Authority revise its approach to interacting with operators prior to the safety case assessment process and subsequently and direct more resources into its advisory functions. We further recommend that National Offshore Petroleum Safety Authority develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on latest information, including the interaction with the operator. Implementation should be reviewed at a senior level within National Offshore Petroleum Safety Authority. |
REC161-3036 | 32 - Doctrine, standards, and reform | That the Commonwealth and States/Northern Territory legislate to establish a properly resourced and empowered independent national safety investigation capacity to investigate serious oil and gas industry (including pipeline) incidents including near miss events that could have led to a major accident event. We further recommend that the regulatory investigatory powers under the Offshore Petroleum and Greenhouse Gas Storage Act 2006 be reviewed in the context of powers for the proposed independent national safety investigator, noting that the regulator must retain those investigatory powers necessary in order to fulfil its legislative functions. |
REC161-3023 | 32 - Doctrine, standards, and reform | That the Commonwealth undertake legislative change that will ensure that when any floating facility reverts to a ‘navigable form’, the relevant provisions of the Navigation Act and the OHSMI Act will apply regardless of any voyage criteria. This will help to ensure that all Australian seafarers are covered. |
REC161-3028 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources continue to support a duty of care safety case regime for best practice offshore petroleum industry regulation augmented to include regulation of integrity. Since the safety case is at the centre of the duty of care co-regulatory regime, we consider that the requirement for the implementation of the safety case at facilities involved in the exploitation of petroleum resources should be provided for within the Offshore Petroleum and Greenhouse Gas Storage Act 2006 itself. |
REC161-3035 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources liaise with Ministers with environmental and planning responsibilities, and if necessary Council of Australian Governments, to ensure that environmental requirements for oil and gas projects are not imposed subsequent to safety assessments and do not increase the risk of major accident events. |
REC161-3040 | 32 - Doctrine, standards, and reform | We recommend the Commonwealth consider a plain English rewrite of the Navigation Act 1912 with the aim of producing a modern, performance-based Act. |
REC161-3027 | 32 - Doctrine, standards, and reform | That powers should be conferred on National Offshore Petroleum Safety Authority to enable it to effectively regulate safety and integrity for all facilities and pipelines in the water and the WA islands which export gas by pipeline. National Offshore Petroleum Safety Authority’s authority should extend to the nearest valve on the mainland above the shore crossing. |
REC161-3033 | 32 - Doctrine, standards, and reform | That the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations 1996 regulations be amended to explicitly enable assessment of safety culture, leadership, and consideration of operator past history, motivation and current capacity in approvals of safety cases. National Offshore Petroleum Safety Authority should be able to audit against these criteria and challenge operators on these issues. |
REC161-3039 | 32 - Doctrine, standards, and reform | We recommend that AMSA should have a role in assuring continuing marine standards that are not inconsistent with Offshore Petroleum and Greenhouse Gas Storage Act (OPGGS) Act provisions and that AMSA needs defined powers to assist NOPSA in minimising risk in the offshore petroleum industry. Potential mechanisms for achieving this outcome include: providing AMSA with defined powers and obligations under the OPGGS Act, thereby ensuring that the Authority becomes an effective inspector/regulator of vessels while they are deemed to be facilities; or revising the current Commonwealth maritime legislation disapplication provisions of the OPGGS Act with the aim of achieving the same goal. If it can be readily achieved and is an efficient regulatory option, we believe the first option is preferable. |
REC161-3026 | 32 - Doctrine, standards, and reform | That the Commonwealth consider a plain English rewrite of the Navigation Act 1912 with the aim of producing a modern, performance-based Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC152-3405 | 32 - Doctrine, standards, and reform | Clarity of Role with regard to legislative and policy requirements |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3073 | 32 - Doctrine, standards, and reform | Sections 56 and 83 be repealed and replaced with a single section which unifies their provisions. |
REC151-3094 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to ‘South Australian Volunteer Fire-Brigades Association’ this be removed and replaced with, ‘Country Fire Service Volunteers Association’. |
REC151-3082 | 32 - Doctrine, standards, and reform | The Regulations be amended to include appropriate references to the Unit Managers Advisory Group (SASES) consistent with those of the Group Committee (SACFS). |
REC151-3101 | 32 - Doctrine, standards, and reform | Divisions and Subdivisions and Regulations 22 and 62 headings relating to conduct and discipline be changed to have similar wording and should include, “Conduct, Discipline and Grievance Procedures for Members”. |
REC151-3065 | 32 - Doctrine, standards, and reform | The FES Act be amended to create the position which currently has the working title of ‘Commissioner of Fire and Emergencies’ to replace the position of CE and that the FES Act be amended in places where this position is mentioned. |
REC151-3088 | 32 - Doctrine, standards, and reform | Sections 68 and 116 – provisions relating to the establishment/dissolution of SACFS Brigades and SASES Units be amended so as to retain the head of power in the principal FES Act and that the procedural provisions within each of these sections be placed in the Regulations. |
REC151-3106 | 32 - Doctrine, standards, and reform | A schedule for revocation of permits be included in the Regulations. |
REC151-3072 | 32 - Doctrine, standards, and reform | Provisions in the FES Act relating to, “land management principles” be reviewed in consultation with appropriate agencies and having due regard to the recommendations of the Wangary Coronial Inquest. |
REC151-3094 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to ‘South Australian Volunteer Fire-Brigades Association’ this be removed and replaced with, ‘Country Fire Service Volunteers Association’. |
REC151-3081 | 32 - Doctrine, standards, and reform | So as to increase the pool of volunteers from which the Minister can appoint Advisory Board members, Section 18(3)(c) and (d) be amended to include nominations from the Group Committee (SACFS) and Unit Managers Advisory Group (SASES). |
REC151-3100 | 32 - Doctrine, standards, and reform | Section 70(12) (relating to disciplinary action) be amended to include, where the officer is an employee of a government agency, the Chief Officer shall advise an appropriate representative of the agency prior to any disciplinary action being taken. |
REC151-3064 | 32 - Doctrine, standards, and reform | The FES Act be amended to include a definition of ‘operations’ and/or ‘operational’. |
REC151-3087 | 32 - Doctrine, standards, and reform | Section 90 – provisions relating to smoking, and throwing burning material be removed from the principal FES Act and placed in the Regulations. |
REC151-3105 | 32 - Doctrine, standards, and reform | With the implementation of the Ministerial Review of Bushfire Management in South Australia, the provisions in Sections 84 and 85 be reviewed in terms of enforcing hazard reduction on council or Crown land. |
REC151-3071 | 24 - Govt responsibility | The comprehensive prevention, preparedness, response and recovery (PPRR) approach to the management of bushfires as recommended by the Ministerial Review of Bushfire Management in South Australia is supported: its implementation should consider issues raised by councils and should also be considerate of the recommendations of the Wangary Coronial Inquest. |
REC151-3093 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to, ‘an officer of the National Parks and Wildlife Service’ this be removed and replaced with, ‘an officer of the Department for Environment and Heritage’. |
REC151-3076 | 32 - Doctrine, standards, and reform | Provisions in Section 11(1)(e)(i) and (ii) relating to appointments of volunteer associations to the SAFECOM Board be removed. |
REC151-3097 | 32 - Doctrine, standards, and reform | Regulation 8(4)(b) be amended to allow persons of or above 16 years of age to register as fire-fighters. |
REC151-3063 | 32 - Doctrine, standards, and reform | The preamble of the Fire and Emergency Services (FES) Act be amended to include a stronger emphasis on the strategic and policy purposes of the Commission, highlighting its key role in the governance of the emergency services sector. |
REC151-3086 | 32 - Doctrine, standards, and reform | Section 88 – requirement to carry fire extinguishers in a caravan be removed from the principal FES Act and placed in the Regulations. |
REC151-3104 | 32 - Doctrine, standards, and reform | SAFECOM in consultation with SAMFS consider the merits of amending Sections 49- 51 to replace the right to appeal from the District Court to the South Australian Industrial Relations Commission. |
REC151-3070 | 32 - Doctrine, standards, and reform | Crown law opinion be obtained to determine whether additional functions now undertaken by the Commission following the devolvement of the functions of the Security and Emergency Management Office (SEMO) require an amendment to the FES Act. |
REC151-3091 | 32 - Doctrine, standards, and reform | Regulation 48 regarding prescribed offences be amended to include Section 79(2)(e) or its equivalent under the amendment proposed in Recommendation 22 above. |
REC151-3075 | 32 - Doctrine, standards, and reform | Section 92 include the facility to issue a warrant for the relevant authority to break into land or buildings for the purposes of determining what measures have been taken for the prevention, control or suppression of fire or for the prevention of, or for dealing with, the escape of hazardous materials; and that costs and expenses in doing so are recoverable. |
REC151-3096 | 32 - Doctrine, standards, and reform | All Regulations relating to constitutions be deleted; the FES Act be amended to allow the Chief Officers to prescribe the constitution; and the process for the management of a SACFS brigade/group and a SASES unit to be in the form of an administrative instruction. |
REC151-3085 | 32 - Doctrine, standards, and reform | With the implementation of the Ministerial Review of Bushfire Management in South Australia, consideration should be given to provisions within Part 4, Division 7 of the principal FES Act which would be more appropriately placed in the Regulations. |
REC151-3103 | 32 - Doctrine, standards, and reform | Provisions be included in the Regulations for mediation in appropriate circumstances. |
REC151-3069 | 32 - Doctrine, standards, and reform | Consistent with the requirement for Emergency Service Organisations, the FES Act be amended to require South Australian Fire and Emergency Commission (SAFECOM) to submit a workforce plan to the Board. |
REC151-3090 | 32 - Doctrine, standards, and reform | Following the amendment to Section 79 as proposed above in Recommendation 22, a definition of, ‘properly constructed fire place’ and ‘properly constructed incinerator’ be included in the new Regulation. |
REC151-3111 | 32 - Doctrine, standards, and reform | Crown law opinion be obtained as to what amendments, if necessary or appropriate, are required to satisfy Recommendation 29.9(7) of the Wangary Coronial Inquest, that a dedicated bushfire prevention officer be appointed. |
REC151-3074 | 32 - Doctrine, standards, and reform | Sections 56 and 83 (amended as suggested above) include the facility to issue a warrant for the relevant authority to break into land or buildings to carry out requirements regarding flammable undergrowth or material; and that costs and expenses in doing so are recoverable. |
REC151-3095 | 24 - Govt responsibility | SAFECOM re-evaluate and determine a more meaningful definition of fire districts. |
REC151-3084 | 32 - Doctrine, standards, and reform | Section 79(1) – provisions relating to lighting or maintaining a fire in the open air during the fire danger season be retained in the principal FES Act; Section 79(2) be amended to provide that a fire may be lit or maintained in accordance with the Regulations; provisions specifying the conditions under which a fire can be lit or maintained, and currently under Section 79(2), be placed in the Regulations. |
REC151-3102 | 32 - Doctrine, standards, and reform | Regulations 22 and 62 be reviewed to ensure reports regarding conduct must be relevant to the enquiry. |
REC151-3068 | 32 - Doctrine, standards, and reform | The FES Act be amended so as to allow the Chief Executive (CE) to manage the Commission (SAFECOM) Office by removing provisions relative to the SAFECOM Board’s managerial and administrative oversight of the Commission. |
REC151-3089 | 32 - Doctrine, standards, and reform | The definition of ‘officer’ in Section 3 be amended to include reference to the designation being made by the Chief Officer. |
REC151-3110 | 32 - Doctrine, standards, and reform | Further to Recommendations 11 and 12 above concerning the joining of Sections 56 and 83 of the FES Act, that these existing provisions be examined to determine whether they provide sufficient authority to address Recommendation 29.9(4) of the Wangary Coronial Inquest so as to require the owners or occupiers of rural land to create fire breaks and/or the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3552 | 37 - Funding | Department of Health and Human Services (DHHS) to fund 3 Full-Time Equivalent (FTE) Senior Registrar positions at the Royal Hobart Hospital (RHH) for the Tasmanian Medical Retrieval Service (TMRS). One registrar in the Anaesthesia Department, one in the Intensive Care Unit and one in Emergency Department is proposed. |
REC140-3568 | 37 - Funding | The State Medical Retrieval Cost Centre (TMRS and NETS) be formed and be supported by the appropriate administrative and resource accountant expertise. This cost centre should be placed with those responsible for its management. |
REC140-3567 | 37 - Funding | A uniform retrieval charge to the region of referral should be considered. This should be independent of the mode of transport used. |
REC140-3554 | 37 - Funding | DHHS fund the equivalent of 2 FTE Consultant positions for retrieval duties (1.5 FTE existing, 0.5 FTE new) |
REC140-3575 | 24 - Govt responsibility | The preferred model for the Tasmanian Medical Retrieval Services is to have TMRS and NETS staff based in RHH. The fixed wing would remain based in Launceston (for the present) with the helicopter to remain based in Hobart. |
REC140-3553 | 37 - Funding | RHH Neonatal Emergency Transport Service receive DHHS funding for a Senior Registrar to assume the responsibilities of retrieval staffing, quality assurance, data collection and reporting demands. |
REC140-3572 | 32 - Doctrine, standards, and reform | A DHHS website be developed to list policies, procedures and guidelines relevant to critical care retrieval including the NETS policies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3591 | 32 - Doctrine, standards, and reform | Joint development of templates for provision of core incident information by regional Incident Management Teams to CFA and DSE emergency coordination centres as basis for updates to the VBIL and other authorised information recipients |
REC132-3595 | 32 - Doctrine, standards, and reform | Development of framework document investigating future direction of VBIL including its role during incidents and its role in the transition from bushfire preparation to incident to bushfire recovery phases |
REC132-3592 | 32 - Doctrine, standards, and reform | Clarifying protocols for activating VBIL beyond normal working hours and for 24 hour activations |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3887 | 32 - Doctrine, standards, and reform | Give priority to the establishment of risk management processes across all stages of prescribed burning within the Department’s broader risk management strategy: |
REC124-3886 | 32 - Doctrine, standards, and reform | Clarify, strengthen and document roles, responsibilities and accountabilities of DSE and its partner organisations in the prescribed burning program: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3879 | 32 - Doctrine, standards, and reform | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan, to consider the use of alternative locations for staging, evacuation, assembly and incident coordination, to increase separation of emergency operations from non emergency activity be adopted. |
REC123-3878 | 32 - Doctrine, standards, and reform | Melbourne Airport management, the emergency services and airlines develop risk based tactical plans that, where safe and appropriate, allow the staged or progressive closure or re-opening of terminal space to support continuity of airport operations during emergencies. |
REC123-3874 | 32 - Doctrine, standards, and reform | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan to confirm that planning and response arrangements appropriately consider the protection of public safety, the current security environment and the timely restoration of airport operations, and that it is consistent with state emergency response planning arrangements. |
REC123-3881 | 32 - Doctrine, standards, and reform | Reference to the Aviation Rescue and Fire Fighting service in Part 6 of the Emergency Management Manual Victoria, table of control and support agencies, be extended to include its responsibility for hazardous materials emergencies at the airport. |
REC123-3880 | 32 - Doctrine, standards, and reform | Victoria Police, Melbourne Airport management, airlines and emergency services develop a Memorandum of Understanding for media coordination and public communications at Melbourne Airport that documents the responsibility for media coordination during emergencies to Victoria Police. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2198 | 32 - Doctrine, standards, and reform | That an explicit formulation of the interactions between terrain, fuel, ignition pattern, time of day and weather be created to better define those days suited to prescribed burning. |
REC104-2244 | 37 - Funding | That DSE assesses the environmental and monetary cost of establishment and rehabilitation of temporary tracks, per 100 km, constructed during firefighting operations, and compare this with the recurrent costs of a program of maintaining existing tracks. |
REC104-2308 | 37 - Funding | That Government funding for Community Development Officers engaged in community support and rebuilding incorporates flexible resources to enable the purchase of services from a range of providers to ensure choice for those requiring support. |
REC104-2226 | 32 - Doctrine, standards, and reform | That the new Municipal Fire Management Plan is informed by the policy directions of the subcommittee of the Victoria Emergency Management Council. |
REC104-2254 | 24 - Govt responsibility | That a single state-of-the-art all hazards State Emergency Operations Centre be established for Victoria. This could, if necessary, be implemented in stages, initially incorporating DSE, CFA, MFESB and the State Aircraft Unit. |
REC104-2321 | 24 - Govt responsibility | That Government confirms that the Model of Fire Cover/Fire Safety Victoria strategy should be a seamless model for the whole of the State and include both private and public land. |
REC104-2236 | 32 - Doctrine, standards, and reform | That the Statewide Fire Control Priorities: |
REC104-2274 | 7 - Inter-agency communication | That when Incident Management Teams implement significant changes to objectives and strategies, these are effectively communicated to firefighters, fire ground supervisors and affected communities, and are incorporated into the broader organisational planning. |
REC104-2196 | 32 - Doctrine, standards, and reform | That, as a result of this monitoring, weather conditions for the safe conduct of burning in such operations should be defined. |
REC104-2243 | 37 - Funding | That Government reviews the funding for DSE for the 2004-2005 fire season to ensure that appropriate resources are available for fire prevention planning and preparedness. |
REC104-2303 | 24 - Govt responsibility | That Interstate Agreements prepared by the fire agencies be reviewed to include protocols for the joint release of consistent and appropriate information relating to fires burning across State borders. |
REC104-2225 | 24 - Govt responsibility | That the Victoria Emergency Management Council establish a sub-committee by June 2004 to ensure an all-agency and appropriate industries’ policy framework is developed and agreed in respect to the planning for fire prevention, mitigation and suppression. |
REC104-2253 | 32 - Doctrine, standards, and reform | That Victoria Police, CFA and DSE review the relationship between fire service regional co-ordination arrangements and Divisional Emergency Response Plans and that any changes be formalised in the emergency management arrangements. |
REC104-2318 | 37 - Funding | When the research into prescribed burning and optimum fire protection described in Chapter 11, and the financial analysis of appropriate funding levels for prevention and suppression recommended in Chapter 15, are completed, DSE should develop a business case with Department of Treasury and Finance for assured funding to an agreed level over a three-year rolling cycle. |
REC104-2232 | 24 - Govt responsibility | That Government in the development of its statewide water policy includes appropriate consideration of access to water for firefighting. |
REC104-2261 | 32 - Doctrine, standards, and reform | That the emergency management arrangements be amended to require Police Divisional Emergency Response Coordinators, in consultation with other response agencies, to establish and document procedures and structures at regional level in order to ensure there is: |
REC104-2331 | 24 - Govt responsibility | That a State Emergency Operations Centre be established to replace the existing separate fire agency centres. This could, if necessary, be initially confined to being a State Fire Operations Centre as recommended in Chapter 18, Part D. |
REC104-2192 | 24 - Govt responsibility | That, according to available scientific evidence, a decision regarding cattle grazing in the High Country should not be based on the argument that ‘grazing prevents blazing.’ |
REC104-2242 | 37 - Funding | That the financial arrangements incorporate full cost recovery for prescribed burning to be undertaken over a number of weekends utilising Project Firefighters, CFA volunteers and MFESB members. |
REC104-2288 | 32 - Doctrine, standards, and reform | That CFA develop protocols to integrate Ultra High Frequency and Citizen Band radios into their communication structures. |
REC104-2224 | 32 - Doctrine, standards, and reform | That the Country Fire Authority Act 1958 be amended to: |
REC104-2252 | 32 - Doctrine, standards, and reform | That existing DSE and CFA regional co-ordination arrangements be reviewed and any changes, such as the continued use of Integrated Multi-Agency Co-ordination Centres, be reflected in the Victorian emergency management arrangements. |
REC104-2315 | 24 - Govt responsibility | That the Privacy Commissioner be asked for advice in the development of this model. |
REC104-2230 | 24 - Govt responsibility | That DSE investigates whether such agreements should exist with other government Departments and agencies, particularly those with officers located in rural Victoria who may be involved in fire response and support operations in the future, based on their expertise and experience. |
REC104-2257 | 32 - Doctrine, standards, and reform | That the Emergency Management Act 1986 be amended to require the development of agreements that describe joint operational arrangements between emergency response agencies. |
REC104-2330 | 32 - Doctrine, standards, and reform | That this unified system include recommendations for the appointment of one person or agency to be responsible for overall control of fire suppression activity in country Victoria, including for any legislative reform considered necessary. |
REC104-2241 | 37 - Funding | That the financial models incorporate changes in public land use, particularly ‘Our Forests Our Future’, and the subsequent changes in fire management priorities. |
REC104-2285 | 32 - Doctrine, standards, and reform | That, as a matter of urgency and in consultation with stakeholders, CFA and DSE develop and communicate clear guidelines on how and when privately owned firefighting equipment should be integrated into the fire response. |
REC104-2219 | 32 - Doctrine, standards, and reform | That, following the review of Forest Industry Brigades, the Country Fire Authority Act 1958 be amended to ensure that the Forest Industry Brigades, which are acting in an approved manner, have the same powers and rights as other Brigades when attending fires on public land or interstate. |
REC104-2247 | 24 - Govt responsibility | That an appropriately resourced, national aerial firefighting strategy is urgently required, and that the Victorian Government make representations to the Commonwealth to support the Australasian Fire Authorities Council recommendations |
REC104-2311 | 32 - Doctrine, standards, and reform | That all Departments, statutory authorities, utility providers and Local Governments be made aware of the need to develop contingency plans for recovery activities, and that such plans, and the associated public education and information strategies, are included in the Municipal Emergency Management Plans. |
REC104-2229 | 32 - Doctrine, standards, and reform | That DSE and the Department of Primary Industries formalise an agreement by the 2003-2004 fire season documenting the policies, procedures and financial arrangements relating to the availability of Department of Primary Industries staff to be trained and released for fire prevention and suppression activities on public land. |
REC104-2256 | 24 - Govt responsibility | That the State Emergency Operations Centre develop and maintain strong and close links with the State Emergency Response Coordination Centre, if collocation is not possible. |
REC104-2329 | 32 - Doctrine, standards, and reform | That CFA, DSE, MFESB and Victoria Police jointly develop a unified command and control system that better integrates with the State's emergency management arrangements, and that this be endorsed by the Victoria Emergency Management Council by July 2004. |
REC104-2240 | 37 - Funding | That Government supports the immediate development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2278 | 32 - Doctrine, standards, and reform | That DSE and CFA review the standards and protocols for documentation, including mapping, provided to fire line managers as part of their briefing notes, to ensure these are concise and appropriate. |
REC104-2199 | 32 - Doctrine, standards, and reform | That evidence of the rekindling or otherwise of spring prescribed burns in forests be assembled and a model constructed and tested to see whether or not some days in spring could be used for prescribed burning in certain circumstances and places, especially in Zone 1. |
REC104-2245 | 37 - Funding | That DSE includes the cost of tracks, as above, in the development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2309 | 32 - Doctrine, standards, and reform | That the Emergency Management Act 1986 be amended to include a provision that, on the recommendation of the Minister for Police and Emergency Services as Co-ordinator-in-Chief of Emergency Management, or of another Minister, the Premier establish a Ministerial Task Force to oversee recovery in situations of extreme natural disaster or other emergency events. |
REC104-2227 | 32 - Doctrine, standards, and reform | That the Municipal Fire Management Plan amendment includes appropriate provisions for the audit of the plans including: |
REC104-2255 | 24 - Govt responsibility | That the options of collocating the State Emergency Response Coordination Centre with the new State Emergency Operations Centre |
REC104-2324 | 32 - Doctrine, standards, and reform | That this group reports to the Minister for Police and Emergency Services on proposed legislative amendments to the Emergency Management Act 1986, the Country Fire Authority Act 1958 and any associated legislation by June 2004. |
REC104-2239 | 24 - Govt responsibility | That any local level agreements developed to address geographically specific risks or issues must be consistent with State-level arrangements. |
REC104-2276 | 32 - Doctrine, standards, and reform | That CFA and DSE jointly develop procedures to ensure that a more consistent strategic approach can be maintained at shift and tour of duty changes. |