Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC312-2506 | 9 - Community education | The chairpersons of disaster management groups within the Townsville Disaster District, supported by the Queensland Police Service, Queensland Fire and Emergency Services and the Queensland Reconstruction Authority develop a district action plan based on the capability enhancement strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2481 | 22 - Role of local Gvt | Greater clarity about responsibilities for recovery at the community, local, and district levels should be considered in any future review of the Disaster Management Act (2003). |
REC310-2486 | 9 - Community education | State arrangements for on-the-ground support to recovering local governments should be in line with Queensland’s disaster management arrangements, and ensure the best balance between local relationships, suitable capability and sufficient capacity. |
REC310-2483 | 9 - Community education | 09-Community education/engagement/preparedness |
REC310-2482 | 9 - Community education | Practical guidance on what community-led recovery means, and how it can be best implemented should be captured and shared with all who have responsibility for it. This should be done to help individuals and communities to take the lead in recovery and so that community-led recovery becomes the norm following disasters and other events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
REC309-2467 | 9 - Community education | Further work be undertaken to develop effective public flood risk messaging and community education materials that are easy to understand and tested with the community to ensure flood risk is understood. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
REC308-2457 | 8 - Communications and warnings | Efforts are made to improve the timeliness, accuracy and targeting of Emergency Alert messaging by: |
REC308-2456 | 22 - Role of local Gvt | A Local Government Association of Queensland representative should be included on the Crisis Communications Network to enhance the delivery of consistent information across and between levels of government. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1329 | 8 - Communications and warnings | Review and update Part 3, Annex C, of the SEMP ‘Public Information and Warnings’ to: a) clarify the role and responsibilities of the Public Information Functional Support Group and control agencies in relation to public information b) define requirements and processes for liaising with the community, including holding community meetings |
REC295-1296 | 8 - Communications and warnings | That the SES in collaboration with MFS Communications Centre (Comcen) investigate and implement options to reduce the number of calls coming into the Comcen, (particularly on 132500). Options could include better utilisation of the available options on the Interactive Voice Recording and community education to increase community resilience. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1306 | 9 - Community education | Develop practical policy outcomes to support resilience (e.g. the 72- hour model) and promote this broadly to community through media, awareness campaigns, policies etc. Research should be undertaken to gain insight into the types of messaging and activities that have the most impact on sustained behaviour change within the community before committing to a particular model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1449 | 9 - Community education | Develop coastal inundation education materials that meet the needs of exposed communities. |
REC286-2052 | 22 - Role of local Gvt | Undertake local level emergency management planning for areas at risk of debris flow. |
REC286-2085 | 9 - Community education | Up-skill isolated communities in emergency PPRR skills. |
REC286-2028 | 8 - Communications and warnings | Review community information and warning systems to ensure they cater for heatwave messages |
REC286-1446 | 9 - Community education | Introduce child-centred household level disaster risk reduction strategies in school programs. |
REC286-2043 | 22 - Role of local Gvt | Assessment of council’s capacity to manage land effectively. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-2027 | 8 - Communications and warnings | Develop arrangements to identify and communicate with people vulnerable to heat stress |
REC286-1443 | 14 - Incident Mgt Teams | Build capacity to enable Incident Management Teams to manage the likely increased frequency and intensity of major fire events. |
REC286-2041 | 22 - Role of local Gvt | Development mechanisms to support small councils to manage treatment across the PPRR spectrum (across all hazards). |
REC286-1476 | 9 - Community education | Develop and implement a targeted community flood awareness program. |
REC286-2083 | 9 - Community education | Enhance the community development program. |
REC286-1440 | 9 - Community education | Expand the existing Fire Ready Schools Program with enhanced support and incorporate other sites used by vulnerable groups. |
REC286-2035 | 9 - Community education | Include heatwave in existing preparedness programs. |
REC286-1475 | 8 - Communications and warnings | Integrate existing capabilities into a Total Flood Warning System. |
REC286-2075 | 9 - Community education | Develop and implement a community storm safe awareness program. |
REC286-1439 | 9 - Community education | Continue the Community Bushfire Protection Program with a renewed focus on vulnerable groups. |
REC286-2034 | 9 - Community education | Improve community educational information. |
REC286-1466 | 9 - Community education | Develop and deliver earthquake hazard awareness products. |
REC286-2074 | 8 - Communications and warnings | Continue the enhancement of forecast and warning services. |
REC286-2088 | 9 - Community education | Develop a community education strategy for when to call 000, 131 444, and 132 500. |
REC286-1437 | 9 - Community education | Continue the Bushfire Ready Neighbourhoods Program. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1203 | 22 - Role of local Gvt | Impact Assessment Data Sharing The Office of Emergency Management: · with the SEOCON, jointly provides further guidance to Regional Emergency Management Officers about their role in facilitating local council access to the Impact Assessment Data Base · with REMOs and the SEOCON jointly provides further information to local councils about Impact Assessment Data Sharing Arrangements and the data available through this mechanism · includes information about the Impact Assessment Data Sharing Arrangements in the Local Recovery Toolkit · develops a mechanism to allow local councils to have direct access to the collated impact data. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1425 | 8 - Communications and warnings | The Public Information and Warnings Sub-plan Guide is reviewed to include: |
REC268-1433 | 8 - Communications and warnings | Queensland Fire and Emergency Services should consider supporting local government in the annual development of at least one pre-formatted Emergency Alert message and polygon map based on a risk assessment and hazard modelling. |
REC268-1423 | 22 - Role of local Gvt | The State Disaster Coordination Centre Notification Matrix is reviewed to ensure local governments are notified of any event affecting, or likely to affect, their local government area. |
REC268-1432 | 9 - Community education | Queensland Fire and Emergency Services should consider developing and implementing mechanisms, such as face-to-face forums, for disaster management practitioners to share knowledge, contemporary research findings and document good practice about warnings. |
REC268-1431 | 8 - Communications and warnings | Queensland Fire and Emergency Services should consider new and emerging technologies for issuing warnings (including opportunities for Emergency Alert to be distributed in other languages or to people with vision or hearing impairment). |
REC268-1427 | 8 - Communications and warnings | The Warning and Alert Systems training package is updated to align the content to the Standard for Disaster Management in Queensland and to include advice and scenarios from the Information Commissioner. |
REC268-1426 | 8 - Communications and warnings | A qualitative assessment of public information and warnings arrangements is undertaken as part of the 2016 disaster management plan assessment process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1159 | 9 - Community education | Improving Community Preparedness and Resilience |
REC267-1150 | 9 - Community education | Media Engagement Consideration should be given on future recovery operations to adopting a more structured approach to media engagement, with regular media briefings undertaken at a frequency dependent upon the phase of the recovery activities and the level of media interest. These briefings could be conducted at different locations around the region, if appropriate, and would provide the opportunity for communication of key messages and provide journalists with the opportunity to ask questions regarding the recovery. This could be complemented by media coverage of community engagement visits. For all recovery operations, |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2591 | 17 - Assets and technology | That until the outcome of the Whole of Government project is complete (and interoperability is achieved), emergency services should investigate and implement methods for further improving interoperability. |
REC245-2597 | 17 - Assets and technology | That the project team become independent from any of the entities involved in the Whole of Government network. |
REC245-2595 | 17 - Assets and technology | That stakeholders involved with the Whole of Government radio project re-engage positively to ensure a solution to the current impasse is achieved in the best interests of the stakeholders and the State as a whole. |
REC245-2594 | 17 - Assets and technology | That the network managers produce business cases for all major upgrades. |
REC245-2593 | 17 - Assets and technology | That network managers develop and document strategic plans for the management of their radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2606 | 22 - Role of local Gvt | The Act be amended to require the mandatory appointment of Authorised Officers by each rural council or council that has within its area a Designated Urban Bushfire Risk Area(s) with an option for the CFS Chief Officer to exempt council from this requirement (similar to Section 105B). |
REC244-2604 | 8 - Communications and warnings | Notification of a total fire ban should be broadcast to the public via any means reasonably available. Section 80, parts (2), (5) and (6) be amended so that broadcast fire ban warnings include, but not be limited to, radio stations, internet sites, social media outlets etc. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0848 | 17 - Assets and technology | That the Government resume funding for the helicopter surveillance service rather than by fixed-wing aircraft along Adelaide, South Coast and other high-risk coastlines during summer recreational periods for monitoring shark and other rescue situations, to bring the State back into line with interstate best practice. |
REC243-0846 | 17 - Assets and technology | That the Government adequately fund Community Safety and Emergency Services budgets so that fire-bombing aircraft are available on call for rapid deployment throughout Autumn and Spring at short notice to bomb fires at the earliest and safest possible opportunity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2647 | 8 - Communications and warnings | That Government agencies work closely with the Bureau of Meteorology and radio stations that broadcast emergency service announcements, to ensure the earliest possible determination of, and communications about, dangerous bushfire conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2690 | 8 - Communications and warnings | That the Chief Executive Officer Portfolio Business and Commissioners establish a high level working group with the ABC and commercial media to identify and implement an improved information flow to the community on disasters. |
REC239-2775 | 17 - Assets and technology | That efforts by the courts, the Director of Public Prosecutions, the legal profession, Queensland Corrective Services and the Queensland Police Service to adopt technology for court processes should be supported through Government funding in so far as they create efficiencies, result in lower costs and produce better human rights outcomes. |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2770 | 9 - Community education | That the efficiency review of the Queensland Police Service develop options for better management of community expectations and divesting the organisation of historical practices. |
REC239-2664 | 17 - Assets and technology | That Queensland Corrective Service should increase the use of technology as an alternative to court appearances and ensure the provision of appropriate number and level of facilities under its control. |
REC239-2769 | 9 - Community education | That the Chief Executive Officer portfolio business and Commissioner of Police in line with the government’s open data policy consider introducing an improved social media style forum for interaction with the community and stakeholders across the portfolio. |
REC239-2659 | 9 - Community education | That Queensland Health continues to recognise and foster the important contributions of Local Ambulance Committees to supporting effective community focused ambulance services across the State. |
REC239-2768 | 9 - Community education | Recommendation: That: |
REC239-2709 | 17 - Assets and technology | That the information and communication technology solution being developed to provide situational awareness, decision support, event management and that logs critical decisions receives urgent attention to ensure timely completion. |
REC239-2778 | 17 - Assets and technology | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative ANPR models should form part of the design architecture considerations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0830 | 9 - Community education | That Bush Fire Risk Management Plans be tabled at Local Emergency Management Committees for comment. |
REC237-0829 | 9 - Community education | That Bush Fire Risk Management Plans be posted on the NSW Rural Fire Service website. |
REC237-0828 | 9 - Community education | That the NSW Rural Fire Service develop a strategy to better inform the community and NSW Rural Fire Service members about the NSW bush fire management system and its components. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1863 | 8 - Communications and warnings | The Fire and Emergency Services Authority should expand their use of social media to better inform the Western Australian community. |
REC222-1855 | 22 - Role of local Gvt | Local government authorities incorporate into their Local Emergency Management Plans their procedures for dealing with any trauma experienced by bushfire brigade volunteers, having regard to best practice in managing trauma. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2881 | 17 - Assets and technology | Extend ICT governance arrangements to all applications and subject in-house development to rigorous approval processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1897 | 9 - Community education | The Australian Government initiative to improve the coordination and dissemination of flood-risk information should proceed in the most cost-effective way, be regularly updated and be expanded over time to encompass other natural hazards. Guidelines to improve the quality and consistency of risk information should also be regularly updated and take climate change into account where feasible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC186-0393 | 17 - Assets and technology | The committee recommends that interoperability of narrowband voice radiocommunications between federal, state and territory emergency service organisations is achieved as soon as practicable and that all services attending major incidents be compelled to maintain a common emergency communications platform to ensure seamless real time communication from and to the Incident Controller. |
REC186-0399 | 8 - Communications and warnings | The committee recommends the government consider granting public broadcasters priority access to fuel during times of emergency for the purpose of broadcasting emergency warnings and information, and in a way that does not impede the ability of emergency service organisations to access fuel. |
REC186-0398 | 9 - Community education | The committee recommends emergency service organisations in collaboration with television and radio broadcasters, the print media and other relevant organisations, use regular and ongoing public education well in advance of an emergency situation as an opportunity to teach the public about their responsibilities during an emergency and how they can appropriately prepare themselves for such an event. |
REC186-0395 | 17 - Assets and technology | The committee further recommends that any allocation of broadband spectrum to emergency service organisations (ESOs) for PPDR must be provided on the basis of interoperability amongst Australian ESOs and with ESO counterparts overseas. |
REC186-0394 | 17 - Assets and technology | The committee recommends the Commonwealth Government allocate sufficient spectrum for dedicated broadband public protection and disaster relief (PPDR) radiocommunications in Australia. |
Rec-ID | Code | Recommendation |
---|---|---|
REC180-2969 | 22 - Role of local Gvt | Councils should strengthen governance arrangements for business continuity by: |
REC180-2973 | 22 - Role of local Gvt | Local Government Victoria should, further to its work on strengthening the oversight role of audit committees, assist councils to develop good practice approaches to implementing, overseeing and continuously improving business continuity management. |
REC180-2972 | 22 - Role of local Gvt | Councils should strengthen their continuous improvement frameworks by: |
REC180-2971 | 22 - Role of local Gvt | Councils should improve the structure, format and content of their business continuity plans to provide greater clarity on roles and responsibilities for emergencies, more specificity on continuity and recovery responses, and better integration with other council disaster recovery and emergency plans. |
REC180-2970 | 22 - Role of local Gvt | Councils should improve assessments of business continuity risks by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2981 | 8 - Communications and warnings | The Department of Human Services should complete work on emergency communication and information management issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2987 | 9 - Community education | To improve customer awareness of the availability of disaster recovery assistance, the ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0055 | 22 - Role of local Gvt | SEMC and EM WA should: monitor and take action to ensure local plans are in place and cover areas where the hazard could occur |
REC170-0054 | 22 - Role of local Gvt | SEMC and EM WA should: work with local government to ensure up-to-date, comprehensive local arrangements are in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0087 | 8 - Communications and warnings | The SDMG commission the Department of Community Safety and seek the necessary funding to develop and enhance the Statewide Disaster Management information and communications system building on alternatives already in place and in consultation with all levels of Government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3509 | 8 - Communications and warnings | The Victoria State Emergency Service, Department of Primary Industries, Energy Safe Victoria and the energy sector develop a coordinated set of safety messaging about preparedness for storm events and clearly outline the responsibilities for delivering these messages before during and after an emergency. |
REC156-3492 | 22 - Role of local Gvt | The review of the municipal emergency management planning guidelines being led by the Office of the Emergency Services Commissioner clarify local governments’ role in community information about emergencies. |
REC156-3507 | 8 - Communications and warnings | Victoria progress, as a matter of priority, a telephony based public emergency notification system to reduce demand on Triple Zero and other emergency telephone lines during a major emergency. |
REC156-3491 | 8 - Communications and warnings | The Victoria State Emergency Service improve its communication with local governments, especially in relation to severe weather and storm warning information. |
REC156-3503 | 8 - Communications and warnings | Emergency Service Organisations review their use of Emergency Alerting System paging message categories to ensure that priority messages are not compromised by inappropriate use. An education program may be required to ensure that all users understand message categories, their intended use and ramifications of each category on network and message delivery sequence. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3517 | 9 - Community education | The Victoria State Emergency Service work with the electricity distribution businesses, Department of Primary Industries and Energy Safe Victoria to develop and implement a joint community education program for public safety during and after storms and power outages. |
REC156-3497 | 8 - Communications and warnings | Emergency Service Organisations work with government departments, local governments and private industry to identify and implement a model for communication flow during an emergency incident. |
REC156-3515 | 8 - Communications and warnings | The electricity distribution businesses enhance power outage information on their websites which are accessible to electricity retail businesses, the media and the public and also consider improving their capacity to communicate with customers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3231 | 22 - Role of local Gvt | The Committee recommends that the Australian Government request that the Centre for Excellence for Local Government ensure a particular focus on capacity building for coastal local councils. Capacity building should focus on addressing issues relating to: |
REC145-3205 | 17 - Assets and technology | The Committee recommends that, following the completion of the ‘first pass’ National Coastal Vulnerability Assessment, the Australian Government consider the resourcing and financing of second and third pass assessments, in conjunction with state, territory and local government authorities. |
REC145-3234 | 9 - Community education | The Committee recommends that the Australian Government nominate 2012 as the Year of the Coast, to further build community awareness about the issues facing the coastal zone. The Australian Government should work with coastal stakeholders, volunteer groups and the general community in determining key activities as part of this initiative. |
REC145-3233 | 9 - Community education | The Committee recommends that the Australian Government undertake an awareness campaign to alert coastal communities to the key challenges facing the coastal zone and the value of community engagement in addressing these challenges. The campaign should aim to build understanding and awareness of coastal management issues to encourage the continued membership and support of volunteer networks in the coastal zone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3399 | 9 - Community education | The Committee recommends that the Emergency Services Agency post all its publications, which are not internal working documents or otherwise confidential, on its website. |
REC144-3398 | 9 - Community education | The Committee recommends that the Emergency Services Agency update its website to accommodate, at a minimum, a publications menu item and a search function. |
REC144-3397 | 9 - Community education | The Committee recommends that the ACT Government investigate the Victorian Community Fireguard model with a view to implementing a similar scheme in the ACT to enhance community preparedness for and ability to respond to bushfire emergencies. |
REC144-3396 | 9 - Community education | The Committee recommends that information in relation to proposed fuel load activity and controlled burning should be disseminated to the community and in an accessible format. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3580 | 17 - Assets and technology | That FESA investigate the use of new technologies such as Voice over Internet Protocol (VoIP) for supplementing the dissemination of WANDRA information in cases where landlines have been disrupted. |
REC143-3579 | 9 - Community education | That FESA develop comprehensive internet-based information including but not limited to detail of WANDRA objectives, assistance measures, administering agencies, eligibility criteria (where applicable) and application forms. |
REC143-3577 | 8 - Communications and warnings | That following the declaration of a natural disaster, complete and accurate information on Western Australian Natural Disaster Relief Arrangements assistance measures and application processes is disseminated through public communications channels, including the media. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3556 | 17 - Assets and technology | The use of hospital transport vehicles to support retrieval operations be investigated. |
REC140-3564 | 17 - Assets and technology | The medical equipment used in retrieval and air ambulance duties undertaken by helicopter and fixed wing must be standardised. |
REC140-3563 | 17 - Assets and technology | An additional secure emergency oxygen supply source to be located in the BK 117 helicopter. An internal supply is preferred. |
REC140-3561 | 17 - Assets and technology | Development of a helipad at Mersey Hospital. |
REC140-3560 | 17 - Assets and technology | RHH requires a helipad. Plans to rebuild RHH must include a helipad at its earliest stage of conception. |
REC140-3559 | 17 - Assets and technology | A service level agreement is negotiated with the Police department that will cover access, tasking, price, equipment and staffing. This will enable a more strategic use of the helicopter. |
REC140-3565 | 17 - Assets and technology | The TMRS medical equipment inventory requires an overhaul. The TMRS medical equipment should be located with the TMRS team. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3528 | 8 - Communications and warnings | An early and high priority task in recovery from a natural disaster should be the development of a coordinated, succinct, practical and flexible public communications plan. |
REC136-3527 | 8 - Communications and warnings | In any future large-scale disaster or event, consideration be given to a centrally located Media Operations Centre. |
REC136-3526 | 8 - Communications and warnings | That consideration be given to additional ways and means to improve broadcast capability into disaster-affected regions, particularly for the early aftermath of any disaster when a loss of power characterises the event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2112 | 8 - Communications and warnings | The Working Group recommends that the Commonwealth Attorney General’s Department hold discussions with the Commonwealth Department of Communications, Information, Technology and the Arts regarding the Integrated Public Telephone Network Database (IPND) being made accessible for use in times of emergency where the need to disseminate community information and warnings to telephones within a specified area is identified. Discussions should also be held between the Commonwealth Attorney General’s Department and with the Federal Privacy Commissioner’s Office to identify any impediments to the use of the IPND in such circumstances. |
REC116-2111 | 9 - Community education | The Working Group recommends that the national forum mentioned in recommendation 13 consider the ongoing need for dissemination of information on a national basis both during and following a catastrophic disaster and also identify strategies to ensure the ability of this to be facilitated. |
REC116-2110 | 9 - Community education | The Working Group recommends that EMA convene a national forum to explore community information and warning needs in catastrophic disasters, to review existing information and warning systems, and to identify possible technologies and techniques that might be used to enhance community needs in disasters. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |