Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC327-4347 | 36 - Volunteers | By December 2023, the Rural Fire Service should: develop a strategy to ensure that local brigade volunteers are adequate in numbers and appropriately trained to operate fleet appliances in the RFS Districts where they are required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4255 | 42 - Culture and Heritage | The Inspector-General Emergency Management recommends a set of guiding principles that reflect a unified response to World Heritage listed sites in Queensland be included in the Queensland State Disaster Management Plan and reflected in the Queensland Bushfire Plan. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
REC322-4220 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science monitor the progress of relevant improvement activities resulting from the K’gari (Fraser Island) Bushfire Review, through their respective lessons management programs. |
REC322-4246 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the Interagency Protocol for Fire Management be reviewed by all relevant entities, including representatives of the Butchulla people, and be updated as a matter of priority. Entities responsible for the protocol should implement a process for regular review and evaluation of its effectiveness. This review process should be conducted after a major bushfire event, or to reflect any material change to applicable legislation and policy. It should also consider pre-arranged approvals and a range of agreed fiscal protocols between the agencies. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
REC322-4252 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services regularly review and evaluate the effectiveness of the Queensland Bushfire Plan with land managers and stakeholders, including disaster management groups. A review should occur in line with any material change to the Queensland State Disaster Management Plan, the Disaster Management Act 2003, the Prevention Preparedness Response and Recovery Guideline, or after major bushfire events, to ensure appropriate alignment and currency. |
REC322-4239 | 42 - Culture and Heritage | The Inspector-General Emergency Management recommends entities with responsibilities for land and fire management consider the establishment of roles for Traditional Owner and First Nations representatives in incident management structures for significant bushfire or disaster events including those that may impact on cultural heritage in Queensland’s World Heritage sites. |
REC322-4253 | 42 - Culture and Heritage | The Inspector-General Emergency Management recommends the Queensland State Disaster Management Plan and the Queensland Bushfire Plan be reviewed to enhance appropriate arrangements for the management of bushfire and disaster events where a threat is posed to significant environmental and cultural heritage sites. |
REC322-4240 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the next review of the Queensland State Disaster Management Plan examines and provides guidance in respect to the application of Queensland’s disaster management arrangements to support hazard specific events such as bushfire. |
REC322-4218 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends this report be returned to the IGEM to monitor, evaluate and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC322-4254 | 42 - Culture and Heritage | The Inspector-General Emergency Management recommends that the Queensland Government works with the Commonwealth Government to review the Project Agreement for World Heritage Management to ensure Queensland and Australia continue to meet their obligations under the World Heritage Convention to protect, conserve and present our World Heritage properties. |
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4219 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends should a Queensland Government Action Plan be considered, clarity about the intent of the recommendations be sought from the Inspector-General Emergency Management to assist in informing this process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4197 | 36 - Volunteers | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department develop and resource an ongoing strategy to coordinate spontaneous volunteers that can be activated before, during or after emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4171 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the State review (and where necessary amend) legislation including but not limited to the Country Fire Authority Act 1958, Forest Act 1958 and Local Government Act 2020 to: |
REC318-4183 | 13 - Mapping and data quality | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in consultation with relevant agencies – develop a system to manage personnel and asset deployments to all tiers of incident management to meet the needs of the emergency and support the health and wellbeing of personnel. Where appropriate and within occupational health and safety requirements, this may include: |
REC318-4182 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in partnership with agencies engaged in state, regional and incident control centres: |
REC318-4181 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in collaboration with the emergency management sector and as part of the emergency management planning reforms: |
REC318-4178 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in collaboration with the Country Fire Authority and local government – undertake a review of the current residual risk target to ensure that it remains contemporary in terms of its designated percentage value. The review should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4045 | 42 - Culture and Heritage | WHoG desktop exercise should be conducted to test and support relocation and evacuation planning. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3860 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure the guiding principles and approval processes are contemporary, streamlined and more flexible, the NSW and Commonwealth Governments review the Defence Assistance to the Civil Community (DACC) arrangements. This review should include the circumstances in which the State can request Commonwealth assistance, and the level of information provided by the ADF to the State on available resources and capabilities. |
REC315-3812 | 25 - Inquiry, audit, lessons management and after action review | That Government commit to: |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3859 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure State Emergency Operations Centre (SEOC) interoperability during all natural disasters, Resilience NSW review the current SEOC arrangements and location including responsibilities for ongoing resourcing and maintenance. |
REC315-3801 | 13 - Mapping and data quality | That, in order to improve capability to detect ignitions and monitor accurately all fire edge intensity and progression automatically across the State in near real time, Government establish a spatial technology acceleration program to maximise the information available from the various remote sensing technologies currently in use and to plan for inclusion of new remote sensing systems that can sense precisely and rapidly through heavy smoke, cloud, fog and dust. This will require work within the State and with partners nationally and internationally. |
REC315-3824 | 1 - Land-use and building regs | That Government commit to shifting to a strategic approach to planning for bush fire, and develop a new NSW Bush Fire Policy similar to the NSW Flood Prone Land Policy in order to accommodate changing climate conditions and the increasing likelihood of catastrophic bush fire conditions; to build greater resilience into both existing and future communities; and to decrease costs associated with recovery and rebuilding. |
REC315-3858 | 25 - Inquiry, audit, lessons management and after action review | That, in order to improve cross-agency communication and coordination during bush fires, the NSW RFS review Fire Control Centres (FCCs) in areas that were heavily affected by fire. The results should be combined with the Emergency Operations Centre (EOC) Facilities Review to identify areas that would benefit from a purpose-built FCC, enabling co-location with the EOC. |
REC315-3800 | 13 - Mapping and data quality | That the NSW Government, along with other Australian governments, ask AFAC to establish a national bush fire database. This database would enable: |
REC315-3823 | 42 - Culture and Heritage | That, in order to increase the respectful, collaborative and effective use of Aboriginal land management practices in planning and preparing for bush fire, Government commit to pursuing greater application of Aboriginal land management, including cultural burning, through a program to be coordinated by Aboriginal Affairs and Department of Planning, Industry and Environment working in partnership with Aboriginal communities. This should be accompanied by a program of evaluation alongside the scaled-up application of these techniques. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3798 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure recommendations accepted by the Government are implemented in a timely and transparent manner, Government establish a central accountability mechanism to track implementation of recommendations from bush fire-related reviews and inquiries and consider expanding this to other policy areas. |
REC315-3873 | 25 - Inquiry, audit, lessons management and after action review | That Resilience NSW review existing functional area arrangements to ensure they are closely aligned to agencies responsible for direct service delivery. |
REC315-3822 | 42 - Culture and Heritage | That Government adopt the principle that cultural burning is one component of a broader practice of traditional Aboriginal land management and is an important cultural practice, not simply another technique of hazard reduction burning. |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3869 | 42 - Culture and Heritage | That, in order to ensure Aboriginal people can access appropriate support during evacuation, Resilience NSW work with Local Emergency Management Committees and Aboriginal Affairs to ensure: |
REC315-3819 | 13 - Mapping and data quality | That, as part of the spatial technology acceleration program, Government support deployment of remote sensing and picture processing technologies to monitor and audit how well Asset Protection Zones and defendable space are being maintained, especially around towns. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
REC307-2437 | 13 - Mapping and data quality | The ability to share, analyse, interrogate and display information from disparate entities should be progressed as a matter of some urgency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1474 | 1 - Land-use and building regs | Raised access routes. |
REC286-2046 | 1 - Land-use and building regs | Incentivising safer sites (charge people less rates and discounts for defensive actions by land managers). |
REC286-1435 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning and Building System reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1453 | 1 - Land-use and building regs | Review building controls to ensure they are adaptive to changing coastal inundation risks. |
REC286-2023 | 1 - Land-use and building regs | Locate and design new public infrastructure so that it can continue to operate during flood events. |
REC286-1473 | 13 - Mapping and data quality | Develop a statewide flood hazard map for use within the Tasmanian Planning System. |
REC286-2044 | 1 - Land-use and building regs | Develop linkages between landslide risk assessors and building engineers/structural works. |
REC286-2076 | 36 - Volunteers | Review volunteering arrangements to improve recruitment and retention. |
REC286-1451 | 1 - Land-use and building regs | Include consideration of coastal inundation in land use planning for new developments and uses. |
REC286-2015 | 1 - Land-use and building regs | Build flood capable infrastructure. |
REC286-1471 | 1 - Land-use and building regs | Promote the use of Water Sensitive Urban Design in stormwater systems. |
REC286-2040 | 1 - Land-use and building regs | Further development of Landslide Hazard Banding of the State (MRT). |
REC286-2070 | 25 - Inquiry, audit, lessons management and after action review | Test the Biosecurity Act 2015. |
REC286-1443 | 14 - Incident Mgt Teams | Build capacity to enable Incident Management Teams to manage the likely increased frequency and intensity of major fire events. |
REC286-1460 | 25 - Inquiry, audit, lessons management and after action review | Review seismic monitoring network alert systems to ensure emergency managers are on the contact lists. |
REC286-2038 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-2051 | 1 - Land-use and building regs | Establish arrangements to enable the buy-back of specified landslip prone land. |
REC286-1442 | 25 - Inquiry, audit, lessons management and after action review | Review legislation relating to Fuel Stove only areas, Fire Permit System and Total Fire Bans to ensure appropriate incentives to modify individuals’ behaviour. |
REC286-2097 | 13 - Mapping and data quality | Extend current tsunami maritime hazard modelling project to deliver coastal inundation modelling. |
REC286-1459 | 13 - Mapping and data quality | Improve beach morphology mapping to understand coastal inundation, including post-event surveys. |
REC286-2037 | 1 - Land-use and building regs | Make property level information on landslide hazards publicly available |
REC286-2050 | 1 - Land-use and building regs | Ensure landuse planning and building systems, including appeal mechanisms, are transparent, equitable and integrated at the municipal, State and national levels. |
REC286-1438 | 25 - Inquiry, audit, lessons management and after action review | Consider outcomes of national review of warnings and review resilience of warning systems’ infrastructure. |
REC286-2094 | 13 - Mapping and data quality | Deliver updated inundation mapping. |
REC286-1458 | 13 - Mapping and data quality | Make coastal mapping available to public. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1202 | 13 - Mapping and data quality | Impact Assessment Data Collection: The Office of Emergency Management continues to progress the Impact Assessment Data Collection Project and: · incorporate recovery schema in Rapid Impact Assessments · review procedures for collection of Rapid Impact Assessment Data · review and combine current templates into one, single template for Impact Assessment Reports that is used by all agencies · further develop Impact Assessment Guidelines for agency personnel undertaking impact assessments |
REC281-1201 | 25 - Inquiry, audit, lessons management and after action review | Preventing Flood Related Fatalities: The NSW Government consider the recommendations from the Preventing Flood Related Fatalities Report when it is released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1154 | 36 - Volunteers | Coordination of Volunteer Support |
REC267-1152 | 13 - Mapping and data quality | Impact Assessment Data Sharing Project |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1102 | 25 - Inquiry, audit, lessons management and after action review | SEMC Secretariat Community Emergency Management Officers should work with the Shire to document the Shire of Mundaring’s learnings from the Parkerville Stoneville Mt Helena fire with a view to sharing this with other local authorities particularly those facing similar situations in order to extend the range of tools available to assist local governments to understand their roles and responsibilities in future emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0978 | 36 - Volunteers | That in recognition of their commitment to the community volunteers employed by the State Government should be released to assist as volunteers for up to five (5) days per year in appropriately identified emergency operations. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-0971 | 13 - Mapping and data quality | That the RFSQ central office undertake a review of Firecom procedures in relation to Rural Fire Service callouts. Each Rural Fire Service Queensland district office should also undertake a review of the Firecom data sets/callout information for their district to establish call out protocols are correct. |
REC241-1023 | 13 - Mapping and data quality | That Rural Fire Service Queensland develops a simple data collection system to record the activities of brigades. |
REC241-0955 | 36 - Volunteers | That corporate support, such as administration and finance, to volunteer services be shared to enable a closer working relationship between the services. |
REC241-1017 | 36 - Volunteers | That each District office establish and maintain a register of suitably qualified Australasian Inter-service Incident Management System trained volunteers who are prepared to undertake the management of operations and provide these to the District Fire Management Group. |
REC241-1003 | 13 - Mapping and data quality | The Manager of the Geographic Information Systems unit conduct an audit of the Firecom mapping system to ensure that rural Brigade and road addressing is up to date. |
REC241-1002 | 13 - Mapping and data quality | That the Rural Fire Service Queensland upgrades its subscription to technology for the Brigade Mapping Toolset to make it available to all Brigades who want it. |
REC241-1040 | 36 - Volunteers | That RFSQ review local SAP function and delegation to enable effective and timely support for volunteers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0814 | 1 - Land-use and building regs | Develop a NSW Planning Policy and Guideline to improve land use planning practices on flood prone land. |
REC238-0808 | 1 - Land-use and building regs | Ensure future road infrastructure planning considers flood evacuation requirements throughout the Hawkesbury-Nepean floodplain. |
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
REC238-0801 | 1 - Land-use and building regs | Establish a dedicated group or body within an existing agency to provide a more integrated, coordinated and regional approach to land use, infrastructure and evacuation planning and flood modelling in the Hawkesbury-Nepean Valley. |
REC238-0816 | 1 - Land-use and building regs | Ensure appropriate consideration of flood risk in regional and subregional planning |
REC238-0800 | 1 - Land-use and building regs | Improve regional transport infrastructure to address current and projected flood evacuation capacity constraints and timelines. |
REC238-0815 | 1 - Land-use and building regs | Provide improved land use planning tools for managing flood prone land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1590 | 25 - Inquiry, audit, lessons management and after action review | Department of Broadband, Communications and the Digital Economy seek regular updates from Telstra on the implementation of the recommendations of its inquiry into the Warrnambool exchange fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0547 | 13 - Mapping and data quality | Fuel loads on private property need to be identified and included in understanding fire behaviour in determine the contribution they make to the burn risk assessment. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0546 | 13 - Mapping and data quality | Maps prepared for prescribed burns should address the fuel type and burn history of the burn area as well as surrounding areas. Predicted rates of spread under prescribed and other conditions should recognise the complexity of coastal heathlands. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0576 | 13 - Mapping and data quality | Better maps are required for urban/rural interface fires |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0540 | 25 - Inquiry, audit, lessons management and after action review | : In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1879 | 25 - Inquiry, audit, lessons management and after action review | Regulators can help to achieve improved outcomes by auditing compliance with the BPEM guidelines on a regular basis |
REC215-1875 | 1 - Land-use and building regs | Fire services can improve outcomes by seeking input to decisions about siting, design and fire water systems as part of the planning and licensing processes |
REC215-1871 | 14 - Incident Mgt Teams | Fire services can improve outcomes by developing a checklist for use by incident controllers |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1645 | 14 - Incident Mgt Teams | Ensure that adequate administrative personnel are available within the incident control structure to provide administrative and knowledge management support for incident management. |
REC209-1643 | 25 - Inquiry, audit, lessons management and after action review | An evaluation be conducted into the integration of the appropriate elements of the South Australian Country Fire Service “Crimson” networking system into Bushfires NT ICT. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2902 | 14 - Incident Mgt Teams | The Fire Services Commissioner clarifies the role of regional controller for major fires and incidents other than bushfire. |
REC198-2905 | 14 - Incident Mgt Teams | The Fire Services Commissioner ensures that there is a single standard for the tabards worn by the IMT on the fireground and in control centres to ensure consistency and aid interoperability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0330 | 13 - Mapping and data quality | The Fire Services develop a program that enables all communication mediums, including social media and agency websites, to be monitored in real time to provide quality assurance for outgoing messages and additional sources of information and intelligence relating to an emergency |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0104 | 1 - Land-use and building regs | That FESA assess the cost and other implications of proposed changes to bushfire prone zone declarations which would allow the whole State to be declared bushfire prone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0027 | 13 - Mapping and data quality | Add an ‘Aviation’ map to the standard set of incident maps. The standard for this map will need to be developed by subject matter experts from the Air Ops group. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2320 | 13 - Mapping and data quality | That Government acknowledge the importance of spatial information as a key element of planning, operations and program evaluation, and support the Geospatial Emergency Information Network as a means of ensuring integrated and co-ordinated information management on a whole-ofGovernment basis. |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2191 | 13 - Mapping and data quality | That DSE and CFA, recognising that the Bureau of Meteorology does not routinely store all variables required to produce the calculations and indices necessary for research and planning into fire occurrence and behaviour, develop appropriate systems to ensure that such current and historical information is readily available and accessible. |
REC104-2281 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA work cooperatively to review the management and application of bulldozers in fire suppression operations to ensure that they are used effectively, appropriately and are adequately supervised. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2319 | 13 - Mapping and data quality | That all emergency service agencies, CFA and DSE in particular, give greater priority to information management – especially the collection, maintenance and quality control of base data sets necessary for planning, operations and program evaluation. |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2190 | 13 - Mapping and data quality | That DSE institute additional routine data storage and analysis to supplement current climate records with at least daily 3 pm values for the Grassland and Forest Fire Danger Index, and Keetch-Byram Drought Index, for selected high quality stations representing a cross-section of environments throughout Victoria. |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2228 | 25 - Inquiry, audit, lessons management and after action review | That the Government identifies an appropriate body, or bodies, to undertake the audit of the Municipal Fire Management Plans. |
REC104-2293 | 25 - Inquiry, audit, lessons management and after action review | That aviation contractors be required to submit a copy of their annual independent regulatory compliance audit prepared for Civil Aviation Safety Authority to the State Aircraft Unit. |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2333 | 25 - Inquiry, audit, lessons management and after action review | That in doing so, this Review must consult with the agencies mentioned above, and others such as VICSES and the Departments of Human Services and Primary Industries. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2292 | 25 - Inquiry, audit, lessons management and after action review | That a systematic performance audit of State Aircraft Fleet contractors be conducted jointly by agency and SAU personnel. |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2332 | 25 - Inquiry, audit, lessons management and after action review | That the Review of emergency operations centres by the Departments of Premier and Cabinet and Treasury and Finance and the Office of the Emergency Services Commissioner: |
REC104-2277 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review methods of gathering and processing fire information to ensure all methods are pursued to greatest effect. |
REC104-2202 | 13 - Mapping and data quality | That DSE and CFA map all unplanned fires greater than four hectares on public and private land in order to further develop an understanding of the risk to rural Victoria from unplanned fires. |
REC104-2284 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review the management of personnel deployed ensuring that: |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2328 | 36 - Volunteers | That CFA, VICSES and other volunteer-based emergency service organisations develop proposals in support of the strategies for sustainable volunteerism, and that the State Government advocate these initiatives to the Federal Government. |
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2197 | 25 - Inquiry, audit, lessons management and after action review | That a review of the fuel management zones be implemented with a view to reducing the number of zones so as to focus clearly on (i) asset protection (especially at the Public/Private land interface), and (ii) ecological burns. |
REC104-2282 | 25 - Inquiry, audit, lessons management and after action review | That quality control or performance assessments are routinely completed post fire season, to ensure that contractors who have not performed to an agreed standard are not re-engaged for the consequential rehabilitation works. |