Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
REC324-4298 | 37 - Funding | Housing and development funding options: That, to empower vulnerable people and communities to avoid significant impacts from flood as well as drive broader investment in adaptation, Government through NSWRA: |
REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3261 | 24 - Govt responsibility | Consider amending the Fire and Emergency Services Act 2005 to align SAFECOM Board operations with accepted governance standards with the Minister appointing an Independent Chair of the SAFECOM Board. The SAFECOM Chief Executive (CE) should report to the Board and maintain SAFECOM’s role at the direction of the Board. Alternatively, SAFECOM could be abolished, moving to a model of a Department of Fire and Emergency Services where the departmental head reports to the Minister but the value proposition of any such machinery of government change would need to be thoroughly examined. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2399 | 24 - Govt responsibility | Implement a fully integrated civilianised single call and dispatch centre, that includes a redundancy option outside the Sydney CBD, which will adopt an agnostic approach to deploy the quickest most suitable resource to an emergency. Such a centre should be managed by either a non uniformed public servant staffed organisation like the Office for Emergency Management, or the NSW Police Force |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1261 | 28 - Personal responsibility | That heightened awareness and action is needed by communities when BoM issues flood watches and related warnings. Councils and SES need to facilitate this. |
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1302 | 28 - Personal responsibility | That the State Emergency Service together with the Local Government Association and Country Fire Service establish a plan for coordinated provision of sandbags to the public, including options for what is provided, where and when, and the process for effective communication of availability to the public. |
REC295-1305 | 18 - Access to fire ground | That the annexure to the State Emergency Management Plan, ‘Traffic management during emergencies’, be updated to include: responsibilities and processes for road closures; and, Department of Planning, Transport and Infrastructure requirements in regards to provision of road closure information, notification of changes in road closure status and publishing of that information. |
REC295-1318 | 24 - Govt responsibility | That the recommendation made following the Pinery bushfire, ‘to review control facilities at State, region and incident level’, be expanded to include all emergency services facilities that will be utilised for major incidents other than bushfire e.g. flood and earthquake and to also be extended into metropolitan areas, and implemented. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
REC295-1316 | 24 - Govt responsibility | That the position of Deputy Director, Office for Digital Government is dedicated to the Office for Digital Government; and that people throughout DPC are identified and trained to perform appropriate roles within the State Crisis Centre |
REC295-1312 | 24 - Govt responsibility | That the Department of Education and Child Development be included as a member of State Emergency Management Council and represented in the State Emergency Centre. |
REC295-1308 | 24 - Govt responsibility | That the Department of the Premier and Cabinet revise the ministerial documents relating to emergency management. |
REC295-1291 | 24 - Govt responsibility | That the Flood Reform Task Group, as proposed by the Department |
REC295-1319 | 24 - Govt responsibility | That a single emergency service multi-agency control centre be established with sufficient capacity and capability to deal with all types of emergency incidents in SA. Also consider Police and State Emergency Centre. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1288 | 24 - Govt responsibility | That Attorney General’s Department explore options to overcome fatigue and welfare issues of SAGRN staff associated with emergency events of extended duration. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2379 | 24 - Govt responsibility | I recommend that the Premier of New South Wales consider whether the Privacy and Personal Information Protection Act 1998 and the Health Records and Information Privacy Act 2002 should be amended to ensure that there is appropriate access to health related information available to ASIO (consistent with recommendation 12 of the report of the Martin Place Siege Joint Commonwealth—New South Wales review) |
REC292-2380 | 24 - Govt responsibility | I recommend that the New South Wales Police Force, in conjunction with NSW Health, establish a Fixated Threat Assessment Centre to identify and gather information about fixated persons, assess the risks they pose, and attempt to mitigate such risks through early intervention. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1246 | 18 - Access to fire ground | The State Emergency Management Committee to review the policy for traffic management at emergency incidents so it reflects national ‘best practice’. This includes the production and issuing of an aide-memoire to guide traffic management, emergency and incident management personnel. |
REC291-1245 | 18 - Access to fire ground | The Department of Fire and Emergency Services to issue a photo identification card to DFES members, members of Bush Fire Brigades, volunteer emergency services, Incident Management Teams, forestry industry brigade members and Networked Government Emergency Agency members. DFES also to consider temporary windscreen signage to identify vehicles carrying such personnel. |
REC291-1248 | 24 - Govt responsibility | The State Emergency Management Committee to establish a State Bushfire Coordinating Committee as a sub-committee of SEMC. The State Bushfire Coordinating Committee will be chaired by the Director of the Office of Bushfire Risk Management and will have the primary responsibility to: · develop a State Bushfire Management Policy and a set of long term bushfire risk management objectives; · provide a forum for key bushfire risk management stakeholder agencies; · advise the SEMC on matters pertaining to bushfire, in particular, to report against the investment in, and achievement of the bushfire risk management objectives; · provide advice and support to the proposed Chief Officer of the Rural Fire Service on bushfire risk management matters; and · report to SEMC and to the community on bushfire risk management matters on at least an annual basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1184 | 24 - Govt responsibility | The Tasmanian fire agencies think more broadly about how staff who are already employed by Government could support the management of future emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1142 | 18 - Access to fire ground | That SACFS consider the Traffic Management Procedures and guiding principles adopted in Tasmania as a model that could be implemented within SA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1058 | 28 - Personal responsibility | That NPWS and the RFS consider developing a land management policy that requires active engagement with property owners adjoining the Park to ensure that hazard reduction and asset protection is encouraged and undertaken before the bush fire season commences |
REC260-1061 | 18 - Access to fire ground | That the National Parks and Wildlife Service, in consultation with the relevant local Council(s), devise a policy that enables the John Renshaw Parkway to be closed at either end of the Warrumbungle National Park during a bush fire in such a way that its closure would not impede access by emergency services vehicles into the park. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2561 | 24 - Govt responsibility | The Australian Government amends regulations so that background checks and the requirement to hold an Aviation Security Identification Card are only required for unescorted access to Security Restricted Areas, not for general airside access. This approach would align with international practice. |
REC258-2530 | 24 - Govt responsibility | The Australian Government appoints an additional Australian Transport Safety Bureau Commissioner with aviation operational and safety management experience. |
REC258-2526 | 24 - Govt responsibility | The Australian Government develops the State Safety Program into a strategic plan for Australia’s aviation safety system, under the leadership of the Aviation Policy Group, and uses it as the foundation for rationalising and improving coordination mechanisms. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1568 | 24 - Govt responsibility | State governments, where they have not already done so, should provide local governments with statutory protection from liability for releasing natural hazard information and making changes to local planning schemes where such actions have been taken ‘in good faith’ and in accordance with state planning policy and legislation. |
REC256-1556 | 37 - Funding | The Australian Government should fund natural disaster recovery by: |
REC256-1577 | 37 - Funding | The Australian Government should develop a formula for allocating mitigation funding to state and territory governments on the basis of where such funding is likely to achieve the greatest net benefits, taking into account the future risks of natural disasters. This should be completed within five years and in consultation with state and territory governments. |
REC256-1567 | 24 - Govt responsibility | State and territory governments should: |
REC256-1560 | 37 - Funding | The Australian Government should: |
REC256-1566 | 24 - Govt responsibility | State and territory governments should prioritise and accelerate implementation of the Enhancing Disaster Resilience in the Built Environment Roadmap, including reviewing the regulatory components of vendor disclosure statements. The Land Use Planning and Building Codes Taskforce should be tasked to identify and consider options for regular, low-cost dissemination of hazard information to households by governments and insurers. |
REC256-1559 | 37 - Funding | The Australian Government should gradually increase the amount of annual mitigation funding it provides to state and territory governments to $200 million. Initially, this funding should be distributed to state and territory governments in accordance with the allocation under the National Partnership Agreement on Natural Disaster Resilience. |
REC256-1561 | 24 - Govt responsibility | State and territory governments should be required to report on the following accountability requirements: |
REC256-1575 | 24 - Govt responsibility | State and territory governments should develop benchmark prices for the reconstruction of essential public assets and submit these to the Australian Government for approval within one year. In developing these prices, they should consult with local governments and relevant experts, and draw on asset management plans. The prices should be reviewed and updated over time. |
REC256-1558 | 37 - Funding | Funding to state and territory governments for community recovery should be provided as untied grants, with a transition period pending the development of a framework to assess community recovery costs. During the transition period, the Australian Government should continue to provide funding for community recovery through a reimbursement model. |
REC256-1571 | 24 - Govt responsibility | State and territory taxes and levies on general insurance should be phased out and replaced with less distortionary taxes. |
REC256-1557 | 37 - Funding | Where asset management plans at the local, state or territory level pre-identify and cost betterment of assets (improving asset resilience to natural disasters), the Australian Government should share 50 per cent of the betterment component of reconstruction costs following damage from a (eligible) natural disaster. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0928 | 24 - Govt responsibility | That the Government take into account demographic change in its assessment of the consequences of climate change on emergency events. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
REC247-0910 | 33 - Relief and recovery | That suitable facilities are established from which to effectively control and coordinate immediate recovery operations. |
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0932 | 37 - Funding | That the resources available to the Parks and Wildlife Service, to manage bushfire risk following the recent increase in land under its tenure, is reviewed. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0907 | 33 - Relief and recovery | That the State Emergency Management Committee ensures that a program of debriefing on recovery issues is completed by all relevant agencies and organisations, and detailed plans and operating procedures are established ready for implementation. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0896 | 33 - Relief and recovery | That the state level structural arrangements for managing recovery operations are reviewed. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2606 | 22 - Role of local Gvt | The Act be amended to require the mandatory appointment of Authorised Officers by each rural council or council that has within its area a Designated Urban Bushfire Risk Area(s) with an option for the CFS Chief Officer to exempt council from this requirement (similar to Section 105B). |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2699 | 24 - Govt responsibility | That the Minister establish a public sector office to be headed by an Inspector General of Emergency Management. The Inspector General of Emergency Management will be responsible for most of the functions listed under part 16A of the current Disaster Management Act 2003. |
REC239-2753 | 37 - Funding | That the proposed Chief Executive Officer Portfolio Business be responsible for developing a cost attribution model for portfolio agencies, including the Queensland Police Service, as a priority. |
REC239-2721 | 24 - Govt responsibility | That the Chief Executive Officer Portfolio Business collaborate with the two portfolio Commissioners to: |
REC239-2662 | 24 - Govt responsibility | That responsibility for prisoner transport and non-managerial roles within the larger watch-houses is transferred to Queensland Corrective Service. |
REC239-2687 | 24 - Govt responsibility | That funding, staffing and responsibility associated with administration of the NDRP be transferred from Emergency Management Queensland to the Department of Local Government, Community Recovery and Resilience. |
REC239-2683 | 37 - Funding | That the Office of Portfolio Business follows the same budget processes as other agencies. |
REC239-2712 | 24 - Govt responsibility | That Emergency Management Queensland be integrated with the current Queensland Fire and Rescue to become the Department of Fire and Emergency Services. |
REC239-2661 | 24 - Govt responsibility | That Queensland Corrective Service remains a separate program within the Department of Justice and Attorney-General so that while opportunities for improved services and efficacy can be realised, there is a clear separation from the youth justice services. |
REC239-2782 | 24 - Govt responsibility | That transparency of the Ministerial direction be achieved through publishing and monitoring for effectiveness. |
REC239-2686 | 24 - Govt responsibility | That primacy of control should rest with the State Disaster Coordinator. This position should, by default, be the Deputy Commissioner, Regional Operations, Queensland Police Service. |
REC239-2682 | 37 - Funding | That a budget based on the desired functional accountabilities should be appropriated to the Portfolio Business as part of the Government budget process. |
REC239-2708 | 24 - Govt responsibility | That the role of the Inspector General Emergency Management not extend to conducting reviews on behalf of agencies and that the role consider the effectiveness of all agencies and how their work contributes to a whole of Government response. |
REC239-2660 | 24 - Govt responsibility | That Queensland Corrective Services be transferred to the Department of Justice and Attorney-General by a machinery-of-Government change as soon as is practicable. |
REC239-2759 | 24 - Govt responsibility | That the new Chief Executive Officer Portfolio Business be accountable for delivering the reformed Communications Centre arrangement by the 2017–18 financial year in time for the Commonwealth Games of 2018. |
REC239-2685 | 24 - Govt responsibility | That primacy of control for disaster operations remains with the Queensland Police Service and be reinforced. |
REC239-2681 | 37 - Funding | That the funding model for the Portfolio Business is not based on fee- for-service arrangements or notional contributions from the operational services. |
REC239-2701 | 24 - Govt responsibility | That the Inspector General Emergency Management provide continuing advice to Government on the level of interoperability in disaster management arrangements, as well as the level of interoperability being achieved within the new portfolio. |
REC239-2780 | 37 - Funding | That should the Westgate project proceed, that consideration must be given to opportunities to partner the investment with the private and public sectors. The business case should also consider alternative facilities such as Australian Defence Force sites. |
REC239-2657 | 24 - Govt responsibility | That negotiation takes place between Queensland Health and the Queensland Ambulance Service to determine the broad governance requirements of any such arrangements. |
REC239-2749 | 24 - Govt responsibility | That the Prostitution Licensing Authority be moved to the Department of Justice and Attorney General Office of Fair Trading. |
REC239-2679 | 24 - Govt responsibility | To remove the Queensland Ambulance Service and Queensland Corrective Services from the Department of Community Safety—we recommend that it be renamed the Department of Fire and Emergency Services and be led by a Commissioner. |
REC239-2700 | 24 - Govt responsibility | That the position of Inspector General Emergency Management (in addition to some of the responsibilities of the chief executive officer under the current Disaster Management Act 2003) will: |
REC239-2779 | 37 - Funding | That a new business case for Westgate project should be prepared by an independent party. |
REC239-2655 | 24 - Govt responsibility | That the Queensland Ambulance Service is transferred to Queensland Health by a machinery-of-Government change as soon as is practicable and that the Commissioner report directly to the Director General Queensland Health. |
REC239-2732 | 24 - Govt responsibility | There be a formation of an Office of Portfolio Business, providing support and governance across a range of corporate functions, which are essential to the delivery of frontline services. The Review team considers that the functions of the Operations Business and Strategy Directorate should become part of that Office and that any exception should be carefully considered by those charged with implementation of approved recommendations. |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2678 | 24 - Govt responsibility | That probation and parole should continue to work together with the Queensland Police Service to reduce the risk of reoffending and reduce crime. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0834 | 37 - Funding | That the NSW Rural Fire Service apply for funding from the NSW Treasury for the development of a multi-agency business case for a BRIMS replacement that includes internal management, risk communication, community engagement capability and publishing activities on websites. |
REC237-0833 | 37 - Funding | That the NSW Rural Fire Service and the NSW Treasury explore ways to ensure that unspent hazard reduction funds be carried over to the next financial year in a timely manner and to ensure that hazard reduction funding has a seamless transition from one financial year to the next. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2889 | 37 - Funding | Review level of investment in research activities to free up budget and reduce pressure on computing capacity |
REC207-2879 | 37 - Funding | Firm up approval processes and funding for any departures from provision of the basic product set |
REC207-2877 | 37 - Funding | Explore opportunities to re-phase investments in large scale projects and programs such as the Strategic Radar Enhancement Program, the NexGen Forecast and Warning System Products and the Improving Water Information Program. |
REC207-2893 | 37 - Funding | Explore options to obtain revenue from advertising on the Bureau’s website |
REC207-2892 | 37 - Funding | Apply a consistent cost-recovery model to all services delivered to state/territory fire agencies. |
REC207-2890 | 37 - Funding | Review and rebalance relative investment in long term climate modelling and medium-term seasonal outlook. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1904 | 24 - Govt responsibility | State and territory taxes and levies on general insurance constitute a barrier to effective adaptation to climate change. State and territory governments should phase out these taxes and replace them with less distortionary taxes. |
REC205-1899 | 24 - Govt responsibility | Local governments’ uncertainty about their legal liability is a barrier to effective climate change adaptation. State governments should clarify the legal liability of councils with respect to climate change adaptation matters and the processes required to manage that liability. |
REC205-1898 | 24 - Govt responsibility | To help clarify roles and responsibilities of local government for climate change adaptation, the state and Northern Territory governments should publish and maintain a comprehensive list of laws that delegate regulatory roles to local governments. This would assist both state and local governments to assess whether local governments have the capacity to discharge their roles effectively. |
REC205-1896 | 24 - Govt responsibility | Australian governments should implement policies that help the community deal with the current climate by improving the flexibility of the economy. This would also build adaptive capacity to deal with future climate change. This includes reforms to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0247 | 28 - Personal responsibility | Local residents must take a degree of shared responsibility to prepare their properties by reducing the risk of bushfire around their properties and planning for a bushfire emergency. |
REC201-0256 | 22 - Role of local Gvt | Noting existing legislative and policy arrangements, there is merit in considering options for the future management of Level 3 fires in Local Government areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0354 | 22 - Role of local Gvt | Local governments consider increasing the number of green waste collections carried out each year to encourage a more proactive approach to property (and vegetation) maintenance by residents. |
REC200-1727 | 24 - Govt responsibility | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-1725 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-1683 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. |
REC200-0385 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-1694 | 24 - Govt responsibility | The State Government give its full support to the Western Australian Local Government Association's Send to Solve initiative. |
REC200-0353 | 22 - Role of local Gvt | The State Government give its full support to the Western Australian Local Government Association’s Send to Solve initiative. |
REC200-1723 | 24 - Govt responsibility | The State Government restructure the Fire and Emergency Services Authority as a Department. As part of this restructure, Emergency Management Western Australia should either |
REC200-1682 | 24 - Govt responsibility | The State Government give legislative effect to the Planning for Bush Fire Protection Guidelines. |
REC200-0345 | 22 - Role of local Gvt | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-1719 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-1729 | 22 - Role of local Gvt | The Fire and Emergency Services Authority and local governments ensure that Community Emergency Service Managers are physically based in local government. |
REC200-1681 | 24 - Govt responsibility | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-0342 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. Local Government provide information to residents on any changes to the Australian Standard relating to tethering gas tanks and encourage property owners to take action to comply with the Standard. |
REC200-1717 | 24 - Govt responsibility | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-0375 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. This program should be implemented and managed under the Bush Fires Act 1954 in a manner similar to the fire break inspection program. |
REC200-1715 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. |
REC200-0379 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-0373 | 33 - Relief and recovery | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-1716 | 24 - Govt responsibility | State and locals governments: |
REC200-0367 | 22 - Role of local Gvt | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0369 | 18 - Access to fire ground | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
REC200-1728 | 24 - Govt responsibility | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-1695 | 22 - Role of local Gvt | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-1699 | 24 - Govt responsibility | The State Government ensure that the continued development of the Fire and Emergency Service Authority's Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost-effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0135 | 33 - Relief and recovery | FESA revises its standard operating procedures to provide guidance on the format and timing of post-incident community meetings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3364 | 37 - Funding | The funding arrangements that support the National Plan should be reviewed to ensure that the costs associated with both preparedness and response capability are equitably shared between the shipping and offshore petroleum industries. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
REC165-0098 | 24 - Govt responsibility | The SDMG take into account key improvement initiatives and change processes suggested when deciding on an effective implementation strategy for agreed recommendations. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
REC165-0097 | 24 - Govt responsibility | Revised governance arrangements be implemented involving Disaster Management Groups at the three levels supported by EMQ as outlined in this report to achieve continuous improvement in the Disaster Management arrangements in the State. A new provision in Section 5 emphasise the discretion available to all involved in the Disaster Management system to take action to prevent impending loss of life even if contrary to the agreed arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3028 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources continue to support a duty of care safety case regime for best practice offshore petroleum industry regulation augmented to include regulation of integrity. Since the safety case is at the centre of the duty of care co-regulatory regime, we consider that the requirement for the implementation of the safety case at facilities involved in the exploitation of petroleum resources should be provided for within the Offshore Petroleum and Greenhouse Gas Storage Act 2006 itself. |
REC161-3035 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources liaise with Ministers with environmental and planning responsibilities, and if necessary Council of Australian Governments, to ensure that environmental requirements for oil and gas projects are not imposed subsequent to safety assessments and do not increase the risk of major accident events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1780 | 22 - Role of local Gvt | That the Minister for Local Government cause rural councils to appoint an Officer whose duties consist entirely of bushfire prevention, such Officer being required to become a trained, operative member of the South Australian Country Fire Service during the currency of his or her appointment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3095 | 24 - Govt responsibility | SAFECOM re-evaluate and determine a more meaningful definition of fire districts. |
REC151-3071 | 24 - Govt responsibility | The comprehensive prevention, preparedness, response and recovery (PPRR) approach to the management of bushfires as recommended by the Ministerial Review of Bushfire Management in South Australia is supported: its implementation should consider issues raised by councils and should also be considerate of the recommendations of the Wangary Coronial Inquest. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3553 | 37 - Funding | RHH Neonatal Emergency Transport Service receive DHHS funding for a Senior Registrar to assume the responsibilities of retrieval staffing, quality assurance, data collection and reporting demands. |
REC140-3552 | 37 - Funding | Department of Health and Human Services (DHHS) to fund 3 Full-Time Equivalent (FTE) Senior Registrar positions at the Royal Hobart Hospital (RHH) for the Tasmanian Medical Retrieval Service (TMRS). One registrar in the Anaesthesia Department, one in the Intensive Care Unit and one in Emergency Department is proposed. |
REC140-3568 | 37 - Funding | The State Medical Retrieval Cost Centre (TMRS and NETS) be formed and be supported by the appropriate administrative and resource accountant expertise. This cost centre should be placed with those responsible for its management. |
REC140-3575 | 24 - Govt responsibility | The preferred model for the Tasmanian Medical Retrieval Services is to have TMRS and NETS staff based in RHH. The fixed wing would remain based in Launceston (for the present) with the helicopter to remain based in Hobart. |
REC140-3567 | 37 - Funding | A uniform retrieval charge to the region of referral should be considered. This should be independent of the mode of transport used. |
REC140-3554 | 37 - Funding | DHHS fund the equivalent of 2 FTE Consultant positions for retrieval duties (1.5 FTE existing, 0.5 FTE new) |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3529 | 24 - Govt responsibility | The Queensland Government should consider the endorsement of transitional arrangements proposed in this report, in order to ensure as far as possible the smooth completion of the recovery and the ultimate return to government operations as usual in the cyclone-affected area. |
REC136-3525 | 24 - Govt responsibility | In any future disaster of comparable proportions, consideration should be given to the co-location of the Building Coordination Centre and the principal One Stop Shop. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1979 | 24 - Govt responsibility | That the policy and practice just recommended be the subject of a memorandum of understanding between the Emergency Services Agency and the Department of Territory and Municipal Services (previously the Department of Urban Services) or other relevant department or agency, so as to ensure that the land management agency on whose land a fire starts has responsibility to respond immediately to that fire in accordance with the applicable standards for weight of response. Further, the land management agency should be responsible for efforts to suppress fire until such time as it becomes clear that the suppression task is beyond capacity of the agency, at which point the ACT Rural Fire Service should assume direct responsibility for coordinating the ongoing response |
REC126-2012 | 24 - Govt responsibility | If they are willing and available to participate, that the taskforce's membership include Mr Phil Cheney, Mr Tony Bartlett, Mr Val Jeffery and Mr John Lowe |
REC126-1976 | 24 - Govt responsibility | That the Emergency Services Agency have authority over the land management agencies and other landholders in order to implement preparedness and prevention measures – including fuel-reduction works where there are failures in compliance |
REC126-2009 | 24 - Govt responsibility | That a taskforce be established to give effect to the recommendations in this report |
REC126-1962 | 24 - Govt responsibility | That, because of the small jurisdiction of the ACT (equivalent to one fire district in NSW) the ACT Government consider all possible options for the provision of fire services to the ACT, among them: |
REC126-2006 | 24 - Govt responsibility | I recommend that, as appropriate, the ACT cooperate with the Commonwealth in the implementation of the committee's recommendations and, in particular, give careful consideration to adoption of the following recommendations: |
REC126-1948 | 24 - Govt responsibility | That the Emergency Services Agency be removed from the Department of Justice and Community Safety and transformed into an independent statutory authority reporting directly to the responsible Minister. Note in this regard that Mr McLeod made a similar recommendation, and I endorse it unequivocally. Placing the agency within a government department puts unnecessary layers of bureaucracy between the agency and the responsible Minister, and the bureaucrats concerned usually have no special knowledge of or experience in emergency management, regardless of their seniority in the bureaucracy |
REC126-1985 | 24 - Govt responsibility | That the Emergency Services Agency, with the suport of the ACT Government, seek to establish with the NSW Department of Environment and Conservation and the NSW Rural Fire Service a protocol that will provide for the establishment of a joint incident management team as part of unified control arrangements based on adoption of the following principles: |
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-1942 | 24 - Govt responsibility | That the ACT Attorney-General and the ACT Government - in consulation with the Chief Justice of the ACT and the ACT Chief Magistrate - take legislative action that would have the effect of funds being directly appropriated annually to the courts, preferable along the lines of the Commonwealth model as it applies to the High Court of Australia, the Federal Court of Australia, the Family Court of Australia and the Federal Magistrates Court. Alternatively, the funds could be appropriated in accordance with the South Australian model, which has a seperate Courts Administartion Authority. |
REC126-1984 | 24 - Govt responsibility | That the Emergency Services Agency, with the support of the ACT Government, develop a single, new memorandum of understanding with the NSW Department of Environment and Conservation and the NSW Rural Fire Service, providing for liaison and joint operations as soon as it becomes apparent to whichever jurisdiction is managing a fire that the fire will probably affect the other jurisdiction. Joint operations should not be limited to when an incident occurs on both sides of the border, as is the current arrangement |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |