Rec-ID | Code | Recommendation |
---|---|---|
REC316-4023 | 41 - Emergency Management exercises | An opportunity to exercise and test the formation and functioning of a Management Executive through desktop and/or limited scenario-based exercises be provided. |
REC316-4034 | 15 - Inter-service cooperation | Efforts be increased to build trust, confidence and a common operating picture across PCS and RFS and seek mechanisms that identifies RFS and PCS as equitable partners in delivery of fire management across the territory. |
REC316-4019 | 15 - Inter-service cooperation | In collaboration with other jurisdictions the ACT share the learnings for this bushfire event and work to officially embedded values officers and RRATs as key elements of bushfire response. |
REC316-4032 | 41 - Emergency Management exercises | Concurrent and/or non–standard emergencies such as energy supply impacts be included in future exercise programs. |
REC316-4043 | 15 - Inter-service cooperation | NDIA be engaged in regard to information sharing in emergencies as part of the above actions. |
REC316-4017 | 15 - Inter-service cooperation | The working group (Rec 1) should include relevant stakeholders deciding collectively what the declaration might mean for such things as sub and supporting plans and the relevant community messages and calls to action. |
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
REC316-4041 | 9 - Community education | The ESA Community Education and Engagement program be adapted to include an expanded role for RFS volunteers and include a wider set of stakeholders who are more vulnerable to the impact of bushfire. A plan would require wider involvement across stakeholder organisations such as Directorates who have existing relationships with vulnerable groups. |
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4040 | 41 - Emergency Management exercises | The PICC be exercised in conjunction with any and all Emergency Plan exercises to test and refine strengthened arrangements. |
REC316-4028 | 41 - Emergency Management exercises | Any changes to the ECC structure and role be exercised both within ESA and across a WHoG exercise and testing program. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
REC291-1242 | 15 - Inter-service cooperation | The Departments of Fire and Emergency Services and Parks and Wildlife to investigate and adopt an emergency services resource management system that will enable the registration, tasking, tracking, management and coordination of emergency management personnel, vehicles, plant and aircraft. |
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1210 | 15 - Inter-service cooperation | Co‐designed arrangements that support a unified response to fire |
REC290-1209 | 15 - Inter-service cooperation | Coordinated and targeted mitigation of fire risk |
REC290-1219 | 17 - Assets and technology | Live resource tracking system that can be used by all response agencies |
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1117 | 17 - Assets and technology | Automatic Vehicle Location technology should be adopted to enable a better appreciation of the deployment and location of appliances at an incident, in order to increase situational awareness |
REC265-1106 | 15 - Inter-service cooperation | In addition to regular meetings of the DFES/DPaW Interagency Bushfire Management Committee, the two organisations should use joint exercises to identify agreed firefighting approaches for common or likely scenarios. |
REC265-1116 | 17 - Assets and technology | Procedures should be established to monitor the use of heavy plant during a bushfire incident, including the tasking of support appliances. Procedures should provide for the appointment of a dedicated Machinery Supervisor as prescribed within the Australasian Interservice Incident Management System. |
REC265-1105 | 15 - Inter-service cooperation | The Executive Teams of both DFES and DPaW should meet quarterly to review and agree joint improvements relating to issues of interoperability, complementarity and the alignment of firefighting doctrine. The establishment of a unified command in joint State Operations Centre, Regional Operations Centre and Incident Management Teams should be pursued as an overarching goal. |
REC265-1112 | 17 - Assets and technology | Radio infrastructure in the Perth Hills should be reviewed to assess whether it is practicable for radio and/or mobile phone coverage to be improved to achieve better coverage across the area. |
REC265-1101 | 9 - Community education | Staff and consultants skilled in community engagement practice should be specifically included in bushfire risk management planning and preparedness building programs undertaken by State agencies and/or local government. |
REC265-1111 | 15 - Inter-service cooperation | All agencies engaged in bushfire response should develop expeditious procedures for the mobilisation of resources in support of other agencies. See discussion in Section 7.1. |
REC265-1123 | 17 - Assets and technology | Every effort should be made to enhance the ability of communications personnel to cope with fast moving and time critical fire events by providing and maintaining: ongoing extensive communications training; advanced vehicle capability for clear communication within areas of radio coverage dead spots; ability to receive Air intelligence live streaming; map production facilities; deployment of multiple Incident Control Vehicles when required; all Incident Control Vehicles with access to DFES Information Technology Systems. |
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1120 | 9 - Community education | DFES should prepare a Standard Operating Procedure for the conduct of community meetings, and have available the appropriate audio visual and other equipment, to ensure that such meetings are able to fulfil their function in providing information and direction |
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1582 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1586 | 15 - Inter-service cooperation | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1622 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should continue to improve working arrangements between the ACT Rural Fire Service Parks Brigade and the ACT Rural Fire Service headquarters, by: |
REC228-1619 | 1 - Land-use and building regs | The Territory and Municipal Services Directorate, in consultation with the Emergency Services Agency, should improve its management of Land Management Agreements, with respect to rural leaseholders’ fire management responsibilities, by: |
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
REC228-1623 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should develop and routinely review a strategic bushfire capability for the ACT. The contribution of ACT Fire and Rescue (including the Community Fire Units) and the ACT Rural Fire Service (including Parks Brigade) should be explicitly stated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2851 | 17 - Assets and technology | I recommend that consideration should be given to acquiring two personal water craft for deployment by appropriately trained and equipped staff of the AFP or the VMRS or both on Christmas Island. |
REC227-2850 | 17 - Assets and technology | I recommend that the AFP be provided with a search and rescue vessel which is suitable to the specific conditions of Christmas Island. I further recommend that steps be taken to ensure that if for any reason the search and rescue vessel is not available, there is a replacement vessel on Christmas Island capable of providing an emergency response in difficult sea conditions. |
REC227-2848 | 17 - Assets and technology | I recommend that the AFP take steps to determine whether access can be obtained to the National Search and Rescue Council endorsed SARMAP program covering the Australian Search and Rescue Region as well as adjoining tiles for Indonesia. Steps should be taken to ensure that if possible coverage would include high traffic areas where SIEVs enter the Australian Search and Rescue region allowing timely search and rescue plans to be drawn up for any potential incidents. |
REC227-2859 | 17 - Assets and technology | I recommend that the issue of RHIB jet intake protection be allocated a high priority and that there be ongoing investigation of possible solutions to reduce the problem. |
REC227-2847 | 15 - Inter-service cooperation | I recommend that Border Protection Command implement a surveillance strategy, possibly with the assistance of other Commonwealth authorities and organisations on the island such as the AFP, which heightens its coverage at times when the weather and sea conditions are rough. |
REC227-2858 | 13 - Mapping and data quality | I recommend that the Commonwealth prioritise completion of a hydrographic survey of Christmas Island and ensure that such a survey is completed in the near future. |
REC227-2846 | 17 - Assets and technology | I recommend that Border Protection Command continues to examine ways of improving its surveillance capability around Christmas Island so that the risk of SIEVs arriving undetected is reduced. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0582 | 17 - Assets and technology | The state should progressively align on a shared platform, such as WebEOC, to establish a COP [Common Operating Picture or Platform?]. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0545 | 26 - Research | Improved understanding of fire behaviour in coastal heathlands would support sound risk management through the southwest of W |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0578 | 15 - Inter-service cooperation | There would be benefit in progressively aligning the geographic boundaries of each of the agencies and seeking to co-locate their headquarters within those boundaries. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0576 | 13 - Mapping and data quality | Better maps are required for urban/rural interface fires |
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0548 | 15 - Inter-service cooperation | Inter-agency cooperation to manage fire precincts in a tenure-blind fashion is necessary for effective fire suppression. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0560 | 15 - Inter-service cooperation | There would be value in progressively aligning the geographical boundaries of emergency management agencies and co-locating where possible within regions and districts. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0547 | 13 - Mapping and data quality | Fuel loads on private property need to be identified and included in understanding fire behaviour in determine the contribution they make to the burn risk assessment. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
REC226-0583 | 17 - Assets and technology | The state should converge on a single communications platform for all emergency management and support agencies. |
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0546 | 13 - Mapping and data quality | Maps prepared for prescribed burns should address the fuel type and burn history of the burn area as well as surrounding areas. Predicted rates of spread under prescribed and other conditions should recognise the complexity of coastal heathlands. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC225-0533 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
REC224-1630 | 13 - Mapping and data quality | The Minister for Emergency Services ensure that a Statewide fuel load database that includes data from Western Power, the Department of Fire and Emergency Services and the Department of Environment and Conservation be established before the 2013-14 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
REC223-0521 | 9 - Community education | The Department of Environment and Conservation develop and implement a strategy to better inform the community about the complexities and decisions surrounding prescribed burns when they are undertaken in the rural urban area. |
REC223-0517 | 26 - Research | The Department of Environment and Conservation be supported to conduct further research into the fuel management of coastal heath in the south west of Western Australia exploring alternatives to burning as well as best practice for burning. |
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1861 | 41 - Emergency Management exercises | The Ministers for Health, Emergency Services, Environment and Police provide additional funds to their agencies so that a detailed exercise is held on a regular basis based on a disaster that will create the worst outcome for the State. |
REC222-1857 | 15 - Inter-service cooperation | The Ministers for Health, Police, and Emergency Services ensure that the Western Australia Police, the Fire and Emergency Services Authority and St John Ambulance establish a formal platform to share their knowledge and experience in delivering programs to their staff and volunteers to address issues of stress from disasters and critical incidents, as is done in other Australian jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1918 | 1 - Land-use and building regs | Department of Regional Development and Lands and Department of Environment and Conservation should consider how their respective land use approval processes can incorporate the input of Local Emergency Management Committees (LEMCs) as part of risk assessments for high risk events and adventure sport activities. |
REC204-1914 | 15 - Inter-service cooperation | FESA, WA Police and St John Ambulance establish a uniform protocol for handling multiple agency emergency responses that does not involve callers having to make multiple calls to 000. |
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
REC204-1919 | 1 - Land-use and building regs | Tourism WA must give specific regard as to whether land use approvals need to be sought, particularly from Department of Regional Development and Lands, when conducting due diligence for event sponsorship proposals that require sign off by both departments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
REC203-0298 | 15 - Inter-service cooperation | The state should progressively align on a shared platform, such as WebEO C , to establish a Common Operating Picture (COP). |
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
REC203-0288 | 15 - Inter-service cooperation | The State Duty Officer from DEC and the State Duty Director, FES A need to confer whenever a Level 2 or 3 incident is declared to satisfy themselves that they have appropriate incident management structures and resources across the state are at an appropriate level of preparedness. |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
REC203-0301 | 15 - Inter-service cooperation | Early in an incident, close and effective liaison needs to be established with local government agencies. |
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0287 | 15 - Inter-service cooperation | On a regional basis there would be value in closer working relationship between DEC crews and VBFBs to build mutual trust and confidence. This could be done by opportunity engagement of VBFBs in DEC fire management or through exercises. |
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0299 | 15 - Inter-service cooperation | The state should converge on a single communications platform for all emergency management and support agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0504 | 15 - Inter-service cooperation | The Minister for Emergency Services ensure that the annual budget of FESA contains the funds it requires to coordinate an annual multi-agency bushfire field exercise, alongside other desktop exercises, to be held in different regions of the State each year. The outcomes of this field exercise should be included in the proposed annual Ministerial statement to Parliament on bushfire readiness before each season. |
REC202-0512 | 9 - Community education | The Minister for Emergency Services commission an independent report to Parliament by June 2012 on an assessment of the success of FESA’s Total Fire Ban community education campaign in improving the community’s knowledge on this issue. |
REC202-0496 | 17 - Assets and technology | The Minister for Emergency Services ensure that a whole-of-government equipment register of the firefighting equipment held by FESA, DEC and local government authorities is in place for the 2012-13 bushfire season. |
REC202-0511 | 9 - Community education | The Minister for Emergency Services commission an independent report to Parliament by June 2012 on the best practices in other jurisdictions to increase the rate of residents likely to be effected by a bushfire who properly prepare their properties before the bushfire season. |
REC202-0510 | 9 - Community education | The Minister for Emergency Services and the Minister for Local Government provide additional resources to FESA, DEC and WALGA in the 2012-13 Budget to improve the Western Australian community’s knowledge of bushfire safety and to allow these agencies to involve the public in their exercises. |
REC202-0507 | 13 - Mapping and data quality | The Minister for Emergency Services, with advice from the Interagency Bushfire Management Committee Fuel Load Management sub-committee, report to Parliament by May 2012 on the estimated cost of developing one fuel load information system across all lands in Western Australia, no matter who manages it. This system’s information should be readily accessible and easily understood by all stakeholders, including the public. |
REC202-0506 | 17 - Assets and technology | The Minister for Emergency Services ensure that FESA has the funds to implement the installation and use of WebEOC for use during the 2011-12 bushfire season and immediately put in place common protocols with the Police and DEC to record significant events during a bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0249 | 17 - Assets and technology | FRS fire appliance allocation and training needs to be reviewed to enhance offensive bushfire capability within the metropolitan area. |
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
REC201-0247 | 28 - Personal responsibility | Local residents must take a degree of shared responsibility to prepare their properties by reducing the risk of bushfire around their properties and planning for a bushfire emergency. |
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
REC201-0260 | 15 - Inter-service cooperation | There are a range of opportunities identified from reviewing the three fires that will improve coordination between FESA and DEC, requiring limited resources, potentially generating some efficiencies and reflecting a joint, tenure blind approach to fire management in WA. The MIR acknowledges the progress made through the IBMC in these matters and notes these measures will require ongoing strong leadership. These include: · Clarification and consistent application of the Zone 2 and 2A mobilisation protocols; · Duplicating available information on websites; · Establishing a single State air desk and cross-utilising Air Attack Supervisors; · Completing common training for the conduct of public meetings;· Coordinating IMT training and exercises; · Operating joint IMT‘s during interface fires; FESA utilising the DEC mobile ICC when suitable ICPs are not available; · FESA engaging in daily weather teleconferences with DEC; Engaging a permanent BoM officer to support a common FESA and DEC SOC; · Developing a common ‗Tool Box‘ of forms and operational procedures for fire response; · Developing common jurisdictional arrangements to accommodate interstate support; · Developing a joint FESA/DEC SOC at the new (FESA) Emergency Services facility at Cockburn; · Adopting common and transparent Level 3 IC accreditation · Using a single mapping capability across both agencies and · Using common naming conventions for fires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1688 | 9 - Community education | The Department of Education oversee the provision of bushfire education in schools that are located in bushfire prone areas, ensuring that all schools in these areas incorporate key bushfire messages in their curriculum. |
REC200-0343 | 9 - Community education | The Fire and Emergency Services Authority, in partnership with local governments, conduct more focused pre-season bushfire education, which emphasises: Water supply is not guaranteed during a bushfire Power supply is not guaranteed during a bushfire Saving life will be a priority over saving property so expect to be evacuated Once evacuated, access to affected areas may not be possible for several days Water ‘bombing’ by aircraft cannot be guaranteed in bushfire SMS warnings are advice only and may not be timely. |
REC200-0365 | 17 - Assets and technology | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA’s own policy of ‘Use of Private Vehicles in Fires’. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-0349 | 9 - Community education | The Fire and Emergency Services Authority work in partnership with Main Roads Western Australia and local governments to develop and implement a comprehensive strategy for the use of mobile variable message boards to alert the community to the declaration of a total fire ban and what it means. |
REC200-0386 | 15 - Inter-service cooperation | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. This should include field exercises which test: Evacuation centres Critical infrastructure (including at the local level) Traffic management, including road blocks. Consideration should also be given to involving the community in exercising (see Recommendation 7) and using prescribed burns as exercises (see Recommendation 14) More detailed planning for exercises should be included in a revised WESTPLANBUSHFIRE to be endorsed by the State Emergency Management Committee. |
REC200-1679 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-1687 | 9 - Community education | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-0340 | 1 - Land-use and building regs | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-0364 | 17 - Assets and technology | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-0348 | 9 - Community education | The Fire and Emergency Services Authority consider alternative wording to Total Fire Ban that ensures people gain a more complete understanding of what actions are prohibited. |
REC200-0378 | 17 - Assets and technology | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0355 | 13 - Mapping and data quality | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-1686 | 9 - Community education | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-0338 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
REC200-1697 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-0347 | 9 - Community education | The Department of Education oversee the provision of bushfire education in schools that are located in bushfire prone areas, ensuring that all schools in these areas incorporate key bushfire messages in their curriculum. |
REC200-0377 | 1 - Land-use and building regs | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-1708 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-0352 | 13 - Mapping and data quality | The Fire and Emergency Services Authority and local governments ensure that the ability to: measure and map fuel loads maintain fuel load databases draw up prescriptions for, and oversee controlled burns are included as key competencies in any future recruitment of Chief Bushfire Control Officers and Community and Emergency Services Managers. |
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
REC200-1685 | 9 - Community education | The Fire and Emergency Services Authority (FESA) review its distribution of information material, including Prepare. Act. Survive. FESA should also consider including the community in pre-season exercising, in consultation with the Department for Child Protection and local governments. |
REC200-0359 | 13 - Mapping and data quality | The State Government ensure that the continued development of the Fire and Emergency Service Authority’s Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-0346 | 1 - Land-use and building regs | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-0376 | 1 - Land-use and building regs | State and locals governments: a) recognise that regardless of future declarations of bushfire prone areas, the existing planning and building problems in the Perth Hills related to bushfire risk will persist; b) urge residents in these areas to retrofit their homes and evaporative air conditioners in compliance with AS 3959 - 2009; c) examine options to retrospectively bring these areas into compliance with Planning for Bushfire Protection Guidelines. |
REC200-1707 | 1 - Land-use and building regs | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
REC200-0388 | 17 - Assets and technology | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-1684 | 9 - Community education | The Fire and Emergency Services Authority, in partnership with local governments, conduct more focused pre-season bushfire education, which emphasises: |
REC200-0358 | 13 - Mapping and data quality | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. The system should enable public access to allow members of the community to access information about the fuel load in a given locality. |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-0344 | 9 - Community education | The Fire and Emergency Services Authority (FESA) review its distribution of information material, including Prepare. Act. Survive. FESA should also consider including the community in pre-season exercising, in consultation with the Department for Child Protection and local governments. |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-0387 | 17 - Assets and technology | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the Recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-1680 | 15 - Inter-service cooperation | Emergency Management Western Australia establish an inter-agency working group to continue the development of the new single emergency services Act. |
REC200-1726 | 41 - Emergency Management exercises | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. |
REC200-0357 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0118 | 15 - Inter-service cooperation | A Memorandum of Understanding signed by the Chief Executives of DEC and FESA would be a valuable statement of joint commitment between the two agencies. |
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
REC183-0117 | 15 - Inter-service cooperation | The Interagency Bushfire Management Committee and its sub-committees are the logical central platform for developing and strengthening future joint bushfire strategies and common systems of work between bushfire management agencies in Western Australia. |
REC183-0109 | 1 - Land-use and building regs | It is sensible that, in considering planning development proposals on land adjacent to the DEC estate, that development authorities invite comment from DEC on the fire management consequences of development proposals. |
REC183-0116 | 15 - Inter-service cooperation | Triggers and a process for transfer of command and control from DEC to FESA should be developed and documented. |
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
REC183-0120 | 17 - Assets and technology | Maintaining the DEC fleet of tankers, bulldozers and low loaders is crucial to DEC’s fire management and control capability. |
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0119 | 17 - Assets and technology | The development of a three year aerial firefighting strategy for W.A. would ensure optimal development of a joint air capability. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0126 | 9 - Community education | FESA promotes a whole-of-community approach, involving FESA, Local Governments and the community, in fire prevention functions, activities and planning. |
REC182-0134 | 17 - Assets and technology | FESA reviews its air reconnaissance capability and determines if multiple multi-sensor air reconnaissance aircraft or unmanned aerial vehicles are required for managing concurrent and/or complex incidents. |
REC182-0125 | 15 - Inter-service cooperation | FESA, in partnership with other agencies and the community, develops Western Australia’s urban interface fire fighting capability and capacity. |
REC182-0132 | 9 - Community education | FESA implements an education and awareness campaign to promote the purpose and utility of community information systems. |
REC182-0124 | 15 - Inter-service cooperation | FESA and DEC take a whole of capability approach to joint operations, including developing joint doctrine that provides a common and articulated understanding of roles and responsibilities, resources and capabilities |
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
REC182-0129 | 15 - Inter-service cooperation | FESA maintains inter-agency relationships and arrangements, and develops formalised arrangements across the entire emergency management cycle for joint activities such as training, exercises and procedure development. |
REC182-0127 | 9 - Community education | FESA strengthens its planning process to ensure learnings are incorporated and communicated, levels of preparedness are linked to threat analyses and public awareness and education activities are sustained. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
REC173-0104 | 1 - Land-use and building regs | That FESA assess the cost and other implications of proposed changes to bushfire prone zone declarations which would allow the whole State to be declared bushfire prone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0029 | 17 - Assets and technology | Provide a photocopier in the Mobile Communications Facility or the mobile equipment cache that is capable of large volume production of collated documents. |
REC172-0019 | 17 - Assets and technology | A centralised, regional, multi-agency resource coordination and tracking system/facility be established to accommodate and coordinate the movement of resources from all agencies within and between regions. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0028 | 17 - Assets and technology | Ensure the S61 helicopter has all appropriate channels for water bombing operations throughout the State by including this requirement on a pre-deployment checklist. |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
REC172-0027 | 13 - Mapping and data quality | Add an ‘Aviation’ map to the standard set of incident maps. The standard for this map will need to be developed by subject matter experts from the Air Ops group. |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0026 | 17 - Assets and technology | At large incidents a communications bus should be provided for the use by Air Ops and a designated work space should be provided for the Air Ops management group. |
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0025 | 17 - Assets and technology | Suppression resources should be ordered and mobilised as 2 truck Strike Teams with a STL and consistently deployed to the fire ground as a unit. |
REC172-0047 | 17 - Assets and technology | There is an established need to develop mobile accommodation and accommodation facility support solutions that allows an acceptable standard of accommodation to be provided to fire fighters in close proximity to the incident. |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0022 | 15 - Inter-service cooperation | The declaration of a potential Level 3 incident should be notified to FESA who can facilitate an early warning to CFCO’s in the Shire and surrounding LGA’s. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0069 | 17 - Assets and technology | That in any consideration being given to the allocation of responsibility for control of operations in respect of major fires, consideration be given to the availability of technology and other resources, particularly when particular skills are required to make best use of such technology or resources. |
REC171-0067 | 14 - Incident Mgt Teams | That to the extent it has not already done so, DEC take action to ensure that in future cases relevant weather forecast information, particularly information as to significant wind changes, is promptly transmitted through the Incident Management Team and made available to persons with field operation responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0059 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure all agencies use the same approach to managing incidents. |
REC170-0058 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure that all agencies can access other agencies’ operations centres when needed and that the procedures to do so are documented |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3395 | 15 - Inter-service cooperation | The Committee recommends that the ACT Emergency Services and the Rural Fire Service in particular institute regular meetings with the NSW Rural Fire Service and other appropriate authorities, such as environment |
REC144-3393 | 1 - Land-use and building regs | The Committee recommends that the responsibility for land management issues lie within a single portfolio, specifically the Minister for Territory and Municipal Services. |
REC144-3399 | 9 - Community education | The Committee recommends that the Emergency Services Agency post all its publications, which are not internal working documents or otherwise confidential, on its website. |
REC144-3385 | 41 - Emergency Management exercises | The Committee recommends that the ESA hold discussions with NSW with a view to developing a joint exercise program with the NSW Rural Fire Service on an ongoing basis. |
REC144-3398 | 9 - Community education | The Committee recommends that the Emergency Services Agency update its website to accommodate, at a minimum, a publications menu item and a search function. |
REC144-3384 | 41 - Emergency Management exercises | The Committee recommends that the ESA develop a schedule of proposed exercises as a five year rolling plan, in order that all the elements of emergency services are able to be tested over that time and in differing |
REC144-3397 | 9 - Community education | The Committee recommends that the ACT Government investigate the Victorian Community Fireguard model with a view to implementing a similar scheme in the ACT to enhance community preparedness for and ability to respond to bushfire emergencies. |
REC144-3396 | 9 - Community education | The Committee recommends that information in relation to proposed fuel load activity and controlled burning should be disseminated to the community and in an accessible format. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3580 | 17 - Assets and technology | That FESA investigate the use of new technologies such as Voice over Internet Protocol (VoIP) for supplementing the dissemination of WANDRA information in cases where landlines have been disrupted. |
REC143-3579 | 9 - Community education | That FESA develop comprehensive internet-based information including but not limited to detail of WANDRA objectives, assistance measures, administering agencies, eligibility criteria (where applicable) and application forms. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1981 | 15 - Inter-service cooperation | That senior officers in the Australian Federal Police and the Emergency Services Agency maintain regular and meaningful contact during fire emergencies, to ensure full dissemination of information and thus facilitate the making of good operational decisions |
REC126-1954 | 15 - Inter-service cooperation | That senior officers of the Emergency Services Agency give greater recognition to the skills, knowledge and experience of people from other agencies – particularly the land management agencies – as well as rural residents and private individuals and use these people in roles commensurate with their skills and experience |
REC126-1992 | 9 - Community education | That implementation of the Bushfire Wise Program continue and include a letterbox drop of the updated Bushfire Information Booklet |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |
REC126-2001 | 9 - Community education | That community education programs provide information about fire behaviour, urban design principles that contribute to a specific level of risk, and the benefits of fitting basic ember protection materials in areas at risk from bushfire |
REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-1953 | 14 - Incident Mgt Teams | That appointments of personnel to functional positions within the incident management team be based solely on competence and experience and be made by the Chief of the ACT Rural Fire Service or, in the absence of that officer, the Deputy Chief of the ACT Rural Fire Service |
REC126-1991 | 9 - Community education | That the Emergency Services Agency establish annual targets for the introduction of community education programs and provide resources to conduct regular independent assessments of the level of community preparedness engendered as a result of the programs |
REC126-1967 | 40 - Equipment and consumables | That the Emergency Services Agency give priority to ensuring it has guaranteed access to an adequate number and type of bulldozers, as well as experienced operators, during the fire season, for immediate deployment as required |
REC126-2000 | 1 - Land-use and building regs | That the ACT Government consider taking measures to implement the provisions of Australian Standard 3959, Construction of Buildings in Bushfire Prone Areas, for the ACT urban area |
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
REC126-1990 | 9 - Community education | That the Emergency Services Agency take measures to ensure that the community regularly receives up-to-date information on the risks of bushfires |
REC126-1960 | 13 - Mapping and data quality | That an appropriate geographic information systems capability be maintained to enable the production of fire-specific maps as the need arises and that personnel from the Emergency Services Agency and other agencies be trained in the operation of map production systems, so that 9maps can be modified to include fire-specific information as required |
REC126-1999 | 9 - Community education | That the Canberra Urban Development Working Group referred to in Mr Peter Dunn's letter consider the report prepared by Mr Leonard and note particularly that the community awareness information currently available to householders in connection with measures they can take to better protect their homes from bushfires does not refer to the potential of wooden fences, conifers and outbuildings to contribute greatly to fire spread, particularly in suburban areas. Also noteworthy is Mr Leonard's evidence that the linear sitting of homes on house blocks in Canberra seems to be an important factor contributing to house-to-house fire spread and that this should be avoided in future developments on the urban fringe |
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
REC126-2005 | 9 - Community education | That community education programs include unambiguous information that at times of unusually high water demand there might be a drop in or loss of water pressure and it might be appropriate for residents who intend to remain and fight a fire to have auxilary water pumps or booster pumps |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1959 | 13 - Mapping and data quality | That the Emergency Services Agency introduce a program with land management agencies in the ACT to ensure that maps of all public and private land in the ACT are subjected to regular review and amendment as required. Maps of a scale sufficient to facilitate fire management operations should be available in printed form and maintained on an electronic database capable of modification to add relevant features during a firefighting operation |
REC126-1996 | 9 - Community education | That the Emergency Services Agency develop a clear policy for disseminating information to the public and the media in times of emergency and that, as required, that policy incorporate advance door-knocking of homes in the area affected, as well as regular broadcasts by local radio and television stations and regular updates on the relevant website - be that Canberra Connect or a different ACT government website - as well as the Emergency Services Agency's website |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
REC126-2003 | 9 - Community education | That the community be made aware of the risk presented by heavy loads of garden fuels and certain types of vegetation around their houses and take active, regular measures to reduce that risk |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1956 | 15 - Inter-service cooperation | That courses and programs be conducted to increase the level of Incident Control System training and augment the expertise of people who are likely to perform functions in an incident management team |
REC126-1993 | 9 - Community education | That consulations and negotiations occur between the Emergncy Services Agency and the NSW Rural Fire Service to ensure that fire risk and safety messages to the community are coordinated. Maximum use should be made of television and radio announcements throughout the ACT and southern NSW, consistent with NSW timetables for targeted programs in conjunction with the United Firefighters Union ACT Branch and volunteer fire brigade representative. The Emergency Services Agency should consider using ACT Fire Brigade staff and ACT Rural Fire Service volunteers to talk to groups in the community on request, thus furthering face-to-face community education in high-risk suburban areas of the ACT |
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-2002 | 1 - Land-use and building regs | That consideration be given when building to the positioning of outbuildings around residential structures such that their potential impact on the main structure is reduced |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
REC113-3902 | 14 - Incident Mgt Teams | Government should: establish a State-wide command structure across volunteer Bush Fire Brigades for fighting major bushfires, to more effectively manage the coordination of personnel and resources |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
REC019-4133 | 9 - Community education | The Bush Fires Board take a more active part in enlightening the public generally and the local communities in particular to their responsibilites on fire control. |
REC019-4151 | 26 - Research | The Forests Department carry out more research into both the technical and practical side of fire control as a necessary accompaniment to the expenditure of money on other forest works and that forest fire control officers be sent overseas at intervals to gain information regarding the latest developments in this work. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4156 | 26 - Research | A fire control research advisory committee be formed to co-operate with the Forests Department in carrying out scientific research into fire control. |
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4153 | 17 - Assets and technology | No opportunity be lost by the Forests Department to improve the efficiency of their fire fighting gangs, radio and other equipment in the light of the latest practical and scientific developments. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |