Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that currently use pre-formatted messages within the Emergency Alert system review and, where necessary, redraft messages using the principles of Clear Explicit Translatable Language (CETL). |
REC325-4336 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services, in consultation with the Queensland Police Service, incorporate into the workflow of the current Emergency Alert system a process that ensures the inclusion of an ‘urgent approval and distribution without delay’ process for Emergency Alert messages by 1 November 2022. |
REC325-4323 | 7 - Inter-agency communication | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services adopt measures to achieve a common operating picture between deployed Queensland Fire and Emergency Services assets in disaster management operations by 1 November 2023. |
REC325-4337 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an urgent multi-agency (including but not limited to the Queensland Police Service and Brisbane City Council) review of the workflow, of the current Emergency Alert system, including requesting, composing, authorising and issuing of Emergency Alerts by 1 November 2022. |
REC325-4329 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services implement the Australian Warning System for all nationally agreed hazards by 1 November 2023. Implementation should include guidance and training to all local governments and agencies operationally involved in disaster management, with emphasis on those agencies with hazard specific responsibility. |
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that do not have pre-formatted messages and polygons engage with Queensland Fire and Emergency Services and determine whether their local disaster management group capability could be improved through the development of pre-formatted polygons and messages. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4250 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the Locality Specific Fire Management Group for K’gari meet at least twice per year, in person or virtually. |
REC322-4232 | 11 - Evacuation and shelters | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to plan for the evacuation of K’gari due to bushfire. Once developed, the plan should be exercised and regularly reviewed. |
REC322-4225 | 8 - Communications and warnings | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to prepare and exercise a communications sub-plan with all responsible agencies, to clarify the roles, responsibilities and communication channels used for restricting access to K’gari. |
REC322-4251 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services facilitate an annual state level exercise of the Queensland Bushfire Plan that includes all relevant stakeholders and land managers. The exercise should focus on roles, responsibilities, interagency arrangements and handover arrangements between agencies and land managers. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
REC322-4227 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the membership of the K’gari Locality Specific Fire Management Group be expanded to include representatives of the Butchulla people, community associations from each township and tourism and business operators with interests on the island. |
REC322-4242 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends the Department of Environment and Science review the format and delivery of Queensland Parks and Wildlife Service annual fire refresher training to include a scenario-based exercise. |
REC322-4228 | 8 - Communications and warnings | The Inspector-General Emergency Management recommends a public information resource be developed by Queensland Fire and Emergency Services to inform the community and stakeholders about aerial assets utilised in bushfire response. |
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4230 | 34 - Local knowledge | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services engages with land managers and other stakeholders on K’gari to source data to inform Predictive Services products. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
REC322-4231 | 8 - Communications and warnings | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services examines the use of predictive service capability to inform prevention and preparedness in addition to response activities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2481 | 22 - Role of local Gvt | Greater clarity about responsibilities for recovery at the community, local, and district levels should be considered in any future review of the Disaster Management Act (2003). |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2475 | 15 - Inter-service cooperation | Greater emphasis be placed on pre-planned and pre-determined arrangements between the Australian Defence Force and State and local agencies. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2469 | 12 - EM agency and authority | Entities with disaster management responsibilities need to integrate the eight priorities identified within the Emergency Management Sector Adaptation Plan for Climate Change into their disaster management planning cycle. |
REC309-2479 | 34 - Local knowledge | Local groups should plan for and establish clear arrangements to effectively manage offers of assistance including the management of goods, services and volunteers. |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
REC308-2457 | 8 - Communications and warnings | Efforts are made to improve the timeliness, accuracy and targeting of Emergency Alert messaging by: |
REC308-2456 | 22 - Role of local Gvt | A Local Government Association of Queensland representative should be included on the Crisis Communications Network to enhance the delivery of consistent information across and between levels of government. |
REC308-2466 | 41 - Emergency Management exercises | Exercising should focus on vertical integration and include all levels of the system. A strategic program of exercises should be developed and implemented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
REC307-2444 | 41 - Emergency Management exercises | All disaster management groups should run an exercise that has full involvement of a hazard-specific primary agency in the next 12 months and regularly thereafter. |
REC307-2440 | 8 - Communications and warnings | Communications protocols about hazard-specific events should be developed to clarify responsibilities and the principles for the release of information and warnings. They should be included in all related hazard-specific plans and published on relevant websites, and used during events. |
REC307-2438 | 8 - Communications and warnings | The national messages for catastrophic fire danger ratings should be integrated with all existing and new community bushfire safety information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
REC272-1418 | 12 - EM agency and authority | Queensland Fire and Emergency Services should consider examining regulatory provisions to improve disaster management and business continuity planning for aged care providers. |
REC272-1414 | 12 - EM agency and authority | Queensland Fire and Emergency Services coordinate the development of an integrated risk based approach to disaster management planning for Queensland that is consistent with the Standard and applicable at all levels of the arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1533 | 14 - Incident Mgt Teams | State Disaster Coordination Centre considers requesting a representative from critical infrastructure owners be present as a liaison officer in the State Disaster Coordination Centre during activations for events that may impact on their assets. |
REC271-1529 | 8 - Communications and warnings | As part of the above, both the Banana Shire Council and SunWater ensure Emergency Alert messages are pre-formatted, consistent, polygons are identified according to risk, and that they are tested and practiced with the State Disaster Coordination Centre. |
REC271-1528 | 8 - Communications and warnings | Prior to September 2015, SunWater and the Banana Shire Council jointly develop a multi-channel, common warning strategy, including common language and consistent messaging, for residents downstream of |
REC271-1527 | 8 - Communications and warnings | Prior to September 2015, the Banana Shire Council develops a multi-channel warning strategy and associated public information campaign, including common language and consistent messaging, for the Banana Shire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC270-1146 | 12 - EM agency and authority | Strengthens its oversight role as lead agency for mitigating Queensland's bushfire risk to acceptable levels by: · coordinating land managers' efforts to assess and mitigate bushfire risk · formalising the role of fire management groups to manage Queensland's fuel loads, including reporting planned and conducted hazard reduction burns and the effectiveness of hazard reduction burns · amending its bushfire mitigation planning to address prevention, preparedness, response and recovery and to manage Queensland's residual bushfire risk · developing and implementing a coordinated strategy to address arson, deterring would-be offenders and rehabilitating convicted offenders · working with local councils to develop and communicate local bushfire plans for communities located in high risk, bushfire-prone areas |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1423 | 22 - Role of local Gvt | The State Disaster Coordination Centre Notification Matrix is reviewed to ensure local governments are notified of any event affecting, or likely to affect, their local government area. |
REC268-1431 | 8 - Communications and warnings | Queensland Fire and Emergency Services should consider new and emerging technologies for issuing warnings (including opportunities for Emergency Alert to be distributed in other languages or to people with vision or hearing impairment). |
REC268-1429 | 2 - Emergency powers | A dynamic online list of positions and contact details is published for those able to authorise Emergency Alert, and made accessible to local government. |
REC268-1427 | 8 - Communications and warnings | The Warning and Alert Systems training package is updated to align the content to the Standard for Disaster Management in Queensland and to include advice and scenarios from the Information Commissioner. |
REC268-1426 | 8 - Communications and warnings | A qualitative assessment of public information and warnings arrangements is undertaken as part of the 2016 disaster management plan assessment process. |
REC268-1425 | 8 - Communications and warnings | The Public Information and Warnings Sub-plan Guide is reviewed to include: |
REC268-1433 | 8 - Communications and warnings | Queensland Fire and Emergency Services should consider supporting local government in the annual development of at least one pre-formatted Emergency Alert message and polygon map based on a risk assessment and hazard modelling. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0958 | 12 - EM agency and authority | That the Rural Operations division currently sitting within the Queensland Fire and Rescue Service become an autonomous unit called Rural Fire Service Queensland and be led by a Deputy Chief Officer. Structure and Leadership of the Rural Fire Service |
REC241-1004 | 15 - Inter-service cooperation | That a memorandum of understanding be developed between RFSQ and other organisations with fire fighting capacity at state level, to establish operational procedures when these organisations may be required for a joint response roles. Specifically, the intent will be: Vegetation Fire in a Rural Area: The Rural Fire Brigade in that area (boundary) is in charge and is the first Brigade called by Firecom. Structural Fire in a Rural Area: Firecom calls the Urban Brigade first and they control the incident. Local Rural Fire Brigade must also be notified by Firecom at the same time. Vegetation Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. At their discretion they may call Rural Fire Brigades for assistance. Structural Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. |
REC241-0963 | 12 - EM agency and authority | That there be three (3) RFSQ regions in Queensland - North, Central and South-East. |
REC241-1010 | 12 - EM agency and authority | That where a Brigade supports another community and this involves the use of any brigade equipment it shall be the decision of that brigade in relation to the deployment and use of their equipment and resources. |
REC241-1037 | 12 - EM agency and authority | That Rural Fire Service Queensland and its staff be exempt from the Travel Management System. The Travel Management System does not work in the rural fire operation areas as it is not flexible in the rapid escalation of wild fire events or cater for volunteering timeframes. It has been proven to be inefficient and costly. |
REC241-0986 | 12 - EM agency and authority | That the founding principle of the Rural Fire Service, that Brigades are formed on the principle of neighbour helping neighbour to collectively manage fire events, remains on of the foundation of Rural Fire Service Queensland. |
REC241-0957 | 12 - EM agency and authority | That a strong emphasis be placed on the establishment and recruitment of PCYC emergency cadets. |
REC241-0993 | 12 - EM agency and authority | That wherever possible, for future appointments of Fire Wardens, where that Wardens’ district is totally covered a by Rural Fire Brigade, consideration should be given that the appointed Fire Warden is a Rural Brigade Member. |
REC241-0962 | 12 - EM agency and authority | That Rural Fire Service Queensland consider service delivery needs with a view to establishing boundary/ staff/budget changes according to State standards. |
REC241-1008 | 12 - EM agency and authority | That the colour of Rural Fire Service Queensland Brigade operational vehicles remain yellow and that they retain the Rural Fire Service Queensland logo. |
REC241-1021 | 12 - EM agency and authority | That Brigades that do not have a truck and are currently classified as Rural conduct a self-determination to ascertain if they wish to be reclassified as a Primary Producer Brigade. |
REC241-0975 | 12 - EM agency and authority | That employee selection panels for field staff positions only comprise three members and include a Rural Fire Service Queensland representative, a Rural Fire Brigades Association of Queensland representative and one representative from the District Fire Management Group. |
REC241-0953 | 12 - EM agency and authority | That a separate area of responsibility be established to provide independent oversight and monitor disaster readiness across all hazards. |
REC241-0990 | 12 - EM agency and authority | Membership of the District Fire Management Group is at the discretion of the Chair of the District Fire Management Group, however members must have the necessary expertise and experience for the role and membership should include where applicable, the District Inspector - Rural Fire Service Queensland, a representative of relevant local governments and representatives of agencies responsible for parks and wildlife, transport and main roads, forestry and natural resources among other appropriate representatives. |
REC241-0961 | 12 - EM agency and authority | That staffing at Rural Fire Service Queensland District offices remain at current levels within establishment and, if needed, base staffing levels be increased. |
REC241-1007 | 12 - EM agency and authority | That the Rural Fire Service Queensland consider a less formal uniform which volunteers can better identify with, and that National rank markings be retained. |
REC241-0972 | 12 - EM agency and authority | That Rural Fire Service Queensland designate a position of Lands Procurement Officer to support volunteers by project managing the acquisition of land for Brigade sheds and their construction where required. |
REC241-1020 | 12 - EM agency and authority | That members of Village and Izone classified Brigades only be required to conduct a criminal history check when they first join a Brigade. Criminal history checks will no longer be required when a Member who has already undergone a criminal history check takes an office bearing role within a Brigade or changes Brigades. Criminal history checks are to still be conducted on Rural Fire Service volunteers undertaking interstate deployments. Members of other voluntary organisations in Queensland (e.g. State Emergency Service, Volunteer Marine Rescue) who wish to join the Rural Fire Service Queensland will not be required to undertake an additional criminal history check with an internal check to be conducted by the Department of Community Safety. |
REC241-0952 | 12 - EM agency and authority | That an operational organisation be established comprising of three streams – a. urban fire service; b. rural fire service; and c. the state emergency service. Each of the three organisations will be led by a Deputy Chief Officer, reporting to a Chief Officer. |
REC241-0989 | 12 - EM agency and authority | That the first tier comprise at least one District Fire Management Group in each Rural Fire Service Queensland District. The District Fire Management Group will be chaired by a person with the necessary expertise and experience, nominated by the community and appointed by Government. Chairs will hold the deciding vote in matters related to fire management at the local level. |
REC241-0960 | 12 - EM agency and authority | That Rural Fire Service Queensland District offices remain at least at their current number of 14, with consideration given by the Rural Fire Service Queensland to expanding the number of District offices by opening an office in the South Burnett, considering a new office in the southern Central Highlands, and the option of part time offices on a risk/need/growth basis, particularly in north-west Queensland. |
REC241-1006 | 12 - EM agency and authority | That Brigades’ financial contributions to groups must be voluntary and approved by a recorded minute at a meeting of that brigade. |
REC241-0966 | 12 - EM agency and authority | That District offices be located in areas that enhance ease of access for out of town volunteers and the general public and also provide suitable parking, onsite storage and be suitable for operational use. |
REC241-1019 | 12 - EM agency and authority | That a local committee consisting of Elders and community leaders be formed in remote and Indigenous communities to determine Brigade membership applications. |
REC241-0988 | 12 - EM agency and authority | That the planning system is to have a two tiered structure comprising District Fire Management Groups and linking to the State Disaster Management Group. |
REC241-0959 | 12 - EM agency and authority | That Rural Fire Service Queensland District offices report directly to the Deputy Chief Officer. |
REC241-1005 | 12 - EM agency and authority | That fire groups can only be formed through the agreement of all brigades that will become a part of that group, and the management and operational procedures of the group must be approved by the contributing brigades. Local District Inspectors are to provide mentoring and support when brigades form a group. |
REC241-0964 | 12 - EM agency and authority | That the position of Regional Manager Rural Operations be re-designated to Regional Co-ordinator in the North, Central and South-East regions to emphasise the supporting role the position will take. |
REC241-1014 | 12 - EM agency and authority | That the Rural Fire Service Queensland should engage a private provider offsite and outside the Government firewall to establish an email address for each Brigade and Fire Warden. The email address would reflect the Brigade name and Fire Warden district. E.g.: GreenbankRFB@msn.com.au |
REC241-1038 | 12 - EM agency and authority | That District Inspectors retain the discretion to allocate gratuity to Fire Wardens for out of pocket expenses if required. |
REC241-0987 | 12 - EM agency and authority | That to assist the Rural Fire Service Queensland and other agencies in managing wildfire risk, a planning system for wildfire management be established in legislation that complements the existing disaster management arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2690 | 8 - Communications and warnings | That the Chief Executive Officer Portfolio Business and Commissioners establish a high level working group with the ABC and commercial media to identify and implement an improved information flow to the community on disasters. |
REC239-2733 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service reduce the number of communication centres to two, with one being a primary site and the other site providing redundancy and business continuity functionality. |
REC239-2765 | 12 - EM agency and authority | That the Chief Executive Officer Portfolio Business promote innovation and drive cultural change in terms of business practice. |
REC239-2658 | 12 - EM agency and authority | That the Queensland Ambulance Service maintains its own identity to: |
REC239-2707 | 12 - EM agency and authority | That the Inspector General Emergency Management ensures that improvement strategies identified are acted upon and improvement strategies embedded within agencies as standard practice. |
REC239-2745 | 12 - EM agency and authority | That the Emergency Service Cadet Program take a full spectrum approach to emergency services |
REC239-2670 | 12 - EM agency and authority | That prisoner transport and non-managerial roles within watch-houses should be a priority for contestability. |
REC239-2719 | 12 - EM agency and authority | That the current Queensland Fire and Rescue Service model of functional management be expanded, shifting line management responsibility for community safety operations and professional development from Regional Assistant Commissioners to the State Commanders. Regional Assistant Commissioners become responsible for operations and coordination of departmental support within geographic locations and report to the Deputy Commissioner operations. |
REC239-2752 | 20 - Role of police | That the roll-out of the Queensland Police Service digital technology should take into consideration adopting and facilitating new processes including the police response to domestic violence. |
REC239-2689 | 20 - Role of police | That, where appropriate, the Commissioner of Police appoints appropriately trained and experienced public service officers to appropriate roles in the disaster management system to support District Disaster Coordinators in their vital roles. |
REC239-2731 | 12 - EM agency and authority | That the CEO Portfolio Business and the Commissioner Queensland Fire and Rescue Service find a more appropriate method of accounting for part time and volunteer staff when considering the support required to raise, train and sustain this very large part of the workforce. |
REC239-2762 | 15 - Inter-service cooperation | That the Chief Executive Officer Portfolio Business in consultation with the Police Commissioner and the Commissioner Fire & Emergency Services should provide the direction for future information and communication technology strategies and acquisitions. |
REC239-2656 | 12 - EM agency and authority | That the Queensland Ambulance Service is maintained as a state-wide service into the future. |
REC239-2706 | 12 - EM agency and authority | The establishment, management, support and education of the State Emergency Service (SES) become the responsibility of a Deputy Commissioner, Fire and Emergency Services and this person should also be responsible for Rural Fire Service Queensland. |
REC239-2744 | 12 - EM agency and authority | That the revitalised PCYC Emergency Service Cadet Program continue to be supported by government. |
REC239-2669 | 12 - EM agency and authority | That specific business cases should be developed for contestability of correctional services in Queensland, including: |
REC239-2716 | 12 - EM agency and authority | That the remainder of the current Emergency Management structure transition to the Commissioner, Fire and Emergency Services for further consideration regarding the most appropriate reporting alignment giving due consideration to existing capacity. This should be done in consultation with the Commissioner, the Queensland Police Service to ensure proper collaboration with the Queensland Police Service Disaster Management Unit staff. |
REC239-2751 | 12 - EM agency and authority | That collaboration on new initiatives such as the co-responder model in Cairns continue and if successful, initiatives should be considered for state wide or service wide adoption. |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2730 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service actively progress initiatives for flexible employment including: |
REC239-2761 | 15 - Inter-service cooperation | That systems development in the Queensland Police Service capitalises on the advances made by the Queensland Fire and Rescue Service in recent years. |
REC239-2703 | 15 - Inter-service cooperation | That the protocols developed by the Queensland Police Service and SES for operations define the respective roles and responsibilities as well as recognise the varying capabilities of SES units across the State. |
REC239-2743 | 12 - EM agency and authority | That where practicable, the consideration for new or enhanced facilities include an assessment of the viability of creating a Rural Fire Service /SES common user facility. |
REC239-2667 | 15 - Inter-service cooperation | That Queensland Corrective Service, the Queensland Police Service and Queensland Health should work together to develop a position that enables prisoners to have timely access to their prescribed medication despite travel between facilities and without the need for costly re-prescription. |
REC239-2715 | 12 - EM agency and authority | That the Disaster Management Standards Branch element of Standards Improvement, transition to the Inspector General Emergency Management. |
REC239-2750 | 20 - Role of police | That the Queensland Police Service: |
REC239-2680 | 12 - EM agency and authority | That the fire service takes a broader view of its role as an emergency management organisation. |
REC239-2726 | 20 - Role of police | That the Queensland Fire and Rescue Service enters into discussion with the Queensland Police Service regarding the possibility for the Queensland Police Service to assist with prosecutions that may arise out of fire safety matters. |
REC239-2760 | 12 - EM agency and authority | That a suitably qualified Chief Information Officer with whole of portfolio responsibility is appointed to oversight corporate support and capability development |
REC239-2698 | 12 - EM agency and authority | That the Deputy Commissioner, Operations (of the proposed new Department of Fire and Emergency Services) should be responsible for ensuring the readiness of the disaster operations system, including the State Disaster Coordination Centre, enabling seamless transition to police control when required. |
REC239-2742 | 12 - EM agency and authority | That the recommendations of The Malone Review in relation to Criminal History checks, so far as supported, by the Review team in this report be progressed inclusive of SES issues. |
REC239-2781 | 34 - Local knowledge | That the current provisions enabling there to be a Ministerial Direction be maintained and actioned as the Minister sees fit. |
REC239-2665 | 12 - EM agency and authority | That planning, especially for infrastructure, must take into account the service delivery model (e.g. the fact that prisoners have high level health needs). |
REC239-2714 | 12 - EM agency and authority | That the following units of Emergency Management Queensland transition to the control of the position of Deputy Commissioner Rural Fire Service Queensland and State Emergency Services: |
REC239-2748 | 20 - Role of police | That the Queensland Police Service considers adopting the broader use of ANPR in line with other Australian jurisdictions in consultation with the Privacy Commissioner. |
REC239-2677 | 12 - EM agency and authority | That biometric tools be leveraged for other demands (e.g. bail reporting). |
REC239-2722 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service should introduce alternative means of response to automatic alarms such as small first response investigative crews e.g. two fire–fighters in a sedan (not responding under lights and siren). |
REC239-2757 | 20 - Role of police | That the Queensland Police Service executive team reassesses its preparedness to collaborate with other agencies to deliver a whole of Government approach to delivering community safety. |
REC239-2694 | 15 - Inter-service cooperation | That Queensland enters into a similar arrangement with Bureau of Meteorology to have an experienced forecaster seconded to Kedron State Disaster Coordination Centre for at least the duration of fire and storm seasons. |
REC239-2734 | 12 - EM agency and authority | That a new Deputy Commissioner position be created to manage volunteer emergency services including the Rural Fire Service and the State Emergency Service. |
REC239-2766 | 12 - EM agency and authority | Recommendation: |
REC239-2663 | 12 - EM agency and authority | That the Commissioner of Queensland Corrective Service report directly to the Director-General the Department of Justice and Attorney-General. |
REC239-2713 | 12 - EM agency and authority | That the following units of Emergency Management Queensland transition to the control of the Deputy Commissioner of Regional Operations (Department of Fire and Emergency Services): |
REC239-2747 | 20 - Role of police | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative automated number plate recognition models should form part of the design architecture. |
REC239-2672 | 12 - EM agency and authority | That Queensland Corrective Service conduct business analysis and planning to clearly identify its customers and its contribution to the Government’s priorities |
REC239-2720 | 12 - EM agency and authority | That a reduced regional model for fire and emergency services be generally aligned to that of the Queensland Police Service with a district structure that accords with disaster districts. |
REC239-2754 | 12 - EM agency and authority | That the Chief Executive Officer Portfolio Business should overhaul portfolio information and communication technology and appoint a Chief Information Officer with appropriate qualifications and significant industry experience as a first priority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0725 | 12 - EM agency and authority | The fire service should ensure that station officers are familiar with the procedure for contacting management when requesting the calling in of additional staff; and, in particular, that they have available to them the names and current telephone numbers of the officers to be contacted in the first instance, with alternative contact details in the event that those officers prove unavailable. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0731 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directives it develops in relation to these matters. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0730 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop clear directives about: • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the process for dealing with requests for assistance that exceed an SES unit’s capacity to respond them • the process for seeking extra support for an SES unit that has been overwhelmed by a disaster (whether by way of Emergency Management Queensland or the disaster management arrangements or both) • the role of SES liaison officers in communications with disaster managers about SES disaster operations • the role of incident controllers, and their teams, relative to those SES (or Emergency Management Queensland) personnel charged with the command of SES operations. |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0729 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directive when it is developed. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0728 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop a directive that makes clear the authority of an officer of that agency to command a major SES operation. This could be expected to occur when a deployment of additional SES members is made to a region because the response needed is beyond the capacity of its local units. The directive should make clear the powers of the officer and his or her reporting responsibilities to disaster managers in these circumstances. Emergency Management Queensland must also ensure that any officer who assumes such a role has adequate training and skills in the conduct of disaster operations. |
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0271 | 12 - EM agency and authority | that QFRS should establish a Rural Fire Service division within QFRS with the aim of integrating and strengthening the relationship between the urban and rural fire services. |
REC191-0270 | 12 - EM agency and authority | that QFRS implement procedures to ensure that rural fire brigades receive written confirmation of the Commissioner’s approval after office bearer elections in compliance with section 81 of the Fire and Rescue Service Act 1990. |
REC191-0269 | 12 - EM agency and authority | that QFRS implement procedures to provide a clear grievance process which is available to rural fire brigade volunteers. |
REC191-0264 | 12 - EM agency and authority | that QFRS update its website to include the Rural Fire Service as part of its www.fire.qld.gov.au web presence. |
REC191-0263 | 12 - EM agency and authority | that QFRS investigate and implement an internal email system for rural fire brigades. |
REC191-0272 | 12 - EM agency and authority | that QFRS establish the position of Assistant Commissioner, Rural Fire Service to lead the proposed Rural Fire Service division within QFRS. |
REC191-0262 | 12 - EM agency and authority | that QFRS include consultation with rural fire brigades as mandatory when boundary changes are proposed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0086 | 2 - Emergency powers | Suggested escalation trigger points be discussed with District Disaster Coordinators and Local Disaster Coordinators, and if considered practical and useful, be incorporated in Local, District and State Disaster Management Plans. |
REC165-0085 | 20 - Role of police | The Commissioner of Police, through a dedicated Assistant Commissioner (supported by a cohort of Assistant Commissioners to ensure adequate coverage), be assigned responsibility for overall control of each natural Disaster Management event in Queensland as the preferred arrangement. |
REC165-0096 | 15 - Inter-service cooperation | The Department of Community Safety and Councils develop MOUs to reflect the genuine partnership that exists in present arrangements including an emphasis on the use of the agreed State disaster arrangements to task and deploy SES units following State/Local consultation. |
REC165-0081 | 2 - Emergency powers | District and State levels utilise the current Act to make pre-emptive declarations of a disaster event (likely disasters) so as to be proactive in leading and controlling disaster events. All levels of the system should immediately notify other levels if they activate the Disaster Management arrangements. The Public Safety Preservation Act 1986 be amended to provide powers for Police Officers to provide an immediate response in the event of a rapid onset disaster event such as a landslide. |
REC165-0095 | 11 - Evacuation and shelters | Planning and consultation be undertaken by EMQ with all levels of the Disaster Management system to ensure that necessary risk-based disaster evacuation plans are prepared at Local, District and State levels, supported by necessary community education and preparedness programs. |
REC165-0090 | 7 - Inter-agency communication | The SDMG lead an initiative to integrate and/or inter-connect all of the control centres involved at all levels of the Disaster Management system in Queensland as part of the project to integrate State communications. |
REC165-0087 | 8 - Communications and warnings | The SDMG commission the Department of Community Safety and seek the necessary funding to develop and enhance the Statewide Disaster Management information and communications system building on alternatives already in place and in consultation with all levels of Government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3114 | 12 - EM agency and authority | QFRS implement a process to review brigade plans and incorporate specific issues identified into forward planning at the area and regional levels. |
REC150-3120 | 12 - EM agency and authority | QFRS provide assistance to brigades in determining and budgeting for their resource needs. |
REC150-3113 | 12 - EM agency and authority | QFRS provide guidance and support to rural fire brigades in the development of their one year operational plan and three year management plan. |
REC150-3119 | 12 - EM agency and authority | QFRS implement a system to collate and analyse brigade funding information. |
REC150-3112 | 12 - EM agency and authority | Queensland Fire and Rescue Service (QFRS) implement a forward planning process specific to rural fire management as part of the QFRS strategic planning process, which involves regional and area offices and incorporates: |
REC150-3118 | 12 - EM agency and authority | QFRS review the financial accountability and audit requirements of the rural fire brigades to reflect their status as part of QFRS. |
REC150-3124 | 12 - EM agency and authority | QFRS establish a suitable process to reliably capture that information. |
REC150-3117 | 12 - EM agency and authority | QFRS ensure compliance with the brigade accountability requirements for funding received by rural fire brigades as specified in the Rural Fire Brigade Manual |
REC150-3123 | 12 - EM agency and authority | QFRS determine the performance information needed to support effective decision making . |
REC150-3116 | 12 - EM agency and authority | QFRS implement a brigade issues management process to capture, manage and report specific brigade issues. |
REC150-3121 | 12 - EM agency and authority | QFRS utilise performance information on brigade activity as a factor in determining brigade resource and funding needs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3526 | 8 - Communications and warnings | That consideration be given to additional ways and means to improve broadcast capability into disaster-affected regions, particularly for the early aftermath of any disaster when a loss of power characterises the event. |
REC136-3528 | 8 - Communications and warnings | An early and high priority task in recovery from a natural disaster should be the development of a coordinated, succinct, practical and flexible public communications plan. |
REC136-3527 | 8 - Communications and warnings | In any future large-scale disaster or event, consideration be given to a centrally located Media Operations Centre. |