Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4208 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) develops financial reporting to monitor fuel management costs and estimate future costs. |
REC321-4207 | 25 - Inquiry, audit, lessons management and after action review | We recommend that DELWP reviews its target for the number of fuel hazard assessments conducted and ensures that this measure is evidence based, accurately reflects regional performance, and that the department monitors and reports on each region’s performance against it. |
REC321-4209 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) systemically documents and publicly reports reasons why it does not complete planned burns. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4194 | 8 - Communications and warnings | Public communications: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and / or the entity referred to in Recommendation 13, or otherwise responsible government department, work with councils and government to refine an operational relief and recovery public communications strategy that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4171 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the State review (and where necessary amend) legislation including but not limited to the Country Fire Authority Act 1958, Forest Act 1958 and Local Government Act 2020 to: |
REC318-4182 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in partnership with agencies engaged in state, regional and incident control centres: |
REC318-4177 | 38 - Agency/Department Reporting | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in conjunction with legislated fuel management organisations – develop a common set of objectives, metrics and reporting requirements for fuel management that form part of a compulsory regime that enables the Victorian Government to report publicly on a holistic fuel management program. The reporting requirements should: |
REC318-4181 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in collaboration with the emergency management sector and as part of the emergency management planning reforms: |
REC318-4178 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in collaboration with the Country Fire Authority and local government – undertake a review of the current residual risk target to ensure that it remains contemporary in terms of its designated percentage value. The review should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3271 | 8 - Communications and warnings | Better coordinate public information and warnings including evacuation plans and provide a single source of information about, the location and direction of fires, how and when to use Safer Places, Places of Last Resort, relief and recovery centres and directed evacuations. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2512 | 38 - Agency/Department Reporting | Documenting results and recommendations from disaster recovery tests. |
REC313-2508 | 25 - Inquiry, audit, lessons management and after action review | Regularly reviewing these plans to ensure that they reflect the current operating environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1344 | 25 - Inquiry, audit, lessons management and after action review | That a review of the cross‑tenure approach be undertaken to determine its effectiveness and to address issues that arise in fire prevention on private and public land. |
REC299-1343 | 25 - Inquiry, audit, lessons management and after action review | That the Government conduct a review of fire prevention |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1276 | 25 - Inquiry, audit, lessons management and after action review | That SA Health undertake a review of their emergency management arrangements. Health State Controllers should be consulted during this review and arrangements should be consistent throughout the department and across the State and compatible with State emergency management arrangements and information systems |
REC295-1328 | 25 - Inquiry, audit, lessons management and after action review | Update the SEMP Part 3, Annex F ‘Debriefs’ to provide more guidance regarding the types of debriefs, when they are required to be undertaken and at what level and guidance for undertaking and recording debriefs, and implementing lessons identified. |
REC295-1329 | 8 - Communications and warnings | Review and update Part 3, Annex C, of the SEMP ‘Public Information and Warnings’ to: a) clarify the role and responsibilities of the Public Information Functional Support Group and control agencies in relation to public information b) define requirements and processes for liaising with the community, including holding community meetings |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1327 | 25 - Inquiry, audit, lessons management and after action review | Establish a lessons management capability across the SA emergency management sector to collect, analyse and track lessons identified during debriefs and reviews following events and other sources such as interstate and oversees reviews and inquiries. |
REC295-1296 | 8 - Communications and warnings | That the SES in collaboration with MFS Communications Centre (Comcen) investigate and implement options to reduce the number of calls coming into the Comcen, (particularly on 132500). Options could include better utilisation of the available options on the Interactive Voice Recording and community education to increase community resilience. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1317 | 25 - Inquiry, audit, lessons management and after action review | Review representation in the State Emergency Centre including: a) determining if there is a more suitable functional support group e.g. the Procurement Functional Support Group, to replace the Logistics Functional Support Group, and if so, Chief Procurement Officer, DPC, has responsibility for the management of this role within the State Emergency Centre. b) That when the State Crisis Centre is not operating from a physical location, a State Crisis Centre liaison officer is attached to the State Emergency Centre. |
REC295-1315 | 25 - Inquiry, audit, lessons management and after action review | That a review of the role and effectiveness of the State Emergency Management Committee (SEMC) including: the legislative functions; membership including the chair; roles and responsibilities; and, SEMC Advisory Groups be undertaken. |
REC295-1297 | 25 - Inquiry, audit, lessons management and after action review | Engage an independent business analyst to review the current call, receipt and dispatch process for emergency services i.e. the Metropolitan Fire Service, Country Fire Service and State Emergency Service, from the initial call for assistance through to response of emergency service resources, including the allocation and coordination of multiple taskings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1140 | 8 - Communications and warnings | Review the current practise of issuing an ‘emergency alert’ telephone message or an emergency warning and/or watch and act alert to ensure that it is consistent, relevant and necessary. Prior to issuing an emergency alert message, consider state level involvement so that other agencies are made aware of message and intent. |
REC273-1134 | 8 - Communications and warnings | That future declarations be undertaken to ensure that the areas affected by the declaration are clear and concise. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1082 | 8 - Communications and warnings | The State review and revise its communication strategy, to: • needed for effective and rapid public communications during an emergency; and ensure all emergency response agencies have, or have access to, the capability and resources • ensure, where appropriate, that private operators of essential infrastructure are included in the coordination of public communications during an emergency concerning that infrastructure. |
REC264-1087 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • practice and ensures that, by taking a risk management approach, it is suitable for fire prevention, mitigation and suppression in all parts of the Hazelwood mine; and review its ‘Mine Fire Service Policy and Code of Practice’ so that it refects industry best • work plan for the Hazelwood mine. incorporate the revised ‘Mine Fire Service Policy and Code of Practice’ into the approved |
REC264-1086 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • consequences of fire in the worked out areas of the Hazelwood mine, and an assessment of the most effective fre protection for the exposed coal surfaces; conduct, assisted by an independent consultant, a risk assessment of the likelihood and • controls are in place to eliminate or reduce the risk of fre; and prepare an implementation plan that ensures the most effective and reasonably practicable • implement the plan |
REC264-1072 | 25 - Inquiry, audit, lessons management and after action review | The State empower and require the Auditor-General or another appropriate agency, to: • oversee the implementation of these recommendations and the commitments made by the State and GDF Suez during this Inquiry; and • report publicly every year for the next three years on the progress made in implementing recommendations and commitments. |
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
REC264-1089 | 8 - Communications and warnings | GDF Suez improve its crisis management communication strategy for the Hazelwood mine in line with international best practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
REC250-0792 | 8 - Communications and warnings | The Department of Human Services should develop an improved model for communication for future disasters that provides a single point of information and contact for disaster affected communities |
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2620 | 25 - Inquiry, audit, lessons management and after action review | Review employment conditions under the F&ES Act to align with those under the Public Sector Act unless there is a compelling reason to the contrary. |
REC244-2617 | 25 - Inquiry, audit, lessons management and after action review | When judging major incidents in the future, consideration be given to Eburn and Dover’s proposal to establish processes with a statutory basis that sufficiently balance the community’s interests in ensuring that true lessons, including lessons of error or neglect, are identified, whilst also protecting members of the emergency services. Processes need to be developed for emergency services such as those used in aviation and medicine, to facilitate open and honest disclosure of errors. |
REC244-2601 | 25 - Inquiry, audit, lessons management and after action review | That an independent review of the operational and geographic boundaries of the ESOs be conducted recognising the limitations of the current governance structures to adequately address such issues. Such a review needs to be performed periodically, but not less than every 8 years. |
REC244-2604 | 8 - Communications and warnings | Notification of a total fire ban should be broadcast to the public via any means reasonably available. Section 80, parts (2), (5) and (6) be amended so that broadcast fire ban warnings include, but not be limited to, radio stations, internet sites, social media outlets etc. |
REC244-2600 | 25 - Inquiry, audit, lessons management and after action review | An external audit of shared services performed by SAFECOM and services now provided by the three ESOs which have the potential to be shared, be undertaken to determine the most efficient and cost effective way such services can be delivered to the sector. The three ESO Chiefs need to have input into this process. |
REC244-2631 | 25 - Inquiry, audit, lessons management and after action review | Review Section 134 to ensure that it is not a deterrent to a group of farm fire units operating at an incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2647 | 8 - Communications and warnings | That Government agencies work closely with the Bureau of Meteorology and radio stations that broadcast emergency service announcements, to ensure the earliest possible determination of, and communications about, dangerous bushfire conditions. |
REC242-2643 | 25 - Inquiry, audit, lessons management and after action review | That the Government consult broadly upon and review impediments to volunteering in the community and establish a taskforce to assist in removing barriers to volunteering, particularly with respect to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1628 | 8 - Communications and warnings | The Emergency Services Agency should develop and test administrative procedures for the communications systems used for the distribution of public warning and emergency alerts. |
REC228-1620 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the Territory and Municipal Services Directorate, should review the Farm FireWise Program, including: |
REC228-1615 | 38 - Agency/Department Reporting | The Territory and Municipal Services Directorate, as part of its Bushfire Operations Plan monitoring and reporting, should assess and publicly report on cumulative progress against broader outcomes identified in the Regional Fire Management Plans and the Strategic Bushfire Management Plan. |
REC228-1614 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the ACT Bushfire Council, should conduct a review of the ACT Bushfire Council against its recently developed terms of reference (July 2013) within two years. |
REC228-1609 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency should undertake audits to meet the requirements in the Strategic Bushfire Management Plan for the preparation, sharing and publication of annual progress reports. Annual progress reports should be made available to the ACT Bushfire Council. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2869 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: developing tools and workflows to quickly and reliably transform technical data into intelligence that can be used to construct messages for community information that are timely, relevant, tailored and effective. |
REC216-2870 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: streamlining the authorisation processes for urgent warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1873 | 8 - Communications and warnings | Fire services can improve outcomes by implementing standard procedures that ensure the welfare and safety of crews and the public are not compromised |
REC215-1879 | 25 - Inquiry, audit, lessons management and after action review | Regulators can help to achieve improved outcomes by auditing compliance with the BPEM guidelines on a regular basis |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0433 | 8 - Communications and warnings | the state develop and implement standards for Emergency Alert to ensure consistent use, training and application by accredited operators within agencies across ‘all hazards’. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0438 | 8 - Communications and warnings | the state investigate the ability to refine the Flood and Storm Information Line to enable it to receive as well as provide information. |
REC199-0432 | 8 - Communications and warnings | the state develop and implement a single web portal as a means of providing emergency information to communities and local government on an ‘all hazards’ basis, including the information referred to in recommendations 74, 89 and 92. |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0437 | 8 - Communications and warnings | the state engage with local government to ensure emergency services’ public information and warnings reflect the community demographic. |
REC199-0402 | 8 - Communications and warnings | the state develop a flood warning system for each basin and location with community input and make relevant documents publicly available. Each warning system should include key performance indicators. |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0436 | 8 - Communications and warnings | the state develop a standard approach to the provision of emergency warnings and information in formats – spoken and written – that recognise diverse community needs, including language and disability |
REC199-0471 | 8 - Communications and warnings | the state and the commonwealth, during a flood event, make information available on providers who have capacity to accommodate patients and residents who require evacuation. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0435 | 8 - Communications and warnings | the state put in place appropriate measures to inform the community of the intended purpose of the Emergency Alert warning system. |
REC199-0440 | 8 - Communications and warnings | the state actively pursue the use of social media as part of its emergency warning and public information system. |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0434 | 8 - Communications and warnings | the state require that agencies operate in compliance with the guidelines of the Victorian Warning Protocol to ensure efficacy of warning messages. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0439 | 8 - Communications and warnings | the state review its Memoranda of Understanding with official emergency broadcasters to take account of increased usage of internet based information, including social media and the ability to broadcast community meetings |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1733 | 25 - Inquiry, audit, lessons management and after action review | That a review of the Country Fire Authority Act 1958 and the Country Fire Authority Regulations 2004 be undertaken. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0236 | 8 - Communications and warnings | Review the use of the terms in the templates e.g. ‘out of control’ so that community misconceptions are minimised. |
REC196-0242 | 8 - Communications and warnings | Integrate social media into the OSOM system. |
REC196-0231 | 8 - Communications and warnings | Allow the MFB and SES access to using OSOM. |
REC196-0241 | 8 - Communications and warnings | Review OSOM to enable monitoring or tracking of where messages were sent, who they were sent to and when they are due for review. |
REC196-0246 | 8 - Communications and warnings | Review the suite of community bushfire warning systems available to tourists across the State. |
REC196-0229 | 8 - Communications and warnings | Amend SOP J4.01and other strategic and procedural documents to reflect the goal of ‘timely, relevant and tailored’ for community bushfire warnings. |
REC196-0240 | 8 - Communications and warnings | Improve links and interactions between the communication systems e.g. customise OSOM messages to each of the communication mechanisms, link OSOM with Emergency Alert. |
REC196-0245 | 8 - Communications and warnings | Develop a robust evaluation framework to review community bushfire warning policies, processes, systems and procedures both internally and with communities at regular intervals and immediately after a major bushfire event. |
REC196-0239 | 8 - Communications and warnings | Review Emergency Alert and OSOM systems to improve ease of use. |
REC196-0244 | 8 - Communications and warnings | Educate and engage with fire-affected landholders about the types of warnings, what they might expect from the warnings and their responsibility for response to prevent loss of life. |
REC196-0237 | 8 - Communications and warnings | Ensure that warning terminology used in the templates and FireWeb is consistent. |
REC196-0243 | 8 - Communications and warnings | Review the potential use of ‘crowdsourcing’ sites such as Bushfire Connect in community bushfire warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0325 | 8 - Communications and warnings | The Fire Services evaluate the new information and warning systems to identify ways to integrate them and improve their capacity to issue timely, relevant and tailored messages. This should include the use of social media. |
REC195-0324 | 8 - Communications and warnings | The Fire Services, in consultation with media outlets, develop a more effective strategy for informing the community of Total Fire Ban days. |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0331 | 8 - Communications and warnings | The Fire Services ensure information and warning projects are able to be integrated with a common operating platform. |
REC195-0328 | 8 - Communications and warnings | The Fire Services ensure that information and warnings are developed in accordance with the Victorian Warning Protocol |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0217 | 25 - Inquiry, audit, lessons management and after action review | The State consider the development of legislation for the conduct of inquiries in Victoria —in particular, the conduct of royal commissions. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0216 | 25 - Inquiry, audit, lessons management and after action review | The State appoint an independent monitor or the Victorian Auditor-General to assess progress with implementing the Commission’s recommendations and report to the Parliament and the people of Victoria by 31 July 2012. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2981 | 8 - Communications and warnings | The Department of Human Services should complete work on emergency communication and information management issues. |
REC179-2977 | 38 - Agency/Department Reporting | The Department of Human Services should create evaluation guidelines for recovery operations, including links to planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC169-2998 | 38 - Agency/Department Reporting | Reports on the training exercises should be retained in an appropriately secured central repository so that consolidated results of the exercises can be drawn together effectively. |
REC169-2997 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet and Victoria Police, in consultation with departments, should standardise reporting on training exercises conducted under Part 6 of the Act and the CIP framework to promote greater consistency and to enable better identification of lessons learned and continuous improvement. |
REC169-2989 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet should lead the development of a performance management framework for measuring, monitoring and reporting on the implementation of Part 6 of the Act and the CIP framework. The framework should include key indicators, targets and reporting arrangements for assessing the extent to which departments, agencies and industry have fulfilled their obligations, as well as measures for monitoring achievement of joint objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3047 | 38 - Agency/Department Reporting | ACTAS should develop a comprehensive performance management framework that includes key performance indicators and targets aligned to its service delivery activities, to help inform management and stakeholders of its performance. |
REC159-3062 | 38 - Agency/Department Reporting | ACTAS should develop a set of standards to measure and monitor patient satisfaction, so that improvements to the service can be made, based on patient satisfaction information. |
REC159-3058 | 25 - Inquiry, audit, lessons management and after action review | ACTAS should improve patient care processes by: |
REC159-3059 | 38 - Agency/Department Reporting | ACTAS should establish a clinical information database that: |
REC159-3055 | 38 - Agency/Department Reporting | ACTAS should implement systems to enable the accurate collection and measurement of non-emergency ambulance service bookings to facilitate monitoring of performance and the provision of accurate advice to Government. |
REC159-3050 | 38 - Agency/Department Reporting | ACTAS should log all emergency calls on CAD to document non-ambulance dispatch decisions, and to provide more complete data on demand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3428 | 38 - Agency/Department Reporting | That the nominated marine safety authority, in consultation with the Emergency Services Commissioner and senior emergency services personnel, is responsible for monitoring the implementation and auditing against appropriate performance standards, risk management guidelines and good practice guidelines. |
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
REC158-3429 | 38 - Agency/Department Reporting | That the nominated marine safety authority is required to ensure that incident notification and data recording requirements for Victorian commercial ports are consistent and adhered to. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3497 | 8 - Communications and warnings | Emergency Service Organisations work with government departments, local governments and private industry to identify and implement a model for communication flow during an emergency incident. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3491 | 8 - Communications and warnings | The Victoria State Emergency Service improve its communication with local governments, especially in relation to severe weather and storm warning information. |
REC156-3515 | 8 - Communications and warnings | The electricity distribution businesses enhance power outage information on their websites which are accessible to electricity retail businesses, the media and the public and also consider improving their capacity to communicate with customers. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3509 | 8 - Communications and warnings | The Victoria State Emergency Service, Department of Primary Industries, Energy Safe Victoria and the energy sector develop a coordinated set of safety messaging about preparedness for storm events and clearly outline the responsibilities for delivering these messages before during and after an emergency. |
REC156-3507 | 8 - Communications and warnings | Victoria progress, as a matter of priority, a telephony based public emergency notification system to reduce demand on Triple Zero and other emergency telephone lines during a major emergency. |
REC156-3503 | 8 - Communications and warnings | Emergency Service Organisations review their use of Emergency Alerting System paging message categories to ensure that priority messages are not compromised by inappropriate use. An education program may be required to ensure that all users understand message categories, their intended use and ramifications of each category on network and message delivery sequence. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3477 | 38 - Agency/Department Reporting | That the details of any variation or amendment of a Fire Operations Plan, including: the carrying forward or postponement of burns within the three-year period covered by a Fire Operations Plan; the carry over, removal or rescheduling of burns between past, present and future Fire Operations Plans; and the alteration of burn boundaries (including alterations of less than 25 per cent); should appear on the Department of Sustainability and Environment’s website at the time of the change and be included in the Fire Operations Plan for the following year. |
REC155-3476 | 38 - Agency/Department Reporting | That finalised Fire Operations Plans be made publicly available in their entirety (with the exception of any private information) on the Department of Sustainability and Environment’s website and in hard-copy, and that this requirement be clearly stated in future Codes of Practice. This should include the “district burns list”, or its future equivalents, and a map which shows the corresponding burns for each Fire District. Each map should be provided in a format which can be downloaded directly from the Department’s website without the need for further data manipulation by the user. An identical hardcopy version of the map for each Fire District should be also be available to members of the public on request and free of charge. |
REC155-3468 | 38 - Agency/Department Reporting | That the Department of Sustainability and Environment, Department of Primary Industries, Parks Victoria & VicForests separately cost, and report, annual expenditure on fuel reduction burning, ecological burning and regeneration burning in their Annual Reports. |
REC155-3466 | 25 - Inquiry, audit, lessons management and after action review | A comprehensive review of the effectiveness of the increased prescribed burning target in meeting ecological and bushfire suppression needs should be conducted every three years. |
REC155-3467 | 38 - Agency/Department Reporting | The Department of Sustainability and Environment should report its performance against the increased prescribed burning target in its annual report, which should also include the following details: |
REC155-3478 | 38 - Agency/Department Reporting | That all information pertaining to current and planned prescribed burns be published more prominently on the Department of Sustainability and Environment’s website, with a single prominent link to this material on the website homepage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1784 | 8 - Communications and warnings | That the South Australian Country Fire Service empower the Regional Public Warnings Officer to create and deliver public warnings on that Officer’s initiative without the necessity of seeking the approval of personnel at State Headquarters. |
REC153-1782 | 8 - Communications and warnings | That the Minister for Emergency Services, the Chief Officer of the South Australian Country Fire Service, the Chief Officer of the South Australian State Emergency Services and the Commissioner of Police establish a panel to develop policies and practices to ensure that at the time bushfire warnings are created and delivered, all such warnings are made known to all emergency service entities, and to ensure that warnings of an approaching fire are delivered in a timely manner with detailed and specific information relevant to the circumstances of the section of the public to whom they are directed. |
REC153-1781 | 8 - Communications and warnings | That the Minister for Emergency Services in conjunction with the Chief Officer of the South Australian Country Fire Service, the Chief Officer of the South Australian State Emergency Services and the Commissioner of South Australia Police develop policies and practices regarding the issuing of public warnings that address the risk posed to the public by an existing fire incident with a view to disseminating such warnings to the public at a time before the escalation of an existing fire incident occurs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3379 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that a thorough review be undertaken of the communications and coordination between the separate agencies which make up the Emergency Services Agency, to assess the extent to which cultural factors are detrimental to the effective operation of the ESA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3594 | 8 - Communications and warnings | Need for scripting of messages by fire agency representatives when promoting VBIL services via radio, TV and newspapers. |
REC132-3590 | 8 - Communications and warnings | Investigate procedures for updating the Victoria Bushfire Information Line (VBIL) Integrated Voice Response recorded message system to allow recording of permanent bushfire safety, and incident-specific, messages, accessible when the VBIL is experiencing high call volumes during large and/or numerous significant incidents |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1982 | 8 - Communications and warnings | That the Australian Federal Police and the Emergency Services Agency agree on a policy on community safety and evacuation during bushfires, based on the Australasian Fire Authorities Council position outlined in its paper Community Safety and Evacuation during Bushfires. Community education programs should incorporate advice on this, including the ‘stay or go’ policy |
REC126-2010 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the extent to which the recommendations in the McLeod report have been implemented in order to ensure implementation of those not yet implemented |
REC126-1952 | 25 - Inquiry, audit, lessons management and after action review | That regular periodic reviews be undertaken of changes made to the operational and management arrangements for dealing with wildfires and other emergencies in the ACT, to ensure that those arrangements continue to comply with the Australian Inter-Agency Incident Management System Incident Control System |
REC126-1947 | 25 - Inquiry, audit, lessons management and after action review | That the ACT Government commission a review of coroners’ jurisdiction in order to determine whether that jurisdiction ought to be limited or expanded and, if so, to what extend |
REC126-1998 | 8 - Communications and warnings | That a system of public warnings that uses grid references shown on the maps in the Canberra telephone directory be adopted |
REC126-1997 | 8 - Communications and warnings | That the Emergency Services Agency conduct investigations - and liase with emergency services agencies in other jurisdicions - in order to ascertain what technologies exist and are effective for use in disseminating warnings and associated information to the community of the ACT |
REC126-1994 | 8 - Communications and warnings | That the Emergnecy Services Agency publicise and demonstrate the use of the Standard Emergency Warning Signal and provide to the community adequate explanation of the application of the signal. This should occur at least annually, in conjunction with any pre-summer fire awareness initiatives |
REC126-2011 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the recommendations of the seven reviews of the Emergency Services Bureau carried out before the McLeod inquiry and ensure implementation of any of those recommendations that remain relevant but have not been implemented |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3888 | 8 - Communications and warnings | Strengthen internal and external communications to ensure adequate stakeholder involvement throughout the prescribed burning program: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2194 | 38 - Agency/Department Reporting | That the success of current buffers in terms of assisting suppression operations be continually reviewed, evaluated and documented. |
REC104-2300 | 8 - Communications and warnings | That Victoria Police Media Unit coordinate work with the Australian Broadcasting Corporation and the emergency service agencies to implement this arrangement. |
REC104-2333 | 25 - Inquiry, audit, lessons management and after action review | That in doing so, this Review must consult with the agencies mentioned above, and others such as VICSES and the Departments of Human Services and Primary Industries. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2216 | 8 - Communications and warnings | That Victoria include an agenda item for both the National Emergency Management Committee and the National Meeting of Emergency Services Ministers recommending that the Australian Communications Authority review both the Commercial Radio Codes of Practice and Guidelines, and Community Broadcasting Codes of Practice, to ensure they provide necessary guidance and obligations on radio stations during emergencies and in relation to emergency warnings. |
REC104-2281 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA work cooperatively to review the management and application of bulldozers in fire suppression operations to ensure that they are used effectively, appropriately and are adequately supervised. |
REC104-2193 | 38 - Agency/Department Reporting | That if ‘link’ burns continue to be used, then on-site weather sequences and fuel conditions marking successful (‘within explicit prescription’) and unsuccessful burns be documented. |
REC104-2299 | 8 - Communications and warnings | That consideration be given to formalising Australian Broadcasting Corporation Local Radio as the official emergency radio station for Victoria, given it is the only radio station that can cover the whole of the State. |
REC104-2332 | 25 - Inquiry, audit, lessons management and after action review | That the Review of emergency operations centres by the Departments of Premier and Cabinet and Treasury and Finance and the Office of the Emergency Services Commissioner: |
REC104-2290 | 38 - Agency/Department Reporting | That instances where demand for air support outstrips the supply of State Fleet Aircraft available are recorded. |
REC104-2215 | 8 - Communications and warnings | That the Coordinator-in-Chief of Emergency Management directs the Media sub-committee of the State Emergency Response Committee to review the use of the Standard Emergency Warning Signal and its accompanying message. |
REC104-2277 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review methods of gathering and processing fire information to ensure all methods are pursued to greatest effect. |
REC104-2298 | 8 - Communications and warnings | That relevant Government agencies including Emergency Communications Victoria, the Bureau of Emergency Services Telecommunications and the Victoria Police Media Unit, evaluate the proposals put forward by the Australian Communications Authority with respect to the hearing impaired. |
REC104-2293 | 25 - Inquiry, audit, lessons management and after action review | That aviation contractors be required to submit a copy of their annual independent regulatory compliance audit prepared for Civil Aviation Safety Authority to the State Aircraft Unit. |
REC104-2289 | 38 - Agency/Department Reporting | That the joint agencies introduce a system of performance measures for reporting the effectiveness of aircraft in firefighting operations. |
REC104-2228 | 25 - Inquiry, audit, lessons management and after action review | That the Government identifies an appropriate body, or bodies, to undertake the audit of the Municipal Fire Management Plans. |
REC104-2297 | 8 - Communications and warnings | That the model of community engagement developed by DSE and CFA and applied during the 2002-2003 fires is further developed and refined, particularly in regard to short-duration, rapidly escalating incidents. |
REC104-2292 | 25 - Inquiry, audit, lessons management and after action review | That a systematic performance audit of State Aircraft Fleet contractors be conducted jointly by agency and SAU personnel. |
REC104-2200 | 38 - Agency/Department Reporting | That DSE: |
REC104-2302 | 8 - Communications and warnings | That opportunities be explored to use community radio to complement other methods of communication with isolated communities. |
REC104-2197 | 25 - Inquiry, audit, lessons management and after action review | That a review of the fuel management zones be implemented with a view to reducing the number of zones so as to focus clearly on (i) asset protection (especially at the Public/Private land interface), and (ii) ecological burns. |
REC104-2296 | 8 - Communications and warnings | That in relation to the provision of information to communities affected by fires and other emergencies, DSE and CFA ensure that: |
REC104-2284 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review the management of personnel deployed ensuring that: |
REC104-2195 | 38 - Agency/Department Reporting | That the creation of buffers by chaining and then burning swaths of mallee be explicitly monitored for: |
REC104-2301 | 8 - Communications and warnings | That CFA and DSE work with Australian Broadcasting Corporation Local Radio to identify black spots, and explore opportunities to further improve coverage for broadcasting emergency information. |
REC104-2287 | 8 - Communications and warnings | That DSE and CFA work with the Bureau of Emergency Services Telecommunications to ensure that rural communication issues are appropriately addressed in the Statewide Integrated Public Safety and Communications Strategy, and that priorities and business cases are agreed for critical issues. |
REC104-2282 | 25 - Inquiry, audit, lessons management and after action review | That quality control or performance assessments are routinely completed post fire season, to ensure that contractors who have not performed to an agreed standard are not re-engaged for the consequential rehabilitation works. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3246 | 38 - Agency/Department Reporting | The Committee recommends that performance monitoring standards be established, reviewed and maintained through a common reporting system by the Minister for Police and Emergency Services. |
REC061-3258 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3423 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |