Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4222 | 4 - Fire season preparation | The Inspector-General Emergency Management recommends the Department of Environment and Science undertake a review of campfire locations on K’gari, including all relevant signage on and off the island, maps and visitor permit information, to promote a consistent message about lighting campfires on K’gari. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4048 | 37 - Funding | Government consider adopting a similar model to NSW for the management of emergency costs and reimbursements within ACT Government agencies. |
REC316-4047 | 37 - Funding | Government consider an alternative funding arrangement for extraordinary costs borne by Government agencies in combating emergencies such as bushfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2423 | 37 - Funding | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning as a matter of priority, establish what funding is reasonably required and complete all elements of the Brisbane River Catchment Flood Studies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2564 | 37 - Funding | Western Australia Health should collate and centrally monitor financial data including the cost to government of IHPT |
REC252-2563 | 37 - Funding | Western Australia Health should develop and agree with St John Ambulance a new funding model for emergency ambulance services focusing on standards, performance and allocation of risk |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1033 | 37 - Funding | When a local Rural Fire Brigade requests an equipment and maintenance levy from a local government authority, that authority will either supply the brigade’s equipment and maintenance costs or raise the requested levy. The amount to be collected is to be agreed between the local Brigade and the local government authority. |
REC241-1032 | 37 - Funding | That the current Urban Fire Levy be changed to the Queensland Fire Levy. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
REC241-1035 | 37 - Funding | That the State Government contribution towards the purchase of operational vehicles is to be retained at 80 percent but that the District Inspector can recommend full Government subsidy of vehicles for Brigades experiencing financial hardship. |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
REC241-1034 | 37 - Funding | That the State Government contribution towards the construction of Brigade sheds be changed from $10,000 to a maximum of 25 percent, subject to the approval of the Deputy Chief Officer, Rural Fire Service Queensland. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2681 | 37 - Funding | That the funding model for the Portfolio Business is not based on fee- for-service arrangements or notional contributions from the operational services. |
REC239-2780 | 37 - Funding | That should the Westgate project proceed, that consideration must be given to opportunities to partner the investment with the private and public sectors. The business case should also consider alternative facilities such as Australian Defence Force sites. |
REC239-2779 | 37 - Funding | That a new business case for Westgate project should be prepared by an independent party. |
REC239-2753 | 37 - Funding | That the proposed Chief Executive Officer Portfolio Business be responsible for developing a cost attribution model for portfolio agencies, including the Queensland Police Service, as a priority. |
REC239-2683 | 37 - Funding | That the Office of Portfolio Business follows the same budget processes as other agencies. |
REC239-2682 | 37 - Funding | That a budget based on the desired functional accountabilities should be appropriated to the Portfolio Business as part of the Government budget process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1617 | 37 - Funding | The Territory and Municipal Services Directorate should annually (and on a cumulative basis) track and report on funds allocated for, and spent on, its Bushfire Operations Plan to the Minister for Police and Emergency Services. |
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
REC228-1616 | 37 - Funding | The Territory and Municipal Services Directorate should enhance internal monitoring of its implementation of bushfire management activities and spending under the Bushfire Operations Plan by routinely reconciling figures in this plan with those in the Directorate’s corporate financial system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1856 | 37 - Funding | The Ministers for Emergency Services, Environment and Police provide additional funds in the 2013-14 Budget so that the State’s emergency response agencies can implement a Psychological First Aid approach to preparing staff to deal with critical incidents and disasters, as is used in other Australian jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0732 | 37 - Funding | Emergency Management Queensland should develop and implement a new formula for the distribution of its recurrent SES subsidy, which takes into account relevant factors including the size of a local SES contingent and the population, area and natural hazard risk profile of the local government area concerned. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1725 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0385 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0274 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services undertake a thorough review, including consultation with rural fire brigades, regarding the proposed formula for distribution of funding. |
REC191-0273 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services implement system of fire levies for landholders situated in urban, iZone and village brigade areas. |
REC191-0266 | 37 - Funding | that QFRS cover the cost of annual vehicle inspection certificates for rural fire brigade registered vehicles. |
REC191-0275 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services ensure that the formula for distribution of funding as recommended above allows rural fire brigades to control any donation or sponsorship funding raised by individual brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3589 | 37 - Funding | That consideration be given to the establishment of a ‘Heritage Reserve Fund’ that might underwrite urgent initial repairs to private heritage listed properties. |
REC143-3586 | 37 - Funding | That the ‘opportunity cost’ for Local Authorities in meeting the 25% contribution to the restoration of eligible public assets damaged by a natural disaster event be considered when FESA and Main Roads Western Australia, in consultation with Western Australian Local Government Authority, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs as recommended in Recommendation 1. |
REC143-3582 | 37 - Funding | That the Department of Treasury and Finance, in consultation with FESA, consider alternative funding arrangements to alleviate the need for FESA to ‘underwrite’ NDRA costs during the year. |
REC143-3581 | 37 - Funding | That, in tandem with their consideration of local government cost sharing arrangements under WANDRA (refer Recommendation 1), the Fire and Emergency Services Authority and Main Roads Western Australia also establish ‘exceptional circumstances’ criteria to provide for additional assistance to local government where it may be warranted in order to avoid undue financial pressure caused by delays to secure reimbursement. |
REC143-3576 | 37 - Funding | That Fire and Emergency Services Authority of Western Australia and Main Roads Western Australia, in consultation with the Western Australian Local Government Association, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs. In particular consideration should be given to regulations applying in the eastern states i.e. Queensland. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
REC126-1967 | 40 - Equipment and consumables | That the Emergency Services Agency give priority to ensuring it has guaranteed access to an adequate number and type of bulldozers, as well as experienced operators, during the fire season, for immediate deployment as required |
REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4145 | 37 - Funding | A fund be established to subsidise the purchase of equipment for bush fire brigades but that the granting of subsidies depend upon a certificate being received from the Bush Fires Board that the brigade in question is of a standard that will be available at all times for effective use and that adequate facilities are available for its storage and maintenance at a centre suitable for the brigade. |