Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2512 | 38 - Agency/Department Reporting | Documenting results and recommendations from disaster recovery tests. |
Rec-ID | Code | Recommendation |
---|---|---|
REC312-2506 | 9 - Community education | The chairpersons of disaster management groups within the Townsville Disaster District, supported by the Queensland Police Service, Queensland Fire and Emergency Services and the Queensland Reconstruction Authority develop a district action plan based on the capability enhancement strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2482 | 9 - Community education | Practical guidance on what community-led recovery means, and how it can be best implemented should be captured and shared with all who have responsibility for it. This should be done to help individuals and communities to take the lead in recovery and so that community-led recovery becomes the norm following disasters and other events. |
REC310-2486 | 9 - Community education | State arrangements for on-the-ground support to recovering local governments should be in line with Queensland’s disaster management arrangements, and ensure the best balance between local relationships, suitable capability and sufficient capacity. |
REC310-2483 | 9 - Community education | 09-Community education/engagement/preparedness |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
REC309-2467 | 9 - Community education | Further work be undertaken to develop effective public flood risk messaging and community education materials that are easy to understand and tested with the community to ensure flood risk is understood. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1306 | 9 - Community education | Develop practical policy outcomes to support resilience (e.g. the 72- hour model) and promote this broadly to community through media, awareness campaigns, policies etc. Research should be undertaken to gain insight into the types of messaging and activities that have the most impact on sustained behaviour change within the community before committing to a particular model. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1439 | 9 - Community education | Continue the Community Bushfire Protection Program with a renewed focus on vulnerable groups. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1476 | 9 - Community education | Develop and implement a targeted community flood awareness program. |
REC286-2083 | 9 - Community education | Enhance the community development program. |
REC286-1473 | 13 - Mapping and data quality | Develop a statewide flood hazard map for use within the Tasmanian Planning System. |
REC286-1437 | 9 - Community education | Continue the Bushfire Ready Neighbourhoods Program. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-1466 | 9 - Community education | Develop and deliver earthquake hazard awareness products. |
REC286-2075 | 9 - Community education | Develop and implement a community storm safe awareness program. |
REC286-1459 | 13 - Mapping and data quality | Improve beach morphology mapping to understand coastal inundation, including post-event surveys. |
REC286-2097 | 13 - Mapping and data quality | Extend current tsunami maritime hazard modelling project to deliver coastal inundation modelling. |
REC286-1449 | 9 - Community education | Develop coastal inundation education materials that meet the needs of exposed communities. |
REC286-1443 | 14 - Incident Mgt Teams | Build capacity to enable Incident Management Teams to manage the likely increased frequency and intensity of major fire events. |
REC286-2035 | 9 - Community education | Include heatwave in existing preparedness programs. |
REC286-1458 | 13 - Mapping and data quality | Make coastal mapping available to public. |
REC286-2094 | 13 - Mapping and data quality | Deliver updated inundation mapping. |
REC286-1446 | 9 - Community education | Introduce child-centred household level disaster risk reduction strategies in school programs. |
REC286-2034 | 9 - Community education | Improve community educational information. |
REC286-2088 | 9 - Community education | Develop a community education strategy for when to call 000, 131 444, and 132 500. |
REC286-1440 | 9 - Community education | Expand the existing Fire Ready Schools Program with enhanced support and incorporate other sites used by vulnerable groups. |
REC286-2085 | 9 - Community education | Up-skill isolated communities in emergency PPRR skills. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2525 | 38 - Agency/Department Reporting | The report recommends that Ambulance Tasmania outline what KPIs are measured and provide targets or benchmarks to define what is good or poor performance. |
REC285-2518 | 38 - Agency/Department Reporting | The report recommends that regional summary reports of clinical reviews be standardised to facilitate review and comparison across regions. |
REC285-2517 | 38 - Agency/Department Reporting | The report recommends that Ambulance Tasmania collects data to allow regular and meaningful comparison of clinical outcomes at the regional level, to better allocate resources and to rapidly identify problems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1202 | 13 - Mapping and data quality | Impact Assessment Data Collection: The Office of Emergency Management continues to progress the Impact Assessment Data Collection Project and: · incorporate recovery schema in Rapid Impact Assessments · review procedures for collection of Rapid Impact Assessment Data · review and combine current templates into one, single template for Impact Assessment Reports that is used by all agencies · further develop Impact Assessment Guidelines for agency personnel undertaking impact assessments |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1408 | 7 - Inter-agency communication | That the Department of Health & Human Services uses Emergency Services Telecommunications Authority Computer Aided Dispatch data to report ambulance emergency response time performance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1432 | 9 - Community education | Queensland Fire and Emergency Services should consider developing and implementing mechanisms, such as face-to-face forums, for disaster management practitioners to share knowledge, contemporary research findings and document good practice about warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1152 | 13 - Mapping and data quality | Impact Assessment Data Sharing Project |
REC267-1159 | 9 - Community education | Improving Community Preparedness and Resilience |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1150 | 9 - Community education | Media Engagement Consideration should be given on future recovery operations to adopting a more structured approach to media engagement, with regular media briefings undertaken at a frequency dependent upon the phase of the recovery activities and the level of media interest. These briefings could be conducted at different locations around the region, if appropriate, and would provide the opportunity for communication of key messages and provide journalists with the opportunity to ask questions regarding the recovery. This could be complemented by media coverage of community engagement visits. For all recovery operations, |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1485 | 7 - Inter-agency communication | That Victoria Police implements the recommendations relating to protective services officers in the Service Demand and Dispatcher Capacity Analysis dated September 2013 and: |
REC262-1484 | 7 - Inter-agency communication | That Ambulance Victoria: |
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1483 | 7 - Inter-agency communication | That the Emergency Services Telecommunications Authority includes Victoria State Emergency Service vehicle capability details in the Computer Aided Dispatch database. |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
REC262-1491 | 7 - Inter-agency communication | That Emergency Management Victoria expedites the expansion of the Rural Mobile Radio network to all emergency services organisations. |
REC262-1487 | 7 - Inter-agency communication | That the Emergency Services Telecommunications Authority, assisted by the Inspector-General for Emergency Management and responder agencies, improves the process for changing call-taking and dispatch procedures by comprehensively appraising the costs, benefits and operational impacts of these changes and agreeing a plan for their implementation with all affected agencies. |
REC262-1486 | 7 - Inter-agency communication | That Emergency Management Victoria novates the head contract for the StateNet Mobile Radio network to the Emergency Services Telecommunications Authority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1565 | 13 - Mapping and data quality | Governments should task the Australia–New Zealand Emergency Management Committee with leading the development of guidelines for the collection and dissemination of natural hazard mapping, modelling and metadata. Guidelines should be developed for all hazards that need to be modelled and mapped at the local/regional level and where consistency across regions is desirable. |
REC256-1563 | 13 - Mapping and data quality | Governments at all levels should make new and currently held natural hazard data publicly available in accordance with open public sector information principles. When collecting new natural hazard data or undertaking modelling, all levels of government should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC255-1579 | 38 - Agency/Department Reporting | The ANAO recommends that the Department of Defence take steps to strengthen the priority afforded by Defence units to meeting these reporting requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2566 | 38 - Agency/Department Reporting | Western Australia Health should require service providers to report more comprehensive performance data using additional cost and clinical indicators |
REC252-2565 | 38 - Agency/Department Reporting | Western Australia Health should include in contracts minimum standards for emergency and secondary ambulance services and effective mechanisms to monitor these |
REC252-2571 | 38 - Agency/Department Reporting | St John Ambulance should develop quantitative performance targets for community paramedics and report these to Western Australia Health |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2589 | 7 - Inter-agency communication | That TFS and Ambulance Tasmania work together to resolve problems around congestion, particularly during the fire season. |
REC245-2588 | 7 - Inter-agency communication | That Tasmania Police, Tasmania Fire Service (TFS), Ambulance Tasmania and State Emergency Services (SES) investigate ways of providing secure and confidential radio communications. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2651 | 13 - Mapping and data quality | That the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomesThat the Department of Health facilitates the sharing of hospital patient outcome data with Queensland Ambulance Service to help measure the effect of pre-hospital care on patient outcomes. |
REC240-2653 | 38 - Agency/Department Reporting | That the Department of Health publicly reports a comprehensive suite of performance information, including: |
REC240-2652 | 38 - Agency/Department Reporting | That the Department of Health enhances management reporting processes over complaints by recording the number and nature of complaints, following up outstanding complaints formally and reporting complaints data to executive management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2710 | 13 - Mapping and data quality | That all agencies participating in these activities should, as far as legally possible, share data sets whether or not the relevance is immediately obvious. |
REC239-2768 | 9 - Community education | Recommendation: That: |
REC239-2674 | 38 - Agency/Department Reporting | That Queensland Corrective Service continues to develop its proposed recidivism index as a priority, including place and program based measures. |
REC239-2773 | 38 - Agency/Department Reporting | That should the Mobile Strategy in its current form be approved by government the CEO Portfolio Business and the Deputy Commissioner Operations: |
REC239-2659 | 9 - Community education | That Queensland Health continues to recognise and foster the important contributions of Local Ambulance Committees to supporting effective community focused ambulance services across the State. |
REC239-2673 | 38 - Agency/Department Reporting | That Queensland Corrective Service, in consultation with key partners in the criminal justice and social services sectors, develops specific performance indicators focused on efficiencies and customer/stakeholder outcomes across the criminal justice system. |
REC239-2772 | 38 - Agency/Department Reporting | That the roll-out of the mobile service program business case mentioned earlier |
REC239-2771 | 38 - Agency/Department Reporting | That the Queensland Police Service Commissioner addresses the situation regarding statistical reporting. The Commissioner, in collaboration with the Chief Executive Officer Portfolio Business and the Queensland Fire and Rescue Service Commissioner should also examine the opportunity to acquire the services of a qualified and experienced Chief Information Officer or Chief Digital Officer in line with other Queensland and Australian government agencies. |
REC239-2770 | 9 - Community education | That the efficiency review of the Queensland Police Service develop options for better management of community expectations and divesting the organisation of historical practices. |
REC239-2767 | 38 - Agency/Department Reporting | Recommendation: That the CEO Portfolio Business collaborates with the two portfolio Commissioners to: |
REC239-2769 | 9 - Community education | That the Chief Executive Officer portfolio business and Commissioner of Police in line with the government’s open data policy consider introducing an improved social media style forum for interaction with the community and stakeholders across the portfolio. |
REC239-2684 | 38 - Agency/Department Reporting | The Chief Executive Officer Portfolio Business establishes a set of performance indicators to provide a transparent process for government to monitor its performance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0830 | 9 - Community education | That Bush Fire Risk Management Plans be tabled at Local Emergency Management Committees for comment. |
REC237-0829 | 9 - Community education | That Bush Fire Risk Management Plans be posted on the NSW Rural Fire Service website. |
REC237-0828 | 9 - Community education | That the NSW Rural Fire Service develop a strategy to better inform the community and NSW Rural Fire Service members about the NSW bush fire management system and its components. |
Rec-ID | Code | Recommendation |
---|---|---|
REC231-2830 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Department of Regional Australia, Local Government, Arts and Sport improve its monitoring of the delivery of the Natural Disaster Recovery Work Plans for Queensland and Victoria by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1853 | 38 - Agency/Department Reporting | The Ministers for Emergency Services, Environment and Police ensure their departments include in their annual reports the expenditure they have incurred on preparing their staff for critical incidents, and for managing their response to these incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC221-2862 | 38 - Agency/Department Reporting | Housing should use risk based analysis of its tenant and property information, job order data and quality assurance results to better inform target setting for KPIs, job order controls, and the sampling used for completed work inspections before and after payment. This analysis should synthesise information from all sources and include a risk assessment of tenants and properties, as well as consideration of the various types of maintenance work being done (emergency, priority and routine, and planned maintenance). |
REC221-2861 | 38 - Agency/Department Reporting | Housing should further develop its Head Contractor key performance indicators to include quality, cost and tenant satisfaction. Currently performance reporting is focused entirely on timeliness indicators. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2885 | 13 - Mapping and data quality | Increased automation and outsourcing of observations |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1897 | 9 - Community education | The Australian Government initiative to improve the coordination and dissemination of flood-risk information should proceed in the most cost-effective way, be regularly updated and be expanded over time to encompass other natural hazards. Guidelines to improve the quality and consistency of risk information should also be regularly updated and take climate change into account where feasible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1929 | 38 - Agency/Department Reporting | That the Queensland Reconstruction Authority consider extending the suite of internal performance indicators being used as the Authority matures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC186-0398 | 9 - Community education | The committee recommends emergency service organisations in collaboration with television and radio broadcasters, the print media and other relevant organisations, use regular and ongoing public education well in advance of an emergency situation as an opportunity to teach the public about their responsibilities during an emergency and how they can appropriately prepare themselves for such an event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2977 | 38 - Agency/Department Reporting | The Department of Human Services should create evaluation guidelines for recovery operations, including links to planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2987 | 9 - Community education | To improve customer awareness of the availability of disaster recovery assistance, the ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0057 | 7 - Inter-agency communication | SEMC and EM WA should: ensure that agencies have a common or compatible crisis information management system in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0090 | 7 - Inter-agency communication | The SDMG lead an initiative to integrate and/or inter-connect all of the control centres involved at all levels of the Disaster Management system in Queensland as part of the project to integrate State communications. |
Rec-ID | Code | Recommendation |
---|---|---|
REC160-3044 | 38 - Agency/Department Reporting | The ANAO recommends that the Business Continuity, Crisis Management and Security Sub committee: |
REC160-3042 | 38 - Agency/Department Reporting | In order to identify key business processes and provide for the regular comparative assessment of Maximum Allowable Outage periods (MAOs), the ANAO recommends that Centrelink: |
REC160-3045 | 38 - Agency/Department Reporting | The ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3059 | 38 - Agency/Department Reporting | ACTAS should establish a clinical information database that: |
REC159-3055 | 38 - Agency/Department Reporting | ACTAS should implement systems to enable the accurate collection and measurement of non-emergency ambulance service bookings to facilitate monitoring of performance and the provision of accurate advice to Government. |
REC159-3050 | 38 - Agency/Department Reporting | ACTAS should log all emergency calls on CAD to document non-ambulance dispatch decisions, and to provide more complete data on demand. |
REC159-3047 | 38 - Agency/Department Reporting | ACTAS should develop a comprehensive performance management framework that includes key performance indicators and targets aligned to its service delivery activities, to help inform management and stakeholders of its performance. |
REC159-3062 | 38 - Agency/Department Reporting | ACTAS should develop a set of standards to measure and monitor patient satisfaction, so that improvements to the service can be made, based on patient satisfaction information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC147-3186 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that, in order to assist management decision making and to inform Parliament about performance, Emergency Management Australia (EMA) develop and report appropriate measures for its key emergency management activities and outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3235 | 13 - Mapping and data quality | The Committee recommends that the National Coastal Zone Database be expanded over time to include information on environmental data and management and planning information relevant to the coastal zone. |
REC145-3234 | 9 - Community education | The Committee recommends that the Australian Government nominate 2012 as the Year of the Coast, to further build community awareness about the issues facing the coastal zone. The Australian Government should work with coastal stakeholders, volunteer groups and the general community in determining key activities as part of this initiative. |
REC145-3218 | 13 - Mapping and data quality | The Committee recommends that the Australian Government, through the Australian Bureau of Statistics, ensure that: |
REC145-3233 | 9 - Community education | The Committee recommends that the Australian Government undertake an awareness campaign to alert coastal communities to the key challenges facing the coastal zone and the value of community engagement in addressing these challenges. The campaign should aim to build understanding and awareness of coastal management issues to encourage the continued membership and support of volunteer networks in the coastal zone. |
REC145-3204 | 13 - Mapping and data quality | The Committee recommends that the Australian Government establish a National Coastal Zone Database to improve access to and consistency of information relevant to coastal zone adaptation. The National Coastal Zone Database should be an online portal that allows ready access to: |
REC145-3201 | 13 - Mapping and data quality | The Committee recommends that the Department of Climate Change share all data collected through vulnerability assessments undertaken as part of the Australian Government Local Adaptation Pathways Program on the proposed National Coastal Zone Database (see also recommendation 42). |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3399 | 9 - Community education | The Committee recommends that the Emergency Services Agency post all its publications, which are not internal working documents or otherwise confidential, on its website. |
REC144-3398 | 9 - Community education | The Committee recommends that the Emergency Services Agency update its website to accommodate, at a minimum, a publications menu item and a search function. |
REC144-3397 | 9 - Community education | The Committee recommends that the ACT Government investigate the Victorian Community Fireguard model with a view to implementing a similar scheme in the ACT to enhance community preparedness for and ability to respond to bushfire emergencies. |
REC144-3396 | 9 - Community education | The Committee recommends that information in relation to proposed fuel load activity and controlled burning should be disseminated to the community and in an accessible format. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3579 | 9 - Community education | That FESA develop comprehensive internet-based information including but not limited to detail of WANDRA objectives, assistance measures, administering agencies, eligibility criteria (where applicable) and application forms. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3574 | 38 - Agency/Department Reporting | Formation of a subcommittee of the DHHS Tasmanian Medical Retrieval Services Committee to identify risk exposures, system problems and potential solutions. The subcommittee should review data, problem cases, system issues and generate a risk register. Meetings should occur at least quarterly. |
REC140-3573 | 13 - Mapping and data quality | Databases with a common minimum data set complete with incident monitoring should be established for TAS Air Ambulance, TMRS and NETS missions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3648 | 38 - Agency/Department Reporting | It is recommended that providers supply data to the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2111 | 9 - Community education | The Working Group recommends that the national forum mentioned in recommendation 13 consider the ongoing need for dissemination of information on a national basis both during and following a catastrophic disaster and also identify strategies to ensure the ability of this to be facilitated. |
REC116-2110 | 9 - Community education | The Working Group recommends that EMA convene a national forum to explore community information and warning needs in catastrophic disasters, to review existing information and warning systems, and to identify possible technologies and techniques that might be used to enhance community needs in disasters. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |