Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4214 | 1 - Land-use and building regs | We recommend that DELWP determines which elements of different regional planning approaches are the most effective and implements these across the state. |
REC321-4215 | 1 - Land-use and building regs | We recommend that DELWP develops more holistic bushfire-management planning that focuses on the best mix of risk treatments rather than planned burning alone. |
REC321-4207 | 25 - Inquiry, audit, lessons management and after action review | We recommend that DELWP reviews its target for the number of fuel hazard assessments conducted and ensures that this measure is evidence based, accurately reflects regional performance, and that the department monitors and reports on each region’s performance against it. |
REC321-4211 | 1 - Land-use and building regs | We recommend that CFA (in consultation with FRV) improves planning on private land to ensure risk assessments and plans are conducted consistently across public and private land to address state-wide bushfire risk based on where and how they can most effectively reduce risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4189 | 33 - Relief and recovery | Donated good: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department: |
REC319-4195 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, leads the development of a comprehensive, person-centred, trauma-informed recovery financial assistance system that establishes: |
REC319-4196 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, works with the emergency management sector to develop a recovery funding model that enables: |
REC319-4198 | 33 - Relief and recovery | Relief and recovery capability: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions works with the entity referred to in Recommendation 13, or otherwise responsible government department and/or Municipal Association of Victoria, councils and local relief and recovery organisations to provide centralised capability development opportunities to increase local capability and capacity to plan and deliver on their relief and recovery responsibilities: |
REC319-4200 | 33 - Relief and recovery | Foundations of emergency management: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in consultation with the emergency management sector – establish policies and platforms to improve operational and personal information sharing between relief and recovery organisations. These policies and platforms should enable: |
REC319-4187 | 33 - Relief and recovery | Recovery governance: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, work with councils, relevant recovery organisations and communities to develop clear roles and responsibilities for: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4181 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in collaboration with the emergency management sector and as part of the emergency management planning reforms: |
REC318-4178 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in collaboration with the Country Fire Authority and local government – undertake a review of the current residual risk target to ensure that it remains contemporary in terms of its designated percentage value. The review should: |
REC318-4171 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the State review (and where necessary amend) legislation including but not limited to the Country Fire Authority Act 1958, Forest Act 1958 and Local Government Act 2020 to: |
REC318-4182 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in partnership with agencies engaged in state, regional and incident control centres: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4116 | 33 - Relief and recovery | Governments should create and publish standing policy guidance on whether they will or will not assist to clean-up debris, including contaminated debris, resulting from natural hazards. |
REC317-4126 | 33 - Relief and recovery | Australian, state and territory governments should expedite the development of pre-agreed recovery programs, including those that address social needs, such as legal assistance domestic violence, and also environmental recovery. |
REC317-4104 | 33 - Relief and recovery | Australian, state and territory governments should refine arrangements to support localised planning and the delivery of appropriate mental health services following a natural disaster. |
REC317-4122 | 33 - Relief and recovery | Australian, state and territory and local governments should evaluate the effectiveness of existing financial assistance measures to inform the development of a suite of pre-effective pre-determined recovery supports. |
REC317-4115 | 1 - Land-use and building regs | The Australian Building Codes Board, working with other bodies as appropriate, should: |
REC317-4119 | 33 - Relief and recovery | The Australian Government, through the mechanism of the proposed standing national recovery and resilience agency, should convene regular and ongoing national forums for charities, non-government organisations and volunteer groups, with a role in natural disaster recovery, with a view to continuous improvement of coordination of recovery support. |
REC317-4114 | 1 - Land-use and building regs | State, territory and local governments should be required to consider present and future natural disaster risk when making land-use planning decisions for new developments. |
REC317-4118 | 33 - Relief and recovery | Australian, state and territory governments should create a single national scheme for the regulation of charitable fundraising. |
REC317-4102 | 25 - Inquiry, audit, lessons management and after action review | Australian, state and territory governments should review Australian Medical Assistance Team capabilities and procedures and develop necessary training, exercising and other arrangements to build capacity for domestic deployments. |
REC317-4117 | 33 - Relief and recovery | State and territory governments should develop and implement efficient and effective arrangements to: |
REC317-4074 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should review the content of the Defence Assistance to the Civil Community manual to ensure consistency of language and application with a revised COMDISPLAN. |
REC317-4127 | 33 - Relief and recovery | Australian, state and territory governments should incorporate the principle of ‘build back better’ more broadly into the Disaster Recovery Funding Arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1344 | 25 - Inquiry, audit, lessons management and after action review | That a review of the cross‑tenure approach be undertaken to determine its effectiveness and to address issues that arise in fire prevention on private and public land. |
REC299-1343 | 25 - Inquiry, audit, lessons management and after action review | That the Government conduct a review of fire prevention |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1412 | 20 - Role of police | That Victoria Police assesses and where practical addresses limitations to available data and trials the use of response times for internal performance measurement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1087 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • practice and ensures that, by taking a risk management approach, it is suitable for fire prevention, mitigation and suppression in all parts of the Hazelwood mine; and review its ‘Mine Fire Service Policy and Code of Practice’ so that it refects industry best • work plan for the Hazelwood mine. incorporate the revised ‘Mine Fire Service Policy and Code of Practice’ into the approved |
REC264-1086 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • consequences of fire in the worked out areas of the Hazelwood mine, and an assessment of the most effective fre protection for the exposed coal surfaces; conduct, assisted by an independent consultant, a risk assessment of the likelihood and • controls are in place to eliminate or reduce the risk of fre; and prepare an implementation plan that ensures the most effective and reasonably practicable • implement the plan |
REC264-1072 | 25 - Inquiry, audit, lessons management and after action review | The State empower and require the Auditor-General or another appropriate agency, to: • oversee the implementation of these recommendations and the commitments made by the State and GDF Suez during this Inquiry; and • report publicly every year for the next three years on the progress made in implementing recommendations and commitments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1548 | 25 - Inquiry, audit, lessons management and after action review | The Regional Director-Defence Support-Northern NSW, make contact with Deputy Commissioner ~~~~~ Director of Operational Services Rural Fire Service, to arrange a headquarters driven bipartite review of the events of 16 October 2013 with a review to mitigation of future fire events generally, and with specific reference to: |
REC257-1546 | 25 - Inquiry, audit, lessons management and after action review | Defence undertake a review of its ability to respond to a fire within Marrangaroo Training Area, whether bushfire or structural. The underlying assumption should be that the only response available to fight a fire within Marrangaroo Training Area will be provided by Defence. Further, such response must occur while a fire is in its initial stages. A review must either acknowledge the risk of fire occurring in th future, or upgrade Defence's firefighting capability at Marrangaroo Training Area. |
REC257-1539 | 25 - Inquiry, audit, lessons management and after action review | Defence Security Authority conduct an investigation into the whereabouts of items of anaccounted explosive ordnance issued to Defence Explosive Ordnance Training School Exercise Marrangaroo. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1573 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should schedule an independent and public review of the progress of reforms to natural disaster funding arrangements five years after implementation has commenced. This review should examine the operation and efficacy of the arrangements, including the: |
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2792 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the investigation be re-opened by the ATSB with a focus on organisational, oversight and broader systemic issues. |
REC236-2806 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies investigate appropriate methods to ensure that information about the incidence of, and variable weather conditions at, Norfolk Island is available to assist flight crews and operators managing risk that may result from unforseen weather events. |
REC236-2805 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies review whether any equipment or other changes can be made to improve the weather forecasting at Norfolk Island. The review would include whether the Unicom operator should be an approved meteorological observer. |
REC236-2801 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the ATSB review its process to track the implementation of recommendations or safety actions to ensure it is an effective closed loop system. This should be made public, and provided to the Senate Regional and Rural Affairs and Transport Committee prior to each Budget Estimates. |
REC236-2795 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that a short inquiry be conducted by the Senate Standing Committee on Rural and Regional Affairs and Transport into the current status of aviation regulatory reform to assess the direction, progress and resources expended to date to ensure greater visibility of the processes. |
REC236-2793 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that CASA processes in relation to matters highlighted by this investigation be reviewed. This could involve an evaluation benchmarked against a credible peer (such as FAA or CAA) of regulation and audits with respect to: non-RPT passenger carrying operations; approach to audits; and training and standardisation of FOI across regional offices. |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1591 | 35 - Business and Industry in relation to industry | While noting the importance of voice communications, telecommunications providers should consider as part of their mass outage business continuity planning, options for the provision of interim mobile broadband services for the community e.g. local wireless broadband access hubs (i.e. Wi-Fi). |
REC233-1598 | 35 - Business and Industry in relation to industry | Community service providers consider developing information and advice regarding telecommunications outages for clients managed remotely using telecommunication services, including personal alert devices. |
REC233-1590 | 25 - Inquiry, audit, lessons management and after action review | Department of Broadband, Communications and the Digital Economy seek regular updates from Telstra on the implementation of the recommendations of its inquiry into the Warrnambool exchange fire. |
REC233-1597 | 35 - Business and Industry in relation to industry | Community service providers consider updating their business continuity plans to take into account the possibility of a major telecommunications outage involving both fixed and mobile voice and data services. |
REC233-1595 | 35 - Business and Industry in relation to industry | Department of Broadband, Communications and the Digital Economy to work with the Trusted Information Sharing Network’s Communications Sector Group to develop general telecommunications continuity advice for businesses and individuals to assist in developing continuity plans. |
REC233-1601 | 35 - Business and Industry in relation to industry | Community service providers consider in their business continuity planning how they could assist with facilitating access to telecommunications services for the public during mass outages. |
REC233-1594 | 35 - Business and Industry in relation to industry | When businesses review their business continuity plans they should take into account the prospect of a major telecommunications outage that affects both mobile and fixed voice and data services. |
REC233-1600 | 35 - Business and Industry in relation to industry | Community service providers consider, in consultation with relevant government authorities, reviewing their current privacy practices concerning personal information about vulnerable persons to ensure they are able to appropriately share information during major disruptive incidents. |
REC233-1593 | 35 - Business and Industry in relation to industry | Telstra and other service providers to consider improving processes to assist customers with setting up temporary call diversions during future outages. |
REC233-1599 | 35 - Business and Industry in relation to industry | Providers of personal alert devices consider telecommunications outages in their service continuity plans and provide clear advice to their customers regarding their options during a telecommunications service outage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2828 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, commission an independent review to assess the case for establishing a national centre for communicable disease control in Australia. The review should outline the role of a national centre and how it might be structured to build on and enhance existing systems. It should examine different models, considering a range of options for location, governance and staffing. The review should incorporate a cost-benefit analysis for each of the models presented. |
REC232-2827 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, conduct a comprehensive national audit and mapping exercise to: |
REC232-2815 | 25 - Inquiry, audit, lessons management and after action review | The Department of Health and Ageing review the existing evidence base to evaluate the cost-effectiveness of its policy to use heat scanners at ports of entry as a measure to mitigate the risk of infectious disease importation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2841 | 1 - Land-use and building regs | The committee recommends that credible and reliable flood mapping activities and the development of other information that would best inform landowners or prospective landowners of potential risks from extreme weather events are prioritised and used to inform land use planning laws. |
REC229-2842 | 1 - Land-use and building regs | The committee recommends that building codes incorporate mitigation measures that take into account foreseeable risks from extreme weather events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1875 | 1 - Land-use and building regs | Fire services can improve outcomes by seeking input to decisions about siting, design and fire water systems as part of the planning and licensing processes |
REC215-1881 | 35 - Business and Industry in relation to industry | Landfill operators must be encouraged to achieve greater compliance with the required outcomes relating to fire that are set out in the BPEM guidelines, particularly with regard to water supplies |
REC215-1879 | 25 - Inquiry, audit, lessons management and after action review | Regulators can help to achieve improved outcomes by auditing compliance with the BPEM guidelines on a regular basis |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2888 | 35 - Business and Industry in relation to industry | Foster private sector service providers who can offer tailored services or broadcast high quality presentation of general purpose weather information |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
REC205-1903 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should commission an independent public review of disaster prevention and recovery arrangements. This should be broader than the review currently being conducted by the Attorney-General’s Department. The review should cover the Natural Disaster Relief and Recovery Arrangements, as well as the funding mechanisms for disaster mitigation, including the National Partnership Agreement on Natural Disaster Resilience. This review should: |
REC205-1902 | 25 - Inquiry, audit, lessons management and after action review | The Council of Australian Governments should commission an independent public inquiry to develop an appropriate response to managing the risks of climate change to existing settlements. The inquiry should: |
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0427 | 35 - Business and Industry in relation to industry | the state require dam owners and operators provide regular situational reports to the relevant control agency where dam issues may impact incident management. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0426 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform people situated downstream of water storages if the owners/operators become aware of an immediate threat arising from the dam to the safety of those people. The owner/operators should provide this information as soon as the owner/operators become aware of the threat. |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0425 | 35 - Business and Industry in relation to industry | the state require that dam owners and operators inform the control agency and the Bureau of Meteorology about the management and operation of dams and weirs consistent with the flood warning requirements of the relevant river systems, including providing telemetry at sites as necessary. This may require the state proactively liaising with other states to ensure equivalent obligations are placed on interstate dam operators where the dam may impact Victorian communities. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0424 | 35 - Business and Industry in relation to industry | the state require dam owners and operators to review storage operating manuals to incorporate lessons from the 2010–11 floods and make this information publicly available. The manuals should include a clear policy on dam surcharging and pre-release. |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
REC199-0453 | 20 - Role of police | Victoria Police revise coordinator arrangements to ensure: • a coordinator presence is maintained at the place where incident control is being exercised • effective control is established and is maintained until the response phase has concluded • key control roles may be performed by personnel from agencies other than the designated control agency • that the timely compilation and distribution of an appropriate Incident Action Plan is recognised as a fundamental component of establishing effective control • those performing the coordinator role at an Incident Control Centre be suitably trained, skilled and experienced in emergency management and where possible possess a degree of local knowledge of the relevant area; and • that the revised coordinator arrangements are reflected within the State Emergency Response Plan |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1733 | 25 - Inquiry, audit, lessons management and after action review | That a review of the Country Fire Authority Act 1958 and the Country Fire Authority Regulations 2004 be undertaken. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0336 | 20 - Role of police | Victoria Police, under the auspice of the Regional Emergency Response Plan, lead a task force to ensure that the Princes Highway is treated as an asset of significance and an appropriate risk-based approach is adopted to minimise the impact of fire. This approach is to be integrated into regional and municipal fire management plan |
Rec-ID | Code | Recommendation |
---|---|---|
REC188-2915 | 33 - Relief and recovery | The committee recommends that Department of Immigration and Citizenship (DIAC) and its relevant contractors continue to monitor the wellbeing of the survivors and that counselling and support services should be provided for as long as is necessary. |
REC188-2917 | 33 - Relief and recovery | The committee recommends that relevant Commonwealth agencies continue to monitor the wellbeing of their personnel and that counselling and support services should be provided for as long as necessary. |
REC188-2916 | 33 - Relief and recovery | The committee recommends that the Department of Regional Australia and DIAC liaise with the Christmas Island community to explore options for a permanent memorial to be erected on the island, at a site of the residents' choosing, for the victims of the tragedy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0185 | 20 - Role of police | Victoria Police continue to pursue a coordinated statewide approach to arson prevention and regularly review its approach to ensure that it contains the following elements: ■ high-level commitment from senior police; ■ a research program aimed at refining arson prevention and detection strategies; ■ centralised coordination that includes comprehensive training, periodic evaluation of arson prevention strategies and programs, and promotion of best-practice prevention approaches; ■ a requirement that all fire-prone police service areas have arson prevention plans and programs, according to their level of risk. |
REC181-0191 | 1 - Land-use and building regs | The State: ■ amend the Victoria Planning Provisions to require that, when assessing a permit to remove native vegetation around an existing dwelling, the responsible authority and the Department of Sustainability and Environment, as referral authority, take into account fire hazard and give weight to fire protection purposes; ■ develop guidelines for determining the maximum level of native vegetation removal for bushfire risk mitigation, beyond which level the application would be rejected. |
REC181-0200 | 1 - Land-use and building regs | Standards Australia move expeditiously to develop a standard for bushfire sprinklers and sprayers. |
REC181-0160 | 20 - Role of police | The State clarify whether, during major fires, Victoria Police should discharge its coordination functions from the State Emergency Response Coordination Centre or from the State Control Centre. |
REC181-0190 | 1 - Land-use and building regs | The Country Fire Authority amend its guidelines for assessing permit applications for dwellings, nondwellings and subdivisions in the Bushfire-prone Overlay in order to accommodate the amendments to the Wildfire Management Overlay that are implemented as a result of recommendation 39 and make the guidelines available to municipal councils and the public. The revised guidelines should do the following: ■ substantially restrict new developments and subdivisions in those areas of highest risk in the Bushfire-prone Overlay; ■ set out the CFA’s guidelines for assessing permit applications for dwellings, non-dwellings and subdivisions—including the minimum defendable space requirements for different risk levels; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ emphasise the need for enduring permit conditions—in particular, conditions for the creation and maintenance of minimum defendable space to be maintained for the life of the development. |
REC181-0199 | 1 - Land-use and building regs | The State modify its adoption of the Building Code of Australia for the following purposes: ■ to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ to apply bushfire construction provisions to non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities; ■ other than in exceptional circumstances, to apply a minimum AS 3959-2009 construction level of BAL-12.5 to all new buildings and extensions in bushfire-prone areas. |
REC181-0217 | 25 - Inquiry, audit, lessons management and after action review | The State consider the development of legislation for the conduct of inquiries in Victoria —in particular, the conduct of royal commissions. |
REC181-0189 | 1 - Land-use and building regs | The State amend the Victoria Planning Provisions relating to bushfire to ensure that the provisions give priority to the protection of human life, adopt a clear objective of substantially restricting development in the areas of highest bushfire risk—giving due consideration to biodiversity conservation—and provide clear guidance for decision makers. The amendments should take account of the conclusions reached by the Commission and do the following: ■ outline the State’s objectives for managing bushfire risk through land-use planning in an amended state planning policy for bushfire, as set out in clause 15.07 of the Victoria Planning Provisions; ■ allow municipal councils to include a minimum lot size for use of land for a dwelling, both with and without a permit, in a schedule to each of the Rural Living Zone, Green Wedge Zone, Green Wedge A Zone, Rural Conservation Zone, Farming Zone and Rural Activity Zone; ■ amend clause 44.06 of the Victoria Planning Provisions to provide a comprehensive Bushfire-prone Overlay provision. |
REC181-0198 | 1 - Land-use and building regs | The Australian Building Codes Board do the following: ■ amend the performance requirements in the Building Code of Australia to ensure that they incorporate reducing the risk of ignition from ember attack; ■ work with Standards Australia to effect expeditious continuing review and development of AS 3959, Construction of Buildings in Bushfire-prone Areas, and other bushfire-related standards referred to in the Building Code of Australia; ■ negotiate with Standards Australia and SAI Global Ltd an arrangement for free online access to AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, the other Australian standards referred to in AS 3959-2009, and any other bushfire-related Australian standards referred to in the Building Code of Australia; ■ amend the Building Code of Australia to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ include in the Building Code of Australia bushfire construction provisions for non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities. |
REC181-0216 | 25 - Inquiry, audit, lessons management and after action review | The State appoint an independent monitor or the Victorian Auditor-General to assess progress with implementing the Commission’s recommendations and report to the Parliament and the people of Victoria by 31 July 2012. |
REC181-0188 | 1 - Land-use and building regs | The State implement a regional settlement policy that: ■ takes account of the management of bushfire risk, including that associated with small, undeveloped rural lots; ■ includes a process for responding to bushfire risk at the planning stage for new urban developments in regional cities, the process being similar to that used for new developments in Melbourne’s Urban Growth Zone. |
REC181-0197 | 1 - Land-use and building regs | Standards Australia do the following: ■ amend the objective of AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, to ensure that it incorporates reducing the risk of ignition from ember attack; ■ review, and amend as appropriate, the testing methods prescribed in its standards for Tests on Elements of Construction for Buildings Exposed to Simulated Bushfire Attack (AS 1530.8.1 and AS 1530.8.2) to ensure that, so far as is possible, the methods provide a reliable predictor of the performance of construction elements under bushfire conditions. |
REC181-0205 | 1 - Land-use and building regs | The State initiate the development of education and training options to improve understanding of bushfire risk management in the building and planning regimes by: ■ providing regular training and guidance material to planning and building practitioners; ■ providing regular training and guidance material to planning and building practitioners. |
REC181-0196 | 1 - Land-use and building regs | The State develop and implement a retreat and resettlement strategy for existing developments in areas of unacceptably high bushfire risk, including a scheme for non-compulsory acquisition by the State of land in these areas. |
REC181-0203 | 1 - Land-use and building regs | The State amend s. 32 of the Sale of Land Act 1962 to require that a vendor’s statement include whether the land is in a designated Bushfire-prone Area, a statement about the standard (if any) to which the dwelling was constructed, the bushfire attack level assessment at the time of construction (where relevant) and a current bushfire attack level assessment of the site of the dwelling. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0142 | 1 - Land-use and building regs | The Commonwealth consult with local, state and territory government planning authorities on the development and dissemination of a house loss risk index for households in Australia's highest risk bushfire areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3022 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of how to ensure good communication and flow of information between the liquid fuels and other energy sectors. One approach that may be considered is that: |
REC162-3010 | 35 - Business and Industry in relation to industry | Energy Security Working Group (ESWG) recommends consideration be given to government and industry working together to understand that investment opportunities in the energy sector are realised in a timely fashion to better manage potential longer term supply shortfalls. |
REC162-3015 | 35 - Business and Industry in relation to industry | ESWG recommends National Gas Emergency Response Advisory Committee maintain its industry, jurisdiction and consumer representation noting the importance of input from each of these groups in developing its advice. |
REC162-3021 | 35 - Business and Industry in relation to industry | ESWG notes that existing and future contracts and the impending introduction of the Short Term Trading Market will be the primary mechanisms for addressing future gas supply shortfalls. |
REC162-3014 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to leveraging AEMO’s expanded responsibilities in gas markets by undertaking the role of the National Gas Emergency Response Advisory Committee (NGERAC) Secretariat while the Commonwealth continue as Chair, with the Chair’s position to be reviewed once the short term trading market (STTM) commences in June 2010. ESWG also recommends that the review be undertaken by NGERAC jurisdictional members. |
REC162-3020 | 35 - Business and Industry in relation to industry | ESWG recommends that as far as reasonably practical, arrangements for load shedding be as transparent as possible to give consumers confidence in the process. |
REC162-3013 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to consolidating gas and electricity network status and emergency information on one webpage for central communication. |
REC162-3019 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to the spokesperson role AEMO can undertake during an electricity and/or gas supply shortfall in its covered markets and relevant jurisdictional emergencies, noting that AEMO has clear responsibility for the bulk supply of electricity as outlined in the Power System Emergency Management Plan and the Victorian wholesale gas market, and that for multi-jurisdiction gas supply emergencies, any AEMO spokesperson role would be to reflect NGERAC’s advice. |
REC162-3012 | 35 - Business and Industry in relation to industry | ESWG recommends reviewing AEMO’s Gas Bulletin Board (GBB) to ensure it is effectively communicating all publicly available information to market participants to assist in monitoring daily gas supplies, and any changes to the GBB rules required to improve information and awareness of any potential shortages that will assist the market to make the necessary investments and/or adjustments in maintenance. |
REC162-3018 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of a review of communication protocols with the aim of achieving high level policy consistency of communication across jurisdictions to the maximum extent possible. |
REC162-3011 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to expanding the role of AEMO in providing market information on gas by: |
REC162-3017 | 35 - Business and Industry in relation to industry | ESWG notes NGERAC already informally advises ministers on the possible effects of gas emergencies on electricity supplies. ESWG recommends formalising this role by acknowledging it in NGERAC’s MOU. ESWG also recommends an editorial review of NGERAC’s MOU to ensure accuracy and consistency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3030 | 25 - Inquiry, audit, lessons management and after action review | That National Offshore Petroleum Safety Authority review the risk assessment of pipelines. National Offshore Petroleum Safety Authority should focus, in particular, on the efficacy of anti-corrosion systems, and recognise potential interference effects and MAE escalation risks associated with adjacent pipelines and unlicenced pipes even if they fall outside its direct regulatory responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3493 | 35 - Business and Industry in relation to industry | The electricity distribution businesses and retailers work with the Department of Human Services and hospitals to review the registration, notification and removal process for those on life support machinery. |
REC156-3502 | 35 - Business and Industry in relation to industry | The Emergency Services Telecommunications Authority in partnership with Telstra should develop testing regimes that will ensure the integrity of the call queue arrangements and correct configuration of the Recorded Voice Announcements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3466 | 25 - Inquiry, audit, lessons management and after action review | A comprehensive review of the effectiveness of the increased prescribed burning target in meeting ecological and bushfire suppression needs should be conducted every three years. |
REC155-3480 | 1 - Land-use and building regs | That the Integrated Fire Management Planning framework establish zones in the interface between public and private land in which bushfire risk management is the shared responsibility of the Victorian Government and private landholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3182 | 25 - Inquiry, audit, lessons management and after action review | That Biosecurity Australia review that formal import risk analysis at least once every two years to take into account any relevant developments in scientific knowledge—specifically testing methods, vaccines, vaccination procedures and other matters that affect biosecurity. Reports on the reviews should be provided to the officer responsible for the importation of horses and should contain recommendations for any necessary changes to policies for importation. |
REC148-3175 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to review, at least once every two years, the operating procedures to ensure that they adequately identify and manage the risk of entry and spread of equine influenza associated with the importation of horses into Australia. The outcome of each such review should be the subject of a written report and recommendations to the person responsible for the importation of horses and the Executive Director of AQIS. A determination should then be made as to whether any, and if so what, changes should be made to the operating procedures. |
REC148-3170 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to conduct within six months, an inspection and review of the process of horse importation from the time horses arrive in Australia until the completion of their post-arrival quarantine in order to: |
REC148-3167 | 25 - Inquiry, audit, lessons management and after action review | That the facilities at Eastern Creek and Spotswood Quarantine Stations be reviewed by AQIS in consultation with experts in biosecurity and interested parties including state and territory governments, import agents, veterinarians, farriers, operators of private quarantine stations, and representatives of horse owners, horse racing organisations and equestrian organisations. There should in any event be constructed without delay, an adequate supply of hygienic, modern showering facilities and places of entry and exit to the stations and the horse sections of them that can be supervised and monitored continually. There should also be provided at those stations as soon as is practicable suitable means of electronic surveillance, including closed-circuit television; a secure place to store chemicals, drugs, instruments and equipment for use by people attending the quarantined horses, and a set of horse stalls and yards separate from the main stalls and yards to enable isolation of horses suffering from contagious or infectious diseases. These reviews should also consider the desirability of separate areas in quarantine stations to hold horses forming part of a single quarantine intake but that have been imported from different regions or have undergone pre-export quarantine in different places. The reviews should be carried out without delay, and the two quarantine stations should be upgraded in accordance with the recommendations of the reviews. |
REC148-3154 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia or another qualified body to inspect and review the activities and events that occur from the time horses enter pre-export quarantine until the time they arrive at an airport in Australia, in order to identify any biosecurity risks and recommend any necessary changes to import conditions or other requirements. This inspection and review shall be performed without delay for each country or region from which horses are imported to Australia, and it should take account of my other recommendations and comments in this report. |
Rec-ID | Code | Recommendation |
---|---|---|
REC146-3193 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the Australian National Audit Office audit CASA's implementation and administration of its Safety Management Systems approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3222 | 1 - Land-use and building regs | The Committee recommends that the Australian Government: |
REC145-3215 | 1 - Land-use and building regs | The Committee recommends that the Building Code of Australia, including cyclone building codes, be revised with the objective of increasing resilience to climate change. |
REC145-3214 | 1 - Land-use and building regs | The Committee recommends that the Australian Government consider the benefits of adopting a nationally consistent sea level rise planning benchmark and, if so, whether this be done on a statutory basis or otherwise. The outcomes of this consideration should then be included as part of the action plan for the proposed Intergovernmental Agreement on the Coastal Zone. |
REC145-3213 | 1 - Land-use and building regs | The Committee notes the Council of Australian Governments initiative (through the Local Government and Planning Ministers Council) to develop state-specific climate change planning policies by mid 2011, to inform local governments and regional planning responses to climate change. The Committee recommends that the Australian Government ensure that the outcomes of this initiative are included as part of the action plan under the proposed new Intergovernmental Agreement on the Coastal Zone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
REC125-3893 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures that stakeholders (and especially local councils) are fully consulted before and during the development of drainage strategies and plans. These plans should consider councils’ drainage systems. |
REC125-3892 | 35 - Business and Industry in relation to industry | That Melbourne Water ensures stakeholder expectations are fully considered when setting flood risk reduction targets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2102 | 35 - Business and Industry in relation to industry | The Working Group recommends that jurisdictions identify appropriate commercial organisations/bodies able to ensure maintenance of supply of food items and packaged water to commercial outlets in times of disaster. |
REC116-2117 | 33 - Relief and recovery | The Working Group recommends that potential shortfalls in the capacity to deal with large numbers of unprotected children and other special needs groups in a catastrophic event be referred to the Disaster Recovery Sub Committee of Community Services Ministers’ Advisory Council (CSMAC) for consideration and report back. |
REC116-2101 | 35 - Business and Industry in relation to industry | The Working Group recommends that each jurisdiction; |
REC116-2103 | 33 - Relief and recovery | The Working Group recommends that jurisdictions plan for the logistics of supply and delivery of meals to large numbers of homebound persons in an attempt to identify possible ways of resolving existing shortcomings. |
REC116-2122 | 33 - Relief and recovery | The Working Group recommends that States/Territories consider their ability to house large numbers of domestic pets, and where necessary, develop plans and arrangements that facilitate this need. |
REC116-2121 | 35 - Business and Industry in relation to industry | The Working Group recommends that the Australian Government investigate, in consultation with the finance and banking sector, the development of arrangements to ensure that essential transactions can continue in the event of a catastrophic failure of the banking system that includes access to cash. |
REC116-2120 | 33 - Relief and recovery | The Working Group recommends that the National Recovery Coordinators Group considers the issue of emergency relief centres in the context of catastrophic disaster with a view to assisting jurisdictions to plan for the need to accommodate thousands of people following a disaster. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
REC112-3918 | 35 - Business and Industry in relation to industry | That DPI effectively communicates to all sectors of the industry their responsibilities to report new threats, and how to report them. |
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3913 | 35 - Business and Industry in relation to industry | That DPI works with industry to develop a training module on the certification and verification system for inclusion in industry quality assurance programs. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
REC112-3929 | 35 - Business and Industry in relation to industry | That DPI develops a comprehensive strategy for communicating to industry their rights and responsibilities in relation to threats, incursions, outbreaks and post-outbreak; and also for communicating internally. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2282 | 25 - Inquiry, audit, lessons management and after action review | That quality control or performance assessments are routinely completed post fire season, to ensure that contractors who have not performed to an agreed standard are not re-engaged for the consequential rehabilitation works. |
REC104-2307 | 33 - Relief and recovery | That the Victorian Government recommend to the Commonwealth Government that it reviews eligibility for those without employment who may or may not be engaged in an emergency response, and are unable to access the appropriate infrastructure to register for financial assistance. |
REC104-2333 | 25 - Inquiry, audit, lessons management and after action review | That in doing so, this Review must consult with the agencies mentioned above, and others such as VICSES and the Departments of Human Services and Primary Industries. |
REC104-2316 | 33 - Relief and recovery | That the State Emergency Recovery Committee explore opportunities to establish a 'one-stop shop’ approach wherever practicable following emergencies, including a single telephone number to connect a person to all agencies involved in the recovery process. |
REC104-2281 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA work cooperatively to review the management and application of bulldozers in fire suppression operations to ensure that they are used effectively, appropriately and are adequately supervised. |
REC104-2306 | 33 - Relief and recovery | That VicRoads and Municipal Councils review procedures and processes to ensure that the identification and delivery of remedial works on State and Council roads following emergency events are as efficient as possible. |
REC104-2332 | 25 - Inquiry, audit, lessons management and after action review | That the Review of emergency operations centres by the Departments of Premier and Cabinet and Treasury and Finance and the Office of the Emergency Services Commissioner: |
REC104-2314 | 33 - Relief and recovery | That DHS, in conjunction with Local Government, Government departments and the nongovernment sector, modify recovery planning at all levels to include a case management approach supported by an appropriate information system to be activated at the time of an emergency. |
REC104-2277 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review methods of gathering and processing fire information to ensure all methods are pursued to greatest effect. |
REC104-2305 | 33 - Relief and recovery | That DPI actively promote as widely as possible within the community, the agricultural recovery service available during emergencies to ensure that all farmers are aware of the services provided. |
REC104-2293 | 25 - Inquiry, audit, lessons management and after action review | That aviation contractors be required to submit a copy of their annual independent regulatory compliance audit prepared for Civil Aviation Safety Authority to the State Aircraft Unit. |
REC104-2313 | 33 - Relief and recovery | That Government review the emergency relief and financial assistance policy, and develop and communicate a predictable, consistent and equitable policy designed to assist the community to recover from emergencies, including natural disasters. |
REC104-2221 | 35 - Business and Industry in relation to industry | That CFA and the Plantation Industry jointly develop and agree on Fire Prevention Guidelines for Plantations by June 2004, to be then promoted and distributed by the Industry. |
REC104-2228 | 25 - Inquiry, audit, lessons management and after action review | That the Government identifies an appropriate body, or bodies, to undertake the audit of the Municipal Fire Management Plans. |
REC104-2292 | 25 - Inquiry, audit, lessons management and after action review | That a systematic performance audit of State Aircraft Fleet contractors be conducted jointly by agency and SAU personnel. |
REC104-2312 | 33 - Relief and recovery | That all agencies engaged in recovery participate in community briefings prior to and during emergency events, to ensure recovery issues are reinforced and communities are informed of the processes established to assist individuals – including matters that are not the responsibility of Victoria, such as Centrelink payments. |
REC104-2197 | 25 - Inquiry, audit, lessons management and after action review | That a review of the fuel management zones be implemented with a view to reducing the number of zones so as to focus clearly on (i) asset protection (especially at the Public/Private land interface), and (ii) ecological burns. |
REC104-2284 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review the management of personnel deployed ensuring that: |
REC104-2310 | 33 - Relief and recovery | That recovery is recognised as commencing at the same time as response and that recovery planning and delivery is an integral part of the operations of the Municipal Emergency Co-ordination Centres. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2155 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that Emergency Management Australia initiate a process involving Australasian Fire Authorities Council and the Australian Assembly of Volunteer Fire Brigades Association to review |
REC098-2178 | 1 - Land-use and building regs | The Committee recommends that Standards Australia review the clarity of AS3959–1999: Construction of buildings in Bushfire Prone Areas to ensure that all relevant stakeholders can interpret and apply the Standard in the way it is intended. |
REC098-2176 | 1 - Land-use and building regs | The Committee recommends that Standards Australia incorporate building maintenance into AS3959–1999: Construction of buildings in Bushfire Prone Areas, perhaps renaming it as AS3959–1999: Construction and maintenance of buildings in Bushfire Prone Areas. |
REC098-2133 | 1 - Land-use and building regs | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve when asset protection zones will be located on private land and when on public land and gain assurances that adequate maintenance of zones will be enforced. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3258 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
REC061-3423 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that the Metropolitan Fire Brigades Board be reviewed five years from the tabling of this report in Parliament. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3960 | 33 - Relief and recovery | It is recommended that the Forests Commission recognize and provide for the efficient exercise of three major functions, namely those of Commerce, Reclamation and Rehabilitation. |
REC015_3962 | 35 - Business and Industry in relation to industry | It is recommended that the matter be submitted to experts, of which there are many in the Public Service; and that such experts determine the best manner of construction. |