Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4087 | 4 - Fire season preparation | State and territory governments, working with local governments and fire and emergency service agencies, should ensure that there are appropriate arrangements for roadside vegetation management that take into account, among other things: |
REC317-4128 | 37 - Funding | Australian, state and territory governments should broaden Category D of the Disaster Recovery Funding Arrangements to encompass funding for recovery measures that are focused on resilience, including in circumstances which are not ‘exceptional’. |
REC317-4114 | 1 - Land-use and building regs | State, territory and local governments should be required to consider present and future natural disaster risk when making land-use planning decisions for new developments. |
REC317-4119 | 33 - Relief and recovery | The Australian Government, through the mechanism of the proposed standing national recovery and resilience agency, should convene regular and ongoing national forums for charities, non-government organisations and volunteer groups, with a role in natural disaster recovery, with a view to continuous improvement of coordination of recovery support. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4127 | 33 - Relief and recovery | Australian, state and territory governments should incorporate the principle of ‘build back better’ more broadly into the Disaster Recovery Funding Arrangements. |
REC317-4108 | 4 - Fire season preparation | Australian, state and territory governments should review the assessment and approval processes relating to vegetation management, bushfire mitigation and hazard reduction to: |
REC317-4118 | 33 - Relief and recovery | Australian, state and territory governments should create a single national scheme for the regulation of charitable fundraising. |
REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4126 | 33 - Relief and recovery | Australian, state and territory governments should expedite the development of pre-agreed recovery programs, including those that address social needs, such as legal assistance domestic violence, and also environmental recovery. |
REC317-4107 | 4 - Fire season preparation | Public land managers should clearly convey and make available to the public their fuel load management strategies, including the rationale behind them, as well as report annually on the implementation and outcomes of those strategies. |
REC317-4117 | 33 - Relief and recovery | State and territory governments should develop and implement efficient and effective arrangements to: |
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
REC317-4125 | 37 - Funding | Australian, state and territory and local governments should develop greater consistency in the financial support provided to individuals, small businesses and primary producers under the Disaster Recovery Funding Arrangements. |
REC317-4104 | 33 - Relief and recovery | Australian, state and territory governments should refine arrangements to support localised planning and the delivery of appropriate mental health services following a natural disaster. |
REC317-4116 | 33 - Relief and recovery | Governments should create and publish standing policy guidance on whether they will or will not assist to clean-up debris, including contaminated debris, resulting from natural hazards. |
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
REC317-4076 | 12 - EM agency and authority | Australian, state and territory governments should develop an Australian-based and registered national aerial firefighting capability, to be tasked according to greatest national need. This capability should include: |
REC317-4122 | 33 - Relief and recovery | Australian, state and territory and local governments should evaluate the effectiveness of existing financial assistance measures to inform the development of a suite of pre-effective pre-determined recovery supports. |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
REC317-4129 | 37 - Funding | Australian, state and territory governments should create simpler Disaster Recovery Funding Arrangements application processes. |
REC317-4115 | 1 - Land-use and building regs | The Australian Building Codes Board, working with other bodies as appropriate, should: |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4121 | 41 - Emergency Management exercises | Australian, state and territory governments should work together to develop a program for national level recovery exercises, building on the work currently underway through the Community Outcomes and Recovery Subcommittee of the Australia-New Zealand Emergency Management Committee. |
REC317-4071 | 41 - Emergency Management exercises | Australian, state and territory governments should conduct multi-agency, national-level exercises, not limited to cross-border jurisdictions. These exercises should, at a minimum: |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4036 | 12 - EM agency and authority | Government give consideration to investment in professional specialities such as fire behaviour analysts, airbase managers, aerial firefighting technical specialists etc for the RFS. |
REC316-4048 | 37 - Funding | Government consider adopting a similar model to NSW for the management of emergency costs and reimbursements within ACT Government agencies. |
REC316-4023 | 41 - Emergency Management exercises | An opportunity to exercise and test the formation and functioning of a Management Executive through desktop and/or limited scenario-based exercises be provided. |
REC316-4032 | 41 - Emergency Management exercises | Concurrent and/or non–standard emergencies such as energy supply impacts be included in future exercise programs. |
REC316-4047 | 37 - Funding | Government consider an alternative funding arrangement for extraordinary costs borne by Government agencies in combating emergencies such as bushfires. |
REC316-4022 | 12 - EM agency and authority | That when determining their Management Executive, at a minimum the EC should consider appointing Director-General JACS and the PIC as standing members. |
REC316-4031 | 12 - EM agency and authority | The ESA hold bi-lateral executive level meetings with the utility providers on a regular basis in consultation with other relevant Government stakeholders. |
REC316-4046 | 33 - Relief and recovery | Emergency Plan and Recovery sub-plans should be amended to better define recovery mechanisms and responsibilities, including hand over points to recovery authorities and community engagement for the delivery of long term recovery mechanisms. |
REC316-4028 | 41 - Emergency Management exercises | Any changes to the ECC structure and role be exercised both within ESA and across a WHoG exercise and testing program. |
REC316-4040 | 41 - Emergency Management exercises | The PICC be exercised in conjunction with any and all Emergency Plan exercises to test and refine strengthened arrangements. |
REC316-4016 | 12 - EM agency and authority | That the Emergency Plan be amended to include considerations for declaring a State of Alert or Emergency (and also wind back from these) and guidance as to what actions and decisions at a minimum should be taken as a consequence of such a declaration. |
REC316-4027 | 12 - EM agency and authority | All organisations who have a role in the ECC should review their existing arrangements to ensure there is a sufficient cohort of staff to maintain a presence in the ECC at a level and with an imprimatur sufficient to make decisions and allocate resources and have access to senior executive levels if needed. |
REC316-4039 | 12 - EM agency and authority | Establish a Communications Working Group (CWG) with representatives from across key Directorates (CMTEDD, ESA, ACT Policing, Health, CHS, EPSDD for example) to review the CCIP and to further identify how the CCIP can be best implemented and utilised. The CWG should report its progress though SEMSOG and coordinate with other WG’s. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4015 | 12 - EM agency and authority | The working group should report to SEMSOG on progress. |
REC316-4026 | 12 - EM agency and authority | The role, level, requirements and expectations of an ECC LO be clarified in the Emergency Plan and ECC Ops Sub-plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
REC291-1241 | 12 - EM agency and authority | The State Emergency Management Committee, in consultation with Western Australian Farmers Federation, the Association of Bush Fire Brigades, the Contractors Association of WA, and the Forest Industries Federation of WA, to establish systems for the voluntary registration of: · farmer firefighting units; · contractor firefighting resources; and · forestry industry brigades. |
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1212 | 12 - EM agency and authority | Resourcing models appropriate to local needs, including fire risk and remoteness |
REC290-1208 | 12 - EM agency and authority | A unified and integrated fire sector across the whole fire hazard |
REC290-1217 | 12 - EM agency and authority | IAP formats and processes appropriate to the nature of the emergency response. |
REC290-1216 | 12 - EM agency and authority | Resolve reoccurring issues with systems and processes |
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
REC265-1104 | 12 - EM agency and authority | DFES should increase and maintain urban interface bushfire skills and expertise. Appointments to senior roles within the agency should include people with experience and credibility in bushfire firefighting and management. |
REC265-1127 | 33 - Relief and recovery | Consultation should be undertaken with agencies and organisations that are engaged in emergency welfare provision to identify more effective ways to provide a consistent message to the community that non-cash donations are not required. |
REC265-1126 | 33 - Relief and recovery | Development of a template contract for the clean-up of affected properties to speed-up the process; |
REC265-1125 | 33 - Relief and recovery | Consultation with the Board of the Lord Mayor’s Distress Relief Fund and other disaster appeal organisers should be undertaken to determine the potential for software development to consolidate the application and approval process, including provision of templates and application forms; |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2547 | 12 - EM agency and authority | The Civil Aviation Safety Authority establishes small offices at specific industry centres to improve monitoring, service quality, communications and collaborative relationships. |
REC258-2546 | 12 - EM agency and authority | The Civil Aviation Safety Authority changes its organisational structure to a client-oriented output model. |
REC258-2545 | 12 - EM agency and authority | The Australian Transport Safety Bureau transfers its safety education function to the Civil Aviation Safety Authority. |
REC258-2532 | 12 - EM agency and authority | The next Director of Aviation Safety has leadership and management experience and capabilities in cultural change of large organisations. Aviation or other safety industry experience is highly desirable. |
REC258-2558 | 12 - EM agency and authority | The Civil Aviation Safety Authority applies a project management approach to the completion of all Civil Aviation Safety Regulation Parts not yet in force, with drafting to be completed within one year and consultation completed one year later, with: |
REC258-2553 | 12 - EM agency and authority | The Civil Aviation Safety Authority establishes a safety oversight risk management hierarchy based on a categorisation of operations. Rule making and surveillance priorities should be proportionate to the safety risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1558 | 37 - Funding | Funding to state and territory governments for community recovery should be provided as untied grants, with a transition period pending the development of a framework to assess community recovery costs. During the transition period, the Australian Government should continue to provide funding for community recovery through a reimbursement model. |
REC256-1557 | 37 - Funding | Where asset management plans at the local, state or territory level pre-identify and cost betterment of assets (improving asset resilience to natural disasters), the Australian Government should share 50 per cent of the betterment component of reconstruction costs following damage from a (eligible) natural disaster. |
REC256-1577 | 37 - Funding | The Australian Government should develop a formula for allocating mitigation funding to state and territory governments on the basis of where such funding is likely to achieve the greatest net benefits, taking into account the future risks of natural disasters. This should be completed within five years and in consultation with state and territory governments. |
REC256-1556 | 37 - Funding | The Australian Government should fund natural disaster recovery by: |
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
REC256-1560 | 37 - Funding | The Australian Government should: |
REC256-1559 | 37 - Funding | The Australian Government should gradually increase the amount of annual mitigation funding it provides to state and territory governments to $200 million. Initially, this funding should be distributed to state and territory governments in accordance with the allocation under the National Partnership Agreement on Natural Disaster Resilience. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1589 | 12 - EM agency and authority | In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2567 | 12 - EM agency and authority | Western Australia Health should re-engage with St John Ambulance at a senior level to address strategic and complex issues including long term solutions to ramping |
REC252-2564 | 37 - Funding | Western Australia Health should collate and centrally monitor financial data including the cost to government of IHPT |
REC252-2563 | 37 - Funding | Western Australia Health should develop and agree with St John Ambulance a new funding model for emergency ambulance services focusing on standards, performance and allocation of risk |
REC252-2573 | 12 - EM agency and authority | St John Ambulance should build on its regionalisation model and improve engagement with local services in the Kimberley and Pilbara regions |
REC252-2572 | 12 - EM agency and authority | St John Ambulance should explore opportunities for extending the community paramedic model to other areas of identified need |
REC252-2568 | 12 - EM agency and authority | Western Australia Health should develop criteria with St John Ambulance for the allocation of paramedics across the state |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2791 | 37 - Funding | The committee recommends that the government develop a process by which the ATSB can request access to supplementary funding via the minister. |
REC236-2790 | 12 - EM agency and authority | The committee recommends that an expert aviation safety panel be established to ensure quality control of ATSB investigation and reporting processes along the lines set out by the committee. |
REC236-2797 | 12 - EM agency and authority | The committee recommends that all meetings between the ATSB and CASA, whether formal or informal, where particulars of a given investigation are being discussed be appropriately minuted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2812 | 37 - Funding | In order to further build on the value for money review work being undertaken by the National Disaster Recovery Taskforce (on behalf of the Australian Government Reconstruction Inspectorate), the Australian National Audit Office (ANAO) recommends that the Taskforce: |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2824 | 41 - Emergency Management exercises | The Australian Department of Health and Ageing consult with members of the general public or representatives of health consumers in the pandemic planning process, including in pandemic exercises designed to test the ability of government to respond to a pandemic event. Consumer involvement should include testing the ability of any communication strategy designed to inform and engage consumers about a pandemic event. |
REC232-2822 | 41 - Emergency Management exercises | The Australian Government test Australia’s ability to respond to a widespread outbreak of infectious disease other than influenza, by undertaking a pandemic exercise across the relevant Commonwealth, state and territory government agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2835 | 37 - Funding | The committee recommends that the Australian Government direct an appropriate portion of the proceeds derived from the auction of spectrum to fund the allocation of 20 MHz of spectrum in the 700 MHz band for the purposes of a national public safety mobile broadband network. |
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2840 | 39 - Disaster Risk Management | The committee recommends relevant authorities work with community service organisations in both planning responses to and responding to extreme weather events, in particular those organisations that provide vital services to vulnerable groups. |
REC229-2842 | 1 - Land-use and building regs | The committee recommends that building codes incorporate mitigation measures that take into account foreseeable risks from extreme weather events. |
REC229-2841 | 1 - Land-use and building regs | The committee recommends that credible and reliable flood mapping activities and the development of other information that would best inform landowners or prospective landowners of potential risks from extreme weather events are prioritised and used to inform land use planning laws. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1626 | 12 - EM agency and authority | The Emergency Services Agency and the Territory and Municipal Services Directorate should clarify the timing of the requirement for meeting firefighter fitness requirements, as set out in ACT Rural Fire Service operating procedures and the Territory and Municipal Directorate’s Enterprise Agreement, and give priority to meeting that requirement. |
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
REC228-1624 | 12 - EM agency and authority | The Emergency Services Agency should: |
REC228-1619 | 1 - Land-use and building regs | The Territory and Municipal Services Directorate, in consultation with the Emergency Services Agency, should improve its management of Land Management Agreements, with respect to rural leaseholders’ fire management responsibilities, by: |
REC228-1617 | 37 - Funding | The Territory and Municipal Services Directorate should annually (and on a cumulative basis) track and report on funds allocated for, and spent on, its Bushfire Operations Plan to the Minister for Police and Emergency Services. |
REC228-1627 | 12 - EM agency and authority | The Emergency Services Agency (ACT Rural Fire Service headquarters) should implement a system to provide assurance to the Chief Officer of the ACT Rural Fire Service that personnel and equipment readiness meets requirements. |
REC228-1616 | 37 - Funding | The Territory and Municipal Services Directorate should enhance internal monitoring of its implementation of bushfire management activities and spending under the Bushfire Operations Plan by routinely reconciling figures in this plan with those in the Directorate’s corporate financial system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2856 | 12 - EM agency and authority | I recommend that BPC establish an onshore presence as recommended by Lieutenant Commander Livingstone. |
REC227-2854 | 12 - EM agency and authority | I recommend that the Christmas Island VMRS be given autonomy to maintain operational readiness for the VMRS rescue vessel(s) and an appropriate budget be provided to allow this to take place. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0598 | 33 - Relief and recovery | When communities are grieving there is a need to provide special forms of support to affected residents. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0596 | 33 - Relief and recovery | An early decision on relief funding enables timely responses. D CP should review their communication of relief arrangements to ensure that they are clear. |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
REC226-0595 | 33 - Relief and recovery | Shire experiences in managing these traumatic events should be captured and passed into emergency management procedures. |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0594 | 33 - Relief and recovery | Procedures to resolve issues surrounding financial assistance need to be reviewed to ensure they are as smooth, fast and transparent as possible possible. Review and streamline current financial relief procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0520 | 12 - EM agency and authority | The Department of Environment and Conservation review the utility of its current regional model in terms of the capability of operational centres such as Kirup to service major fire activity on land proximate to the rural urban area (this recommendation should also be considered in the context of Recommendation 5). |
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1866 | 12 - EM agency and authority | The State’s emergency response agencies should offer exit interviews to all of their staff and volunteers and use the information they gather to improve their trauma management procedures. |
REC222-1861 | 41 - Emergency Management exercises | The Ministers for Health, Emergency Services, Environment and Police provide additional funds to their agencies so that a detailed exercise is held on a regular basis based on a disaster that will create the worst outcome for the State. |
REC222-1860 | 12 - EM agency and authority | The Minister for Emergency Services and the Minister for Police provide additional resources so that the Fire and Emergency Services Authority and the Western Australia Police can at least double their number of peer support officers, with an aim to increase the number in regional areas of the State. |
REC222-1856 | 37 - Funding | The Ministers for Emergency Services, Environment and Police provide additional funds in the 2013-14 Budget so that the State’s emergency response agencies can implement a Psychological First Aid approach to preparing staff to deal with critical incidents and disasters, as is used in other Australian jurisdictions. |
REC222-1851 | 12 - EM agency and authority | The Ministers for Emergency Services, Environment and Police request their departments to place some of their staff and resources providing trauma-related services in regional Western Australia. |
REC222-1868 | 12 - EM agency and authority | The Fire and Emergency Services Authority, Department of Environment and Conservation and Western Australia Police explore the usefulness of using retired staff as mentors or peer supporters, either directly employed or through a suitable nongovernment organisation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2879 | 37 - Funding | Firm up approval processes and funding for any departures from provision of the basic product set |
REC207-2893 | 37 - Funding | Explore options to obtain revenue from advertising on the Bureau’s website |
REC207-2877 | 37 - Funding | Explore opportunities to re-phase investments in large scale projects and programs such as the Strategic Radar Enhancement Program, the NexGen Forecast and Warning System Products and the Improving Water Information Program. |
REC207-2892 | 37 - Funding | Apply a consistent cost-recovery model to all services delivered to state/territory fire agencies. |
REC207-2890 | 37 - Funding | Review and rebalance relative investment in long term climate modelling and medium-term seasonal outlook. |
REC207-2889 | 37 - Funding | Review level of investment in research activities to free up budget and reduce pressure on computing capacity |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC206-1892 | 37 - Funding | The Committee recommends that the Australian Government allocate additional and continuing funding in the 2012–2013 budget to the Insurance Law Service to establish a consumer advisory position at the Financial Services Ombudsman. The position should be co-funded by the Insurance Law Service and the insurance industry. |
REC206-1891 | 37 - Funding | The Committee recommends that the Australian Government and relevant State and territory governments jointly allocate additional and continuing funding in the 2012–13 budget to the Insurance Law Service for the mobilisation of a temporary physical presence in areas of need following natural disasters. The service should be available to all persons in an affected disaster area and not subject to means-testing. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1919 | 1 - Land-use and building regs | Tourism WA must give specific regard as to whether land use approvals need to be sought, particularly from Department of Regional Development and Lands, when conducting due diligence for event sponsorship proposals that require sign off by both departments. |
REC204-1918 | 1 - Land-use and building regs | Department of Regional Development and Lands and Department of Environment and Conservation should consider how their respective land use approval processes can incorporate the input of Local Emergency Management Committees (LEMCs) as part of risk assessments for high risk events and adventure sport activities. |
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0308 | 33 - Relief and recovery | Early resolution and clear communication of the financial and other support measures that will be available to affected residents is an important contributor to community resilience. |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0295 | 12 - EM agency and authority | There would be benefit in progressively aligning the geographic boundaries of each of the agencies and seeking to co-locate their headquarters within those boundaries. |
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-1725 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-0383 | 12 - EM agency and authority | The State Government restructure the Fire and Emergency Services Authority as a Department. 22 As part of this restructure, Emergency Management Western Australia should either be: 1. clearly separated from the fire and emergency services response function (see figure 2); or 2. moved to the Department of the Premier and Cabinet (see figures 3 and 4) or 3. moved to the Attorney-General’s department (see figures 3 and 5). |
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-0377 | 1 - Land-use and building regs | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0376 | 1 - Land-use and building regs | State and locals governments: a) recognise that regardless of future declarations of bushfire prone areas, the existing planning and building problems in the Perth Hills related to bushfire risk will persist; b) urge residents in these areas to retrofit their homes and evaporative air conditioners in compliance with AS 3959 - 2009; c) examine options to retrospectively bring these areas into compliance with Planning for Bushfire Protection Guidelines. |
REC200-0346 | 1 - Land-use and building regs | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-1707 | 1 - Land-use and building regs | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0373 | 33 - Relief and recovery | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-0389 | 12 - EM agency and authority | The Fire and Emergency Services Authority and local governments ensure that Community Emergency Service Managers are physically based in local government. |
REC200-0340 | 1 - Land-use and building regs | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
REC200-1726 | 41 - Emergency Management exercises | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. |
REC200-0385 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC188-2917 | 33 - Relief and recovery | The committee recommends that relevant Commonwealth agencies continue to monitor the wellbeing of their personnel and that counselling and support services should be provided for as long as necessary. |
REC188-2916 | 33 - Relief and recovery | The committee recommends that the Department of Regional Australia and DIAC liaise with the Christmas Island community to explore options for a permanent memorial to be erected on the island, at a site of the residents' choosing, for the victims of the tragedy. |
REC188-2915 | 33 - Relief and recovery | The committee recommends that Department of Immigration and Citizenship (DIAC) and its relevant contractors continue to monitor the wellbeing of the survivors and that counselling and support services should be provided for as long as is necessary. |
Rec-ID | Code | Recommendation |
---|---|---|
REC185-1931 | 37 - Funding | The committee recommends that the Commonwealth Grants Commission ensures that as part of the current redesign of its data request, state and territory governments are required to include their past insurance and reinsurance receipts for natural disaster insurance premiums. These data must be taken into account by the Commission in determining the states' GST share. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0109 | 1 - Land-use and building regs | It is sensible that, in considering planning development proposals on land adjacent to the DEC estate, that development authorities invite comment from DEC on the fire management consequences of development proposals. |
REC183-0106 | 12 - EM agency and authority | The DEC corporate statement should affirm a strong commitment to fire management. |
REC183-0121 | 12 - EM agency and authority | A DEC fire management staff succession plan would minimise the loss of core fire management skills and experience in the future and provide a planned approach to development of prospective fire management staff. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0135 | 33 - Relief and recovery | FESA revises its standard operating procedures to provide guidance on the format and timing of post-incident community meetings. |
REC182-0130 | 12 - EM agency and authority | FESA identifies and documents its information requirements for end-to-end information exchange and then assess the adequacy of current systems to meet these information requirements. |
REC182-0128 | 12 - EM agency and authority | FESA establishes a process (and associated systems and policies) to mobilise staff to an incident, incorporating pre-formed multi-agency Incident Management Teams. The development of Incident Management Teams should align with the principles of seamless and integrated escalation of command and control arrangements, and be based on a whole of capability approach (people, organisations, systems, training, procedures etc.). |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3337 | 12 - EM agency and authority | Supervision/oversight of well control operations (within licensees, rig operators and by regulators) must occur without assuming adherence to good oilfield practice. The opposite assumption should prevail: namely adherence to good oilfield practice may well be compromised by the pursuit of time and cost savings. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3336 | 12 - EM agency and authority | Achievement and maintenance of well control should be written into the job responsibilities of key personnel, at every level up to and including CEOs. That is, a functional line of accountability for well control must exist up to, and including, CEOs. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3336 | 12 - EM agency and authority | Achievement and maintenance of well control should be written into the job responsibilities of key personnel, at every level up to and including CEOs. That is, a functional line of accountability for well control must exist up to, and including, CEOs. |
REC177-3364 | 37 - Funding | The funding arrangements that support the National Plan should be reviewed to ensure that the costs associated with both preparedness and response capability are equitably shared between the shipping and offshore petroleum industries. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3338 | 12 - EM agency and authority | Licensees and rig operators should be astute in ensuring that corporate systems and culture encourage rather than discourage raising of well control issues. For instance, do performance bonuses or rewards actually encourage or discourage reporting of issues? Is there a system in place to enable anonymous reporting of well control concerns? What whistleblower protections are in place? |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0144 | 37 - Funding | Further Commonwealth funding for bushfire suppression be made conditional on state fire agencies agreeing to the Commonwealth evaluating and auditing their fuel reduction programs. |
REC176-0142 | 1 - Land-use and building regs | The Commonwealth consult with local, state and territory government planning authorities on the development and dissemination of a house loss risk index for households in Australia's highest risk bushfire areas. |
REC176-0140 | 4 - Fire season preparation | The Commonwealth seek agreement from the states and territories that would enable it to evaluate the adequacy of fuel reduction programs applied by public land management agencies in high bushfire risk areas, and audit their implementation against the program's stated objectives. |
REC176-0147 | 5 - Hazard reduction burns | The Commonwealth encourages further research into prescribed burning and its effectiveness and into alternative bushfire mitigation approaches through improved bushfire risk understanding at the asset level. |
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
REC173-0104 | 1 - Land-use and building regs | That FESA assess the cost and other implications of proposed changes to bushfire prone zone declarations which would allow the whole State to be declared bushfire prone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0020 | 12 - EM agency and authority | The role of ‘BFB Task Force Liaison’ be defined and appropriately trained personnel be provided by the HMA (possibly from support brigades) to facilitate brigade movements on and off the fire ground. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0024 | 12 - EM agency and authority | Transport plans for BFB resources should be prepared by the Ground Support Unit in close liaison with FESA who will liaise with the home jurisdictions of the brigades. Moving personnel whilst leaving the equipment at the fire ground staging areas is preferred to moving equipment in and out with every shift. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3016 | 37 - Funding | ESWG recommends investigation of options to fund NGERAC’s on-going activities including through AEMO’s funding model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3034 | 12 - EM agency and authority | That National Offshore Petroleum Safety Authority critically review its regulatory manning levels based on its current workload and the recommendations for additional areas of focus and increased auditing presented in this Report. To meet these requirements, we estimate that National Offshore Petroleum Safety Authority requires up to 50 inspectors in total plus associated support staff to bring overall staffing from about 55 to 75. RET should help facilitate the necessary ongoing levy funding in consultation with industry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3046 | 12 - EM agency and authority | ACT Ambulance Service (ACTAS) should revise its Business Plan to address key priorities and activities for each key service delivery function. This would include clearer expected outputs to be delivered annually and their prioritisation. |
REC159-3054 | 12 - EM agency and authority | ACTAS should improve systems to manage its non-emergency transport services, provide training and guidance to staff on use of these systems, and implement a quality assurance process. |
REC159-3052 | 12 - EM agency and authority | ACTAS should develop and implement as a matter of priority, appropriate strategies to address declining response times. |
REC159-3049 | 12 - EM agency and authority | ACTAS should enhance its approach to demand modelling in order to better guide current and future ambulance resourcing by: |
REC159-3048 | 12 - EM agency and authority | ACTAS should enhance its approach to risk management by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3185 | 37 - Funding | That, until the review of those fees has been completed, the fee charged by the government controlled and operated quarantine stations for thoroughbred stallions temporarily imported into Australia be not be less than $165.00 plus GST a day and the fee for all other horses be not less than $65.00 plus GST a day. No discount is to be allowed for the number of horses in a consignment. |
REC148-3184 | 37 - Funding | That the fees charged in relation to the importation and quarantining of horses be reviewed and fixed without delay having regard to the following factors: |
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
REC148-3177 | 12 - EM agency and authority | That the officer responsible for the importation of horses ensure that: |
REC148-3169 | 37 - Funding | That the budgets for airport reception of horses and government controlled and operated quarantine stations be determined so as to be sufficient to fund the operations of the Quarantine Stations in accordance with these recommendations and any further procedures and requirements that are laid down from time to time. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3189 | 37 - Funding | The ANAO recommends that, to ensure that grant conditions are satisfied, EMA enhance procedures to monitor the progress of projects and follow up those behind schedule or not fulfilling funding agreement requirements. |
REC147-3188 | 12 - EM agency and authority | The ANAO recommends that EMA maintain the Internet site to ensure that material is appropriate, current and readily accessible for users. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3209 | 39 - Disaster Risk Management | The Committee notes that major initiatives relating to climate change adaptation risk assessment and infrastructure are currently in progress. Given that much of Australia’s infrastructure is in the coastal zone and the particular threats facing the coastal zone from climate change, involving significant socioeconomic costs, the Committee recommends that the Australian Government ensure there is a comprehensive national assessment of coastal infrastructure vulnerability to inundation from sea level rise and extreme sea level events. |
REC145-3222 | 1 - Land-use and building regs | The Committee recommends that the Australian Government: |
REC145-3207 | 37 - Funding | To further enhance Australia’s disaster mitigation, preparedness, response and recovery arrangements in the event of possible major coastal disasters, the Committee recommends that the Australian Government establish a grants program, the Coastal Natural Disaster Mitigation Program, to fund natural disaster mitigation projects in the Australian coastal zone. |
REC145-3215 | 1 - Land-use and building regs | The Committee recommends that the Building Code of Australia, including cyclone building codes, be revised with the objective of increasing resilience to climate change. |
REC145-3203 | 39 - Disaster Risk Management | The Committee recommends that: |
REC145-3214 | 1 - Land-use and building regs | The Committee recommends that the Australian Government consider the benefits of adopting a nationally consistent sea level rise planning benchmark and, if so, whether this be done on a statutory basis or otherwise. The outcomes of this consideration should then be included as part of the action plan for the proposed Intergovernmental Agreement on the Coastal Zone. |
REC145-3236 | 37 - Funding | The Committee recommends that the Australian Government provide funding support for the ongoing activities of the Australian Coastal Alliance in providing a national information and communication interface between research organisations and local government authorities and other coastal stakeholders. |
REC145-3200 | 37 - Funding | The Committee recommends that the Australian Government: |
REC145-3213 | 1 - Land-use and building regs | The Committee notes the Council of Australian Governments initiative (through the Local Government and Planning Ministers Council) to develop state-specific climate change planning policies by mid 2011, to inform local governments and regional planning responses to climate change. The Committee recommends that the Australian Government ensure that the outcomes of this initiative are included as part of the action plan under the proposed new Intergovernmental Agreement on the Coastal Zone. |
REC145-3232 | 37 - Funding | The Committee recommends that the Australian Government give consideration to establishing a separate funding program for infrastructure enhancement in coastal areas vulnerable to climate change. Such funding should be provided according to a formula requiring contributions, either financial or in-kind, from state governments and relevant local government authorities. |
REC145-3210 | 39 - Disaster Risk Management | The Committee recommends that the Department of Climate Change, in collaboration with the Queensland Government, CSIRO and Indigenous communities in the Torres Strait, undertake a major study into the vulnerability of the Torres Strait to the impacts of climate change and provide assistance in the development of an adaptation plan. |
REC145-3227 | 39 - Disaster Risk Management | The Committee recommends that coastal based Natural Resource Management bodies seeking funding under the Caring for our Country program have coastal and marine priorities, as well as coastal zone management principles integrated in their management plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3385 | 41 - Emergency Management exercises | The Committee recommends that the ESA hold discussions with NSW with a view to developing a joint exercise program with the NSW Rural Fire Service on an ongoing basis. |
REC144-3384 | 41 - Emergency Management exercises | The Committee recommends that the ESA develop a schedule of proposed exercises as a five year rolling plan, in order that all the elements of emergency services are able to be tested over that time and in differing |
REC144-3400 | 12 - EM agency and authority | The Committee recommends that each element of the Emergency Services Agency publish organisation charts showing names, positions and contact details on the individual webpages. |
REC144-3393 | 1 - Land-use and building regs | The Committee recommends that the responsibility for land management issues lie within a single portfolio, specifically the Minister for Territory and Municipal Services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3588 | 33 - Relief and recovery | That, in line with recommendations contained in the 2004 Report to the Council of Australian Governments, greater flexibility should be introduced to WANDRA to enable damaged infrastructure to be upgraded to a more resilient standard where that is both feasible and cost-effective. |
REC143-3581 | 37 - Funding | That, in tandem with their consideration of local government cost sharing arrangements under WANDRA (refer Recommendation 1), the Fire and Emergency Services Authority and Main Roads Western Australia also establish ‘exceptional circumstances’ criteria to provide for additional assistance to local government where it may be warranted in order to avoid undue financial pressure caused by delays to secure reimbursement. |
REC143-3587 | 12 - EM agency and authority | The secondment of a resource person(s) to an affected local authority to support the work of that authority in its response to a natural disaster be effected. |
REC143-3576 | 37 - Funding | That Fire and Emergency Services Authority of Western Australia and Main Roads Western Australia, in consultation with the Western Australian Local Government Association, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs. In particular consideration should be given to regulations applying in the eastern states i.e. Queensland. |
REC143-3586 | 37 - Funding | That the ‘opportunity cost’ for Local Authorities in meeting the 25% contribution to the restoration of eligible public assets damaged by a natural disaster event be considered when FESA and Main Roads Western Australia, in consultation with Western Australian Local Government Authority, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs as recommended in Recommendation 1. |
REC143-3585 | 33 - Relief and recovery | That the Professional Assistance Grant is formally extended by WANDRA to include non rural businesses and that it be made available to assist with the clean up of disaster related damage to farms and businesses. (The Committee recognises that the amendments to WANDRA as of March 2007 address this recommendation). |
REC143-3583 | 33 - Relief and recovery | That the newly proposed index linked limits for Personal Hardship and Distress Relief Payments as outlined in the paper “National Disaster Relief Arrangements - An Analysis and Recommendations for Personal Hardship Distress Measures” be accepted by government. |
REC143-3589 | 37 - Funding | That consideration be given to the establishment of a ‘Heritage Reserve Fund’ that might underwrite urgent initial repairs to private heritage listed properties. |
REC143-3582 | 37 - Funding | That the Department of Treasury and Finance, in consultation with FESA, consider alternative funding arrangements to alleviate the need for FESA to ‘underwrite’ NDRA costs during the year. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1949 | 12 - EM agency and authority | That the Emergency Services Agency be relocated into accommodation that is purpose-built and more sited to the agency’s operations than the current facility at Curtin |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |
REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-2002 | 1 - Land-use and building regs | That consideration be given when building to the positioning of outbuildings around residential structures such that their potential impact on the main structure is reduced |
REC126-1963 | 12 - EM agency and authority | That priority be given to ensuring that the ACT has an adequate resource of remote area firefighting teams consisting of personnel with high levels of fitness and training in remote fire suppression |
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-2000 | 1 - Land-use and building regs | That the ACT Government consider taking measures to implement the provisions of Australian Standard 3959, Construction of Buildings in Bushfire Prone Areas, for the ACT urban area |
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
REC126-1995 | 12 - EM agency and authority | That the Emergency Services Agency staff the Media Unit within its planning Section with profesisonal, experienced information officers skilled in dissemination of information and media management and liaison |
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3636 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in conjunction with the National Counter-Terrorism Committee’s exercise management advisers, explore options for the incorporation of more contemporary and varied testing and training aids in the National Capability Development Exercise Programme. |
REC117-3634 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter- Terrorism Committee, pursue the adoption of a more strategic approach to determining the National Capability Development Exercise Programme so that: |
REC117-3640 | 37 - Funding | The ANAO recommends that the Attorney-General’s Department better monitor and account for the expenditure of individual exercise costs under the National Capability Development Exercise Programme, through: |
REC117-3639 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the National Counter-Terrorism Committee, strengthens the reporting on the National Capability Development Exercise Programme through: |
REC117-3638 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee: |
REC117-3637 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, pursue a more strategic and systematic approach to the measurement of performance via the National Capability Development Exercise Programme by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2120 | 33 - Relief and recovery | The Working Group recommends that the National Recovery Coordinators Group considers the issue of emergency relief centres in the context of catastrophic disaster with a view to assisting jurisdictions to plan for the need to accommodate thousands of people following a disaster. |
REC116-2103 | 33 - Relief and recovery | The Working Group recommends that jurisdictions plan for the logistics of supply and delivery of meals to large numbers of homebound persons in an attempt to identify possible ways of resolving existing shortcomings. |
REC116-2117 | 33 - Relief and recovery | The Working Group recommends that potential shortfalls in the capacity to deal with large numbers of unprotected children and other special needs groups in a catastrophic event be referred to the Disaster Recovery Sub Committee of Community Services Ministers’ Advisory Council (CSMAC) for consideration and report back. |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2129 | 41 - Emergency Management exercises | The Working Group recommends that Emergency Management Australia and the jurisdictions through the AEMC develop a three year rolling national exercise strategy aimed at testing the response and recovery aspects of large scale disasters. |
REC116-2115 | 41 - Emergency Management exercises | The Working Group recommends that the results of the scenario modeling be presented to the Australian Emergency Management Committee (AEMC) upon completion, and that AEMC form Sub Working Groups of State/Territory emergency management representatives as appropriate to be tasked with considering response and recovery capability (both state/territory and national) against the identified consequences. |
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2122 | 33 - Relief and recovery | The Working Group recommends that States/Territories consider their ability to house large numbers of domestic pets, and where necessary, develop plans and arrangements that facilitate this need. |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2177 | 39 - Disaster Risk Management | The Committee recommends that state and territory governments be required to regularly perform risk assessments to the land within their jurisdictions to ensure that bushfire prone areas are accurately identified |
REC098-2136 | 4 - Fire season preparation | The Committee recommends that the Commonwealth through the National Heritage Trust assist the states and territories in the construction, maintenance and signage of fire trail networks. |
REC098-2158 | 37 - Funding | The Committee recommends that the Commonwealth should commit funding for aerial fire fighting beyond the 2003–04 season on the proviso that the Australasian Fire Authorities Council and the state and territory governments make a commitment to: |
REC098-2176 | 1 - Land-use and building regs | The Committee recommends that Standards Australia incorporate building maintenance into AS3959–1999: Construction of buildings in Bushfire Prone Areas, perhaps renaming it as AS3959–1999: Construction and maintenance of buildings in Bushfire Prone Areas. |
REC098-2133 | 1 - Land-use and building regs | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve when asset protection zones will be located on private land and when on public land and gain assurances that adequate maintenance of zones will be enforced. |
REC098-2150 | 12 - EM agency and authority | The Committee recommends that the Commonwealth seeks to ensure that the proposed Council of Australian Governments review of the bushfire management initiate with the states, as a priority, a review of the |
REC098-2171 | 37 - Funding | The Committee strongly recommends that the New South Wales, Victorian and Tasmanian Governments abolish the Fire Levy tax they impose on home and business insurance premiums (wherever applicable), making it payable through household rates instead. Any cost savings gained by the insurance industry through relief from collecting Fire Levies should be passed on to policyholders through reduced premiums. At the same time the Committee urges the Insurance Council of Australia to run ongoing education campaigns to increase public awareness on bushfire preparedness, including the need for insurance. |
REC098-2142 | 5 - Hazard reduction burns | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek agreement from the states and territories on the optimisation and implementation of prescribed burning targets and programs to a degree that is recognised as adequate for the protection of life, property and the environment. The prescribed burning programs should include strategic evaluation of fuel management at the regional level and the results of annual fuel management in each state should be publicly reported and audited. |
REC098-2169 | 37 - Funding | The Committee recommends that, for the purpose of communications for the police, ambulance and fire brigades, any rental costs associated with the use of radio sites under the care, control or management of the Commonwealth, state, territory or local government be waived, other than for the ongoing cost associated with the use of power at the site. |
REC098-2140 | 12 - EM agency and authority | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments implements arrangements in which greater flexibility is devolved to local brigade captains in the |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2178 | 1 - Land-use and building regs | The Committee recommends that Standards Australia review the clarity of AS3959–1999: Construction of buildings in Bushfire Prone Areas to ensure that all relevant stakeholders can interpret and apply the Standard in the way it is intended. |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4169 | 4 - Fire season preparation | Mitigation and preparedness be enhanced and maintained for the future. Some co—ordinating mechanism or system be introduced at State Government level for this purpose. [Reference paragraphs: 114 to 128] |
REC037-4163 | 12 - EM agency and authority | Effective planning, organisational and training capability be maintained at regional level and developed, as appropriate, for the future. [Reference paragraphs: 260 to 261] |
REC037-4162 | 12 - EM agency and authority | There be a close integration of the responsibilities of the Minister under the State Disasters Act and the State Disaster Plan, thereby strengthening overall counter—disaster management, direction and control. To this end, the organisational arrangements shown in Annexures “J” and “K” should be adopted. The main features of these are: |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4154 | 12 - EM agency and authority | A committee be formed and provided with the finance necessary to enable it to supplement the activities of the local bush fire brigades in districts in the far south-west of the State where ratable values are particularly low and the proportion of Crown lands high, and that the Forests Department be authorised to give approval for control burning of Crown lands throughout the State by bushfire brigades within two miles of a State Forest and that outside this distance the Bush Fires Board through its wardens have similar authority. |
REC019-4138 | 12 - EM agency and authority | That care be exercised in recommending the application of emergency bush fire periods so that they will not be applied to districts where their application is unnecessary. |
REC019-4145 | 37 - Funding | A fund be established to subsidise the purchase of equipment for bush fire brigades but that the granting of subsidies depend upon a certificate being received from the Bush Fires Board that the brigade in question is of a standard that will be available at all times for effective use and that adequate facilities are available for its storage and maintenance at a centre suitable for the brigade. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
REC019-4137 | 12 - EM agency and authority | Before the bush fire season starts, the Minister on the recommendation of the Board nominate a person and a deputy person who will be instructed to take charge of fire fighting operations in each district should a dangerous fire occur and render such an appointment advisable. |
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4150 | 12 - EM agency and authority | The Forests Department direct more staff to the planning and co-ordination of its bush fire control organisation so that emergency conditions can be met immediately by ample reserves of labour and equipment and that co-ordination between the Department, the local authority, sawmills and other sources of man-power and equipment in and around forestry districts is as complete as possible. This particularly includes co-operative protective burning around the boundaries of forest areas. |
REC019-4135 | 12 - EM agency and authority | The Bush Fires Board appoint a Standing Committee of about six of its members, all of whom are likely to be available at any time during the bush fire season to meet and take executive action as necessary. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4134 | 12 - EM agency and authority | All members of the Board be selected for their interest in and experience and knowledge of matters directly associated with bush fire control and not merely as representatives of particular organisations, that the Chairman of the Board be appointed by the Governor instead of being an ex officio appointment of another forester, a member of the timber industry, a police officer and a person with a sound knowledge of weather and its effect upon fire behaviour. |
REC019-4159 | 12 - EM agency and authority | The State Emergency Service be used to meet any additional needs but that as far as possible, requests for assistance be directed in the first instance to the Bush Fires Board or at least referred to that Board by the State Emergency Service for advice before action is taken. |
REC019-4141 | 12 - EM agency and authority | The relative seniority of bush fire control officers be determined with a view to appointing group leaders as chief bush fire control officers. The Shire Clerk should generally be a liaison bush fire control officer rather than a chief fire control officer. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4155 | 12 - EM agency and authority | The management of all National Parks in the State be concentrated under one authority to ensure co-ordination in administration and protective measures. |
REC019-4140 | 12 - EM agency and authority | Local authorities select bush fire control officers for their knowledge and experience of bush fires and their qualities of leadership and that as far as practicable, they be captains of bush fire brigades so that the person issuing the permit to burn has the responsibility of extinguishing the fire if it escapes. |
REC019-4147 | 12 - EM agency and authority | All local authorities form advisory committees of persons from bush fire brigades and of bush fire control officers to plan co-operation in effort and co-ordination between brigades, to group brigades under brigade group officers and to advise the local authority upon all matters of fire control, including the planning of the district firebreak layout and prosecuting for breaches of the Bush Fires Act. |