Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4205 | 26 - Research | We recommend that DELWP in partnership with Parks Victoria, Country Fire Authority, Fire Rescue Victoria and councils as appropriate, collect empirical evidence after bushfire events to assess the effectiveness of different fuel management treatments, including planned burning, mulching, slashing and mineral earth breaks, and build an evidence base to the effectiveness of these treatments. |
REC321-4207 | 25 - Inquiry, audit, lessons management and after action review | We recommend that DELWP reviews its target for the number of fuel hazard assessments conducted and ensures that this measure is evidence based, accurately reflects regional performance, and that the department monitors and reports on each region’s performance against it. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4048 | 37 - Funding | Government consider adopting a similar model to NSW for the management of emergency costs and reimbursements within ACT Government agencies. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4047 | 37 - Funding | Government consider an alternative funding arrangement for extraordinary costs borne by Government agencies in combating emergencies such as bushfires. |
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3812 | 25 - Inquiry, audit, lessons management and after action review | That Government commit to: |
REC315-3818 | 26 - Research | That, in order to improve understanding of optimal hazard reduction techniques and their application in the landscape: |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3798 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure recommendations accepted by the Government are implemented in a timely and transparent manner, Government establish a central accountability mechanism to track implementation of recommendations from bush fire-related reviews and inquiries and consider expanding this to other policy areas. |
REC315-3802 | 26 - Research | That Government establish NSW as a major world centre of bush fire research, and technology development and commercialisation. This should include: |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3873 | 25 - Inquiry, audit, lessons management and after action review | That Resilience NSW review existing functional area arrangements to ensure they are closely aligned to agencies responsible for direct service delivery. |
REC315-3860 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure the guiding principles and approval processes are contemporary, streamlined and more flexible, the NSW and Commonwealth Governments review the Defence Assistance to the Civil Community (DACC) arrangements. This review should include the circumstances in which the State can request Commonwealth assistance, and the level of information provided by the ADF to the State on available resources and capabilities. |
REC315-3859 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure State Emergency Operations Centre (SEOC) interoperability during all natural disasters, Resilience NSW review the current SEOC arrangements and location including responsibilities for ongoing resourcing and maintenance. |
REC315-3845 | 26 - Research | That Government commission further research on the potential risks and benefits of backburning during severe, extreme and catastrophic conditions and/or in particular terrain, and that the NSW RFS use this research to inform future backburning protocols and training. |
REC315-3809 | 37 - Funding | That Government work with other Australian governments to provide long-term funding certainty to AFAC, including the National Resource Sharing Centre (NRSC) and the National Aerial Firefighting Centre (NAFC). |
REC315-3858 | 25 - Inquiry, audit, lessons management and after action review | That, in order to improve cross-agency communication and coordination during bush fires, the NSW RFS review Fire Control Centres (FCCs) in areas that were heavily affected by fire. The results should be combined with the Emergency Operations Centre (EOC) Facilities Review to identify areas that would benefit from a purpose-built FCC, enabling co-location with the EOC. |
REC315-3831 | 26 - Research | That, in order to capture and understand the impacts of bush fire smoke better, Government invest in operational air quality forecasting and alert systems, and public health research and policy development. This would involve investment to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2508 | 25 - Inquiry, audit, lessons management and after action review | Regularly reviewing these plans to ensure that they reflect the current operating environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2423 | 37 - Funding | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning as a matter of priority, establish what funding is reasonably required and complete all elements of the Brisbane River Catchment Flood Studies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2339 | 19 - Offences | I recommend that the Law, Crime and Community Safety Council develop a mechanism to ensure that all information on criminal history (including bail) that is relevant to the investigation and prosecution of criminal offences is readily accessible to police and prosecutors across all Australian jurisdictions. |
REC292-2370 | 25 - Inquiry, audit, lessons management and after action review | I recommend that the New South Wales Police Force undertake a formal assessment of alternatives to the TOU’s current soft-point ammunition to determine whether a more appropriate form of ammunition is reasonably available. |
REC292-2369 | 26 - Research | I recommend that the New South Wales Police Force evaluate whether the use of noise-attenuation devices should be mandated when explosive distraction devices are used. |
REC292-2360 | 2 - Emergency powers | I recommend that the Commissioner of Police consider seeking an agreement with news media outlets whereby the New South Wales Police Force will establish a way for such outlets to rapidly and confidentially determine whether publishing specific material could compromise the response to an ongoing high-risk incident and the media in turn will agree not to publish such material without first alerting a nominated senior police officer of their intention to do so. |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1194 | 37 - Funding | The Committee recommends the State Fire Commission be fully reimbursed for the costs of the State Emergency Service transfer in years 2014 to 2017. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2092 | 26 - Research | Investigate usefulness of satellite data for PPRR (prevention, preparedness, response, recovery) planning. |
REC286-1468 | 39 - Disaster Risk Management | Identify and anlalyse the location of critical infrastructure within defined flood areas. |
REC286-2091 | 37 - Funding | Investigate the costs and benefits in enhancing the current Tsunami detection buoy network. |
REC286-1480 | 26 - Research | Deliver Flood Studies. |
REC286-2024 | 26 - Research | Improve knowledge and understanding of the effect heatwaves coinciding with other hazard events have on the effectiveness and capability of response and recovery capabilities |
REC286-1448 | 39 - Disaster Risk Management | Utilise coastal mapping to assess need for coastal defences. |
REC286-2081 | 39 - Disaster Risk Management | Engage with industry bodies to explore opportunities to better understand and manage risks. |
REC286-1442 | 25 - Inquiry, audit, lessons management and after action review | Review legislation relating to Fuel Stove only areas, Fire Permit System and Total Fire Bans to ensure appropriate incentives to modify individuals’ behaviour. |
REC286-2090 | 26 - Research | Increase understanding of the Puysegur Trench dynamics to improve certainty around the likelihood and magnitude of future Tsunamis. |
REC286-1463 | 39 - Disaster Risk Management | Develop enablers and capacity for Tasmanian earthquake risk owners. |
REC286-1457 | 26 - Research | Improve understanding of how coastal inundation events interact with riverine flood events. |
REC286-1447 | 39 - Disaster Risk Management | Assess vulnerability of ecosystems and species to coastal inundation. |
REC286-2066 | 39 - Disaster Risk Management | Advocate for an National Notifiable Diseases Database. |
REC286-1438 | 25 - Inquiry, audit, lessons management and after action review | Consider outcomes of national review of warnings and review resilience of warning systems’ infrastructure. |
REC286-2079 | 26 - Research | Develop capacity to utilise the new high-resolution satellite products now available. |
REC286-1461 | 39 - Disaster Risk Management | Review all hazards response and recovery plans to ensure they address likely earthquake consequences. |
REC286-1456 | 26 - Research | Improve understanding of the weather systems that cause storm surge events to improve predictability and warnings. |
REC286-2070 | 25 - Inquiry, audit, lessons management and after action review | Test the Biosecurity Act 2015. |
REC286-2095 | 37 - Funding | Investigate the costs and benefits of delivering a public education and awareness program. |
REC286-2056 | 39 - Disaster Risk Management | Review Ambulance Tasmania surge capacity. |
REC286-2048 | 26 - Research | Conduct research into changes of owners’ and occupiers stated and revealed risk tolerance and preference for treatment measures before and after natural hazard events. |
REC286-1455 | 39 - Disaster Risk Management | Assess options for managed coastal retreat. |
REC286-1478 | 39 - Disaster Risk Management | Review environmental risks associated with hazardous uses within flood prone areas. |
REC286-2093 | 37 - Funding | Investigate the costs and benefits in enhancing the current Tsunami warning arrangements with signage and audible warning systems at key exposed locations (e.g. Port Arthur and Kingston Beach). |
REC286-2049 | 39 - Disaster Risk Management | Pro-actively manage landslide areas. |
REC286-2045 | 26 - Research | Investigate the potential effectiveness of economic and financial mechanisms to manage the risk appetites of land owners. |
REC286-1452 | 39 - Disaster Risk Management | Improve understanding of the allocation of ownership across government, business and individuals. |
REC286-1469 | 39 - Disaster Risk Management | Actively manage riparian vegetation to manage flood dynamics. |
REC286-2092 | 37 - Funding | Ensure sufficient investment in controls across the PPRR spectrum with a focus on Prevention and Mitigation. |
REC286-2017 | 39 - Disaster Risk Management | Improve maintenance of flood mitigation infrastructure. |
REC286-2032 | 26 - Research | Quantify the effect of heatwaves on vulnerable people. |
REC286-1450 | 39 - Disaster Risk Management | Improve the understanding of the vulnerability of critical infrastructure. |
REC286-2089 | 39 - Disaster Risk Management | Identify and analyse statewide storm hazard risk. |
REC286-1460 | 25 - Inquiry, audit, lessons management and after action review | Review seismic monitoring network alert systems to ensure emergency managers are on the contact lists. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2524 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate why the level of multiple responses had increased. |
REC285-2520 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate whether the additional resources in the North and North West regions were effective in reducing average response times. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1405 | 37 - Funding | That the Department of Justice & Regulation broadens Budget Paper 3 response time measures to more comprehensively cover emergency responses to fires, rescues and other emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1415 | 25 - Inquiry, audit, lessons management and after action review | An audit of all local government areas vulnerable to storm tide events is completed and opportunities identified to resolve gaps in evacuation zone planning to ensure consistency with the Queensland Evacuation Guidelines for Disaster Management Groups and neighbouring local government areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1522 | 26 - Research | Banana Shire Council investigate means to prioritise the commissioning of a fit-for-purpose flood study for high-risk areas across the Banana Shire to better inform flood risk management, including improved town planning. The outcomes of such a study should be available to the public and inform flood awareness campaigns, flood warnings, and building approvals. |
REC271-1521 | 26 - Research | The Department of Energy and Water Supply and SunWater, undertake the necessary studies to determine whether or not it is feasible to operate Callide Dam as a flood mitigation dam. Such studies should include matters in relation to, but not limited to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1429 | 2 - Emergency powers | A dynamic online list of positions and contact details is published for those able to authorise Emergency Alert, and made accessible to local government. |
REC268-1424 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Emergency Alert Guidelines is reviewed to reflect current practice and incorporate evidence-based improvements informed by lessons learned and research. |
REC268-1430 | 26 - Research | Formal research is commissioned or meta-analysis is undertaken to provide a better understanding of the effectiveness of warnings and other relevant message testing. The outcomes are disseminated to all disaster management entities and learnings used to inform practice. |
REC268-1422 | 25 - Inquiry, audit, lessons management and after action review | The Queensland State Disaster Management Plan is reviewed to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1054 | 2 - Emergency powers | That the Rural Fire Service consider extending pre-emptive section 44 to whole of Castlereagh RFS/Warrumbungle Shire area. |
REC260-1058 | 28 - Personal responsibility | That NPWS and the RFS consider developing a land management policy that requires active engagement with property owners adjoining the Park to ensure that hazard reduction and asset protection is encouraged and undertaken before the bush fire season commences |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2563 | 37 - Funding | Western Australia Health should develop and agree with St John Ambulance a new funding model for emergency ambulance services focusing on standards, performance and allocation of risk |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2564 | 37 - Funding | Western Australia Health should collate and centrally monitor financial data including the cost to government of IHPT |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0788 | 25 - Inquiry, audit, lessons management and after action review | TFS seek to address the following outstanding items from the recommendations of the Victorian Bushfires Royal Commission. § 45 out of 53 Community Bushfire Response Plans for “at risk” communities have been finalized. The remaining eight should be completed as a priority action. § That TFS progress the development of Community Bushfire Mitigation Plans for the 53 at risk communities, possibly as an action for reactivated Fire Management Area Committees. § TFS, together with other ESOs and local government, should develop a common comprehensive approach to the option of planned evacuation from dangerous or potentially dangerous areas to safer areas and eventual return. § TFS should include factors for consideration for evacuation during a bushfire into their training doctrine for Incident Controllers. § The IAP Template and its application be reinforced as an important operational requirement for IMT’s during the 2013-14 pre-season briefing program. 10 § That TFS review their use of IRMS to ascertain if either its full potential is not being realized through a lack of operator training or it is in fact not providing the required functionality and there is a need to research an improved resource management system which enhances interoperability. § The TFS Publication: Guidelines for Development in Bushfire Prone Areas of Tasmania http://www.fire.tas.gov.au/userfiles/stuartp/file/Publications/BushDeve… s2012.pdf requires an update to reflect the provisions of Planning Directive #5 Bushfire-Prone Areas Code. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2592 | 37 - Funding | That duplication of infrastructure be costed and taken into account when considering whether to proceed with the Whole of Government network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-1035 | 37 - Funding | That the State Government contribution towards the purchase of operational vehicles is to be retained at 80 percent but that the District Inspector can recommend full Government subsidy of vehicles for Brigades experiencing financial hardship. |
REC241-1034 | 37 - Funding | That the State Government contribution towards the construction of Brigade sheds be changed from $10,000 to a maximum of 25 percent, subject to the approval of the Deputy Chief Officer, Rural Fire Service Queensland. |
REC241-1033 | 37 - Funding | When a local Rural Fire Brigade requests an equipment and maintenance levy from a local government authority, that authority will either supply the brigade’s equipment and maintenance costs or raise the requested levy. The amount to be collected is to be agreed between the local Brigade and the local government authority. |
REC241-0999 | 28 - Personal responsibility | That on all land where fuel load creates a fire risk, the owner shall be responsible for the construction and maintenance of effective firebreaks. Failure to provide effective and accessible firebreaks will result in the cost of firebreak construction to control a wildfire on this land being debited to the land owner |
REC241-1032 | 37 - Funding | That the current Urban Fire Levy be changed to the Queensland Fire Levy. |
REC241-0967 | 26 - Research | That a Rural Fire Research and Investigation Team be established to coordinate and communicate fire research knowledge, including fire behaviour as well as coordinate fire investigations and complaints for the state. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2654 | 26 - Research | That the Department of Health determines the underlying causes for the rapid growth in demand for Queensland Ambulance Service emergency responses and implements strategies to address these causes and reduce the cost per head of population to service this demand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2812 | 37 - Funding | In order to further build on the value for money review work being undertaken by the National Disaster Recovery Taskforce (on behalf of the Australian Government Reconstruction Inspectorate), the Australian National Audit Office (ANAO) recommends that the Taskforce: |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1620 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the Territory and Municipal Services Directorate, should review the Farm FireWise Program, including: |
REC228-1617 | 37 - Funding | The Territory and Municipal Services Directorate should annually (and on a cumulative basis) track and report on funds allocated for, and spent on, its Bushfire Operations Plan to the Minister for Police and Emergency Services. |
REC228-1614 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the ACT Bushfire Council, should conduct a review of the ACT Bushfire Council against its recently developed terms of reference (July 2013) within two years. |
REC228-1616 | 37 - Funding | The Territory and Municipal Services Directorate should enhance internal monitoring of its implementation of bushfire management activities and spending under the Bushfire Operations Plan by routinely reconciling figures in this plan with those in the Directorate’s corporate financial system. |
REC228-1609 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency should undertake audits to meet the requirements in the Strategic Bushfire Management Plan for the preparation, sharing and publication of annual progress reports. Annual progress reports should be made available to the ACT Bushfire Council. |
Rec-ID | Code | Recommendation |
---|---|---|
REC221-2860 | 19 - Offences | Housing should ensure it has sound systems, processes and controls in place that minimise the opportunity for fraud and gives it the best chance of detecting it by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0221 | 37 - Funding | Funding be sought to enable the State Fire Management Council to take a greater coordination role for bushfire risk management and mitigation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0062 | 25 - Inquiry, audit, lessons management and after action review | Agencies should: annually assess their capability to respond to emergencies and take measures to address any shortfalls |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3009 | 25 - Inquiry, audit, lessons management and after action review | That the Tasmania Fire Service conduct an audit of all shopping centres to ensure that there exists within those centres adequate fire protection and evacuation systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3016 | 37 - Funding | ESWG recommends investigation of options to fund NGERAC’s on-going activities including through AEMO’s funding model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3058 | 25 - Inquiry, audit, lessons management and after action review | ACTAS should improve patient care processes by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1776 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to establish means by which risk of bushfires, as created by continuous cropping, minimum tillage, direct drilling seeding practices and the retention of cropping stubble across the landscape, can be minimised. |
REC153-1775 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to identify the effects of continuous cropping, minimum tillage, direct drilling seeding practices and of the retention of cropping stubble, in respect of bushfire risk and prevention. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3189 | 37 - Funding | The ANAO recommends that, to ensure that grant conditions are satisfied, EMA enhance procedures to monitor the progress of projects and follow up those behind schedule or not fulfilling funding agreement requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1952 | 25 - Inquiry, audit, lessons management and after action review | That regular periodic reviews be undertaken of changes made to the operational and management arrangements for dealing with wildfires and other emergencies in the ACT, to ensure that those arrangements continue to comply with the Australian Inter-Agency Incident Management System Incident Control System |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1947 | 25 - Inquiry, audit, lessons management and after action review | That the ACT Government commission a review of coroners’ jurisdiction in order to determine whether that jurisdiction ought to be limited or expanded and, if so, to what extend |
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-2011 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the recommendations of the seven reviews of the Emergency Services Bureau carried out before the McLeod inquiry and ensure implementation of any of those recommendations that remain relevant but have not been implemented |
REC126-2010 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the extent to which the recommendations in the McLeod report have been implemented in order to ensure implementation of those not yet implemented |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3649 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3640 | 37 - Funding | The ANAO recommends that the Attorney-General’s Department better monitor and account for the expenditure of individual exercise costs under the National Capability Development Exercise Programme, through: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
REC116-2113 | 26 - Research | The Working Group recommends support for ongoing research into natural hazard risks and an improved understanding of emergency management capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3934 | 37 - Funding | That DPI prepares guidelines, both internally and externally with Treasury, about funding arrangements for an outbreak. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |
REC111-3939 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the State Disaster Management Group and the Department of Emergency Services review the current disaster district boundary framework and its relevance to the regional boundaries established by other public sector lead entities to ensure that resources within the Disaster Management System are economically, efficiently and effectively allocated across Queensland. |