Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
REC317-4107 | 4 - Fire season preparation | Public land managers should clearly convey and make available to the public their fuel load management strategies, including the rationale behind them, as well as report annually on the implementation and outcomes of those strategies. |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4121 | 41 - Emergency Management exercises | Australian, state and territory governments should work together to develop a program for national level recovery exercises, building on the work currently underway through the Community Outcomes and Recovery Subcommittee of the Australia-New Zealand Emergency Management Committee. |
REC317-4071 | 41 - Emergency Management exercises | Australian, state and territory governments should conduct multi-agency, national-level exercises, not limited to cross-border jurisdictions. These exercises should, at a minimum: |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
REC317-4120 | 16 - Training and behaviour | Australian, state and territory governments should establish a national mechanism for sharing of trained and qualified recovery personnel and best practice during and following natural disasters. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4087 | 4 - Fire season preparation | State and territory governments, working with local governments and fire and emergency service agencies, should ensure that there are appropriate arrangements for roadside vegetation management that take into account, among other things: |
REC317-4115 | 1 - Land-use and building regs | The Australian Building Codes Board, working with other bodies as appropriate, should: |
REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4114 | 1 - Land-use and building regs | State, territory and local governments should be required to consider present and future natural disaster risk when making land-use planning decisions for new developments. |
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4108 | 4 - Fire season preparation | Australian, state and territory governments should review the assessment and approval processes relating to vegetation management, bushfire mitigation and hazard reduction to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
REC291-1242 | 15 - Inter-service cooperation | The Departments of Fire and Emergency Services and Parks and Wildlife to investigate and adopt an emergency services resource management system that will enable the registration, tasking, tracking, management and coordination of emergency management personnel, vehicles, plant and aircraft. |
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
REC290-1210 | 15 - Inter-service cooperation | Co‐designed arrangements that support a unified response to fire |
REC290-1209 | 15 - Inter-service cooperation | Coordinated and targeted mitigation of fire risk |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC276-1178 | 16 - Training and behaviour | Within six months, consider improved processes for consulting with and engaging volunteers and continue to work with LGs to improve information sharing and communication. Specifically, DFES should improve communication around its decisions on equipment and training as well as provide better information about access to services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1105 | 15 - Inter-service cooperation | The Executive Teams of both DFES and DPaW should meet quarterly to review and agree joint improvements relating to issues of interoperability, complementarity and the alignment of firefighting doctrine. The establishment of a unified command in joint State Operations Centre, Regional Operations Centre and Incident Management Teams should be pursued as an overarching goal. |
REC265-1115 | 16 - Training and behaviour | Training and awareness raising should be conducted to enhance the appreciation and understanding of DFES State and Regional operational personnel, including potential Incident Management Team members, of the nationally adopted Bushfire Alert and Messaging Matrix, in order to ensure that the most appropriate alert levels and associated community messaging are applied during bushfire incidents. |
REC265-1103 | 16 - Training and behaviour | DFES should review its training courses and Standard Operating Procedures to satisfy itself that all incident management personnel have the required level of understanding of WA emergency management arrangements, including those that relate to the roles of the Incident Management Team and Incident Support Group and the declaration of incident levels. |
REC265-1111 | 15 - Inter-service cooperation | All agencies engaged in bushfire response should develop expeditious procedures for the mobilisation of resources in support of other agencies. See discussion in Section 7.1. |
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
REC265-1106 | 15 - Inter-service cooperation | In addition to regular meetings of the DFES/DPaW Interagency Bushfire Management Committee, the two organisations should use joint exercises to identify agreed firefighting approaches for common or likely scenarios. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2559 | 15 - Inter-service cooperation | The Civil Aviation Safety Authority’s Director of Aviation Safety meet with industry sector leaders to jointly develop a plan for renewing a collaborative and effective Standards Consultative Committee. |
REC258-2542 | 16 - Training and behaviour | The Civil Aviation Safety Authority publishes and demonstrates the philosophy of ‘just culture’ whereby individuals involved in a reportable event are not punished for actions, omissions or decisions taken by them that are commensurate with their experience and training. However, actions of gross negligence, wilful violations and destructive acts should not be tolerated. |
REC258-2541 | 16 - Training and behaviour | The Civil Aviation Safety Authority finalises its Capability Framework and overhauls its training program to ensure identified areas of need are addressed, including: |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2534 | 16 - Training and behaviour | The Civil Aviation Safety Authority develops a staff exchange program with industry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1545 | 15 - Inter-service cooperation | Range Control Officer Marrangaroo Training Area liase with the local Rural Fire Service units to develop a map indicating the areas of the range likely to contain unexploded ordnance. |
REC257-1540 | 16 - Training and behaviour | Commanding Officer Defence Explosive Ordnance Training School, assisted by Joint Logistics Command Regional Explosive Ordnance Serices staff, conduct explosive ordnance accounting training for all instructional staff as a matter of priority and that such training be conducted for Defence Explosive Ordnance Training School staff on an annual basis. |
REC257-1536 | 16 - Training and behaviour | The Australian defence Force Explosive Ordnance Disposal course be reviewed by Manager Joint Training - Air Force, to ensure the assessments meet the learning outcomes specificed in the relevant Training Management Package. |
REC257-1555 | 14 - Incident Mgt Teams | The lines of responsibility be made clearer and some individual, perhaps the Regional Environmental Officer, or agency be given overarching responsibility to ensure recommended works related to bushfire mitigation on Defence Estate are carried out in accordance with the Bushfire Management Plan which the Manual for Fire Protection Engineering directs be prepared. |
REC257-1547 | 15 - Inter-service cooperation | The Marrangaroo Training Area Regional Environmental Officer confer with the local Rural Fire Service at least annually and determine a hazard reduction regime capable of implementation. It is furter recommended all ranges be reviewed in relation to the same issue, that is, that personnel involved in the management of each range under Defence control be directed to confer with local firefighting authorities on at least an annual basis to assess hazard reduction responses to be pursued for that range in subsequent years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
REC254-1583 | 16 - Training and behaviour | Once Recommendation 1 has been actioned, all agencies give greater priority to the promulgation of Red Flag warnings in order to enhance situational awareness on the fireground. |
REC254-1581 | 16 - Training and behaviour | All agencies ensure fire managers are trained to correctly interpret the new Spot Fire Weather Forecast and to familiarise themselves with the entire format – ensuring consideration of the whole forecast - not just the tabular data containing the 12 hour forecast. |
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1586 | 15 - Inter-service cooperation | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2788 | 16 - Training and behaviour | The committee recommends that, as far as available resources allow, ATSB investigators be given access to training provided by the agency's international counterparts. Where this does not occur, resultant gaps in |
REC236-2787 | 16 - Training and behaviour | The committee recommends that the training offered by the ATSB across all investigator skills sets be benchmarked against other agencies by an independent body by, for example, inviting the NTSB or commissioning an industry body to conduct such a benchmarking exercise. |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1594 | 35 - Business and Industry in relation to industry | When businesses review their business continuity plans they should take into account the prospect of a major telecommunications outage that affects both mobile and fixed voice and data services. |
REC233-1600 | 35 - Business and Industry in relation to industry | Community service providers consider, in consultation with relevant government authorities, reviewing their current privacy practices concerning personal information about vulnerable persons to ensure they are able to appropriately share information during major disruptive incidents. |
REC233-1593 | 35 - Business and Industry in relation to industry | Telstra and other service providers to consider improving processes to assist customers with setting up temporary call diversions during future outages. |
REC233-1599 | 35 - Business and Industry in relation to industry | Providers of personal alert devices consider telecommunications outages in their service continuity plans and provide clear advice to their customers regarding their options during a telecommunications service outage. |
REC233-1591 | 35 - Business and Industry in relation to industry | While noting the importance of voice communications, telecommunications providers should consider as part of their mass outage business continuity planning, options for the provision of interim mobile broadband services for the community e.g. local wireless broadband access hubs (i.e. Wi-Fi). |
REC233-1598 | 35 - Business and Industry in relation to industry | Community service providers consider developing information and advice regarding telecommunications outages for clients managed remotely using telecommunication services, including personal alert devices. |
REC233-1597 | 35 - Business and Industry in relation to industry | Community service providers consider updating their business continuity plans to take into account the possibility of a major telecommunications outage involving both fixed and mobile voice and data services. |
REC233-1595 | 35 - Business and Industry in relation to industry | Department of Broadband, Communications and the Digital Economy to work with the Trusted Information Sharing Network’s Communications Sector Group to develop general telecommunications continuity advice for businesses and individuals to assist in developing continuity plans. |
REC233-1601 | 35 - Business and Industry in relation to industry | Community service providers consider in their business continuity planning how they could assist with facilitating access to telecommunications services for the public during mass outages. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2824 | 41 - Emergency Management exercises | The Australian Department of Health and Ageing consult with members of the general public or representatives of health consumers in the pandemic planning process, including in pandemic exercises designed to test the ability of government to respond to a pandemic event. Consumer involvement should include testing the ability of any communication strategy designed to inform and engage consumers about a pandemic event. |
REC232-2822 | 41 - Emergency Management exercises | The Australian Government test Australia’s ability to respond to a widespread outbreak of infectious disease other than influenza, by undertaking a pandemic exercise across the relevant Commonwealth, state and territory government agencies. |
REC232-2818 | 16 - Training and behaviour | The Royal Australian College of General Practitioners provide resources and training to general practitioners on the complex health needs of migrants and refugees, with a focus on identifying infectious diseases which are notifiable in Australia, or diseases which are of specific concern to refugee and migrant communities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2844 | 15 - Inter-service cooperation | The committee recommends that Australian governments specifically address issues of compatibility and capacity to facilitate the most effective interoperability of emergency service organisations and their key personnel, especially for fire services. |
REC229-2842 | 1 - Land-use and building regs | The committee recommends that building codes incorporate mitigation measures that take into account foreseeable risks from extreme weather events. |
REC229-2841 | 1 - Land-use and building regs | The committee recommends that credible and reliable flood mapping activities and the development of other information that would best inform landowners or prospective landowners of potential risks from extreme weather events are prioritised and used to inform land use planning laws. |
REC229-2840 | 39 - Disaster Risk Management | The committee recommends relevant authorities work with community service organisations in both planning responses to and responding to extreme weather events, in particular those organisations that provide vital services to vulnerable groups. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2847 | 15 - Inter-service cooperation | I recommend that Border Protection Command implement a surveillance strategy, possibly with the assistance of other Commonwealth authorities and organisations on the island such as the AFP, which heightens its coverage at times when the weather and sea conditions are rough. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0578 | 15 - Inter-service cooperation | There would be benefit in progressively aligning the geographic boundaries of each of the agencies and seeking to co-locate their headquarters within those boundaries. |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0548 | 15 - Inter-service cooperation | Inter-agency cooperation to manage fire precincts in a tenure-blind fashion is necessary for effective fire suppression. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0560 | 15 - Inter-service cooperation | There would be value in progressively aligning the geographical boundaries of emergency management agencies and co-locating where possible within regions and districts. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC225-0532 | 16 - Training and behaviour | All agencies ensure fire managers are trained to correctly interpret the new Spot Fire Weather Forecast and to familiarise themselves with the entire format – ensuring consideration of the whole forecast - not just the tabular data containing the 12 hour forecast. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0518 | 16 - Training and behaviour | The Department of Environment and Conservation explore human resourcing models that: · make succession planning a priority; · look at options for the attraction and retention of staff; and · review how the salary levels of staff matches the decision making required in major activities such as prescribed burns. |
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1867 | 16 - Training and behaviour | The Minister for Emergency Services ensure that the Fire and Emergency Services Authority’s peer support program is rejuvenated as soon as possible with increased funding to provided added training for staff volunteering for this program |
REC222-1865 | 16 - Training and behaviour | The Minister for Police immediately instigate processes to ensure that the psychological well-being of officers is at the forefront of the Western Australia Police’s staff planning. These processes should include all officers being trained in psychological first aid, with subsequent regular refresher courses. Senior officers should be the first priority for psychological first aid training. |
REC222-1861 | 41 - Emergency Management exercises | The Ministers for Health, Emergency Services, Environment and Police provide additional funds to their agencies so that a detailed exercise is held on a regular basis based on a disaster that will create the worst outcome for the State. |
REC222-1857 | 15 - Inter-service cooperation | The Ministers for Health, Police, and Emergency Services ensure that the Western Australia Police, the Fire and Emergency Services Authority and St John Ambulance establish a formal platform to share their knowledge and experience in delivering programs to their staff and volunteers to address issues of stress from disasters and critical incidents, as is done in other Australian jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC221-2860 | 19 - Offences | Housing should ensure it has sound systems, processes and controls in place that minimise the opportunity for fraud and gives it the best chance of detecting it by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2888 | 35 - Business and Industry in relation to industry | Foster private sector service providers who can offer tailored services or broadcast high quality presentation of general purpose weather information |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1918 | 1 - Land-use and building regs | Department of Regional Development and Lands and Department of Environment and Conservation should consider how their respective land use approval processes can incorporate the input of Local Emergency Management Committees (LEMCs) as part of risk assessments for high risk events and adventure sport activities. |
REC204-1914 | 15 - Inter-service cooperation | FESA, WA Police and St John Ambulance establish a uniform protocol for handling multiple agency emergency responses that does not involve callers having to make multiple calls to 000. |
REC204-1909 | 35 - Business and Industry in relation to industry | Eventscorp should ensure that organisers of events its sponsors are directed to all appropriate authorities and stakeholders to ensure the responsible, safe and efficient planning and conduct of the event. |
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
REC204-1919 | 1 - Land-use and building regs | Tourism WA must give specific regard as to whether land use approvals need to be sought, particularly from Department of Regional Development and Lands, when conducting due diligence for event sponsorship proposals that require sign off by both departments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0299 | 15 - Inter-service cooperation | The state should converge on a single communications platform for all emergency management and support agencies. |
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
REC203-0298 | 15 - Inter-service cooperation | The state should progressively align on a shared platform, such as WebEO C , to establish a Common Operating Picture (COP). |
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
REC203-0288 | 15 - Inter-service cooperation | The State Duty Officer from DEC and the State Duty Director, FES A need to confer whenever a Level 2 or 3 incident is declared to satisfy themselves that they have appropriate incident management structures and resources across the state are at an appropriate level of preparedness. |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
REC203-0301 | 15 - Inter-service cooperation | Early in an incident, close and effective liaison needs to be established with local government agencies. |
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0287 | 15 - Inter-service cooperation | On a regional basis there would be value in closer working relationship between DEC crews and VBFBs to build mutual trust and confidence. This could be done by opportunity engagement of VBFBs in DEC fire management or through exercises. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0504 | 15 - Inter-service cooperation | The Minister for Emergency Services ensure that the annual budget of FESA contains the funds it requires to coordinate an annual multi-agency bushfire field exercise, alongside other desktop exercises, to be held in different regions of the State each year. The outcomes of this field exercise should be included in the proposed annual Ministerial statement to Parliament on bushfire readiness before each season. |
REC202-0494 | 16 - Training and behaviour | The Minister for Emergency Services introduce by the 2012-13 bushfire season psychological testing of all FESA career staff and bushfire and rescue volunteers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
REC201-0260 | 15 - Inter-service cooperation | There are a range of opportunities identified from reviewing the three fires that will improve coordination between FESA and DEC, requiring limited resources, potentially generating some efficiencies and reflecting a joint, tenure blind approach to fire management in WA. The MIR acknowledges the progress made through the IBMC in these matters and notes these measures will require ongoing strong leadership. These include: · Clarification and consistent application of the Zone 2 and 2A mobilisation protocols; · Duplicating available information on websites; · Establishing a single State air desk and cross-utilising Air Attack Supervisors; · Completing common training for the conduct of public meetings;· Coordinating IMT training and exercises; · Operating joint IMT‘s during interface fires; FESA utilising the DEC mobile ICC when suitable ICPs are not available; · FESA engaging in daily weather teleconferences with DEC; Engaging a permanent BoM officer to support a common FESA and DEC SOC; · Developing a common ‗Tool Box‘ of forms and operational procedures for fire response; · Developing common jurisdictional arrangements to accommodate interstate support; · Developing a joint FESA/DEC SOC at the new (FESA) Emergency Services facility at Cockburn; · Adopting common and transparent Level 3 IC accreditation · Using a single mapping capability across both agencies and · Using common naming conventions for fires. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-1708 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-0376 | 1 - Land-use and building regs | State and locals governments: a) recognise that regardless of future declarations of bushfire prone areas, the existing planning and building problems in the Perth Hills related to bushfire risk will persist; b) urge residents in these areas to retrofit their homes and evaporative air conditioners in compliance with AS 3959 - 2009; c) examine options to retrospectively bring these areas into compliance with Planning for Bushfire Protection Guidelines. |
REC200-1730 | 16 - Training and behaviour | The Fire and Emergency Services Authority and local governments examine the current competencies of Chief Bushfire Control Officers and Community Emergency Services Managers (or Community Fire Managers) and consider what further development is needed to ensure these staff are capable of: |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-0346 | 1 - Land-use and building regs | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-1707 | 1 - Land-use and building regs | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-1726 | 41 - Emergency Management exercises | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. |
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
REC200-1680 | 15 - Inter-service cooperation | Emergency Management Western Australia establish an inter-agency working group to continue the development of the new single emergency services Act. |
REC200-0340 | 1 - Land-use and building regs | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-0390 | 16 - Training and behaviour | The Fire and Emergency Services Authority and local governments examine the current competencies of Chief Bushfire Control Officers and Community Emergency Services Managers (or Community Fire Managers) and consider what further development is needed to ensure these staff are capable of: measuring and mapping fuel loads maintaining fuel load databases drawing up prescriptions for, and overseeing controlled burns building effective working relationships with all relevant stakeholders. |
REC200-1679 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-0338 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-1718 | 35 - Business and Industry in relation to industry | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-0386 | 15 - Inter-service cooperation | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. This should include field exercises which test: Evacuation centres Critical infrastructure (including at the local level) Traffic management, including road blocks. Consideration should also be given to involving the community in exercising (see Recommendation 7) and using prescribed burns as exercises (see Recommendation 14) More detailed planning for exercises should be included in a revised WESTPLANBUSHFIRE to be endorsed by the State Emergency Management Committee. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0377 | 1 - Land-use and building regs | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-1731 | 16 - Training and behaviour | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0122 | 16 - Training and behaviour | A staff recognition and reward framework for service to fire management should be considered for DEC fire staff. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
REC183-0118 | 15 - Inter-service cooperation | A Memorandum of Understanding signed by the Chief Executives of DEC and FESA would be a valuable statement of joint commitment between the two agencies. |
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
REC183-0117 | 15 - Inter-service cooperation | The Interagency Bushfire Management Committee and its sub-committees are the logical central platform for developing and strengthening future joint bushfire strategies and common systems of work between bushfire management agencies in Western Australia. |
REC183-0110 | 16 - Training and behaviour | DEC should emphasise the principle of foresight by adopting an appreciation and decision making process and training staff in that process. |
REC183-0116 | 15 - Inter-service cooperation | Triggers and a process for transfer of command and control from DEC to FESA should be developed and documented. |
REC183-0109 | 1 - Land-use and building regs | It is sensible that, in considering planning development proposals on land adjacent to the DEC estate, that development authorities invite comment from DEC on the fire management consequences of development proposals. |
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0124 | 15 - Inter-service cooperation | FESA and DEC take a whole of capability approach to joint operations, including developing joint doctrine that provides a common and articulated understanding of roles and responsibilities, resources and capabilities |
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
REC182-0129 | 15 - Inter-service cooperation | FESA maintains inter-agency relationships and arrangements, and develops formalised arrangements across the entire emergency management cycle for joint activities such as training, exercises and procedure development. |
REC182-0125 | 15 - Inter-service cooperation | FESA, in partnership with other agencies and the community, develops Western Australia’s urban interface fire fighting capability and capacity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0140 | 4 - Fire season preparation | The Commonwealth seek agreement from the states and territories that would enable it to evaluate the adequacy of fuel reduction programs applied by public land management agencies in high bushfire risk areas, and audit their implementation against the program's stated objectives. |
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0147 | 5 - Hazard reduction burns | The Commonwealth encourages further research into prescribed burning and its effectiveness and into alternative bushfire mitigation approaches through improved bushfire risk understanding at the asset level. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
REC176-0146 | 16 - Training and behaviour | The Commonwealth organise the co-operation of state land management and fire agencies to provide the practical training aspect of the curriculum as part of a national bushfire accreditation course. |
REC176-0145 | 16 - Training and behaviour | The Commonwealth assist the states with bushfire training for land managers and volunteers by co-ordinating curriculum development and delivery of a national bushfire accreditation course, to be delivered by the relevant state agencies. |
REC176-0142 | 1 - Land-use and building regs | The Commonwealth consult with local, state and territory government planning authorities on the development and dissemination of a house loss risk index for households in Australia's highest risk bushfire areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0105 | 19 - Offences | That the Department of the Attorney General, in consultation with FESA and Western Australia Police (WAPOL), consider options for legislative amendments to extend criminal liability to all damage, injury or death directly caused by arson. |
REC173-0104 | 1 - Land-use and building regs | That FESA assess the cost and other implications of proposed changes to bushfire prone zone declarations which would allow the whole State to be declared bushfire prone. |
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0023 | 16 - Training and behaviour | Pre-season multi- agency refresher training for Ground Controllers should be undertaken each year. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0022 | 15 - Inter-service cooperation | The declaration of a potential Level 3 incident should be notified to FESA who can facilitate an early warning to CFCO’s in the Shire and surrounding LGA’s. |
REC172-0031 | 16 - Training and behaviour | Pre-season refresher training to include an emphasis on check in/out procedures |
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0041 | 16 - Training and behaviour | Media liaison personnel are needed to ‘ride’ shotgun’ on media personnel to facilitate them getting their stories without imposing on the effectiveness of operations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0067 | 14 - Incident Mgt Teams | That to the extent it has not already done so, DEC take action to ensure that in future cases relevant weather forecast information, particularly information as to significant wind changes, is promptly transmitted through the Incident Management Team and made available to persons with field operation responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0058 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure that all agencies can access other agencies’ operations centres when needed and that the procedures to do so are documented |
REC170-0065 | 16 - Training and behaviour | Agencies should: train their staff who will be involved in emergencies in incident management. |
REC170-0059 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure all agencies use the same approach to managing incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3017 | 35 - Business and Industry in relation to industry | ESWG notes NGERAC already informally advises ministers on the possible effects of gas emergencies on electricity supplies. ESWG recommends formalising this role by acknowledging it in NGERAC’s MOU. ESWG also recommends an editorial review of NGERAC’s MOU to ensure accuracy and consistency. |
REC162-3011 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to expanding the role of AEMO in providing market information on gas by: |
REC162-3015 | 35 - Business and Industry in relation to industry | ESWG recommends National Gas Emergency Response Advisory Committee maintain its industry, jurisdiction and consumer representation noting the importance of input from each of these groups in developing its advice. |
REC162-3021 | 35 - Business and Industry in relation to industry | ESWG notes that existing and future contracts and the impending introduction of the Short Term Trading Market will be the primary mechanisms for addressing future gas supply shortfalls. |
REC162-3010 | 35 - Business and Industry in relation to industry | Energy Security Working Group (ESWG) recommends consideration be given to government and industry working together to understand that investment opportunities in the energy sector are realised in a timely fashion to better manage potential longer term supply shortfalls. |
REC162-3014 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to leveraging AEMO’s expanded responsibilities in gas markets by undertaking the role of the National Gas Emergency Response Advisory Committee (NGERAC) Secretariat while the Commonwealth continue as Chair, with the Chair’s position to be reviewed once the short term trading market (STTM) commences in June 2010. ESWG also recommends that the review be undertaken by NGERAC jurisdictional members. |
REC162-3020 | 35 - Business and Industry in relation to industry | ESWG recommends that as far as reasonably practical, arrangements for load shedding be as transparent as possible to give consumers confidence in the process. |
REC162-3013 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to consolidating gas and electricity network status and emergency information on one webpage for central communication. |
REC162-3019 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to the spokesperson role AEMO can undertake during an electricity and/or gas supply shortfall in its covered markets and relevant jurisdictional emergencies, noting that AEMO has clear responsibility for the bulk supply of electricity as outlined in the Power System Emergency Management Plan and the Victorian wholesale gas market, and that for multi-jurisdiction gas supply emergencies, any AEMO spokesperson role would be to reflect NGERAC’s advice. |
REC162-3012 | 35 - Business and Industry in relation to industry | ESWG recommends reviewing AEMO’s Gas Bulletin Board (GBB) to ensure it is effectively communicating all publicly available information to market participants to assist in monitoring daily gas supplies, and any changes to the GBB rules required to improve information and awareness of any potential shortages that will assist the market to make the necessary investments and/or adjustments in maintenance. |
REC162-3018 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of a review of communication protocols with the aim of achieving high level policy consistency of communication across jurisdictions to the maximum extent possible. |
REC162-3022 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of how to ensure good communication and flow of information between the liquid fuels and other energy sectors. One approach that may be considered is that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3136 | 16 - Training and behaviour | There is a need for industry in consultation with NOPSA to establish a priority programme of accredited education modules in the Safety Case regime targeting stakeholders in the regime at their respective levels to improve the understanding of the Safety Case and correspondent responsibilities. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3142 | 19 - Offences | NOPSA should use encouragement as the primary tool of enforcing compliance provided willingness to improve is exhibited by the players. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3137 | 16 - Training and behaviour | As professional competency is one of the key pillars of any Safety Case, commitment to training for current and future needs remains a fundamental requirement for achieving best practice outcomes in safety. Industry should be encouraged to build on its training commitment now being made to achieve a competent and fully accredited workforce over the next five years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC147-3187 | 16 - Training and behaviour | The ANAO recommends that, in order to maximise the benefit of emergency management training activities, EMA review periodically its approach to delivering individual training courses, to ensure the most appropriate delivery mechanism is used commensurate with training objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3215 | 1 - Land-use and building regs | The Committee recommends that the Building Code of Australia, including cyclone building codes, be revised with the objective of increasing resilience to climate change. |
REC145-3203 | 39 - Disaster Risk Management | The Committee recommends that: |
REC145-3214 | 1 - Land-use and building regs | The Committee recommends that the Australian Government consider the benefits of adopting a nationally consistent sea level rise planning benchmark and, if so, whether this be done on a statutory basis or otherwise. The outcomes of this consideration should then be included as part of the action plan for the proposed Intergovernmental Agreement on the Coastal Zone. |
REC145-3199 | 16 - Training and behaviour | The Committee recommends that the Australian Government continue funding under the Climate Change Adaptation Skills for Professionals Program. In addition, the Australian Government should liaise with tertiary institutions to ensure an adequate supply of appropriately skilled coastal planners and engineers. |
REC145-3213 | 1 - Land-use and building regs | The Committee notes the Council of Australian Governments initiative (through the Local Government and Planning Ministers Council) to develop state-specific climate change planning policies by mid 2011, to inform local governments and regional planning responses to climate change. The Committee recommends that the Australian Government ensure that the outcomes of this initiative are included as part of the action plan under the proposed new Intergovernmental Agreement on the Coastal Zone. |
REC145-3227 | 39 - Disaster Risk Management | The Committee recommends that coastal based Natural Resource Management bodies seeking funding under the Caring for our Country program have coastal and marine priorities, as well as coastal zone management principles integrated in their management plans. |
REC145-3210 | 39 - Disaster Risk Management | The Committee recommends that the Department of Climate Change, in collaboration with the Queensland Government, CSIRO and Indigenous communities in the Torres Strait, undertake a major study into the vulnerability of the Torres Strait to the impacts of climate change and provide assistance in the development of an adaptation plan. |
REC145-3222 | 1 - Land-use and building regs | The Committee recommends that the Australian Government: |
REC145-3209 | 39 - Disaster Risk Management | The Committee notes that major initiatives relating to climate change adaptation risk assessment and infrastructure are currently in progress. Given that much of Australia’s infrastructure is in the coastal zone and the particular threats facing the coastal zone from climate change, involving significant socioeconomic costs, the Committee recommends that the Australian Government ensure there is a comprehensive national assessment of coastal infrastructure vulnerability to inundation from sea level rise and extreme sea level events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3634 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter- Terrorism Committee, pursue the adoption of a more strategic approach to determining the National Capability Development Exercise Programme so that: |
REC117-3639 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the National Counter-Terrorism Committee, strengthens the reporting on the National Capability Development Exercise Programme through: |
REC117-3638 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee: |
REC117-3637 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, pursue a more strategic and systematic approach to the measurement of performance via the National Capability Development Exercise Programme by: |
REC117-3636 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in conjunction with the National Counter-Terrorism Committee’s exercise management advisers, explore options for the incorporation of more contemporary and varied testing and training aids in the National Capability Development Exercise Programme. |
REC117-3635 | 15 - Inter-service cooperation | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, seek to create systematic mechanisms for better targeting and evaluating inter- agency coordination within the National Capability Development Exercise Programme and continuous improvement cycle. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
REC116-2121 | 35 - Business and Industry in relation to industry | The Working Group recommends that the Australian Government investigate, in consultation with the finance and banking sector, the development of arrangements to ensure that essential transactions can continue in the event of a catastrophic failure of the banking system that includes access to cash. |
REC116-2102 | 35 - Business and Industry in relation to industry | The Working Group recommends that jurisdictions identify appropriate commercial organisations/bodies able to ensure maintenance of supply of food items and packaged water to commercial outlets in times of disaster. |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2101 | 35 - Business and Industry in relation to industry | The Working Group recommends that each jurisdiction; |
REC116-2115 | 41 - Emergency Management exercises | The Working Group recommends that the results of the scenario modeling be presented to the Australian Emergency Management Committee (AEMC) upon completion, and that AEMC form Sub Working Groups of State/Territory emergency management representatives as appropriate to be tasked with considering response and recovery capability (both state/territory and national) against the identified consequences. |
REC116-2098 | 15 - Inter-service cooperation | The Working Group recommends that Emergency Management Australia (EMA) facilitate national discussions into the capability of States/Territories to ensure thorough collaborative systems and plans for inter-jurisdictional resource interoperability exist, and where this has not already occurred at State/Territory level and appropriate agencies, committees or government departments can be identified, they should be tasked with progressing specific issues in the following areas: |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2129 | 41 - Emergency Management exercises | The Working Group recommends that Emergency Management Australia and the jurisdictions through the AEMC develop a three year rolling national exercise strategy aimed at testing the response and recovery aspects of large scale disasters. |
REC116-2106 | 16 - Training and behaviour | The Working Group recommends that appropriate building/surveyor peak bodies be identified, and that discussions be held between the emergency management sector and those peak bodies at State/Territory and national level with a view to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
REC113-3902 | 14 - Incident Mgt Teams | Government should: establish a State-wide command structure across volunteer Bush Fire Brigades for fighting major bushfires, to more effectively manage the coordination of personnel and resources |
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
REC113-3905 | 16 - Training and behaviour | Firefighting organisations should: address their key training and development issues |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2142 | 5 - Hazard reduction burns | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek agreement from the states and territories on the optimisation and implementation of prescribed burning targets and programs to a degree that is recognised as adequate for the protection of life, property and the environment. The prescribed burning programs should include strategic evaluation of fuel management at the regional level and the results of annual fuel management in each state should be publicly reported and audited. |
REC098-2178 | 1 - Land-use and building regs | The Committee recommends that Standards Australia review the clarity of AS3959–1999: Construction of buildings in Bushfire Prone Areas to ensure that all relevant stakeholders can interpret and apply the Standard in the way it is intended. |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2177 | 39 - Disaster Risk Management | The Committee recommends that state and territory governments be required to regularly perform risk assessments to the land within their jurisdictions to ensure that bushfire prone areas are accurately identified |
REC098-2136 | 4 - Fire season preparation | The Committee recommends that the Commonwealth through the National Heritage Trust assist the states and territories in the construction, maintenance and signage of fire trail networks. |
REC098-2176 | 1 - Land-use and building regs | The Committee recommends that Standards Australia incorporate building maintenance into AS3959–1999: Construction of buildings in Bushfire Prone Areas, perhaps renaming it as AS3959–1999: Construction and maintenance of buildings in Bushfire Prone Areas. |
REC098-2133 | 1 - Land-use and building regs | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve when asset protection zones will be located on private land and when on public land and gain assurances that adequate maintenance of zones will be enforced. |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4169 | 4 - Fire season preparation | Mitigation and preparedness be enhanced and maintained for the future. Some co—ordinating mechanism or system be introduced at State Government level for this purpose. [Reference paragraphs: 114 to 128] |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4139 | 19 - Offences | Local authorities prosecute in all cases of deliberate breaches of the provisions of the Bush Fires Act and thay failing this the Bush Fires Board take appropriate action to initiate such prosecutions. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4144 | 16 - Training and behaviour | No opportunity be lost of encouraging the formation of bush fire brigades and the maintenance of enthusiasm and that the Bush Fires Board assist the brigades in any way possible to obtain adequate training and equipment. |
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4158 | 16 - Training and behaviour | That needs in the direction of a fire emergency service be met as far as practicable by the Bush Fires Board in its training programme and in the tactical organisation of existing brigades for use as reserves in districts other than their own. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |