Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4108 | 4 - Fire season preparation | Australian, state and territory governments should review the assessment and approval processes relating to vegetation management, bushfire mitigation and hazard reduction to: |
REC317-4107 | 4 - Fire season preparation | Public land managers should clearly convey and make available to the public their fuel load management strategies, including the rationale behind them, as well as report annually on the implementation and outcomes of those strategies. |
REC317-4087 | 4 - Fire season preparation | State and territory governments, working with local governments and fire and emergency service agencies, should ensure that there are appropriate arrangements for roadside vegetation management that take into account, among other things: |
REC317-4102 | 25 - Inquiry, audit, lessons management and after action review | Australian, state and territory governments should review Australian Medical Assistance Team capabilities and procedures and develop necessary training, exercising and other arrangements to build capacity for domestic deployments. |
REC317-4074 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should review the content of the Defence Assistance to the Civil Community manual to ensure consistency of language and application with a revised COMDISPLAN. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
REC291-1249 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Premier and Cabinet to conduct an independent review of the current arrangement for the management and distribution of the Emergency Services Levy. The review will have the specific purpose of: · seeking input from key entities including the Departments of Treasury, Finance, Fire and Emergency Services, Lands, and Parks and Wildlife, WA Local Government Association, and the Office of Bushfire Risk Management. · ensuring the arrangement has the flexibility and agility to deal with emerging bushfire risk priorities. · establishing a budget process that enables a shift in investment towards prevention, mitigation and building community resilience and capability. |
REC291-1233 | 25 - Inquiry, audit, lessons management and after action review | The State Government to explore options for streamlining the functions and the independence of the State Emergency Management Committee Secretariat and the Office of Bushfire Risk Management with a view to including an inspectorate function, and appointing a person who is dedicated to that role. The purpose is to provide assurance and reporting, and to inquire into, monitor and report transparently on emergency management standards, preparedness, capability, service delivery and investment performance outcomes. Within two years of the establishment of this arrangement the State Government to review and assess whether it is meeting the desired outcomes. |
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
REC265-1102 | 25 - Inquiry, audit, lessons management and after action review | SEMC Secretariat Community Emergency Management Officers should work with the Shire to document the Shire of Mundaring’s learnings from the Parkerville Stoneville Mt Helena fire with a view to sharing this with other local authorities particularly those facing similar situations in order to extend the range of tools available to assist local governments to understand their roles and responsibilities in future emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2560 | 29 - Operational Health and Safety | The Civil Aviation Safety Authority devolve to Designated Aviation Medical Examiners the ability to renew aviation medical certificates (for Classes 1, 2, and 3) where the applicant meets the required standard at the time of the medical examination. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1546 | 25 - Inquiry, audit, lessons management and after action review | Defence undertake a review of its ability to respond to a fire within Marrangaroo Training Area, whether bushfire or structural. The underlying assumption should be that the only response available to fight a fire within Marrangaroo Training Area will be provided by Defence. Further, such response must occur while a fire is in its initial stages. A review must either acknowledge the risk of fire occurring in th future, or upgrade Defence's firefighting capability at Marrangaroo Training Area. |
REC257-1555 | 14 - Incident Mgt Teams | The lines of responsibility be made clearer and some individual, perhaps the Regional Environmental Officer, or agency be given overarching responsibility to ensure recommended works related to bushfire mitigation on Defence Estate are carried out in accordance with the Bushfire Management Plan which the Manual for Fire Protection Engineering directs be prepared. |
REC257-1539 | 25 - Inquiry, audit, lessons management and after action review | Defence Security Authority conduct an investigation into the whereabouts of items of anaccounted explosive ordnance issued to Defence Explosive Ordnance Training School Exercise Marrangaroo. |
REC257-1548 | 25 - Inquiry, audit, lessons management and after action review | The Regional Director-Defence Support-Northern NSW, make contact with Deputy Commissioner ~~~~~ Director of Operational Services Rural Fire Service, to arrange a headquarters driven bipartite review of the events of 16 October 2013 with a review to mitigation of future fire events generally, and with specific reference to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1573 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should schedule an independent and public review of the progress of reforms to natural disaster funding arrangements five years after implementation has commenced. This review should examine the operation and efficacy of the arrangements, including the: |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2792 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the investigation be re-opened by the ATSB with a focus on organisational, oversight and broader systemic issues. |
REC236-2806 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies investigate appropriate methods to ensure that information about the incidence of, and variable weather conditions at, Norfolk Island is available to assist flight crews and operators managing risk that may result from unforseen weather events. |
REC236-2805 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies review whether any equipment or other changes can be made to improve the weather forecasting at Norfolk Island. The review would include whether the Unicom operator should be an approved meteorological observer. |
REC236-2801 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the ATSB review its process to track the implementation of recommendations or safety actions to ensure it is an effective closed loop system. This should be made public, and provided to the Senate Regional and Rural Affairs and Transport Committee prior to each Budget Estimates. |
REC236-2795 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that a short inquiry be conducted by the Senate Standing Committee on Rural and Regional Affairs and Transport into the current status of aviation regulatory reform to assess the direction, progress and resources expended to date to ensure greater visibility of the processes. |
REC236-2793 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that CASA processes in relation to matters highlighted by this investigation be reviewed. This could involve an evaluation benchmarked against a credible peer (such as FAA or CAA) of regulation and audits with respect to: non-RPT passenger carrying operations; approach to audits; and training and standardisation of FOI across regional offices. |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1601 | 35 - Business and Industry in relation to industry | Community service providers consider in their business continuity planning how they could assist with facilitating access to telecommunications services for the public during mass outages. |
REC233-1594 | 35 - Business and Industry in relation to industry | When businesses review their business continuity plans they should take into account the prospect of a major telecommunications outage that affects both mobile and fixed voice and data services. |
REC233-1600 | 35 - Business and Industry in relation to industry | Community service providers consider, in consultation with relevant government authorities, reviewing their current privacy practices concerning personal information about vulnerable persons to ensure they are able to appropriately share information during major disruptive incidents. |
REC233-1593 | 35 - Business and Industry in relation to industry | Telstra and other service providers to consider improving processes to assist customers with setting up temporary call diversions during future outages. |
REC233-1599 | 35 - Business and Industry in relation to industry | Providers of personal alert devices consider telecommunications outages in their service continuity plans and provide clear advice to their customers regarding their options during a telecommunications service outage. |
REC233-1590 | 25 - Inquiry, audit, lessons management and after action review | Department of Broadband, Communications and the Digital Economy seek regular updates from Telstra on the implementation of the recommendations of its inquiry into the Warrnambool exchange fire. |
REC233-1591 | 35 - Business and Industry in relation to industry | While noting the importance of voice communications, telecommunications providers should consider as part of their mass outage business continuity planning, options for the provision of interim mobile broadband services for the community e.g. local wireless broadband access hubs (i.e. Wi-Fi). |
REC233-1598 | 35 - Business and Industry in relation to industry | Community service providers consider developing information and advice regarding telecommunications outages for clients managed remotely using telecommunication services, including personal alert devices. |
REC233-1597 | 35 - Business and Industry in relation to industry | Community service providers consider updating their business continuity plans to take into account the possibility of a major telecommunications outage involving both fixed and mobile voice and data services. |
REC233-1595 | 35 - Business and Industry in relation to industry | Department of Broadband, Communications and the Digital Economy to work with the Trusted Information Sharing Network’s Communications Sector Group to develop general telecommunications continuity advice for businesses and individuals to assist in developing continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2828 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, commission an independent review to assess the case for establishing a national centre for communicable disease control in Australia. The review should outline the role of a national centre and how it might be structured to build on and enhance existing systems. It should examine different models, considering a range of options for location, governance and staffing. The review should incorporate a cost-benefit analysis for each of the models presented. |
REC232-2827 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, conduct a comprehensive national audit and mapping exercise to: |
REC232-2815 | 25 - Inquiry, audit, lessons management and after action review | The Department of Health and Ageing review the existing evidence base to evaluate the cost-effectiveness of its policy to use heat scanners at ports of entry as a measure to mitigate the risk of infectious disease importation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2849 | 20 - Role of police | I recommend that the AFP takes steps to ensure that there are on Christmas Island at all times appropriately trained AFP officers who have completed the National Police Search and Rescue Manager’s Course and that upskilling should be ongoing to establish a cadre of trained search and rescue personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0540 | 25 - Inquiry, audit, lessons management and after action review | : In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0522 | 25 - Inquiry, audit, lessons management and after action review | The response operation to the Margaret River bushfire in November 2011 be the subject of a review with independent oversight. |
REC223-0516 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Conservation review its implementation of the findings of the Ferguson Review conducted in 2010. |
REC223-0523 | 25 - Inquiry, audit, lessons management and after action review | The Government consider enacting legislation to facilitate the review of all future major incidents, including but not limited to fire, earthquake, storm and marine inundation, and the emergency response to them. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1858 | 29 - Operational Health and Safety | The Ministers for Environment, Police, Child Protection and Emergency Services fund additional chaplaincy services, particularly for staff and volunteers based in rural and regional Western Australia. |
REC222-1852 | 29 - Operational Health and Safety | The Minister for Health immediately establish the road trauma counselling service to be funded by the Road Trauma Trust Account. |
REC222-1869 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments include provisions for regular external audits of invoices for payment in their next round of Employee Assistance Program contract negotiations. |
REC222-1850 | 29 - Operational Health and Safety | The Ministers for Emergency Services, Environment and Police ensure that their departments develop as a high priority a computer system for tracking their staff and the number of traumatic events they have attended over a particular period. |
REC222-1862 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services request the State Emergency Management Committee to review by June 2013 the sharing of data between the State’s emergency response agencies using the WebEOC software and any further enhancements that can be made to this process. |
REC222-1849 | 29 - Operational Health and Safety | Departmental chief executives of the Western Australia Police, Department of Environment and Conservation and the Fire and Emergency Services Authority should be made personally responsible for the psychological health (as a result of critical incident trauma) of their staff and volunteers. This obligation should be reflected in their performance agreements. |
REC222-1847 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments undertake a formal review by 30 June 2013 of the welfare services addressing stress and trauma provided to both their career and volunteer members. |
REC222-1848 | 29 - Operational Health and Safety | The Western Australian Government amend current State occupational health and safety legislation so that it includes a definition for ‘health’ that includes psychological health. |
REC222-1859 | 29 - Operational Health and Safety | The Attorney General and the Ministers for Health and Mental Health fund their departments to establish a peer support program by the end of 2013 for their staff undertaking stressful tasks during a disaster or critical incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2888 | 35 - Business and Industry in relation to industry | Foster private sector service providers who can offer tailored services or broadcast high quality presentation of general purpose weather information |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1903 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should commission an independent public review of disaster prevention and recovery arrangements. This should be broader than the review currently being conducted by the Attorney-General’s Department. The review should cover the Natural Disaster Relief and Recovery Arrangements, as well as the funding mechanisms for disaster mitigation, including the National Partnership Agreement on Natural Disaster Resilience. This review should: |
REC205-1902 | 25 - Inquiry, audit, lessons management and after action review | The Council of Australian Governments should commission an independent public inquiry to develop an appropriate response to managing the risks of climate change to existing settlements. The inquiry should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1909 | 35 - Business and Industry in relation to industry | Eventscorp should ensure that organisers of events its sponsors are directed to all appropriate authorities and stakeholders to ensure the responsible, safe and efficient planning and conduct of the event. |
REC204-1916 | 25 - Inquiry, audit, lessons management and after action review | Local Emergency Management Committee (LEMC) processes should be reviewed to ensure that: |
REC204-1913 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Attorney General consider conducting a review of the Civil Liability Act 2002 (WA) in light of the 2011 Kimberley Ultramarathon. Such a review should consider issues such as the effectiveness given to competitor waivers under the Act and the potential difficulties of establishing proceedings and enforcing a judgement against foreign‐based providers of recreational activities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0497 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Local Government have urgent discussions with the Western Australian Local Government Association (WALGA) as to why they are not supporting the full Recommendations addressed to local government in the Keelty Report. The Minister ensure that by May 2012 WALGA and its member councils have the resources to fully implement theimplementation of the Recommendations. |
REC202-0495 | 25 - Inquiry, audit, lessons management and after action review | At the conclusion to the 2011-12 bushfire season, the Minister for Emergency Services institute a thorough review of the operations of FESA, the Police and DEC in protecting the State from bushfires and other natural disasters, with a primary focus on: · staffing levels; · equipment levels and coordination; and · training needs. The Minister report to Parliament by June 2012 on any changes that need to be made to the current departmental structures to optimise the State’s preparedness for the 2012-13 bushfire season. |
REC202-0493 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services report to Parliament every six months on the progress made in completing all of the outstanding Recommendations of the Keelty Report. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0257 | 29 - Operational Health and Safety | FESA needs to place greater priority on the appointment of Safety Advisors to Level 3 incidents as is reflected in WESTPLAN Bushfire. |
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0392 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry’s Recommendations in two years. |
REC200-1732 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry's recommendations in two years. |
REC200-1705 | 29 - Operational Health and Safety | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA‟s own policy of „Use of Private Vehicles in Fires‟ |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0384 | 25 - Inquiry, audit, lessons management and after action review | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-1701 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. |
REC200-0368 | 20 - Role of police | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-0361 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. This session should include open discussion and explain the decisions of all parties – including how the incident controllers determined priorities, and why residents chose not follow their advice to evacuate. The learning outcomes should be promulgated across all agencies and incorporated in future level 3 incident controller training programs. |
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
REC200-1718 | 35 - Business and Industry in relation to industry | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2911 | 29 - Operational Health and Safety | The review team recommend that: |
REC189-2907 | 29 - Operational Health and Safety | a) For the purposes of designing and implementing its regulatory activities, National Offshore Petroleum Safety Authority (NOPSA) should continue to identify priority hazards and risks and their underlying causes, in consultation with the NOPSA Advisory Board and stakeholders (see Theme 9, Stakeholder engagement). |
REC189-2912 | 29 - Operational Health and Safety | The review team recommend that the safety case system be strengthened by including provisions for a design notification scheme along the lines of that under the British Offshore Safety Case Regulations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
REC182-0133 | 29 - Operational Health and Safety | FESA reviews its approach to safety and safety culture. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0140 | 4 - Fire season preparation | The Commonwealth seek agreement from the states and territories that would enable it to evaluate the adequacy of fuel reduction programs applied by public land management agencies in high bushfire risk areas, and audit their implementation against the program's stated objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0030 | 29 - Operational Health and Safety | A strategically located Staging Area serviced with check in/out personnel should be considered as early as possible at incidents involving an extended attack. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0067 | 14 - Incident Mgt Teams | That to the extent it has not already done so, DEC take action to ensure that in future cases relevant weather forecast information, particularly information as to significant wind changes, is promptly transmitted through the Incident Management Team and made available to persons with field operation responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0062 | 25 - Inquiry, audit, lessons management and after action review | Agencies should: annually assess their capability to respond to emergencies and take measures to address any shortfalls |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3019 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to the spokesperson role AEMO can undertake during an electricity and/or gas supply shortfall in its covered markets and relevant jurisdictional emergencies, noting that AEMO has clear responsibility for the bulk supply of electricity as outlined in the Power System Emergency Management Plan and the Victorian wholesale gas market, and that for multi-jurisdiction gas supply emergencies, any AEMO spokesperson role would be to reflect NGERAC’s advice. |
REC162-3012 | 35 - Business and Industry in relation to industry | ESWG recommends reviewing AEMO’s Gas Bulletin Board (GBB) to ensure it is effectively communicating all publicly available information to market participants to assist in monitoring daily gas supplies, and any changes to the GBB rules required to improve information and awareness of any potential shortages that will assist the market to make the necessary investments and/or adjustments in maintenance. |
REC162-3018 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of a review of communication protocols with the aim of achieving high level policy consistency of communication across jurisdictions to the maximum extent possible. |
REC162-3011 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to expanding the role of AEMO in providing market information on gas by: |
REC162-3017 | 35 - Business and Industry in relation to industry | ESWG notes NGERAC already informally advises ministers on the possible effects of gas emergencies on electricity supplies. ESWG recommends formalising this role by acknowledging it in NGERAC’s MOU. ESWG also recommends an editorial review of NGERAC’s MOU to ensure accuracy and consistency. |
REC162-3022 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of how to ensure good communication and flow of information between the liquid fuels and other energy sectors. One approach that may be considered is that: |
REC162-3010 | 35 - Business and Industry in relation to industry | Energy Security Working Group (ESWG) recommends consideration be given to government and industry working together to understand that investment opportunities in the energy sector are realised in a timely fashion to better manage potential longer term supply shortfalls. |
REC162-3015 | 35 - Business and Industry in relation to industry | ESWG recommends National Gas Emergency Response Advisory Committee maintain its industry, jurisdiction and consumer representation noting the importance of input from each of these groups in developing its advice. |
REC162-3021 | 35 - Business and Industry in relation to industry | ESWG notes that existing and future contracts and the impending introduction of the Short Term Trading Market will be the primary mechanisms for addressing future gas supply shortfalls. |
REC162-3014 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to leveraging AEMO’s expanded responsibilities in gas markets by undertaking the role of the National Gas Emergency Response Advisory Committee (NGERAC) Secretariat while the Commonwealth continue as Chair, with the Chair’s position to be reviewed once the short term trading market (STTM) commences in June 2010. ESWG also recommends that the review be undertaken by NGERAC jurisdictional members. |
REC162-3020 | 35 - Business and Industry in relation to industry | ESWG recommends that as far as reasonably practical, arrangements for load shedding be as transparent as possible to give consumers confidence in the process. |
REC162-3013 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to consolidating gas and electricity network status and emergency information on one webpage for central communication. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3030 | 25 - Inquiry, audit, lessons management and after action review | That National Offshore Petroleum Safety Authority review the risk assessment of pipelines. National Offshore Petroleum Safety Authority should focus, in particular, on the efficacy of anti-corrosion systems, and recognise potential interference effects and MAE escalation risks associated with adjacent pipelines and unlicenced pipes even if they fall outside its direct regulatory responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3147 | 29 - Operational Health and Safety | As all stakeholders have responsibility for safe outcomes, decisions regarding target subjects for safety promotion need to have the support of all stakeholders including NOPSA and the workforce. Industry, which ultimately has the responsibility for managing risk as well as funding the promotion, should take a leadership role in implementation. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3144 | 29 - Operational Health and Safety | The Safety Case proponent should be allowed some flexibility to involve appropriate experience matched with the proposed workforce competencies to enable the Safety Case to be developed with value adding processes. Subsequent to the hiring of the workforce Final Government Response Offshore Petroleum Safety Regulation Inquiry and 2008 Review of NOPSA Operational Activities and preferably before the commencement of operations a review of the Safety Case should take place with the new workforce to ensure they understand the accepted Safety Case, its risks and Safety Management Plan. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3135 | 29 - Operational Health and Safety | The initial acceptance of a new facility Safety Case should be in conjunction with inspection of a facility upon commencement of operations. |
REC149-3128 | 29 - Operational Health and Safety | National Offshore Petroleum Safety Authority (NOPSA) should develop guidelines in consultation with stakeholders to provide clarity and consistency to the process which ultimately will result in better safety outcomes. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3175 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to review, at least once every two years, the operating procedures to ensure that they adequately identify and manage the risk of entry and spread of equine influenza associated with the importation of horses into Australia. The outcome of each such review should be the subject of a written report and recommendations to the person responsible for the importation of horses and the Executive Director of AQIS. A determination should then be made as to whether any, and if so what, changes should be made to the operating procedures. |
REC148-3170 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to conduct within six months, an inspection and review of the process of horse importation from the time horses arrive in Australia until the completion of their post-arrival quarantine in order to: |
REC148-3167 | 25 - Inquiry, audit, lessons management and after action review | That the facilities at Eastern Creek and Spotswood Quarantine Stations be reviewed by AQIS in consultation with experts in biosecurity and interested parties including state and territory governments, import agents, veterinarians, farriers, operators of private quarantine stations, and representatives of horse owners, horse racing organisations and equestrian organisations. There should in any event be constructed without delay, an adequate supply of hygienic, modern showering facilities and places of entry and exit to the stations and the horse sections of them that can be supervised and monitored continually. There should also be provided at those stations as soon as is practicable suitable means of electronic surveillance, including closed-circuit television; a secure place to store chemicals, drugs, instruments and equipment for use by people attending the quarantined horses, and a set of horse stalls and yards separate from the main stalls and yards to enable isolation of horses suffering from contagious or infectious diseases. These reviews should also consider the desirability of separate areas in quarantine stations to hold horses forming part of a single quarantine intake but that have been imported from different regions or have undergone pre-export quarantine in different places. The reviews should be carried out without delay, and the two quarantine stations should be upgraded in accordance with the recommendations of the reviews. |
REC148-3154 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia or another qualified body to inspect and review the activities and events that occur from the time horses enter pre-export quarantine until the time they arrive at an airport in Australia, in order to identify any biosecurity risks and recommend any necessary changes to import conditions or other requirements. This inspection and review shall be performed without delay for each country or region from which horses are imported to Australia, and it should take account of my other recommendations and comments in this report. |
REC148-3182 | 25 - Inquiry, audit, lessons management and after action review | That Biosecurity Australia review that formal import risk analysis at least once every two years to take into account any relevant developments in scientific knowledge—specifically testing methods, vaccines, vaccination procedures and other matters that affect biosecurity. Reports on the reviews should be provided to the officer responsible for the importation of horses and should contain recommendations for any necessary changes to policies for importation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC146-3193 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the Australian National Audit Office audit CASA's implementation and administration of its Safety Management Systems approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2121 | 35 - Business and Industry in relation to industry | The Working Group recommends that the Australian Government investigate, in consultation with the finance and banking sector, the development of arrangements to ensure that essential transactions can continue in the event of a catastrophic failure of the banking system that includes access to cash. |
REC116-2102 | 35 - Business and Industry in relation to industry | The Working Group recommends that jurisdictions identify appropriate commercial organisations/bodies able to ensure maintenance of supply of food items and packaged water to commercial outlets in times of disaster. |
REC116-2101 | 35 - Business and Industry in relation to industry | The Working Group recommends that each jurisdiction; |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3902 | 14 - Incident Mgt Teams | Government should: establish a State-wide command structure across volunteer Bush Fire Brigades for fighting major bushfires, to more effectively manage the coordination of personnel and resources |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2155 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that Emergency Management Australia initiate a process involving Australasian Fire Authorities Council and the Australian Assembly of Volunteer Fire Brigades Association to review |
REC098-2151 | 29 - Operational Health and Safety | The Committee recommends that the Commonwealth Attorney-General engage the Commonwealth, states and territories in a review of occupational health and safety legislation as it affects the proper and effective functioning of bush fire services. |
REC098-2136 | 4 - Fire season preparation | The Committee recommends that the Commonwealth through the National Heritage Trust assist the states and territories in the construction, maintenance and signage of fire trail networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4169 | 4 - Fire season preparation | Mitigation and preparedness be enhanced and maintained for the future. Some co—ordinating mechanism or system be introduced at State Government level for this purpose. [Reference paragraphs: 114 to 128] |