Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4324 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the tasking protocols used to manage State Emergency Service (SES) tasks undertaken in the response phase of a disaster to enable more complete recording of details for all ‘jobs of opportunity’ (including the personal details of those assisted and/or rescued) to enable better coordination of tasks and reflect outcomes of activities by 1 November 2023. |
REC325-4325 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review and implement State Emergency Service (SES) protocol by 1 November 2023 outlining procedures to be undertaken to ensure persons uplifted from places of immediate danger or risk are transferred to a place of safety. |
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
REC325-4334 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services develop and publish an operationally based quick reference guide that complements the training offered (as per Recommendation 5) by 1 November 2022. The guide will identify key and critical aspects of the Emergency Alert system in relation to the development, composition, request for and authorising of Emergency Alerts and will include a template and an example of ‘good’ messaging using concise, minimal language and Clear Explicit Translatable Language (CETL). |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4301 | 32 - Doctrine, standards, and reform | Floodplains as assets: That, to establish the capacity and maximise the economic, social and environmental potential and consequently unlock the value of NSW floodplains, Government adopt the following guiding principles for floodplain management: |
REC324-4302 | 32 - Doctrine, standards, and reform | Disaster adaptation plans for all towns: That, to establish realistic expectations of safe spaces to live and deliver much needed housing quickly, Government through NSWRA working with local government: |
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
REC324-4317 | 32 - Doctrine, standards, and reform | Flood rescue capability: That, to help improve the protection of life across NSW in flood events: |
REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4262 | 33 - Relief and recovery | That the NSW Government provide an increased level of targeted support to flood affected communities contending with widespread mould. |
REC323-4289 | 33 - Relief and recovery | That the NSW Government ensure that all emergency and recovery plans, including state plans, local emergency management plans and functional area plans, are reviewed and updated regularly and provide clarity on the role of non-government partners. |
REC323-4275 | 34 - Local knowledge | That the NSW Government, in partnership with community groups, including First Nations groups, develop initiatives to build community resilience, particularly in regions at high risk of future natural disaster events. |
REC323-4264 | 34 - Local knowledge | That the NSW Government work in partnership with key Aboriginal stakeholders, including the Jali Local Aboriginal Land Council, to prioritise the rebuild of Cabbage Tree Island, and ensure a safe and resourced evacuation plan is in place. |
REC323-4276 | 34 - Local knowledge | That the NSW Government ensure that community groups, both existing and emerging, including First Nations groups, are well integrated into disaster recovery, by incorporating them into state recovery plans and engaging with them in between and in the lead up to natural disasters. |
REC323-4265 | 34 - Local knowledge | That the NSW Government work with First Nations peoples to support Aboriginal organisations in their capacity to operate and respond in times of natural disasters. |
REC323-4277 | 33 - Relief and recovery | That the NSW Government develop a more proactive, rapid response to manage animal welfare following natural disasters which includes improved collaboration and communication with local veterinarians and animal welfare organisations. |
REC323-4269 | 33 - Relief and recovery | That the NSW Government address the mental health needs of local communities following the February-March 2022 floods by: • embedding within state emergency and recovery plans a strategy that provides surge capacity for mental health and social workers by: • prioritising funding for community groups that are currently providing social and mental health support to their local communities • ensuring all flood-impacted communities receive the mental health support they need to fully recover. |
REC323-4271 | 33 - Relief and recovery | That Service NSW establish teams of assessors that can be on the ground to assess and approve grant applications. |
REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
REC323-4287 | 34 - Local knowledge | That the NSW State Emergency Service, in partnership with the Bureau of Meteorology, investigate ways in which local communities and local media with local knowledge can play a stronger role in flood predictions and warnings. |
REC323-4273 | 33 - Relief and recovery | That the NSW Government overhaul the way in which it conducts its grants process as it frustrated applicants and further traumatised them by repeatedly re-interviewing them and making them prove that they were flooded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2516 | 33 - Relief and recovery | Documenting disaster recovery risks in agency risk registers, along with controls and treatment plans. |
REC313-2513 | 33 - Relief and recovery | Assessing the availability and skillsets of the resources needed to respond to a major disaster recovery event. |
REC313-2509 | 33 - Relief and recovery | Developing detailed recovery procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2488 | 33 - Relief and recovery | The basic capacity needs of each functional recovery group and how this can be scaled up should be identified. Plans for functional recovery groups should reflect this in clear statements for every level of the system, for all relevant entities about their required function, role and responsibilities during recovery. |
REC310-2485 | 33 - Relief and recovery | Recovery plans at all levels should include transition arrangements. They should be implemented during recovery. The arrangements should: |
REC310-2484 | 33 - Relief and recovery | There remains a need to maximise the effect of all offers of assistance to recovering communities. This recommendation presents an opportunity to resolve any outstanding aspects of Recommendation 4 and Actions in Response from the Cyclone Debbie Review Action Plan: |
REC310-2481 | 22 - Role of local Gvt | Greater clarity about responsibilities for recovery at the community, local, and district levels should be considered in any future review of the Disaster Management Act (2003). |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1260 | 32 - Doctrine, standards, and reform | That DPIPWE clarifies responsibility for river restoration and riparian management and, having done so, communicates this to councils, landowners and other owners of relevant infrastructure. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
Rec-ID | Code | Recommendation |
---|---|---|
REC294-1364 | 24 - Govt responsibility | The Chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services recommend implementing the Mackay District Improvement Strategy (refer to page 53 of the inquiry). |
Rec-ID | Code | Recommendation |
---|---|---|
REC293-1336 | 32 - Doctrine, standards, and reform | The chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services, implement the Mackay Disaster District capability improvement strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC289-1226 | 32 - Doctrine, standards, and reform | IGEM recommends that Emergency Management Victoria continue to lead the development and application of a comprehensive sector wide preparedness model for integration within and across emergency management arrangements in Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2059 | 24 - Govt responsibility | Enhance business continuity planning by the Tasmanian Health Service. |
REC286-2019 | 24 - Govt responsibility | Assess water supply resilience in the case of an interruption. |
REC286-2067 | 24 - Govt responsibility | Improve integration of health information systems. |
REC286-2039 | 41 - Emergency Management exercises | Nuance the exercises for flood / dam-break / debris flow to incorporate consideration. |
REC286-2086 | 32 - Doctrine, standards, and reform | Develop SOP for recovery package. |
REC286-1445 | 41 - Emergency Management exercises | Develop, implement, review and exercise inter-agency community evacuation and recovery plans across the State. |
REC286-2058 | 24 - Govt responsibility | Clarify the relationship between the DHHS and THS in the establishment of flu services. |
REC286-2063 | 24 - Govt responsibility | Review Tas Govt interoperability arrangements. |
REC286-2033 | 24 - Govt responsibility | Incorporate heatwave surge response planning into business continuity planning. |
REC286-2082 | 41 - Emergency Management exercises | Undertake inter-agency severe storm exercises. |
REC286-2052 | 22 - Role of local Gvt | Undertake local level emergency management planning for areas at risk of debris flow. |
REC286-1481 | 32 - Doctrine, standards, and reform | Integrate clean-up arrangements into emergency plans. |
REC286-2062 | 32 - Doctrine, standards, and reform | Review State Special Emergency Plan: Human Influenza Pandemic Emergencies. |
REC286-2030 | 32 - Doctrine, standards, and reform | Develop innovative response models of patient care to improve surge capacity. |
REC286-2080 | 32 - Doctrine, standards, and reform | Formalise response triage arrangements. |
REC286-2043 | 22 - Role of local Gvt | Assessment of council’s capacity to manage land effectively. |
REC286-1470 | 32 - Doctrine, standards, and reform | Integrate Storage Operating Rules with downstream flood response plans. |
REC286-2061 | 41 - Emergency Management exercises | Review and exercise the Tasmanian Mass Vaccination Plan. |
REC286-2029 | 32 - Doctrine, standards, and reform | Create a stakeholder plan template to aid heatwave preparedness and response in facilities occupied by people vulnerable to heatwaves (e.g. nursing homes) |
REC286-2069 | 24 - Govt responsibility | Implement a database management approach for notifiable disease record systems. |
REC286-2042 | 32 - Doctrine, standards, and reform | Increased regulation of landslide risk assessment. |
REC286-2096 | 32 - Doctrine, standards, and reform | Review current all-hazards emergency management arrangements to evaluate if they adequately address Tsunami response and recovery requirements. |
REC286-1464 | 41 - Emergency Management exercises | Exercise time-critical decision making processes within the context of an earthquake scenario. |
REC286-2060 | 32 - Doctrine, standards, and reform | Develop a flexible plan for establishing flu-specific services. |
REC286-2025 | 41 - Emergency Management exercises | Exercise heatwave arrangements with a focus on the public administration sector and management of vulnerable people |
REC286-2068 | 24 - Govt responsibility | Develop a disaster client record system. |
REC286-2041 | 22 - Role of local Gvt | Development mechanisms to support small councils to manage treatment across the PPRR spectrum (across all hazards). |
REC286-2087 | 41 - Emergency Management exercises | Develop and exercise Severe Storm Emergency Management Plan. |
REC286-1462 | 32 - Doctrine, standards, and reform | Develop a strategic plan for the operation and management of the seismic monitoring network in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2523 | 32 - Doctrine, standards, and reform | The report recommends that Ambulance Tasmania regularly reviews its emergency and urgent determinants methodology to ensure that it continues to be best practice and in accordance with requirements of the National Academy of Emergency Medical Dispatch. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1531 | 32 - Doctrine, standards, and reform | Banana Shire Council completes business continuity planning as a matter of priority, including documentation and testing of the plan. |
REC271-1532 | 32 - Doctrine, standards, and reform | The evacuation sub-plan component of the Local Disaster Managment Plan should be reviewed, including any identified triggers for activation. Ideally, the plan should be tested in a live, multi-agency exercise prior to next summer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC269-1171 | 32 - Doctrine, standards, and reform | State agencies with disaster management roles and responsibilities assess their performance by including a disaster management performance measure in chief executive officers’ performance agreements. This measure should reinforce an obligation for agencies to participate in the arrangements at all levels. |
REC269-1170 | 32 - Doctrine, standards, and reform | Responsibilities of functional lead agencies and hazard-specific primary agencies are clearly articulated in state level doctrine, including the Queensland State Disaster Management Plan. |
REC269-1169 | 32 - Doctrine, standards, and reform | An integrated risk-based approach to disaster management planning for Queensland is developed that is consistent with the Standard for Disaster Management in Queensland and applicable at all levels of the arrangements. |
REC269-1168 | 32 - Doctrine, standards, and reform | The Local and District Disaster Management Guidelines are reviewed to align with the Standard for Disaster Management in Queensland. |
REC269-1167 | 32 - Doctrine, standards, and reform | That Queensland’s disaster management arrangements are reviewed to enhance integration. Specifically: · to address the disparity between functions and structure of local government and disaster groups · to integrate hazard specific agency planning at all levels of the arrangements (This may include legislative, policy and procedural considerations). |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1423 | 22 - Role of local Gvt | The State Disaster Coordination Centre Notification Matrix is reviewed to ensure local governments are notified of any event affecting, or likely to affect, their local government area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1488 | 32 - Doctrine, standards, and reform | That the Emergency Services Telecommunications Authority, assisted by Ambulance Victoria, reviews the business rules to be applied by the Emergency Services Telecommunications Authority ambulance dispatchers in selecting appropriate resources for dispatching to events, taking account of meal-break procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1567 | 24 - Govt responsibility | State and territory governments should: |
REC256-1575 | 24 - Govt responsibility | State and territory governments should develop benchmark prices for the reconstruction of essential public assets and submit these to the Australian Government for approval within one year. In developing these prices, they should consult with local governments and relevant experts, and draw on asset management plans. The prices should be reviewed and updated over time. |
REC256-1566 | 24 - Govt responsibility | State and territory governments should prioritise and accelerate implementation of the Enhancing Disaster Resilience in the Built Environment Roadmap, including reviewing the regulatory components of vendor disclosure statements. The Land Use Planning and Building Codes Taskforce should be tasked to identify and consider options for regular, low-cost dissemination of hazard information to households by governments and insurers. |
REC256-1574 | 32 - Doctrine, standards, and reform | The Australian Government should establish a framework for the development of benchmark prices for the reconstruction of essential public assets. This should set out the broad parameters that state and territory governments should follow, without prescribing particular prices to be used. |
REC256-1562 | 32 - Doctrine, standards, and reform | The Australian Government should: |
REC256-1571 | 24 - Govt responsibility | State and territory taxes and levies on general insurance should be phased out and replaced with less distortionary taxes. |
REC256-1561 | 24 - Govt responsibility | State and territory governments should be required to report on the following accountability requirements: |
REC256-1569 | 32 - Doctrine, standards, and reform | The provisions in the Queensland Sustainable Planning Act 2009 for injurious affection should be repealed. |
REC256-1568 | 24 - Govt responsibility | State governments, where they have not already done so, should provide local governments with statutory protection from liability for releasing natural hazard information and making changes to local planning schemes where such actions have been taken ‘in good faith’ and in accordance with state planning policy and legislation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC255-1578 | 32 - Doctrine, standards, and reform | The ANAO recommends that the Department of Defence review the minimum information necessary to be reported for each emergency DACC task to discharge accountability obligations, identify costs, undertake cost recovery where appropriate, maintain records for future use and learn from emergency DACC activities |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2574 | 32 - Doctrine, standards, and reform | St John Ambulance should ensure the positive gains in clinical governance achieved since the Inquiry become embedded throughout the whole organisation. |
REC252-2569 | 32 - Doctrine, standards, and reform | Western Australia Health should consider publishing information on St John Ambulance’s complaints processes to assist Western Australia Health staff. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2598 | 24 - Govt responsibility | That government considers the establishment of a separate unit to implement and operate a Whole of Government network if existing stakeholders fail to make significant progress toward an agreed Whole of Government solution. |
REC245-2596 | 24 - Govt responsibility | That the Whole of Government project’s objectives should include meeting entity requirements and the consultant be asked to reevaluate the revised set of objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2602 | 32 - Doctrine, standards, and reform | That South Australia’s Hazard Leader Plan for Rural Fire, prepared in accordance with the State Emergency Management Plan, replace the F&ES Act requirement for a separate State Bushfire Management Plan. |
REC244-2626 | 32 - Doctrine, standards, and reform | Section 70 (5) be amended to preclude a person from being elected as a group officer, brigade captain or brigade lieutenant if he or she is an employee of the CFS. |
REC244-2609 | 32 - Doctrine, standards, and reform | That the proposed ‘Permit Information Management System’ (PIMS) be implemented as soon as possible and incorporated into the Call Receipt and Dispatch process. Following implementation, amend Regulation 33 (5) (d) and (10) (c) in line with the automated notification process. |
REC244-2633 | 32 - Doctrine, standards, and reform | Amend Section 143 to strengthen the capacity of the ESOs to recover outstanding debts (e.g. penalty for late payment provisions). |
REC244-2614 | 32 - Doctrine, standards, and reform | Consider the amendment of Section 82 (2) to include the power to order the cessation of harvesting or any other actions (including the lighting of fires authorised under Section 81) that because of the weather conditions, may cause a fire, if ignited, to get out of control. |
REC244-2599 | 32 - Doctrine, standards, and reform | That the MFS, CFS and SES be incorporated into a departmental structure under the direction of a Chief Executive based on interstate developments over the past two decades, which establishes this arrangement as the benchmark for the governance of Emergency Services in Australia. The MFS, CFS and SES would operate as separate units under the ultimate direction of the CEO. |
REC244-2625 | 32 - Doctrine, standards, and reform | Sections 42 and 97 be amended to provide greater flexibility in the engagement of contractors by Senior MFS and CFS Officers. Consideration be given to providing similar powers in Section 118 to enable the SES to engage contractors. |
REC244-2608 | 32 - Doctrine, standards, and reform | Consider whether Regulation 71 be amended to extend the range of offences for which expiation fees apply to include a breach of any permit condition imposed by an authorised officer. |
REC244-2632 | 32 - Doctrine, standards, and reform | Section 142 be amended to include the SES |
REC244-2613 | 32 - Doctrine, standards, and reform | Should the State Bushfire Coordination Committee continue to exist under the F&ES Act amend Section 94 (4) (c) to refer to the ‘State Bushfire Coordination Committee’. |
REC244-2624 | 32 - Doctrine, standards, and reform | The F&ES Act be amended to clarify the meaning of ‘closure’ in Section 38 and that provisions relating to the extension and rescission of closure orders be reviewed. |
REC244-2607 | 32 - Doctrine, standards, and reform | Amend Regulation 41 to exempt the use of prescribed appliances when a Hot Work Permit compliant with AS1674.1 has been issued. |
REC244-2630 | 32 - Doctrine, standards, and reform | Clarify that Section 128 of the F&ES Act is not compromised by any other legislation. |
REC244-2612 | 32 - Doctrine, standards, and reform | Develop a code of practice which is referenced by the F&ES Act for burning off including the option to issue seasonal permits for relevant purposes throughout the State. |
REC244-2623 | 32 - Doctrine, standards, and reform | That the F&ES Act be amended to enable fire safety inspections in and outside fire districts. |
REC244-2606 | 22 - Role of local Gvt | The Act be amended to require the mandatory appointment of Authorised Officers by each rural council or council that has within its area a Designated Urban Bushfire Risk Area(s) with an option for the CFS Chief Officer to exempt council from this requirement (similar to Section 105B). |
REC244-2629 | 32 - Doctrine, standards, and reform | The power of the Chief Officer to appoint officers from the staff of the SES as well as appoint volunteer officers of the SES be clarified. A command structure section (similar to Section 70) be incorporated into the Act and include the power to register, appoint, disqualify and terminate volunteer members. |
REC244-2611 | 32 - Doctrine, standards, and reform | Review the format and necessity for Schedules 9 and 10 of the Regulations |
REC244-2636 | 32 - Doctrine, standards, and reform | Amend the F&ES Act to provide for the operation of interstate fire and emergency service workers in South Australia. The issue of liability may need to be considered. |
REC244-2622 | 32 - Doctrine, standards, and reform | Amend Sections 28, 61 and 110 to provide the Chief Officers greater flexibility over organisational structure. |
REC244-2603 | 32 - Doctrine, standards, and reform | Should the State Bushfire Coordination Committee continue to exist under the F&ES Act, then Section 71 of the Act be amended to provide for the appointment of an independent presiding member of the committee. |
REC244-2628 | 32 - Doctrine, standards, and reform | Amend the F&ES Act to reflect the SES expanded responsibilities as Hazard Leader for ‘Extreme Weather’ including their community education role. |
REC244-2610 | 32 - Doctrine, standards, and reform | Amend Regulation 33 (6) and (8) to include respectively ‘notice given’ and ‘permit application’ using the online medium. |
REC244-2635 | 32 - Doctrine, standards, and reform | The requirement to consult with members of the unit and the SESVA before an SES Unit is dissolved should remain but the need for public meetings be removed from the regulations. |
REC244-2615 | 32 - Doctrine, standards, and reform | In consultation with stakeholders including CFA, develop a Forest Industry Brigade standard for inclusion in the Fire and Emergency Services Regulations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0839 | 32 - Doctrine, standards, and reform | That noting the precedents for legislated charters in the Carers Recognition Act 2005 and the Health and Community Services Complaints Act 2004, that the Government support the Fire and Emergency Services (Volunteer Charters) Amendment Bill introduced by the Member for Morphett in November 2012 to enshrine the Country Fire Service and the State Emergency Service at law. |
REC243-0837 | 32 - Doctrine, standards, and reform | That the Government’s Workers Rehabilitation and Compensation (SAMFS Firefighters) Amendment Bill be amended to include Country Fire Service firefighters alongside Metropolitan Fire Service firefighters. |
REC243-0836 | 24 - Govt responsibility | That the Government explore as a matter of priority the transitioning to St John Ambulance SA Ltd providing non-emergency ambulance carriage services in South Australia, and be appropriately funded for doing so. |
REC243-0844 | 32 - Doctrine, standards, and reform | That the State Government give high priority to liaising with interstate and Federal processes, and offer to take a lead, on changing the climatic and fire rating arrangements to ensure these match the conditions that can create dangerous bushfire conditions at short notice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2641 | 32 - Doctrine, standards, and reform | That noting the precedents for legislated charters in the Carers Recognition Act 2005 and the Health and Community Services Complaints Act 2004, that the Government support the Fire and Emergency Services (Volunteer Charters) Amendment Bill introduced by the Member for Morphett in November 2012 to enshrine the Country Fire Service and the State Emergency Service at law. |
REC242-2639 | 24 - Govt responsibility | That the Government’s Workers Rehabilitation and Compensation (SAMFS Firefighters) Amendment Bill be amended to include Country Fire Service firefighters alongside Metropolitan Fire Service firefighters. |
REC242-2638 | 24 - Govt responsibility | That the Government explore as a matter of priority the transitioning to St John Ambulance SA Ltd providing non-emergency ambulance carriage services in South Australia, and be appropriately funded for doing so. |
REC242-2646 | 24 - Govt responsibility | That the State Government give high priority to liaising with interstate and Federal processes, and offer to take a lead, on changing the climatic and fire rating arrangements to ensure these match the conditions that can create dangerous bushfire conditions at short notice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2781 | 34 - Local knowledge | That the current provisions enabling there to be a Ministerial Direction be maintained and actioned as the Minister sees fit. |
REC239-2662 | 24 - Govt responsibility | That responsibility for prisoner transport and non-managerial roles within the larger watch-houses is transferred to Queensland Corrective Service. |
REC239-2701 | 24 - Govt responsibility | That the Inspector General Emergency Management provide continuing advice to Government on the level of interoperability in disaster management arrangements, as well as the level of interoperability being achieved within the new portfolio. |
REC239-2679 | 24 - Govt responsibility | To remove the Queensland Ambulance Service and Queensland Corrective Services from the Department of Community Safety—we recommend that it be renamed the Department of Fire and Emergency Services and be led by a Commissioner. |
REC239-2712 | 24 - Govt responsibility | That Emergency Management Queensland be integrated with the current Queensland Fire and Rescue to become the Department of Fire and Emergency Services. |
REC239-2693 | 32 - Doctrine, standards, and reform | That the presence of police in State Disaster Coordination Centre response teams is mandated and formalised through documented standard operating procedures. |
REC239-2732 | 24 - Govt responsibility | There be a formation of an Office of Portfolio Business, providing support and governance across a range of corporate functions, which are essential to the delivery of frontline services. The Review team considers that the functions of the Operations Business and Strategy Directorate should become part of that Office and that any exception should be carefully considered by those charged with implementation of approved recommendations. |
REC239-2759 | 24 - Govt responsibility | That the new Chief Executive Officer Portfolio Business be accountable for delivering the reformed Communications Centre arrangement by the 2017–18 financial year in time for the Commonwealth Games of 2018. |
REC239-2661 | 24 - Govt responsibility | That Queensland Corrective Service remains a separate program within the Department of Justice and Attorney-General so that while opportunities for improved services and efficacy can be realised, there is a clear separation from the youth justice services. |
REC239-2700 | 24 - Govt responsibility | That the position of Inspector General Emergency Management (in addition to some of the responsibilities of the chief executive officer under the current Disaster Management Act 2003) will: |
REC239-2678 | 24 - Govt responsibility | That probation and parole should continue to work together with the Queensland Police Service to reduce the risk of reoffending and reduce crime. |
REC239-2708 | 24 - Govt responsibility | That the role of the Inspector General Emergency Management not extend to conducting reviews on behalf of agencies and that the role consider the effectiveness of all agencies and how their work contributes to a whole of Government response. |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2728 | 32 - Doctrine, standards, and reform | That the Fire and Rescue Act 1990 be amended so that Commissioner’s position is not limited to a “person with professional experience in fire prevention and fire fighting”. |
REC239-2756 | 32 - Doctrine, standards, and reform | That the Chief Executive Officer Portfolio Business consider ‘big data’ problems and solutions in line with the outcome of the efficiency review into the Queensland Police Service and ensure alignment with whole of government solutions. |
REC239-2660 | 24 - Govt responsibility | That Queensland Corrective Services be transferred to the Department of Justice and Attorney-General by a machinery-of-Government change as soon as is practicable. |
REC239-2699 | 24 - Govt responsibility | That the Minister establish a public sector office to be headed by an Inspector General of Emergency Management. The Inspector General of Emergency Management will be responsible for most of the functions listed under part 16A of the current Disaster Management Act 2003. |
REC239-2676 | 32 - Doctrine, standards, and reform | That any changed arrangements to the operations of Queensland Corrective Service ensure anti-corruption, prisoner management, and accountability processes are defined and established. |
REC239-2705 | 32 - Doctrine, standards, and reform | That the Inspector General Emergency Management assess the effectiveness of plans and policy in relation to SES deployment and command and control. |
REC239-2687 | 24 - Govt responsibility | That funding, staffing and responsibility associated with administration of the NDRP be transferred from Emergency Management Queensland to the Department of Local Government, Community Recovery and Resilience. |
REC239-2721 | 24 - Govt responsibility | That the Chief Executive Officer Portfolio Business collaborate with the two portfolio Commissioners to: |
REC239-2657 | 24 - Govt responsibility | That negotiation takes place between Queensland Health and the Queensland Ambulance Service to determine the broad governance requirements of any such arrangements. |
REC239-2697 | 32 - Doctrine, standards, and reform | That the Queensland Police Service Disaster Management Unit work with emergency management staff in the new portfolio to produce the State disaster management plan. |
REC239-2755 | 32 - Doctrine, standards, and reform | That the Queensland Police Service bring this practice to the attention of the Privacy Commissioner and discuss a new service wide policy on the retention of data to ensure that their officers are not acting in breach of the law. |
REC239-2668 | 32 - Doctrine, standards, and reform | That as part of reviewing its legislation, Queensland Corrective Service should ensure that amendments be made to ensure a stronger onus is placed upon a more efficient process to receive prisoners with a view to reducing the time spent in police watch houses. |
REC239-2704 | 32 - Doctrine, standards, and reform | That the current SES memoranda of agreement between the Department of Community Safety and local governments be revised to include a clear statement as to the command and control arrangements between State and respective local governments. These arrangements should also be reflected in the local disaster management plans. |
REC239-2686 | 24 - Govt responsibility | That primacy of control should rest with the State Disaster Coordinator. This position should, by default, be the Deputy Commissioner, Regional Operations, Queensland Police Service. |
REC239-2718 | 32 - Doctrine, standards, and reform | That the Department of Fire and Emergency Services be created through the renaming and amendment to the existing Fire and Rescue Service Act 1990 including: |
REC239-2655 | 24 - Govt responsibility | That the Queensland Ambulance Service is transferred to Queensland Health by a machinery-of-Government change as soon as is practicable and that the Commissioner report directly to the Director General Queensland Health. |
REC239-2696 | 32 - Doctrine, standards, and reform | That the Queensland Police Service Disaster Management Unit be given responsibility for production of the State disaster management plan for the State Disaster Management Group’s approval. |
REC239-2749 | 24 - Govt responsibility | That the Prostitution Licensing Authority be moved to the Department of Justice and Attorney General Office of Fair Trading. |
REC239-2782 | 24 - Govt responsibility | That transparency of the Ministerial direction be achieved through publishing and monitoring for effectiveness. |
REC239-2666 | 32 - Doctrine, standards, and reform | That a system should be designed so that the prisoner and the prisoner’s prescribed drugs are treated as one and therefore travel together through the system for whatever purpose. |
REC239-2702 | 32 - Doctrine, standards, and reform | That the Queensland Police Service and SES develop clear operational protocols to ensure that SES assistance is not exploited. |
REC239-2685 | 24 - Govt responsibility | That primacy of control for disaster operations remains with the Queensland Police Service and be reinforced. |
REC239-2717 | 32 - Doctrine, standards, and reform | That the ‘Functions of Chief Executive’ under the Disaster Management Act 2003 are amended to remove those functions that will become the role of the proposed Inspector General of Emergency Management. |
REC239-2695 | 32 - Doctrine, standards, and reform | That the Disaster Management Act 2003 be amended to: |
REC239-2735 | 32 - Doctrine, standards, and reform | That the new Department of Fire and Emergency Services develop a common doctrine to protect people from fire and emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0805 | 33 - Relief and recovery | Develop a Hawkesbury-Nepean Flood Recovery Plan, which identifies strategies and arrangement for recovery from severe floods in the Hawkesbury-Nepean Valley. |
REC238-0803 | 32 - Doctrine, standards, and reform | Ensure effective flood gauging arrangements in the Hawkesbury-Nepean Valley |
REC238-0798 | 32 - Doctrine, standards, and reform | Optimise the configuration of a raised Warragamba Dam for flood mitigation of the full range of flood events and water supply, with due consideration of upstream impacts. |
REC238-0797 | 32 - Doctrine, standards, and reform | Determine the appropriateness and the steps required to allow the reduction of full supply level by up to five metres and/or the implementation of alternative gate operation at Warragamba Dam for the mitigation of minor to moderate flood events in the short-term. |
REC238-0806 | 33 - Relief and recovery | Review the adequacy of current arrangements for infrastructure reconstruction following a major flood event in the Hawkesbury-Nepean Valley. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0821 | 32 - Doctrine, standards, and reform | That the definition of “bush fire hazard reduction work” in the Dictionary of the Rural Fires Act 1997 be amended to include the establishment or maintenance of fire trails. |
REC237-0827 | 32 - Doctrine, standards, and reform | The Panel notes and endorses the NSW bush fire management system based on a multi-agency, tenure blind approach using locally focused Bush Fire Management Committees, Bush Fire Management Plans and the Bush Fire Environmental Assessment Code as best practice. |
REC237-0820 | 32 - Doctrine, standards, and reform | That the Rural Fires Act 1997 be amended to allow the Commissioner of the NSW Rural Fire Service to carry out hazard reduction on land without the consent of the owner after reasonable attempts to contact the landowner have failed, without serving a notice under section 66 of the Rural Fires Act. |
REC237-0826 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service hold discussions with the Commonwealth Department of Sustainability, Environment, Water, Population and Communities about hazard reduction and roadside vegetation, including potential changes to the NSW Bush Fire Environmental Assessment Code. |
REC237-0819 | 32 - Doctrine, standards, and reform | That section 56 of the Rural Fires Act 1997 be amended to give the Commissioner of the NSW Rural Fire Service the power to direct a Bush Fire Management Committee to amend its Bush Fire Risk Management Plan if it is inadequate, in the opinion of the Commissioner. |
REC237-0824 | 32 - Doctrine, standards, and reform | That section 100I of the Rural Fires Act 1997 be amended to allow hazard reduction certificates to be issued for annual low impact works for a period of three years, where appropriate. |
REC237-0818 | 32 - Doctrine, standards, and reform | That section 9(4)(b) of the Rural Fires Act 1997, which sets out the functions of the NSW Rural Fire Service, be amended to include protecting infrastructure, environmental, economic, cultural, agricultural and social assets from damage. |
REC237-0823 | 32 - Doctrine, standards, and reform | That section 74 of the Rural Fires Act 1997 be amended to require public authorities to report monthly to the Commissioner of the NSW Rural Fire Service on activities undertaken to reduce bush fire hazards on managed land during the preceding month and the reasons why any planned activities did not take place. |
REC237-0832 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service investigate use of appropriate modelling, such as PHOENIX RapidFire and the Bayesian Network analysis, to quantify the level of bush fire risk to critical values and assets. |
REC237-0817 | 32 - Doctrine, standards, and reform | That section 3(c) of the Rural Fires Act 1997, which sets out the objects of the Act, be extended to include protecting infrastructure, environmental, economic, cultural, agricultural and social assets from damage. |
REC237-0822 | 32 - Doctrine, standards, and reform | That section 74 of the Rural Fires Act 1997 be amended to require public authorities to report to the Commissioner of the NSW Rural Fire Service within one month of the end of the financial year on activities undertaken to reduce bush fire hazards on managed land during the preceding financial year. |
REC237-0831 | 32 - Doctrine, standards, and reform | That Bush Fire Management Committees be required to take into account fuel age and fire frequency thresholds when developing Bush Fire Risk Management Plans |
Rec-ID | Code | Recommendation |
---|---|---|
REC235-2809 | 32 - Doctrine, standards, and reform | The Australian National Audit Office recommends that the Department of Regional Australia, Local Government, Arts and Sport improve the arrangements for conducting value for money reviews of Victorian reconstruction projects by pursuing amendments to the operating protocol with Victoria to require that, at regular intervals, the Taskforce is provided with information on all reconstruction projects being delivered within the scope of the National Partnership Agreement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2811 | 32 - Doctrine, standards, and reform | In order to maximise the envisaged benefits from the Inspectorate’s program of value for money reviews, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce improve the application of the sampling approach to make it more representative of the |
Rec-ID | Code | Recommendation |
---|---|---|
REC231-2829 | 32 - Doctrine, standards, and reform | The Australian National Audit Office (ANAO) recommends that the Department of Regional Australia, Local Government, Arts and Sport, in preparation for the forthcoming reviews of the National Partnership Agreements, identify the most effective means of obtaining the project level information on the respective reconstruction programs required by the Agreements to be reported on and, if appropriate, seek amendments to the Agreements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2834 | 32 - Doctrine, standards, and reform | The committee recommends that the Attorney-General's Department facilitate a public consultation process on a regulatory framework for overflow arrangements between public safety agencies and commercial carriers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2845 | 24 - Govt responsibility | The committee recommends that the Commonwealth government works with state and territory governments to continue to implement the recommendations of the Productivity Commission report, where possible, to improve coordination in relation to climate change adaptation. |
REC229-2843 | 32 - Doctrine, standards, and reform | The committee recommends that Commonwealth, state and territory governments ensure that all facilities caring for vulnerable groups, in particular hospitals, schools, childcare and aged care facilities, have emergency management plans, relevant to their geographic settings, in place and regularly revised. |
REC229-2839 | 32 - Doctrine, standards, and reform | The committee recommends that disincentives to insurance, such as taxes and levies applied by the states and territories, should be removed as part of a national reform process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1855 | 22 - Role of local Gvt | Local government authorities incorporate into their Local Emergency Management Plans their procedures for dealing with any trauma experienced by bushfire brigade volunteers, having regard to best practice in managing trauma. |
REC222-1864 | 32 - Doctrine, standards, and reform | The Chief Executive Officer of the Fire and Emergency Services Authority request the Australasian Fire and Emergency Services Authorities Council to include a new module in the Australasian Inter-service Incident Management System to guide the provision of welfare services for emergency service workers during a disaster. |
REC222-1861 | 41 - Emergency Management exercises | The Ministers for Health, Emergency Services, Environment and Police provide additional funds to their agencies so that a detailed exercise is held on a regular basis based on a disaster that will create the worst outcome for the State. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1830 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop a code of practice on the removal of vegetation around critical public assets, in consultation with councils, CMAs and asset managers. Regional Flood Strategies will support this code of practice as part of shared flood risk management planning. |
REC217-1838 | 32 - Doctrine, standards, and reform | That statements of obligations, issued under the Water Industry Act 1994 for water authorities, be amended to include a provision whereby managing authorities must: |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1829 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment should develop guidelines for streamlining the permitting system for works on waterways for incorporation in the revised Victoria Flood Management Strategy. An exemption process will be introduced, with particular application to identified reaches of rivers and streams that require ongoing vegetation management and maintenance: |
REC217-1837 | 32 - Doctrine, standards, and reform | The state government give consideration to enacting legislation to provide protection from legal liability for public authorities conducting works on priority levees in good faith, acting reasonably and responsibly in the public interest, and in accordance with standards agreed to under approved schemes. Public authorities should not be excluded from liability if they have acted negligently. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
REC217-1828 | 32 - Doctrine, standards, and reform | The revised Victoria Flood Management Strategy should clearly articulate the policy guidelines for the management of vegetation and debris in Victorian waterways, for the purposes of flood protection and mitigation, taking into account the localised potential flooding effects of in‐stream vegetation in townships. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1820 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop guidelines for the management of levees in emergencies, during and after a flood event, which can be incorporated into local flood response plans. The department will also provide, as part of these guidelines, a set of criteria for assessing the ongoing viability of ad hoc levees post‐flood. The Emergency Management Act 1986 will be amended to support the implementation of these guidelines. A more effective means for councils to remove illegal levees will also be examined by the Department of Sustainability and Environment. |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1834 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop clear policy for the coordinated management of rural drainage, clarifying the legal framework, and identifying authorities with responsibility for the management and ongoing maintenance of formal schemes, and their development: |
REC217-1819 | 22 - Role of local Gvt | In consultation with local communities, local councils will develop flood response plans as subplans to their current Municipal Emergency Management Plans. As part of the flood risk assessment process, these plans will be informed by the best available flood mapping and modelling, and will identify agreed activities to be undertaken during floods including, where appropriate, the construction of temporary levees. The condition of levees will be incorporated into such plans to enable improved emergency response. |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1825 | 22 - Role of local Gvt | When developing flood mitigation options in lowland areas, local governments should give consideration to the use of temporary levees as an alternative or addition to permanent structures. To maximise the use of these structures and limit flood damage, and aid affordability, consideration should be given by local governments to the sharing of temporary levees among different townships and different council areas. |
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2871 | 22 - Role of local Gvt | Efficient and effective supporting tools and processes: high-quality local/municipal planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0770 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to oblige each owner of a referable dam to have an emergency action plan approved by the appropriate Queensland Government agency. Such plans should be reviewed periodically |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0749 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Water Supply (Safety and Reliability) Act 2008 to designate the Minister as the person who must approve a flood mitigation manual. |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0714 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 so that it allows for the relaxation of environmental authority conditions, by transitional environmental program or otherwise, as to discharge of water: • pre-emptively, in advance of rainfall or flooding events, or • for all mines in a catchment that is flooding. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0759 | 32 - Doctrine, standards, and reform | CS Energy should review its emergency action plan and business procedures to ensure they are wholly consistent and give appropriate consideration to flooding as a possible emergency event. |
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
REC210-0719 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Environmental Protection Act 1994 so as to permit an emergency direction to be given orally where it is not practicable to provide the direction in writing, with provision for its subsequent confirmation in writing |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0712 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to clarify the purposes for which a transitional environmental program can be granted. In particular, if the government considers the transitional environmental program the appropriate regulatory mechanism to deal with the discharge of water from mines during flood, section 330 of the Environmental Protection Act 1994 should be clarified to make it clear that it extends to that use. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0717 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 to provide a definition of the term ‘emergency’ for the purposes of section 468 of that Act. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0733 | 32 - Doctrine, standards, and reform | Emergency Management Queensland should pursue the execution of the ‘Local Arrangements’ with councils where a Memorandum of Agreement is in place. The contents of the arrangements should be reviewed and updated regularly |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0750 | 32 - Doctrine, standards, and reform | The assessment of flood mitigation manuals should be completed by a person with appropriate expertise who has had no involvement in its development, at any stage, and who can be seen to be independent of all individuals who were so involved. |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0760 | 32 - Doctrine, standards, and reform | CS Energy should amend its business procedure to remove any ambiguity as to the establishment of communications with Seqwater and to acknowledge the formal communications protocol regarding releases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2874 | 32 - Doctrine, standards, and reform | Formalise and standardise service levels provided to emergency services. |
REC207-2884 | 32 - Doctrine, standards, and reform | Focus leadership practices to re-orient culture away from customisation and experimentation and towards reliable, efficient and consistent documented processes |
REC207-2883 | 32 - Doctrine, standards, and reform | Start a project to introduce organisational process thinking with a view to standardising processes and product specifications. |
REC207-2880 | 32 - Doctrine, standards, and reform | Ensure the Bureau puts in place necessary planning and governance arrangements to develop its bid for capital funding to maintain its critical supercomputing capacity |
REC207-2875 | 32 - Doctrine, standards, and reform | Agree clear allocation of responsibilities to state and local government for flood management, with defined boundaries on the Bureau’s role and: |
Rec-ID | Code | Recommendation |
---|---|---|
REC206-1884 | 24 - Govt responsibility | The Committee recommends that the Australian Parliament pass the Insurance Contracts Amendment Bill 2011 and ensure its enactment by 1 July 2012. The Committee further recommends that the standard definition of ‘flood’ be included in the definition of Standard Cover in the Insurance Contracts Regulations 1985. |
REC206-1890 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Securities and Investments Commission amend Regulatory Guideline 165 to: |
REC206-1883 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government amend the Insurance Contracts Act 1984 (Cth) so that from 1 July 2012 any derogation from Standard Cover is required to be communicated to policyholders as a departure from ideal standards: |
REC206-1889 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government introduce legislation by 1 March 2013 to make adherence to the General Insurance Code of Practice a compulsory requirement for all general insurers. |
REC206-1882 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government amend the Insurance Contracts Act 1984 (Cth) to make it obligatory that insurers offer to consumers the option of a general insurance policy that conforms to Standard Cover, as prescribed in the Insurance Contracts Regulations 1985 (Cth), from 1 July 2012, so that all insurers carry a product that provides full replacement in the event of total loss and cover for damages resulting from flood. |
REC206-1888 | 24 - Govt responsibility | The Committee recommends that the Australian Government empower the Australian Securities and Investments Commission to regulate claims handling and settlement of financial service providers. This can be achieved by the Treasurer introducing legislation by 1 July 2012 to give effect to the measures contained in Schedule 1, Part 1 of the lapsed Insurance Contracts Amendment Bill 2010, so that breaches of the duty of utmost good faith in relation to claims handling constitute a breach of the Insurance Contracts Act. |
REC206-1887 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Securities and Investments Commission amend Regulatory Guideline 139 by 1 July 2012 to require the Financial Ombudsman Service to report regularly to the Australian Securities and Investments Commission and also to make public: |
REC206-1885 | 24 - Govt responsibility | The Committee recommends that the Australian Government introduce legislative changes required to remove the exemption for general insurers to unfair contract terms laws, and ensure its enactment by the end of 2012. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1904 | 24 - Govt responsibility | State and territory taxes and levies on general insurance constitute a barrier to effective adaptation to climate change. State and territory governments should phase out these taxes and replace them with less distortionary taxes. |
REC205-1899 | 24 - Govt responsibility | Local governments’ uncertainty about their legal liability is a barrier to effective climate change adaptation. State governments should clarify the legal liability of councils with respect to climate change adaptation matters and the processes required to manage that liability. |
REC205-1898 | 24 - Govt responsibility | To help clarify roles and responsibilities of local government for climate change adaptation, the state and Northern Territory governments should publish and maintain a comprehensive list of laws that delegate regulatory roles to local governments. This would assist both state and local governments to assess whether local governments have the capacity to discharge their roles effectively. |
REC205-1896 | 24 - Govt responsibility | Australian governments should implement policies that help the community deal with the current climate by improving the flexibility of the economy. This would also build adaptive capacity to deal with future climate change. This includes reforms to: |
REC205-1895 | 32 - Doctrine, standards, and reform | Reforms to address barriers to effective climate change adaptation should be assessed on a case-by-case basis to determine whether they are likely to deliver net benefits to the community. This should include consideration of any risks to their implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
REC199-0456 | 32 - Doctrine, standards, and reform | the state: • ensure an ‘all hazards, all agencies’ approach to Incident Action Plan compilation is developed and implemented to enable the timely issue of functional Incident Action Plans. All agency incident action planning processes should be standardised to the fullest extent possible, including consideration of a library of pro-forma Incident Action Plans; and • develop and implement mechanisms to test and ensure that agencies possess satisfactory incident action planning capability and capacity for ‘all hazards’ at all levels of operations. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0464 | 32 - Doctrine, standards, and reform | the state develop and implement a strategy that maximises the flexibility and united capacity of the Country Fire Authority and Victoria State Emergency Service to respond to emergencies. |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0469 | 32 - Doctrine, standards, and reform | the state update the current fire specific guidelines and resources for evacuation planning to take an ‘all hazards’ approach |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0454 | 32 - Doctrine, standards, and reform | the State Emergency Response Coordinator further develop the Strategic Emergency Management Assurance Team process by involving subject matter experts from relevant emergency management control agencies who are the subject of Strategic Emergency Management Assurance Team focus. |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0461 | 32 - Doctrine, standards, and reform | the state ensure: • water rescue/swift water rescue definitions, roles and responsibilities are clarified and communicated to all stakeholders to ensure common understanding • appropriate training, equipment and support is provided to those required to perform water rescue/swift water rescue. Common training programs, standards and accreditation should be utilised wherever possible to increase potential for joined up operations and maximised capability • that based upon the experiences of these flood events, an appropriate level of water rescue capacity and capability is established and maintained • flood plans (all levels) and flood emergency response planning incorporate consideration of pre-positioning of appropriate water rescue capability in the event that such services should be required; and • that revised water rescue roles, responsibilities and arrangements are clearly defined in the Emergency Management Manual Victoria and such definitions are replicated in all individual agency planning and operational documents |
REC199-0487 | 32 - Doctrine, standards, and reform | the state develop and incorporate into emergency management planning regimes plans based on geographic risk, such as sub-regional plans |
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0443 | 32 - Doctrine, standards, and reform | the state reconfigure the Victorian Emergency Management Council and the supportive committee arrangements to ensure a comprehensive, accountable, effective and integrated approach to the development of emergency management arrangements is in place for Victoria. The process should also include consideration of the Security and Emergencies Committee and Central Government Response Committee roles, functions, reporting arrangements and relationships with other state level emergency management groups. Settled arrangements must be clearly articulated to ensure stakeholder understanding. |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0459 | 32 - Doctrine, standards, and reform | the state undertake a complete review of emergency management legislation. This should include agencyspecific emergency management legislation and should focus on service interoperability and securing an ‘all hazards, all agencies’ capability |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
REC199-0467 | 32 - Doctrine, standards, and reform | the state review and align all policies and procedures for evacuation, such as the interim evacuation guidelines and the State Health Emergency Response Plan, to ensure consistency and to clarify roles and responsibilities. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0442 | 32 - Doctrine, standards, and reform | the state appoint a state emergency controller who is ultimately accountable for all major emergencies. |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0457 | 32 - Doctrine, standards, and reform | the state: • revise the Emergency Management Team Practice Note to include a template to ensure an appropriate and consistent approach to Emergency Management Team operations • provide the revised Emergency Management Team Practice Note to all stakeholders to enable familiarisation; and • ensure that there is regular exercising of Emergency Management Teams with an `all hazards’ focus. |
REC199-0484 | 32 - Doctrine, standards, and reform | the state: • assess current risk and risk mitigation strategies for essential services, with a focus on ensuring that risks are appropriately identified at all levels of emergency planning; and • ensure that the responsible authority or owner/ operator of essential services put in place appropriate strategies to mitigate any risk to service continuity |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1924 | 32 - Doctrine, standards, and reform | That the Queensland Reconstruction Authority review and approve the draft organisational policies and procedures, in the areas of human resources, finance, communications and information technology. |
REC190-1928 | 24 - Govt responsibility | That the Queensland Reconstruction Authority finalise the value for money policies and procedures, particularly those that take into account the role and responsibilities of the external service providers. |
REC190-1927 | 24 - Govt responsibility | That the Queensland Reconstruction Authority agree on and finalise the work plan and attach it as a Schedule to the Agreement as required in section 15 of the Agreement. |
REC190-1926 | 24 - Govt responsibility | That the Queensland Reconstruction Authority clarify and communicate the roles of the Lines of Reconstruction sub-committees to the Chairs of each committee. |
REC190-1925 | 32 - Doctrine, standards, and reform | That the Queensland Reconstruction Authority develop and implement policies and procedures to ensure the adequate management and security of public records in accordance with the Public Records Act 2009. |
Rec-ID | Code | Recommendation |
---|---|---|
REC186-0396 | 32 - Doctrine, standards, and reform | The committee recommends that the Commonwealth Government together with national, state and territory emergency service organisations and radio and television broadcasters, develop a secure database of up-to-date contact details for key personnel to be used during an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC180-2970 | 22 - Role of local Gvt | Councils should improve assessments of business continuity risks by: |
REC180-2969 | 22 - Role of local Gvt | Councils should strengthen governance arrangements for business continuity by: |
REC180-2973 | 22 - Role of local Gvt | Local Government Victoria should, further to its work on strengthening the oversight role of audit committees, assist councils to develop good practice approaches to implementing, overseeing and continuously improving business continuity management. |
REC180-2972 | 22 - Role of local Gvt | Councils should strengthen their continuous improvement frameworks by: |
REC180-2971 | 22 - Role of local Gvt | Councils should improve the structure, format and content of their business continuity plans to provide greater clarity on roles and responsibilities for emergencies, more specificity on continuity and recovery responses, and better integration with other council disaster recovery and emergency plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2975 | 32 - Doctrine, standards, and reform | The Department of Human Services should improve regional recovery plans through: |
REC179-2979 | 24 - Govt responsibility | The Department of Human Services should communicate strategic priorities to achieve state and regional level alignment in building recovery capacity and capability. |
REC179-2974 | 32 - Doctrine, standards, and reform | The Department of Human Services should develop practical, operational guidelines for implementing recovery at the state level. |
REC179-2976 | 41 - Emergency Management exercises | The Department of Human Services should regularly test recovery plans with partner agencies. |
REC179-2983 | 24 - Govt responsibility | The Department of Human Services should work with the State Emergency Recovery Planning Committee, regions, and other partners to facilitate understanding and ownership of roles and responsibilities for common recovery services. |
REC179-2980 | 24 - Govt responsibility | The Department of Human Services should work with regions and partner agencies at the state level to create consistent, streamlined impact assessment processes and systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2986 | 32 - Doctrine, standards, and reform | The ANAO recommends that Centrelink assess the reliability of emergency recovery payment data and reports generated from its system(s), and update the approach, standards and procedures for the collection, storage and use of the data. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0050 | 24 - Govt responsibility | SEMC and EM WA should: assess the state’s level of preparedness at least annually, identifying gaps and significant risks |
REC170-0049 | 24 - Govt responsibility | SEMC and EM WA should: formally and regularly assess which hazards the state should prepare for |
REC170-0052 | 32 - Doctrine, standards, and reform | SEMC and EM WA should: ensure agencies fulfil their obligations under the Act |
REC170-0063 | 32 - Doctrine, standards, and reform | Agencies should: ensure their Westplans and support plans have supporting local arrangements in place |
REC170-0053 | 32 - Doctrine, standards, and reform | SEMC and EM WA should: submit outstanding legislative changes to Parliament as a matter of priority |
REC170-0055 | 22 - Role of local Gvt | SEMC and EM WA should: monitor and take action to ensure local plans are in place and cover areas where the hazard could occur |
REC170-0051 | 32 - Doctrine, standards, and reform | SEMC and EM WA should: review procedures for plan preparation and approval so that agencies can prepare their plans in a more timely way |
REC170-0061 | 32 - Doctrine, standards, and reform | Agencies should: identify overlaps between Westplans and develop written procedures for these circumstances |
REC170-0064 | 32 - Doctrine, standards, and reform | Agencies should: ensure their internal emergency management arrangements are up-to-date and regularly reviewed |
REC170-0060 | 32 - Doctrine, standards, and reform | Agencies should: update out-of-date Westplans and support plans as a matter of urgency |
REC170-0054 | 22 - Role of local Gvt | SEMC and EM WA should: work with local government to ensure up-to-date, comprehensive local arrangements are in place |
REC170-0056 | 32 - Doctrine, standards, and reform | SEMC and EM WA should: define key roles within the emergency management framework |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0083 | 32 - Doctrine, standards, and reform | The Chairperson of SDMG (where leadership is not already defined in relevant National Plans) nominate a senior officer to assume overall responsibility for control and coordination of each disaster event to ensure a decisive and effective response. At Local level the Act provide for the CEO in consultation with the LDMC to appoint a public official/s with required training and competence as Local Controller. |
REC165-0099 | 32 - Doctrine, standards, and reform | The suggested summary of legislative changes guide the legislative response to the report incorporating consultation with key stakeholders at State, District and Local levels. |
REC165-0079 | 32 - Doctrine, standards, and reform | The Act be amended (Sections 45, 46, 47) to enable verbal directions in times of disaster responses from a State Controller to DDC to Local Controller, which must be committed to writing promptly to formalise the record. |
REC165-0091 | 32 - Doctrine, standards, and reform | EMQ resources be directed to continually improving, monitoring and regularly evaluating the State's Disaster Management system with a priority focus on providing support to Local Government levels including interlinking exercises involving District and State arrangements. |
REC165-0098 | 24 - Govt responsibility | The SDMG take into account key improvement initiatives and change processes suggested when deciding on an effective implementation strategy for agreed recommendations. |
REC165-0078 | 32 - Doctrine, standards, and reform | The basic tenet of a local community response as the foundation of Queensland's Disaster Management framework, with a clear description of the relationships between the levels and description of the phases of Disaster Management, needs to be more strongly emphasised in the "objects" of the legislation and "how objects are to be achieved". |
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
REC165-0097 | 24 - Govt responsibility | Revised governance arrangements be implemented involving Disaster Management Groups at the three levels supported by EMQ as outlined in this report to achieve continuous improvement in the Disaster Management arrangements in the State. A new provision in Section 5 emphasise the discretion available to all involved in the Disaster Management system to take action to prevent impending loss of life even if contrary to the agreed arrangements. |
REC165-0088 | 32 - Doctrine, standards, and reform | The State Disaster Management Act be strengthened by a description of the phases of Disaster Management with emphasis on the key elements within each phase including the recovery phase; Lead Agencies and nominated leaders in each area of Queensland for each of the four key elements of recovery be identified and provided with the appropriate training and familiarisation of their role to ensure the adequacy of planning at District and Local level throughout Queensland; Lead Agencies be responsible for maintaining strong relationships with counterparts at the Federal Government level to ensure necessary Federal support for State and Local recovery initiatives after disaster events; Response arrangements remain in place until the State Controller is satisfied that recovery leadership arrangements are in place at Local, District and State levels; Recovery leadership and support from State level remain in place until local recovery is substantially completed. |
REC165-0094 | 32 - Doctrine, standards, and reform | The Act be amended to make it clear that Disaster Controllers/Coordinators at all levels are to be authorised public officials with the necessary training and authority to properly discharge the role and provide an effective direct line of support, coordination and control of disaster events. The Act and State Plan provide guidance about appropriate role and functions of elected representatives during all disaster event phases. The Major Incidents Group and State Security Committee be merged to become the State Disaster and Security Council with role as suggested in this report. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
REC165-0093 | 32 - Doctrine, standards, and reform | The Department of Community Safety (through EMQ) be assigned in the Act with the responsibility to develop, maintain, monitor and continuously improve the State's Disaster Management arrangements and systems. The Executive Director, EMQ, be a member of SDMG with the Director-General, Department of Community Safety. The position of Executive Officer, SDMG, be assigned appropriate support roles to SDMG. An officer other than the Executive Director, EMQ, or the State Controller of a disaster event, perform the role of Executive Officer to the SDMG. A dedicated Assistant Commissioner of Police be assigned the role of control, coordination and overall responsibility for Queensland's response to disaster events other than those subject to National Plans and Agreements. |
REC165-0080 | 32 - Doctrine, standards, and reform | The State Disaster Management Plan incorporate linkages with all Lead Agencies and officers in control of National Plan or Agreement response. All of these Plans and Agreements should have a formal requirement to ensure officers in charge work within the State's Disaster Management framework to deliver Disaster Management responses. |
REC165-0084 | 32 - Doctrine, standards, and reform | The State Disaster Management Group focus on Disaster Management strategy and policy with sub-committees or appropriate levels in the Disaster Management system assigned detailed disaster planning or risk management assessment roles. New group members be provided with an induction briefing about the State's Disaster Management arrangements by the Executive Officer prior to attending their first meeting. |
REC165-0092 | 32 - Doctrine, standards, and reform | Executive Officers to DDCs be serving Police Officers. Regional and Area officers of EMQ be members of Local and District Disaster Management Groups to enable them to fulfil their Statewide support and governance roles. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0071 | 32 - Doctrine, standards, and reform | SERCon consider the establishment of a body, such as a State Recovery Committee, with responsibility for the |
REC164-0077 | 32 - Doctrine, standards, and reform | SERCon consider the continued development of a State Recovery Sub-Plan (including complementary local and district |
REC164-0076 | 32 - Doctrine, standards, and reform | SERCon consider meeting with the State Emergency Management Committee, Directors General and agency heads to |
REC164-0072 | 32 - Doctrine, standards, and reform | SERCon consider that the proposed State Recovery Committee review the recommended considerations arising from |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3031 | 32 - Doctrine, standards, and reform | That National Offshore Petroleum Safety Authority develop a robust risk assessment matrix for use in assessing and responding to the changing risk associated with each facility and the operator. Further, we recommend that National Offshore Petroleum Safety Authority increase auditing frequency and duration to audit each manned facility on average twice per year (covering each staff swing), but more often if the risk matrix indicates this is necessary; and that audits should average several days actually on major facilities. |
REC161-3037 | 32 - Doctrine, standards, and reform | We recommend that the Commonwealth undertake legislative change that will ensure that when any floating facility reverts to a ‘navigable form’, the relevant provisions of the Navigation Act and the OHSMI Act will apply regardless of any voyage criteria. This will help to ensure that all Australian seafarers are covered. |
REC161-3024 | 32 - Doctrine, standards, and reform | That the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations 1996 Regulations be amended to ensure that the safety case for a floating facility specifically identifies when command structure changes occur (which may be well before departing the site and associated zone). We also recommend that the Offshore Petroleum and Greenhouse Gas Storage Act 2006 be amended so that a vessel becomes a facility when any part of it comes within 500 metres of the site and continues to be a facility until no part of the |
REC161-3029 | 32 - Doctrine, standards, and reform | In relation to safety case development and compliance overall, that National Offshore Petroleum Safety Authority revise its approach to interacting with operators prior to the safety case assessment process and subsequently and direct more resources into its advisory functions. We further recommend that National Offshore Petroleum Safety Authority develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on latest information, including the interaction with the operator. Implementation should be reviewed at a senior level within National Offshore Petroleum Safety Authority. |
REC161-3036 | 32 - Doctrine, standards, and reform | That the Commonwealth and States/Northern Territory legislate to establish a properly resourced and empowered independent national safety investigation capacity to investigate serious oil and gas industry (including pipeline) incidents including near miss events that could have led to a major accident event. We further recommend that the regulatory investigatory powers under the Offshore Petroleum and Greenhouse Gas Storage Act 2006 be reviewed in the context of powers for the proposed independent national safety investigator, noting that the regulator must retain those investigatory powers necessary in order to fulfil its legislative functions. |
REC161-3023 | 32 - Doctrine, standards, and reform | That the Commonwealth undertake legislative change that will ensure that when any floating facility reverts to a ‘navigable form’, the relevant provisions of the Navigation Act and the OHSMI Act will apply regardless of any voyage criteria. This will help to ensure that all Australian seafarers are covered. |
REC161-3028 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources continue to support a duty of care safety case regime for best practice offshore petroleum industry regulation augmented to include regulation of integrity. Since the safety case is at the centre of the duty of care co-regulatory regime, we consider that the requirement for the implementation of the safety case at facilities involved in the exploitation of petroleum resources should be provided for within the Offshore Petroleum and Greenhouse Gas Storage Act 2006 itself. |
REC161-3035 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources liaise with Ministers with environmental and planning responsibilities, and if necessary Council of Australian Governments, to ensure that environmental requirements for oil and gas projects are not imposed subsequent to safety assessments and do not increase the risk of major accident events. |
REC161-3040 | 32 - Doctrine, standards, and reform | We recommend the Commonwealth consider a plain English rewrite of the Navigation Act 1912 with the aim of producing a modern, performance-based Act. |
REC161-3027 | 32 - Doctrine, standards, and reform | That powers should be conferred on National Offshore Petroleum Safety Authority to enable it to effectively regulate safety and integrity for all facilities and pipelines in the water and the WA islands which export gas by pipeline. National Offshore Petroleum Safety Authority’s authority should extend to the nearest valve on the mainland above the shore crossing. |
REC161-3033 | 32 - Doctrine, standards, and reform | That the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations 1996 regulations be amended to explicitly enable assessment of safety culture, leadership, and consideration of operator past history, motivation and current capacity in approvals of safety cases. National Offshore Petroleum Safety Authority should be able to audit against these criteria and challenge operators on these issues. |
REC161-3039 | 32 - Doctrine, standards, and reform | We recommend that AMSA should have a role in assuring continuing marine standards that are not inconsistent with Offshore Petroleum and Greenhouse Gas Storage Act (OPGGS) Act provisions and that AMSA needs defined powers to assist NOPSA in minimising risk in the offshore petroleum industry. Potential mechanisms for achieving this outcome include: providing AMSA with defined powers and obligations under the OPGGS Act, thereby ensuring that the Authority becomes an effective inspector/regulator of vessels while they are deemed to be facilities; or revising the current Commonwealth maritime legislation disapplication provisions of the OPGGS Act with the aim of achieving the same goal. If it can be readily achieved and is an efficient regulatory option, we believe the first option is preferable. |
REC161-3026 | 32 - Doctrine, standards, and reform | That the Commonwealth consider a plain English rewrite of the Navigation Act 1912 with the aim of producing a modern, performance-based Act. |
REC161-3032 | 32 - Doctrine, standards, and reform | That the Offshore Petroleum and Greenhouse Gas Storage Act 2006 and its subsidiary regulations be amended to enable National Offshore Petroleum Safety Authority to have a broader range of graduated compliance tools including the ability to impose a civil fine on an operator per day of non compliance with an improvement or prohibition notice. Legislation should also be considered that would enable National Offshore Petroleum Safety Authority to make public, with appropriate safeguards, specific information concerning its enforcement actions including the name of the operator, the breach, and the enforcement action required including potential penalties. |
REC161-3038 | 32 - Doctrine, standards, and reform | We recommend that the Commonwealth Petroleum (Submerged Lands) (Management of Safety on Offshore Facilities) Regulations (MOSO) be amended to ensure that the safety case for a floating facility specifically identifies when command structure changes occur (which may be well before departing the site and associated zone). We also recommend that the OPGGS Act be amended so that a vessel becomes a facility when any part of it comes within 500 metres of the site and continues to be a facility until no part of the vessel remains within 500 metres of the site. |
REC161-3025 | 32 - Doctrine, standards, and reform | That Australian Maritime Safety Authority should have a role in assuring continuing marine standards that are not inconsistent with Offshore Petroleum and Greenhouse Gas Storage Act 2006 provisions and that Australian Maritime Safety Authority needs defined powers to assist National Offshore Petroleum Safety Authority (NOPSA) in minimising risk in the offshore petroleum industry. Potential mechanisms for achieving this outcome include: providing Australian Maritime Safety Authority with defined powers and obligations under the Offshore Petroleum and Greenhouse Gas Storage Act 2006, thereby ensuring that the Authority becomes an effective inspector/regulator of vessels while they are deemed to be facilities; or revising the current Commonwealth maritime legislation disapplication provisions of the Offshore Petroleum and Greenhouse Gas Storage Act 2006 with the aim of achieving the same goal. If it can be readily achieved and is an efficient regulatory option, we believe the first option is preferable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3061 | 32 - Doctrine, standards, and reform | ACTAS should develop and implement policies and guidance to staff on how complaints should be assessed and actioned, including timeliness targets. |
REC159-3051 | 32 - Doctrine, standards, and reform | ACTAS should: |
REC159-3060 | 32 - Doctrine, standards, and reform | ACTAS should develop a policy that provides direction on what type of feedback it will seek, from whom it will seek the feedback, and how this feedback will be used to improve the patient care experience. |
REC159-3057 | 32 - Doctrine, standards, and reform | ACTAS should conduct formal reviews of its clinical procedures manuals in consultation with its Clinical Advisory Committee, and develop guidance to oversight these reviews. |
REC159-3056 | 32 - Doctrine, standards, and reform | ACTAS should specify and document the role of each of its various clinical governance processes, how they relate to each other, and how these will be managed, measured and monitored within an overarching clinical framework. |
REC159-3053 | 32 - Doctrine, standards, and reform | ACTAS should develop policies and guidelines to assist ambulance officers’ decisions on whether or not to transport a patient to hospital. This guidance might include appropriate responses when a mentally impaired patient declines transport or treatment, and when to call on management or clinical guidance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC152-3405 | 32 - Doctrine, standards, and reform | Clarity of Role with regard to legislative and policy requirements |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3082 | 32 - Doctrine, standards, and reform | The Regulations be amended to include appropriate references to the Unit Managers Advisory Group (SASES) consistent with those of the Group Committee (SACFS). |
REC151-3100 | 32 - Doctrine, standards, and reform | Section 70(12) (relating to disciplinary action) be amended to include, where the officer is an employee of a government agency, the Chief Officer shall advise an appropriate representative of the agency prior to any disciplinary action being taken. |
REC151-3088 | 32 - Doctrine, standards, and reform | Sections 68 and 116 – provisions relating to the establishment/dissolution of SACFS Brigades and SASES Units be amended so as to retain the head of power in the principal FES Act and that the procedural provisions within each of these sections be placed in the Regulations. |
REC151-3104 | 32 - Doctrine, standards, and reform | SAFECOM in consultation with SAMFS consider the merits of amending Sections 49- 51 to replace the right to appeal from the District Court to the South Australian Industrial Relations Commission. |
REC151-3069 | 32 - Doctrine, standards, and reform | Consistent with the requirement for Emergency Service Organisations, the FES Act be amended to require South Australian Fire and Emergency Commission (SAFECOM) to submit a workforce plan to the Board. |
REC151-3073 | 32 - Doctrine, standards, and reform | Sections 56 and 83 be repealed and replaced with a single section which unifies their provisions. |
REC151-3093 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to, ‘an officer of the National Parks and Wildlife Service’ this be removed and replaced with, ‘an officer of the Department for Environment and Heritage’. |
REC151-3111 | 32 - Doctrine, standards, and reform | Crown law opinion be obtained as to what amendments, if necessary or appropriate, are required to satisfy Recommendation 29.9(7) of the Wangary Coronial Inquest, that a dedicated bushfire prevention officer be appointed. |
REC151-3097 | 32 - Doctrine, standards, and reform | Regulation 8(4)(b) be amended to allow persons of or above 16 years of age to register as fire-fighters. |
REC151-3087 | 32 - Doctrine, standards, and reform | Section 90 – provisions relating to smoking, and throwing burning material be removed from the principal FES Act and placed in the Regulations. |
REC151-3103 | 32 - Doctrine, standards, and reform | Provisions be included in the Regulations for mediation in appropriate circumstances. |
REC151-3068 | 32 - Doctrine, standards, and reform | The FES Act be amended so as to allow the Chief Executive (CE) to manage the Commission (SAFECOM) Office by removing provisions relative to the SAFECOM Board’s managerial and administrative oversight of the Commission. |
REC151-3072 | 32 - Doctrine, standards, and reform | Provisions in the FES Act relating to, “land management principles” be reviewed in consultation with appropriate agencies and having due regard to the recommendations of the Wangary Coronial Inquest. |
REC151-3081 | 32 - Doctrine, standards, and reform | So as to increase the pool of volunteers from which the Minister can appoint Advisory Board members, Section 18(3)(c) and (d) be amended to include nominations from the Group Committee (SACFS) and Unit Managers Advisory Group (SASES). |
REC151-3096 | 32 - Doctrine, standards, and reform | All Regulations relating to constitutions be deleted; the FES Act be amended to allow the Chief Officers to prescribe the constitution; and the process for the management of a SACFS brigade/group and a SASES unit to be in the form of an administrative instruction. |
REC151-3086 | 32 - Doctrine, standards, and reform | Section 88 – requirement to carry fire extinguishers in a caravan be removed from the principal FES Act and placed in the Regulations. |
REC151-3102 | 32 - Doctrine, standards, and reform | Regulations 22 and 62 be reviewed to ensure reports regarding conduct must be relevant to the enquiry. |
REC151-3065 | 32 - Doctrine, standards, and reform | The FES Act be amended to create the position which currently has the working title of ‘Commissioner of Fire and Emergencies’ to replace the position of CE and that the FES Act be amended in places where this position is mentioned. |
REC151-3091 | 32 - Doctrine, standards, and reform | Regulation 48 regarding prescribed offences be amended to include Section 79(2)(e) or its equivalent under the amendment proposed in Recommendation 22 above. |
REC151-3110 | 32 - Doctrine, standards, and reform | Further to Recommendations 11 and 12 above concerning the joining of Sections 56 and 83 of the FES Act, that these existing provisions be examined to determine whether they provide sufficient authority to address Recommendation 29.9(4) of the Wangary Coronial Inquest so as to require the owners or occupiers of rural land to create fire breaks and/or the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
REC151-3076 | 32 - Doctrine, standards, and reform | Provisions in Section 11(1)(e)(i) and (ii) relating to appointments of volunteer associations to the SAFECOM Board be removed. |
REC151-3095 | 24 - Govt responsibility | SAFECOM re-evaluate and determine a more meaningful definition of fire districts. |
REC151-3085 | 32 - Doctrine, standards, and reform | With the implementation of the Ministerial Review of Bushfire Management in South Australia, consideration should be given to provisions within Part 4, Division 7 of the principal FES Act which would be more appropriately placed in the Regulations. |
REC151-3101 | 32 - Doctrine, standards, and reform | Divisions and Subdivisions and Regulations 22 and 62 headings relating to conduct and discipline be changed to have similar wording and should include, “Conduct, Discipline and Grievance Procedures for Members”. |
REC151-3064 | 32 - Doctrine, standards, and reform | The FES Act be amended to include a definition of ‘operations’ and/or ‘operational’. |
REC151-3090 | 32 - Doctrine, standards, and reform | Following the amendment to Section 79 as proposed above in Recommendation 22, a definition of, ‘properly constructed fire place’ and ‘properly constructed incinerator’ be included in the new Regulation. |
REC151-3106 | 32 - Doctrine, standards, and reform | A schedule for revocation of permits be included in the Regulations. |
REC151-3071 | 24 - Govt responsibility | The comprehensive prevention, preparedness, response and recovery (PPRR) approach to the management of bushfires as recommended by the Ministerial Review of Bushfire Management in South Australia is supported: its implementation should consider issues raised by councils and should also be considerate of the recommendations of the Wangary Coronial Inquest. |
REC151-3075 | 32 - Doctrine, standards, and reform | Section 92 include the facility to issue a warrant for the relevant authority to break into land or buildings for the purposes of determining what measures have been taken for the prevention, control or suppression of fire or for the prevention of, or for dealing with, the escape of hazardous materials; and that costs and expenses in doing so are recoverable. |
REC151-3094 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to ‘South Australian Volunteer Fire-Brigades Association’ this be removed and replaced with, ‘Country Fire Service Volunteers Association’. |
REC151-3084 | 32 - Doctrine, standards, and reform | Section 79(1) – provisions relating to lighting or maintaining a fire in the open air during the fire danger season be retained in the principal FES Act; Section 79(2) be amended to provide that a fire may be lit or maintained in accordance with the Regulations; provisions specifying the conditions under which a fire can be lit or maintained, and currently under Section 79(2), be placed in the Regulations. |
REC151-3063 | 32 - Doctrine, standards, and reform | The preamble of the Fire and Emergency Services (FES) Act be amended to include a stronger emphasis on the strategic and policy purposes of the Commission, highlighting its key role in the governance of the emergency services sector. |
REC151-3089 | 32 - Doctrine, standards, and reform | The definition of ‘officer’ in Section 3 be amended to include reference to the designation being made by the Chief Officer. |
REC151-3105 | 32 - Doctrine, standards, and reform | With the implementation of the Ministerial Review of Bushfire Management in South Australia, the provisions in Sections 84 and 85 be reviewed in terms of enforcing hazard reduction on council or Crown land. |
REC151-3070 | 32 - Doctrine, standards, and reform | Crown law opinion be obtained to determine whether additional functions now undertaken by the Commission following the devolvement of the functions of the Security and Emergency Management Office (SEMO) require an amendment to the FES Act. |
REC151-3074 | 32 - Doctrine, standards, and reform | Sections 56 and 83 (amended as suggested above) include the facility to issue a warrant for the relevant authority to break into land or buildings to carry out requirements regarding flammable undergrowth or material; and that costs and expenses in doing so are recoverable. |
REC151-3094 | 32 - Doctrine, standards, and reform | Where in the FES Act reference is made to ‘South Australian Volunteer Fire-Brigades Association’ this be removed and replaced with, ‘Country Fire Service Volunteers Association’. |
Rec-ID | Code | Recommendation |
---|---|---|
REC147-3190 | 32 - Doctrine, standards, and reform | The ANAO recommends that, to facilitate EMA’s response to requests for assistance in overseas emergency management situations, a statement of the broad principles, responsibilities and performance expectations to apply when EMA is involved in overseas operations be developed and agreed between EMA, DFAT, AusAID and other relevant stakeholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC146-3192 | 32 - Doctrine, standards, and reform | The committee recommends, in accordance with the findings of the Hawke Taskforce, that CASA's Regulatory Reform Program be brought to a conclusion as quickly as possible to provide certainty to industry and to ensure CASA and industry are ready to address future safety challenges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3219 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3230 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3240 | 32 - Doctrine, standards, and reform | The Committee recommends that proposals for a National Oceans and Coast Act and a statutory Coastal Council be the subject of ongoing consideration once the Intergovernmental Coastal Zone Agreement is determined. |
REC145-3217 | 24 - Govt responsibility | The Committee recommends that the Australian Government, through the Council of Australian Governments process, examine the establishment of a system of national coastal zone environmental accounts, employing the model developed by the South East Queensland Healthy Waterways Partnership. |
REC145-3226 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3239 | 24 - Govt responsibility | The Committee recommends that the Australian Government establish a National Coastal Advisory Council to: |
REC145-3208 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government, through the Ministerial Council for Police and Emergency Management, recognise the extensive Surf Life Saving Australia network and take appropriate steps to integrate this network into emergency services preparedness, planning, and response systems and activities. |
REC145-3224 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3238 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government: |
REC145-3223 | 24 - Govt responsibility | The Committee recommends that the Australian Government urgently commission a detailed climate change vulnerability assessment for Kakadu National Park, in consultation with the park’s traditional owners and other stakeholders and drawing on the results of the ‘first pass’ National Coastal Vulnerability Assessment of the park. This assessment should specifically focus on the vulnerability of Kakadu’s freshwater wetland systems to saltwater intrusion. A key outcome of the assessment should be the development of a Climate Change Action Plan for Kakadu National Park, with coordinated input from the Australian Government and Northern Territory Government, Indigenous land owners, researchers and other stakeholders. |
REC145-3237 | 24 - Govt responsibility | The Committee recommends that the Australian Government, in cooperation with state, territory and local governments, and in consultation with coastal stakeholders, develop an Intergovernmental Agreement on the Coastal Zone to be endorsed by the Council of Australian Governments. The intergovernmental agreement should: |
REC145-3197 | 32 - Doctrine, standards, and reform | The Committee recommends that the coastal zone component of the National Climate Change Science Framework and proposed National Climate Change Science strategy be clearly identified by the proposed high level coordination group and involve key coastal stakeholders. |
REC145-3221 | 24 - Govt responsibility | The Committee recommends that the Australian Government, in considering its response to the Independent Review of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act), take into account concerns about the EPBC Act and coastal zone management raised as part of this inquiry—in particular, the need to address the cumulative impacts of coastal development. This could be achieved by numerous means, including: |
REC145-3231 | 22 - Role of local Gvt | The Committee recommends that the Australian Government request that the Centre for Excellence for Local Government ensure a particular focus on capacity building for coastal local councils. Capacity building should focus on addressing issues relating to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3394 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government develops a joint strategic bushfire management plan with the NSW Government and the NSW Rural Fire Service in relation to those areas which have the potential to impact on both jurisdictions. |
REC144-3382 | 24 - Govt responsibility | The Committee recommends that responsibility for oversighting the progress of the implementation of agreed recommendations of the Coroner be undertaken by a truly independent body and not by the Bushfire Council. |
REC144-3388 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government re-investigate the suitability of the Fairbairn site as a proposed centralised accommodation facility for emergency services. |
REC144-3392 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government finalise Version 2 of the Strategic Bushfire Management Plan as required under the Emergencies Act. |
REC144-3381 | 32 - Doctrine, standards, and reform | The Committee recommends that the Bushfire Council consultative requirements under the Emergencies Act 2004 be reviewed, with a view to removing the requirement to consult with the Bushfire Council on operational matters, such as staff appointments and matters prescribed by regulation. |
REC144-3386 | 24 - Govt responsibility | The Committee considers that the ACT Government should table in the ACT Legislative Assembly the cost-benefit analysis and business plan for Fairbairn as a central site for emergency services in the ACT. |
REC144-3391 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government explain its reasons to the Legislative Assembly for not proceeding with the release of Version 2 of the Strategic Bushfire Management Plan in July 2005. |
REC144-3380 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government develop and publish an operational policy document which spells out the command and control structures and procedures should an emergency event arise. |
REC144-3385 | 41 - Emergency Management exercises | The Committee recommends that the ESA hold discussions with NSW with a view to developing a joint exercise program with the NSW Rural Fire Service on an ongoing basis. |
REC144-3390 | 24 - Govt responsibility | If the ACT Government decides to proceed with the site as the emergency services headquarters, that it accord a high priority to the finalisation of the site preparations for the ESA at Fairbairn as a matter of urgency. |
REC144-3384 | 41 - Emergency Management exercises | The Committee recommends that the ESA develop a schedule of proposed exercises as a five year rolling plan, in order that all the elements of emergency services are able to be tested over that time and in differing |
REC144-3389 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government make a public announcement about the future accommodation plans for the Emergency Services Agency and its component parts so that both the ESA and the ACT public are informed about current proposals and timeframes. |
REC144-3383 | 32 - Doctrine, standards, and reform | The Committee recommends that, if the Bushfire Council is to have an advisory role generally in emergency management, it should be renamed to reflect a general emergency role rather than a role specifically in relation to bushfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3584 | 32 - Doctrine, standards, and reform | That the guidelines of WANDRA be revised to provide for the inclusion of the cost of materials expended in the repair of boundary fences. |
REC143-3583 | 33 - Relief and recovery | That the newly proposed index linked limits for Personal Hardship and Distress Relief Payments as outlined in the paper “National Disaster Relief Arrangements - An Analysis and Recommendations for Personal Hardship Distress Measures” be accepted by government. |
REC143-3578 | 32 - Doctrine, standards, and reform | That Fire and Emergency Services Authority of Western Australia (FESA), in consultation with local governments, develop and make broadly available Western Australian Natural Disaster Relief Arrangements (WANDRA) guidelines with a view to improving pre-disaster awareness of assistance measures and application processes. |
REC143-3588 | 33 - Relief and recovery | That, in line with recommendations contained in the 2004 Report to the Council of Australian Governments, greater flexibility should be introduced to WANDRA to enable damaged infrastructure to be upgraded to a more resilient standard where that is both feasible and cost-effective. |
REC143-3585 | 33 - Relief and recovery | That the Professional Assistance Grant is formally extended by WANDRA to include non rural businesses and that it be made available to assist with the clean up of disaster related damage to farms and businesses. (The Committee recognises that the amendments to WANDRA as of March 2007 address this recommendation). |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3575 | 24 - Govt responsibility | The preferred model for the Tasmanian Medical Retrieval Services is to have TMRS and NETS staff based in RHH. The fixed wing would remain based in Launceston (for the present) with the helicopter to remain based in Hobart. |
REC140-3572 | 32 - Doctrine, standards, and reform | A DHHS website be developed to list policies, procedures and guidelines relevant to critical care retrieval including the NETS policies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |
REC125-3895 | 32 - Doctrine, standards, and reform | That all agencies develop drainage asset management plans, consistent with best practice, and that these incorporate: |
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3882 | 41 - Emergency Management exercises | The Office of the Emergency Services Commissioner convene a working group of key emergency services and emergency management agencies to develop a flow chart based on scenario testing, to support decision making and the assessment of response requirements to medical, hazardous materials and CBR emergencies including their transition from one type to another. |
REC123-3881 | 32 - Doctrine, standards, and reform | Reference to the Aviation Rescue and Fire Fighting service in Part 6 of the Emergency Management Manual Victoria, table of control and support agencies, be extended to include its responsibility for hazardous materials emergencies at the airport. |
REC123-3880 | 32 - Doctrine, standards, and reform | Victoria Police, Melbourne Airport management, airlines and emergency services develop a Memorandum of Understanding for media coordination and public communications at Melbourne Airport that documents the responsibility for media coordination during emergencies to Victoria Police. |
REC123-3879 | 32 - Doctrine, standards, and reform | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan, to consider the use of alternative locations for staging, evacuation, assembly and incident coordination, to increase separation of emergency operations from non emergency activity be adopted. |
REC123-3878 | 32 - Doctrine, standards, and reform | Melbourne Airport management, the emergency services and airlines develop risk based tactical plans that, where safe and appropriate, allow the staged or progressive closure or re-opening of terminal space to support continuity of airport operations during emergencies. |
REC123-3874 | 32 - Doctrine, standards, and reform | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan to confirm that planning and response arrangements appropriately consider the protection of public safety, the current security environment and the timely restoration of airport operations, and that it is consistent with state emergency response planning arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3647 | 32 - Doctrine, standards, and reform | It is recommended that the Board: |
REC119-3646 | 32 - Doctrine, standards, and reform | It is recommended that the Board develop response time standards for metropolitan and rural rescue services to guide committees in determining the number, type and location of rescue units (page 25). |
REC119-3645 | 32 - Doctrine, standards, and reform | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2105 | 24 - Govt responsibility | The Working Group recommends that the adequacy of existing national mortuary capability to meet the likely demands of a catastrophic disaster be assessed by State/Territory Coroners. This assessment should also consider the need for a mobile mortuary capability and involve discussions with the Australian Federal Police. |
REC116-2118 | 24 - Govt responsibility | The Working Group recommends that State/Territory Recovery Committees review their membership to ensure that it is reflective of community needs, including representation from the Insurance Disaster Response Organisation. |
REC116-2125 | 24 - Govt responsibility | The Working group recommends that the Australian Government take a leadership role with regard to addressing the national capability issues identified within this review. Further, that the States/Territories recognise and accept the collaborative nature of developing national capability and commit through engagement and consultation to assisting the Australian Government in this task. |
REC116-2103 | 33 - Relief and recovery | The Working Group recommends that jurisdictions plan for the logistics of supply and delivery of meals to large numbers of homebound persons in an attempt to identify possible ways of resolving existing shortcomings. |
REC116-2117 | 33 - Relief and recovery | The Working Group recommends that potential shortfalls in the capacity to deal with large numbers of unprotected children and other special needs groups in a catastrophic event be referred to the Disaster Recovery Sub Committee of Community Services Ministers’ Advisory Council (CSMAC) for consideration and report back. |
REC116-2124 | 32 - Doctrine, standards, and reform | The whole of government disaster plan should also be written in such a way as to manage continuity of national government, ensure delivery of key services for which the Australian Government has responsibility and establish (or document existing) command and control mechanisms. |
REC116-2100 | 32 - Doctrine, standards, and reform | The Working Group recommends that agreed national protocols be developed to manage the integration of overseas workers and international aid into an affected jurisdiction. |
REC116-2115 | 41 - Emergency Management exercises | The Working Group recommends that the results of the scenario modeling be presented to the Australian Emergency Management Committee (AEMC) upon completion, and that AEMC form Sub Working Groups of State/Territory emergency management representatives as appropriate to be tasked with considering response and recovery capability (both state/territory and national) against the identified consequences. |
REC116-2123 | 24 - Govt responsibility | The Working Group recommends that the Australian Government consider developing an overarching whole of government disaster plan that clearly articulates authority, roles and responsibilities of agencies, inter-departmental committees and key officials, to link the range of existing Australian Government disaster plans. |
REC116-2099 | 32 - Doctrine, standards, and reform | The Working Group recommends that a review of the operation of the Commonwealth Mutual Recognition Act 1992 be conducted and that agreed national protocols be developed to manage the integration of |
REC116-2129 | 41 - Emergency Management exercises | The Working Group recommends that Emergency Management Australia and the jurisdictions through the AEMC develop a three year rolling national exercise strategy aimed at testing the response and recovery aspects of large scale disasters. |
REC116-2109 | 24 - Govt responsibility | The Working Group recommends that participants in the exercises designed to test continuity of executive government plans and procedures should be the office holders themselves. |
REC116-2122 | 33 - Relief and recovery | The Working Group recommends that States/Territories consider their ability to house large numbers of domestic pets, and where necessary, develop plans and arrangements that facilitate this need. |
REC116-2128 | 32 - Doctrine, standards, and reform | The Working Group recommends that jurisdictions review their emergency management arrangements (plans, legislation, etc) to ensure that they are able to mitigate, respond to and recover from disasters, and maximise the duration of self reliance that can be achieved. |
REC116-2108 | 24 - Govt responsibility | The Working Group recommends that all States/Territories and the Australian Government should regularly (annually) test their continuity of executive government plans and contingencies. |
REC116-2120 | 33 - Relief and recovery | The Working Group recommends that the National Recovery Coordinators Group considers the issue of emergency relief centres in the context of catastrophic disaster with a view to assisting jurisdictions to plan for the need to accommodate thousands of people following a disaster. |
REC116-2126 | 24 - Govt responsibility | The Working Group recommends the Australian Emergency Management Committee note that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3942 | 32 - Doctrine, standards, and reform | It is recommended that public sector entities establish frameworks which will provide for more effective governance over business continuity management. |
REC111-3938 | 32 - Doctrine, standards, and reform | To ensure an effective and co-ordinated approach to communication throughout the Queensland disaster management system, it is recommended that — |
REC111-3936 | 24 - Govt responsibility | To enhance the governance of the Queensland disaster management system, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services ensure that — |
REC111-3935 | 24 - Govt responsibility | To provide the strategic leadership and governance required to implement the Disaster Management Act 2003, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable governance framework for disaster management which includes the establishment of — |