Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4222 | 4 - Fire season preparation | The Inspector-General Emergency Management recommends the Department of Environment and Science undertake a review of campfire locations on K’gari, including all relevant signage on and off the island, maps and visitor permit information, to promote a consistent message about lighting campfires on K’gari. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4204 | 4 - Fire season preparation | We recommend that DEWLP and CFA (in consultation with FRV) in partnership with councils, provide advice to government in line with the Safer Together: A new approach to reducing the risk of bushfire in Victoria policy on options to better resource the assessment of risk on private land, its treatment and activities to enforce compliance of land owners with risk-reduction treatments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4175 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – supported by other organisations with a legislated responsibility for fuel management – plan for and increase the application of non-burning fuel management treatments including mechanical means. The annual fuel management report should include the non-burn component of fuel management treatment, track annual change, and provide a comparison to the previous three years. |
REC318-4170 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that responder agencies and Emergency Management Victoria review preparedness arrangements to ensure procedural documentation (including plans), recruitment, briefings and training are completed before significant seasonal events are likely to occur. Seasonal preparedness should culminate in attestations of assurance to confirm that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4108 | 4 - Fire season preparation | Australian, state and territory governments should review the assessment and approval processes relating to vegetation management, bushfire mitigation and hazard reduction to: |
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4107 | 4 - Fire season preparation | Public land managers should clearly convey and make available to the public their fuel load management strategies, including the rationale behind them, as well as report annually on the implementation and outcomes of those strategies. |
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
REC317-4087 | 4 - Fire season preparation | State and territory governments, working with local governments and fire and emergency service agencies, should ensure that there are appropriate arrangements for roadside vegetation management that take into account, among other things: |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
REC317-4066 | 2 - Emergency powers | The Australian Government should make provision, in legislation, for a declaration of a state of national emergency. The declaration should include the following components: |
REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3838 | 29 - Operational Health and Safety | That, in order to ensure all NSW RFS members can access the mental health support they need, the NSW RFS expands in-house mental health support for members. |
REC315-3829 | 4 - Fire season preparation | That, in order to ensure outcomes-based roadside vegetation management to reduce roadside tree fall and grass ignitions in planning and preparing for bush fire, Transport for NSW, working with local government and NSW RFS, establish a consistent framework for roadside vegetation management that analyses road priority, utility, amenity, strategic value and risk. The framework should: |
REC315-3821 | 4 - Fire season preparation | That government agencies managing land (at all levels and through all agencies) be the best neighbours possible by considering their neighbours when undertaking activities related to bush fire preparation and having clear, two-way communication about these activities, with the aspiration that government landholders will be seen as highly desirable neighbours. |
REC315-3840 | 29 - Operational Health and Safety | That, in order to ensure firefighter sustenance is of sufficient volume and quality, the NSW RFS reviews food standards and procedures in consultation with volunteers. The review should include catering service standards, including food safety, as well as the viability of sourcing commercial contracts and providing 12-hour food packs to firefighters. |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3839 | 29 - Operational Health and Safety | That, to ensure firefighters can access mental health support through GPs, Government work with the Commonwealth Government to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2407 | 39 - Disaster Risk Management | Discontinue the automatic allocation of Fire Warden powers to Council and Committee members and substitute an option for members to be appointed as Fire Wardens. |
REC304-2416 | 4 - Fire season preparation | Establish a capacity to prescribe bushfire management arrangements for individual properties based on bushfire risk assessment. |
REC304-2419 | 28 - Personal responsibility | Further define the principle of landholder responsibility for fire management and strengthen its fundamental place in the Act. This should include a clear requirement for landholders to prevent fire on their land from spreading to neighbouring properties. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1348 | 4 - Fire season preparation | In keeping with the Victorian Bushfires Royal Commission’s findings and recommendations, human life has primacy in bushfire‑related regulations and it is important that this is maintained in the implementation of bushfire management overlays and relevant vegetation removal exemptions should reflect the primacy of human life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2360 | 2 - Emergency powers | I recommend that the Commissioner of Police consider seeking an agreement with news media outlets whereby the New South Wales Police Force will establish a way for such outlets to rapidly and confidentially determine whether publishing specific material could compromise the response to an ongoing high-risk incident and the media in turn will agree not to publish such material without first alerting a nominated senior police officer of their intention to do so. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1386 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC280-1382 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC280-1381 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1515 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service: |
REC261-1503 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC261-1502 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
REC261-1499 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC261-1498 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC261-1494 | 4 - Fire season preparation | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1054 | 2 - Emergency powers | That the Rural Fire Service consider extending pre-emptive section 44 to whole of Castlereagh RFS/Warrumbungle Shire area. |
REC260-1058 | 28 - Personal responsibility | That NPWS and the RFS consider developing a land management policy that requires active engagement with property owners adjoining the Park to ensure that hazard reduction and asset protection is encouraged and undertaken before the bush fire season commences |
REC260-1071 | 4 - Fire season preparation | The NPWS to consider developing a land management policy that requires hazard reduction around identified assets within the Park and the clearing of fire trials within the Park before the bush fire season commences. Consideration should also be given to developing additional fire trails in the Park, bearing in mind the lack of available fire trails to the south of the John Renshaw Parkway in the park. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0931 | 4 - Fire season preparation | That a specific risk prevention and mitigation advisory body be established for the State Emergency Management Committee. |
REC247-0857 | 2 - Emergency powers | That the Tasmania Emergency Management Plan enable, and all organisations with a role in emergency management activate, emergency plans at lower threshold events to practice their arrangements and achieve a ‘hot start’ in escalating events. |
REC247-0856 | 2 - Emergency powers | That the Government reconsider the current position on emergency declarations in the Emergency Management Act 2006 and the Act is amended to provide: • a graduated scale of emergency declarations; • the ability to make a declaration when an emergency has occurred, is occurring or is about to occur; • the ability for the State Controller (or whatever the person in overall control of response and recovery operations is called) to make one or more declarations; • a declaration to enable access to all emergency powers. |
REC247-0935 | 4 - Fire season preparation | That the State Emergency Management Committee includes in its planning, the development of contingency emergency management plans for areas of high risk due to local conditions. |
REC247-0947 | 20 - Role of police | That Tasmania Police develops and implements a program for examining emergency management arrangements and facilities in Australia. |
REC247-0934 | 4 - Fire season preparation | That the State Fire Management Committee considers developing a structured, systemic and proactive bushfire hazard reduction program with municipal councils and Tasmania Fire Service; and advises the Government on any legislative or other changes required to implement such a program. |
REC247-0946 | 20 - Role of police | That Tasmania Police establishes a section within its structure with responsibility for developing and maintaining contemporary expertise in emergency management, progressing innovation, assisting organisational change initiatives and supporting its responsibilities in state emergency management arrangements. |
REC247-0933 | 4 - Fire season preparation | That the Government considers whether a peak body should be established, with authority to effectively implement a bushfire mitigation plan. |
REC247-0945 | 20 - Role of police | That Tasmania Police conducts a review to ensure emergency management is treated as a priority and a core function throughout the organisation, including the development of contemporary capabilities, and is supported by an appropriate culture. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
REC241-0999 | 28 - Personal responsibility | That on all land where fuel load creates a fire risk, the owner shall be responsible for the construction and maintenance of effective firebreaks. Failure to provide effective and accessible firebreaks will result in the cost of firebreak construction to control a wildfire on this land being debited to the land owner |
REC241-1022 | 29 - Operational Health and Safety | That Rural Fire Service Queensland in consultation with the Rural Fire Brigades Association Queensland will undertake a full review of the medical and health protocols to support the new Volunteer organisation. |
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1015 | 29 - Operational Health and Safety | That the First Officer or Brigade Officer retain the ability to seek assistance from any person whose services are available at the fire. Any person appointed to provide this assistance should be protected under relevant Workplace Health and Safety and Workcover legislation. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-0965 | 29 - Operational Health and Safety | That the number of Bushfire Safety Officer positions be, over time, increased so that one BSO operates out of each District office. |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0535 | 2 - Emergency powers | DFES or DEC (depending on land tenure) is mandated to take over control of emergency incidents from Local Government once they have been declared Level 2 incidents. WESTPLAN BUSHFIRE and legislation to be amended accordingly. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1675 | 39 - Disaster Risk Management | PowerWater Corporation be consulted with the intention of establishing a Memorandum Of Understanding for the maintenance of PowerWater land for the purpose of coordinated fire reduction. |
REC209-1674 | 39 - Disaster Risk Management | That the concession holder of the rail corridor be approached to formalise a Memorandum of Understanding for the maintenance of the railway corridor for the purposes of fuel load reduction. |
REC209-1673 | 4 - Fire season preparation | That a trial be commissioned to assess the most effective means of road verge management, including regional variations, for future application across the Territory. |
REC209-1667 | 39 - Disaster Risk Management | Prepare a formal proposal for the creation of pastoral/Indigenous Lands Fire Management Teams. |
REC209-1672 | 4 - Fire season preparation | Annual property inspections assessing access and fuel loads are conducted in all peri urban areas. |
REC209-1666 | 39 - Disaster Risk Management | Investigate the application and cost of the creation of District Coordination Officers to key high demand brigade districts. |
REC209-1646 | 28 - Personal responsibility | Spreading the message of enforcement of landholder’s obligations and responsibilities through active consultation and ultimately the issuing of infringement notices be adopted as a planned strategic intervention to promote the importance of compliance with the Bushfires Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0501 | 2 - Emergency powers | The Minister for Emergency Services amend section 50 of the Emergency Management Act 2005 by June 2012 to allow the State Emergency Coordinator, as well as a hazard management agency, to make an emergency situation declaration. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0247 | 28 - Personal responsibility | Local residents must take a degree of shared responsibility to prepare their properties by reducing the risk of bushfire around their properties and planning for a bushfire emergency. |
REC201-0257 | 29 - Operational Health and Safety | FESA needs to place greater priority on the appointment of Safety Advisors to Level 3 incidents as is reflected in WESTPLAN Bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-1705 | 29 - Operational Health and Safety | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA‟s own policy of „Use of Private Vehicles in Fires‟ |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-0381 | 2 - Emergency powers | The State Government amend section 50 of the Emergency Management Act 2005 to allow the Chair of the State Emergency Coordination Group to declare an emergency situation. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-0368 | 20 - Role of police | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0336 | 20 - Role of police | Victoria Police, under the auspice of the Regional Emergency Response Plan, lead a task force to ensure that the Princes Highway is treated as an asset of significance and an appropriate risk-based approach is adopted to minimise the impact of fire. This approach is to be integrated into regional and municipal fire management plan |
REC195-0334 | 4 - Fire season preparation | The Fire Services Commissioner leads a task force to: a. identify legislation, policies and guidelines that impact on vegetation management and recommend necessary changes b. develop a set of risk-based standards for vegetation management with respect to strategic firebreaks and the assets being protected c. integrate maintenance standards across all areas of responsibility and tenure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0133 | 29 - Operational Health and Safety | FESA reviews its approach to safety and safety culture. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0176 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment adopt the title ‘safety officer’ (as opposed to ‘safety adviser’) and require without exception that a safety officer be appointed to every level 3 incident management team. |
REC181-0185 | 20 - Role of police | Victoria Police continue to pursue a coordinated statewide approach to arson prevention and regularly review its approach to ensure that it contains the following elements: ■ high-level commitment from senior police; ■ a research program aimed at refining arson prevention and detection strategies; ■ centralised coordination that includes comprehensive training, periodic evaluation of arson prevention strategies and programs, and promotion of best-practice prevention approaches; ■ a requirement that all fire-prone police service areas have arson prevention plans and programs, according to their level of risk. |
REC181-0212 | 4 - Fire season preparation | VicRoads implement a systematic statewide program of bushfire risk assessment for all roads for which it is responsible, to ensure conformity with the obligations in s. 43 of the Country Fire Authority Act 1958 and with the objectives expressed in the VicRoads 1985 Code of Practice. |
REC181-0174 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures for investigating safety incidents and ‘near-misses’ to ensure that all dangerous incidents, including back-burns, are fully investigated and that all relevant people are consulted and informed of the results. |
REC181-0160 | 20 - Role of police | The State clarify whether, during major fires, Victoria Police should discharge its coordination functions from the State Emergency Response Coordination Centre or from the State Control Centre. |
REC181-0211 | 4 - Fire season preparation | The State and Commonwealth provide for municipal councils adequate guidance on resolving the competing tensions arising from the legislation affecting roadside clearing and, where necessary, amend environment protection legislation to facilitate annual bushfire-prevention activities by the appropriate agencies. |
REC181-0210 | 4 - Fire season preparation | The State amend the exemptions in clause 52.17-6 of the Victoria Planning Provisions to ensure that the provisions allow for a broad range of roadside works capable of reducing fire risk and provide specifically for a new exemption where the purpose of the works is to reduce bushfire risk. |
REC181-0204 | 2 - Emergency powers | The State amend the Country Fire Authority Act 1958 to enable the Chief Officer to delegate the power to issue fire prevention notices. |
REC181-0192 | 4 - Fire season preparation | The Department of Sustainability and Environment develop and administer a collective offset solution for individual landholders who are permitted to remove native vegetation for the purpose of fire protection. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3345 | 2 - Emergency powers | NOPSA’s prohibition powers should be extended such that a prohibition notice can be issued where a NOPSA Occupational Health and Safety Inspector believes, on reasonable grounds, that an activity is occurring or may occur at a facility involving an immediate threat to the health or safety of a person. |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0140 | 4 - Fire season preparation | The Commonwealth seek agreement from the states and territories that would enable it to evaluate the adequacy of fuel reduction programs applied by public land management agencies in high bushfire risk areas, and audit their implementation against the program's stated objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0030 | 29 - Operational Health and Safety | A strategically located Staging Area serviced with check in/out personnel should be considered as early as possible at incidents involving an extended attack. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
Rec-ID | Code | Recommendation |
---|---|---|
REC163-1939 | 2 - Emergency powers | That the Rural Fires Act 1997 be amended to provide to designated Fire Investigation Officers of the Rural Fire Service the power to enter any land upon which a bushfire has occurred for the purposes of investigation for a period of up to 24 hours after a fire has been declared out. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1779 | 4 - Fire season preparation | That the South Australian Farmers’ Federation encourage its members and constituents to keep and maintain on rural land in proper working order machinery that is capable of removing, modifying or reducing cropping stubble at short notice in order to minimise or mitigate bushfire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3122 | 29 - Operational Health and Safety | QFRS implement a system to monitor the condition and safety of brigade buildings and equipment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3785 | 4 - Fire season preparation | The Committee recommends that the government, via the CFS, coordinate the preparation and implementation of native vegetation management plans that incorporate management of fuel loads and includes a prescribed burning regime for the area. |
REC122-3783 | 4 - Fire season preparation | The Committee recommends that the government establish designated fire safety areas within native vegetation and at road intersections. |
REC122-3782 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities prepare a management plan that includes firebreaks and access tracks in the region, including the location of current breaks and access tracks and where breaks and tracks need to be established. |
REC122-3781 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities assess fire tracks and breaks to determine if firebreaks and access tracks need to be wider and/or native vegetation removed so that it does not impinge on firebreaks or tracks. |
REC122-3780 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities identify if: sufficient firebreaks and access track exist; they are strategically located; and they are being managed. |
REC122-3787 | 4 - Fire season preparation | The Committee recommends that the Native Vegetation Council provide landholders with assistance for applications for prescribed burning (via a guide, a proforma or staff). |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2220 | 2 - Emergency powers | That CFA should not be given the power to direct Forest Industry Brigades to engage in fire prevention and suppression activities off their land and that decision should remain the responsibility of the plantation company. |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2291 | 28 - Personal responsibility | That after each fire season, measures of the effectiveness of aerial firefighting be collated, analysed and used for the assessment of the State Aircraft Fleet composition and the adequacy of Training and Accreditation programs. |
REC104-2270 | 29 - Operational Health and Safety | That DSE and CFA continue to stress firefighter safety as their highest priority for incident managers and fire ground supervisors |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2177 | 39 - Disaster Risk Management | The Committee recommends that state and territory governments be required to regularly perform risk assessments to the land within their jurisdictions to ensure that bushfire prone areas are accurately identified |
REC098-2136 | 4 - Fire season preparation | The Committee recommends that the Commonwealth through the National Heritage Trust assist the states and territories in the construction, maintenance and signage of fire trail networks. |
REC098-2168 | 2 - Emergency powers | The Committee recommends that the Commonwealth investigate, and where necessary, require the urgent enhancement of the provision of emergency power and telecommunications services for the purpose of |
REC098-2151 | 29 - Operational Health and Safety | The Committee recommends that the Commonwealth Attorney-General engage the Commonwealth, states and territories in a review of occupational health and safety legislation as it affects the proper and effective functioning of bush fire services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4169 | 4 - Fire season preparation | Mitigation and preparedness be enhanced and maintained for the future. Some co—ordinating mechanism or system be introduced at State Government level for this purpose. [Reference paragraphs: 114 to 128] |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3952 | 4 - Fire season preparation | It is recommended that the question of the future responsibility be made certain and that the body so made responsible keep the grounds of the hospital free from undergrowth and trees wherever their presence may be a possible source of future danger. |
REC016_3950 | 4 - Fire season preparation | It is recommended that on days of abnormal danger loads of briquettes be not kept in the station yard. The real danger, which transcends in gravity the danger of time destruction of loads of briquettes, is that the prevailing wind or a change of wind might carry showers of burning embers to the town, which is but the width of a road away, and thereby cause material damage in the town. It is further recommended that the yard and its surroundings be kept clear of scrub and growth; and that special provision be made for quelling fire which may break out in the deposits of inflammable dust which lie in time yard. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3978 | 4 - Fire season preparation | Where possible to build stone or brick fireplaces for the use of travellers, teamsters, and drovers on the camping areas that are mostly used and where there is a risk of fire. |
REC013_3976 | 4 - Fire season preparation | To burn camping areas at suitable water and camping reserves. |