Rec-ID | Code | Recommendation |
---|---|---|
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4200 | 33 - Relief and recovery | Foundations of emergency management: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in consultation with the emergency management sector – establish policies and platforms to improve operational and personal information sharing between relief and recovery organisations. These policies and platforms should enable: |
REC319-4187 | 33 - Relief and recovery | Recovery governance: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, work with councils, relevant recovery organisations and communities to develop clear roles and responsibilities for: |
REC319-4189 | 33 - Relief and recovery | Donated good: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department: |
REC319-4195 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, leads the development of a comprehensive, person-centred, trauma-informed recovery financial assistance system that establishes: |
REC319-4196 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, works with the emergency management sector to develop a recovery funding model that enables: |
REC319-4198 | 33 - Relief and recovery | Relief and recovery capability: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions works with the entity referred to in Recommendation 13, or otherwise responsible government department and/or Municipal Association of Victoria, councils and local relief and recovery organisations to provide centralised capability development opportunities to increase local capability and capacity to plan and deliver on their relief and recovery responsibilities: |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1342 | 6 - Insurance and legal liability | That fire managers responsible for planned burns be |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1412 | 20 - Role of police | That Victoria Police assesses and where practical addresses limitations to available data and trials the use of response times for internal performance measurement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1125 | 33 - Relief and recovery | Consultation with the Board of the Lord Mayor’s Distress Relief Fund and other disaster appeal organisers should be undertaken to determine the potential for software development to consolidate the application and approval process, including provision of templates and application forms; |
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1127 | 33 - Relief and recovery | Consultation should be undertaken with agencies and organisations that are engaged in emergency welfare provision to identify more effective ways to provide a consistent message to the community that non-cash donations are not required. |
REC265-1126 | 33 - Relief and recovery | Development of a template contract for the clean-up of affected properties to speed-up the process; |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2849 | 20 - Role of police | I recommend that the AFP takes steps to ensure that there are on Christmas Island at all times appropriately trained AFP officers who have completed the National Police Search and Rescue Manager’s Course and that upskilling should be ongoing to establish a cadre of trained search and rescue personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0598 | 33 - Relief and recovery | When communities are grieving there is a need to provide special forms of support to affected residents. |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0596 | 33 - Relief and recovery | An early decision on relief funding enables timely responses. D CP should review their communication of relief arrangements to ensure that they are clear. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0595 | 33 - Relief and recovery | Shire experiences in managing these traumatic events should be captured and passed into emergency management procedures. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0594 | 33 - Relief and recovery | Procedures to resolve issues surrounding financial assistance need to be reviewed to ensure they are as smooth, fast and transparent as possible possible. Review and streamline current financial relief procedures. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1633 | 6 - Insurance and legal liability | The Treasurer undertake a review by the next bushfire season of the ability of RiskCover to efficiently undertake loss assessing and compensation activities for victims of major natural disasters, such as a bushfire, in an empathic and timely fashion. |
REC224-1632 | 6 - Insurance and legal liability | The State Government prepare a consistent policy on how to assist or compensate the victims of future major natural disasters, such as bushfires, in an equitable fashion. |
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1871 | 14 - Incident Mgt Teams | Fire services can improve outcomes by developing a checklist for use by incident controllers |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1920 | 6 - Insurance and legal liability | The Attorney General gives urgent consideration to determining an ex gratia payment for: |
REC204-1910 | 6 - Insurance and legal liability | As part of its review of its contract management processes, Tourism WA (with the Board of Tourism WA taking a lead role) should amend its contract template for event sponsorship to ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0308 | 33 - Relief and recovery | Early resolution and clear communication of the financial and other support measures that will be available to affected residents is an important contributor to community resilience. |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0368 | 20 - Role of police | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-1724 | 6 - Insurance and legal liability | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0373 | 33 - Relief and recovery | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0453 | 20 - Role of police | Victoria Police revise coordinator arrangements to ensure: • a coordinator presence is maintained at the place where incident control is being exercised • effective control is established and is maintained until the response phase has concluded • key control roles may be performed by personnel from agencies other than the designated control agency • that the timely compilation and distribution of an appropriate Incident Action Plan is recognised as a fundamental component of establishing effective control • those performing the coordinator role at an Incident Control Centre be suitably trained, skilled and experienced in emergency management and where possible possess a degree of local knowledge of the relevant area; and • that the revised coordinator arrangements are reflected within the State Emergency Response Plan |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2905 | 14 - Incident Mgt Teams | The Fire Services Commissioner ensures that there is a single standard for the tabards worn by the IMT on the fireground and in control centres to ensure consistency and aid interoperability. |
REC198-2902 | 14 - Incident Mgt Teams | The Fire Services Commissioner clarifies the role of regional controller for major fires and incidents other than bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
REC195-0336 | 20 - Role of police | Victoria Police, under the auspice of the Regional Emergency Response Plan, lead a task force to ensure that the Princes Highway is treated as an asset of significance and an appropriate risk-based approach is adopted to minimise the impact of fire. This approach is to be integrated into regional and municipal fire management plan |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0135 | 33 - Relief and recovery | FESA revises its standard operating procedures to provide guidance on the format and timing of post-incident community meetings. |
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0160 | 20 - Role of police | The State clarify whether, during major fires, Victoria Police should discharge its coordination functions from the State Emergency Response Coordination Centre or from the State Control Centre. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0185 | 20 - Role of police | Victoria Police continue to pursue a coordinated statewide approach to arson prevention and regularly review its approach to ensure that it contains the following elements: ■ high-level commitment from senior police; ■ a research program aimed at refining arson prevention and detection strategies; ■ centralised coordination that includes comprehensive training, periodic evaluation of arson prevention strategies and programs, and promotion of best-practice prevention approaches; ■ a requirement that all fire-prone police service areas have arson prevention plans and programs, according to their level of risk. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0067 | 14 - Incident Mgt Teams | That to the extent it has not already done so, DEC take action to ensure that in future cases relevant weather forecast information, particularly information as to significant wind changes, is promptly transmitted through the Incident Management Team and made available to persons with field operation responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3481 | 6 - Insurance and legal liability | That the Victorian Government establish a clear and consistent Bushfire Fencing Policy for damage caused by all future bushfires and prescribed burns. The Bushfire Fencing Policy should include the following provisions: |
REC155-3471 | 6 - Insurance and legal liability | That the Victorian Government replace or compensate for water taken from domestic, stock and irrigation dams, or water needed for essential use, in the event of a fire, regardless of where the bushfire starts. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3583 | 33 - Relief and recovery | That the newly proposed index linked limits for Personal Hardship and Distress Relief Payments as outlined in the paper “National Disaster Relief Arrangements - An Analysis and Recommendations for Personal Hardship Distress Measures” be accepted by government. |
REC143-3588 | 33 - Relief and recovery | That, in line with recommendations contained in the 2004 Report to the Council of Australian Governments, greater flexibility should be introduced to WANDRA to enable damaged infrastructure to be upgraded to a more resilient standard where that is both feasible and cost-effective. |
REC143-3585 | 33 - Relief and recovery | That the Professional Assistance Grant is formally extended by WANDRA to include non rural businesses and that it be made available to assist with the clean up of disaster related damage to farms and businesses. (The Committee recognises that the amendments to WANDRA as of March 2007 address this recommendation). |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3902 | 14 - Incident Mgt Teams | Government should: establish a State-wide command structure across volunteer Bush Fire Brigades for fighting major bushfires, to more effectively manage the coordination of personnel and resources |
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3927 | 6 - Insurance and legal liability | That PSB and PIRVIC review their service agreement to ensure that PIRVIC is compensated for its costs in providing PSB with the specified level of service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2217 | 6 - Insurance and legal liability | That CFA, in their education and information packages, encourage appropriate insurance cover, and ensure that insurance becomes a part of the householder’s annual checklist. |
REC104-2310 | 33 - Relief and recovery | That recovery is recognised as commencing at the same time as response and that recovery planning and delivery is an integral part of the operations of the Municipal Emergency Co-ordination Centres. |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2307 | 33 - Relief and recovery | That the Victorian Government recommend to the Commonwealth Government that it reviews eligibility for those without employment who may or may not be engaged in an emergency response, and are unable to access the appropriate infrastructure to register for financial assistance. |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2316 | 33 - Relief and recovery | That the State Emergency Recovery Committee explore opportunities to establish a 'one-stop shop’ approach wherever practicable following emergencies, including a single telephone number to connect a person to all agencies involved in the recovery process. |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2306 | 33 - Relief and recovery | That VicRoads and Municipal Councils review procedures and processes to ensure that the identification and delivery of remedial works on State and Council roads following emergency events are as efficient as possible. |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2314 | 33 - Relief and recovery | That DHS, in conjunction with Local Government, Government departments and the nongovernment sector, modify recovery planning at all levels to include a case management approach supported by an appropriate information system to be activated at the time of an emergency. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2305 | 33 - Relief and recovery | That DPI actively promote as widely as possible within the community, the agricultural recovery service available during emergencies to ensure that all farmers are aware of the services provided. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2231 | 6 - Insurance and legal liability | That DSE commences discussion with the Victorian WorkCover Authority in respect to employer liability for those staff being released to, and directed, by another agency in fire prevention and suppression activities. |
REC104-2313 | 33 - Relief and recovery | That Government review the emergency relief and financial assistance policy, and develop and communicate a predictable, consistent and equitable policy designed to assist the community to recover from emergencies, including natural disasters. |
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2218 | 6 - Insurance and legal liability | That Government work with the insurance industry to explore options for incentives such as a reduction in premiums for those who take appropriate self-protection measures on their properties, similar to incentives for anti-theft home security |
REC104-2312 | 33 - Relief and recovery | That all agencies engaged in recovery participate in community briefings prior to and during emergency events, to ensure recovery issues are reinforced and communities are informed of the processes established to assist individuals – including matters that are not the responsibility of Victoria, such as Centrelink payments. |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4146 | 6 - Insurance and legal liability | Insurance companies be asked to subsidise the bush fire equipment fund by an amount at least equal to the amount they at present remit on premiums received for fire insurance in approved districts and that the Government contribute an amount to the fund at least equal to that contributed by the Insurance Companies. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3960 | 33 - Relief and recovery | It is recommended that the Forests Commission recognize and provide for the efficient exercise of three major functions, namely those of Commerce, Reclamation and Rehabilitation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |