REC327-4346 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: establish a fleet maintenance framework to ensure regular update of District Service Agreements with local councils. |
REC327-4350 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: develop a fleet enhancement framework and strategy that is informed by an assessment of current fleet capability to respond to fire incidents, and research into the most appropriate technologies and appliances to address emerging and future fire risks across NSW. |
REC327-4345 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: review and improve processes for timely recording of fleet asset movements, locations, and maintenance status. |
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4324 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the tasking protocols used to manage State Emergency Service (SES) tasks undertaken in the response phase of a disaster to enable more complete recording of details for all ‘jobs of opportunity’ (including the personal details of those assisted and/or rescued) to enable better coordination of tasks and reflect outcomes of activities by 1 November 2023. |
REC325-4325 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review and implement State Emergency Service (SES) protocol by 1 November 2023 outlining procedures to be undertaken to ensure persons uplifted from places of immediate danger or risk are transferred to a place of safety. |
REC325-4334 | 32 - Doctrine, standards, and reform | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services develop and publish an operationally based quick reference guide that complements the training offered (as per Recommendation 5) by 1 November 2022. The guide will identify key and critical aspects of the Emergency Alert system in relation to the development, composition, request for and authorising of Emergency Alerts and will include a template and an example of ‘good’ messaging using concise, minimal language and Clear Explicit Translatable Language (CETL). |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4257 | 1 - Land-use and building regs | That the NSW Government work with local government, industry and sustainable planning experts, including the Government Architect, on policy initiatives in the New South Wales planning system that will help deliver more resilient and sustainable homes, buildings and places. |
REC323-4271 | 33 - Relief and recovery | That Service NSW establish teams of assessors that can be on the ground to assess and approve grant applications. |
REC323-4262 | 33 - Relief and recovery | That the NSW Government provide an increased level of targeted support to flood affected communities contending with widespread mould. |
REC323-4273 | 33 - Relief and recovery | That the NSW Government overhaul the way in which it conducts its grants process as it frustrated applicants and further traumatised them by repeatedly re-interviewing them and making them prove that they were flooded. |
REC323-4266 | 1 - Land-use and building regs | That the NSW Government review the provision of temporary and long term housing options provided to those affected by the February-March 2022 floods, with a view to: • ensuring a range of options are identified and embedded within emergency and recovery plans, so that solutions can be implemented as soon as possible after a natural disaster • ensuring that housing options meet individual and community needs • removing planning impediments that prevent those from accessing more safe and secure housing in times of crisis. |
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
REC323-4267 | 1 - Land-use and building regs | That the NSW Government consider investing in supporting relocations, land swaps and providing fair and adequate compensation for landowners who wish to relocate from severely flood-impacted areas. |
REC323-4289 | 33 - Relief and recovery | That the NSW Government ensure that all emergency and recovery plans, including state plans, local emergency management plans and functional area plans, are reviewed and updated regularly and provide clarity on the role of non-government partners. |
REC323-4277 | 33 - Relief and recovery | That the NSW Government develop a more proactive, rapid response to manage animal welfare following natural disasters which includes improved collaboration and communication with local veterinarians and animal welfare organisations. |
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
REC323-4269 | 33 - Relief and recovery | That the NSW Government address the mental health needs of local communities following the February-March 2022 floods by: • embedding within state emergency and recovery plans a strategy that provides surge capacity for mental health and social workers by: • prioritising funding for community groups that are currently providing social and mental health support to their local communities • ensuring all flood-impacted communities receive the mental health support they need to fully recover. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4237 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science develop and implement a Wildfire Response Plan for Queensland Parks and Wildlife Service Coastal and Islands Region, to be included in the region’s Disaster Management Operations Plan. |
REC322-4232 | 11 - Evacuation and shelters | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to plan for the evacuation of K’gari due to bushfire. Once developed, the plan should be exercised and regularly reviewed. |
REC322-4238 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science ensure that all Queensland Parks and Wildlife Service regions develop a Disaster Management Operations Plan based on a standardised format. The plans should include provision for annual review to ensure they remain contemporary, interoperable with relevant disaster management plans and aligned to the Department of Environment and Science Emergency Management Plan. |
REC322-4233 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science review the current description of Level 1, 2, and 3 bushfire incidents and the implied meaning of property in the Queensland Bushfire Plan. This review should identify and agree on clear criteria and decision points for the transfer of control and develop a standard process and templates. |
REC322-4241 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services consider expanding specialist Remote Area Firefighting Team capability to assist in responding to significant bushfire events which occur in rugged or inaccessible terrain. |
REC322-4234 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science review its suite of operational doctrine to ensure arrangements for situational reporting and requests for assistance are aligned to recognised multi-agency practices used in disaster management. |
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
REC322-4236 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the arrangements and requirements for situational reporting when an incident is under the control of the Department of Environment and Science be detailed in the Queensland Bushfire Plan. These arrangements should also be outlined in relevant joint entity agreements and operational doctrine. |
REC322-4247 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends a collaborative review of firelines, tracks and trails on K’gari be undertaken by the Department of Environment and Science, in collaboration with the Locality Specific Area Fire Management Group and the Butchulla people, to ensure an adequate network is agreed by relevant stakeholders, and roles and responsibilities for maintenance are agreed and documented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4190 | 11 - Evacuation and shelters | Humanitarian relief: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions work with the Municipal Association of Victoria and councils to build contingencies into emergency relief centre planning to ensure places of shelter are inclusive, recognise diversity and are better placed to support all displaced people in circumstances of: |
REC319-4195 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, leads the development of a comprehensive, person-centred, trauma-informed recovery financial assistance system that establishes: |
REC319-4196 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, works with the emergency management sector to develop a recovery funding model that enables: |
REC319-4198 | 33 - Relief and recovery | Relief and recovery capability: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions works with the entity referred to in Recommendation 13, or otherwise responsible government department and/or Municipal Association of Victoria, councils and local relief and recovery organisations to provide centralised capability development opportunities to increase local capability and capacity to plan and deliver on their relief and recovery responsibilities: |
REC319-4187 | 33 - Relief and recovery | Recovery governance: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, work with councils, relevant recovery organisations and communities to develop clear roles and responsibilities for: |
REC319-4200 | 33 - Relief and recovery | Foundations of emergency management: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in consultation with the emergency management sector – establish policies and platforms to improve operational and personal information sharing between relief and recovery organisations. These policies and platforms should enable: |
REC319-4189 | 33 - Relief and recovery | Donated good: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4180 | 11 - Evacuation and shelters | The Inspector-General for Emergency Management recommends that Victoria Police – in collaboration with the community and the emergency management sector – reflect on events of the 2019–20 fire season to review and enhance evacuation plans and processes with consideration of: |
REC318-4173 | 32 - Doctrine, standards, and reform | The Inspector-General for Emergency Management recommends that in conjunction with Inquiry Recommendation 2, the State establish or assign responsibility to a single body or entity to lead and coordinate the implementation of evidence-based fuel management policy, practice and assurance and reporting on activities on both public and private land in Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4055 | 32 - Doctrine, standards, and reform | The Australian Government should revise the COMDISPLAN thresholds to provide that a request for Australian Government assistance, including Defence assistance, is able to be made by a state or territory government when: |
REC317-4117 | 33 - Relief and recovery | State and territory governments should develop and implement efficient and effective arrangements to: |
REC317-4089 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4127 | 33 - Relief and recovery | Australian, state and territory governments should incorporate the principle of ‘build back better’ more broadly into the Disaster Recovery Funding Arrangements. |
REC317-4093 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review those plans, and update where appropriate, to provide for coordination between states and territories in cross border areas and to provide cross-border access to evacuation centres. |
REC317-4116 | 33 - Relief and recovery | Governments should create and publish standing policy guidance on whether they will or will not assist to clean-up debris, including contaminated debris, resulting from natural hazards. |
REC317-4088 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4126 | 33 - Relief and recovery | Australian, state and territory governments should expedite the development of pre-agreed recovery programs, including those that address social needs, such as legal assistance domestic violence, and also environmental recovery. |
REC317-4092 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review these plans, and update them where appropriate, to account for the existence and standard of any evacuation centres and safer places (however described) in the community, including: |
REC317-4115 | 1 - Land-use and building regs | The Australian Building Codes Board, working with other bodies as appropriate, should: |
REC317-4072 | 32 - Doctrine, standards, and reform | The Australian Government should consider whether employment protections under the Fair Work Act 2009 (Cth) are sufficient to ensure that fire and emergency services volunteers will not be discriminated against, disadvantaged or dismissed for reasons associated with their volunteer service during natural disasters. |
REC317-4122 | 33 - Relief and recovery | Australian, state and territory and local governments should evaluate the effectiveness of existing financial assistance measures to inform the development of a suite of pre-effective pre-determined recovery supports. |
REC317-4091 | 11 - Evacuation and shelters | State and territory governments should provide further community education on the function and limitations of different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. This education should be nationally consistent. |
REC317-4114 | 1 - Land-use and building regs | State, territory and local governments should be required to consider present and future natural disaster risk when making land-use planning decisions for new developments. |
REC317-4064 | 32 - Doctrine, standards, and reform | Australian, state and territory governments should work together to develop consistent data standards to measure disaster impact. |
REC317-4119 | 33 - Relief and recovery | The Australian Government, through the mechanism of the proposed standing national recovery and resilience agency, should convene regular and ongoing national forums for charities, non-government organisations and volunteer groups, with a role in natural disaster recovery, with a view to continuous improvement of coordination of recovery support. |
REC317-4090 | 11 - Evacuation and shelters | State and territory governments should, as a priority, adopt nationally consistent terminology and functions for the different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. |
REC317-4104 | 33 - Relief and recovery | Australian, state and territory governments should refine arrangements to support localised planning and the delivery of appropriate mental health services following a natural disaster. |
REC317-4118 | 33 - Relief and recovery | Australian, state and territory governments should create a single national scheme for the regulation of charitable fundraising. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2488 | 33 - Relief and recovery | The basic capacity needs of each functional recovery group and how this can be scaled up should be identified. Plans for functional recovery groups should reflect this in clear statements for every level of the system, for all relevant entities about their required function, role and responsibilities during recovery. |
REC310-2485 | 33 - Relief and recovery | Recovery plans at all levels should include transition arrangements. They should be implemented during recovery. The arrangements should: |
REC310-2484 | 33 - Relief and recovery | There remains a need to maximise the effect of all offers of assistance to recovering communities. This recommendation presents an opportunity to resolve any outstanding aspects of Recommendation 4 and Actions in Response from the Cyclone Debbie Review Action Plan: |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2455 | 32 - Doctrine, standards, and reform | The Queensland Offers of Assistance Policy, particularly for corporate donations, should be updated and exercised prior to the next season. |
REC308-2453 | 32 - Doctrine, standards, and reform | Business continuity planning should feature permanently in disaster management doctrine. |
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2434 | 32 - Doctrine, standards, and reform | Given an increasing risk of intense fires, the framework of legislation relating to vegetation management, bushfire mitigation and preparation priorities should be re-assessed. The re-assessment should aim to enable more appropriate and flexible means at the local level for the reduction of intense fires. |
REC307-2432 | 32 - Doctrine, standards, and reform | Legislation at state and local level requiring landholders to reduce fire risk on their property should be actively applied |
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
REC307-2427 | 32 - Doctrine, standards, and reform | Wherever possible, the antecedents that will lead to catastrophic fire weather conditions existing for a particular area should be identified and documented within fire management plan relevant to the area. |
REC307-2443 | 32 - Doctrine, standards, and reform | Planning for response to bushfire risk should identify all stakeholders to be engaged in the response phase and their roles and responsibilities should be clearly documented. |
REC307-2426 | 32 - Doctrine, standards, and reform | Queensland's plans and arrangements for heatwave should be reviewed to provide for an intergrated multi-agency approach to their management. A single agency should lead and oversee this process. |
REC307-2442 | 32 - Doctrine, standards, and reform | Hazard-specific plans and guidelines should be published on external websites for access by relevant stakeholders. |
REC307-2441 | 32 - Doctrine, standards, and reform | Hazard-specific and disaster management guidelines and plans should explain the circumstances and process for hazard-specific activation of the disaster management arrangements in support of an incident. They should be relevant to local authorities and local and district groups, and used during events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2408 | 32 - Doctrine, standards, and reform | Introduce clear Terms of Reference for the Bushfires Council and Regional Bushfires Committees, and introduce a requirement for the Minister to consider advice and recommendations from the Council. |
REC304-2420 | 32 - Doctrine, standards, and reform | Enshrine the broader fire management principles, including coordination, strategic planning, mitigation, monitoring and control within the Act. |
REC304-2418 | 32 - Doctrine, standards, and reform | Amend the object to provide for ‘The mitigation, management, and suppression of bushfires’. Definitions of these terms should be included in the Act, and should include clarification that bushfire suppression can include emergency response activities in certain circumstances |
REC304-2417 | 32 - Doctrine, standards, and reform | Amend the Act title to ‘Bushfires Management Act’. |
REC304-2415 | 32 - Doctrine, standards, and reform | Define formal bushfire management regimes for areas with different bushfire management requirements and define bushfire management responsibilities in those areas. One category will provide for areas that warrant provision of a wildfire response capacity, another will allow for the declaration of temporary fire management arrangements for the duration of identified high-risk circumstances. |
REC304-2409 | 32 - Doctrine, standards, and reform | Formalise and clearly define the powers and duties of Bushfires NT personnel, including volunteers, thereby clarifying Bushfires NT’s role in bushfire management in the Northern Territory. |
REC304-2421 | 32 - Doctrine, standards, and reform | Include a detailed description of the role, responsibility and accountability of |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4011 | 32 - Doctrine, standards, and reform | The Commission feel that the 4th clause in the present Act, relating to the spacing of cut-throughs, should be amended to admit of any convenient or safe system of mining being pursued. This is a matter of detail that would be better out of the Act. The Commission would advise that the word should not occur at all, and that, if bratticing be used, or the air by some other satisfactory device be conveyed to the face, scope would be given to Managers to introduce systems of mining adapted to the circumstance of each particular coal-seam, with advantage to all concerned. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
REC290-1211 | 32 - Doctrine, standards, and reform | Review of institutional arrangements in the fire sector |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1207 | 33 - Relief and recovery | Communicating in Recovery: The Office of Emergency Management: · considers the development of a communications and engagement strategy for major disaster events · progresses the development of the ‘Communicating In Recovery’ Guideline in the Local Recovery Toolkit. |
REC281-1206 | 33 - Relief and recovery | Transition from Response to Recovery: That Region Emergency Management Committees meet post event to: · consider available impact data · determine the need to establish a Recovery Committee · document the rationale for the decision · advise the Office of Emergency Management of the decision. |
REC281-1204 | 33 - Relief and recovery | Transition from Response to Recovery That the Office of Emergency Management, in consultation with the NSW Police Force Emergency Management Unit develops a template for handover of the Response to Recovery Phase of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1389 | 32 - Doctrine, standards, and reform | That the NSW Government, as a matter of urgency, amend the Rural Fires Act 1997 to codify the current interim arrangements for command and notification requirements for class 1 and class 2 fires, which clarify that the NSW Rural Fire Service or Fire and Rescue NSW: |
REC280-1398 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service: |
REC280-1385 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
REC280-1397 | 32 - Doctrine, standards, and reform | That the NSW National Parks and Wildlife Service adopt an interim fencing agreement in the immediate aftermath of a fire. This will enable emergency and interim works to commence, but features such as length, fencing components and site of the fence line are not binding. A final fencing agreement would be negotiated no earlier than six months following a major national park fire. |
REC280-1383 | 1 - Land-use and building regs | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC280-1395 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service reassess the protection of pastoral assets during bush fires to ensure that priority for protection is not simply afforded to the homestead, and that land holders are, within reason, able to request which of their own assets are protected. |
REC280-1391 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service review its procedures, systems and infrastructure for notifying community members of bush fires, both when a fire has broken out and as it proceeds, to ensure the provision of timely and adequate information. |
REC280-1403 | 32 - Doctrine, standards, and reform | That the Ministry for Police and Emergency Services urgently review its policies for the provision of disaster welfare services to ensure that in the event of a bush fire emergency and the declaration of a fire under section 44 of the Rural Fires Act 1997, adequate funding and services, especially recovery centres and mental health services, are provided for an adequate length of time, with gradual transition to normal service delivery when those services are no longer required. |
REC280-1390 | 32 - Doctrine, standards, and reform | That the NSW Government consider enabling the default position during catastrophic and extreme fire danger periods to be the same as for section 44 fires, so that fire control centres have the same systems and resources ready to deploy should a fire break out. |
REC280-1399 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service remove from its boundary fencing policy and standard contract the condition that requires adjoining land owners to maintain a fence that has been damaged by trees falling from national park land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC278-1225 | 32 - Doctrine, standards, and reform | The committee recommends that the Australian and Tasmanian Governments: • develop options to increase co-operation to ensure that the Tasmanian Wilderness World Heritage Area is protected and conserved in line with Australia's obligations under the World Heritage Convention; and • work together to ensure strong provisions to protect the Tasmanian Wilderness World Heritage Area from bushfire risks are included in the Tasmanian Wilderness World Heritage Area Management Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1165 | 32 - Doctrine, standards, and reform | Clarify the role of the ROC and SOC and their reporting relationships: The ROC and SOC have important coordination roles under the State Emergency Management Arrangements to support both the incident and the broader region and state. Clarifying the role of the ROC and SOC, their reporting relationships, and how the command structures of other agencies are integrated, will have three main benefits: the ROC and SOC can perform their functions effectively • no inconsistencies, gaps or duplication in the activities of the IMT, ROC and SOC • transparency of incident management |
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1148 | 33 - Relief and recovery | Planning for Recovery Centres Recovery Centres are a proven means of providing support to affected communities. More comprehensive recovery planning is needed at local levels, including the identification of potential Recovery Centre sites in Local EM Plans to help facilitate streamlined establishment of the Centres in future events. Consideration should be given to developing a clear set of standard messaging regarding |
REC267-1163 | 33 - Relief and recovery | Corrections Volunteer Labour Teams |
REC267-1161 | 33 - Relief and recovery | VIP Visits |
REC267-1160 | 33 - Relief and recovery | Transition from Response to Recovery |
REC267-1156 | 33 - Relief and recovery | Streamlining NDRRA Grants Processes |
REC267-1155 | 33 - Relief and recovery | MP Recovery Reference Group |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1113 | 32 - Doctrine, standards, and reform | The role of the Ground Controller should be reaffirmed in operational doctrine and reinforced in Incident Management Team training. During incidents involving aircraft the appointment of a Ground Controller should be confirmed by the Incident Controller |
REC265-1127 | 33 - Relief and recovery | Consultation should be undertaken with agencies and organisations that are engaged in emergency welfare provision to identify more effective ways to provide a consistent message to the community that non-cash donations are not required. |
REC265-1110 | 32 - Doctrine, standards, and reform | Whenever a Bush Fires Act 1954 section 13 transfer of control is invoked, the Incident level of an event should also be reviewed and any changes documented. |
REC265-1126 | 33 - Relief and recovery | Development of a template contract for the clean-up of affected properties to speed-up the process; |
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1125 | 33 - Relief and recovery | Consultation with the Board of the Lord Mayor’s Distress Relief Fund and other disaster appeal organisers should be undertaken to determine the potential for software development to consolidate the application and approval process, including provision of templates and application forms; |
REC265-1107 | 32 - Doctrine, standards, and reform | Standard Operating Procedure 1 (Mobilisation Zone 2, Perth Hills area) should be reviewed to ensure that appropriate escalation triggers and levels of operational readiness are in place for future periods when severe fire weather conditions are forecast. |
REC265-1124 | 32 - Doctrine, standards, and reform | EMP 4.4 and Westplan – Recovery Coordination should be amended to: clarify the wording around handing over control of the incident from the Controlling Agency to local government and the transition from response to recovery; include principles and criteria that will assist the Controlling Agency and local government to determine the best time to effect a hand over of control of the incident; make explicit the roles and responsibilities of the parties involved in the handover of control of the incident; specify the information required in the needs and impact assessments provided to local government by the Controlling Agency so that local government is given sufficient information to take control of incidents; clarify the roles, responsibilities and the title of the State Recovery Controller and ensure that the appropriate wording is reflected in Westplans and State Emergency Management Policies; Hazard Management Agencies, combat and support agencies and local governments need to fully inform themselves of the role of the State Recovery Controller and implement a more effective approach to communicating |
REC265-1100 | 32 - Doctrine, standards, and reform | The forthcoming review by SEMC of SEMP 4.4 Recovery Coordination and Westplan – Recovery Coordination and SEMP 4.1 Incident Management should include consideration of: |
REC265-1114 | 32 - Doctrine, standards, and reform | Procedures should be reviewed to address the risks associated with response aircraft all working from one forward operating base, including the need for a designated fire protection unit to be available in the event of an aircraftrelated fire or other emergency incident |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1514 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service adopt an interim fencing agreement in the immediate aftermath of a fire. This will enable emergency and interim works to commence, but features such as length, fencing components and site of the fence line are not binding. A final fencing agreement would be negotiated no earlier than six months following a major national park fire. |
REC261-1512 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service reassess the protection of pastoral assets during bush fires to ensure that priority for protection is not simply afforded to the homestead, and that land holders are, within reason, able to request which of their own assets are protected. |
REC261-1506 | 32 - Doctrine, standards, and reform | That the NSW Government, as a matter of urgency, amend the Rural Fires Act 1997 to codify the current interim arrangements for command and notification requirements for class 1 and class 2 fires, which clarify that the NSW Rural Fire Service or Fire and Rescue NSW: |
REC261-1520 | 33 - Relief and recovery | That the Ministry for Police and Emergency Services urgently review its policies for the provision of disaster welfare services to ensure that in the event of a bush fire emergency and the declaration of a fire under section 44 of the Rural Fires Act 1997, adequate funding and services, especially recovery centres and mental health services, are provided for an adequate length of time, with gradual transition to normal service delivery when those services are no longer required. |
REC261-1516 | 32 - Doctrine, standards, and reform | That the NSW National Parks and Wildlife Service remove from its boundary fencing policy and standard contract the condition that requires adjoining land owners to maintain a fence that has been damaged by trees falling from national park land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC259-1046 | 33 - Relief and recovery | That prior to the commencement of any major clean-up, firm policy be established and made known to the extent to which material removal will be the responsibility of the home owner, the Council or the State led recovery effort. |
REC259-1043 | 33 - Relief and recovery | That a single victim registration form be designed, which captures all relevant details required for use by any support agency both in the Response Phase at Evacuation centres and during the Recovery Phase. That such documents when completed form part of a wider database which can be accessed by all relevant agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
REC254-1584 | 32 - Doctrine, standards, and reform | DFES or DEC (depending on land tenure) is mandated to take over control of emergency incidents from Local Government once they have been declared Level 2 incidents. WESTPLAN BUSHFIRE and legislation to be amended accordingly. |
REC254-1580 | 32 - Doctrine, standards, and reform | Critical operational procedures such as ‘Red Flag Warnings’, on a common fireground need to be consistent across DFES, DEC and Local Government. In particular, the operational procedure of Red Flag Warnings needs to be adopted by all WA fire agencies. |
REC254-1588 | 32 - Doctrine, standards, and reform | WA fire agencies adopt a common set of standing orders, operational procedures, training and competencies for rural firefighting that are produced in hard copy, leading to integrated multi-agency training, IMTs, Regional and State coordination/control centres. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0844 | 32 - Doctrine, standards, and reform | That the State Government give high priority to liaising with interstate and Federal processes, and offer to take a lead, on changing the climatic and fire rating arrangements to ensure these match the conditions that can create dangerous bushfire conditions at short notice. |
REC243-0839 | 32 - Doctrine, standards, and reform | That noting the precedents for legislated charters in the Carers Recognition Act 2005 and the Health and Community Services Complaints Act 2004, that the Government support the Fire and Emergency Services (Volunteer Charters) Amendment Bill introduced by the Member for Morphett in November 2012 to enshrine the Country Fire Service and the State Emergency Service at law. |
REC243-0837 | 32 - Doctrine, standards, and reform | That the Government’s Workers Rehabilitation and Compensation (SAMFS Firefighters) Amendment Bill be amended to include Country Fire Service firefighters alongside Metropolitan Fire Service firefighters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2641 | 32 - Doctrine, standards, and reform | That noting the precedents for legislated charters in the Carers Recognition Act 2005 and the Health and Community Services Complaints Act 2004, that the Government support the Fire and Emergency Services (Volunteer Charters) Amendment Bill introduced by the Member for Morphett in November 2012 to enshrine the Country Fire Service and the State Emergency Service at law. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0816 | 1 - Land-use and building regs | Ensure appropriate consideration of flood risk in regional and subregional planning |
REC238-0803 | 32 - Doctrine, standards, and reform | Ensure effective flood gauging arrangements in the Hawkesbury-Nepean Valley |
REC238-0815 | 1 - Land-use and building regs | Provide improved land use planning tools for managing flood prone land. |
REC238-0801 | 1 - Land-use and building regs | Establish a dedicated group or body within an existing agency to provide a more integrated, coordinated and regional approach to land use, infrastructure and evacuation planning and flood modelling in the Hawkesbury-Nepean Valley. |
REC238-0814 | 1 - Land-use and building regs | Develop a NSW Planning Policy and Guideline to improve land use planning practices on flood prone land. |
REC238-0800 | 1 - Land-use and building regs | Improve regional transport infrastructure to address current and projected flood evacuation capacity constraints and timelines. |
REC238-0808 | 1 - Land-use and building regs | Ensure future road infrastructure planning considers flood evacuation requirements throughout the Hawkesbury-Nepean floodplain. |
REC238-0798 | 32 - Doctrine, standards, and reform | Optimise the configuration of a raised Warragamba Dam for flood mitigation of the full range of flood events and water supply, with due consideration of upstream impacts. |
REC238-0806 | 33 - Relief and recovery | Review the adequacy of current arrangements for infrastructure reconstruction following a major flood event in the Hawkesbury-Nepean Valley. |
REC238-0797 | 32 - Doctrine, standards, and reform | Determine the appropriateness and the steps required to allow the reduction of full supply level by up to five metres and/or the implementation of alternative gate operation at Warragamba Dam for the mitigation of minor to moderate flood events in the short-term. |
REC238-0805 | 33 - Relief and recovery | Develop a Hawkesbury-Nepean Flood Recovery Plan, which identifies strategies and arrangement for recovery from severe floods in the Hawkesbury-Nepean Valley. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2804 | 32 - Doctrine, standards, and reform | The committee recommends that Airservices Australia discuss the safety case for providing a hazard alert service with Fijian and New Zealand ATC (and any other relevant jurisdictions) and encourage them to adopt this practice. |
REC236-2789 | 32 - Doctrine, standards, and reform | The committee recommends that the Transport Safety Investigation Act 2003 be amended to require that the Chief Commissioner of the ATSB be able to demonstrate extensive aviation safety expertise and experience as a prerequisite for the selection process. |
REC236-2803 | 32 - Doctrine, standards, and reform | The committee recommends that the government consider setting a time limit for agencies to implement or reject recommendations, beyond which ministerial oversight is required where the agencies concerned must report to the minister why the recommendation has not been implemented or that, with ministerial approval, it has been formally rejected. |
REC236-2786 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB be required to document investigative avenues that were explored and then discarded, providing detailed explanations as to why. |
REC236-2802 | 32 - Doctrine, standards, and reform | The committee recommends that where the consideration and implementation of an ATSB recommendation may be protracted, the requirement for regular updates (for example 6 monthly) should be included in the TSI Act. |
REC236-2785 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB move away from its current approach of forecasting the probability of future events and focus on the analysis of factors which allowed the accident under investigation to occur. This would enable the industry to identify, assess and implement lessons relevant to their own operations. |
REC236-2798 | 32 - Doctrine, standards, and reform | The committee recommends that, where relevant, the ATSB include thorough human factors analysis and discussion in future investigation reports. Where human factors are not considered relevant, the ATSB should include a statement explaining why. |
REC236-2784 | 32 - Doctrine, standards, and reform | The committee recommends that the minister, in issuing a new Statement of Expectations to the ATSB, valid from 1 July 2013, make it clear that safety in aviation operations involving passengers (fare paying or those with no control over the flight they are on, e.g. air ambulance) is to be accorded equal priority irrespective of flight classification. |
REC236-2796 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB-CASA Memorandum of Understanding be re-drafted to remove any ambiguity in relation to information that should be shared between the agencies in relation to aviation accident investigations, to require CASA to: |
REC236-2807 | 32 - Doctrine, standards, and reform | The committee recommends that the Aeronautical Information Package (AIP) En Route Supplement Australia (ERSA) is updated to reflect the need for caution with regard to Norfolk Island forecasts where the actual conditions can change rapidly and vary from forecasts. |
REC236-2794 | 32 - Doctrine, standards, and reform | The committee recommends that CASA, in consultation with an Emergency Medical Services industry representative group (eg. Royal Flying Doctor Service, air ambulance operators, rotary wing rescue providers) consider the merit, form and standards of a new category of operations for Emergency Medical Services. The minister should require CASA to approve the industry plan unless there is a clear safety case not to. Scope for industry to assist as part of an audit team should also be investigated where standardisation is an issue. This should be completed within 12 months and the outcome reported publicly. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2816 | 32 - Doctrine, standards, and reform | The Australian Department of Health and Ageing work with the states and territories to provide a uniform notifiable diseases list across Australia, with consistent reporting requirements across each state and territory and consistent public health information on infectious diseases disseminated to the public. This work should be a priority of Australian Health Ministers’ Advisory Council (AHMAC). |
REC232-2814 | 32 - Doctrine, standards, and reform | The relevant government agencies that have a significant role in managing the biosecurity threat develop a coordinated approach which addresses the health threats to Australians and recognises the impact on the economy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2834 | 32 - Doctrine, standards, and reform | The committee recommends that the Attorney-General's Department facilitate a public consultation process on a regulatory framework for overflow arrangements between public safety agencies and commercial carriers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2839 | 32 - Doctrine, standards, and reform | The committee recommends that disincentives to insurance, such as taxes and levies applied by the states and territories, should be removed as part of a national reform process. |
REC229-2843 | 32 - Doctrine, standards, and reform | The committee recommends that Commonwealth, state and territory governments ensure that all facilities caring for vulnerable groups, in particular hospitals, schools, childcare and aged care facilities, have emergency management plans, relevant to their geographic settings, in place and regularly revised. |
REC229-2842 | 1 - Land-use and building regs | The committee recommends that building codes incorporate mitigation measures that take into account foreseeable risks from extreme weather events. |
REC229-2841 | 1 - Land-use and building regs | The committee recommends that credible and reliable flood mapping activities and the development of other information that would best inform landowners or prospective landowners of potential risks from extreme weather events are prioritised and used to inform land use planning laws. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0594 | 33 - Relief and recovery | Procedures to resolve issues surrounding financial assistance need to be reviewed to ensure they are as smooth, fast and transparent as possible possible. Review and streamline current financial relief procedures. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0580 | 32 - Doctrine, standards, and reform | The role of district and local emergency management committees should be reviewed to ensure they are appropriately engaged in the active management of emergencies across the PPR R continuum |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0592 | 11 - Evacuation and shelters | Decisions on evacuations need to be made early enough for people to be fully informed, prepared and to move to a place of greater safety. Failure to conduct good planning can create situations where loss of life can occur |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0579 | 32 - Doctrine, standards, and reform | Legislative change may be needed to enable FES A to better manage fire- fighting resources across the state. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0569 | 32 - Doctrine, standards, and reform | Section 13 arrangements need to be clarified across key agencies. |
REC226-0598 | 33 - Relief and recovery | When communities are grieving there is a need to provide special forms of support to affected residents. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0596 | 33 - Relief and recovery | An early decision on relief funding enables timely responses. D CP should review their communication of relief arrangements to ensure that they are clear. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0595 | 33 - Relief and recovery | Shire experiences in managing these traumatic events should be captured and passed into emergency management procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0539 | 32 - Doctrine, standards, and reform | WA fire agencies adopt a common set of standing orders, operational procedures, training and competencies for rural firefighting that are produced in hard copy, leading to integrated multi-agency training, IMTs, Regional and State coordination/control centres. |
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC225-0536 | 32 - Doctrine, standards, and reform | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
REC225-0534 | 32 - Doctrine, standards, and reform | Once Recommendation 1 has been actioned, all agencies give greater priority to the promulgation of Red Flag warnings in order to enhance situational awareness on the fireground. |
REC225-0531 | 32 - Doctrine, standards, and reform | Critical operational procedures such as ‘Red Flag Warnings’, on a common fireground need to be consistent across DFES, DEC and Local Government. In particular, the operational procedure of Red Flag Warnings needs to be adopted by all WA fire agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1864 | 32 - Doctrine, standards, and reform | The Chief Executive Officer of the Fire and Emergency Services Authority request the Australasian Fire and Emergency Services Authorities Council to include a new module in the Australasian Inter-service Incident Management System to guide the provision of welfare services for emergency service workers during a disaster. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1820 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop guidelines for the management of levees in emergencies, during and after a flood event, which can be incorporated into local flood response plans. The department will also provide, as part of these guidelines, a set of criteria for assessing the ongoing viability of ad hoc levees post‐flood. The Emergency Management Act 1986 will be amended to support the implementation of these guidelines. A more effective means for councils to remove illegal levees will also be examined by the Department of Sustainability and Environment. |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1830 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop a code of practice on the removal of vegetation around critical public assets, in consultation with councils, CMAs and asset managers. Regional Flood Strategies will support this code of practice as part of shared flood risk management planning. |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1838 | 32 - Doctrine, standards, and reform | That statements of obligations, issued under the Water Industry Act 1994 for water authorities, be amended to include a provision whereby managing authorities must: |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1829 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment should develop guidelines for streamlining the permitting system for works on waterways for incorporation in the revised Victoria Flood Management Strategy. An exemption process will be introduced, with particular application to identified reaches of rivers and streams that require ongoing vegetation management and maintenance: |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1837 | 32 - Doctrine, standards, and reform | The state government give consideration to enacting legislation to provide protection from legal liability for public authorities conducting works on priority levees in good faith, acting reasonably and responsibly in the public interest, and in accordance with standards agreed to under approved schemes. Public authorities should not be excluded from liability if they have acted negligently. |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1828 | 32 - Doctrine, standards, and reform | The revised Victoria Flood Management Strategy should clearly articulate the policy guidelines for the management of vegetation and debris in Victorian waterways, for the purposes of flood protection and mitigation, taking into account the localised potential flooding effects of in‐stream vegetation in townships. |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1834 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop clear policy for the coordinated management of rural drainage, clarifying the legal framework, and identifying authorities with responsibility for the management and ongoing maintenance of formal schemes, and their development: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1878 | 32 - Doctrine, standards, and reform | Regulators can help to achieve improved outcomes by acknowledging that changes to legislation and the BPEM guidelines may be required to help address the identified issues |
REC215-1875 | 1 - Land-use and building regs | Fire services can improve outcomes by seeking input to decisions about siting, design and fire water systems as part of the planning and licensing processes |
REC215-1872 | 32 - Doctrine, standards, and reform | Fire services can improve outcomes by implementing standard procedures that ensure the welfare and safety of crews and the public are not compromised |
REC215-1871 | 14 - Incident Mgt Teams | Fire services can improve outcomes by developing a checklist for use by incident controllers |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0613 | 1 - Land-use and building regs | Councils should ensure that areas for which there has been no assessment of the likelihood of flooding are indicated on a map and that, as part of the development assessment process for these, there is at least some enquiry into whether a site proposed for development could be subject to flooding. |
REC210-0636 | 1 - Land-use and building regs | The Queensland Government should consider allowing councils to amend a planning scheme to update existing flood mapping information by way of the minor amendment process, provided that adequate public consultation has occurred. |
REC210-0659 | 1 - Land-use and building regs | The Queensland Government should consult with councils to formulate a definition of ‘levee’ to identify what should be regulated. |
REC210-0694 | 1 - Land-use and building regs | The Queensland Government should consider whether there should be a legislative requirement that customer dedicated assets be built at or above the applicable defined flood level and if so, the Queensland Government should consider which legislation should contain such a requirement. |
REC210-0733 | 32 - Doctrine, standards, and reform | Emergency Management Queensland should pursue the execution of the ‘Local Arrangements’ with councils where a Memorandum of Agreement is in place. The contents of the arrangements should be reviewed and updated regularly |
REC210-0623 | 1 - Land-use and building regs | The Department of Community Safety should put in place administrative arrangements which ensure it can readily ascertain whether its comments are being reflected in council planning schemes. If the Department of Community Safety becomes aware that its comments are not being adequately addressed, it should take steps to follow this up with the Department of Local Government and Planning. |
REC210-0642 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require the impact of flood on commercial property to be minimised. |
REC210-0672 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirement relating to building design and construction (Performance Requirement P1) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot, and • either: – declared a velocity to be the expected maximum velocity of flood water for the area in which the lot is located, or – designated the area in which the lot is located an inactive flow or backwater area. |
REC210-0770 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to oblige each owner of a referable dam to have an emergency action plan approved by the appropriate Queensland Government agency. Such plans should be reviewed periodically |
REC210-0628 | 1 - Land-use and building regs | The Queensland Government should draft model flood planning controls, using a similar format and structure to that in the Queensland Planning Provisions, that councils can adapt for local conditions. The Queensland Government should require these controls to be reflected in new planning schemes. This may be achieved by including the controls in either: • a state planning policy dealing with flood, with an accompanying amendment to the Sustainable Planning Act 2009, or • the Queensland Planning Provisions. The Queensland Government should consult councils to determine which of the two state planning instruments is the more appropriate to include the model flood planning controls. |
REC210-0649 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters. |
REC210-0677 | 1 - Land-use and building regs | Authorities responsible for the management of sewerage infrastructure should conduct a review of their existing infrastructure to identify electrical infrastructure that may be vulnerable to inundation and perform risk and cost/benefit assessments to determine if it should be relocated to a higher level. |
REC210-0612 | 1 - Land-use and building regs | For non-urban areas or areas where limited development is expected to occur councils should consider, on a risk basis, what level of information about flood risk is required for the area, and undertake the highest ranked of the following options which is appropriate to that need and within the capacities (financial and technical) of the council: a. a map showing ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. a map showing the extent of floods of a range of likelihoods (at least three) c. a flood map based on historic flood levels that have been subjected to a flood frequency analysis to estimate the annual exceedance probability of the selected historical flood d. a historic flood map without flood frequency analysis e. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay as a way to determine those areas for which further flood studies are required, or f. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay (preferably refined using local flood information) as a trigger for development assessment. |
REC210-0635 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to expressly provide either a power to remake or a power to extend a temporary local planning instrument containing interim flood regulation for a further limited period. The power to remake or extend should: a. permit the modification of the temporary local planning instrument to the extent required to ensure its provisions remain relevant, having regard to any requirement that may have been introduced or any information that may have become available while the original temporary local planning instrument was in force b. be contingent on the Minister’s being satisfied that the circumstances listed in section 105 of the Sustainable Planning Act continue to exist and that there are proper grounds for the failure to make a permanent scheme amendment while the original temporary local planning instrument was in force. |
REC210-0658 | 1 - Land-use and building regs | The Queensland Government should consult with councils to determine an effective method for the regulation of the construction of levees in Queensland. In particular, the Queensland Government should consider: • requiring a development permit for the construction of a levee by designating levees as assessable development in the Sustainable Planning Regulation 2009, or • requiring, by way of a state planning policy or mandatory provision in the Queensland Planning Provisions, that councils nominate the construction of a levee as assessable development in their planning schemes. |
REC210-0691 | 1 - Land-use and building regs | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0719 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Environmental Protection Act 1994 so as to permit an emergency direction to be given orally where it is not practicable to provide the direction in writing, with provision for its subsequent confirmation in writing |
REC210-0622 | 1 - Land-use and building regs | If, as part of a state interest review process, the Department of Local Government and Planning decides that no condition should be imposed requiring a council’s proposed planning scheme to incorporate the effect of the Department of Community Safety’s comments about State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide, it should advise the Department of Community Safety of the reasons for its decision. |
REC210-0640 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0666 | 1 - Land-use and building regs | The Queensland Government should draft a model planning scheme policy to be included in the model flood planning controls that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0760 | 32 - Doctrine, standards, and reform | CS Energy should amend its business procedure to remove any ambiguity as to the establishment of communications with Seqwater and to acknowledge the formal communications protocol regarding releases. |
REC210-0627 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to require that consideration be given to the risk of flooding in the preparation or revision of a regional plan. |
REC210-0647 | 1 - Land-use and building regs | The Department of Environment and Resource Management should ensure that, when applications for a material change of use for an environmentally relevant activity are approved by the department, the details of those activities, including their nature and location, are provided to the council within whose area the activity will be conducted. |
REC210-0676 | 1 - Land-use and building regs | Authorities responsible for the construction of sewerage infrastructure should, when embarking on new works, undertake risk and cost/benefit assessments to determine the level at which electrical infrastructure that may be vulnerable to inundation should be placed. |
REC210-0611 | 1 - Land-use and building regs | For urban areas or areas where development is expected to occur: a. councils with the requisite resources should develop a flood map which shows ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. councils without the requisite resources to produce a flood behaviour map should develop a flood map which shows the extent of floods of a range of likelihoods (at least three). |
REC210-0634 | 1 - Land-use and building regs | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include in their planning schemes a planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as a part of the development application, or • for development proposed on land where potential for flooding is unknown requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information to allow an assessment of the flood risk. |
REC210-0657 | 1 - Land-use and building regs | Levees should be regulated. |
REC210-0690 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0717 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 to provide a definition of the term ‘emergency’ for the purposes of section 468 of that Act. |
REC210-0621 | 1 - Land-use and building regs | The Queensland Government should: a. narrow the definition of ‘development commitment’ in State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide to ensure more development applications are assessed for compatibility with flood, and b. investigate whether the compensation provisions of the Sustainable Planning Act 2009 act as a deterrent to the inclusion of flood controls in a planning scheme and consider whether they ought be amended. |
REC210-0639 | 1 - Land-use and building regs | The Queensland Government should consider extending the application of a state planning policy dealing with flood to the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood. |
REC210-0662 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0759 | 32 - Doctrine, standards, and reform | CS Energy should review its emergency action plan and business procedures to ensure they are wholly consistent and give appropriate consideration to flooding as a possible emergency event. |
REC210-0626 | 1 - Land-use and building regs | Councils should consider using the limited development (constrained land) zone in their planning schemes for areas that have a very high flood risk. |
REC210-0646 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend the template assessment report used to assess applications for a material change of use for environmentally relevant activities so that it prompts departmental officers to give specific consideration, as part of the assessment process, to the risk of flooding at the site where the activity is proposed to occur. |
REC210-0675 | 1 - Land-use and building regs | The Queensland Government should consider including in the criteria in the Queensland Plumbing and Wastewater Code a requirement that the risk of leakage from private on-site sewerage systems during floods be minimised. |
REC210-0633 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as part of the development application, or • for development proposed on land where the potential for flooding is unknown, requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information, to allow an assessment of the flood risk. |
REC210-0656 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Regulation 2009 so that operational work or plumbing or drainage work (including maintenance and repair work) carried out by or on behalf of a public sector entity authorised under a state law to carry out the work is not exempt development under the Sustainable Planning Act 2009 if the development has the potential to reduce floodplain storage. |
REC210-0685 | 1 - Land-use and building regs | In assessing and determining development applications for material change of use in areas susceptible to flood, councils should consider whether the new developments locate essential services infrastructure above basement level, or, alternatively, whether essential services infrastructure located at basement level can be constructed so that it can continue to function during a flood. |
REC210-0714 | 32 - Doctrine, standards, and reform | The Queensland Government should consider amending the Environmental Protection Act 1994 so that it allows for the relaxation of environmental authority conditions, by transitional environmental program or otherwise, as to discharge of water: • pre-emptively, in advance of rainfall or flooding events, or • for all mines in a catchment that is flooding. |
REC210-0617 | 1 - Land-use and building regs | The Queensland Government should consider implementing a mechanism by which prospective purchasers of property are alerted to the issue of flood risk. To that end, the Queensland Government should consider consulting the Real Estate Institute of Queensland and the Law Society of Queensland as to the appropriateness of amending standard contract conditions so as to include a ‘subject to flood search’ condition, or other means of achieving the same objective. |
REC210-0638 | 1 - Land-use and building regs | The Coordinator-General should amend the guideline for preparing an ‘initial advice statement’ for a significant project under the State Development and Public Works Organisation Act 1971 so that it specifically requires an applicant to consider and provide information about the project’s flood risk. |
REC210-0661 | 1 - Land-use and building regs | There should be a common set of considerations in the decision whether to approve an application to build a levee, including: • the impacts of the proposed levee on the catchment as a whole • the benefits of the proposed levee to the individual or entity applying to build the levee and to any nearby community as a whole • any adverse impacts on other landholders, including the risk of levee failure • the implications of the proposed levee for land planning and emergency management procedures • whether any structural, land planning or emergency management measures can be taken to mitigate the adverse impacts of the proposed levee. |
REC210-0750 | 32 - Doctrine, standards, and reform | The assessment of flood mitigation manuals should be completed by a person with appropriate expertise who has had no involvement in its development, at any stage, and who can be seen to be independent of all individuals who were so involved. |
REC210-0625 | 1 - Land-use and building regs | The Queensland Government should change Temporary State Planning Policy 2/11: Planning for stronger more resilient floodplains to remove the possibility of councils’ using the interim floodplain assessment overlay mapping and Model Code as part of a permanent amendment to their existing planning scheme or as part of a new planning scheme. |
REC210-0645 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend its information sheet about applications for a material change of use for environmentally relevant activities so that applicants are prompted to include information (if any) about the risk of flooding at the site where the activity is proposed to occur. |
REC210-0674 | 1 - Land-use and building regs | The Queensland Government should consider amending the ‘Limitation’ section of the proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, to allow for the possible application of ‘acceptable solution A1’ to a building located on a lot if: • it is reasonable to expect the part of the lot on which the building work is proposed to be subjected to a maximum velocity of less than 1.5 metres per second, or • the part of the lot on which the building work is proposed is located in an inactive flow or backwater area. |
REC210-0631 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0654 | 1 - Land-use and building regs | The Queensland Government should consider drafting assessment criteria to be included in the model flood planning controls which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the applicable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms) • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0684 | 1 - Land-use and building regs | Councils should consider amending their planning schemes to include provisions directed to consideration of the flood resilience of basements as a factor in determining the appropriateness of a material change of use. |
REC210-0712 | 32 - Doctrine, standards, and reform | The Queensland Government should legislate to clarify the purposes for which a transitional environmental program can be granted. In particular, if the government considers the transitional environmental program the appropriate regulatory mechanism to deal with the discharge of water from mines during flood, section 330 of the Environmental Protection Act 1994 should be clarified to make it clear that it extends to that use. |
REC210-0616 | 1 - Land-use and building regs | Councils that do not currently do so should consider offering an online database which allows the public to conduct a search on a parcel of land to find development approvals relevant to that parcel of land. |
REC210-0637 | 1 - Land-use and building regs | The Queensland Government should consider amending the Urban Land Development Authority Act 2007, the South Bank Corporation Act 1989, the State Development and Public Works Organisation Act 1971 insofar as it governs state development areas, and other legislation which establishes alternative planning systems that operate independently of the Sustainable Planning Act 2009, to require that: • any planning scheme, interim or otherwise, appropriately reflects any state planning policy with respect to flood • flood risk be considered in the assessment of any development application. |
REC210-0660 | 1 - Land-use and building regs | There should be a consistent process for the determination of applications to build levees. That process should include: • consulting landholders who may be affected by the proposed levee • obtaining or commissioning appropriate hydrological and hydraulic studies to assess the impacts of the proposed levee. |
REC210-0697 | 1 - Land-use and building regs | Queensland Rail and QR National should continue to investigate opportunities for increasing the flood resilience of their networks, including raising the height of critical equipment. |
REC210-0749 | 32 - Doctrine, standards, and reform | The Queensland Government should amend the Water Supply (Safety and Reliability) Act 2008 to designate the Minister as the person who must approve a flood mitigation manual. |
REC210-0624 | 1 - Land-use and building regs | The Queensland Government should ensure that the circumstances in which the Department of Community Safety is to consult the Department of Environment and Resource Management about a planning scheme’s flood modelling and flood mapping are clear. |
REC210-0644 | 1 - Land-use and building regs | The Queensland Government should ensure that the criteria under the Environmental Protection Act 1994 that apply to the assessment of development applications for material change of use for environmentally relevant activities include consideration of the risk of flooding at the site on which the activity is proposed to occur. |
REC210-0673 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirements about utilities and sanitary drains (Performance Requirement P2 and P3) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot. |
REC210-0629 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a requirement that councils have a flood overlay map in their planning schemes. The map should identify the areas of the council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0652 | 1 - Land-use and building regs | The Queensland Government should review the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003 to consider whether the design and construction standards should be made more stringent than the existing standards. |
REC210-0682 | 1 - Land-use and building regs | The Department of Environment and Resource Management should review the Queensland Urban Drainage Manual to determine whether it requires updating or improvement, in particular, to reflect the current law and to take into account insights gained from the 2010/2011 floods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1678 | 32 - Doctrine, standards, and reform | That the Bushfires Act and Regulations be reviewed and modernised after the implementation of the recommendations of this review. |
REC209-1670 | 32 - Doctrine, standards, and reform | Bushfires NT create a bushfire management strategy and emergency response procedures framework including the criteria that define the escalation and response requirements for all incidents up to and including the establishment of an EOC, applicable for all regions across the Territory. |
REC209-1659 | 32 - Doctrine, standards, and reform | Regional Fire Management Plans be reviewed for all regions prior to the start of each fire season. |
REC209-1645 | 14 - Incident Mgt Teams | Ensure that adequate administrative personnel are available within the incident control structure to provide administrative and knowledge management support for incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0530 | 32 - Doctrine, standards, and reform | That, if necessary, regulation be amended to require Health to approve any script used by any party concerned, for door knocking or other information dissemination, if Health is not the first source of information to affected residents. |
REC208-0529 | 32 - Doctrine, standards, and reform | That, when developing requirements concerning pollution incident response management plans pursuant to the recent legislative amendments, the Office of Environment and Hertiage include appropriate definitions as to the meaning of ‘immediately’, and when ‘material harm to the environment is caused or threatened’. |
REC208-0528 | 32 - Doctrine, standards, and reform | That, as part of the Pollution Incident Management Response Plan to be developed for Orica’s Kooragang Island site, or by another appropriate mechanism, the Office of Environment and Heritage ensure that Orica’s incident-response procedures address the need to consider all relevant factors when assessing potential impacts, including the height and force of emissions as well as the location of any onsite fallout and whether there are off-site impacts following all serious incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC206-1883 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government amend the Insurance Contracts Act 1984 (Cth) so that from 1 July 2012 any derogation from Standard Cover is required to be communicated to policyholders as a departure from ideal standards: |
REC206-1882 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government amend the Insurance Contracts Act 1984 (Cth) to make it obligatory that insurers offer to consumers the option of a general insurance policy that conforms to Standard Cover, as prescribed in the Insurance Contracts Regulations 1985 (Cth), from 1 July 2012, so that all insurers carry a product that provides full replacement in the event of total loss and cover for damages resulting from flood. |
REC206-1890 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Securities and Investments Commission amend Regulatory Guideline 165 to: |
REC206-1889 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government introduce legislation by 1 March 2013 to make adherence to the General Insurance Code of Practice a compulsory requirement for all general insurers. |
REC206-1887 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Securities and Investments Commission amend Regulatory Guideline 139 by 1 July 2012 to require the Financial Ombudsman Service to report regularly to the Australian Securities and Investments Commission and also to make public: |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1917 | 32 - Doctrine, standards, and reform | The review of the Health Act 1911 (WA) should include the following amendments: |
REC204-1907 | 32 - Doctrine, standards, and reform | The Department of Sport and Recreation facilitate the development of an Adventure Activity Standard for ultramarathons in order to determine a minimum safety standard for the sport. |
REC204-1921 | 32 - Doctrine, standards, and reform | The Coroner’s Act 1996 should be amended to give the Coroner jurisdiction to investigate fires that do not cause death, and that the Coroner should be suitably resourced to undertake investigations of the kind the subject of this Report. |
REC204-1919 | 1 - Land-use and building regs | Tourism WA must give specific regard as to whether land use approvals need to be sought, particularly from Department of Regional Development and Lands, when conducting due diligence for event sponsorship proposals that require sign off by both departments. |
REC204-1918 | 1 - Land-use and building regs | Department of Regional Development and Lands and Department of Environment and Conservation should consider how their respective land use approval processes can incorporate the input of Local Emergency Management Committees (LEMCs) as part of risk assessments for high risk events and adventure sport activities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0297 | 32 - Doctrine, standards, and reform | The role of district and local emergency management committees should be reviewed to ensure they are appropriately engaged in the active management of emergencies across the PPR R continuum |
REC203-0296 | 32 - Doctrine, standards, and reform | Legislative change may be needed to enable FES A to manage fire-fighting resources across the state. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
REC203-0308 | 33 - Relief and recovery | Early resolution and clear communication of the financial and other support measures that will be available to affected residents is an important contributor to community resilience. |
REC203-0307 | 11 - Evacuation and shelters | When people are being moved away from their homes it’s important that they move to a place of greater safety and that their movement is relatively assured. |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0502 | 32 - Doctrine, standards, and reform | The Minister for Environment bring to Parliament by June 2012 amendments to the Conservation and Land Management Act 1984 that reflect the use by the Department of Environment and Conservation of prescribed burns for both biodiversity conservation and community protection purposes. |
REC202-0499 | 32 - Doctrine, standards, and reform | The Minister for Emergency Services institute a thorough review by December 2012, including a comparison to other jurisdictions, of the risk analysis processes used by FESA, the Police and DEC to prepare them to protect the State from bushfires and other natural disasters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2905 | 14 - Incident Mgt Teams | The Fire Services Commissioner ensures that there is a single standard for the tabards worn by the IMT on the fireground and in control centres to ensure consistency and aid interoperability. |
REC198-2902 | 14 - Incident Mgt Teams | The Fire Services Commissioner clarifies the role of regional controller for major fires and incidents other than bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0313 | 32 - Doctrine, standards, and reform | The Fire Services expedite programmed work on joint operational command and control, including standards, procedures and training |
REC195-0312 | 32 - Doctrine, standards, and reform | The Fire Services Commissioner ensures that joint fireground command and control, integration and escalation procedures are developed, particularly for ‘fastrunning’ fires |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
REC195-0311 | 32 - Doctrine, standards, and reform | The Fire Services ensure that agency specific operational procedures fully align with the arrangements. |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
Rec-ID | Code | Recommendation |
---|---|---|
REC188-2916 | 33 - Relief and recovery | The committee recommends that the Department of Regional Australia and DIAC liaise with the Christmas Island community to explore options for a permanent memorial to be erected on the island, at a site of the residents' choosing, for the victims of the tragedy. |
REC188-2915 | 33 - Relief and recovery | The committee recommends that Department of Immigration and Citizenship (DIAC) and its relevant contractors continue to monitor the wellbeing of the survivors and that counselling and support services should be provided for as long as is necessary. |
REC188-2917 | 33 - Relief and recovery | The committee recommends that relevant Commonwealth agencies continue to monitor the wellbeing of their personnel and that counselling and support services should be provided for as long as necessary. |
Rec-ID | Code | Recommendation |
---|---|---|
REC186-0396 | 32 - Doctrine, standards, and reform | The committee recommends that the Commonwealth Government together with national, state and territory emergency service organisations and radio and television broadcasters, develop a secure database of up-to-date contact details for key personnel to be used during an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0163 | 32 - Doctrine, standards, and reform | The State consider amending the Emergency Management Act 1986 to introduce a graded scale of emergency declarations short of a state of disaster. |
REC181-0197 | 1 - Land-use and building regs | Standards Australia do the following: ■ amend the objective of AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, to ensure that it incorporates reducing the risk of ignition from ember attack; ■ review, and amend as appropriate, the testing methods prescribed in its standards for Tests on Elements of Construction for Buildings Exposed to Simulated Bushfire Attack (AS 1530.8.1 and AS 1530.8.2) to ensure that, so far as is possible, the methods provide a reliable predictor of the performance of construction elements under bushfire conditions. |
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0205 | 1 - Land-use and building regs | The State initiate the development of education and training options to improve understanding of bushfire risk management in the building and planning regimes by: ■ providing regular training and guidance material to planning and building practitioners; ■ providing regular training and guidance material to planning and building practitioners. |
REC181-0162 | 32 - Doctrine, standards, and reform | The State consider either amending the Emergency Management Act 1986 or adopting a standing practice to require the Minister for Police and Emergency Services or the Chief Commissioner of Police to consult the Premier about the possibility of declaring a state of disaster for all of or any part of Victoria whenever the Minister or the Chief Commissioner of Police becomes aware of circumstances that make it a reasonable possibility that the criteria for making such a declaration will be satisfied. |
REC181-0196 | 1 - Land-use and building regs | The State develop and implement a retreat and resettlement strategy for existing developments in areas of unacceptably high bushfire risk, including a scheme for non-compulsory acquisition by the State of land in these areas. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0203 | 1 - Land-use and building regs | The State amend s. 32 of the Sale of Land Act 1962 to require that a vendor’s statement include whether the land is in a designated Bushfire-prone Area, a statement about the standard (if any) to which the dwelling was constructed, the bushfire attack level assessment at the time of construction (where relevant) and a current bushfire attack level assessment of the site of the dwelling. |
REC181-0188 | 1 - Land-use and building regs | The State implement a regional settlement policy that: ■ takes account of the management of bushfire risk, including that associated with small, undeveloped rural lots; ■ includes a process for responding to bushfire risk at the planning stage for new urban developments in regional cities, the process being similar to that used for new developments in Melbourne’s Urban Growth Zone. |
REC181-0191 | 1 - Land-use and building regs | The State: ■ amend the Victoria Planning Provisions to require that, when assessing a permit to remove native vegetation around an existing dwelling, the responsible authority and the Department of Sustainability and Environment, as referral authority, take into account fire hazard and give weight to fire protection purposes; ■ develop guidelines for determining the maximum level of native vegetation removal for bushfire risk mitigation, beyond which level the application would be rejected. |
REC181-0164 | 32 - Doctrine, standards, and reform | The Victorian fire agencies amend the AIIMS framework before the 2010–11 fire season in order to do the following: ■ designate the Information Unit as a separate section reporting directly to the Incident Controller and require that the Information Unit contain a dedicated Public Information Officer whenever a full incident management team is required; ■ specify a set of functions in relation to which the Deputy Incident Controller for a level 3 incident will have oversight, which may be adjustable for a particular incident by agreement between the Incident Controller and the Deputy Incident Controller; ■ ensure that an individual with local knowledge is incorporated in an incident management team |
REC181-0200 | 1 - Land-use and building regs | Standards Australia move expeditiously to develop a standard for bushfire sprinklers and sprayers. |
REC181-0161 | 32 - Doctrine, standards, and reform | The State consider amending the Emergency Management Act 1986 and the Emergency Management Manual Victoria in order to achieve the following: ■ remove the title of Coordinator in Chief of Emergency Management from the Minister for Police and Emergency Services; ■ clarify the function and powers of the Minister; ■ designate the Chief Commissioner of Police as Coordinator in Chief of Emergency Management, who would have primary responsibility for keeping the Minister informed during an emergency. |
REC181-0190 | 1 - Land-use and building regs | The Country Fire Authority amend its guidelines for assessing permit applications for dwellings, nondwellings and subdivisions in the Bushfire-prone Overlay in order to accommodate the amendments to the Wildfire Management Overlay that are implemented as a result of recommendation 39 and make the guidelines available to municipal councils and the public. The revised guidelines should do the following: ■ substantially restrict new developments and subdivisions in those areas of highest risk in the Bushfire-prone Overlay; ■ set out the CFA’s guidelines for assessing permit applications for dwellings, non-dwellings and subdivisions—including the minimum defendable space requirements for different risk levels; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ emphasise the need for enduring permit conditions—in particular, conditions for the creation and maintenance of minimum defendable space to be maintained for the life of the development. |
REC181-0199 | 1 - Land-use and building regs | The State modify its adoption of the Building Code of Australia for the following purposes: ■ to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ to apply bushfire construction provisions to non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities; ■ other than in exceptional circumstances, to apply a minimum AS 3959-2009 construction level of BAL-12.5 to all new buildings and extensions in bushfire-prone areas. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0213 | 32 - Doctrine, standards, and reform | The State enact legislation designed to achieve two specific ends: ■ appoint a Fire Commissioner as an independent statutory officer responsible to the Minister for Police and Emergency Services and as the senior operational firefighter in Victoria; ■ make the Chief Fire Officer of the Department of Sustainability and Environment a statutory appointment. The Fire Commissioner should have responsibility for the following: ■ promoting and directing reform aimed at increasing the operational capability, interoperability and resilience of Victoria’s fire services; ■ developing and building operational capacity to prepare for the days of highest bushfire risk and exercising control over level 3 fires as the permanent State Controller; ■ providing to government periodic advice on the metropolitan fire district boundary on the basis of triggers, frequency and criteria approved by government; ■ representing Victorian interests on operational matters in national committees. |
REC181-0189 | 1 - Land-use and building regs | The State amend the Victoria Planning Provisions relating to bushfire to ensure that the provisions give priority to the protection of human life, adopt a clear objective of substantially restricting development in the areas of highest bushfire risk—giving due consideration to biodiversity conservation—and provide clear guidance for decision makers. The amendments should take account of the conclusions reached by the Commission and do the following: ■ outline the State’s objectives for managing bushfire risk through land-use planning in an amended state planning policy for bushfire, as set out in clause 15.07 of the Victoria Planning Provisions; ■ allow municipal councils to include a minimum lot size for use of land for a dwelling, both with and without a permit, in a schedule to each of the Rural Living Zone, Green Wedge Zone, Green Wedge A Zone, Rural Conservation Zone, Farming Zone and Rural Activity Zone; ■ amend clause 44.06 of the Victoria Planning Provisions to provide a comprehensive Bushfire-prone Overlay provision. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0198 | 1 - Land-use and building regs | The Australian Building Codes Board do the following: ■ amend the performance requirements in the Building Code of Australia to ensure that they incorporate reducing the risk of ignition from ember attack; ■ work with Standards Australia to effect expeditious continuing review and development of AS 3959, Construction of Buildings in Bushfire-prone Areas, and other bushfire-related standards referred to in the Building Code of Australia; ■ negotiate with Standards Australia and SAI Global Ltd an arrangement for free online access to AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, the other Australian standards referred to in AS 3959-2009, and any other bushfire-related Australian standards referred to in the Building Code of Australia; ■ amend the Building Code of Australia to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ include in the Building Code of Australia bushfire construction provisions for non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities. |
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
REC181-0158 | 32 - Doctrine, standards, and reform | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require the following: ■ that at locations that attract preparedness levels A or B there be a full incident management team under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of code red fire danger and a core incident management team (eight personnel) under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of extreme fire danger; ■ that at locations that attract preparedness levels A or B there be a full incident management team under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of code red fire danger and a core incident management team (eight personnel) under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of extreme fire danger. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0209 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment amend the Code of Practice for Fire Management on Public Land in order to achieve the following: ■ provide a clear statement of objectives, expressed as measurable outcomes; ■ include an explicit risk-analysis model for more objective and transparent resolution of competing objectives, where human life is the highest priority; ■ specify the characteristics of fire management zones—including burn size, percentage area burnt within the prescribed burn, and residual fuel loading; ■ adopt the use of the term ‘bushfire’ rather than ‘wildfire’. |
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0142 | 1 - Land-use and building regs | The Commonwealth consult with local, state and territory government planning authorities on the development and dissemination of a house loss risk index for households in Australia's highest risk bushfire areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0100 | 32 - Doctrine, standards, and reform | The prioritising of the critical amendments to the Bush Fires Act 1954 recommended by the Community Development and Justice Standing Committee that relate to fire management, ie: a. Fire and Emergency Services Authority (FESA)‘s ability to assume control of a fire in specific circumstances b. Amendments to the definition of property c. Providing FESA with the authority to declare a total fire ban |
REC173-0104 | 1 - Land-use and building regs | That FESA assess the cost and other implications of proposed changes to bushfire prone zone declarations which would allow the whole State to be declared bushfire prone. |
REC173-0102 | 32 - Doctrine, standards, and reform | That further amendments be made to the Bush Fires Act 1954 be drafted to provide fire response agencies with the necessary authorisation and statutory protection to respond to a fire on private property, or land that Local Government, Department of Environment and Conservation (DEC) or FESA is responsible for, until such time as the responsible agency is able to attend and take control. The amendments to be drafted, in conjunction with the urgent progression of critical amendments as recommended by the Community Development and Justice Standing Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0018 | 32 - Doctrine, standards, and reform | The Interagency Guidelines need to be amended to reflect what is operationally possible with regard to risk management rather than what is required to achieve an absence of risk. |
REC172-0001 | 32 - Doctrine, standards, and reform | The Emergency Management Regulations 2006 be urgently amended to determine a HMA(s) for bushfire. |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0003 | 32 - Doctrine, standards, and reform | All incidents where the HMA delegates the authority to manage suppression operations to another agency on its behalf, should be achieved via a written delegation setting out the scope, limitations and duration of the delegation. |
REC172-0021 | 32 - Doctrine, standards, and reform | Unassigned resources arriving at incidents should be encouraged to make themselves known and to undertake alternate duties. |
REC172-0002 | 32 - Doctrine, standards, and reform | The Emergency Management Act 2005 is amended to provide a mechanism for one HMA to transfer responsibility to another HMA and ensure that both HMA’s are provided the powers and protection necessary under that Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3441 | 32 - Doctrine, standards, and reform | That, where practical, risk assessments, emergency planning, training and exercising are integrated to minimise duplication of effort. |
REC158-3427 | 32 - Doctrine, standards, and reform | That the standards and guidelines determined by the nominated marine safety authority require port/channel managers to conduct a marine emergency risk assessment using AS/NZ 4360:2004 Risk Management and, in addition, must require port/channel managers to: |
REC158-3440 | 32 - Doctrine, standards, and reform | That the Water Division Emergency Response Plan is amended, by the Water Division emergency response coordinator, to provide a framework to coordinate a marine response that crosses declared port water boundaries and requires resource coordination and prioritisation. |
REC158-3426 | 32 - Doctrine, standards, and reform | That the nominated marine safety authority, in consultation with the Emergency Services Commissioner, senior emergency services personnel and relevant port stakeholders, is responsible for establishing appropriate performance standards, risk management guidelines and good practice guidelines for marine emergency management. |
REC158-3439 | 32 - Doctrine, standards, and reform | That the port marine emergency management arrangements are integrated with the Victorian Water Division Emergency Response Plan. |
REC158-3425 | 32 - Doctrine, standards, and reform | Consequential or complementary amendments to the Emergency Management Act are required to ensure that: |
REC158-3436 | 32 - Doctrine, standards, and reform | That Harbour Masters are the designated principle marine specialists within the port and work directly with emergency services to provide advice and the interface with the marine legislative powers, to manage a marine emergency. |
REC158-3438 | 32 - Doctrine, standards, and reform | That the port/channel managers coordinate marine emergency management planning in the port and are required to ensure that individual port stakeholder marine emergency management arrangements plans are integrated with the whole of port marine emergency management arrangements. |
REC158-3424 | 32 - Doctrine, standards, and reform | That legislation is prepared by the Department of Transport to ensure marine emergency management arrangements are clarified and provide: |
REC158-3435 | 32 - Doctrine, standards, and reform | That Harbour Masters have the appropriate powers, authority, accountability, skills, responsibility and indemnity to provide a coordinated response of marine resources in support of emergency services, except where the nominated marine safety authority is the control agency for a marine pollution or marine casualty emergency. |
REC158-3437 | 32 - Doctrine, standards, and reform | That port/channel managers coordinate marine emergency planning for the port and are required to ensure that marine emergency arrangements are integrated with whole of port emergency management plans. |
REC158-3453 | 32 - Doctrine, standards, and reform | That, where applicable, consideration is given to legislative amendment that will enable the findings of this report to be applied to areas inside State waters but outside commercial port waters. |
REC158-3434 | 32 - Doctrine, standards, and reform | That the accountability relationship between Harbour Masters and the Director of Marine Safety is strengthened in the relevant legislation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3484 | 32 - Doctrine, standards, and reform | The Victoria State Emergency Service finalise its development of strategic emergency response management plans including severe weather and storm events. |
REC156-3504 | 32 - Doctrine, standards, and reform | The Emergency Services Telecommunications Authority develop a protocol to direct the suspension or cessation of scheduled telecommunication maintenance or testing to emergency alert systems during an emergency event. |
REC156-3513 | 32 - Doctrine, standards, and reform | The Department of Primary Industries in consultation with the energy sector develop and implement a Memorandum of Understanding or similar authorising instrument that provides a single contact for emergency |
REC156-3501 | 32 - Doctrine, standards, and reform | The Country Fire Authority review their procedures regarding receipt of Triple Zero calls on the Brigade Spectrum Preset Conference including training material, testing procedures and interface back to the Emergency Services Telecommunications Authority Computer Aided Dispatch system. |
REC156-3511 | 32 - Doctrine, standards, and reform | The operational protocols of the Emergency Management Joint Public Information Committee be formally endorsed by the State Emergency Response Planning Committee and the Victorian Emergency Management |
REC156-3499 | 32 - Doctrine, standards, and reform | The Department of Primary Industries clearly document responsibilities within the Department to ensure better co-ordination of public information during emergencies. |
REC156-3510 | 32 - Doctrine, standards, and reform | Victoria’s emergency management arrangements as they relate to the Emergency Management Joint Public Information Committee be enhanced to include greater clarity of its operational role in the Emergency Management Manual Victoria. |
REC156-3498 | 32 - Doctrine, standards, and reform | The Department of Primary Industries, Department of Premier and Cabinet, and the Office of the Emergency Services Commissioner review and clarify energy sector emergency event trigger points for the activation of Central Government Response Committee. |
REC156-3508 | 32 - Doctrine, standards, and reform | The Australian Broadcast Corporation and Emergency Services Organisations redevelop the protocols for the use of the Memorandum of Understanding; and all relevant emergency services and ABC staff are trained in the use of the protocols. |
REC156-3489 | 32 - Doctrine, standards, and reform | The Department of Primary Industries responsibility for emergency management within the energy sector needs to be reinforced consistent with Recommendation 5. |
REC156-3505 | 32 - Doctrine, standards, and reform | The Emergency Service Organisations and the Emergency Services Telecommunications Authority agree on the direct telephone numbers to be used for contacting the Emergency Services Telecommunications Authority in relation to emergency incidents. The Emergency Service Organisations need to ensure an effective process is in place to educate their personnel in relation to the use of these numbers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3482 | 32 - Doctrine, standards, and reform | That the Victorian Government, and responsible agencies, expedite the implementation of the Integrated Fire Management Planning framework. |
REC155-3480 | 1 - Land-use and building regs | That the Integrated Fire Management Planning framework establish zones in the interface between public and private land in which bushfire risk management is the shared responsibility of the Victorian Government and private landholders. |
REC155-3479 | 32 - Doctrine, standards, and reform | That a process of year round community engagement in the preparation of Fire Operations Plans be established. In addition a record of year round community engagement, as contained in the Gippsland Fire Operations Plan, should be a requirement of all Fire Operations Plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC152-3405 | 32 - Doctrine, standards, and reform | Clarity of Role with regard to legislative and policy requirements |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3180 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that each horse be tested for equine influenza as close as practicable before the end of the quarantine period and that a negative result for that test be available before the horse may be released from quarantine. Until more sensitive and specific detection tests become available, an agent detection test for influenza A - either a quantitative PCR test or an antigen-capture ELISA test - should be used for that purpose. |
REC148-3156 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that the horse be tested for equine influenza at a time as close as practicable to the end of the pre- export quarantine period. Until more sensitive and specific detection tests become available, an agent test for influenza A—either a quantitative PCR or an antigen-capture ELISA test—should be used. |
REC148-3171 | 32 - Doctrine, standards, and reform | That the operating procedures require that there be identified a person who has overall responsibility for the various clearance procedures and biosecurity tasks to be performed in the course of unloading horses at an airport and transferring them to a quarantine station. |
REC148-3179 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that the nasopharyngeal swabs taken within 24 hours of arrival and five days after the last horse arrives in post-arrival quarantine be divided and the swabs made subject to a quantitative PCR test and a ‘rapid’ immuno-assay test to detect influenza A. The operating procedures should also require that these additional tests be conducted. |
REC148-3155 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that a blood sample be taken while a horse is in pre-export quarantine. Part of the sample is to be retained in the country of export and another part of that sample is to be transported to Australia, preferably with the horse. Both parts are to be retained for at least three months. |
REC148-3160 | 32 - Doctrine, standards, and reform | That, before a horse is loaded on to an aircraft or vessel for carriage to Australia, AQIS verify that there exists such certification as is required by its import conditions up to the time the horse arrives at the airport of departure and that the horse complies with those conditions. This could be done by facsimile or electronic communication with AQIS officers in Australia. |
REC148-3176 | 32 - Doctrine, standards, and reform | That there be prepared operating procedures or a manual that: |
REC148-3153 | 32 - Doctrine, standards, and reform | That premises be used for pre-export quarantine only if they have been approved by the officer responsible for the importation of horses and only if they have adequate biosecurity precautions that are the subject of documented procedures that can be audited. The import conditions for horses shall include a requirement that pre-export quarantine premises have been so approved. |
REC148-3159 | 32 - Doctrine, standards, and reform | That the import conditions for horses specify that there be available for inspection at the port of loading and produced on the horse’s arrival in Australia, certification (including in electronic form) that the horse has been vaccinated, has had a blood sample taken during pre-export quarantine, and has passed a suitable detection test, currently either a quantitative PCR or an antigen-capture ELISA test for influenza A. |
REC148-3174 | 32 - Doctrine, standards, and reform | That the operating procedures require, as a condition of entry for all non- AQIS personnel to a quarantine station, that each person report any suspected breach (by that or any other person) of quarantine procedures in the quarantine station and that a person may be excluded from entry to a quarantine station in the event of a breach of such procedures by that person or in the event of a failure of that person to report any suspected breach. |
REC148-3150 | 32 - Doctrine, standards, and reform | That the position of Inspector General of Horse Importation: |
REC148-3158 | 32 - Doctrine, standards, and reform | That the import conditions for horses specify, based on advice from Biosecurity Australia that is reviewed at least annually, the vaccines for equine influenza to be administered to horses before they are exported, taking account of the countries or regions from which the horses are exported. If there are commercially available vaccines that contain representatives of currently circulating strains, the import conditions should specify that the horses be vaccinated using that vaccine or one of those vaccines. Otherwise, the conditions should specify the vaccine or vaccines that may be used, based on the advice of Biosecurity Australia. |
REC148-3173 | 32 - Doctrine, standards, and reform | That the operating procedures require that the duties of any people responsible for maintaining 24 hour security at a quarantine station (whether they be AQIS officers or private contractors) are recorded in writing and that those people have received training in relation to biosecurity risks sufficient to instil an appreciation of such acts or circumstances as might give rise to biosecurity risks. |
REC148-3183 | 32 - Doctrine, standards, and reform | That the Quarantine Act 1908 be reviewed in order to identify amendments necessary to ensure that the Act clearly and adequately confers all relevant powers to ensure the biosecurity of horse importation and quarantine and to give effect to these recommendations. |
REC148-3157 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that the operations and procedures at the pre-export quarantine premises may from time to time, be inspected and audited by or on behalf of the Australian Government. |
REC148-3172 | 32 - Doctrine, standards, and reform | That the operating procedures require that the manager of a quarantine station be responsible for ensuring that a written report on compliance with procedures is prepared and reviewed daily and that any non-compliance and corrective action are recorded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC146-3192 | 32 - Doctrine, standards, and reform | The committee recommends, in accordance with the findings of the Hawke Taskforce, that CASA's Regulatory Reform Program be brought to a conclusion as quickly as possible to provide certainty to industry and to ensure CASA and industry are ready to address future safety challenges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3213 | 1 - Land-use and building regs | The Committee notes the Council of Australian Governments initiative (through the Local Government and Planning Ministers Council) to develop state-specific climate change planning policies by mid 2011, to inform local governments and regional planning responses to climate change. The Committee recommends that the Australian Government ensure that the outcomes of this initiative are included as part of the action plan under the proposed new Intergovernmental Agreement on the Coastal Zone. |
REC145-3240 | 32 - Doctrine, standards, and reform | The Committee recommends that proposals for a National Oceans and Coast Act and a statutory Coastal Council be the subject of ongoing consideration once the Intergovernmental Coastal Zone Agreement is determined. |
REC145-3208 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government, through the Ministerial Council for Police and Emergency Management, recognise the extensive Surf Life Saving Australia network and take appropriate steps to integrate this network into emergency services preparedness, planning, and response systems and activities. |
REC145-3238 | 32 - Doctrine, standards, and reform | The Committee recommends that the Australian Government: |
REC145-3197 | 32 - Doctrine, standards, and reform | The Committee recommends that the coastal zone component of the National Climate Change Science Framework and proposed National Climate Change Science strategy be clearly identified by the proposed high level coordination group and involve key coastal stakeholders. |
REC145-3222 | 1 - Land-use and building regs | The Committee recommends that the Australian Government: |
REC145-3215 | 1 - Land-use and building regs | The Committee recommends that the Building Code of Australia, including cyclone building codes, be revised with the objective of increasing resilience to climate change. |
REC145-3214 | 1 - Land-use and building regs | The Committee recommends that the Australian Government consider the benefits of adopting a nationally consistent sea level rise planning benchmark and, if so, whether this be done on a statutory basis or otherwise. The outcomes of this consideration should then be included as part of the action plan for the proposed Intergovernmental Agreement on the Coastal Zone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3391 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government explain its reasons to the Legislative Assembly for not proceeding with the release of Version 2 of the Strategic Bushfire Management Plan in July 2005. |
REC144-3383 | 32 - Doctrine, standards, and reform | The Committee recommends that, if the Bushfire Council is to have an advisory role generally in emergency management, it should be renamed to reflect a general emergency role rather than a role specifically in relation to bushfires. |
REC144-3381 | 32 - Doctrine, standards, and reform | The Committee recommends that the Bushfire Council consultative requirements under the Emergencies Act 2004 be reviewed, with a view to removing the requirement to consult with the Bushfire Council on operational matters, such as staff appointments and matters prescribed by regulation. |
REC144-3394 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government develops a joint strategic bushfire management plan with the NSW Government and the NSW Rural Fire Service in relation to those areas which have the potential to impact on both jurisdictions. |
REC144-3380 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government develop and publish an operational policy document which spells out the command and control structures and procedures should an emergency event arise. |
REC144-3393 | 1 - Land-use and building regs | The Committee recommends that the responsibility for land management issues lie within a single portfolio, specifically the Minister for Territory and Municipal Services. |
REC144-3392 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government finalise Version 2 of the Strategic Bushfire Management Plan as required under the Emergencies Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3585 | 33 - Relief and recovery | That the Professional Assistance Grant is formally extended by WANDRA to include non rural businesses and that it be made available to assist with the clean up of disaster related damage to farms and businesses. (The Committee recognises that the amendments to WANDRA as of March 2007 address this recommendation). |
REC143-3584 | 32 - Doctrine, standards, and reform | That the guidelines of WANDRA be revised to provide for the inclusion of the cost of materials expended in the repair of boundary fences. |
REC143-3583 | 33 - Relief and recovery | That the newly proposed index linked limits for Personal Hardship and Distress Relief Payments as outlined in the paper “National Disaster Relief Arrangements - An Analysis and Recommendations for Personal Hardship Distress Measures” be accepted by government. |
REC143-3578 | 32 - Doctrine, standards, and reform | That Fire and Emergency Services Authority of Western Australia (FESA), in consultation with local governments, develop and make broadly available Western Australian Natural Disaster Relief Arrangements (WANDRA) guidelines with a view to improving pre-disaster awareness of assistance measures and application processes. |
REC143-3588 | 33 - Relief and recovery | That, in line with recommendations contained in the 2004 Report to the Council of Australian Governments, greater flexibility should be introduced to WANDRA to enable damaged infrastructure to be upgraded to a more resilient standard where that is both feasible and cost-effective. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3618 | 32 - Doctrine, standards, and reform | That the Department of Primary Industries should complete a review of the Memorandum of Understanding and ensure the roles of the Department and Rural Lands Protection Boards are more clearly identified outlined for effective delivery of animal health programs. |
REC128-3610 | 32 - Doctrine, standards, and reform | That the Minister for Primary Industries consider amending the Stock Diseases Act 1923 to ban the supply of waste swill to pig owners by food retailing businesses such as bakeries, restaurants and supermarkets. |
REC128-3599 | 32 - Doctrine, standards, and reform | In order to improve the response to animal health emergencies, that the Department of Primary Industries prioritise the finalisation of Memoranda of Understanding with the four jurisdictions bordering New South Wales. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3886 | 32 - Doctrine, standards, and reform | Clarify, strengthen and document roles, responsibilities and accountabilities of DSE and its partner organisations in the prescribed burning program: |
REC124-3887 | 32 - Doctrine, standards, and reform | Give priority to the establishment of risk management processes across all stages of prescribed burning within the Department’s broader risk management strategy: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3874 | 32 - Doctrine, standards, and reform | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan to confirm that planning and response arrangements appropriately consider the protection of public safety, the current security environment and the timely restoration of airport operations, and that it is consistent with state emergency response planning arrangements. |
REC123-3881 | 32 - Doctrine, standards, and reform | Reference to the Aviation Rescue and Fire Fighting service in Part 6 of the Emergency Management Manual Victoria, table of control and support agencies, be extended to include its responsibility for hazardous materials emergencies at the airport. |
REC123-3880 | 32 - Doctrine, standards, and reform | Victoria Police, Melbourne Airport management, airlines and emergency services develop a Memorandum of Understanding for media coordination and public communications at Melbourne Airport that documents the responsibility for media coordination during emergencies to Victoria Police. |
REC123-3879 | 32 - Doctrine, standards, and reform | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan, to consider the use of alternative locations for staging, evacuation, assembly and incident coordination, to increase separation of emergency operations from non emergency activity be adopted. |
REC123-3878 | 32 - Doctrine, standards, and reform | Melbourne Airport management, the emergency services and airlines develop risk based tactical plans that, where safe and appropriate, allow the staged or progressive closure or re-opening of terminal space to support continuity of airport operations during emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3790 | 32 - Doctrine, standards, and reform | The Committee recommends that prescribed burning should only be undertaken by professionally trained personnel. |
REC122-3789 | 32 - Doctrine, standards, and reform | The Committee recommends that the native vegetation planning and approval process for prescribed burning be amended to allow flexibility for burning on optimum days. |
REC122-3788 | 32 - Doctrine, standards, and reform | The Committee recommends that the Native Vegetation Council have a consistent approach to prescribed burning on both public and private lands. |
REC122-3786 | 32 - Doctrine, standards, and reform | The Committee recommends that the Native Vegetation Act be amended to allow for prescribed burning. |
REC122-3777 | 1 - Land-use and building regs | The Committee recommends that native vegetation, excluding road reserves be fenced. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2251 | 11 - Evacuation and shelters | That Victoria Police ensure all police members understand the Victorian legislation in relation to evacuation, and that any decision to recommend evacuation remains with the Incident Controller. |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2261 | 32 - Doctrine, standards, and reform | That the emergency management arrangements be amended to require Police Divisional Emergency Response Coordinators, in consultation with other response agencies, to establish and document procedures and structures at regional level in order to ensure there is: |
REC104-2307 | 33 - Relief and recovery | That the Victorian Government recommend to the Commonwealth Government that it reviews eligibility for those without employment who may or may not be engaged in an emergency response, and are unable to access the appropriate infrastructure to register for financial assistance. |
REC104-2219 | 32 - Doctrine, standards, and reform | That, following the review of Forest Industry Brigades, the Country Fire Authority Act 1958 be amended to ensure that the Forest Industry Brigades, which are acting in an approved manner, have the same powers and rights as other Brigades when attending fires on public land or interstate. |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2313 | 33 - Relief and recovery | That Government review the emergency relief and financial assistance policy, and develop and communicate a predictable, consistent and equitable policy designed to assist the community to recover from emergencies, including natural disasters. |
REC104-2236 | 32 - Doctrine, standards, and reform | That the Statewide Fire Control Priorities: |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2330 | 32 - Doctrine, standards, and reform | That this unified system include recommendations for the appointment of one person or agency to be responsible for overall control of fire suppression activity in country Victoria, including for any legislative reform considered necessary. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2306 | 33 - Relief and recovery | That VicRoads and Municipal Councils review procedures and processes to ensure that the identification and delivery of remedial works on State and Council roads following emergency events are as efficient as possible. |
REC104-2203 | 11 - Evacuation and shelters | That CFA further develops the information supporting the decision to stay or go, to incorporate a better understanding of both the likely consequences of leaving home at inappropriate times, and the conditions and |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2312 | 33 - Relief and recovery | That all agencies engaged in recovery participate in community briefings prior to and during emergency events, to ensure recovery issues are reinforced and communities are informed of the processes established to assist individuals – including matters that are not the responsibility of Victoria, such as Centrelink payments. |
REC104-2229 | 32 - Doctrine, standards, and reform | That DSE and the Department of Primary Industries formalise an agreement by the 2003-2004 fire season documenting the policies, procedures and financial arrangements relating to the availability of Department of Primary Industries staff to be trained and released for fire prevention and suppression activities on public land. |
REC104-2278 | 32 - Doctrine, standards, and reform | That DSE and CFA review the standards and protocols for documentation, including mapping, provided to fire line managers as part of their briefing notes, to ensure these are concise and appropriate. |
REC104-2329 | 32 - Doctrine, standards, and reform | That CFA, DSE, MFESB and Victoria Police jointly develop a unified command and control system that better integrates with the State's emergency management arrangements, and that this be endorsed by the Victoria Emergency Management Council by July 2004. |
REC104-2257 | 32 - Doctrine, standards, and reform | That the Emergency Management Act 1986 be amended to require the development of agreements that describe joint operational arrangements between emergency response agencies. |
REC104-2305 | 33 - Relief and recovery | That DPI actively promote as widely as possible within the community, the agricultural recovery service available during emergencies to ensure that all farmers are aware of the services provided. |
REC104-2199 | 32 - Doctrine, standards, and reform | That evidence of the rekindling or otherwise of spring prescribed burns in forests be assembled and a model constructed and tested to see whether or not some days in spring could be used for prescribed burning in certain circumstances and places, especially in Zone 1. |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2311 | 32 - Doctrine, standards, and reform | That all Departments, statutory authorities, utility providers and Local Governments be made aware of the need to develop contingency plans for recovery activities, and that such plans, and the associated public education and information strategies, are included in the Municipal Emergency Management Plans. |
REC104-2227 | 32 - Doctrine, standards, and reform | That the Municipal Fire Management Plan amendment includes appropriate provisions for the audit of the plans including: |
REC104-2276 | 32 - Doctrine, standards, and reform | That CFA and DSE jointly develop procedures to ensure that a more consistent strategic approach can be maintained at shift and tour of duty changes. |
REC104-2324 | 32 - Doctrine, standards, and reform | That this group reports to the Minister for Police and Emergency Services on proposed legislative amendments to the Emergency Management Act 1986, the Country Fire Authority Act 1958 and any associated legislation by June 2004. |
REC104-2253 | 32 - Doctrine, standards, and reform | That Victoria Police, CFA and DSE review the relationship between fire service regional co-ordination arrangements and Divisional Emergency Response Plans and that any changes be formalised in the emergency management arrangements. |
REC104-2288 | 32 - Doctrine, standards, and reform | That CFA develop protocols to integrate Ultra High Frequency and Citizen Band radios into their communication structures. |
REC104-2198 | 32 - Doctrine, standards, and reform | That an explicit formulation of the interactions between terrain, fuel, ignition pattern, time of day and weather be created to better define those days suited to prescribed burning. |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2310 | 33 - Relief and recovery | That recovery is recognised as commencing at the same time as response and that recovery planning and delivery is an integral part of the operations of the Municipal Emergency Co-ordination Centres. |
REC104-2226 | 32 - Doctrine, standards, and reform | That the new Municipal Fire Management Plan is informed by the policy directions of the subcommittee of the Victoria Emergency Management Council. |
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2316 | 33 - Relief and recovery | That the State Emergency Recovery Committee explore opportunities to establish a 'one-stop shop’ approach wherever practicable following emergencies, including a single telephone number to connect a person to all agencies involved in the recovery process. |
REC104-2252 | 32 - Doctrine, standards, and reform | That existing DSE and CFA regional co-ordination arrangements be reviewed and any changes, such as the continued use of Integrated Multi-Agency Co-ordination Centres, be reflected in the Victorian emergency management arrangements. |
REC104-2285 | 32 - Doctrine, standards, and reform | That, as a matter of urgency and in consultation with stakeholders, CFA and DSE develop and communicate clear guidelines on how and when privately owned firefighting equipment should be integrated into the fire response. |
REC104-2196 | 32 - Doctrine, standards, and reform | That, as a result of this monitoring, weather conditions for the safe conduct of burning in such operations should be defined. |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2309 | 32 - Doctrine, standards, and reform | That the Emergency Management Act 1986 be amended to include a provision that, on the recommendation of the Minister for Police and Emergency Services as Co-ordinator-in-Chief of Emergency Management, or of another Minister, the Premier establish a Ministerial Task Force to oversee recovery in situations of extreme natural disaster or other emergency events. |
REC104-2224 | 32 - Doctrine, standards, and reform | That the Country Fire Authority Act 1958 be amended to: |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2314 | 33 - Relief and recovery | That DHS, in conjunction with Local Government, Government departments and the nongovernment sector, modify recovery planning at all levels to include a case management approach supported by an appropriate information system to be activated at the time of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2166 | 32 - Doctrine, standards, and reform | The Committee recommends that Emergency Management Australia work through the Australasian Fire Authorities Council to ensure that: |
REC098-2187 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth require state and territory governments to have in place comprehensive bush fire management plans as a pre-requisite for accessing funding from the National Heritage Trust and like programs. |
REC098-2135 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments implements to a minimum national standard adequate access to all public lands including wilderness areas of national parks. |
REC098-2159 | 32 - Doctrine, standards, and reform | The Committee recommends that in changing the incident management systems as proposed in recommendation 23 above all bushfire agencies review concerns about difficulties in communicating operational information from the fire front to air operations. |
REC098-2181 | 11 - Evacuation and shelters | The Committee recommends that the Australasian Fire Authorities Council’s suggested evacuation protocol be adopted by all of the Australian States and Territories. |
REC098-2133 | 1 - Land-use and building regs | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve when asset protection zones will be located on private land and when on public land and gain assurances that adequate maintenance of zones will be enforced. |
REC098-2154 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek the adoption by all states and territories of multi-agency protocols and agreements for fire |
REC098-2178 | 1 - Land-use and building regs | The Committee recommends that Standards Australia review the clarity of AS3959–1999: Construction of buildings in Bushfire Prone Areas to ensure that all relevant stakeholders can interpret and apply the Standard in the way it is intended. |
REC098-2152 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth, through the Council of Australian Governments and the Australasian Fire Authorities Council, initiate an overhaul of the incident management systems used |
REC098-2176 | 1 - Land-use and building regs | The Committee recommends that Standards Australia incorporate building maintenance into AS3959–1999: Construction of buildings in Bushfire Prone Areas, perhaps renaming it as AS3959–1999: Construction and maintenance of buildings in Bushfire Prone Areas. |
REC098-2149 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth work with the states and territories through the proposed Council of Australian Governments to review the response to bushfires to ensure that principles of fire prevention and rapid and effective initial attack are adopted and implemented by all rural fire authorities and public land managers |
REC098-2170 | 32 - Doctrine, standards, and reform | The Committee recommends that Emergency Management Australia request the Australasian Fire Authorities Council to: |
REC098-2141 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth through the National Heritage Trust, offer assistance to the states and the Australian Capital Territory to develop specific prescribed burning guides, at least |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3410 | 32 - Doctrine, standards, and reform | The Committee recommends that, following the development of standards of fire cover, related standards be established for: |
REC061-3247 | 32 - Doctrine, standards, and reform | The Committee recommends that the Ministry for Police and Emergency Services seek common national fire standards. |
REC061-3412 | 32 - Doctrine, standards, and reform | The Committee recommends that the Ministry for Police and Emergency Services seek common national fire standards. |
REC061-3244 | 32 - Doctrine, standards, and reform | The Committee recommends that, following the development of standards of fire cover, related standards be established for: |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4161 | 32 - Doctrine, standards, and reform | That separate counter—disaster systems be avoided by retaining counter—bushfire arrangements as part of the State’s total counter— disaster system. [Reference paragraph: 228] |
REC037-4160 | 32 - Doctrine, standards, and reform | The current counter—bushfire concept be retained, with the proviso that it be kept under continuous review to ensure that all relevant future developments and techniques are effectively utilised. (Reference paragraphs: 88 to 90 and 257 to 259] |
REC037-4168 | 32 - Doctrine, standards, and reform | The provisions of the State Disasters Act, 1983, be extended to cover the proposed policy and organisational amendments. (Reference paragraph: 286] |
REC037-4167 | 32 - Doctrine, standards, and reform | The definitions of command, control and co—ordination, as stated in the Australian Counter Disaster Handbook, be standardised throughout Victoria’s counter—disaster system. [Reference paragraphs: 106 to 111] |
REC037-4166 | 32 - Doctrine, standards, and reform | In the future development of Victoria’s counter—disaster capability, effective utilisation and management of resources be regarded as a major objective. |
REC037-4165 | 32 - Doctrine, standards, and reform | • Proposed amendments to the State Disaster Plan be formalised |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3960 | 33 - Relief and recovery | It is recommended that the Forests Commission recognize and provide for the efficient exercise of three major functions, namely those of Commerce, Reclamation and Rehabilitation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3979 | 32 - Doctrine, standards, and reform | That burning off by "occupiers" on any lands be regulated by permit or by regulation. |
REC013_3974 | 1 - Land-use and building regs | To link up fallow paddocks and natural fire breaks by ploughing or burning breaks through private or public property, roads, &c. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3991 | 32 - Doctrine, standards, and reform | The Commission recommends that the provisios of section 185 of the "Mining Act 1905" relating to exits from coal mines be extended to metalliferous mines employing more than 20 men in any one shift. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-4000 | 32 - Doctrine, standards, and reform | That section 22 of the Police Offences Act 1890 be amended, to enable the burning of grass and debris along the railway lines in the summer season to be carried out at an earlier hour than two o'clock in the afternoon, when, in the judgement of the railway inspectors, it is safe and necessary to do so. |
REC004-3995 | 32 - Doctrine, standards, and reform | That the standard double arrester, fitted to the locomotives during the summer months, be subjected to more careful daily inspection before and after each journey during such months, in addition to the present periodical examination by the locomotive foreman and boiler inspector; and that any omission of this duty on the part of the running staff be severely punished. |
REC004-3993 | 32 - Doctrine, standards, and reform | That in any case where there is primá facie evidence of a fire, creating damage to the extent of $100 or upwards in value, having been caused by the escape of particles of lighted matter from a locomotive engine, or by the action of railway employes in burning off grass or other inflammable material along any line of railway, a Special Board of Inquiry shall investigate and report on the subject, such Board to consist of a Police Magistrate as Chairman, with a railway officer and a competent person chosen from outside the State service as members. |