Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4298 | 37 - Funding | Housing and development funding options: That, to empower vulnerable people and communities to avoid significant impacts from flood as well as drive broader investment in adaptation, Government through NSWRA: |
REC324-4308 | 26 - Research | Compound mental helath studies: That, to inform Government policies and programs for mental health and disasters, Government commission a longitudinal study on the effect of consecutive disasters on community mental health. |
REC324-4319 | 26 - Research | Climate and weather research: That, to enable effective mitigation and adaptation measures in response to changing climate risks, Government establish NSW as a world centre of disaster research and technology development. This should include: |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4205 | 26 - Research | We recommend that DELWP in partnership with Parks Victoria, Country Fire Authority, Fire Rescue Victoria and councils as appropriate, collect empirical evidence after bushfire events to assess the effectiveness of different fuel management treatments, including planned burning, mulching, slashing and mineral earth breaks, and build an evidence base to the effectiveness of these treatments. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3273 | 26 - Research | Collate data and research the impact of bushfires upon communities, firefighters and animals (both native and domestic) to identify appropriate medium and long-term welfare and support requirements. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2423 | 37 - Funding | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning as a matter of priority, establish what funding is reasonably required and complete all elements of the Brisbane River Catchment Flood Studies. |
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1261 | 28 - Personal responsibility | That heightened awareness and action is needed by communities when BoM issues flood watches and related warnings. Councils and SES need to facilitate this. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1302 | 28 - Personal responsibility | That the State Emergency Service together with the Local Government Association and Country Fire Service establish a plan for coordinated provision of sandbags to the public, including options for what is provided, where and when, and the process for effective communication of availability to the public. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2369 | 26 - Research | I recommend that the New South Wales Police Force evaluate whether the use of noise-attenuation devices should be mandated when explosive distraction devices are used. |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1194 | 37 - Funding | The Committee recommends the State Fire Commission be fully reimbursed for the costs of the State Emergency Service transfer in years 2014 to 2017. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1405 | 37 - Funding | That the Department of Justice & Regulation broadens Budget Paper 3 response time measures to more comprehensively cover emergency responses to fires, rescues and other emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1522 | 26 - Research | Banana Shire Council investigate means to prioritise the commissioning of a fit-for-purpose flood study for high-risk areas across the Banana Shire to better inform flood risk management, including improved town planning. The outcomes of such a study should be available to the public and inform flood awareness campaigns, flood warnings, and building approvals. |
REC271-1521 | 26 - Research | The Department of Energy and Water Supply and SunWater, undertake the necessary studies to determine whether or not it is feasible to operate Callide Dam as a flood mitigation dam. Such studies should include matters in relation to, but not limited to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1423 | 22 - Role of local Gvt | The State Disaster Coordination Centre Notification Matrix is reviewed to ensure local governments are notified of any event affecting, or likely to affect, their local government area. |
REC268-1430 | 26 - Research | Formal research is commissioned or meta-analysis is undertaken to provide a better understanding of the effectiveness of warnings and other relevant message testing. The outcomes are disseminated to all disaster management entities and learnings used to inform practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1081 | 26 - Research | The State should continue the long-term health study, and: • extend the study to at least 20 years; • appoint an independent board, which includes Latrobe Valley community representatives, to govern the study; and • direct that the independent board publish regular progress reports |
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1058 | 28 - Personal responsibility | That NPWS and the RFS consider developing a land management policy that requires active engagement with property owners adjoining the Park to ensure that hazard reduction and asset protection is encouraged and undertaken before the bush fire season commences |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1577 | 37 - Funding | The Australian Government should develop a formula for allocating mitigation funding to state and territory governments on the basis of where such funding is likely to achieve the greatest net benefits, taking into account the future risks of natural disasters. This should be completed within five years and in consultation with state and territory governments. |
REC256-1560 | 37 - Funding | The Australian Government should: |
REC256-1559 | 37 - Funding | The Australian Government should gradually increase the amount of annual mitigation funding it provides to state and territory governments to $200 million. Initially, this funding should be distributed to state and territory governments in accordance with the allocation under the National Partnership Agreement on Natural Disaster Resilience. |
REC256-1558 | 37 - Funding | Funding to state and territory governments for community recovery should be provided as untied grants, with a transition period pending the development of a framework to assess community recovery costs. During the transition period, the Australian Government should continue to provide funding for community recovery through a reimbursement model. |
REC256-1557 | 37 - Funding | Where asset management plans at the local, state or territory level pre-identify and cost betterment of assets (improving asset resilience to natural disasters), the Australian Government should share 50 per cent of the betterment component of reconstruction costs following damage from a (eligible) natural disaster. |
REC256-1556 | 37 - Funding | The Australian Government should fund natural disaster recovery by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2564 | 37 - Funding | Western Australia Health should collate and centrally monitor financial data including the cost to government of IHPT |
REC252-2563 | 37 - Funding | Western Australia Health should develop and agree with St John Ambulance a new funding model for emergency ambulance services focusing on standards, performance and allocation of risk |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0921 | 26 - Research | That Tasmania Fire Service promotes a structured approach to research across Australia, to provide a shared understanding and the capacity to benchmark and judge performance. |
REC247-0866 | 26 - Research | That fire agencies continue to develop their predictive modelling capability for use in actively managing fires. |
REC247-0932 | 37 - Funding | That the resources available to the Parks and Wildlife Service, to manage bushfire risk following the recent increase in land under its tenure, is reviewed. |
REC247-0849 | 26 - Research | That Tasmania Fire Service supports the relevant authorities to continue developing methodologies to forecast and simulate fire risk. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2592 | 37 - Funding | That duplication of infrastructure be costed and taken into account when considering whether to proceed with the Whole of Government network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2606 | 22 - Role of local Gvt | The Act be amended to require the mandatory appointment of Authorised Officers by each rural council or council that has within its area a Designated Urban Bushfire Risk Area(s) with an option for the CFS Chief Officer to exempt council from this requirement (similar to Section 105B). |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2654 | 26 - Research | That the Department of Health determines the underlying causes for the rapid growth in demand for Queensland Ambulance Service emergency responses and implements strategies to address these causes and reduce the cost per head of population to service this demand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2682 | 37 - Funding | That a budget based on the desired functional accountabilities should be appropriated to the Portfolio Business as part of the Government budget process. |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2681 | 37 - Funding | That the funding model for the Portfolio Business is not based on fee- for-service arrangements or notional contributions from the operational services. |
REC239-2780 | 37 - Funding | That should the Westgate project proceed, that consideration must be given to opportunities to partner the investment with the private and public sectors. The business case should also consider alternative facilities such as Australian Defence Force sites. |
REC239-2779 | 37 - Funding | That a new business case for Westgate project should be prepared by an independent party. |
REC239-2753 | 37 - Funding | That the proposed Chief Executive Officer Portfolio Business be responsible for developing a cost attribution model for portfolio agencies, including the Queensland Police Service, as a priority. |
REC239-2683 | 37 - Funding | That the Office of Portfolio Business follows the same budget processes as other agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0834 | 37 - Funding | That the NSW Rural Fire Service apply for funding from the NSW Treasury for the development of a multi-agency business case for a BRIMS replacement that includes internal management, risk communication, community engagement capability and publishing activities on websites. |
REC237-0833 | 37 - Funding | That the NSW Rural Fire Service and the NSW Treasury explore ways to ensure that unspent hazard reduction funds be carried over to the next financial year in a timely manner and to ensure that hazard reduction funding has a seamless transition from one financial year to the next. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2812 | 37 - Funding | In order to further build on the value for money review work being undertaken by the National Disaster Recovery Taskforce (on behalf of the Australian Government Reconstruction Inspectorate), the Australian National Audit Office (ANAO) recommends that the Taskforce: |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1617 | 37 - Funding | The Territory and Municipal Services Directorate should annually (and on a cumulative basis) track and report on funds allocated for, and spent on, its Bushfire Operations Plan to the Minister for Police and Emergency Services. |
REC228-1616 | 37 - Funding | The Territory and Municipal Services Directorate should enhance internal monitoring of its implementation of bushfire management activities and spending under the Bushfire Operations Plan by routinely reconciling figures in this plan with those in the Directorate’s corporate financial system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0517 | 26 - Research | The Department of Environment and Conservation be supported to conduct further research into the fuel management of coastal heath in the south west of Western Australia exploring alternatives to burning as well as best practice for burning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2877 | 37 - Funding | Explore opportunities to re-phase investments in large scale projects and programs such as the Strategic Radar Enhancement Program, the NexGen Forecast and Warning System Products and the Improving Water Information Program. |
REC207-2893 | 37 - Funding | Explore options to obtain revenue from advertising on the Bureau’s website |
REC207-2892 | 37 - Funding | Apply a consistent cost-recovery model to all services delivered to state/territory fire agencies. |
REC207-2890 | 37 - Funding | Review and rebalance relative investment in long term climate modelling and medium-term seasonal outlook. |
REC207-2889 | 37 - Funding | Review level of investment in research activities to free up budget and reduce pressure on computing capacity |
REC207-2879 | 37 - Funding | Firm up approval processes and funding for any departures from provision of the basic product set |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0256 | 22 - Role of local Gvt | Noting existing legislative and policy arrangements, there is merit in considering options for the future management of Level 3 fires in Local Government areas. |
REC201-0247 | 28 - Personal responsibility | Local residents must take a degree of shared responsibility to prepare their properties by reducing the risk of bushfire around their properties and planning for a bushfire emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0345 | 22 - Role of local Gvt | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-0357 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-1715 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. |
REC200-0342 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. Local Government provide information to residents on any changes to the Australian Standard relating to tethering gas tanks and encourage property owners to take action to comply with the Standard. |
REC200-0375 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. This program should be implemented and managed under the Bush Fires Act 1954 in a manner similar to the fire break inspection program. |
REC200-1697 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-1695 | 22 - Role of local Gvt | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-0367 | 22 - Role of local Gvt | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-1725 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-1683 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. |
REC200-0354 | 22 - Role of local Gvt | Local governments consider increasing the number of green waste collections carried out each year to encourage a more proactive approach to property (and vegetation) maintenance by residents. |
REC200-0385 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-0353 | 22 - Role of local Gvt | The State Government give its full support to the Western Australian Local Government Association’s Send to Solve initiative. |
REC200-1729 | 22 - Role of local Gvt | The Fire and Emergency Services Authority and local governments ensure that Community Emergency Service Managers are physically based in local government. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0468 | 22 - Role of local Gvt | municipal councils undertake a risk assessment of caravan parks and decide if any should be included in the list of facilities where vulnerable people may be located. |
REC199-0416 | 26 - Research | the state establish appropriate arrangements to ensure the capacity to maintain technical expertise for flood intelligence is initiated, including appropriate agreements with commercial experts. |
REC199-0486 | 22 - Role of local Gvt | the state, following the completion of the Municipal Association of Victoria Improving Emergency Management in Local Government program, work with municipalities to revise the role and responsibilities of local government in emergency management. The issue of capability and capacity of each local government should be addressed in all related emergency management arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0221 | 37 - Funding | Funding be sought to enable the State Fire Management Council to take a greater coordination role for bushfire risk management and mitigation. |
REC193-0226 | 22 - Role of local Gvt | Local government councils should: strongly encourage owners to make improvements to construction or increase buffers in order to meet minimum safety standards implement programs to audit impacted properties and issue abatement notices where necessary monitor and maintain their reserves to ensure that adequate buffers to neighbouring buildings exist. |
REC193-0225 | 22 - Role of local Gvt | Local government councils should move promptly to: adopt the Tasmania Fire Service Guidelines for Development in Bushfire Prone Areas of Tasmania give effect to the Department of Primary Industries, Parks, Water and Environment Neighbouring Developments and Fire Management Policy. |
REC193-0222 | 22 - Role of local Gvt | The Local Government Association of Tasmania advocate, coordinate and support local councils’ input of bushfire risk assets data into the Bushfire Risk Assessment Model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC180-2969 | 22 - Role of local Gvt | Councils should strengthen governance arrangements for business continuity by: |
REC180-2973 | 22 - Role of local Gvt | Local Government Victoria should, further to its work on strengthening the oversight role of audit committees, assist councils to develop good practice approaches to implementing, overseeing and continuously improving business continuity management. |
REC180-2972 | 22 - Role of local Gvt | Councils should strengthen their continuous improvement frameworks by: |
REC180-2971 | 22 - Role of local Gvt | Councils should improve the structure, format and content of their business continuity plans to provide greater clarity on roles and responsibilities for emergencies, more specificity on continuity and recovery responses, and better integration with other council disaster recovery and emergency plans. |
REC180-2970 | 22 - Role of local Gvt | Councils should improve assessments of business continuity risks by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
REC177-3364 | 37 - Funding | The funding arrangements that support the National Plan should be reviewed to ensure that the costs associated with both preparedness and response capability are equitably shared between the shipping and offshore petroleum industries. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0054 | 22 - Role of local Gvt | SEMC and EM WA should: work with local government to ensure up-to-date, comprehensive local arrangements are in place |
REC170-0055 | 22 - Role of local Gvt | SEMC and EM WA should: monitor and take action to ensure local plans are in place and cover areas where the hazard could occur |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1775 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to identify the effects of continuous cropping, minimum tillage, direct drilling seeding practices and of the retention of cropping stubble, in respect of bushfire risk and prevention. |
REC153-1806 | 40 - Equipment and consumables | That the Minister for Emergency Services and the Minister for Local Government cause local council plant and equipment that is suitable for use in bushfire fighting be fitted with radios connected to the Government Radio Network. |
REC153-1780 | 22 - Role of local Gvt | That the Minister for Local Government cause rural councils to appoint an Officer whose duties consist entirely of bushfire prevention, such Officer being required to become a trained, operative member of the South Australian Country Fire Service during the currency of his or her appointment. |
REC153-1776 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to establish means by which risk of bushfires, as created by continuous cropping, minimum tillage, direct drilling seeding practices and the retention of cropping stubble across the landscape, can be minimised. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3189 | 37 - Funding | The ANAO recommends that, to ensure that grant conditions are satisfied, EMA enhance procedures to monitor the progress of projects and follow up those behind schedule or not fulfilling funding agreement requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3554 | 37 - Funding | DHHS fund the equivalent of 2 FTE Consultant positions for retrieval duties (1.5 FTE existing, 0.5 FTE new) |
REC140-3553 | 37 - Funding | RHH Neonatal Emergency Transport Service receive DHHS funding for a Senior Registrar to assume the responsibilities of retrieval staffing, quality assurance, data collection and reporting demands. |
REC140-3552 | 37 - Funding | Department of Health and Human Services (DHHS) to fund 3 Full-Time Equivalent (FTE) Senior Registrar positions at the Royal Hobart Hospital (RHH) for the Tasmanian Medical Retrieval Service (TMRS). One registrar in the Anaesthesia Department, one in the Intensive Care Unit and one in Emergency Department is proposed. |
REC140-3568 | 37 - Funding | The State Medical Retrieval Cost Centre (TMRS and NETS) be formed and be supported by the appropriate administrative and resource accountant expertise. This cost centre should be placed with those responsible for its management. |
REC140-3567 | 37 - Funding | A uniform retrieval charge to the region of referral should be considered. This should be independent of the mode of transport used. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3593 | 26 - Research | Analysing information from the joint CFA/DSE Post 2006 Wildfire Community Survey about public perceptions of information provision during January bushfires. Note implications for the VBIL and other information provision methods |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-1967 | 40 - Equipment and consumables | That the Emergency Services Agency give priority to ensuring it has guaranteed access to an adequate number and type of bulldozers, as well as experienced operators, during the fire season, for immediate deployment as required |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
Rec-ID | Code | Recommendation |
---|---|---|
REC118-3642 | 26 - Research | Establish a Regional Centre of Excellence for Tsunamis to focus Australian and international science/research and collaboration on the challenge of understanding tsunamis and mitigating their consequences. |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3640 | 37 - Funding | The ANAO recommends that the Attorney-General’s Department better monitor and account for the expenditure of individual exercise costs under the National Capability Development Exercise Programme, through: |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3934 | 37 - Funding | That DPI prepares guidelines, both internally and externally with Treasury, about funding arrangements for an outbreak. |