Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4298 | 37 - Funding | Housing and development funding options: That, to empower vulnerable people and communities to avoid significant impacts from flood as well as drive broader investment in adaptation, Government through NSWRA: |
Rec-ID | Code | Recommendation | |
---|---|---|---|
REC323-4272 | 37 - Funding | That the NSW Government ensure that flood affected individuals can continue to access financial assistance for as long as there is demonstrated need. |
|
REC323-4279 | 37 - Funding |
|
|
REC323-4280 | 37 - Funding | That the NSW Government work with local governments to identify alternative routes to vulnerable roads, and that the NSW and Australian Governments fund the construction of these important routes to improve evacuation and access options in times of disaster. |
|
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
|
REC323-4261 | 37 - Funding | That the NSW Government advocate through the National Cabinet to widen eligibility under the Disaster Funding Recovery Arrangements to allow local councils to build back better. |
|
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
|
REC323-4281 | 37 - Funding | That the NSW Government allocate funding to the improvement of the Pitt Town Evacuation Route and other key possible evacuation routes in Sydney's northwest. |
|
REC323-4270 | 37 - Funding | That the NSW Government consider entering into a service agreement with an organisation that has the resources and capacity to manage donations and activate quickly during natural disasters. |
|
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4252 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services regularly review and evaluate the effectiveness of the Queensland Bushfire Plan with land managers and stakeholders, including disaster management groups. A review should occur in line with any material change to the Queensland State Disaster Management Plan, the Disaster Management Act 2003, the Prevention Preparedness Response and Recovery Guideline, or after major bushfire events, to ensure appropriate alignment and currency. |
REC322-4218 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends this report be returned to the IGEM to monitor, evaluate and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4219 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends should a Queensland Government Action Plan be considered, clarity about the intent of the recommendations be sought from the Inspector-General Emergency Management to assist in informing this process. |
REC322-4232 | 11 - Evacuation and shelters | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to plan for the evacuation of K’gari due to bushfire. Once developed, the plan should be exercised and regularly reviewed. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
REC322-4220 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science monitor the progress of relevant improvement activities resulting from the K’gari (Fraser Island) Bushfire Review, through their respective lessons management programs. |
REC322-4240 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the next review of the Queensland State Disaster Management Plan examines and provides guidance in respect to the application of Queensland’s disaster management arrangements to support hazard specific events such as bushfire. |
REC322-4246 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the Interagency Protocol for Fire Management be reviewed by all relevant entities, including representatives of the Butchulla people, and be updated as a matter of priority. Entities responsible for the protocol should implement a process for regular review and evaluation of its effectiveness. This review process should be conducted after a major bushfire event, or to reflect any material change to applicable legislation and policy. It should also consider pre-arranged approvals and a range of agreed fiscal protocols between the agencies. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3809 | 37 - Funding | That Government work with other Australian governments to provide long-term funding certainty to AFAC, including the National Resource Sharing Centre (NRSC) and the National Aerial Firefighting Centre (NAFC). |
REC315-3867 | 11 - Evacuation and shelters | That, in order to ensure evacuation centres are fit-for-purpose, Resilience NSW work with Local Emergency Management Committees (LEMCs) to: a) update the guidelines for LEMCs identifying evacuation centres to require a risk assessment of potential locations, which should include identifying alternate sources of power for use by evacuation centres and recording these appropriately |
REC315-3858 | 25 - Inquiry, audit, lessons management and after action review | That, in order to improve cross-agency communication and coordination during bush fires, the NSW RFS review Fire Control Centres (FCCs) in areas that were heavily affected by fire. The results should be combined with the Emergency Operations Centre (EOC) Facilities Review to identify areas that would benefit from a purpose-built FCC, enabling co-location with the EOC. |
REC315-3866 | 11 - Evacuation and shelters | That, in order to ensure evacuation arrangements can be scaled up when needed, Resilience NSW: |
REC315-3812 | 25 - Inquiry, audit, lessons management and after action review | That Government commit to: |
REC315-3814 | 11 - Evacuation and shelters | That the NSW RFS identifies remote bush fire prone areas that do not already have an indoor Neighbourhood Safer Place (NSP) and upgrades the relevant NSW RFS Stations to meet NSP guidelines. These stations would require adequate Asset Protection Zones and active/passive protection systems to provide short-term protection. |
REC315-3798 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure recommendations accepted by the Government are implemented in a timely and transparent manner, Government establish a central accountability mechanism to track implementation of recommendations from bush fire-related reviews and inquiries and consider expanding this to other policy areas. |
REC315-3872 | 11 - Evacuation and shelters | That, in order to improve support for people evacuating with animals, the Department of Primary Industries: |
REC315-3873 | 25 - Inquiry, audit, lessons management and after action review | That Resilience NSW review existing functional area arrangements to ensure they are closely aligned to agencies responsible for direct service delivery. |
REC315-3871 | 11 - Evacuation and shelters | That, in order to ensure equitable access to evacuation centres and associated support services for people in border communities, Resilience NSW ensure cross-border access arrangements are reflected in evacuation centre management guidelines. |
REC315-3860 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure the guiding principles and approval processes are contemporary, streamlined and more flexible, the NSW and Commonwealth Governments review the Defence Assistance to the Civil Community (DACC) arrangements. This review should include the circumstances in which the State can request Commonwealth assistance, and the level of information provided by the ADF to the State on available resources and capabilities. |
REC315-3870 | 11 - Evacuation and shelters | That, in order to ensure the safety and wellbeing of vulnerable people during an evacuation, Resilience NSW: |
REC315-3859 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure State Emergency Operations Centre (SEOC) interoperability during all natural disasters, Resilience NSW review the current SEOC arrangements and location including responsibilities for ongoing resourcing and maintenance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2423 | 37 - Funding | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning as a matter of priority, establish what funding is reasonably required and complete all elements of the Brisbane River Catchment Flood Studies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2370 | 25 - Inquiry, audit, lessons management and after action review | I recommend that the New South Wales Police Force undertake a formal assessment of alternatives to the TOU’s current soft-point ammunition to determine whether a more appropriate form of ammunition is reasonably available. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1201 | 25 - Inquiry, audit, lessons management and after action review | Preventing Flood Related Fatalities: The NSW Government consider the recommendations from the Preventing Flood Related Fatalities Report when it is released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1396 | 25 - Inquiry, audit, lessons management and after action review | That the Minister for Police and Emergency Services review the communications technologies used by the NSW Rural Fire Service, Fire and Rescue NSW, the NSW National Parks and Wildlife Service and Forestry NSW during fire fighting operations, to ensure that systems are standardised and effective. Within this context, the potential value of satellite phone technology should be investigated. |
REC280-1388 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service: |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1415 | 25 - Inquiry, audit, lessons management and after action review | An audit of all local government areas vulnerable to storm tide events is completed and opportunities identified to resolve gaps in evacuation zone planning to ensure consistency with the Queensland Evacuation Guidelines for Disaster Management Groups and neighbouring local government areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1533 | 14 - Incident Mgt Teams | State Disaster Coordination Centre considers requesting a representative from critical infrastructure owners be present as a liaison officer in the State Disaster Coordination Centre during activations for events that may impact on their assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1422 | 25 - Inquiry, audit, lessons management and after action review | The Queensland State Disaster Management Plan is reviewed to: |
REC268-1424 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Emergency Alert Guidelines is reviewed to reflect current practice and incorporate evidence-based improvements informed by lessons learned and research. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1158 | 28 - Personal responsibility | Farm Management Deposits |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1492 | 37 - Funding | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
REC261-1508 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service review its procedures, systems and infrastructure for notifying community members of bush fires, both when a fire has broken out and as it proceeds, to ensure the provision of timely and adequate information. |
REC261-1505 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1066 | 14 - Incident Mgt Teams | That during periods of ‘severe’ or worse fire conditions, that the National Parks and Wildlife Service consider adopting a posture of pre-emptive planning and deployment of incident management teams in national parks similar to the manner in which the Rural Fire Service does. |
REC260-1058 | 28 - Personal responsibility | That NPWS and the RFS consider developing a land management policy that requires active engagement with property owners adjoining the Park to ensure that hazard reduction and asset protection is encouraged and undertaken before the bush fire season commences |
REC260-1053 | 14 - Incident Mgt Teams | That in Class 3 fire-fighting operations, the Rural Fire Service consider including a fire behaviour analyst in the incident management team if feasible. |
REC260-1052 | 14 - Incident Mgt Teams | That the Rural Fire Service consider amending its fire prediction reports to include a checklist of significant factors that have not been able to be considered in the prediction model and a warning to be alert for them and seek intelligence on them from fire ground managers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1033 | 37 - Funding | When a local Rural Fire Brigade requests an equipment and maintenance levy from a local government authority, that authority will either supply the brigade’s equipment and maintenance costs or raise the requested levy. The amount to be collected is to be agreed between the local Brigade and the local government authority. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-1032 | 37 - Funding | That the current Urban Fire Levy be changed to the Queensland Fire Levy. |
REC241-0999 | 28 - Personal responsibility | That on all land where fuel load creates a fire risk, the owner shall be responsible for the construction and maintenance of effective firebreaks. Failure to provide effective and accessible firebreaks will result in the cost of firebreak construction to control a wildfire on this land being debited to the land owner |
REC241-1035 | 37 - Funding | That the State Government contribution towards the purchase of operational vehicles is to be retained at 80 percent but that the District Inspector can recommend full Government subsidy of vehicles for Brigades experiencing financial hardship. |
REC241-1034 | 37 - Funding | That the State Government contribution towards the construction of Brigade sheds be changed from $10,000 to a maximum of 25 percent, subject to the approval of the Deputy Chief Officer, Rural Fire Service Queensland. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2727 | 25 - Inquiry, audit, lessons management and after action review | That as part of its efficiency review, the Queensland Fire and Rescue Service instigate an independent review of commercial operations in terms of statutory obligations and current ‘full cost pricing’ methodology to ensure: |
REC239-2681 | 37 - Funding | That the funding model for the Portfolio Business is not based on fee- for-service arrangements or notional contributions from the operational services. |
REC239-2777 | 25 - Inquiry, audit, lessons management and after action review | That the review of this Queensland Fire and Rescue Services business unit be done in conjunction with the efficiency review proposed for the Queensland Police Service. |
REC239-2780 | 37 - Funding | That should the Westgate project proceed, that consideration must be given to opportunities to partner the investment with the private and public sectors. The business case should also consider alternative facilities such as Australian Defence Force sites. |
REC239-2725 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service community safety operations be joined in the efficiency review of the Queensland Police Service focussing on both the community safety outcomes achieved and the extent to which they support the Government’s economic priorities. |
REC239-2776 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review of the Queensland Police Service examine whether: |
REC239-2779 | 37 - Funding | That a new business case for Westgate project should be prepared by an independent party. |
REC239-2724 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service undertake a review of all standing orders, incident directives and guidelines regarding response protocols with a view to reducing risk to staff and other road users associated with urgent duty driving. |
REC239-2764 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review consider whether special service functions are core business, whether this practice is sustainable, and other options such as the use of casual employees. |
REC239-2753 | 37 - Funding | That the proposed Chief Executive Officer Portfolio Business be responsible for developing a cost attribution model for portfolio agencies, including the Queensland Police Service, as a priority. |
REC239-2763 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review includes a focus on the rank structure of both the Queensland Police Service and the proposed Fire and Emergency Services. |
REC239-2683 | 37 - Funding | That the Office of Portfolio Business follows the same budget processes as other agencies. |
REC239-2758 | 25 - Inquiry, audit, lessons management and after action review | That the Chief Executive Officer Portfolio Business leads an efficiency review of portfolio agencies beginning with the Queensland Police Service. |
REC239-2682 | 37 - Funding | That a budget based on the desired functional accountabilities should be appropriated to the Portfolio Business as part of the Government budget process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0834 | 37 - Funding | That the NSW Rural Fire Service apply for funding from the NSW Treasury for the development of a multi-agency business case for a BRIMS replacement that includes internal management, risk communication, community engagement capability and publishing activities on websites. |
REC237-0833 | 37 - Funding | That the NSW Rural Fire Service and the NSW Treasury explore ways to ensure that unspent hazard reduction funds be carried over to the next financial year in a timely manner and to ensure that hazard reduction funding has a seamless transition from one financial year to the next. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0724 | 28 - Personal responsibility | Councils should consider making available to business owners locality specific information that would assist them to develop evacuation plans for commercial premises, for example, any evacuation sub-plan created under Emergency Management Queensland’s disaster evacuation guidelines. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0679 | 28 - Personal responsibility | If the Queensland Development Code is amended to include provisions requiring homeowners to install sewage reflux valves, the Queensland Government should develop and make available to homeowners appropriate guidance material to assist them in meeting their responsibilities to maintain reflux valves. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0723 | 28 - Personal responsibility | Councils should support and encourage business owners to develop private flood evacuation plans by providing the following to business owners in areas known to be affected by flood: • information about the benefits of evacuation plans • contact details of relevant council and emergency service personnel for inclusion in evacuation plans. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0732 | 37 - Funding | Emergency Management Queensland should develop and implement a new formula for the distribution of its recurrent SES subsidy, which takes into account relevant factors including the size of a local SES contingent and the population, area and natural hazard risk profile of the local government area concerned. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0526 | 25 - Inquiry, audit, lessons management and after action review | That OEH’s testing procedures for determining the impact of pollution incidents incorporate additional requirements for the checking and verification of results before those results are released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0274 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services undertake a thorough review, including consultation with rural fire brigades, regarding the proposed formula for distribution of funding. |
REC191-0273 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services implement system of fire levies for landholders situated in urban, iZone and village brigade areas. |
REC191-0266 | 37 - Funding | that QFRS cover the cost of annual vehicle inspection certificates for rural fire brigade registered vehicles. |
REC191-0275 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services ensure that the formula for distribution of funding as recommended above allows rural fire brigades to control any donation or sponsorship funding raised by individual brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0095 | 11 - Evacuation and shelters | Planning and consultation be undertaken by EMQ with all levels of the Disaster Management system to ensure that necessary risk-based disaster evacuation plans are prepared at Local, District and State levels, supported by necessary community education and preparedness programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3617 | 37 - Funding | That the Department of Primary Industries should provide specific information on levies to contributing producers through a separate document, rather than rely on standard audit documents and annual reporting requirements. |
REC128-3616 | 37 - Funding | That the Department of Primary Industries continue to pursue improvements to consultation with industry and accountability mechanisms to further build trust between industry and government, thereby enhancing the effectiveness of the OJD Program. |
REC128-3614 | 37 - Funding | The Committee encourages the Department and the Rural Land Protection Boards to discuss the need for funding of poultry surveillance activities in the context of reviewing the Memorandum of Understanding between the two parties. |
REC128-3598 | 25 - Inquiry, audit, lessons management and after action review | That the Department of Primary Industries incorporates reviews of plans and operating procedures as a result of emergency incidents and exercises and ensures that there is adequate commitment from all participants in the review process. |
REC128-3604 | 37 - Funding | That the Department of Primary Industries restore the level of discretionary testing funds provided to District Veterinarians to previous levels and maintain these in the future in real terms. |
REC128-3603 | 37 - Funding | That the Department of Primary Industries consider applying discretion to the use of user charging policies for testing in times when farm incomes are affected by external circumstances such as widespread drought. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3649 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3939 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the State Disaster Management Group and the Department of Emergency Services review the current disaster district boundary framework and its relevance to the regional boundaries established by other public sector lead entities to ensure that resources within the Disaster Management System are economically, efficiently and effectively allocated across Queensland. |