Rec-ID | Code | Recommendation |
---|---|---|
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4304 | 1 - Land-use and building regs | Landholders can access information on previous disasters: That, to ensure there is a single source of ground truth to prepare for and respond to emergencies, and to provide people with a better understanding of their individual property and community risk exposure, an online visualisation tool be developed to display, for all land parcels (land titles) in NSW, the extent of known disasters that have affected each piece of land in NSW in the past. This information should be made available through the Planning Portal and, particularly in light of climate change, the data involved should be revised and updated at least every two years and after each major natural disaster. |
REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4298 | 37 - Funding | Housing and development funding options: That, to empower vulnerable people and communities to avoid significant impacts from flood as well as drive broader investment in adaptation, Government through NSWRA: |
REC324-4306 | 6 - Insurance and legal liability | NSW Reconstruction Authority: That, to provide rapid and effective recovery from floods (and other disasters) and to provide maximum mitigation of the impacts of future floods (and other disasters), Government establish a permanent state-wide agency, the NSW Reconstruction Authority (NSWRA) dedicated to disaster recovery, reconstruction and preparedness. The NSWRA should: |
REC324-4299 | 1 - Land-use and building regs | Relocating communities most at risk with good homes and amenities: That, to empower vulnerable people and communities to relocate, Government through the NSWRA: |
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
REC324-4300 | 1 - Land-use and building regs | Simplify the planning system disaster provisions: That, to simplify and improve the state planning processes especially when anticipating and recovering from a disaster, Government: |
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4296 | 1 - Land-use and building regs | Caravan parks and manufactured home estates: That, to ensure that permanent residents of caravan parks and mobile housing estates are protected from flood, Government: • prohibit permanent residency in caravan parks and mobile housing estates situated below the risk-based flood planning level. Caravan parks for holiday makers could still be on the floodplain with the provision that, if a flood is imminent, they need to be evacuated • address the issues raised in the 2015 Discussion Paper (Improving the regulation of manufactured homes, caravan parks, manufactured home estates and camping grounds). |
Rec-ID | Code | Recommendation | |
---|---|---|---|
REC323-4272 | 37 - Funding | That the NSW Government ensure that flood affected individuals can continue to access financial assistance for as long as there is demonstrated need. |
|
REC323-4266 | 1 - Land-use and building regs | That the NSW Government review the provision of temporary and long term housing options provided to those affected by the February-March 2022 floods, with a view to: • ensuring a range of options are identified and embedded within emergency and recovery plans, so that solutions can be implemented as soon as possible after a natural disaster • ensuring that housing options meet individual and community needs • removing planning impediments that prevent those from accessing more safe and secure housing in times of crisis. |
|
REC323-4273 | 33 - Relief and recovery | That the NSW Government overhaul the way in which it conducts its grants process as it frustrated applicants and further traumatised them by repeatedly re-interviewing them and making them prove that they were flooded. |
|
REC323-4267 | 1 - Land-use and building regs | That the NSW Government consider investing in supporting relocations, land swaps and providing fair and adequate compensation for landowners who wish to relocate from severely flood-impacted areas. |
|
REC323-4257 | 1 - Land-use and building regs | That the NSW Government work with local government, industry and sustainable planning experts, including the Government Architect, on policy initiatives in the New South Wales planning system that will help deliver more resilient and sustainable homes, buildings and places. |
|
REC323-4281 | 37 - Funding | That the NSW Government allocate funding to the improvement of the Pitt Town Evacuation Route and other key possible evacuation routes in Sydney's northwest. |
|
REC323-4277 | 33 - Relief and recovery | That the NSW Government develop a more proactive, rapid response to manage animal welfare following natural disasters which includes improved collaboration and communication with local veterinarians and animal welfare organisations. |
|
REC323-4269 | 33 - Relief and recovery | That the NSW Government address the mental health needs of local communities following the February-March 2022 floods by: • embedding within state emergency and recovery plans a strategy that provides surge capacity for mental health and social workers by: • prioritising funding for community groups that are currently providing social and mental health support to their local communities • ensuring all flood-impacted communities receive the mental health support they need to fully recover. |
|
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
|
REC323-4289 | 33 - Relief and recovery | That the NSW Government ensure that all emergency and recovery plans, including state plans, local emergency management plans and functional area plans, are reviewed and updated regularly and provide clarity on the role of non-government partners. |
|
REC323-4279 | 37 - Funding |
|
|
REC323-4270 | 37 - Funding | That the NSW Government consider entering into a service agreement with an organisation that has the resources and capacity to manage donations and activate quickly during natural disasters. |
|
REC323-4261 | 37 - Funding | That the NSW Government advocate through the National Cabinet to widen eligibility under the Disaster Funding Recovery Arrangements to allow local councils to build back better. |
|
REC323-4280 | 37 - Funding | That the NSW Government work with local governments to identify alternative routes to vulnerable roads, and that the NSW and Australian Governments fund the construction of these important routes to improve evacuation and access options in times of disaster. |
|
REC323-4271 | 33 - Relief and recovery | That Service NSW establish teams of assessors that can be on the ground to assess and approve grant applications. |
|
REC323-4262 | 33 - Relief and recovery | That the NSW Government provide an increased level of targeted support to flood affected communities contending with widespread mould. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2508 | 25 - Inquiry, audit, lessons management and after action review | Regularly reviewing these plans to ensure that they reflect the current operating environment. |
REC313-2516 | 33 - Relief and recovery | Documenting disaster recovery risks in agency risk registers, along with controls and treatment plans. |
REC313-2513 | 33 - Relief and recovery | Assessing the availability and skillsets of the resources needed to respond to a major disaster recovery event. |
REC313-2509 | 33 - Relief and recovery | Developing detailed recovery procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2488 | 33 - Relief and recovery | The basic capacity needs of each functional recovery group and how this can be scaled up should be identified. Plans for functional recovery groups should reflect this in clear statements for every level of the system, for all relevant entities about their required function, role and responsibilities during recovery. |
REC310-2487 | 39 - Disaster Risk Management | The state’s arrangements for disaster management, including recovery, are articulated in the Disaster Management Act (2003), the Queensland Reconstruction Authority Act (2011), the State Disaster Management Plan and the Queensland Recovery Plan. To enable state-level arrangements to better support community-led recovery and to improve Queensland’s recovery governance |
REC310-2485 | 33 - Relief and recovery | Recovery plans at all levels should include transition arrangements. They should be implemented during recovery. The arrangements should: |
REC310-2484 | 33 - Relief and recovery | There remains a need to maximise the effect of all offers of assistance to recovering communities. This recommendation presents an opportunity to resolve any outstanding aspects of Recommendation 4 and Actions in Response from the Cyclone Debbie Review Action Plan: |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2423 | 37 - Funding | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning as a matter of priority, establish what funding is reasonably required and complete all elements of the Brisbane River Catchment Flood Studies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1272 | 1 - Land-use and building regs | That, to provide greater clarity for building development, design and approval within tolerable risk levels, the Tasmanian Planning Scheme, including a relevant Riverine Flood Hazard Code, is finalised and approved as soon as practicable. |
REC297-1271 | 1 - Land-use and building regs | That the organisations responsible for construction, maintenance and ownership of bridges review their design guidelines and, if necessary, update them to specifically include consideration of debris and flood impacts on bridge design. A review of existing bridges by the responsible organisations could also be undertaken to highlight any potential issues. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2077 | 6 - Insurance and legal liability | Improve working relationship with the insurance industry to access impact information. |
REC286-1455 | 39 - Disaster Risk Management | Assess options for managed coastal retreat. |
REC286-2025 | 41 - Emergency Management exercises | Exercise heatwave arrangements with a focus on the public administration sector and management of vulnerable people |
REC286-2040 | 1 - Land-use and building regs | Further development of Landslide Hazard Banding of the State (MRT). |
REC286-2089 | 39 - Disaster Risk Management | Identify and analyse statewide storm hazard risk. |
REC286-1436 | 4 - Fire season preparation | Continue the development and implementation of community level Bushfire Mitigation Plans. |
REC286-1468 | 39 - Disaster Risk Management | Identify and anlalyse the location of critical infrastructure within defined flood areas. |
REC286-2050 | 1 - Land-use and building regs | Ensure landuse planning and building systems, including appeal mechanisms, are transparent, equitable and integrated at the municipal, State and national levels. |
REC286-1447 | 39 - Disaster Risk Management | Assess vulnerability of ecosystems and species to coastal inundation. |
REC286-1479 | 6 - Insurance and legal liability | Ensure appropriate levels of insurance of public assets from flood risks. |
REC286-2070 | 25 - Inquiry, audit, lessons management and after action review | Test the Biosecurity Act 2015. |
REC286-1453 | 1 - Land-use and building regs | Review building controls to ensure they are adaptive to changing coastal inundation risks. |
REC286-2023 | 1 - Land-use and building regs | Locate and design new public infrastructure so that it can continue to operate during flood events. |
REC286-2087 | 41 - Emergency Management exercises | Develop and exercise Severe Storm Emergency Management Plan. |
REC286-1435 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning and Building System reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-1464 | 41 - Emergency Management exercises | Exercise time-critical decision making processes within the context of an earthquake scenario. |
REC286-2039 | 41 - Emergency Management exercises | Nuance the exercises for flood / dam-break / debris flow to incorporate consideration. |
REC286-2049 | 39 - Disaster Risk Management | Pro-actively manage landslide areas. |
REC286-2095 | 37 - Funding | Investigate the costs and benefits of delivering a public education and awareness program. |
REC286-1445 | 41 - Emergency Management exercises | Develop, implement, review and exercise inter-agency community evacuation and recovery plans across the State. |
REC286-1478 | 39 - Disaster Risk Management | Review environmental risks associated with hazardous uses within flood prone areas. |
REC286-2066 | 39 - Disaster Risk Management | Advocate for an National Notifiable Diseases Database. |
REC286-1452 | 39 - Disaster Risk Management | Improve understanding of the allocation of ownership across government, business and individuals. |
REC286-2020 | 6 - Insurance and legal liability | Improve insurance affordability. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1463 | 39 - Disaster Risk Management | Develop enablers and capacity for Tasmanian earthquake risk owners. |
REC286-2038 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-2047 | 6 - Insurance and legal liability | Raise public awareness of the limitations of general insurance relating to landslide. |
REC286-2093 | 37 - Funding | Investigate the costs and benefits in enhancing the current Tsunami warning arrangements with signage and audible warning systems at key exposed locations (e.g. Port Arthur and Kingston Beach). |
REC286-1442 | 25 - Inquiry, audit, lessons management and after action review | Review legislation relating to Fuel Stove only areas, Fire Permit System and Total Fire Bans to ensure appropriate incentives to modify individuals’ behaviour. |
REC286-1474 | 1 - Land-use and building regs | Raised access routes. |
REC286-2061 | 41 - Emergency Management exercises | Review and exercise the Tasmanian Mass Vaccination Plan. |
REC286-1451 | 1 - Land-use and building regs | Include consideration of coastal inundation in land use planning for new developments and uses. |
REC286-2017 | 39 - Disaster Risk Management | Improve maintenance of flood mitigation infrastructure. |
REC286-2082 | 41 - Emergency Management exercises | Undertake inter-agency severe storm exercises. |
REC286-1461 | 39 - Disaster Risk Management | Review all hazards response and recovery plans to ensure they address likely earthquake consequences. |
REC286-2037 | 1 - Land-use and building regs | Make property level information on landslide hazards publicly available |
REC286-2046 | 1 - Land-use and building regs | Incentivising safer sites (charge people less rates and discounts for defensive actions by land managers). |
REC286-2092 | 37 - Funding | Ensure sufficient investment in controls across the PPRR spectrum with a focus on Prevention and Mitigation. |
REC286-1441 | 5 - Hazard reduction burns | Continue the Fuel Reduction Program. |
REC286-1471 | 1 - Land-use and building regs | Promote the use of Water Sensitive Urban Design in stormwater systems. |
REC286-2056 | 39 - Disaster Risk Management | Review Ambulance Tasmania surge capacity. |
REC286-1450 | 39 - Disaster Risk Management | Improve the understanding of the vulnerability of critical infrastructure. |
REC286-2016 | 6 - Insurance and legal liability | Review legal liability of participants in prevention and mitigation preparedness, response and recovery activities. |
REC286-2081 | 39 - Disaster Risk Management | Engage with industry bodies to explore opportunities to better understand and manage risks. |
REC286-1460 | 25 - Inquiry, audit, lessons management and after action review | Review seismic monitoring network alert systems to ensure emergency managers are on the contact lists. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2044 | 1 - Land-use and building regs | Develop linkages between landslide risk assessors and building engineers/structural works. |
REC286-2091 | 37 - Funding | Investigate the costs and benefits in enhancing the current Tsunami detection buoy network. |
REC286-1438 | 25 - Inquiry, audit, lessons management and after action review | Consider outcomes of national review of warnings and review resilience of warning systems’ infrastructure. |
REC286-1469 | 39 - Disaster Risk Management | Actively manage riparian vegetation to manage flood dynamics. |
REC286-2051 | 1 - Land-use and building regs | Establish arrangements to enable the buy-back of specified landslip prone land. |
REC286-1448 | 39 - Disaster Risk Management | Utilise coastal mapping to assess need for coastal defences. |
REC286-2015 | 1 - Land-use and building regs | Build flood capable infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2524 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate why the level of multiple responses had increased. |
REC285-2520 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate whether the additional resources in the North and North West regions were effective in reducing average response times. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1405 | 37 - Funding | That the Department of Justice & Regulation broadens Budget Paper 3 response time measures to more comprehensively cover emergency responses to fires, rescues and other emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1525 | 6 - Insurance and legal liability | The Department of Energy and Water Supply, in conjunction with SunWater, seek clarification of the dam owners’ legal obligation to comply with Emergency Action Plans and, if required, investigate how a more flexible approach may be adopted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1424 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Emergency Alert Guidelines is reviewed to reflect current practice and incorporate evidence-based improvements informed by lessons learned and research. |
REC268-1422 | 25 - Inquiry, audit, lessons management and after action review | The Queensland State Disaster Management Plan is reviewed to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2550 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority introduces grading of Non-Compliance Notices on a scale of seriousness. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2557 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reassesses the penalties in the Civil Aviation Safety Regulations. |
REC258-2544 | 6 - Insurance and legal liability | The Australian Transport Safety Bureau transfers information from Mandatory Occurrence Reports to the Civil Aviation Safety Authority, without redaction or de-identification. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2543 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reintroduces a ‘use of discretion’ procedure that gives operators or individuals the opportunity to discuss and, if necessary, remedy a perceived breach prior to CASA taking any formal action. This procedure is to be followed in all cases, except where CASA identifies a Serious and Imminent Risk to Air Safety. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2540 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority continues to provide appropriate indemnity to all industry personnel with delegations of authority. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1558 | 37 - Funding | Funding to state and territory governments for community recovery should be provided as untied grants, with a transition period pending the development of a framework to assess community recovery costs. During the transition period, the Australian Government should continue to provide funding for community recovery through a reimbursement model. |
REC256-1572 | 6 - Insurance and legal liability | Insurers should provide additional standardised information to households regarding their insurance policies, the natural hazards they face and indicative costs of rebuilding after a natural disaster. This work should be led by the Insurance Council of Australia developing guidelines, within one year, to ensure consistency in the provision and presentation of this information across insurers. |
REC256-1557 | 37 - Funding | Where asset management plans at the local, state or territory level pre-identify and cost betterment of assets (improving asset resilience to natural disasters), the Australian Government should share 50 per cent of the betterment component of reconstruction costs following damage from a (eligible) natural disaster. |
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
REC256-1556 | 37 - Funding | The Australian Government should fund natural disaster recovery by: |
REC256-1564 | 6 - Insurance and legal liability | State and territory governments, local governments and insurers should explore opportunities for collaboration and partnerships. Partnerships, for example, could be formed through the Insurance Council of Australia and state-based local government associations (or regional organisations of councils). Consideration could be given to the Trusted Information Sharing Network model. Partnerships could involve: |
REC256-1560 | 37 - Funding | The Australian Government should: |
REC256-1577 | 37 - Funding | The Australian Government should develop a formula for allocating mitigation funding to state and territory governments on the basis of where such funding is likely to achieve the greatest net benefits, taking into account the future risks of natural disasters. This should be completed within five years and in consultation with state and territory governments. |
REC256-1559 | 37 - Funding | The Australian Government should gradually increase the amount of annual mitigation funding it provides to state and territory governments to $200 million. Initially, this funding should be distributed to state and territory governments in accordance with the allocation under the National Partnership Agreement on Natural Disaster Resilience. |
REC256-1573 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should schedule an independent and public review of the progress of reforms to natural disaster funding arrangements five years after implementation has commenced. This review should examine the operation and efficacy of the arrangements, including the: |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2563 | 37 - Funding | Western Australia Health should develop and agree with St John Ambulance a new funding model for emergency ambulance services focusing on standards, performance and allocation of risk |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2564 | 37 - Funding | Western Australia Health should collate and centrally monitor financial data including the cost to government of IHPT |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2592 | 37 - Funding | That duplication of infrastructure be costed and taken into account when considering whether to proceed with the Whole of Government network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
REC244-2600 | 25 - Inquiry, audit, lessons management and after action review | An external audit of shared services performed by SAFECOM and services now provided by the three ESOs which have the potential to be shared, be undertaken to determine the most efficient and cost effective way such services can be delivered to the sector. The three ESO Chiefs need to have input into this process. |
REC244-2620 | 25 - Inquiry, audit, lessons management and after action review | Review employment conditions under the F&ES Act to align with those under the Public Sector Act unless there is a compelling reason to the contrary. |
REC244-2617 | 25 - Inquiry, audit, lessons management and after action review | When judging major incidents in the future, consideration be given to Eburn and Dover’s proposal to establish processes with a statutory basis that sufficiently balance the community’s interests in ensuring that true lessons, including lessons of error or neglect, are identified, whilst also protecting members of the emergency services. Processes need to be developed for emergency services such as those used in aviation and medicine, to facilitate open and honest disclosure of errors. |
REC244-2616 | 6 - Insurance and legal liability | That once the review of the Emergency Management Act has been finalised, any reference to the liability of councils should be mirrored in both the EM Act and the F&ES Act. |
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
REC244-2631 | 25 - Inquiry, audit, lessons management and after action review | Review Section 134 to ensure that it is not a deterrent to a group of farm fire units operating at an incident. |
REC244-2601 | 25 - Inquiry, audit, lessons management and after action review | That an independent review of the operational and geographic boundaries of the ESOs be conducted recognising the limitations of the current governance structures to adequately address such issues. Such a review needs to be performed periodically, but not less than every 8 years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0847 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
REC243-0843 | 6 - Insurance and legal liability | That the Government work with the Local Government Association to resolve questions of liability by volunteers who work for Councils, as raised with the Select Committee. |
REC243-0838 | 37 - Funding | That the Government cease drawing from South Australia Police or other Community safety and emergency service budgets to fund the Directorate and instead merge its work and functions with the pre-existing South Australia Fire and Emergency Services Commission for zero total State and other Community safety and emergency service budget impact. |
REC243-0835 | 37 - Funding | That the Government increase the budgets of all emergency services and community safety organisations, including: i. seeking Federal funding where appropriate (and assisting at no cost volunteer organisations with the grants application process); and ii. considering, with full public and cost benefit analysis, reviewing the effectiveness and efficiency of the Emergency Services Levy; and iii. consider including St John Ambulance Australia SA Ltd in the bodies to benefit from the Emergency services Levy if the funding of other Community Safety and Emergency services providers is improved in line with this recommendation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2643 | 25 - Inquiry, audit, lessons management and after action review | That the Government consult broadly upon and review impediments to volunteering in the community and establish a taskforce to assist in removing barriers to volunteering, particularly with respect to: |
REC242-2642 | 6 - Insurance and legal liability | That with regard to volunteer community safety and emergency service organisations that do not own land where their facilities exist: |
REC242-2640 | 37 - Funding | That the Government cease drawing from South Australia Police or other Community safety and emergency service budgets to fund the Directorate and instead merge its work and functions with the pre-existing South Australia Fire and Emergency Services Commission for zero total State and other Community safety and emergency service budget impact. |
REC242-2650 | 37 - Funding | That the Government resume funding for the helicopter surveillance service rather than by fixed-wing aircraft along Adelaide, South Coast and other high-risk coastlines during summer recreational periods for monitoring shark and other rescue situations, to bring the State back into line with interstate best practice. |
REC242-2637 | 37 - Funding | That the Government increase the budgets of all emergency services and community safety organisations, including: |
REC242-2649 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
REC242-2648 | 37 - Funding | That the Government adequately fund Community Safety and Emergency Services budgets so that fire-bombing aircraft are available on call for rapid deployment throughout Autumn and Spring at short notice to bomb fires at the earliest and safest possible opportunity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2724 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service undertake a review of all standing orders, incident directives and guidelines regarding response protocols with a view to reducing risk to staff and other road users associated with urgent duty driving. |
REC239-2763 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review includes a focus on the rank structure of both the Queensland Police Service and the proposed Fire and Emergency Services. |
REC239-2682 | 37 - Funding | That a budget based on the desired functional accountabilities should be appropriated to the Portfolio Business as part of the Government budget process. |
REC239-2779 | 37 - Funding | That a new business case for Westgate project should be prepared by an independent party. |
REC239-2723 | 1 - Land-use and building regs | That the Queensland Fire and Rescue Service examine alternative contractual arrangements with building owners which would reduce the need for physical attendance at alarm activations. |
REC239-2758 | 25 - Inquiry, audit, lessons management and after action review | That the Chief Executive Officer Portfolio Business leads an efficiency review of portfolio agencies beginning with the Queensland Police Service. |
REC239-2681 | 37 - Funding | That the funding model for the Portfolio Business is not based on fee- for-service arrangements or notional contributions from the operational services. |
REC239-2777 | 25 - Inquiry, audit, lessons management and after action review | That the review of this Queensland Fire and Rescue Services business unit be done in conjunction with the efficiency review proposed for the Queensland Police Service. |
REC239-2711 | 39 - Disaster Risk Management | That the Inspector General Emergency Management be empowered to provide an assurance to Government that the disaster management system is both appropriate and capable of dealing with complex events. |
REC239-2753 | 37 - Funding | That the proposed Chief Executive Officer Portfolio Business be responsible for developing a cost attribution model for portfolio agencies, including the Queensland Police Service, as a priority. |
REC239-2776 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review of the Queensland Police Service examine whether: |
REC239-2692 | 39 - Disaster Risk Management | That the Queensland Police Service Disaster Management Unit is to be permanently located at the State Disaster Coordination Centre to work on a day to day basis with the proposed new Department of Fire and Emergency Services. |
REC239-2727 | 25 - Inquiry, audit, lessons management and after action review | That as part of its efficiency review, the Queensland Fire and Rescue Service instigate an independent review of commercial operations in terms of statutory obligations and current ‘full cost pricing’ methodology to ensure: |
REC239-2774 | 39 - Disaster Risk Management | Those final determinations of disaster management districts include consultation with the Local Government Association Queensland, the Queensland Fire and Rescue Service and other Government departments. |
REC239-2691 | 39 - Disaster Risk Management | That the Commissioners of Police and the Queensland Fire and Rescue Service review the current district disaster boundaries as a matter of urgency in-line with the findings and recommendations of the Auditor–General’s report into the Queensland disaster management system. |
REC239-2725 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service community safety operations be joined in the efficiency review of the Queensland Police Service focussing on both the community safety outcomes achieved and the extent to which they support the Government’s economic priorities. |
REC239-2764 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review consider whether special service functions are core business, whether this practice is sustainable, and other options such as the use of casual employees. |
REC239-2683 | 37 - Funding | That the Office of Portfolio Business follows the same budget processes as other agencies. |
REC239-2780 | 37 - Funding | That should the Westgate project proceed, that consideration must be given to opportunities to partner the investment with the private and public sectors. The business case should also consider alternative facilities such as Australian Defence Force sites. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0808 | 1 - Land-use and building regs | Ensure future road infrastructure planning considers flood evacuation requirements throughout the Hawkesbury-Nepean floodplain. |
REC238-0806 | 33 - Relief and recovery | Review the adequacy of current arrangements for infrastructure reconstruction following a major flood event in the Hawkesbury-Nepean Valley. |
REC238-0805 | 33 - Relief and recovery | Develop a Hawkesbury-Nepean Flood Recovery Plan, which identifies strategies and arrangement for recovery from severe floods in the Hawkesbury-Nepean Valley. |
REC238-0816 | 1 - Land-use and building regs | Ensure appropriate consideration of flood risk in regional and subregional planning |
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
REC238-0815 | 1 - Land-use and building regs | Provide improved land use planning tools for managing flood prone land. |
REC238-0801 | 1 - Land-use and building regs | Establish a dedicated group or body within an existing agency to provide a more integrated, coordinated and regional approach to land use, infrastructure and evacuation planning and flood modelling in the Hawkesbury-Nepean Valley. |
REC238-0814 | 1 - Land-use and building regs | Develop a NSW Planning Policy and Guideline to improve land use planning practices on flood prone land. |
REC238-0800 | 1 - Land-use and building regs | Improve regional transport infrastructure to address current and projected flood evacuation capacity constraints and timelines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0833 | 37 - Funding | That the NSW Rural Fire Service and the NSW Treasury explore ways to ensure that unspent hazard reduction funds be carried over to the next financial year in a timely manner and to ensure that hazard reduction funding has a seamless transition from one financial year to the next. |
REC237-0825 | 1 - Land-use and building regs | That the NSW Rural Fire Service hold discussions with the Department of Planning and Infrastructure and Local Government NSW on ways to improve compliance with development consents under section 76A of the Environmental Planning and Assessment Act 1979. |
REC237-0834 | 37 - Funding | That the NSW Rural Fire Service apply for funding from the NSW Treasury for the development of a multi-agency business case for a BRIMS replacement that includes internal management, risk communication, community engagement capability and publishing activities on websites. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2801 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the ATSB review its process to track the implementation of recommendations or safety actions to ensure it is an effective closed loop system. This should be made public, and provided to the Senate Regional and Rural Affairs and Transport Committee prior to each Budget Estimates. |
REC236-2795 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that a short inquiry be conducted by the Senate Standing Committee on Rural and Regional Affairs and Transport into the current status of aviation regulatory reform to assess the direction, progress and resources expended to date to ensure greater visibility of the processes. |
REC236-2793 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that CASA processes in relation to matters highlighted by this investigation be reviewed. This could involve an evaluation benchmarked against a credible peer (such as FAA or CAA) of regulation and audits with respect to: non-RPT passenger carrying operations; approach to audits; and training and standardisation of FOI across regional offices. |
REC236-2792 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the investigation be re-opened by the ATSB with a focus on organisational, oversight and broader systemic issues. |
REC236-2806 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies investigate appropriate methods to ensure that information about the incidence of, and variable weather conditions at, Norfolk Island is available to assist flight crews and operators managing risk that may result from unforseen weather events. |
REC236-2791 | 37 - Funding | The committee recommends that the government develop a process by which the ATSB can request access to supplementary funding via the minister. |
REC236-2805 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies review whether any equipment or other changes can be made to improve the weather forecasting at Norfolk Island. The review would include whether the Unicom operator should be an approved meteorological observer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2812 | 37 - Funding | In order to further build on the value for money review work being undertaken by the National Disaster Recovery Taskforce (on behalf of the Australian Government Reconstruction Inspectorate), the Australian National Audit Office (ANAO) recommends that the Taskforce: |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2822 | 41 - Emergency Management exercises | The Australian Government test Australia’s ability to respond to a widespread outbreak of infectious disease other than influenza, by undertaking a pandemic exercise across the relevant Commonwealth, state and territory government agencies. |
REC232-2815 | 25 - Inquiry, audit, lessons management and after action review | The Department of Health and Ageing review the existing evidence base to evaluate the cost-effectiveness of its policy to use heat scanners at ports of entry as a measure to mitigate the risk of infectious disease importation. |
REC232-2828 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, commission an independent review to assess the case for establishing a national centre for communicable disease control in Australia. The review should outline the role of a national centre and how it might be structured to build on and enhance existing systems. It should examine different models, considering a range of options for location, governance and staffing. The review should incorporate a cost-benefit analysis for each of the models presented. |
REC232-2827 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, conduct a comprehensive national audit and mapping exercise to: |
REC232-2824 | 41 - Emergency Management exercises | The Australian Department of Health and Ageing consult with members of the general public or representatives of health consumers in the pandemic planning process, including in pandemic exercises designed to test the ability of government to respond to a pandemic event. Consumer involvement should include testing the ability of any communication strategy designed to inform and engage consumers about a pandemic event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2835 | 37 - Funding | The committee recommends that the Australian Government direct an appropriate portion of the proceeds derived from the auction of spectrum to fund the allocation of 20 MHz of spectrum in the 700 MHz band for the purposes of a national public safety mobile broadband network. |
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2842 | 1 - Land-use and building regs | The committee recommends that building codes incorporate mitigation measures that take into account foreseeable risks from extreme weather events. |
REC229-2841 | 1 - Land-use and building regs | The committee recommends that credible and reliable flood mapping activities and the development of other information that would best inform landowners or prospective landowners of potential risks from extreme weather events are prioritised and used to inform land use planning laws. |
REC229-2840 | 39 - Disaster Risk Management | The committee recommends relevant authorities work with community service organisations in both planning responses to and responding to extreme weather events, in particular those organisations that provide vital services to vulnerable groups. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1847 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments undertake a formal review by 30 June 2013 of the welfare services addressing stress and trauma provided to both their career and volunteer members. |
REC222-1869 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments include provisions for regular external audits of invoices for payment in their next round of Employee Assistance Program contract negotiations. |
REC222-1862 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services request the State Emergency Management Committee to review by June 2013 the sharing of data between the State’s emergency response agencies using the WebEOC software and any further enhancements that can be made to this process. |
REC222-1861 | 41 - Emergency Management exercises | The Ministers for Health, Emergency Services, Environment and Police provide additional funds to their agencies so that a detailed exercise is held on a regular basis based on a disaster that will create the worst outcome for the State. |
REC222-1856 | 37 - Funding | The Ministers for Emergency Services, Environment and Police provide additional funds in the 2013-14 Budget so that the State’s emergency response agencies can implement a Psychological First Aid approach to preparing staff to deal with critical incidents and disasters, as is used in other Australian jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1814 | 37 - Funding | The funding model for works on levees and their ongoing maintenance be revised, to be primarily based on the beneficiary pays principle. The state government should give consideration to wholly funding, or contributing to, the initial upgrade of high priority levees to an agreed standard. The construction of any new public levees will be the subject of a cost‐benefit analysis to be undertaken by DSE and the public authority, and be supported by a floodplain management study. Levees deemed low priority will be wholly the responsibility of the beneficiaries. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1845 | 37 - Funding | The state government should provide core, ongoing funding to the responsible authority for the FloodSafe community education program. Funding should be provided for education about prevention, response and recovery phases and include information on rates notices about the height of particular floods. |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1842 | 37 - Funding | The state government review the current funding approach used for the operation, maintenance and upgrade of river gauges, with a view to improving the river gauge network. |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0612 | 1 - Land-use and building regs | For non-urban areas or areas where limited development is expected to occur councils should consider, on a risk basis, what level of information about flood risk is required for the area, and undertake the highest ranked of the following options which is appropriate to that need and within the capacities (financial and technical) of the council: a. a map showing ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. a map showing the extent of floods of a range of likelihoods (at least three) c. a flood map based on historic flood levels that have been subjected to a flood frequency analysis to estimate the annual exceedance probability of the selected historical flood d. a historic flood map without flood frequency analysis e. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay as a way to determine those areas for which further flood studies are required, or f. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay (preferably refined using local flood information) as a trigger for development assessment. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0635 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to expressly provide either a power to remake or a power to extend a temporary local planning instrument containing interim flood regulation for a further limited period. The power to remake or extend should: a. permit the modification of the temporary local planning instrument to the extent required to ensure its provisions remain relevant, having regard to any requirement that may have been introduced or any information that may have become available while the original temporary local planning instrument was in force b. be contingent on the Minister’s being satisfied that the circumstances listed in section 105 of the Sustainable Planning Act continue to exist and that there are proper grounds for the failure to make a permanent scheme amendment while the original temporary local planning instrument was in force. |
REC210-0658 | 1 - Land-use and building regs | The Queensland Government should consult with councils to determine an effective method for the regulation of the construction of levees in Queensland. In particular, the Queensland Government should consider: • requiring a development permit for the construction of a levee by designating levees as assessable development in the Sustainable Planning Regulation 2009, or • requiring, by way of a state planning policy or mandatory provision in the Queensland Planning Provisions, that councils nominate the construction of a levee as assessable development in their planning schemes. |
REC210-0690 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0622 | 1 - Land-use and building regs | If, as part of a state interest review process, the Department of Local Government and Planning decides that no condition should be imposed requiring a council’s proposed planning scheme to incorporate the effect of the Department of Community Safety’s comments about State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide, it should advise the Department of Community Safety of the reasons for its decision. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
REC210-0640 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0666 | 1 - Land-use and building regs | The Queensland Government should draft a model planning scheme policy to be included in the model flood planning controls that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0702 | 6 - Insurance and legal liability | The Insurance Council of Australia should consider an amendment to Part 3 of the code which requires insurers to notify policy-holders of the information on which they relied in assessing claims. |
REC210-0627 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to require that consideration be given to the risk of flooding in the preparation or revision of a regional plan. |
REC210-0647 | 1 - Land-use and building regs | The Department of Environment and Resource Management should ensure that, when applications for a material change of use for an environmentally relevant activity are approved by the department, the details of those activities, including their nature and location, are provided to the council within whose area the activity will be conducted. |
REC210-0676 | 1 - Land-use and building regs | Authorities responsible for the construction of sewerage infrastructure should, when embarking on new works, undertake risk and cost/benefit assessments to determine the level at which electrical infrastructure that may be vulnerable to inundation should be placed. |
REC210-0611 | 1 - Land-use and building regs | For urban areas or areas where development is expected to occur: a. councils with the requisite resources should develop a flood map which shows ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. councils without the requisite resources to produce a flood behaviour map should develop a flood map which shows the extent of floods of a range of likelihoods (at least three). |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0634 | 1 - Land-use and building regs | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include in their planning schemes a planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as a part of the development application, or • for development proposed on land where potential for flooding is unknown requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information to allow an assessment of the flood risk. |
REC210-0657 | 1 - Land-use and building regs | Levees should be regulated. |
REC210-0686 | 6 - Insurance and legal liability | SunWater and the Central Highlands Regional Council should determine the issues of ownership and responsibility for maintenance of the LN1 drain system in Emerald. |
REC210-0621 | 1 - Land-use and building regs | The Queensland Government should: a. narrow the definition of ‘development commitment’ in State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide to ensure more development applications are assessed for compatibility with flood, and b. investigate whether the compensation provisions of the Sustainable Planning Act 2009 act as a deterrent to the inclusion of flood controls in a planning scheme and consider whether they ought be amended. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0639 | 1 - Land-use and building regs | The Queensland Government should consider extending the application of a state planning policy dealing with flood to the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood. |
REC210-0662 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0694 | 1 - Land-use and building regs | The Queensland Government should consider whether there should be a legislative requirement that customer dedicated assets be built at or above the applicable defined flood level and if so, the Queensland Government should consider which legislation should contain such a requirement. |
REC210-0701 | 6 - Insurance and legal liability | Letters notifying policy-holders that their claims have been denied should, at a minimum, state the information upon which the insurer has relied in making the decision. These letters should also advise policy-holders that copies of the information will be made available upon request (in accordance with clause 3.4.3 of the General Insurance Code of Practice) and indicate how policy-holders can make a request. |
REC210-0626 | 1 - Land-use and building regs | Councils should consider using the limited development (constrained land) zone in their planning schemes for areas that have a very high flood risk. |
REC210-0646 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend the template assessment report used to assess applications for a material change of use for environmentally relevant activities so that it prompts departmental officers to give specific consideration, as part of the assessment process, to the risk of flooding at the site where the activity is proposed to occur. |
REC210-0675 | 1 - Land-use and building regs | The Queensland Government should consider including in the criteria in the Queensland Plumbing and Wastewater Code a requirement that the risk of leakage from private on-site sewerage systems during floods be minimised. |
REC210-0735 | 6 - Insurance and legal liability | The Crime and Misconduct Commission should investigate whether the conduct of Mr Tibaldi, Mr Ayre and Mr Malone relating to: • preparation of documents surrounding the January 2011 flood event, including the 17 January 2011 brief to the Minister, the 2 March 2011 flood event report, and statements provided to the Commission • oral testimony given to the Commission evidences offence/s against the Criminal Code, and/or official misconduct under the Crime and Misconduct Act 2001 committed by any, or all, of them. |
REC210-0633 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as part of the development application, or • for development proposed on land where the potential for flooding is unknown, requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information, to allow an assessment of the flood risk. |
REC210-0656 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Regulation 2009 so that operational work or plumbing or drainage work (including maintenance and repair work) carried out by or on behalf of a public sector entity authorised under a state law to carry out the work is not exempt development under the Sustainable Planning Act 2009 if the development has the potential to reduce floodplain storage. |
REC210-0685 | 1 - Land-use and building regs | In assessing and determining development applications for material change of use in areas susceptible to flood, councils should consider whether the new developments locate essential services infrastructure above basement level, or, alternatively, whether essential services infrastructure located at basement level can be constructed so that it can continue to function during a flood. |
REC210-0617 | 1 - Land-use and building regs | The Queensland Government should consider implementing a mechanism by which prospective purchasers of property are alerted to the issue of flood risk. To that end, the Queensland Government should consider consulting the Real Estate Institute of Queensland and the Law Society of Queensland as to the appropriateness of amending standard contract conditions so as to include a ‘subject to flood search’ condition, or other means of achieving the same objective. |
REC210-0747 | 6 - Insurance and legal liability | Seqwater should ensure a legal review of the Wivenhoe manual and the North Pine manual is completed before the manual is submitted for approval. |
REC210-0638 | 1 - Land-use and building regs | The Coordinator-General should amend the guideline for preparing an ‘initial advice statement’ for a significant project under the State Development and Public Works Organisation Act 1971 so that it specifically requires an applicant to consider and provide information about the project’s flood risk. |
REC210-0661 | 1 - Land-use and building regs | There should be a common set of considerations in the decision whether to approve an application to build a levee, including: • the impacts of the proposed levee on the catchment as a whole • the benefits of the proposed levee to the individual or entity applying to build the levee and to any nearby community as a whole • any adverse impacts on other landholders, including the risk of levee failure • the implications of the proposed levee for land planning and emergency management procedures • whether any structural, land planning or emergency management measures can be taken to mitigate the adverse impacts of the proposed levee. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0700 | 6 - Insurance and legal liability | Insurers should review their existing systems and processes and implement any improvements necessary to ensure that accurate and complete records of conversations with policy-holders are made. |
REC210-0625 | 1 - Land-use and building regs | The Queensland Government should change Temporary State Planning Policy 2/11: Planning for stronger more resilient floodplains to remove the possibility of councils’ using the interim floodplain assessment overlay mapping and Model Code as part of a permanent amendment to their existing planning scheme or as part of a new planning scheme. |
REC210-0645 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend its information sheet about applications for a material change of use for environmentally relevant activities so that applicants are prompted to include information (if any) about the risk of flooding at the site where the activity is proposed to occur. |
REC210-0674 | 1 - Land-use and building regs | The Queensland Government should consider amending the ‘Limitation’ section of the proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, to allow for the possible application of ‘acceptable solution A1’ to a building located on a lot if: • it is reasonable to expect the part of the lot on which the building work is proposed to be subjected to a maximum velocity of less than 1.5 metres per second, or • the part of the lot on which the building work is proposed is located in an inactive flow or backwater area. |
REC210-0732 | 37 - Funding | Emergency Management Queensland should develop and implement a new formula for the distribution of its recurrent SES subsidy, which takes into account relevant factors including the size of a local SES contingent and the population, area and natural hazard risk profile of the local government area concerned. |
REC210-0631 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0654 | 1 - Land-use and building regs | The Queensland Government should consider drafting assessment criteria to be included in the model flood planning controls which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the applicable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms) • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0684 | 1 - Land-use and building regs | Councils should consider amending their planning schemes to include provisions directed to consideration of the flood resilience of basements as a factor in determining the appropriateness of a material change of use. |
REC210-0616 | 1 - Land-use and building regs | Councils that do not currently do so should consider offering an online database which allows the public to conduct a search on a parcel of land to find development approvals relevant to that parcel of land. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0637 | 1 - Land-use and building regs | The Queensland Government should consider amending the Urban Land Development Authority Act 2007, the South Bank Corporation Act 1989, the State Development and Public Works Organisation Act 1971 insofar as it governs state development areas, and other legislation which establishes alternative planning systems that operate independently of the Sustainable Planning Act 2009, to require that: • any planning scheme, interim or otherwise, appropriately reflects any state planning policy with respect to flood • flood risk be considered in the assessment of any development application. |
REC210-0660 | 1 - Land-use and building regs | There should be a consistent process for the determination of applications to build levees. That process should include: • consulting landholders who may be affected by the proposed levee • obtaining or commissioning appropriate hydrological and hydraulic studies to assess the impacts of the proposed levee. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0624 | 1 - Land-use and building regs | The Queensland Government should ensure that the circumstances in which the Department of Community Safety is to consult the Department of Environment and Resource Management about a planning scheme’s flood modelling and flood mapping are clear. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0644 | 1 - Land-use and building regs | The Queensland Government should ensure that the criteria under the Environmental Protection Act 1994 that apply to the assessment of development applications for material change of use for environmentally relevant activities include consideration of the risk of flooding at the site on which the activity is proposed to occur. |
REC210-0673 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirements about utilities and sanitary drains (Performance Requirement P2 and P3) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot. |
REC210-0699 | 6 - Insurance and legal liability | When a policy-holder makes a claim, the insurer should ascertain the policy-holder’s preferred method of contact and ensure that it is used (with other modes of communication if necessary) to keep the policyholder informed about the progress of the claim. However, important decisions regarding the claim – for example, determinations about the outcome of the claim and settlement sums – should always be confirmed in writing. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0629 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a requirement that councils have a flood overlay map in their planning schemes. The map should identify the areas of the council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0652 | 1 - Land-use and building regs | The Queensland Government should review the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003 to consider whether the design and construction standards should be made more stringent than the existing standards. |
REC210-0682 | 1 - Land-use and building regs | The Department of Environment and Resource Management should review the Queensland Urban Drainage Manual to determine whether it requires updating or improvement, in particular, to reflect the current law and to take into account insights gained from the 2010/2011 floods. |
REC210-0613 | 1 - Land-use and building regs | Councils should ensure that areas for which there has been no assessment of the likelihood of flooding are indicated on a map and that, as part of the development assessment process for these, there is at least some enquiry into whether a site proposed for development could be subject to flooding. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0636 | 1 - Land-use and building regs | The Queensland Government should consider allowing councils to amend a planning scheme to update existing flood mapping information by way of the minor amendment process, provided that adequate public consultation has occurred. |
REC210-0659 | 1 - Land-use and building regs | The Queensland Government should consult with councils to formulate a definition of ‘levee’ to identify what should be regulated. |
REC210-0691 | 1 - Land-use and building regs | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0623 | 1 - Land-use and building regs | The Department of Community Safety should put in place administrative arrangements which ensure it can readily ascertain whether its comments are being reflected in council planning schemes. If the Department of Community Safety becomes aware that its comments are not being adequately addressed, it should take steps to follow this up with the Department of Local Government and Planning. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0642 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require the impact of flood on commercial property to be minimised. |
REC210-0672 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirement relating to building design and construction (Performance Requirement P1) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot, and • either: – declared a velocity to be the expected maximum velocity of flood water for the area in which the lot is located, or – designated the area in which the lot is located an inactive flow or backwater area. |
REC210-0697 | 1 - Land-use and building regs | Queensland Rail and QR National should continue to investigate opportunities for increasing the flood resilience of their networks, including raising the height of critical equipment. |
REC210-0703 | 6 - Insurance and legal liability | The Insurance Council of Australia should amend clause 3.4.3 of the General Insurance Code of Practice so that it requires insurers to inform policy-holders of their right to request a review of an insurer’s decision to refuse to provide access to information on which it relied in assessing claims. |
REC210-0628 | 1 - Land-use and building regs | The Queensland Government should draft model flood planning controls, using a similar format and structure to that in the Queensland Planning Provisions, that councils can adapt for local conditions. The Queensland Government should require these controls to be reflected in new planning schemes. This may be achieved by including the controls in either: • a state planning policy dealing with flood, with an accompanying amendment to the Sustainable Planning Act 2009, or • the Queensland Planning Provisions. The Queensland Government should consult councils to determine which of the two state planning instruments is the more appropriate to include the model flood planning controls. |
REC210-0649 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters. |
REC210-0677 | 1 - Land-use and building regs | Authorities responsible for the management of sewerage infrastructure should conduct a review of their existing infrastructure to identify electrical infrastructure that may be vulnerable to inundation and perform risk and cost/benefit assessments to determine if it should be relocated to a higher level. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0526 | 25 - Inquiry, audit, lessons management and after action review | That OEH’s testing procedures for determining the impact of pollution incidents incorporate additional requirements for the checking and verification of results before those results are released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2877 | 37 - Funding | Explore opportunities to re-phase investments in large scale projects and programs such as the Strategic Radar Enhancement Program, the NexGen Forecast and Warning System Products and the Improving Water Information Program. |
REC207-2892 | 37 - Funding | Apply a consistent cost-recovery model to all services delivered to state/territory fire agencies. |
REC207-2890 | 37 - Funding | Review and rebalance relative investment in long term climate modelling and medium-term seasonal outlook. |
REC207-2889 | 37 - Funding | Review level of investment in research activities to free up budget and reduce pressure on computing capacity |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
REC207-2879 | 37 - Funding | Firm up approval processes and funding for any departures from provision of the basic product set |
REC207-2893 | 37 - Funding | Explore options to obtain revenue from advertising on the Bureau’s website |
Rec-ID | Code | Recommendation |
---|---|---|
REC206-1892 | 37 - Funding | The Committee recommends that the Australian Government allocate additional and continuing funding in the 2012–2013 budget to the Insurance Law Service to establish a consumer advisory position at the Financial Services Ombudsman. The position should be co-funded by the Insurance Law Service and the insurance industry. |
REC206-1891 | 37 - Funding | The Committee recommends that the Australian Government and relevant State and territory governments jointly allocate additional and continuing funding in the 2012–13 budget to the Insurance Law Service for the mobilisation of a temporary physical presence in areas of need following natural disasters. The service should be available to all persons in an affected disaster area and not subject to means-testing. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1905 | 6 - Insurance and legal liability | The Australian Government should only proceed with reforms that require all household insurers to offer flood cover if it can be demonstrated that the benefits to the wider community would exceed the costs. |
REC205-1903 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should commission an independent public review of disaster prevention and recovery arrangements. This should be broader than the review currently being conducted by the Attorney-General’s Department. The review should cover the Natural Disaster Relief and Recovery Arrangements, as well as the funding mechanisms for disaster mitigation, including the National Partnership Agreement on Natural Disaster Resilience. This review should: |
REC205-1902 | 25 - Inquiry, audit, lessons management and after action review | The Council of Australian Governments should commission an independent public inquiry to develop an appropriate response to managing the risks of climate change to existing settlements. The inquiry should: |
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
REC205-1906 | 6 - Insurance and legal liability | Governments should not subsidise household or business property insurance, whether directly or by underwriting risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC188-2917 | 33 - Relief and recovery | The committee recommends that relevant Commonwealth agencies continue to monitor the wellbeing of their personnel and that counselling and support services should be provided for as long as necessary. |
REC188-2916 | 33 - Relief and recovery | The committee recommends that the Department of Regional Australia and DIAC liaise with the Christmas Island community to explore options for a permanent memorial to be erected on the island, at a site of the residents' choosing, for the victims of the tragedy. |
REC188-2915 | 33 - Relief and recovery | The committee recommends that Department of Immigration and Citizenship (DIAC) and its relevant contractors continue to monitor the wellbeing of the survivors and that counselling and support services should be provided for as long as is necessary. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2935 | 6 - Insurance and legal liability | That flood premium discounts not be provided to small businesses and that the reinsurance facility not offer reinsurance for small businesses. |
REC187-2952 | 6 - Insurance and legal liability | That lending institutions remind mortgagors annually of their obligations to hold home insurance and of the risks of under-insurance in order to minimise non-insurance and under-insurance of homes. |
REC187-2968 | 6 - Insurance and legal liability | That the Government give priority to introducing legislation necessary to ensure that all home, contents and home unit insurance policies include flood cover and to establish a new national agency for flood risk management and flood reinsurance purposes. |
REC187-2925 | 6 - Insurance and legal liability | That the following five principles underpin the design of a system of premium discounts: |
REC187-2930 | 6 - Insurance and legal liability | That flood premium discounts be provided, in the same manner as for homes, to the bodies corporate of eligible properties, and on the same basis as for detached homes. |
REC187-2940 | 6 - Insurance and legal liability | That for home contents insurance policies, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $100,000. For contents with a value greater than $100,000 policyholders then pay the full cost of the portion of risk exceeding $100,000. |
REC187-2957 | 6 - Insurance and legal liability | That the Commonwealth Government introduce a standard definition of flood in the form proposed in the ‘Reforming flood insurance: Clearing the waters’ consultation paper. |
REC187-2945 | 6 - Insurance and legal liability | That to facilitate flood risk information being made publicly available, Commonwealth, State and Territory governments grant indemnities to the providers of flood risk information if the information is obtained and provided in good faith and in the absence of any gross negligence. |
REC187-2962 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend clause 4.5 of the General Insurance Code of Practice to extend the time within which claimants in natural disasters have the right to make further claims or lodge reviews after the finalisation of an initial claim to seven months from the date of the relevant natural disaster, regardless of when the initial claim was finalised. |
REC187-2919 | 6 - Insurance and legal liability | That all home insurance, home contents and home unit insurance policies include flood cover. |
REC187-2951 | 6 - Insurance and legal liability | That access to insurance be enhanced through the development of alternative payment options, in particular: |
REC187-2967 | 6 - Insurance and legal liability | That the current formula for the cost of rebuilding of State and Territory assets under the Natural Disaster Relief and Recovery Arrangements be changed to expenditure before any insurance recoveries by the State or Territory rather than net of any insurance recoveries. |
REC187-2924 | 6 - Insurance and legal liability | That whenever flood cover is included in home building insurance policies: |
REC187-2929 | 6 - Insurance and legal liability | That all home unit insurance policies include flood cover, in the same manner as for homes. |
REC187-2939 | 6 - Insurance and legal liability | That for body corporate insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000 times the number of units. For properties with a value greater than $500,000 times the number of units policyholders then pay the full cost of the portion of risk exceeding $500,000 times the number of units. |
REC187-2956 | 6 - Insurance and legal liability | That a ‘health warning’ be provided by insurers to the purchasers of home and contents policies that do not include full flood cover or full replacement cover. The health warning should be provided: |
REC187-2934 | 6 - Insurance and legal liability | That all insurers offering small business insurance be obliged to include flood cover on an opt-out basis, instead of an opt-in/opt-out basis as at present, in all of their small business package policies. |
REC187-2944 | 6 - Insurance and legal liability | That the Commonwealth seek reimbursement of some portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2961 | 6 - Insurance and legal liability | That the Insurance Council of Australia repeal clauses 4.3 and 4.4 of the General Insurance Code of Practice, so that claims arising from natural disasters are subject to the same minimum standards as other claims — including the four month time limit for a determination on liability and the nature of the loss/damage with respect to the claim. |
REC187-2950 | 6 - Insurance and legal liability | That the Commonwealth engage with the insurance industry and the States and Territories in planning for the future coordination of charitable and government payments to individuals to assist with recovery after future natural disasters. |
REC187-2966 | 6 - Insurance and legal liability | That the Commonwealth and State governments provide funding for legal advice and assistance with insurance disputes following natural disasters. |
REC187-2923 | 6 - Insurance and legal liability | That home building and home contents insurance should not be made compulsory. |
REC187-2928 | 6 - Insurance and legal liability | That there be limitations on the size of the discount available to high-value homes. |
REC187-2938 | 6 - Insurance and legal liability | That for home building insurance policies receiving full discounts, policyholders pay for that portion of the risk retained by the insurer and pay nothing for the remainder of the risk up to $500,000. For properties with a value greater than $500,000 policyholders then pay the full cost of the portion of risk exceeding $500,000. |
REC187-2955 | 6 - Insurance and legal liability | That, in endorsing the Government proposal for a Key Facts Statement, the Key Facts Statement list replacement cover and all natural disaster events, identified as ‘standard cover’ in the Insurance Contracts Regulations 1985. That insurers issue a Key Facts Statement to policy holders with all new policies written and all policy renewals on an annual basis. |
REC187-2933 | 6 - Insurance and legal liability | That discounts be provided, in the same manner as for homes, to home contents insurance policies for eligible properties. |
REC187-2943 | 6 - Insurance and legal liability | That the Commonwealth Government guarantee payment of claims from the reinsurance pool by ensuring that, whenever a funding shortfall occurs in the pool through claims exceeding the funds held in the pool, the Commonwealth would meet the shortfall. |
REC187-2960 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the Code of Practice to impose a four month time limit (subject to exceptional circumstances) to make a determination as to liability and the nature of the loss or damage with respect to a claim. That, should a claimant not receive a determination within the four month period, the claim be automatically escalated to an internal dispute resolution complaint and the insurer notify the Code Compliance Committee of the breach of the Code. |
REC187-2949 | 6 - Insurance and legal liability | That all home, contents and home unit insurance policies cover the policyholder for storm surge, tsunami and landslide, where the storm surge, tsunami or landslide is the result of another event that is covered under the policy and regardless of whether the insured property directly suffers damage from the underlying insured event. |
REC187-2965 | 6 - Insurance and legal liability | That ASIC conduct a review of the General Insurance Code of Practice three years after the amendments recommended to the Code in this Review are implemented, in order to assess the effectiveness of the Code with a view to determining whether an ASIC Regulatory Guide for claims handling should then be introduced. |
REC187-2922 | 6 - Insurance and legal liability | That all home building insurance policies include flood cover. |
REC187-2937 | 6 - Insurance and legal liability | That flood premium discounts be delivered through a model that requires insurers to retain and price a portion of the risk with the remainder to be ceded to the reinsurance facility at a discounted reinsurance premium. |
REC187-2954 | 6 - Insurance and legal liability | That subsection 35(2) of the Insurance Contracts Act 1984 be amended so that policyholders are not deemed to be clearly informed of a deviation from ‘standard cover’ by simply being provided a copy of the insurance policy or product disclosure statement. |
REC187-2927 | 6 - Insurance and legal liability | The levels of the discounts and the phasing out periods be reviewed from time to time. |
REC187-2932 | 6 - Insurance and legal liability | That all home contents insurance policies include flood cover. |
REC187-2942 | 6 - Insurance and legal liability | That a flood risk reinsurance facility, or reinsurance pool, be established which would have two primary functions: |
REC187-2959 | 6 - Insurance and legal liability | That every APRA-authorised general insurer adopt and comply with the General Insurance Code of Practice. |
REC187-2948 | 6 - Insurance and legal liability | That: |
REC187-2964 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice such that the General Insurance Code Compliance Committee: |
REC187-2921 | 6 - Insurance and legal liability | The Commonwealth Government guarantee the payment of claims by ensuring that, whenever a funding shortfall occurs in the reinsurance facility through claims exceeding the funds held in the facility, the Commonwealth would meet the shortfall and the Commonwealth would seek reimbursement of a portion of the shortfall from the State or Territory government in whose jurisdiction the flood occurred. |
REC187-2936 | 6 - Insurance and legal liability | That the questions of flood cover as standard in small business policies and access to discounted premiums for small business policyholders should be revisited once the recommended arrangements for homes, home units and home contents are in place. |
REC187-2953 | 6 - Insurance and legal liability | That all home building insurance policies providing sum insured cover be modified by the end of 2014 so as to include replacement value cover in the event of total loss of the home. That during the transition period insurers consider how the design features of home building replacement value policies should respond following a natural disaster, including the conditions under which cash settlements are to be offered and finalised. |
REC187-2926 | 6 - Insurance and legal liability | That flood premium discounts be provided for home building insurance for eligible homes: |
REC187-2931 | 6 - Insurance and legal liability | That the definition of a home for the purposes of flood cover and flood premium discounts be any building for which a homeowner purchases a home insurance policy. |
REC187-2941 | 6 - Insurance and legal liability | That homes at high and extreme risk of flood be provided with discounts initially and that they be assessed regularly for mitigation work already undertaken and the potential for further mitigation. |
REC187-2958 | 6 - Insurance and legal liability | That, in order to give general insurance policyholders the same legal remedies as other consumers, unfair contract terms laws be applied to general insurance. |
REC187-2947 | 6 - Insurance and legal liability | That the Agency charge insurers a small administrative fee for each policy ceded to the reinsurance facility. |
REC187-2963 | 6 - Insurance and legal liability | That the Insurance Council of Australia amend the General Insurance Code of Practice to require that: |
REC187-2920 | 6 - Insurance and legal liability | That a system of premium discounts be introduced in order that most purchasers of home insurance, home contents and home unit insurance policies in areas subject to flood risk be eligible for discounts against the full cost of flood insurance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC185-1933 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Treasury clarify what is meant by the term 'cost-effective' as it relates to the 2011 NDRRA Determination and the scrutiny of the states' and territories' insurance arrangements. |
REC185-1932 | 6 - Insurance and legal liability | The committee recommends that a particular focus of the Natural Disasters Insurance Review into the adequacy of current insurance arrangements should be on whether the international insurance market offers reinsurance for the states' and territories' road networks. |
REC185-1931 | 37 - Funding | The committee recommends that the Commonwealth Grants Commission ensures that as part of the current redesign of its data request, state and territory governments are required to include their past insurance and reinsurance receipts for natural disaster insurance premiums. These data must be taken into account by the Commission in determining the states' GST share. |
REC185-1930 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Government consult with state and territory governments to ensure that the states' and territories' captive insurance and reinsurance arrangements are reported transparently and on a comparable basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2976 | 41 - Emergency Management exercises | The Department of Human Services should regularly test recovery plans with partner agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0062 | 25 - Inquiry, audit, lessons management and after action review | Agencies should: annually assess their capability to respond to emergencies and take measures to address any shortfalls |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3016 | 37 - Funding | ESWG recommends investigation of options to fund NGERAC’s on-going activities including through AEMO’s funding model. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3030 | 25 - Inquiry, audit, lessons management and after action review | That National Offshore Petroleum Safety Authority review the risk assessment of pipelines. National Offshore Petroleum Safety Authority should focus, in particular, on the efficacy of anti-corrosion systems, and recognise potential interference effects and MAE escalation risks associated with adjacent pipelines and unlicenced pipes even if they fall outside its direct regulatory responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3058 | 25 - Inquiry, audit, lessons management and after action review | ACTAS should improve patient care processes by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3450 | 37 - Funding | That emergency services are responsible for funding the development of the emergency services marine emergency response capacity/capability to meet their statutory obligations. |
REC158-3449 | 37 - Funding | That port/channel managers are responsible for funding the preparation of marine emergency risk assessments and marine emergency response arrangements and ensuring the availability of identified marine resources in support of response to a marine emergency, to meet their statutory obligations. |
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
REC158-3451 | 37 - Funding | That port/channel managers should be able, within the general context of the pricing/cost recovery arrangements established under the Port Services Act 1995 and pricing determinations made by the Essential Services Commission, to recover the reasonable costs of meeting their statutory obligations (as per recommendation 26) through charges for prescribed service applied to port users. |
Rec-ID | Code | Recommendation |
---|---|---|
REC154-3462 | 41 - Emergency Management exercises | DPI should formalise the approach and framework for evaluating simulation exercises and response to Emergency Animal Disease incidents with guidelines to define the nature of the review process. This should include: |
REC154-3459 | 41 - Emergency Management exercises | To improve response preparedness, DPI should clearly link the selection of simulation exercises to the risk management framework to target coverage of high risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3182 | 25 - Inquiry, audit, lessons management and after action review | That Biosecurity Australia review that formal import risk analysis at least once every two years to take into account any relevant developments in scientific knowledge—specifically testing methods, vaccines, vaccination procedures and other matters that affect biosecurity. Reports on the reviews should be provided to the officer responsible for the importation of horses and should contain recommendations for any necessary changes to policies for importation. |
REC148-3167 | 25 - Inquiry, audit, lessons management and after action review | That the facilities at Eastern Creek and Spotswood Quarantine Stations be reviewed by AQIS in consultation with experts in biosecurity and interested parties including state and territory governments, import agents, veterinarians, farriers, operators of private quarantine stations, and representatives of horse owners, horse racing organisations and equestrian organisations. There should in any event be constructed without delay, an adequate supply of hygienic, modern showering facilities and places of entry and exit to the stations and the horse sections of them that can be supervised and monitored continually. There should also be provided at those stations as soon as is practicable suitable means of electronic surveillance, including closed-circuit television; a secure place to store chemicals, drugs, instruments and equipment for use by people attending the quarantined horses, and a set of horse stalls and yards separate from the main stalls and yards to enable isolation of horses suffering from contagious or infectious diseases. These reviews should also consider the desirability of separate areas in quarantine stations to hold horses forming part of a single quarantine intake but that have been imported from different regions or have undergone pre-export quarantine in different places. The reviews should be carried out without delay, and the two quarantine stations should be upgraded in accordance with the recommendations of the reviews. |
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
REC148-3154 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia or another qualified body to inspect and review the activities and events that occur from the time horses enter pre-export quarantine until the time they arrive at an airport in Australia, in order to identify any biosecurity risks and recommend any necessary changes to import conditions or other requirements. This inspection and review shall be performed without delay for each country or region from which horses are imported to Australia, and it should take account of my other recommendations and comments in this report. |
REC148-3175 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to review, at least once every two years, the operating procedures to ensure that they adequately identify and manage the risk of entry and spread of equine influenza associated with the importation of horses into Australia. The outcome of each such review should be the subject of a written report and recommendations to the person responsible for the importation of horses and the Executive Director of AQIS. A determination should then be made as to whether any, and if so what, changes should be made to the operating procedures. |
REC148-3185 | 37 - Funding | That, until the review of those fees has been completed, the fee charged by the government controlled and operated quarantine stations for thoroughbred stallions temporarily imported into Australia be not be less than $165.00 plus GST a day and the fee for all other horses be not less than $65.00 plus GST a day. No discount is to be allowed for the number of horses in a consignment. |
REC148-3170 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to conduct within six months, an inspection and review of the process of horse importation from the time horses arrive in Australia until the completion of their post-arrival quarantine in order to: |
REC148-3184 | 37 - Funding | That the fees charged in relation to the importation and quarantining of horses be reviewed and fixed without delay having regard to the following factors: |
REC148-3169 | 37 - Funding | That the budgets for airport reception of horses and government controlled and operated quarantine stations be determined so as to be sufficient to fund the operations of the Quarantine Stations in accordance with these recommendations and any further procedures and requirements that are laid down from time to time. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3189 | 37 - Funding | The ANAO recommends that, to ensure that grant conditions are satisfied, EMA enhance procedures to monitor the progress of projects and follow up those behind schedule or not fulfilling funding agreement requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC146-3193 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the Australian National Audit Office audit CASA's implementation and administration of its Safety Management Systems approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3232 | 37 - Funding | The Committee recommends that the Australian Government give consideration to establishing a separate funding program for infrastructure enhancement in coastal areas vulnerable to climate change. Such funding should be provided according to a formula requiring contributions, either financial or in-kind, from state governments and relevant local government authorities. |
REC145-3200 | 37 - Funding | The Committee recommends that the Australian Government: |
REC145-3212 | 6 - Insurance and legal liability | The Committee recommends that the Australian Government request the Productivity Commission to undertake an inquiry into the projected impacts of climate change and related insurance matters, with a particular focus on: |
REC145-3227 | 39 - Disaster Risk Management | The Committee recommends that coastal based Natural Resource Management bodies seeking funding under the Caring for our Country program have coastal and marine priorities, as well as coastal zone management principles integrated in their management plans. |
REC145-3210 | 39 - Disaster Risk Management | The Committee recommends that the Department of Climate Change, in collaboration with the Queensland Government, CSIRO and Indigenous communities in the Torres Strait, undertake a major study into the vulnerability of the Torres Strait to the impacts of climate change and provide assistance in the development of an adaptation plan. |
REC145-3222 | 1 - Land-use and building regs | The Committee recommends that the Australian Government: |
REC145-3209 | 39 - Disaster Risk Management | The Committee notes that major initiatives relating to climate change adaptation risk assessment and infrastructure are currently in progress. Given that much of Australia’s infrastructure is in the coastal zone and the particular threats facing the coastal zone from climate change, involving significant socioeconomic costs, the Committee recommends that the Australian Government ensure there is a comprehensive national assessment of coastal infrastructure vulnerability to inundation from sea level rise and extreme sea level events. |
REC145-3215 | 1 - Land-use and building regs | The Committee recommends that the Building Code of Australia, including cyclone building codes, be revised with the objective of increasing resilience to climate change. |
REC145-3207 | 37 - Funding | To further enhance Australia’s disaster mitigation, preparedness, response and recovery arrangements in the event of possible major coastal disasters, the Committee recommends that the Australian Government establish a grants program, the Coastal Natural Disaster Mitigation Program, to fund natural disaster mitigation projects in the Australian coastal zone. |
REC145-3214 | 1 - Land-use and building regs | The Committee recommends that the Australian Government consider the benefits of adopting a nationally consistent sea level rise planning benchmark and, if so, whether this be done on a statutory basis or otherwise. The outcomes of this consideration should then be included as part of the action plan for the proposed Intergovernmental Agreement on the Coastal Zone. |
REC145-3236 | 37 - Funding | The Committee recommends that the Australian Government provide funding support for the ongoing activities of the Australian Coastal Alliance in providing a national information and communication interface between research organisations and local government authorities and other coastal stakeholders. |
REC145-3203 | 39 - Disaster Risk Management | The Committee recommends that: |
REC145-3213 | 1 - Land-use and building regs | The Committee notes the Council of Australian Governments initiative (through the Local Government and Planning Ministers Council) to develop state-specific climate change planning policies by mid 2011, to inform local governments and regional planning responses to climate change. The Committee recommends that the Australian Government ensure that the outcomes of this initiative are included as part of the action plan under the proposed new Intergovernmental Agreement on the Coastal Zone. |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3384 | 41 - Emergency Management exercises | The Committee recommends that the ESA develop a schedule of proposed exercises as a five year rolling plan, in order that all the elements of emergency services are able to be tested over that time and in differing |
REC144-3379 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that a thorough review be undertaken of the communications and coordination between the separate agencies which make up the Emergency Services Agency, to assess the extent to which cultural factors are detrimental to the effective operation of the ESA. |
REC144-3393 | 1 - Land-use and building regs | The Committee recommends that the responsibility for land management issues lie within a single portfolio, specifically the Minister for Territory and Municipal Services. |
REC144-3385 | 41 - Emergency Management exercises | The Committee recommends that the ESA hold discussions with NSW with a view to developing a joint exercise program with the NSW Rural Fire Service on an ongoing basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3576 | 37 - Funding | That Fire and Emergency Services Authority of Western Australia and Main Roads Western Australia, in consultation with the Western Australian Local Government Association, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs. In particular consideration should be given to regulations applying in the eastern states i.e. Queensland. |
REC143-3586 | 37 - Funding | That the ‘opportunity cost’ for Local Authorities in meeting the 25% contribution to the restoration of eligible public assets damaged by a natural disaster event be considered when FESA and Main Roads Western Australia, in consultation with Western Australian Local Government Authority, investigate a more equitable means of calculating the local government contribution to road and infrastructure restoration costs as recommended in Recommendation 1. |
REC143-3585 | 33 - Relief and recovery | That the Professional Assistance Grant is formally extended by WANDRA to include non rural businesses and that it be made available to assist with the clean up of disaster related damage to farms and businesses. (The Committee recognises that the amendments to WANDRA as of March 2007 address this recommendation). |
REC143-3583 | 33 - Relief and recovery | That the newly proposed index linked limits for Personal Hardship and Distress Relief Payments as outlined in the paper “National Disaster Relief Arrangements - An Analysis and Recommendations for Personal Hardship Distress Measures” be accepted by government. |
REC143-3582 | 37 - Funding | That the Department of Treasury and Finance, in consultation with FESA, consider alternative funding arrangements to alleviate the need for FESA to ‘underwrite’ NDRA costs during the year. |
REC143-3589 | 37 - Funding | That consideration be given to the establishment of a ‘Heritage Reserve Fund’ that might underwrite urgent initial repairs to private heritage listed properties. |
REC143-3581 | 37 - Funding | That, in tandem with their consideration of local government cost sharing arrangements under WANDRA (refer Recommendation 1), the Fire and Emergency Services Authority and Main Roads Western Australia also establish ‘exceptional circumstances’ criteria to provide for additional assistance to local government where it may be warranted in order to avoid undue financial pressure caused by delays to secure reimbursement. |
REC143-3588 | 33 - Relief and recovery | That, in line with recommendations contained in the 2004 Report to the Council of Australian Governments, greater flexibility should be introduced to WANDRA to enable damaged infrastructure to be upgraded to a more resilient standard where that is both feasible and cost-effective. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3553 | 37 - Funding | RHH Neonatal Emergency Transport Service receive DHHS funding for a Senior Registrar to assume the responsibilities of retrieval staffing, quality assurance, data collection and reporting demands. |
REC140-3552 | 37 - Funding | Department of Health and Human Services (DHHS) to fund 3 Full-Time Equivalent (FTE) Senior Registrar positions at the Royal Hobart Hospital (RHH) for the Tasmanian Medical Retrieval Service (TMRS). One registrar in the Anaesthesia Department, one in the Intensive Care Unit and one in Emergency Department is proposed. |
REC140-3568 | 37 - Funding | The State Medical Retrieval Cost Centre (TMRS and NETS) be formed and be supported by the appropriate administrative and resource accountant expertise. This cost centre should be placed with those responsible for its management. |
REC140-3567 | 37 - Funding | A uniform retrieval charge to the region of referral should be considered. This should be independent of the mode of transport used. |
REC140-3558 | 6 - Insurance and legal liability | DHHS need to confirm adequate accident insurance coverage for staff working in retrieval medicine. Coverage specific to helicopter and fixed wing duties is required. |
REC140-3554 | 37 - Funding | DHHS fund the equivalent of 2 FTE Consultant positions for retrieval duties (1.5 FTE existing, 0.5 FTE new) |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3624 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and formally establish and oversight a comprehensive program of training, testing and evaluation of plans at the state, area and facility level. |
REC129-3623 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and apply the lessons learnt from Exercise Cumpston to further improve preparedness for major infectious disease emergencies. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
REC129-3628 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test the capability of its contact tracing system to deal with a public health emergency. |
REC129-3627 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test its surveillance systems for early detection of infectious diseases. |
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3614 | 37 - Funding | The Committee encourages the Department and the Rural Land Protection Boards to discuss the need for funding of poultry surveillance activities in the context of reviewing the Memorandum of Understanding between the two parties. |
REC128-3604 | 37 - Funding | That the Department of Primary Industries restore the level of discretionary testing funds provided to District Veterinarians to previous levels and maintain these in the future in real terms. |
REC128-3603 | 37 - Funding | That the Department of Primary Industries consider applying discretion to the use of user charging policies for testing in times when farm incomes are affected by external circumstances such as widespread drought. |
REC128-3598 | 25 - Inquiry, audit, lessons management and after action review | That the Department of Primary Industries incorporates reviews of plans and operating procedures as a result of emergency incidents and exercises and ensures that there is adequate commitment from all participants in the review process. |
REC128-3617 | 37 - Funding | That the Department of Primary Industries should provide specific information on levies to contributing producers through a separate document, rather than rely on standard audit documents and annual reporting requirements. |
REC128-3616 | 37 - Funding | That the Department of Primary Industries continue to pursue improvements to consultation with industry and accountability mechanisms to further build trust between industry and government, thereby enhancing the effectiveness of the OJD Program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3882 | 41 - Emergency Management exercises | The Office of the Emergency Services Commissioner convene a working group of key emergency services and emergency management agencies to develop a flow chart based on scenario testing, to support decision making and the assessment of response requirements to medical, hazardous materials and CBR emergencies including their transition from one type to another. |
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3703 | 6 - Insurance and legal liability | Alcohol and drug testing should be mandatory for any train driver or guard involved in any accident or incident. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3649 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2119 | 6 - Insurance and legal liability | The Working Group recommends that the National Recovery Coordinators Group approach the Investment and Financial Services Association Limited, with a view to identifying the most appropriate way of engaging the life insurance industry in the recovery process. |
REC116-2103 | 33 - Relief and recovery | The Working Group recommends that jurisdictions plan for the logistics of supply and delivery of meals to large numbers of homebound persons in an attempt to identify possible ways of resolving existing shortcomings. |
REC116-2117 | 33 - Relief and recovery | The Working Group recommends that potential shortfalls in the capacity to deal with large numbers of unprotected children and other special needs groups in a catastrophic event be referred to the Disaster Recovery Sub Committee of Community Services Ministers’ Advisory Council (CSMAC) for consideration and report back. |
REC116-2129 | 41 - Emergency Management exercises | The Working Group recommends that Emergency Management Australia and the jurisdictions through the AEMC develop a three year rolling national exercise strategy aimed at testing the response and recovery aspects of large scale disasters. |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2115 | 41 - Emergency Management exercises | The Working Group recommends that the results of the scenario modeling be presented to the Australian Emergency Management Committee (AEMC) upon completion, and that AEMC form Sub Working Groups of State/Territory emergency management representatives as appropriate to be tasked with considering response and recovery capability (both state/territory and national) against the identified consequences. |
REC116-2122 | 33 - Relief and recovery | The Working Group recommends that States/Territories consider their ability to house large numbers of domestic pets, and where necessary, develop plans and arrangements that facilitate this need. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2120 | 33 - Relief and recovery | The Working Group recommends that the National Recovery Coordinators Group considers the issue of emergency relief centres in the context of catastrophic disaster with a view to assisting jurisdictions to plan for the need to accommodate thousands of people following a disaster. |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
REC112-3934 | 37 - Funding | That DPI prepares guidelines, both internally and externally with Treasury, about funding arrangements for an outbreak. |
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
REC112-3927 | 6 - Insurance and legal liability | That PSB and PIRVIC review their service agreement to ensure that PIRVIC is compensated for its costs in providing PSB with the specified level of service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |
REC111-3939 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the State Disaster Management Group and the Department of Emergency Services review the current disaster district boundary framework and its relevance to the regional boundaries established by other public sector lead entities to ensure that resources within the Disaster Management System are economically, efficiently and effectively allocated across Queensland. |
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |