REC325-4328 | 9 - Community education | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services establish a community education program by 1 November 2023 that complements the implementation of the Australian Warning System. An evaluation process should be incorporated into the program to determine effectiveness. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4226 | 9 - Community education | The Inspector-General Emergency Management recommends the Bushfire Risk Mitigation Plan for Fraser Coast Area Fire Management Group include a schedule of planned engagement activities, or a community engagement sub-plan outlining these activities, and be publicly available. |
REC322-4249 | 9 - Community education | The Inspector-General Emergency Management recommends all Area Fire Management Groups in Queensland make their Bushfire Risk Mitigation Plans, bushfire risk mapping and methodology easily understood and available to the community. All public plans should be dated to ensure currency and incorporate mechanisms for community feedback. |
REC322-4221 | 9 - Community education | The Inspector-General Emergency Management recommends Department of Environment and Science implement an awareness and engagement strategy aimed at deterring the lighting of campfires to encourage behavioural change amongst visitors. |
Rec-ID | Code | Recommendation |
---|---|---|
REC312-2506 | 9 - Community education | The chairpersons of disaster management groups within the Townsville Disaster District, supported by the Queensland Police Service, Queensland Fire and Emergency Services and the Queensland Reconstruction Authority develop a district action plan based on the capability enhancement strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2500 | 9 - Community education | To enable the community to make informed choices about disaster management, Bundaberg and North Burnett regional councils and Sunwater undertake a community-informed audible test of the Paradise Dam siren. |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2489 | 9 - Community education | To enable the community to have a shared understanding of risks and enhance community engagement, flood scenarios in Emergency Action Plans be published, and in a format that can be utilised by public mapping systems. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2503 | 9 - Community education | To enable the casual/itinerant worker and tourism sector, including those who do not have English as a first language, to make informed choices about disaster management, community engagement and communication strategies about Paradise Dam and floods in the Burnett river system be tailored to this sector. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2502 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, Sunwater develop and deliver a sustainable long-term communication strategy on the community safety issues and |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2501 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, a joint Sunwater/council community engagement program be conducted to prepare the community downstream from Paradise Dam for events in the 2019/2020 storm and cyclone season, including the possibility of a Paradise Dam failure. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2485 | 33 - Relief and recovery | Recovery plans at all levels should include transition arrangements. They should be implemented during recovery. The arrangements should: |
REC310-2487 | 39 - Disaster Risk Management | The state’s arrangements for disaster management, including recovery, are articulated in the Disaster Management Act (2003), the Queensland Reconstruction Authority Act (2011), the State Disaster Management Plan and the Queensland Recovery Plan. To enable state-level arrangements to better support community-led recovery and to improve Queensland’s recovery governance |
REC310-2484 | 33 - Relief and recovery | There remains a need to maximise the effect of all offers of assistance to recovering communities. This recommendation presents an opportunity to resolve any outstanding aspects of Recommendation 4 and Actions in Response from the Cyclone Debbie Review Action Plan: |
REC310-2486 | 9 - Community education | State arrangements for on-the-ground support to recovering local governments should be in line with Queensland’s disaster management arrangements, and ensure the best balance between local relationships, suitable capability and sufficient capacity. |
REC310-2483 | 9 - Community education | 09-Community education/engagement/preparedness |
REC310-2482 | 9 - Community education | Practical guidance on what community-led recovery means, and how it can be best implemented should be captured and shared with all who have responsibility for it. This should be done to help individuals and communities to take the lead in recovery and so that community-led recovery becomes the norm following disasters and other events. |
REC310-2488 | 33 - Relief and recovery | The basic capacity needs of each functional recovery group and how this can be scaled up should be identified. Plans for functional recovery groups should reflect this in clear statements for every level of the system, for all relevant entities about their required function, role and responsibilities during recovery. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
REC309-2467 | 9 - Community education | Further work be undertaken to develop effective public flood risk messaging and community education materials that are easy to understand and tested with the community to ensure flood risk is understood. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2463 | 6 - Insurance and legal liability | Principles, applicable to all tourist budgets, covering liabilities for costs and shelter in the event of evacuation should be developed and promulgated as part of tourism marketing. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
REC307-2429 | 9 - Community education | A good neighbour policy such as that of the Queensland Parks and Wildlife Service, setting out clear expectations, be developed to guide all landholders. |
REC307-2448 | 9 - Community education | Targeted education about the short- and long-term effects of chemical suppressants should reach those likely to be exposed to them before aerial chemical suppressants are used in Queensland again. |
REC307-2447 | 9 - Community education | Clear public messaging regarding risks (if any) from the use of suppressants, including to 'organic' producers, should be developed and socialised before the next fire season and be readily available for dissemination when needed. |
REC307-2439 | 9 - Community education | Education on bushfires should include information about: |
REC307-2431 | 9 - Community education | Area Fire Management Groups should share seasonal risk information with local groups and actively and appropriately contribute to disaster management planning. |
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2430 | 9 - Community education | All Area Fire Management Groups should adopt and be guided by a good neighbour policy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2407 | 39 - Disaster Risk Management | Discontinue the automatic allocation of Fire Warden powers to Council and Committee members and substitute an option for members to be appointed as Fire Wardens. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1524 | 9 - Community education | SunWater provide downstream residents with easily understood information regarding operation of the dam, and the impacts that various outflows may have for them, in accordance with mapping prepared for the Emergency Action Plan. This information should be complementary to any information from the Banana Shire Council. |
REC271-1523 | 9 - Community education | Banana Shire Council coordinates the development of a strategy to significantly enhance public education regarding local disaster management arrangements within the Banana Shire, focusing on key identified risks. |
REC271-1525 | 6 - Insurance and legal liability | The Department of Energy and Water Supply, in conjunction with SunWater, seek clarification of the dam owners’ legal obligation to comply with Emergency Action Plans and, if required, investigate how a more flexible approach may be adopted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC270-1147 | 9 - Community education | improves engagement with communities to prepare for and respond to bushfires by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1432 | 9 - Community education | Queensland Fire and Emergency Services should consider developing and implementing mechanisms, such as face-to-face forums, for disaster management practitioners to share knowledge, contemporary research findings and document good practice about warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1120 | 9 - Community education | DFES should prepare a Standard Operating Procedure for the conduct of community meetings, and have available the appropriate audio visual and other equipment, to ensure that such meetings are able to fulfil their function in providing information and direction |
REC265-1126 | 33 - Relief and recovery | Development of a template contract for the clean-up of affected properties to speed-up the process; |
REC265-1101 | 9 - Community education | Staff and consultants skilled in community engagement practice should be specifically included in bushfire risk management planning and preparedness building programs undertaken by State agencies and/or local government. |
REC265-1125 | 33 - Relief and recovery | Consultation with the Board of the Lord Mayor’s Distress Relief Fund and other disaster appeal organisers should be undertaken to determine the potential for software development to consolidate the application and approval process, including provision of templates and application forms; |
REC265-1127 | 33 - Relief and recovery | Consultation should be undertaken with agencies and organisations that are engaged in emergency welfare provision to identify more effective ways to provide a consistent message to the community that non-cash donations are not required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1016 | 6 - Insurance and legal liability | That a volunteer shall not be liable for any act or omission made in good faith provided it is not proven to be reckless, negligent or malicious. This protection is to be afforded in both Criminal and Common law. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2659 | 9 - Community education | That Queensland Health continues to recognise and foster the important contributions of Local Ambulance Committees to supporting effective community focused ambulance services across the State. |
REC239-2691 | 39 - Disaster Risk Management | That the Commissioners of Police and the Queensland Fire and Rescue Service review the current district disaster boundaries as a matter of urgency in-line with the findings and recommendations of the Auditor–General’s report into the Queensland disaster management system. |
REC239-2770 | 9 - Community education | That the efficiency review of the Queensland Police Service develop options for better management of community expectations and divesting the organisation of historical practices. |
REC239-2774 | 39 - Disaster Risk Management | Those final determinations of disaster management districts include consultation with the Local Government Association Queensland, the Queensland Fire and Rescue Service and other Government departments. |
REC239-2769 | 9 - Community education | That the Chief Executive Officer portfolio business and Commissioner of Police in line with the government’s open data policy consider introducing an improved social media style forum for interaction with the community and stakeholders across the portfolio. |
REC239-2711 | 39 - Disaster Risk Management | That the Inspector General Emergency Management be empowered to provide an assurance to Government that the disaster management system is both appropriate and capable of dealing with complex events. |
REC239-2768 | 9 - Community education | Recommendation: That: |
REC239-2692 | 39 - Disaster Risk Management | That the Queensland Police Service Disaster Management Unit is to be permanently located at the State Disaster Coordination Centre to work on a day to day basis with the proposed new Department of Fire and Emergency Services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0598 | 33 - Relief and recovery | When communities are grieving there is a need to provide special forms of support to affected residents. |
REC226-0596 | 33 - Relief and recovery | An early decision on relief funding enables timely responses. D CP should review their communication of relief arrangements to ensure that they are clear. |
REC226-0595 | 33 - Relief and recovery | Shire experiences in managing these traumatic events should be captured and passed into emergency management procedures. |
REC226-0594 | 33 - Relief and recovery | Procedures to resolve issues surrounding financial assistance need to be reviewed to ensure they are as smooth, fast and transparent as possible possible. Review and streamline current financial relief procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1633 | 6 - Insurance and legal liability | The Treasurer undertake a review by the next bushfire season of the ability of RiskCover to efficiently undertake loss assessing and compensation activities for victims of major natural disasters, such as a bushfire, in an empathic and timely fashion. |
REC224-1632 | 6 - Insurance and legal liability | The State Government prepare a consistent policy on how to assist or compensate the victims of future major natural disasters, such as bushfires, in an equitable fashion. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0521 | 9 - Community education | The Department of Environment and Conservation develop and implement a strategy to better inform the community about the complexities and decisions surrounding prescribed burns when they are undertaken in the rural urban area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0680 | 9 - Community education | Queensland Urban Utilities, and other distributor-retailers and councils, that have identified a practice of stormwater drains being connected to sewerage infrastructure, should conduct a program of education to raise public awareness that this practice is illegal and impedes the operation of the sewerage infrastructure. |
REC210-0703 | 6 - Insurance and legal liability | The Insurance Council of Australia should amend clause 3.4.3 of the General Insurance Code of Practice so that it requires insurers to inform policy-holders of their right to request a review of an insurer’s decision to refuse to provide access to information on which it relied in assessing claims. |
REC210-0615 | 9 - Community education | Flood maps, and property specific flooding information intended for use by the general public, should be readily interpretable and should, where necessary, be accompanied by a comprehensible explanatory note. |
REC210-0702 | 6 - Insurance and legal liability | The Insurance Council of Australia should consider an amendment to Part 3 of the code which requires insurers to notify policy-holders of the information on which they relied in assessing claims. |
REC210-0614 | 9 - Community education | Councils and the Queensland Government should display on their websites all flood mapping they have commissioned or adopted. |
REC210-0701 | 6 - Insurance and legal liability | Letters notifying policy-holders that their claims have been denied should, at a minimum, state the information upon which the insurer has relied in making the decision. These letters should also advise policy-holders that copies of the information will be made available upon request (in accordance with clause 3.4.3 of the General Insurance Code of Practice) and indicate how policy-holders can make a request. |
REC210-0604 | 9 - Community education | By reference to the order of priority determined in accordance with recommendation 2.5, the Queensland Government and councils should together ensure that the council responsible for each urban area in Queensland has access to current flood study information. This will include determining: a. a process or processes by which the flood studies will be completed, including the involvement of the Queensland Government and relevant councils b. how, and from whom, the necessary technical and financial resources will be obtained c. a reasonable timeframe by which all flood studies required will be completed. |
REC210-0700 | 6 - Insurance and legal liability | Insurers should review their existing systems and processes and implement any improvements necessary to ensure that accurate and complete records of conversations with policy-holders are made. |
REC210-0699 | 6 - Insurance and legal liability | When a policy-holder makes a claim, the insurer should ascertain the policy-holder’s preferred method of contact and ensure that it is used (with other modes of communication if necessary) to keep the policyholder informed about the progress of the claim. However, important decisions regarding the claim – for example, determinations about the outcome of the claim and settlement sums – should always be confirmed in writing. |
REC210-0747 | 6 - Insurance and legal liability | Seqwater should ensure a legal review of the Wivenhoe manual and the North Pine manual is completed before the manual is submitted for approval. |
REC210-0603 | 9 - Community education | The Queensland Government, in consultation with councils, should determine which urban areas in Queensland do not have access to flood information from a current flood study. The Queensland Government should rank those areas in order of priority in accordance with their need for updated flood information by reference to factors including: a. population b. sophistication of land use planning and emergency management measures already in place in those areas c. currency of any flood risk information available to the council d. approximate frequency of damaging floods in the area according to the historical record |
REC210-0689 | 9 - Community education | Councils should conduct education campaigns directed to ensuring that all residents and property owners in areas identified as being at risk of backflow flooding are aware of the circumstances in which backflow flooding can occur, the hazard it presents and what should be done if it occurs. |
REC210-0686 | 6 - Insurance and legal liability | SunWater and the Central Highlands Regional Council should determine the issues of ownership and responsibility for maintenance of the LN1 drain system in Emerald. |
REC210-0735 | 6 - Insurance and legal liability | The Crime and Misconduct Commission should investigate whether the conduct of Mr Tibaldi, Mr Ayre and Mr Malone relating to: • preparation of documents surrounding the January 2011 flood event, including the 17 January 2011 brief to the Minister, the 2 March 2011 flood event report, and statements provided to the Commission • oral testimony given to the Commission evidences offence/s against the Criminal Code, and/or official misconduct under the Crime and Misconduct Act 2001 committed by any, or all, of them. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1639 | 40 - Equipment and consumables | An equipment replacement schedule for all Bushfires NT equipment be developed. |
REC209-1674 | 39 - Disaster Risk Management | That the concession holder of the rail corridor be approached to formalise a Memorandum of Understanding for the maintenance of the railway corridor for the purposes of fuel load reduction. |
REC209-1647 | 9 - Community education | A comprehensive pre bushfire season communications strategy, that supplements and extends the information provided on the DNRETAS website, be implemented to inform and educate landholders. |
REC209-1661 | 9 - Community education | Arrange a forum that includes all stakeholders in large scale fire management for the purposes of aligning the various stakeholder strategies across the Territory. |
REC209-1638 | 40 - Equipment and consumables | The Assets and Equipment Register be reviewed prior to each fire season. |
REC209-1667 | 39 - Disaster Risk Management | Prepare a formal proposal for the creation of pastoral/Indigenous Lands Fire Management Teams. |
REC209-1657 | 9 - Community education | Information for all landholders, in appropriate cultural and language formats be developed and distributed through events and multiple media. |
REC209-1637 | 40 - Equipment and consumables | Implement maintenance schedules for all common assets and shared equipment. |
REC209-1666 | 39 - Disaster Risk Management | Investigate the application and cost of the creation of District Coordination Officers to key high demand brigade districts. |
REC209-1656 | 9 - Community education | Ensure educational material is available prior to the commencement of each fire season in each region. |
REC209-1636 | 40 - Equipment and consumables | Update the Asset and Equipment Register for all assets and equipment. |
REC209-1655 | 9 - Community education | Professional communications and educational resources be contracted to develop an integrated communications and engagement strategy and program for implementation by Bushfires NT. |
REC209-1635 | 40 - Equipment and consumables | Conduct a stocktake of all assets and equipment in all regions for Bushfires NT and Volunteer Brigades. |
REC209-1640 | 40 - Equipment and consumables | Conduct a stocktake of all PPE and implement a top up program to bring all PPE to a fully operational standard. |
REC209-1675 | 39 - Disaster Risk Management | PowerWater Corporation be consulted with the intention of establishing a Memorandum Of Understanding for the maintenance of PowerWater land for the purpose of coordinated fire reduction. |
REC209-1653 | 9 - Community education | Develop a continuing education program for new members of the Bushfires Council, the Regional Committees and stakeholders’ representatives, to ensure that all stakeholders clearly understand the role and processes involved in the Bushfires Council advisory function. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1910 | 6 - Insurance and legal liability | As part of its review of its contract management processes, Tourism WA (with the Board of Tourism WA taking a lead role) should amend its contract template for event sponsorship to ensure that: |
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
REC204-1920 | 6 - Insurance and legal liability | The Attorney General gives urgent consideration to determining an ex gratia payment for: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0308 | 33 - Relief and recovery | Early resolution and clear communication of the financial and other support measures that will be available to affected residents is an important contributor to community resilience. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0512 | 9 - Community education | The Minister for Emergency Services commission an independent report to Parliament by June 2012 on an assessment of the success of FESA’s Total Fire Ban community education campaign in improving the community’s knowledge on this issue. |
REC202-0511 | 9 - Community education | The Minister for Emergency Services commission an independent report to Parliament by June 2012 on the best practices in other jurisdictions to increase the rate of residents likely to be effected by a bushfire who properly prepare their properties before the bushfire season. |
REC202-0510 | 9 - Community education | The Minister for Emergency Services and the Minister for Local Government provide additional resources to FESA, DEC and WALGA in the 2012-13 Budget to improve the Western Australian community’s knowledge of bushfire safety and to allow these agencies to involve the public in their exercises. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1684 | 9 - Community education | The Fire and Emergency Services Authority, in partnership with local governments, conduct more focused pre-season bushfire education, which emphasises: |
REC200-0347 | 9 - Community education | The Department of Education oversee the provision of bushfire education in schools that are located in bushfire prone areas, ensuring that all schools in these areas incorporate key bushfire messages in their curriculum. |
REC200-1724 | 6 - Insurance and legal liability | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-1688 | 9 - Community education | The Department of Education oversee the provision of bushfire education in schools that are located in bushfire prone areas, ensuring that all schools in these areas incorporate key bushfire messages in their curriculum. |
REC200-0344 | 9 - Community education | The Fire and Emergency Services Authority (FESA) review its distribution of information material, including Prepare. Act. Survive. FESA should also consider including the community in pre-season exercising, in consultation with the Department for Child Protection and local governments. |
REC200-1687 | 9 - Community education | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-0343 | 9 - Community education | The Fire and Emergency Services Authority, in partnership with local governments, conduct more focused pre-season bushfire education, which emphasises: Water supply is not guaranteed during a bushfire Power supply is not guaranteed during a bushfire Saving life will be a priority over saving property so expect to be evacuated Once evacuated, access to affected areas may not be possible for several days Water ‘bombing’ by aircraft cannot be guaranteed in bushfire SMS warnings are advice only and may not be timely. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-1686 | 9 - Community education | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-0349 | 9 - Community education | The Fire and Emergency Services Authority work in partnership with Main Roads Western Australia and local governments to develop and implement a comprehensive strategy for the use of mobile variable message boards to alert the community to the declaration of a total fire ban and what it means. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-0373 | 33 - Relief and recovery | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-1685 | 9 - Community education | The Fire and Emergency Services Authority (FESA) review its distribution of information material, including Prepare. Act. Survive. FESA should also consider including the community in pre-season exercising, in consultation with the Department for Child Protection and local governments. |
REC200-0348 | 9 - Community education | The Fire and Emergency Services Authority consider alternative wording to Total Fire Ban that ensures people gain a more complete understanding of what actions are prohibited. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0268 | 6 - Insurance and legal liability | that the QFRS investigate the possibility of insurance recovery when involved in vehicle retrieval activities at accident sites. |
REC191-0261 | 6 - Insurance and legal liability | that the Minister for Police, Corrective Services and Emergency Services undertake a comprehensive legal review in order to clarify the legal position of RFBs and their members. |
REC191-0267 | 9 - Community education | that the Deputy Premier, Attorney-General, Minister for Local Government and Special Minister of State establish with local government a communication strategy to inform all residents about their fire prevention responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0126 | 9 - Community education | FESA promotes a whole-of-community approach, involving FESA, Local Governments and the community, in fire prevention functions, activities and planning. |
REC182-0135 | 33 - Relief and recovery | FESA revises its standard operating procedures to provide guidance on the format and timing of post-incident community meetings. |
REC182-0132 | 9 - Community education | FESA implements an education and awareness campaign to promote the purpose and utility of community information systems. |
REC182-0127 | 9 - Community education | FESA strengthens its planning process to ensure learnings are incorporated and communicated, levels of preparedness are linked to threat analyses and public awareness and education activities are sustained. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3585 | 33 - Relief and recovery | That the Professional Assistance Grant is formally extended by WANDRA to include non rural businesses and that it be made available to assist with the clean up of disaster related damage to farms and businesses. (The Committee recognises that the amendments to WANDRA as of March 2007 address this recommendation). |
REC143-3583 | 33 - Relief and recovery | That the newly proposed index linked limits for Personal Hardship and Distress Relief Payments as outlined in the paper “National Disaster Relief Arrangements - An Analysis and Recommendations for Personal Hardship Distress Measures” be accepted by government. |
REC143-3579 | 9 - Community education | That FESA develop comprehensive internet-based information including but not limited to detail of WANDRA objectives, assistance measures, administering agencies, eligibility criteria (where applicable) and application forms. |
REC143-3588 | 33 - Relief and recovery | That, in line with recommendations contained in the 2004 Report to the Council of Australian Governments, greater flexibility should be introduced to WANDRA to enable damaged infrastructure to be upgraded to a more resilient standard where that is both feasible and cost-effective. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4146 | 6 - Insurance and legal liability | Insurance companies be asked to subsidise the bush fire equipment fund by an amount at least equal to the amount they at present remit on premiums received for fire insurance in approved districts and that the Government contribute an amount to the fund at least equal to that contributed by the Insurance Companies. |
REC019-4133 | 9 - Community education | The Bush Fires Board take a more active part in enlightening the public generally and the local communities in particular to their responsibilites on fire control. |