Rec-ID | Code | Recommendation |
---|---|---|
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that do not have pre-formatted messages and polygons engage with Queensland Fire and Emergency Services and determine whether their local disaster management group capability could be improved through the development of pre-formatted polygons and messages. |
REC325-4332 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends that all local governments that currently use pre-formatted messages within the Emergency Alert system review and, where necessary, redraft messages using the principles of Clear Explicit Translatable Language (CETL). |
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC325-4336 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services, in consultation with the Queensland Police Service, incorporate into the workflow of the current Emergency Alert system a process that ensures the inclusion of an ‘urgent approval and distribution without delay’ process for Emergency Alert messages by 1 November 2022. |
REC325-4337 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an urgent multi-agency (including but not limited to the Queensland Police Service and Brisbane City Council) review of the workflow, of the current Emergency Alert system, including requesting, composing, authorising and issuing of Emergency Alerts by 1 November 2022. |
REC325-4329 | 8 - Communications and warnings | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services implement the Australian Warning System for all nationally agreed hazards by 1 November 2023. Implementation should include guidance and training to all local governments and agencies operationally involved in disaster management, with emphasis on those agencies with hazard specific responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4313 | 8 - Communications and warnings | NSW disaster app: That, to improve community confidence in government messaging and warnings, the SEOCON and DCS develop a single ‘NSW disaster app’. This: |
REC324-4314 | 8 - Communications and warnings | PIFAC function: That, to ensure the community can better understand the threat of flood, storm and tsunami activity, the Department of Customer Service (DCS) be made accountable for PIFAC in all emergencies. This will improve access to clear, reliable and consistent messaging prior to and during emergencies. This transfers the PIFAC role from NSW Police Force to Service NSW. Under this PIFAC function, DCS would be responsible for: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4284 | 8 - Communications and warnings | That the NSW Government review its public awareness and communication strategies in relation to natural disasters. |
REC323-4288 | 8 - Communications and warnings | That the NSW Government work with the Commonwealth to develop a national cross-agency app to integrate all community services and agencies into a single platform so that everyone can receive accurate and timely information from one source during emergencies. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
REC323-4283 | 8 - Communications and warnings | That the NSW Government work with the community broadcasting sector to identify ways in which community broadcasters could be better supported to provide critical services during natural disasters, with a view to providing them adequate long term funding. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2508 | 25 - Inquiry, audit, lessons management and after action review | Regularly reviewing these plans to ensure that they reflect the current operating environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2487 | 39 - Disaster Risk Management | The state’s arrangements for disaster management, including recovery, are articulated in the Disaster Management Act (2003), the Queensland Reconstruction Authority Act (2011), the State Disaster Management Plan and the Queensland Recovery Plan. To enable state-level arrangements to better support community-led recovery and to improve Queensland’s recovery governance |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2457 | 8 - Communications and warnings | Efforts are made to improve the timeliness, accuracy and targeting of Emergency Alert messaging by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1267 | 8 - Communications and warnings | That emergency management authorities react with heightened awareness and action when BoM issues flood watches and related warnings. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1266 | 8 - Communications and warnings | That Government supports the anticipated SES State Flood Warning proposals aimed at improving public warnings and communication, and that the proposed warning system is consistent with the National Frameworks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2066 | 39 - Disaster Risk Management | Advocate for an National Notifiable Diseases Database. |
REC286-1438 | 25 - Inquiry, audit, lessons management and after action review | Consider outcomes of national review of warnings and review resilience of warning systems’ infrastructure. |
REC286-1452 | 39 - Disaster Risk Management | Improve understanding of the allocation of ownership across government, business and individuals. |
REC286-1469 | 39 - Disaster Risk Management | Actively manage riparian vegetation to manage flood dynamics. |
REC286-1467 | 15 - Inter-service cooperation | Review the allocation of responsibilities for earthquake risk management. |
REC286-2056 | 39 - Disaster Risk Management | Review Ambulance Tasmania surge capacity. |
REC286-2070 | 25 - Inquiry, audit, lessons management and after action review | Test the Biosecurity Act 2015. |
REC286-1450 | 39 - Disaster Risk Management | Improve the understanding of the vulnerability of critical infrastructure. |
REC286-2074 | 8 - Communications and warnings | Continue the enhancement of forecast and warning services. |
REC286-1465 | 15 - Inter-service cooperation | Improve the coordination and delivery of the National seismic monitoring program. |
REC286-1468 | 39 - Disaster Risk Management | Identify and anlalyse the location of critical infrastructure within defined flood areas. |
REC286-2049 | 39 - Disaster Risk Management | Pro-actively manage landslide areas. |
REC286-2078 | 15 - Inter-service cooperation | Review interagency information sharing arrangements. |
REC286-1448 | 39 - Disaster Risk Management | Utilise coastal mapping to assess need for coastal defences. |
REC286-2028 | 8 - Communications and warnings | Review community information and warning systems to ensure they cater for heatwave messages |
REC286-1463 | 39 - Disaster Risk Management | Develop enablers and capacity for Tasmanian earthquake risk owners. |
REC286-2017 | 39 - Disaster Risk Management | Improve maintenance of flood mitigation infrastructure. |
REC286-2014 | 15 - Inter-service cooperation | Integrate non-government entities into emergency response and recovery arrangements. |
REC286-2089 | 39 - Disaster Risk Management | Identify and analyse statewide storm hazard risk. |
REC286-1475 | 8 - Communications and warnings | Integrate existing capabilities into a Total Flood Warning System. |
REC286-1447 | 39 - Disaster Risk Management | Assess vulnerability of ecosystems and species to coastal inundation. |
REC286-2027 | 8 - Communications and warnings | Develop arrangements to identify and communicate with people vulnerable to heat stress |
REC286-1460 | 25 - Inquiry, audit, lessons management and after action review | Review seismic monitoring network alert systems to ensure emergency managers are on the contact lists. |
REC286-1461 | 39 - Disaster Risk Management | Review all hazards response and recovery plans to ensure they address likely earthquake consequences. |
REC286-2081 | 39 - Disaster Risk Management | Engage with industry bodies to explore opportunities to better understand and manage risks. |
REC286-1442 | 25 - Inquiry, audit, lessons management and after action review | Review legislation relating to Fuel Stove only areas, Fire Permit System and Total Fire Bans to ensure appropriate incentives to modify individuals’ behaviour. |
REC286-1455 | 39 - Disaster Risk Management | Assess options for managed coastal retreat. |
REC286-1478 | 39 - Disaster Risk Management | Review environmental risks associated with hazardous uses within flood prone areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2524 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate why the level of multiple responses had increased. |
REC285-2520 | 25 - Inquiry, audit, lessons management and after action review | The report recommends that Ambulance Tasmania investigate whether the additional resources in the North and North West regions were effective in reducing average response times. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1404 | 15 - Inter-service cooperation | That the Department of Health & Human Services and the Department of Justice & Regulation, in consultation with their portfolio emergency service agencies that have response time measures, determine relevant targets for these. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1529 | 8 - Communications and warnings | As part of the above, both the Banana Shire Council and SunWater ensure Emergency Alert messages are pre-formatted, consistent, polygons are identified according to risk, and that they are tested and practiced with the State Disaster Coordination Centre. |
REC271-1528 | 8 - Communications and warnings | Prior to September 2015, SunWater and the Banana Shire Council jointly develop a multi-channel, common warning strategy, including common language and consistent messaging, for residents downstream of |
REC271-1527 | 8 - Communications and warnings | Prior to September 2015, the Banana Shire Council develops a multi-channel warning strategy and associated public information campaign, including common language and consistent messaging, for the Banana Shire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1431 | 8 - Communications and warnings | Queensland Fire and Emergency Services should consider new and emerging technologies for issuing warnings (including opportunities for Emergency Alert to be distributed in other languages or to people with vision or hearing impairment). |
REC268-1427 | 8 - Communications and warnings | The Warning and Alert Systems training package is updated to align the content to the Standard for Disaster Management in Queensland and to include advice and scenarios from the Information Commissioner. |
REC268-1424 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Emergency Alert Guidelines is reviewed to reflect current practice and incorporate evidence-based improvements informed by lessons learned and research. |
REC268-1426 | 8 - Communications and warnings | A qualitative assessment of public information and warnings arrangements is undertaken as part of the 2016 disaster management plan assessment process. |
REC268-1422 | 25 - Inquiry, audit, lessons management and after action review | The Queensland State Disaster Management Plan is reviewed to: |
REC268-1425 | 8 - Communications and warnings | The Public Information and Warnings Sub-plan Guide is reviewed to include: |
REC268-1433 | 8 - Communications and warnings | Queensland Fire and Emergency Services should consider supporting local government in the annual development of at least one pre-formatted Emergency Alert message and polygon map based on a risk assessment and hazard modelling. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1095 | 15 - Inter-service cooperation | CFA and VICSES should: explore further opportunities to collaborate with each other. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1482 | 15 - Inter-service cooperation | That Emergency Management Victoria be responsible for facilitating the interoperability of all organisations involved in emergency response, including the Emergency Services Telecommunications Authority and Ambulance Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1573 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should schedule an independent and public review of the progress of reforms to natural disaster funding arrangements five years after implementation has commenced. This review should examine the operation and efficacy of the arrangements, including the: |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
REC252-2570 | 25 - Inquiry, audit, lessons management and after action review | Western Australia Health should carry out targeted clinical audits in volunteer country sub-centres until longer term solutions are in place |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0792 | 8 - Communications and warnings | The Department of Human Services should develop an improved model for communication for future disasters that provides a single point of information and contact for disaster affected communities |
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2617 | 25 - Inquiry, audit, lessons management and after action review | When judging major incidents in the future, consideration be given to Eburn and Dover’s proposal to establish processes with a statutory basis that sufficiently balance the community’s interests in ensuring that true lessons, including lessons of error or neglect, are identified, whilst also protecting members of the emergency services. Processes need to be developed for emergency services such as those used in aviation and medicine, to facilitate open and honest disclosure of errors. |
REC244-2601 | 25 - Inquiry, audit, lessons management and after action review | That an independent review of the operational and geographic boundaries of the ESOs be conducted recognising the limitations of the current governance structures to adequately address such issues. Such a review needs to be performed periodically, but not less than every 8 years. |
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
REC244-2600 | 25 - Inquiry, audit, lessons management and after action review | An external audit of shared services performed by SAFECOM and services now provided by the three ESOs which have the potential to be shared, be undertaken to determine the most efficient and cost effective way such services can be delivered to the sector. The three ESO Chiefs need to have input into this process. |
REC244-2604 | 8 - Communications and warnings | Notification of a total fire ban should be broadcast to the public via any means reasonably available. Section 80, parts (2), (5) and (6) be amended so that broadcast fire ban warnings include, but not be limited to, radio stations, internet sites, social media outlets etc. |
REC244-2631 | 25 - Inquiry, audit, lessons management and after action review | Review Section 134 to ensure that it is not a deterrent to a group of farm fire units operating at an incident. |
REC244-2620 | 25 - Inquiry, audit, lessons management and after action review | Review employment conditions under the F&ES Act to align with those under the Public Sector Act unless there is a compelling reason to the contrary. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2643 | 25 - Inquiry, audit, lessons management and after action review | That the Government consult broadly upon and review impediments to volunteering in the community and establish a taskforce to assist in removing barriers to volunteering, particularly with respect to: |
REC242-2647 | 8 - Communications and warnings | That Government agencies work closely with the Bureau of Meteorology and radio stations that broadcast emergency service announcements, to ensure the earliest possible determination of, and communications about, dangerous bushfire conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2727 | 25 - Inquiry, audit, lessons management and after action review | That as part of its efficiency review, the Queensland Fire and Rescue Service instigate an independent review of commercial operations in terms of statutory obligations and current ‘full cost pricing’ methodology to ensure: |
REC239-2692 | 39 - Disaster Risk Management | That the Queensland Police Service Disaster Management Unit is to be permanently located at the State Disaster Coordination Centre to work on a day to day basis with the proposed new Department of Fire and Emergency Services. |
REC239-2667 | 15 - Inter-service cooperation | That Queensland Corrective Service, the Queensland Police Service and Queensland Health should work together to develop a position that enables prisoners to have timely access to their prescribed medication despite travel between facilities and without the need for costly re-prescription. |
REC239-2777 | 25 - Inquiry, audit, lessons management and after action review | That the review of this Queensland Fire and Rescue Services business unit be done in conjunction with the efficiency review proposed for the Queensland Police Service. |
REC239-2725 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service community safety operations be joined in the efficiency review of the Queensland Police Service focussing on both the community safety outcomes achieved and the extent to which they support the Government’s economic priorities. |
REC239-2691 | 39 - Disaster Risk Management | That the Commissioners of Police and the Queensland Fire and Rescue Service review the current district disaster boundaries as a matter of urgency in-line with the findings and recommendations of the Auditor–General’s report into the Queensland disaster management system. |
REC239-2776 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review of the Queensland Police Service examine whether: |
REC239-2762 | 15 - Inter-service cooperation | That the Chief Executive Officer Portfolio Business in consultation with the Police Commissioner and the Commissioner Fire & Emergency Services should provide the direction for future information and communication technology strategies and acquisitions. |
REC239-2724 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service undertake a review of all standing orders, incident directives and guidelines regarding response protocols with a view to reducing risk to staff and other road users associated with urgent duty driving. |
REC239-2690 | 8 - Communications and warnings | That the Chief Executive Officer Portfolio Business and Commissioners establish a high level working group with the ABC and commercial media to identify and implement an improved information flow to the community on disasters. |
REC239-2764 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review consider whether special service functions are core business, whether this practice is sustainable, and other options such as the use of casual employees. |
REC239-2761 | 15 - Inter-service cooperation | That systems development in the Queensland Police Service capitalises on the advances made by the Queensland Fire and Rescue Service in recent years. |
REC239-2763 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review includes a focus on the rank structure of both the Queensland Police Service and the proposed Fire and Emergency Services. |
REC239-2774 | 39 - Disaster Risk Management | Those final determinations of disaster management districts include consultation with the Local Government Association Queensland, the Queensland Fire and Rescue Service and other Government departments. |
REC239-2703 | 15 - Inter-service cooperation | That the protocols developed by the Queensland Police Service and SES for operations define the respective roles and responsibilities as well as recognise the varying capabilities of SES units across the State. |
REC239-2758 | 25 - Inquiry, audit, lessons management and after action review | That the Chief Executive Officer Portfolio Business leads an efficiency review of portfolio agencies beginning with the Queensland Police Service. |
REC239-2711 | 39 - Disaster Risk Management | That the Inspector General Emergency Management be empowered to provide an assurance to Government that the disaster management system is both appropriate and capable of dealing with complex events. |
REC239-2694 | 15 - Inter-service cooperation | That Queensland enters into a similar arrangement with Bureau of Meteorology to have an experienced forecaster seconded to Kedron State Disaster Coordination Centre for at least the duration of fire and storm seasons. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2823 | 8 - Communications and warnings | The Australian Government, in consultation with consumers and other relevant federal, state and territory agencies, develop a national communication strategy for consumers to be used in the event of an infectious disease outbreak. |
REC232-2828 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, commission an independent review to assess the case for establishing a national centre for communicable disease control in Australia. The review should outline the role of a national centre and how it might be structured to build on and enhance existing systems. It should examine different models, considering a range of options for location, governance and staffing. The review should incorporate a cost-benefit analysis for each of the models presented. |
REC232-2827 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, conduct a comprehensive national audit and mapping exercise to: |
REC232-2815 | 25 - Inquiry, audit, lessons management and after action review | The Department of Health and Ageing review the existing evidence base to evaluate the cost-effectiveness of its policy to use heat scanners at ports of entry as a measure to mitigate the risk of infectious disease importation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2844 | 15 - Inter-service cooperation | The committee recommends that Australian governments specifically address issues of compatibility and capacity to facilitate the most effective interoperability of emergency service organisations and their key personnel, especially for fire services. |
REC229-2840 | 39 - Disaster Risk Management | The committee recommends relevant authorities work with community service organisations in both planning responses to and responding to extreme weather events, in particular those organisations that provide vital services to vulnerable groups. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1847 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments undertake a formal review by 30 June 2013 of the welfare services addressing stress and trauma provided to both their career and volunteer members. |
REC222-1857 | 15 - Inter-service cooperation | The Ministers for Health, Police, and Emergency Services ensure that the Western Australia Police, the Fire and Emergency Services Authority and St John Ambulance establish a formal platform to share their knowledge and experience in delivering programs to their staff and volunteers to address issues of stress from disasters and critical incidents, as is done in other Australian jurisdictions. |
REC222-1869 | 25 - Inquiry, audit, lessons management and after action review | The Ministers for Emergency Services, Environment and Police ensure their departments include provisions for regular external audits of invoices for payment in their next round of Employee Assistance Program contract negotiations. |
REC222-1863 | 8 - Communications and warnings | The Fire and Emergency Services Authority should expand their use of social media to better inform the Western Australian community. |
REC222-1862 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services request the State Emergency Management Committee to review by June 2013 the sharing of data between the State’s emergency response agencies using the WebEOC software and any further enhancements that can be made to this process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2869 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: developing tools and workflows to quickly and reliably transform technical data into intelligence that can be used to construct messages for community information that are timely, relevant, tailored and effective. |
REC216-2870 | 8 - Communications and warnings | Efficient and effective supporting tools and processes: streamlining the authorisation processes for urgent warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1903 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should commission an independent public review of disaster prevention and recovery arrangements. This should be broader than the review currently being conducted by the Attorney-General’s Department. The review should cover the Natural Disaster Relief and Recovery Arrangements, as well as the funding mechanisms for disaster mitigation, including the National Partnership Agreement on Natural Disaster Resilience. This review should: |
REC205-1902 | 25 - Inquiry, audit, lessons management and after action review | The Council of Australian Governments should commission an independent public inquiry to develop an appropriate response to managing the risks of climate change to existing settlements. The inquiry should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0437 | 8 - Communications and warnings | the state engage with local government to ensure emergency services’ public information and warnings reflect the community demographic. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0402 | 8 - Communications and warnings | the state develop a flood warning system for each basin and location with community input and make relevant documents publicly available. Each warning system should include key performance indicators. |
REC199-0436 | 8 - Communications and warnings | the state develop a standard approach to the provision of emergency warnings and information in formats – spoken and written – that recognise diverse community needs, including language and disability |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0471 | 8 - Communications and warnings | the state and the commonwealth, during a flood event, make information available on providers who have capacity to accommodate patients and residents who require evacuation. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0435 | 8 - Communications and warnings | the state put in place appropriate measures to inform the community of the intended purpose of the Emergency Alert warning system. |
REC199-0440 | 8 - Communications and warnings | the state actively pursue the use of social media as part of its emergency warning and public information system. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0434 | 8 - Communications and warnings | the state require that agencies operate in compliance with the guidelines of the Victorian Warning Protocol to ensure efficacy of warning messages. |
REC199-0439 | 8 - Communications and warnings | the state review its Memoranda of Understanding with official emergency broadcasters to take account of increased usage of internet based information, including social media and the ability to broadcast community meetings |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0433 | 8 - Communications and warnings | the state develop and implement standards for Emergency Alert to ensure consistent use, training and application by accredited operators within agencies across ‘all hazards’. |
REC199-0438 | 8 - Communications and warnings | the state investigate the ability to refine the Flood and Storm Information Line to enable it to receive as well as provide information. |
REC199-0451 | 15 - Inter-service cooperation | the state ensure, as a matter of priority, that the State Control Centre is able to function as a fit for purpose, multi-agency emergency management centre. Necessary works to achieve this outcome should have an overarching focus on the implementation of common agency systems and processes to the fullest extent possible. |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0432 | 8 - Communications and warnings | the state develop and implement a single web portal as a means of providing emergency information to communities and local government on an ‘all hazards’ basis, including the information referred to in recommendations 74, 89 and 92. |
Rec-ID | Code | Recommendation |
---|---|---|
REC186-0399 | 8 - Communications and warnings | The committee recommends the government consider granting public broadcasters priority access to fuel during times of emergency for the purpose of broadcasting emergency warnings and information, and in a way that does not impede the ability of emergency service organisations to access fuel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2981 | 8 - Communications and warnings | The Department of Human Services should complete work on emergency communication and information management issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0062 | 25 - Inquiry, audit, lessons management and after action review | Agencies should: annually assess their capability to respond to emergencies and take measures to address any shortfalls |
REC170-0059 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure all agencies use the same approach to managing incidents. |
REC170-0058 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure that all agencies can access other agencies’ operations centres when needed and that the procedures to do so are documented |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0087 | 8 - Communications and warnings | The SDMG commission the Department of Community Safety and seek the necessary funding to develop and enhance the Statewide Disaster Management information and communications system building on alternatives already in place and in consultation with all levels of Government. |
REC165-0096 | 15 - Inter-service cooperation | The Department of Community Safety and Councils develop MOUs to reflect the genuine partnership that exists in present arrangements including an emphasis on the use of the agreed State disaster arrangements to task and deploy SES units following State/Local consultation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3030 | 25 - Inquiry, audit, lessons management and after action review | That National Offshore Petroleum Safety Authority review the risk assessment of pipelines. National Offshore Petroleum Safety Authority should focus, in particular, on the efficacy of anti-corrosion systems, and recognise potential interference effects and MAE escalation risks associated with adjacent pipelines and unlicenced pipes even if they fall outside its direct regulatory responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3058 | 25 - Inquiry, audit, lessons management and after action review | ACTAS should improve patient care processes by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3497 | 8 - Communications and warnings | Emergency Service Organisations work with government departments, local governments and private industry to identify and implement a model for communication flow during an emergency incident. |
REC156-3485 | 15 - Inter-service cooperation | The integrated Emergency Coordination Centre be utilised during all significant multi-agency or multi-incident events with effective liaison with the State Emergency Response Coordinator. |
REC156-3491 | 8 - Communications and warnings | The Victoria State Emergency Service improve its communication with local governments, especially in relation to severe weather and storm warning information. |
REC156-3515 | 8 - Communications and warnings | The electricity distribution businesses enhance power outage information on their websites which are accessible to electricity retail businesses, the media and the public and also consider improving their capacity to communicate with customers. |
REC156-3509 | 8 - Communications and warnings | The Victoria State Emergency Service, Department of Primary Industries, Energy Safe Victoria and the energy sector develop a coordinated set of safety messaging about preparedness for storm events and clearly outline the responsibilities for delivering these messages before during and after an emergency. |
REC156-3507 | 8 - Communications and warnings | Victoria progress, as a matter of priority, a telephony based public emergency notification system to reduce demand on Triple Zero and other emergency telephone lines during a major emergency. |
REC156-3503 | 8 - Communications and warnings | Emergency Service Organisations review their use of Emergency Alerting System paging message categories to ensure that priority messages are not compromised by inappropriate use. An education program may be required to ensure that all users understand message categories, their intended use and ramifications of each category on network and message delivery sequence. |
Rec-ID | Code | Recommendation |
---|---|---|
REC152-3401 | 15 - Inter-service cooperation | The streamlining correspondence to Emergency Service Agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3175 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to review, at least once every two years, the operating procedures to ensure that they adequately identify and manage the risk of entry and spread of equine influenza associated with the importation of horses into Australia. The outcome of each such review should be the subject of a written report and recommendations to the person responsible for the importation of horses and the Executive Director of AQIS. A determination should then be made as to whether any, and if so what, changes should be made to the operating procedures. |
REC148-3170 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to conduct within six months, an inspection and review of the process of horse importation from the time horses arrive in Australia until the completion of their post-arrival quarantine in order to: |
REC148-3167 | 25 - Inquiry, audit, lessons management and after action review | That the facilities at Eastern Creek and Spotswood Quarantine Stations be reviewed by AQIS in consultation with experts in biosecurity and interested parties including state and territory governments, import agents, veterinarians, farriers, operators of private quarantine stations, and representatives of horse owners, horse racing organisations and equestrian organisations. There should in any event be constructed without delay, an adequate supply of hygienic, modern showering facilities and places of entry and exit to the stations and the horse sections of them that can be supervised and monitored continually. There should also be provided at those stations as soon as is practicable suitable means of electronic surveillance, including closed-circuit television; a secure place to store chemicals, drugs, instruments and equipment for use by people attending the quarantined horses, and a set of horse stalls and yards separate from the main stalls and yards to enable isolation of horses suffering from contagious or infectious diseases. These reviews should also consider the desirability of separate areas in quarantine stations to hold horses forming part of a single quarantine intake but that have been imported from different regions or have undergone pre-export quarantine in different places. The reviews should be carried out without delay, and the two quarantine stations should be upgraded in accordance with the recommendations of the reviews. |
REC148-3154 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia or another qualified body to inspect and review the activities and events that occur from the time horses enter pre-export quarantine until the time they arrive at an airport in Australia, in order to identify any biosecurity risks and recommend any necessary changes to import conditions or other requirements. This inspection and review shall be performed without delay for each country or region from which horses are imported to Australia, and it should take account of my other recommendations and comments in this report. |
REC148-3182 | 25 - Inquiry, audit, lessons management and after action review | That Biosecurity Australia review that formal import risk analysis at least once every two years to take into account any relevant developments in scientific knowledge—specifically testing methods, vaccines, vaccination procedures and other matters that affect biosecurity. Reports on the reviews should be provided to the officer responsible for the importation of horses and should contain recommendations for any necessary changes to policies for importation. |
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC146-3193 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the Australian National Audit Office audit CASA's implementation and administration of its Safety Management Systems approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3227 | 39 - Disaster Risk Management | The Committee recommends that coastal based Natural Resource Management bodies seeking funding under the Caring for our Country program have coastal and marine priorities, as well as coastal zone management principles integrated in their management plans. |
REC145-3210 | 39 - Disaster Risk Management | The Committee recommends that the Department of Climate Change, in collaboration with the Queensland Government, CSIRO and Indigenous communities in the Torres Strait, undertake a major study into the vulnerability of the Torres Strait to the impacts of climate change and provide assistance in the development of an adaptation plan. |
REC145-3209 | 39 - Disaster Risk Management | The Committee notes that major initiatives relating to climate change adaptation risk assessment and infrastructure are currently in progress. Given that much of Australia’s infrastructure is in the coastal zone and the particular threats facing the coastal zone from climate change, involving significant socioeconomic costs, the Committee recommends that the Australian Government ensure there is a comprehensive national assessment of coastal infrastructure vulnerability to inundation from sea level rise and extreme sea level events. |
REC145-3203 | 39 - Disaster Risk Management | The Committee recommends that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3395 | 15 - Inter-service cooperation | The Committee recommends that the ACT Emergency Services and the Rural Fire Service in particular institute regular meetings with the NSW Rural Fire Service and other appropriate authorities, such as environment |
REC144-3379 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that a thorough review be undertaken of the communications and coordination between the separate agencies which make up the Emergency Services Agency, to assess the extent to which cultural factors are detrimental to the effective operation of the ESA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3577 | 8 - Communications and warnings | That following the declaration of a natural disaster, complete and accurate information on Western Australian Natural Disaster Relief Arrangements assistance measures and application processes is disseminated through public communications channels, including the media. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3526 | 8 - Communications and warnings | That consideration be given to additional ways and means to improve broadcast capability into disaster-affected regions, particularly for the early aftermath of any disaster when a loss of power characterises the event. |
REC136-3528 | 8 - Communications and warnings | An early and high priority task in recovery from a natural disaster should be the development of a coordinated, succinct, practical and flexible public communications plan. |
REC136-3527 | 8 - Communications and warnings | In any future large-scale disaster or event, consideration be given to a centrally located Media Operations Centre. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3629 | 8 - Communications and warnings | We recommend that NSW Health continue with its good work and continue to improve communication mechanisms with those, such as GPs, likely to be affected in major infectious disease outbreaks. |
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3598 | 25 - Inquiry, audit, lessons management and after action review | That the Department of Primary Industries incorporates reviews of plans and operating procedures as a result of emergency incidents and exercises and ensures that there is adequate commitment from all participants in the review process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3891 | 15 - Inter-service cooperation | That Melbourne Water and councils explore opportunities for working collaboratively to address the management of flooding risks with a view to optimising the efficient and effective use of their flood mitigation resources. |
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3876 | 15 - Inter-service cooperation | Metropolitan Fire Brigade and Aviation Rescue Fire Fighting service review and enhance the existing mutual response Memorandum of Agreement to provide more timely notification and therefore immediate access to appropriate resources to respond to emergencies. |
REC123-3875 | 15 - Inter-service cooperation | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan to ensure the capabilities of agencies are adequately documented and understood by all stakeholders, and that all agencies including airlines are represented at the appropriate organisational level on the Airport Emergency Planning Committee. |
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3649 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2112 | 8 - Communications and warnings | The Working Group recommends that the Commonwealth Attorney General’s Department hold discussions with the Commonwealth Department of Communications, Information, Technology and the Arts regarding the Integrated Public Telephone Network Database (IPND) being made accessible for use in times of emergency where the need to disseminate community information and warnings to telephones within a specified area is identified. Discussions should also be held between the Commonwealth Attorney General’s Department and with the Federal Privacy Commissioner’s Office to identify any impediments to the use of the IPND in such circumstances. |
REC116-2098 | 15 - Inter-service cooperation | The Working Group recommends that Emergency Management Australia (EMA) facilitate national discussions into the capability of States/Territories to ensure thorough collaborative systems and plans for inter-jurisdictional resource interoperability exist, and where this has not already occurred at State/Territory level and appropriate agencies, committees or government departments can be identified, they should be tasked with progressing specific issues in the following areas: |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3933 | 15 - Inter-service cooperation | That DPI formalises agreements between divisions and groups that allow staff to be involved in incursion responses and reflects this requirement in individual duty statements. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3920 | 15 - Inter-service cooperation | That better use be made of Primary Industries Research Victoria's (PIRVIC) facilities by strengthening links with relevant groups of expertise, such as the Forest Science Centre. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |
REC111-3939 | 25 - Inquiry, audit, lessons management and after action review | It is recommended that the State Disaster Management Group and the Department of Emergency Services review the current disaster district boundary framework and its relevance to the regional boundaries established by other public sector lead entities to ensure that resources within the Disaster Management System are economically, efficiently and effectively allocated across Queensland. |