REC322-4223 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the Department of Environment and Science implements the proposed treatments for fire identified in the Queensland Parks and Wildlife Service K’gari Compliance Strategy. |
REC322-4248 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the prescribed burn program for K’gari be developed by the Department of Environment and Science, in collaboration with the Locality Specific Fire Management Group and the Butchulla people, based on the principles of the National Position on Prescribed Burning. This program should incorporate a process for monitoring and evaluation of outcomes and integration of evolving fire management practices. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4217 | 5 - Hazard reduction burns | We recommend that DELWP in partnership with Country Fire Authority and Fire Rescue Victoria develops, implements and publicly reports on a holistic suite of performance metrics to demonstrate: - the impact that planned burning has on public and private land on bushfire risk - the impact that planned burning has on public and private land on ecosystem resilience - the impact that non-burn fuel management activities have on public and private land on bushfire risk - the impact that its activities at local and regional levels have on bushfire risk - the cost-effectiveness of its fuel management activities on public and private land. |
REC321-4205 | 26 - Research | We recommend that DELWP in partnership with Parks Victoria, Country Fire Authority, Fire Rescue Victoria and councils as appropriate, collect empirical evidence after bushfire events to assess the effectiveness of different fuel management treatments, including planned burning, mulching, slashing and mineral earth breaks, and build an evidence base to the effectiveness of these treatments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4184 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria collaborate with the emergency management sector to develop a capacity model that considers current and future: |
REC318-4172 | 26 - Research | The Inspector-General for Emergency Management recommends that the State support the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) and its partners to expand the Safer Together program to: |
REC318-4179 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in accepting that emergency management is a ‘shared responsibility’ - collaborate with the emergency management sector and community to: |
REC318-4185 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria works with the emergency management sector and relevant emergency management entities in New South Wales and South Australia to identify and address key cross border operational and resource management issues. This engagement should aim to enhance interoperability and maximise the capability and capacity of agencies to work together during emergencies along Victoria’s borders. |
REC318-4176 | 26 - Research | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) lead the development and distribution of evidence-based land and fuel management tools for use by all legislated fuel management organisations to ensure a common approach to fuel management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4129 | 37 - Funding | Australian, state and territory governments should create simpler Disaster Recovery Funding Arrangements application processes. |
REC317-4128 | 37 - Funding | Australian, state and territory governments should broaden Category D of the Disaster Recovery Funding Arrangements to encompass funding for recovery measures that are focused on resilience, including in circumstances which are not ‘exceptional’. |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4125 | 37 - Funding | Australian, state and territory and local governments should develop greater consistency in the financial support provided to individuals, small businesses and primary producers under the Disaster Recovery Funding Arrangements. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4132 | 26 - Research | The material published as part of this Royal Commission should remain available and accessible on a long-term basis for the benefit of individuals, communities, organisations, businesses and all levels of government. |
REC317-4077 | 26 - Research | Australian, state and territory governments should support ongoing research and evaluation into aerial firefighting. This research and evaluation should include: |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4043 | 15 - Inter-service cooperation | NDIA be engaged in regard to information sharing in emergencies as part of the above actions. |
REC316-4048 | 37 - Funding | Government consider adopting a similar model to NSW for the management of emergency costs and reimbursements within ACT Government agencies. |
REC316-4034 | 15 - Inter-service cooperation | Efforts be increased to build trust, confidence and a common operating picture across PCS and RFS and seek mechanisms that identifies RFS and PCS as equitable partners in delivery of fire management across the territory. |
REC316-4047 | 37 - Funding | Government consider an alternative funding arrangement for extraordinary costs borne by Government agencies in combating emergencies such as bushfires. |
REC316-4019 | 15 - Inter-service cooperation | In collaboration with other jurisdictions the ACT share the learnings for this bushfire event and work to officially embedded values officers and RRATs as key elements of bushfire response. |
REC316-4017 | 15 - Inter-service cooperation | The working group (Rec 1) should include relevant stakeholders deciding collectively what the declaration might mean for such things as sub and supporting plans and the relevant community messages and calls to action. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3802 | 26 - Research | That Government establish NSW as a major world centre of bush fire research, and technology development and commercialisation. This should include: |
REC315-3855 | 7 - Inter-agency communication | That, in order to ensure all agencies have a clear understanding of cross-border communication channels during bush fires, all MoUs between state or territory agencies include an agreed protocol about how agencies will communicate across borders and that these are reflected in Incident Action Plans. |
REC315-3817 | 5 - Hazard reduction burns | That Government, noting that hazard reduction targeted in proximity to assets is on balance more likely to provide help than hinder, should: |
REC315-3835 | 15 - Inter-service cooperation | That, in order to ensure the safety of local landholders on firegrounds, the NSW RFS emphasises the importance of local landholders using protective clothing while fire fighting as part of the RFS’ ‘Farm Fire Unit Integration’ priority for 2020-21. |
REC315-3854 | 7 - Inter-agency communication | That, in order to ensure emergency response agencies can communicate across state and territory borders, the Commonwealth Government allocate 10 + 10 MHz as a dedicated spectrum for Public Safety Mobile Broadband (PSMB) at no cost to states and territories. |
REC315-3809 | 37 - Funding | That Government work with other Australian governments to provide long-term funding certainty to AFAC, including the National Resource Sharing Centre (NRSC) and the National Aerial Firefighting Centre (NAFC). |
REC315-3816 | 5 - Hazard reduction burns | That Government re-commit to the current, regionally based approach to planning and coordinating hazard reduction activities across all tenures through Bush Fire Management Committees but ensure that it is actually being implemented at a high-level of quality across NSW. Getting it to a high-level of quality requires: |
REC315-3845 | 26 - Research | That Government commission further research on the potential risks and benefits of backburning during severe, extreme and catastrophic conditions and/or in particular terrain, and that the NSW RFS use this research to inform future backburning protocols and training. |
REC315-3853 | 7 - Inter-agency communication | That, in order to ensure the State Emergency Operations Centre (SEOC) can maintain communications during emergencies, the Government provide the SEOC with independent Public Safety Network functionality. |
REC315-3831 | 26 - Research | That, in order to capture and understand the impacts of bush fire smoke better, Government invest in operational air quality forecasting and alert systems, and public health research and policy development. This would involve investment to: |
REC315-3806 | 15 - Inter-service cooperation | That the NSW RFS work with AFAC to analyse the impact of changing fire seasons on inter- jurisdictional resource sharing agreements, both domestic and international, and determine any flow-on effects for NSW fire fighting personnel capacity. |
REC315-3852 | 7 - Inter-agency communication | That, in order to improve fireground communications between NSW agencies and interstate personnel: a) Government ensure all NSW fire authority personnel and vehicles can access and utilise the Public Safety Network (PSN). This should include access to NSW RFS Private Mobile Radio networks where PSN coverage is not yet available. |
REC315-3818 | 26 - Research | That, in order to improve understanding of optimal hazard reduction techniques and their application in the landscape: |
REC315-3863 | 15 - Inter-service cooperation | That, in order to provide real-time information on evacuation doorknocking during emergency events, Government explore a shared data gateway for NSW agencies based on the NSW State Emergency Service Collector app and a common mapping and analytics platform. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3273 | 26 - Research | Collate data and research the impact of bushfires upon communities, firefighters and animals (both native and domestic) to identify appropriate medium and long-term welfare and support requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2396 | 15 - Inter-service cooperation | The Commissioners of Fire and Rescue NSW (FRNSW) and the RFS issue an instruction to FRNSW ComCen that while AVL capability is being made available to the RFS vehicle fleet, no offers of assistance by one agency to the other in combatting a fire is rejected or delayed if what is being offered is appropriate |
REC302-2394 | 15 - Inter-service cooperation | Take immediate steps to eliminate fire boundaries for call and dispatch purposes to create an agnostic approach to the threat of fires from both a departmental and organisational perspective |
REC302-2393 | 15 - Inter-service cooperation | In recognising the success of the work of both the volunteer based Rural Fire Service and the full time Fire and Rescue NSW (FRNSW) members in joint operations – both agencies should be represented at major briefings or press conferences to reinforce successful integrated collaborative efforts rather than individual agency achievements |
REC302-2400 | 15 - Inter-service cooperation | Until a single call centre is developed, continue deployments of a senior RFS officer to Fire and Rescue NSW ComCen on a 24/7 day basis. This arrangement should determine the quickest most suitable resource and who is ‘in charge’ of an incident |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2383 | 15 - Inter-service cooperation | Tasmanian Fire Service (TFS), Tasmanian Parks and Wildlife Service (PWS) and Sustainable Timber Tasmania (STT) initiate a discussion among their Australasian peers about good practice around managing new fire starts in remote terrain, to include issues around identification, predictive analysis, risk management and suppression activities. The outcome should be a document which allows for benchmarking to accepted good practice across Australasia, from which Tasmanian fire agencies can develop protocols against which the management of future events can be tested. |
REC301-2388 | 15 - Inter-service cooperation | TFS, PWS and STT should establish a State Air Desk, to be staffed by specialist staff year-round, with responsibility for managing both preparatory and contractual issues out of season as well as aircraft management when fires or other emergency events are occurring. |
REC301-2386 | 15 - Inter-service cooperation | TFS, PWS and STT should work with government and each other to continue to pursue a whole-of-state fuel management and burning program that encompasses all land tenures, meets the range of outcomes required by the state (township protection, risk reduction and landscape-scale burns) and is inclusive of private landholders and local communities as well as all fire agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1340 | 26 - Research | That any such pilot program ought to be managed by the relevant indigenous organisations, with support provided by DELWP and its partner agencies and the development and the evaluation of any pilot program should be overseen by an independent and reputable academic or research institution. |
REC299-1339 | 26 - Research | That Government provide support in the form of funding for the Return to the Firestick project, and that a formal pilot scheme be established where data can be collected, collated and analysed and the effectiveness of this approach be compared against current burning practices. |
REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
REC299-1346 | 26 - Research | DELWP and its partner agencies, in conjunction with the Department of Health and Human Services, should undertake research into the specific effects on health of people affected by planned burns and the information should be made public. The study should include the direct impact of smoke on affected populations and impacts on water, food supplies and livestock. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
REC291-1245 | 18 - Access to fire ground | The Department of Fire and Emergency Services to issue a photo identification card to DFES members, members of Bush Fire Brigades, volunteer emergency services, Incident Management Teams, forestry industry brigade members and Networked Government Emergency Agency members. DFES also to consider temporary windscreen signage to identify vehicles carrying such personnel. |
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
REC291-1242 | 15 - Inter-service cooperation | The Departments of Fire and Emergency Services and Parks and Wildlife to investigate and adopt an emergency services resource management system that will enable the registration, tasking, tracking, management and coordination of emergency management personnel, vehicles, plant and aircraft. |
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
REC291-1246 | 18 - Access to fire ground | The State Emergency Management Committee to review the policy for traffic management at emergency incidents so it reflects national ‘best practice’. This includes the production and issuing of an aide-memoire to guide traffic management, emergency and incident management personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1218 | 7 - Inter-agency communication | Cross-agency resource management system |
REC290-1210 | 15 - Inter-service cooperation | Co‐designed arrangements that support a unified response to fire |
REC290-1209 | 15 - Inter-service cooperation | Coordinated and targeted mitigation of fire risk |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1195 | 5 - Hazard reduction burns | The Committee finds that on the evidence presented, that the Fuel Reduction Burn Program should be maintained and have its budget directly funded to ensure that the program continues and does not hinder other services or programs. |
REC288-1194 | 37 - Funding | The Committee recommends the State Fire Commission be fully reimbursed for the costs of the State Emergency Service transfer in years 2014 to 2017. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1179 | 15 - Inter-service cooperation | The Tasmanian fire agencies develop a joint multi-agency Fire Preparedness Matrix to guide decision-making in response to severe fire weather conditions or capacity issues. |
REC287-1180 | 15 - Inter-service cooperation | The Tasmanian fire agencies consider the development of fire operational guidelines to avoid long-term environmental impacts such as: • • • strategies and tactics that will minimise the impact of fire management activities conditions under which earthmoving equipment and fire chemicals may be used information on seasonal conditions and the times of year when various strategies and tactics should be applied, and fuel management strategies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1377 | 5 - Hazard reduction burns | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC280-1376 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC280-1375 | 5 - Hazard reduction burns | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
REC280-1378 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: -improve accountability in relation to the implementation of bush fire risk management plans as a means of delivering more hazard reduction. |
Rec-ID | Code | Recommendation |
---|---|---|
REC278-1221 | 26 - Research | The committee recommends that the Australian Government, in cooperation with the Tasmanian Government: • recognise the need to identify the ecological and biodiversity impacts of fire on fire sensitive vegetation communities, organic soils and endemic fauna species in the Tasmanian Wilderness World Heritage Area; and • allocate long-teerm funding to the Commonwealth Scientific and Industrial Research Organisation and/or the Tasmanian Government to assist with the development of fire assessment and modelling specifically suited to the Tasmanian Wilderness World Heritage Area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1166 | 7 - Inter-agency communication | Develop an integrated inter-agency resource management system: Large and complex fire incidents require resources from multiple agencies. Developing an integrated inter-agency resource management system will have three main benefits: identifying potential resources will be more straightforward • the status and location of resource deployments can be tracked • planning of deployments can take into account all relevant information |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1132 | 15 - Inter-service cooperation | Noting the implementation of Common Incident Command and Control System (CICCS) in SA that fire and emergency services together with police (including through AFAC and ANZPAA), continue to liaise regarding the development of a national incident management. |
REC273-1142 | 18 - Access to fire ground | That SACFS consider the Traffic Management Procedures and guiding principles adopted in Tasmania as a model that could be implemented within SA. |
REC273-1131 | 15 - Inter-service cooperation | That the Emergency Management Australia’s ‘Arrangements for Interstate Assistance (Fire and Emergency Services)’ be applied to all future requests for assistance by the SACFS, SAMFS and SASES. |
REC273-1144 | 7 - Inter-agency communication | That SACFS consider a review to develop an effective interagency messaging system and agency resource management system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1105 | 15 - Inter-service cooperation | The Executive Teams of both DFES and DPaW should meet quarterly to review and agree joint improvements relating to issues of interoperability, complementarity and the alignment of firefighting doctrine. The establishment of a unified command in joint State Operations Centre, Regional Operations Centre and Incident Management Teams should be pursued as an overarching goal. |
REC265-1122 | 18 - Access to fire ground | DFES, in consultation with bushfire volunteers should develop a procedure for the controlled entry and exit of volunteers to the fire ground |
REC265-1111 | 15 - Inter-service cooperation | All agencies engaged in bushfire response should develop expeditious procedures for the mobilisation of resources in support of other agencies. See discussion in Section 7.1. |
REC265-1121 | 18 - Access to fire ground | A Restricted Access Permit system for the entry/ re-entry of residents, based on the one developed for the Parkerville Stoneville Mt Helena Bushfire should be finalised. |
REC265-1106 | 15 - Inter-service cooperation | In addition to regular meetings of the DFES/DPaW Interagency Bushfire Management Committee, the two organisations should use joint exercises to identify agreed firefighting approaches for common or likely scenarios. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1073 | 15 - Inter-service cooperation | The State establish, for any future incident, integrated incident management teams with GDF Suez and other Victorian essential industry providers, to: • essential industry providers; and require that emergency services personnel work with GDF Suez and other appropriate • implement the Australasian Inter-service Incident Management System. |
REC264-1081 | 26 - Research | The State should continue the long-term health study, and: • extend the study to at least 20 years; • appoint an independent board, which includes Latrobe Valley community representatives, to govern the study; and • direct that the independent board publish regular progress reports |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1495 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: |
REC261-1493 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC261-1492 | 37 - Funding | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1060 | 7 - Inter-agency communication | That the Rural Fire Service and National Parks and Wildlife Service review the procedures for requesting aerial support in ‘severe’ or worse fire conditions to ensure that delays in providing it are reduced to the minimum time possible. |
REC260-1067 | 15 - Inter-service cooperation | That as part of the adoption of such a posture in ‘severe’ or worse fire conditions, the National Parks and Wildlife Service consider alerting, at an early stage, all relevant persons and organisations, such as shire councils, heavy plant operators, the local RFS captains, Fire & Rescue NSW and other emergency services, that it is doing so, and that their assistance may be required at short notice. |
REC260-1070 | 5 - Hazard reduction burns | The NPWS conduct a review of its prescribed burns program to ensure, as far as reasonably practicable, that all necessary managerial approvals for a prescribed burn are provided as promptly as possible. |
REC260-1063 | 5 - Hazard reduction burns | That the National Parks and Wildlife Service consider reviewing its guidelines and protocols in respect of hazard reduction planning and burning-off operations in the light of the evidence from experts witnesses in these proceedings that the incidence of, and intensity of, major fires is increasing and in the light of expert evidence given in these proceedings concerning the dangers of vorticity-driven lateral spread. |
REC260-1061 | 18 - Access to fire ground | That the National Parks and Wildlife Service, in consultation with the relevant local Council(s), devise a policy that enables the John Renshaw Parkway to be closed at either end of the Warrumbungle National Park during a bush fire in such a way that its closure would not impede access by emergency services vehicles into the park. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1547 | 15 - Inter-service cooperation | The Marrangaroo Training Area Regional Environmental Officer confer with the local Rural Fire Service at least annually and determine a hazard reduction regime capable of implementation. It is furter recommended all ranges be reviewed in relation to the same issue, that is, that personnel involved in the management of each range under Defence control be directed to confer with local firefighting authorities on at least an annual basis to assess hazard reduction responses to be pursued for that range in subsequent years. |
REC257-1545 | 15 - Inter-service cooperation | Range Control Officer Marrangaroo Training Area liase with the local Rural Fire Service units to develop a map indicating the areas of the range likely to contain unexploded ordnance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1586 | 15 - Inter-service cooperation | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0854 | 15 - Inter-service cooperation | That in multi-agency response and recovery operations, arrangements be made so it is unambiguous who is in charge of these operations. |
REC247-0938 | 5 - Hazard reduction burns | That Tasmania Fire Service or another suitable agency provides information to the community which shows, in simple form, the legislation applicable to approvals for lighting fires on private property and the various relationships between that legislation. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0866 | 26 - Research | That fire agencies continue to develop their predictive modelling capability for use in actively managing fires. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
REC247-0902 | 7 - Inter-agency communication | That evacuation centres and other centres have a standard operating procedure for communications. |
REC247-0849 | 26 - Research | That Tasmania Fire Service supports the relevant authorities to continue developing methodologies to forecast and simulate fire risk. |
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0867 | 7 - Inter-agency communication | That Tasmania Fire Service reviews the communication systems used for all emergency management operations, ensures operators are qualified, and ensures there is appropriate accountability. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0859 | 7 - Inter-agency communication | That police and other emergency services examine options for achieving radio interoperability between them in the absence of an integrated radio system. |
REC247-0932 | 37 - Funding | That the resources available to the Parks and Wildlife Service, to manage bushfire risk following the recent increase in land under its tenure, is reviewed. |
REC247-0948 | 15 - Inter-service cooperation | That the Department of Justice conduct an independent review to develop a suitable model for integrated and interoperable emergency management arrangements in Tasmania. |
REC247-0939 | 5 - Hazard reduction burns | That Tasmania Fire Service conducts a review of the fire permit system in the Fire Service Act 1979, and implements change to improve the efficiency and effectiveness of the system by: • considering whether it is appropriate to authorise persons or organisations to conduct fuel reduction burning during a permit period • providing a better match between the period, area and fire risk • maintaining a timely and efficient process for issuing permits • naming the period in a way that draws attention to bushfire risk • establishing a reporting and accountability process. |
REC247-0858 | 7 - Inter-agency communication | That all agencies and the Government support moving to an integrated communications technology for police and the emergency services. |
REC247-0921 | 26 - Research | That Tasmania Fire Service promotes a structured approach to research across Australia, to provide a shared understanding and the capacity to benchmark and judge performance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1035 | 37 - Funding | That the State Government contribution towards the purchase of operational vehicles is to be retained at 80 percent but that the District Inspector can recommend full Government subsidy of vehicles for Brigades experiencing financial hardship. |
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-1034 | 37 - Funding | That the State Government contribution towards the construction of Brigade sheds be changed from $10,000 to a maximum of 25 percent, subject to the approval of the Deputy Chief Officer, Rural Fire Service Queensland. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-1033 | 37 - Funding | When a local Rural Fire Brigade requests an equipment and maintenance levy from a local government authority, that authority will either supply the brigade’s equipment and maintenance costs or raise the requested levy. The amount to be collected is to be agreed between the local Brigade and the local government authority. |
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-1032 | 37 - Funding | That the current Urban Fire Levy be changed to the Queensland Fire Levy. |
REC241-1004 | 15 - Inter-service cooperation | That a memorandum of understanding be developed between RFSQ and other organisations with fire fighting capacity at state level, to establish operational procedures when these organisations may be required for a joint response roles. Specifically, the intent will be: Vegetation Fire in a Rural Area: The Rural Fire Brigade in that area (boundary) is in charge and is the first Brigade called by Firecom. Structural Fire in a Rural Area: Firecom calls the Urban Brigade first and they control the incident. Local Rural Fire Brigade must also be notified by Firecom at the same time. Vegetation Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. At their discretion they may call Rural Fire Brigades for assistance. Structural Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. |
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-0967 | 26 - Research | That a Rural Fire Research and Investigation Team be established to coordinate and communicate fire research knowledge, including fire behaviour as well as coordinate fire investigations and complaints for the state. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1617 | 37 - Funding | The Territory and Municipal Services Directorate should annually (and on a cumulative basis) track and report on funds allocated for, and spent on, its Bushfire Operations Plan to the Minister for Police and Emergency Services. |
REC228-1623 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should develop and routinely review a strategic bushfire capability for the ACT. The contribution of ACT Fire and Rescue (including the Community Fire Units) and the ACT Rural Fire Service (including Parks Brigade) should be explicitly stated. |
REC228-1616 | 37 - Funding | The Territory and Municipal Services Directorate should enhance internal monitoring of its implementation of bushfire management activities and spending under the Bushfire Operations Plan by routinely reconciling figures in this plan with those in the Directorate’s corporate financial system. |
REC228-1622 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should continue to improve working arrangements between the ACT Rural Fire Service Parks Brigade and the ACT Rural Fire Service headquarters, by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0545 | 26 - Research | Improved understanding of fire behaviour in coastal heathlands would support sound risk management through the southwest of W |
REC226-0560 | 15 - Inter-service cooperation | There would be value in progressively aligning the geographical boundaries of emergency management agencies and co-locating where possible within regions and districts. |
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
REC226-0577 | 7 - Inter-agency communication | A system of vehicle tracking should be fitted to all fire appliances and linked to the common operating picture. Good communications planning is essential for good command and control. |
REC226-0548 | 15 - Inter-service cooperation | Inter-agency cooperation to manage fire precincts in a tenure-blind fashion is necessary for effective fire suppression. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0552 | 7 - Inter-agency communication | Communications planning for geographic regions with recognised black spots and specific communications challenges should be prepared in advance of an emergency in order to support the IMT Communications Planning Officer |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0578 | 15 - Inter-service cooperation | There would be benefit in progressively aligning the geographic boundaries of each of the agencies and seeking to co-locate their headquarters within those boundaries. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0537 | 7 - Inter-agency communication | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0517 | 26 - Research | The Department of Environment and Conservation be supported to conduct further research into the fuel management of coastal heath in the south west of Western Australia exploring alternatives to burning as well as best practice for burning. |
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1669 | 15 - Inter-service cooperation | Conduct an information sharing and planning exercise between Bushfires NT and NTFRS to explore the current boundaries and the overlaps in the peri-urban areas between the NTFRS ERA and the Bushfires NT areas of responsibility for all major centres in the NT. |
REC209-1642 | 37 - Funding | That a cost benefit analysis of an integrated ICT desktop and portable capability including iPads and iPhones for all operational personnel be conducted. |
REC209-1651 | 15 - Inter-service cooperation | Review the membership of the Bushfires Council, and the composition of Regional Committees to ensure that the Council and Committees have representational stakeholders. |
REC209-1677 | 37 - Funding | A specialist investigation be conducted, using expertise from NT Treasury, to identify more appropriate ways to optimise the use of available funding for bushfire management. |
REC209-1671 | 15 - Inter-service cooperation | That Bushfires NT, NTFRS, DLP, Weeds Branch, Parks and Wildlife, the Natural Resources Management Board, Biodiversity staff and representatives of the Volunteer Fire Brigades get together, at least annually, to coordinate planning efforts for peri-urban areas. |
REC209-1662 | 37 - Funding | Identify where Australian Government funding is available and apply for funding for integrating weed management, controlled burning, bushfire management and carbon farming initiatives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
REC203-0288 | 15 - Inter-service cooperation | The State Duty Officer from DEC and the State Duty Director, FES A need to confer whenever a Level 2 or 3 incident is declared to satisfy themselves that they have appropriate incident management structures and resources across the state are at an appropriate level of preparedness. |
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0292 | 18 - Access to fire ground | There is a need for community education on how road-blocks and VCPs operate in the event of an emergency. |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0287 | 15 - Inter-service cooperation | On a regional basis there would be value in closer working relationship between DEC crews and VBFBs to build mutual trust and confidence. This could be done by opportunity engagement of VBFBs in DEC fire management or through exercises. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
REC203-0291 | 18 - Access to fire ground | Local knowledge should be accessed to inform the placement and operation of VCPs. |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0301 | 15 - Inter-service cooperation | Early in an incident, close and effective liaison needs to be established with local government agencies. |
REC203-0290 | 18 - Access to fire ground | VCPs are one of the instruments by which the Incident Controller manages the emergency. VCPs without communications cannot be fully effective in their role. Determine and implement an appropriate communications platform for emergency management |
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0299 | 15 - Inter-service cooperation | The state should converge on a single communications platform for all emergency management and support agencies. |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0289 | 18 - Access to fire ground | There needs to be a better appreciation of the role of Vehicle Control Points (VCPs) and how they are managed in bushfire emergencies by all key agencies and the community |
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0298 | 15 - Inter-service cooperation | The state should progressively align on a shared platform, such as WebEO C , to establish a Common Operating Picture (COP). |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0504 | 15 - Inter-service cooperation | The Minister for Emergency Services ensure that the annual budget of FESA contains the funds it requires to coordinate an annual multi-agency bushfire field exercise, alongside other desktop exercises, to be held in different regions of the State each year. The outcomes of this field exercise should be included in the proposed annual Ministerial statement to Parliament on bushfire readiness before each season. |
REC202-0505 | 7 - Inter-agency communication | The Minister for Emergency Services makes it a priority that the annual budgets of FESA and WA Police are sufficient to bring forward the completion dates of the current radio projects now underway. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0260 | 15 - Inter-service cooperation | There are a range of opportunities identified from reviewing the three fires that will improve coordination between FESA and DEC, requiring limited resources, potentially generating some efficiencies and reflecting a joint, tenure blind approach to fire management in WA. The MIR acknowledges the progress made through the IBMC in these matters and notes these measures will require ongoing strong leadership. These include: · Clarification and consistent application of the Zone 2 and 2A mobilisation protocols; · Duplicating available information on websites; · Establishing a single State air desk and cross-utilising Air Attack Supervisors; · Completing common training for the conduct of public meetings;· Coordinating IMT training and exercises; · Operating joint IMT‘s during interface fires; FESA utilising the DEC mobile ICC when suitable ICPs are not available; · FESA engaging in daily weather teleconferences with DEC; Engaging a permanent BoM officer to support a common FESA and DEC SOC; · Developing a common ‗Tool Box‘ of forms and operational procedures for fire response; · Developing common jurisdictional arrangements to accommodate interstate support; · Developing a joint FESA/DEC SOC at the new (FESA) Emergency Services facility at Cockburn; · Adopting common and transparent Level 3 IC accreditation · Using a single mapping capability across both agencies and · Using common naming conventions for fires. |
REC201-0252 | 7 - Inter-agency communication | FESA must actively manage the transition to WAERN and provide alternative means for regional crews to communicate when in areas where WAERN is not operated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-1708 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
REC200-1713 | 7 - Inter-agency communication | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-0357 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-0385 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-1680 | 15 - Inter-service cooperation | Emergency Management Western Australia establish an inter-agency working group to continue the development of the new single emergency services Act. |
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-1725 | 37 - Funding | The State Government move the responsibility for the management and distribution of the Emergency Services Levy to the Department of Finance. |
REC200-0386 | 15 - Inter-service cooperation | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. This should include field exercises which test: Evacuation centres Critical infrastructure (including at the local level) Traffic management, including road blocks. Consideration should also be given to involving the community in exercising (see Recommendation 7) and using prescribed burns as exercises (see Recommendation 14) More detailed planning for exercises should be included in a revised WESTPLANBUSHFIRE to be endorsed by the State Emergency Management Committee. |
REC200-1697 | 26 - Research | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments closely monitor the research and development of alternative fuel reduction techniques to ensure that the most efficient and effective programs are adopted. |
REC200-1679 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-0338 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-0372 | 7 - Inter-agency communication | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0369 | 18 - Access to fire ground | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0322 | 7 - Inter-agency communication | The Fire Services investigate the reported technical communication issues for this fire |
REC195-0318 | 15 - Inter-service cooperation | The Fire Services develop a joint protocol for each Fire Service to notify the other of fires reported from fire towers |
REC195-0309 | 15 - Inter-service cooperation | The Fire Services, and other emergency management agencies, use the Tostaree fire as a scenario exercise to improve understanding of fast-running fires and enhance interoperability and control strategies |
REC195-0321 | 7 - Inter-agency communication | The Fire Services move towards a common and more disciplined approach to fireground communications. |
REC195-0319 | 7 - Inter-agency communication | The Fire Services introduce systems, procedures and operational training that promote information sharing and consistent situational awareness at every level, including to and from the fireground. This should include agencies such as police members on duty at roadblocks |
REC195-0327 | 15 - Inter-service cooperation | The Fire Services Commissioner ensures that the inter-relationship between Information Sections at all levels is understood. |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0221 | 37 - Funding | Funding be sought to enable the State Fire Management Council to take a greater coordination role for bushfire risk management and mitigation. |
REC193-0227 | 5 - Hazard reduction burns | Local government councils implement a zoning approach to fuel management as recommended by COAG 2004. |
Rec-ID | Code | Recommendation |
---|---|---|
REC192-1922 | 37 - Funding | The Committee recommends the provision of substantial funds to improve road infrastructure in the Mitcham Hills to be spent over the 2010/11, 2011/12, 2012/13 and 2013/14 budgets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0273 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services implement system of fire levies for landholders situated in urban, iZone and village brigade areas. |
REC191-0266 | 37 - Funding | that QFRS cover the cost of annual vehicle inspection certificates for rural fire brigade registered vehicles. |
REC191-0275 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services ensure that the formula for distribution of funding as recommended above allows rural fire brigades to control any donation or sponsorship funding raised by individual brigades. |
REC191-0274 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services undertake a thorough review, including consultation with rural fire brigades, regarding the proposed formula for distribution of funding. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0118 | 15 - Inter-service cooperation | A Memorandum of Understanding signed by the Chief Executives of DEC and FESA would be a valuable statement of joint commitment between the two agencies. |
REC183-0117 | 15 - Inter-service cooperation | The Interagency Bushfire Management Committee and its sub-committees are the logical central platform for developing and strengthening future joint bushfire strategies and common systems of work between bushfire management agencies in Western Australia. |
REC183-0116 | 15 - Inter-service cooperation | Triggers and a process for transfer of command and control from DEC to FESA should be developed and documented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0129 | 15 - Inter-service cooperation | FESA maintains inter-agency relationships and arrangements, and develops formalised arrangements across the entire emergency management cycle for joint activities such as training, exercises and procedure development. |
REC182-0125 | 15 - Inter-service cooperation | FESA, in partnership with other agencies and the community, develops Western Australia’s urban interface fire fighting capability and capacity. |
REC182-0124 | 15 - Inter-service cooperation | FESA and DEC take a whole of capability approach to joint operations, including developing joint doctrine that provides a common and articulated understanding of roles and responsibilities, resources and capabilities |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0206 | 5 - Hazard reduction burns | The State fund and commit to implementing a long-term program of prescribed burning based on an annual rolling target of 5 per cent minimum of public land. |
REC181-0215 | 26 - Research | The Commonwealth establish a national centre for bushfire research in collaboration with other Australian jurisdictions to support pure, applied and long-term research in the physical, biological and social sciences relevant to bushfires and to promote continuing research and scholarship in related disciplines. |
REC181-0214 | 37 - Funding | The State replace the Fire Services Levy with a property-based levy and introduce concessions for low-income earners. |
REC181-0172 | 15 - Inter-service cooperation | The Country Fire Authority and the Department of Sustainability and Environment standardise their operating systems and information and communications technologies with the aim of achieving greater efficiency and interoperability between agencies. |
REC181-0169 | 18 - Access to fire ground | The Country Fire Authority provide to all CFA volunteers an identification card or similar to facilitate their passage through roadblocks established in accordance with the 2009 Guidelines for the Operation of Traffic Management Points during Wildfires. |
REC181-0173 | 7 - Inter-agency communication | The Country Fire Authority review and improve its communications strategy as a matter of priority and develop a program for identifying and responding to black spots in radio coverage. |
REC181-0207 | 5 - Hazard reduction burns | The Department of Sustainability and Environment report annually on prescribed burning outcomes in a manner that meets public accountability objectives, including publishing details of targets, area burnt, funds expended on the program, and impacts on biodiversity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0149 | 26 - Research | The Productivity Commission be tasked to assess the economic effects of recent major bushfires on the Australian economy to determine the cost effectiveness of prescribed burning as a mitigation strategy. |
REC176-0148 | 26 - Research | At the conclusion of the current Bushfire CRC funding agreement the Commonwealth establish a new permanent bushfire research institute. |
REC176-0147 | 5 - Hazard reduction burns | The Commonwealth encourages further research into prescribed burning and its effectiveness and into alternative bushfire mitigation approaches through improved bushfire risk understanding at the asset level. |
REC176-0144 | 37 - Funding | Further Commonwealth funding for bushfire suppression be made conditional on state fire agencies agreeing to the Commonwealth evaluating and auditing their fuel reduction programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0016 | 18 - Access to fire ground | Full briefings of traffic management personnel should be provided prior to dispatch to work areas – why road closed, what their authority level is, level of current risk etc |
REC172-0042 | 7 - Inter-agency communication | Portable, reliable mobile repeaters are required to provide radio communications into areas not covered by existing repeater networks. These repeaters need the capacity to be linked. |
REC172-0014 | 18 - Access to fire ground | The Interagency Guidelines for Road closure needs to be reviewed to incorporate a mechanism to identify bone-fide local landholders to facilitate their movement in and out of cordoned areas in sympathy with the Stay and Defend requirements. |
REC172-0013 | 18 - Access to fire ground | In preparing traffic management plans consideration should be given to which VCP’s are critical and need to be resourced with uniformed Police Officers and which VCP’s can be manned with civilian contractors. |
REC172-0012 | 18 - Access to fire ground | Main Roads Western Australia, Police and LGA’s be encouraged via State emergency arrangements to establish a distributed cache of “hard” road barriers for deployment to major incidents |
REC172-0039 | 18 - Access to fire ground | Dedicated information packages should be made available to personnel operating Vehicle Control Points at the shift briefing. |
REC172-0022 | 15 - Inter-service cooperation | The declaration of a potential Level 3 incident should be notified to FESA who can facilitate an early warning to CFCO’s in the Shire and surrounding LGA’s. |
REC172-0011 | 18 - Access to fire ground | At Level 3 incidents the position of ‘Traffic Operations Officer’ –be established and filled by a WAPOL officer. A role description for this position is required and should be included in the “Guidelines for the Operations of Road Closures During Bushfires 2008”. This officer is to be supported by a suitably qualified officer from MRWA that is capable of developing Traffic Management Plans that address risk and are cognisant of considerations associated with road type, appropriate speed limitations, signage requirements, traffic volumes, detours for local traffic and heavy haulage etc. This role should report to the IC and have strong links to the Operations Section, Planning Section (particularly the Situation Unit) and the Information Unit. |
REC172-0017 | 18 - Access to fire ground | Information packs to be provided to road traffic personnel to assist with enquiries by public or provision to members of public and landholders who are defending homes/stock etc |
REC172-0043 | 7 - Inter-agency communication | There needs to be a system that allows laptop computers brought to an incident to be configured at the start of the season and allow them to be easily activated to the correct configuration when they arrive at the incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3472 | 26 - Research | That the Department of Sustainability and Environment and its partner agencies conduct or commission research, and a possible trial study, to determine the potential of thinning and other silvicultural practices – whether alone or in combination with prescribed burning – as a means of reducing fuel loads and as a bushfire management strategy in Victoria’s forests. |
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
REC155-3470 | 37 - Funding | That the Victorian Government provide recurring funding for a significant increase in regionally-based, permanent, or long-tenured, fire management personnel dedicated to the prescribed burning program. The increase in personnel should be consistent with the level required to achieve an annual prescribed burning target of 385,000 hectares. |
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
REC155-3469 | 37 - Funding | That the Victorian Government establish a five year rolling fund which allows unused prescribed burning monies to be rolled over into future financial years for the purpose of subsequent prescribed burning activities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1776 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to establish means by which risk of bushfires, as created by continuous cropping, minimum tillage, direct drilling seeding practices and the retention of cropping stubble across the landscape, can be minimised. |
REC153-1775 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to identify the effects of continuous cropping, minimum tillage, direct drilling seeding practices and of the retention of cropping stubble, in respect of bushfire risk and prevention. |
REC153-1777 | 5 - Hazard reduction burns | That the Minister for Emergency Services and the Minister for Local Government consider the enactment of legislation that would empower Local Government to require the owners or occupiers of rural land to create fire breaks on the land of a kind that Local Government may determine and/or to require the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3593 | 26 - Research | Analysing information from the joint CFA/DSE Post 2006 Wildfire Community Survey about public perceptions of information provision during January bushfires. Note implications for the VBIL and other information provision methods |
REC132-3597 | 15 - Inter-service cooperation | Investigate engaging with other agencies involved in emergency management including SES, VicRoads, VicPolice, OESC and DHS to establish a single united emergency information line for Victoria that can be used to provide information to the public from all agencies involved. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1954 | 15 - Inter-service cooperation | That senior officers of the Emergency Services Agency give greater recognition to the skills, knowledge and experience of people from other agencies – particularly the land management agencies – as well as rural residents and private individuals and use these people in roles commensurate with their skills and experience |
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-1961 | 7 - Inter-agency communication | That the Emergency Services Agency review the communications systems used by the four services (the ACT Ambulance Service, the ACT Rural Fire Service, the ACT State Emergency Service and the ACT Fire Brigade), by the Australian Federal Police, by NSW emergency services and by aircraft and ensure the systems are compatible |
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |
REC126-1981 | 15 - Inter-service cooperation | That senior officers in the Australian Federal Police and the Emergency Services Agency maintain regular and meaningful contact during fire emergencies, to ensure full dissemination of information and thus facilitate the making of good operational decisions |
REC126-1956 | 15 - Inter-service cooperation | That courses and programs be conducted to increase the level of Incident Control System training and augment the expertise of people who are likely to perform functions in an incident management team |
REC126-1987 | 7 - Inter-agency communication | That measures be taken to ensure that ACT and NSW Rural Fire Service radio communications systems are integrated, so that ACT and NSW firefighting units can communicate with each other |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3884 | 5 - Hazard reduction burns | Develop new prescriptions for prescribed burning to accommodate local conditions in those areas where standard prescriptions are assessed to be inappropriate: |
REC124-3889 | 15 - Inter-service cooperation | Develop a component of the DSE Workforce Strategy to build organisational capacity and sustainability of the prescribed burning program across the networked emergency organisation: |
REC124-3883 | 15 - Inter-service cooperation | Integrate information management systems relating to the prescribed burning program to provide consistency across the networked emergency organisation: |
REC124-3885 | 5 - Hazard reduction burns | Align policies and processes, within the year round 365 day focus on fire management, to provide consistency in the approach to fire regardless of its origins,- that is fuel reduction burning, regeneration and ecological burning or unplanned fire; |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3778 | 37 - Funding | The Committee recommends that government consider options for assistance (including cost sharing) for farmers to fence native vegetation areas on private property affected by the Wangary fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2283 | 15 - Inter-service cooperation | That DSE, CFA, MFESB and VICSES work cooperatively to establish a common system for resource tracking during major fires and incidents. |
REC104-2242 | 37 - Funding | That the financial arrangements incorporate full cost recovery for prescribed burning to be undertaken over a number of weekends utilising Project Firefighters, CFA volunteers and MFESB members. |
REC104-2318 | 37 - Funding | When the research into prescribed burning and optimum fire protection described in Chapter 11, and the financial analysis of appropriate funding levels for prevention and suppression recommended in Chapter 15, are completed, DSE should develop a business case with Department of Treasury and Finance for assured funding to an agreed level over a three-year rolling cycle. |
REC104-2266 | 15 - Inter-service cooperation | That DSE and CFA review their joint planning for Incident Control Centres to ensure that, wherever safe and practicable, those Centres are located close to the fire area. |
REC104-2274 | 7 - Inter-agency communication | That when Incident Management Teams implement significant changes to objectives and strategies, these are effectively communicated to firefighters, fire ground supervisors and affected communities, and are incorporated into the broader organisational planning. |
REC104-2241 | 37 - Funding | That the financial models incorporate changes in public land use, particularly ‘Our Forests Our Future’, and the subsequent changes in fire management priorities. |
REC104-2336 | 15 - Inter-service cooperation | That OESC work with the fire agencies in developing implementation strategies for recommendations agreed by Government. |
REC104-2308 | 37 - Funding | That Government funding for Community Development Officers engaged in community support and rebuilding incorporates flexible resources to enable the purchase of services from a range of providers to ensure choice for those requiring support. |
REC104-2265 | 15 - Inter-service cooperation | That in the review of Incident Control Centre locations, DSE and CFA give due consideration to: |
REC104-2240 | 37 - Funding | That Government supports the immediate development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2323 | 15 - Inter-service cooperation | That CFA, DSE, MFESB, VICSES, Victoria Police and OESC, in consultation with the Municipal Association of Victoria, consult on the proposal to combine Municipal Councils’ current responsibilities for the development of an emergency management plan/committee, as required by the Emergency Management Act 1986 and a fire prevention plan/committee as required by the Country Fire Authority Act 1958. |
REC104-2245 | 37 - Funding | That DSE includes the cost of tracks, as above, in the development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2238 | 15 - Inter-service cooperation | That the Victorian fire agencies negotiate with their counterparts in New South Wales and South Australia to put in place agreements for mutual aid and the development of cross border strategy for the management of fires burning in the vicinity of, or across, State borders, and these agreements are reviewed annually. |
REC104-2322 | 15 - Inter-service cooperation | That DSE commits appropriate resources to work with OESC in developing the bushfire component of the model. |
REC104-2244 | 37 - Funding | That DSE assesses the environmental and monetary cost of establishment and rehabilitation of temporary tracks, per 100 km, constructed during firefighting operations, and compare this with the recurrent costs of a program of maintaining existing tracks. |
REC104-2201 | 26 - Research | That DSE undertake a formal study of the level of prescribed burning in south western Australia for its possible application in Victoria by comparing respective fuel arrays, terrain, weather, ground access, staff, prescribed burning days, areas conducive to prescribed burning and fire response systems. |
REC104-2295 | 15 - Inter-service cooperation | That more emphasis should be given to communication and discussion in regard to State Aircraft Unit’s roles, responsibilities, practices and procedures. |
REC104-2243 | 37 - Funding | That Government reviews the funding for DSE for the 2004-2005 fire season to ensure that appropriate resources are available for fire prevention planning and preparedness. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2182 | 26 - Research | The Committee recommends that the Commonwealth Bushfire Cooperative Research Centre’s research and recommend property protection products and programs under Program D. |
REC098-2130 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre establish, as part of its program to implement a single fuel classification system, a national database that provides information on current levels and rates of accumulation of fuel loads that takes into account vegetation type and climate across all tenures of land, including private land where data is available. |
REC098-2144 | 26 - Research | The Committee acknowledges community concerns about smoke pollution as a result of prescribed burning and recommends that the Bushfire Cooperative Research Centre pursue its proposed study into smoke modelling. |
REC098-2180 | 26 - Research | The Committee recommends that (under Programs C and E) the Bushfire Cooperative Research Centre considers the following items as part of a national education program. |
REC098-2143 | 26 - Research | The Committee recommends that, as part of its study into improving the effectiveness of prescribed burning, the Bushfire Cooperative Research Centre establish a national database that includes areas targeted for fuel reduction, the area of fuel reduction achieved based on a specified standard of on ground verification and the season in which the reduction was achieved. The Committee also recommends that in developing this database the Cooperative Research Centre develop a national standard of fire mapping, which accurately maps the extent, intensity, spread and overall pattern of prescribed and wildfires in Australia. |
REC098-2179 | 26 - Research | The Committee recommends that Program D of the Commonwealth Bushfire Cooperative Research Centre examines the (pending) outcome of the ABCB’s review of the existing Building Code of Australia bushfire |
REC098-2165 | 7 - Inter-agency communication | The Committee recommends that Emergency Management Australia and the Australian Communications Authority work with state and territory bush fire authorities to ensure that that district communication plans |
REC098-2137 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre establish a minimum national standard that is common across all tenures of land for water access and availability for bushfire fighting. |
REC098-2147 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre conduct further research on the impact of weeds on the flammability of land and the most economically and environmentally appropriate way to remove weeds after fire events. |
REC098-2164 | 7 - Inter-agency communication | The Committee recommends that: |
REC098-2171 | 37 - Funding | The Committee strongly recommends that the New South Wales, Victorian and Tasmanian Governments abolish the Fire Levy tax they impose on home and business insurance premiums (wherever applicable), making it payable through household rates instead. Any cost savings gained by the insurance industry through relief from collecting Fire Levies should be passed on to policyholders through reduced premiums. At the same time the Committee urges the Insurance Council of Australia to run ongoing education campaigns to increase public awareness on bushfire preparedness, including the need for insurance. |
REC098-2134 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre determine a minimum national standard, taking into account topography and vegetation type, for adequate access to all public lands |
REC098-2146 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre conduct further research into the long term effects and effectiveness of grazing as a fire mitigation practice. |
REC098-2153 | 7 - Inter-agency communication | The Committee recommends that the state and territory bushfire agencies ensure that, on a district basis, communications are addressed within the district operations plans and that the plans are capable of easy adoption to incident action plans. |
REC098-2169 | 37 - Funding | The Committee recommends that, for the purpose of communications for the police, ambulance and fire brigades, any rental costs associated with the use of radio sites under the care, control or management of the Commonwealth, state, territory or local government be waived, other than for the ongoing cost associated with the use of power at the site. |
REC098-2188 | 26 - Research | The Committee recommends that Program E of the Bushfire Cooperative Centre, which is tasked with the development of the next generation of fire researchers and dissemination of the Centre’s work, be tasked further to collect and respond to feedback, particularly from the on ground volunteer levels of fire brigades, on the practicality of its outputs and their future requirements. |
REC098-2132 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre establish, as part of its program to implement a single fuel classification system, standards which take into account local conditions including topography and vegetation type, for determining appropriate dimensions for asset protection zones. |
REC098-2145 | 26 - Research | The Committee recommends that the Bushfire Cooperative Research Centre monitor the effect of grazing on mitigating the return of woody weeds to recently fire effected areas across various landscapes including |
REC098-2142 | 5 - Hazard reduction burns | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek agreement from the states and territories on the optimisation and implementation of prescribed burning targets and programs to a degree that is recognised as adequate for the protection of life, property and the environment. The prescribed burning programs should include strategic evaluation of fuel management at the regional level and the results of annual fuel management in each state should be publicly reported and audited. |
REC098-2158 | 37 - Funding | The Committee recommends that the Commonwealth should commit funding for aerial fire fighting beyond the 2003–04 season on the proviso that the Australasian Fire Authorities Council and the state and territory governments make a commitment to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4157 | 18 - Access to fire ground | Local authorities and if necessary the Minister take active steps to enforce the removal of fire hazards from the vicinity of buildings in rural areas and that special attention be given to the removal of dead trees on the edges of pasture land and on firebreaks in timbered country. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
REC019-4156 | 26 - Research | A fire control research advisory committee be formed to co-operate with the Forests Department in carrying out scientific research into fire control. |
REC019-4151 | 26 - Research | The Forests Department carry out more research into both the technical and practical side of fire control as a necessary accompaniment to the expenditure of money on other forest works and that forest fire control officers be sent overseas at intervals to gain information regarding the latest developments in this work. |
REC019-4145 | 37 - Funding | A fund be established to subsidise the purchase of equipment for bush fire brigades but that the granting of subsidies depend upon a certificate being received from the Bush Fires Board that the brigade in question is of a standard that will be available at all times for effective use and that adequate facilities are available for its storage and maintenance at a centre suitable for the brigade. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3953 | 15 - Inter-service cooperation | It is therefore recommended that the State Electricity Commission should be advised by someone whose profession it is to consider and devise methods of forest fire protection and suppression; that he should collaborate with others to devise a general scheme of organized protection of the undertaking and township of Yallourn; and that above all, he should have direct access to the Commissioners themselves, lest his advice should lose something of its strength and reality in its journey through the “proper channels” of the Commission’s organization. |
REC016_3947 | 15 - Inter-service cooperation | It is recommended that the services of this body [Air Raids Precautions Body] be used in future if to do so be thought desirable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3959 | 37 - Funding | It is recommended that an annual grant be made to the Association for distribution among the brigades for the purposes of purchase of equipment of which the brigades are in urgent need. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3975 | 5 - Hazard reduction burns | To burn, where necessary, at least 33 feet where there is a risk of fire, on the outside of the railway fence, in conjunction with the railway employees. |