REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4275 | 34 - Local knowledge | That the NSW Government, in partnership with community groups, including First Nations groups, develop initiatives to build community resilience, particularly in regions at high risk of future natural disaster events. |
REC323-4276 | 34 - Local knowledge | That the NSW Government ensure that community groups, both existing and emerging, including First Nations groups, are well integrated into disaster recovery, by incorporating them into state recovery plans and engaging with them in between and in the lead up to natural disasters. |
REC323-4287 | 34 - Local knowledge | That the NSW State Emergency Service, in partnership with the Bureau of Meteorology, investigate ways in which local communities and local media with local knowledge can play a stronger role in flood predictions and warnings. |
REC323-4264 | 34 - Local knowledge | That the NSW Government work in partnership with key Aboriginal stakeholders, including the Jali Local Aboriginal Land Council, to prioritise the rebuild of Cabbage Tree Island, and ensure a safe and resourced evacuation plan is in place. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
REC323-4265 | 34 - Local knowledge | That the NSW Government work with First Nations peoples to support Aboriginal organisations in their capacity to operate and respond in times of natural disasters. |
REC323-4282 | 16 - Training and behaviour | That the NSW Government invest in the required personnel, training and vessels to ensure that all agencies involved in flood rescue can be mobilised to their fullest potential. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3807 | 16 - Training and behaviour | That, in order to expand NSW’s specialist aviation personnel safety and capacity, Government expand simulator capabilities at the NSW RFS Training Academy. |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3803 | 16 - Training and behaviour | That Government support training initiatives to increase the capacity of fire authorities to fight the kind of megafires seen in the 2019-20 season. The training initiatives should include: |
REC315-3855 | 7 - Inter-agency communication | That, in order to ensure all agencies have a clear understanding of cross-border communication channels during bush fires, all MoUs between state or territory agencies include an agreed protocol about how agencies will communicate across borders and that these are reflected in Incident Action Plans. |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3854 | 7 - Inter-agency communication | That, in order to ensure emergency response agencies can communicate across state and territory borders, the Commonwealth Government allocate 10 + 10 MHz as a dedicated spectrum for Public Safety Mobile Broadband (PSMB) at no cost to states and territories. |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3853 | 7 - Inter-agency communication | That, in order to ensure the State Emergency Operations Centre (SEOC) can maintain communications during emergencies, the Government provide the SEOC with independent Public Safety Network functionality. |
REC315-3861 | 16 - Training and behaviour | That, in order to expand the pool of trained personnel able to undertake the Public Information Functional Area Coordinator (PIFAC) role, Resilience NSW and the NSW Police Media Unit (PIFAC) develop and deliver a training package for Emergency Management Media Liaison Officers. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3852 | 7 - Inter-agency communication | That, in order to improve fireground communications between NSW agencies and interstate personnel: a) Government ensure all NSW fire authority personnel and vehicles can access and utilise the Public Safety Network (PSN). This should include access to NSW RFS Private Mobile Radio networks where PSN coverage is not yet available. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3267 | 16 - Training and behaviour | Invest in fireground leadership and incident management training for CFS, SES and MFS personnel to improve safety on the fireground. Invest in greater technological interoperability such as AVL, Thermal Imagery, Burnover Protection Systems (BOPS), lightning tracking and appropriate vehicle fleets for bushfire conditions including at the peri-urban interface. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2514 | 16 - Training and behaviour | Upskilling IT resources through disaster recovery testing or formal training. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4009 | 16 - Training and behaviour | In gassy mines the Manager should be specially competent, and one possessing a thorough knowledge of the principles and practice of mining, the properties of gases, and systems of ventilation; and, above all, he must be prudent and cautious, yet resolute, possessing sound judgement. He must have absolute and supreme control over the whole operations, and of the men within the mine, to maintain rigid discipline, and be perfectly free and untrammelled by any outside influences. The competency of a manager should be certified by an examination before a specially-appointed Board. The Commission consider that better results may be obtained if such examinations be oral, and probably assume a more practical form than those hitherto conducted in Great Britain for the same object. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1303 | 16 - Training and behaviour | That the State Emergency Service be provided with resources to enable them to deliver swiftwater awareness training to all first responders including emergency services, SA Police and council crews. |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1284 | 16 - Training and behaviour | Deliver consistent and regular training in the use of the SA Government Radio Network to all users to maximise the efficiency and effectiveness of the network in times of emergency e.g. reduce the issues associated with network busy signals. |
REC295-1324 | 16 - Training and behaviour | Establish a State incident management and emergency management training capability which provides for: a) consistent training across the State b) personal development and endorsement processes for roles c) identification, recruitment and development of personnel from other government agencies; and d) incident management and State emergency centre functional role training and development across all sectors. e) skills maintenance including upskills, refresher training and exercises f)incident and strategic leadership training g) consistent training for inter-agency liaison officers at all levels |
REC295-1321 | 16 - Training and behaviour | Through the Emergency Management Workforce Project, identify and provide training and development for SA’s emergency management sector personnel (government agencies, and non-government agencies including volunteers). State Emergency Management Committee should consider supporting recommendations from stage two of the project when the project report is tabled. |
REC295-1313 | 16 - Training and behaviour | That regular training and exercising is conducted for all State Emergency Centre participants including Liaison Officers. |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2366 | 16 - Training and behaviour | I recommend that the New South Wales Police Force review the training provided to officers in relation to DA planning and approval. |
REC292-2358 | 16 - Training and behaviour | I recommend that the New South Wales Police Force develop a cadre of counterterrorist negotiators and provide them with appropriate training to equip them to respond to a terrorist siege. |
REC292-2352 | 16 - Training and behaviour | The New South Wales Police Force should consider drawing on international experience when reviewing its negotiator training |
REC292-2351 | 16 - Training and behaviour | The sections above dealing with negotiators’ attempts to engage with Monis, their responses to his demands, and their assessment of progress demonstrate deficiencies in current practice. To respond to those deficiencies, I recommend that the New South Wales Police Force conduct a general review of the training afforded to negotiators and the means by which they are assessed and accredited. Specifically, the review should consider the training provided regarding: measuring progress in negotiations; recording of information, including the systems by which that occurs; the use of third-party intermediaries; additional approaches to securing direct contact with a person of interest; and handovers. |
REC292-2337 | 16 - Training and behaviour | I recommend that the Director of Public Prosecutions initiate reviews of the training in file management given to lawyers employed by the Office of the Director of Public Prosecutions to ensure important original documents are not discarded and that the files accurately reflect relevant events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1218 | 7 - Inter-agency communication | Cross-agency resource management system |
REC290-1213 | 34 - Local knowledge | Structures to incorporate local knowledge and situational awareness into the fire response |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1205 | 16 - Training and behaviour | Department of Premier and Cabinet Regional Coordinators: Continue to build the capability of the Department of Premier and Cabinet Regional Coordinator role in recovery operations by providing: · on the ground support for Regional Coordinators during recovery operations by REMOs or OEM Recovery Team · training and developmental opportunities for Regional Coordinators to prepare them for working in the disaster recovery environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC279-1232 | 16 - Training and behaviour | Volunteer Charter: by December 2014, agree a charter with volunteers that clarifies roles and expectations including commitments by: a) SES to support volunteers to prepare for and respond to emergencies b) SES to make the best use of volunteers’ time by introducing user-friendly systems and reducing the administrative burden on them c) volunteers to turn-out when called to respond to emergencies. |
REC279-1231 | 16 - Training and behaviour | Training Strategy: By April 2015, develop a training strategy that identifies volunteer training priorities and provides for ongoing review to ensure operational currency, flexibility of delivery and evaluation |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1166 | 7 - Inter-agency communication | Develop an integrated inter-agency resource management system: Large and complex fire incidents require resources from multiple agencies. Developing an integrated inter-agency resource management system will have three main benefits: identifying potential resources will be more straightforward • the status and location of resource deployments can be tracked • planning of deployments can take into account all relevant information |
Rec-ID | Code | Recommendation |
---|---|---|
REC276-1178 | 16 - Training and behaviour | Within six months, consider improved processes for consulting with and engaging volunteers and continue to work with LGs to improve information sharing and communication. Specifically, DFES should improve communication around its decisions on equipment and training as well as provide better information about access to services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1144 | 7 - Inter-agency communication | That SACFS consider a review to develop an effective interagency messaging system and agency resource management system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1115 | 16 - Training and behaviour | Training and awareness raising should be conducted to enhance the appreciation and understanding of DFES State and Regional operational personnel, including potential Incident Management Team members, of the nationally adopted Bushfire Alert and Messaging Matrix, in order to ensure that the most appropriate alert levels and associated community messaging are applied during bushfire incidents. |
REC265-1103 | 16 - Training and behaviour | DFES should review its training courses and Standard Operating Procedures to satisfy itself that all incident management personnel have the required level of understanding of WA emergency management arrangements, including those that relate to the roles of the Incident Management Team and Incident Support Group and the declaration of incident levels. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC261-1509 | 34 - Local knowledge | That the NSW Rural Fire Service, in order to ensure greater respect for volunteer fire fighters’ knowledge and experience in the management of fires: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1068 | 16 - Training and behaviour | That the National Park and Wildlife Service review its fire weather training regime and consider adopting or adapting the fire weather training courses introduced in Victoria following the 2009 bushfire disaster. |
REC260-1062 | 16 - Training and behaviour | That the National Parks and Wildlife Service consider incorporating “worst-case scenario” training, as proposed in Mr Conway’s report, in its suite of fire-fighting protocols, exercises and training packages for senior incident controllers and other senior managers. |
REC260-1060 | 7 - Inter-agency communication | That the Rural Fire Service and National Parks and Wildlife Service review the procedures for requesting aerial support in ‘severe’ or worse fire conditions to ensure that delays in providing it are reduced to the minimum time possible. |
REC260-1055 | 34 - Local knowledge | That the Rural Fire Service together with other land managers develop a program whereby local stakeholders come together regularly (every 2 months during non-fire season and monthly during the fire season) to share intelligence and to consider hazard and incident management measures for implementation. |
REC260-1057 | 16 - Training and behaviour | That the Rural Fire Service and National Parks and Wildlife Service introduce training, exercises or information packages, or other suitable forms of professional development, for operational fire fighters and analysts concerning the potential effects of atmospheric instability and vorticity-driven lateral spread on fire behaviours in severe-catastrophic fire danger conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1583 | 16 - Training and behaviour | Once Recommendation 1 has been actioned, all agencies give greater priority to the promulgation of Red Flag warnings in order to enhance situational awareness on the fireground. |
REC254-1581 | 16 - Training and behaviour | All agencies ensure fire managers are trained to correctly interpret the new Spot Fire Weather Forecast and to familiarise themselves with the entire format – ensuring consideration of the whole forecast - not just the tabular data containing the 12 hour forecast. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0577 | 7 - Inter-agency communication | A system of vehicle tracking should be fitted to all fire appliances and linked to the common operating picture. Good communications planning is essential for good command and control. |
REC226-0561 | 34 - Local knowledge | Suitably experienced local representatives should be engaged to provide advice to the IMT in all Level 2 and Level 3 incidents at the earliest opportunity. |
REC226-0552 | 7 - Inter-agency communication | Communications planning for geographic regions with recognised black spots and specific communications challenges should be prepared in advance of an emergency in order to support the IMT Communications Planning Officer |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0532 | 16 - Training and behaviour | All agencies ensure fire managers are trained to correctly interpret the new Spot Fire Weather Forecast and to familiarise themselves with the entire format – ensuring consideration of the whole forecast - not just the tabular data containing the 12 hour forecast. |
REC225-0537 | 7 - Inter-agency communication | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0519 | 34 - Local knowledge | The Department of Environment and Conservation review its practices and procedures in the undertaking of prescribed burns so as to fully utilise the skills available to it in a seamless way including but not limited to: · volunteer bushfire brigades, especially in regard to use as a source of local advice; and · staff of the Fire and Emergency Services Authority of Western Australia. |
REC223-0518 | 16 - Training and behaviour | The Department of Environment and Conservation explore human resourcing models that: · make succession planning a priority; · look at options for the attraction and retention of staff; and · review how the salary levels of staff matches the decision making required in major activities such as prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1867 | 16 - Training and behaviour | The Minister for Emergency Services ensure that the Fire and Emergency Services Authority’s peer support program is rejuvenated as soon as possible with increased funding to provided added training for staff volunteering for this program |
REC222-1865 | 16 - Training and behaviour | The Minister for Police immediately instigate processes to ensure that the psychological well-being of officers is at the forefront of the Western Australia Police’s staff planning. These processes should include all officers being trained in psychological first aid, with subsequent regular refresher courses. Senior officers should be the first priority for psychological first aid training. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0293 | 34 - Local knowledge | Suitably experienced personnel with local knowledge should be connected to the Operations and Planning section in all Level 3 incidents in the vicinity of substantial settlements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0494 | 16 - Training and behaviour | The Minister for Emergency Services introduce by the 2012-13 bushfire season psychological testing of all FESA career staff and bushfire and rescue volunteers. |
REC202-0505 | 7 - Inter-agency communication | The Minister for Emergency Services makes it a priority that the annual budgets of FESA and WA Police are sufficient to bring forward the completion dates of the current radio projects now underway. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0252 | 7 - Inter-agency communication | FESA must actively manage the transition to WAERN and provide alternative means for regional crews to communicate when in areas where WAERN is not operated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-0372 | 7 - Inter-agency communication | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-1713 | 7 - Inter-agency communication | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-1731 | 16 - Training and behaviour | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. |
REC200-0390 | 16 - Training and behaviour | The Fire and Emergency Services Authority and local governments examine the current competencies of Chief Bushfire Control Officers and Community Emergency Services Managers (or Community Fire Managers) and consider what further development is needed to ensure these staff are capable of: measuring and mapping fuel loads maintaining fuel load databases drawing up prescriptions for, and overseeing controlled burns building effective working relationships with all relevant stakeholders. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-1730 | 16 - Training and behaviour | The Fire and Emergency Services Authority and local governments examine the current competencies of Chief Bushfire Control Officers and Community Emergency Services Managers (or Community Fire Managers) and consider what further development is needed to ensure these staff are capable of: |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0110 | 16 - Training and behaviour | DEC should emphasise the principle of foresight by adopting an appreciation and decision making process and training staff in that process. |
REC183-0122 | 16 - Training and behaviour | A staff recognition and reward framework for service to fire management should be considered for DEC fire staff. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0043 | 7 - Inter-agency communication | There needs to be a system that allows laptop computers brought to an incident to be configured at the start of the season and allow them to be easily activated to the correct configuration when they arrive at the incident. |
REC172-0038 | 34 - Local knowledge | The ISU should be provided with a person with local knowledge at Level 3 incidents. |
REC172-0041 | 16 - Training and behaviour | Media liaison personnel are needed to ‘ride’ shotgun’ on media personnel to facilitate them getting their stories without imposing on the effectiveness of operations. |
REC172-0042 | 7 - Inter-agency communication | Portable, reliable mobile repeaters are required to provide radio communications into areas not covered by existing repeater networks. These repeaters need the capacity to be linked. |
REC172-0031 | 16 - Training and behaviour | Pre-season refresher training to include an emphasis on check in/out procedures |
REC172-0023 | 16 - Training and behaviour | Pre-season multi- agency refresher training for Ground Controllers should be undertaken each year. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0057 | 7 - Inter-agency communication | SEMC and EM WA should: ensure that agencies have a common or compatible crisis information management system in place |
REC170-0065 | 16 - Training and behaviour | Agencies should: train their staff who will be involved in emergencies in incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0075 | 16 - Training and behaviour | SERCon consider development of an education program for other government and non-government agencies (with |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1794 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of all Incident Management Team members, in particular but not limited to the Incident Controller and Planning Officer, of the need to conduct a full risk assessment that not only addresses operational risk, but the risk posed to the general public by an existing incident and at all times to consider and identify the ‘worst case scenario’ outcome. |
REC153-1793 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of those Officers who perform the role of Regional Duty Officer the need to deliver to the Deputy State Coordinator timely, accurate and relevant information pertaining to an ongoing fire incident. |
REC153-1798 | 16 - Training and behaviour | That the South Australian Country Fire Service design tuition courses aimed specifically at developing among its members skill and competency in identifying and implementing feasible and appropriate containment measures designed to bring control to a fire incident so as to minimise the risk posed to the general public. |
REC153-1792 | 16 - Training and behaviour | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service reinforce in the minds of those Officers who perform the role of Regional Duty Officer the duties and responsibilities attaching to that position insofar as they apply to an ongoing fire incident, and in particular to recognise the need to conduct a risk assessment in relation to an incident and the need to scrutinise, evaluate and validate the strategies and Incident Action Plans of Incident Management Teams. |
REC153-1797 | 16 - Training and behaviour | That the South Australian Country Fire Service develop as part of competency for inclusion on a Level 2 or Level 3 Incident Management Team a minimum requirement of demonstrated skill and competency in identifying and implementing feasible and appropriate containment measures designed to bring control to a fire incident so as to minimise the risk posed to the general public. |
REC153-1796 | 16 - Training and behaviour | That the South Australian Country Fire Service design tuition courses aimed specifically at developing among its members skill and competency in risk assessment. |
REC153-1795 | 16 - Training and behaviour | That the South Australian Country Fire Service develop as part of competency for inclusion on a Level 2 or Level 3 Incident Management Team a minimum requirement of demonstrated skill and competency in risk assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3600 | 34 - Local knowledge | The Department of Primary Industries continue to consult local community about emergency planning and sites for disposal to retain confidence in the event of a genuine emergency. |
REC128-3609 | 16 - Training and behaviour | That the Department of Primary Industries be conscious of its responsibilities in maintaining the continued enthusiasm of Industry Liaison Officers and offer training and refresher training as required. |
REC128-3608 | 16 - Training and behaviour | That emergency animal health training be included in induction programs for newly recruited District Veterinarians and all District Veterinarians be encouraged to maintain their skills by attending regular refresher training as appropriate. |
REC128-3607 | 16 - Training and behaviour | That the Department of Primary Industries should continue efforts to develop the skills of private sector veterinarians to increase the level of resources available in emergency responses. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3791 | 16 - Training and behaviour | The Committee recommends that training be provided to landholders to enable them to assist with prescribed burns. |
REC122-3784 | 34 - Local knowledge | The Committee recommends that the government provide authority to a single community representative body to authorise clearing of native vegetation for fire management. (The community representative body must incorporate the CFS, DEH, Native Vegetation Council and local council) |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3650 | 16 - Training and behaviour | Staff at the Rail Management Centre (RMC) should receive training from RailCorp to enable them to quickly and accurately assess that an emergency has occurred and to provide precise and reliable information to emergency response personnel about the location of the emergency, the available access to the site and the resources necessary. |
REC121-3751 | 16 - Training and behaviour | RailCorp should make it a condition of employment that all level 2 managers have or obtain a formal qualification in system safety management. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3672 | 16 - Training and behaviour | All emergency response personnel should be specifically trained in the features of railways which are relevant to their work, such as the location and means of operation of all emergency door releases on trains, the location and use of signal telephones, the methods by which electrical power can be isolated and the means by which they can readily identify and obtain information from the on-site rail commander. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3716 | 16 - Training and behaviour | Train driver and guard training should encourage teamwork and discourage authority gradients. |
REC121-3746 | 16 - Training and behaviour | All emergency services personnel should be trained in the location and operation of emergency door release mechanisms on all rail cars. |
REC121-3670 | 16 - Training and behaviour | The RailCorp emergency response plan should be provided to all emergency response agencies. The officers of each emergency service should be trained in any rail specific features of the plan, so as to better ensure inter-agency co-ordination in the circumstances of an emergency. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3715 | 16 - Training and behaviour | RailCorp should use its simulators to train drivers and guards in methods of dealing with degraded operations on the rail network. |
REC121-3744 | 16 - Training and behaviour | All RailCorp operational personnel should be trained in the location and operation of external emergency door release mechanisms. |
REC121-3669 | 16 - Training and behaviour | All operational rail staff should be trained by RailCorp in the action check list relevant to each. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3714 | 16 - Training and behaviour | RailCorp should use its simulators in an interactive manner. |
REC121-3719 | 16 - Training and behaviour | The position of team leader should be created by RailCorp to be responsible for a group of approximately 30 train drivers, with responsibility to ensure that each train driver’s training needs are being met and that any safety concerns of train drivers are being properly addressed. The team leaders are to have direct access to the Chief Executive of RailCorp if any safety concerns they have are not addressed. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3677 | 16 - Training and behaviour | A training centre for emergency services personnel should be established by RailCorp. The emergency services personnel should be required to undertake training at such a centre, which should be equipped with features replicating railway infrastructure and rolling stock. |
REC121-3718 | 16 - Training and behaviour | Training should be based upon a needs analysis, to determine what skills a particular person will require to carry out the tasks of any position safely and efficiently, and instruction and practice, to acquire and demonstrate those skills. |
REC121-3654 | 16 - Training and behaviour | All train guards should be trained by RailCorp in the use of the Metronet radio and instructed to use it in any emergency. |
REC121-3756 | 16 - Training and behaviour | RailCorp should ensure that where the safety competency of any manager is deficient such manager is required to undertake professional development courses to raise his or her safety competency level to an adequate standard. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3675 | 16 - Training and behaviour | All rail employees should be trained by their employer to commence any emergency communication with the words “Emergency, emergency, emergency”, thereafter to identify themselves, the train, its location, what has occurred, the approximate passenger load and whether death or injuries have occurred. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3717 | 16 - Training and behaviour | RailCorp must establish a task analysis for particular categories of employees, to identify the specific skills and responsibility of those employees or groups of employees, and thereafter undertake a training needs analysis, to develop the skills required in particular areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
REC113-3905 | 16 - Training and behaviour | Firefighting organisations should: address their key training and development issues |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4158 | 16 - Training and behaviour | That needs in the direction of a fire emergency service be met as far as practicable by the Bush Fires Board in its training programme and in the tactical organisation of existing brigades for use as reserves in districts other than their own. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4144 | 16 - Training and behaviour | No opportunity be lost of encouraging the formation of bush fire brigades and the maintenance of enthusiasm and that the Bush Fires Board assist the brigades in any way possible to obtain adequate training and equipment. |
REC019-4136 | 34 - Local knowledge | The Bush Fires Board appoint a Regional Committee of Board members co-opt local members for each climatic region of the State to study the bush fire control problems of the region and advise the Board so that inter alia adequate attention may be given by the Board to co-ordinating the beginning and termination of the prohibited burning times in adjoining districts and to any advisable variations of these duties according to seasonal conditions each year. |