Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4232 | 11 - Evacuation and shelters | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to plan for the evacuation of K’gari due to bushfire. Once developed, the plan should be exercised and regularly reviewed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4190 | 11 - Evacuation and shelters | Humanitarian relief: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions work with the Municipal Association of Victoria and councils to build contingencies into emergency relief centre planning to ensure places of shelter are inclusive, recognise diversity and are better placed to support all displaced people in circumstances of: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4180 | 11 - Evacuation and shelters | The Inspector-General for Emergency Management recommends that Victoria Police – in collaboration with the community and the emergency management sector – reflect on events of the 2019–20 fire season to review and enhance evacuation plans and processes with consideration of: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4089 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4093 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review those plans, and update where appropriate, to provide for coordination between states and territories in cross border areas and to provide cross-border access to evacuation centres. |
REC317-4088 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4092 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review these plans, and update them where appropriate, to account for the existence and standard of any evacuation centres and safer places (however described) in the community, including: |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4091 | 11 - Evacuation and shelters | State and territory governments should provide further community education on the function and limitations of different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. This education should be nationally consistent. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4090 | 11 - Evacuation and shelters | State and territory governments should, as a priority, adopt nationally consistent terminology and functions for the different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. |
REC317-4063 | 23 - Climate Change | Australian, state and territory governments should produce downscaled climate |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4044 | 11 - Evacuation and shelters | A Relocation and Evacuation working group be established from stakeholder organisations to consider and develop an Evacuation and Relocations Sub- Plan. The Sub-Plan should consider the lessons learned this year and address principles, lead agency, WHoG coordination, trigger points etc. This could be the same working group formed for reviewing the Emergencies Act, Plan and sub-plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3814 | 11 - Evacuation and shelters | That the NSW RFS identifies remote bush fire prone areas that do not already have an indoor Neighbourhood Safer Place (NSP) and upgrades the relevant NSW RFS Stations to meet NSP guidelines. These stations would require adequate Asset Protection Zones and active/passive protection systems to provide short-term protection. |
REC315-3872 | 11 - Evacuation and shelters | That, in order to improve support for people evacuating with animals, the Department of Primary Industries: |
REC315-3871 | 11 - Evacuation and shelters | That, in order to ensure equitable access to evacuation centres and associated support services for people in border communities, Resilience NSW ensure cross-border access arrangements are reflected in evacuation centre management guidelines. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3870 | 11 - Evacuation and shelters | That, in order to ensure the safety and wellbeing of vulnerable people during an evacuation, Resilience NSW: |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3867 | 11 - Evacuation and shelters | That, in order to ensure evacuation centres are fit-for-purpose, Resilience NSW work with Local Emergency Management Committees (LEMCs) to: a) update the guidelines for LEMCs identifying evacuation centres to require a risk assessment of potential locations, which should include identifying alternate sources of power for use by evacuation centres and recording these appropriately |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3866 | 11 - Evacuation and shelters | That, in order to ensure evacuation arrangements can be scaled up when needed, Resilience NSW: |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1244 | 11 - Evacuation and shelters | The Department of Fire and Emergency Services to work with the Department of Planning and Local Governments to adopt a policy which enables Local Governments to identify, register and communicate, ‘Places of Bushfire Last Resort’ in settlements and townsites where the life risk from bushfire is very high or greater. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1472 | 11 - Evacuation and shelters | Develop flood evacuation plans for at risk communities. |
REC286-1454 | 11 - Evacuation and shelters | Review coastal inundation evacuation and response plans. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2026 | 11 - Evacuation and shelters | Identify facilities that can be used as cool spaces during heatwaves and establish linkages between operators and emergency management organisations |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0889 | 11 - Evacuation and shelters | That Tasmania Police be identified as the lead agency on evacuations. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0888 | 11 - Evacuation and shelters | That arrangements are made and appropriate pre-planning occurs to effectively implement the policy on evacuation. |
REC247-0887 | 11 - Evacuation and shelters | That qualifying the evacuation authority in section 47 of the Fire Service Act 1979 be considered — by exempting those people with a pecuniary interest in a property from a directed evacuation where it is reasonable for them to remain. |
REC247-0886 | 11 - Evacuation and shelters | That a state-level policy on evacuations be developed in the emergency management plans, including specific requirements for vulnerable people and guidelines for its implementation. |
REC247-0901 | 11 - Evacuation and shelters | That evacuation centres and other centres have plans and arrangements for electrical power redundancy. |
REC247-0890 | 11 - Evacuation and shelters | That decisions to open Community Fire Refuges and evacuation centres be coordinated with Tasmania Police. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0592 | 11 - Evacuation and shelters | Decisions on evacuations need to be made early enough for people to be fully informed, prepared and to move to a place of greater safety. Failure to conduct good planning can create situations where loss of life can occur |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0307 | 11 - Evacuation and shelters | When people are being moved away from their homes it’s important that they move to a place of greater safety and that their movement is relatively assured. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0259 | 11 - Evacuation and shelters | FESA seek legal and policing advice regarding the policy to leave residents who chose not to evacuate in a declared ‗dangerous area‘ after a bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0374 | 11 - Evacuation and shelters | Hazard Management Agencies overseeing the response to incidents on the urban fringe select evacuation centres that are well within the urban environment and unlikely to be impacted by the incident. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-1714 | 11 - Evacuation and shelters | Hazard Management Agencies overseeing the response to incidents on the urban fringe select evacuation centres that are well within the urban environment and unlikely to be impacted by the incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0095 | 11 - Evacuation and shelters | Planning and consultation be undertaken by EMQ with all levels of the Disaster Management system to ensure that necessary risk-based disaster evacuation plans are prepared at Local, District and State levels, supported by necessary community education and preparedness programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2251 | 11 - Evacuation and shelters | That Victoria Police ensure all police members understand the Victorian legislation in relation to evacuation, and that any decision to recommend evacuation remains with the Incident Controller. |
REC104-2203 | 11 - Evacuation and shelters | That CFA further develops the information supporting the decision to stay or go, to incorporate a better understanding of both the likely consequences of leaving home at inappropriate times, and the conditions and |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2181 | 11 - Evacuation and shelters | The Committee recommends that the Australasian Fire Authorities Council’s suggested evacuation protocol be adopted by all of the Australian States and Territories. |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |