Rec-ID | Code | Recommendation |
---|---|---|
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4316 | 12 - EM agency and authority | Resilience NSW and recovery: That, in order to enhance NSW disaster preparedness, response and recovery, and meet the needs of the people of NSW prior to, during and after a disaster, and provide clarity on agency roles and responsibilities, Resilience NSW be reshaped to ‘Recovery NSW’. The new agency will be more streamlined and agile to drive recovery in the first 100 days post disaster. To achieve this, Resilience NSW’s functions should be reallocated as follows: |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4318 | 12 - EM agency and authority | Permanent SEOCON: That, to improve NSW’s ability to prepare and respond to floods and other disasters, Government establish a new Deputy Commissioner of NSW Police Force to take on permanently the SEOCON role. This role, in addition to current SEOCON functions, would be responsible for: |
REC324-4320 | 12 - EM agency and authority | Knowledge resources to support flood management: That, to provide more accurate and complete data for flood threat identification, warning and modelling systems, Government through the proposed new NSW Reconstruction Authority (NSWRA) work with the Australian Government to: |
REC324-4309 | 12 - EM agency and authority | SES and RFS back-office merger: That, to help protect life and property across NSW in storm and flood events, and to improve resourcing and NSW State Emergency Service (SES) frontline capability, Government implement, before the next storm season, a merger of the SES and NSW Rural Fire Services (RFS) back-office and corporate service functions, while maintaining their separate legislative identity, brand, uniform and volunteer membership. This ‘joined-up’ RFS/SES corporate support structure would be under the command of the RFS given its corporate and operational maturity and would be responsible for: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4291 | 12 - EM agency and authority | That the NSW Government consider abolishing Resilience NSW if it is unable to ensure: |
REC323-4292 | 12 - EM agency and authority | That the NSW Government consider a restructure of the NSW State Emergency Service with consideration to: realigning the focus of the organisation to harness local knowledge and networks; coordinating more closely with other rescue agencies to bolster its capacity to respond; and increasing salaried staff and resources, and driving volunteer recruitment. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4222 | 4 - Fire season preparation | The Inspector-General Emergency Management recommends the Department of Environment and Science undertake a review of campfire locations on K’gari, including all relevant signage on and off the island, maps and visitor permit information, to promote a consistent message about lighting campfires on K’gari. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4204 | 4 - Fire season preparation | We recommend that DEWLP and CFA (in consultation with FRV) in partnership with councils, provide advice to government in line with the Safer Together: A new approach to reducing the risk of bushfire in Victoria policy on options to better resource the assessment of risk on private land, its treatment and activities to enforce compliance of land owners with risk-reduction treatments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4188 | 12 - EM agency and authority | Recovery governance: The Inspector-General for Emergency Management recommends that the Victorian Government establish a permanent and comprehensive entity dedicated to recovery management with the authority, capability, capacity and resourcing to coordinate the planning and delivery of recovery functions for all emergencies. |
REC319-4191 | 12 - EM agency and authority | Relief governance: The Inspector General for Emergency Management recommends that Emergency Management Victoria lead the development of relief arrangements to achieve greater clarity of roles, reporting and accountability in relief across state, regional and incident tiers. These arrangements should: |
REC319-4192 | 12 - EM agency and authority | Relief governance: The Inspector-General for Emergency Management recommends that the Emergency Management Commissioner strengthen the State Emergency Management Plan and supporting operational arrangements in accordance with his legislative obligations to ensure the roles and responsibilities of the State Emergency Relief Coordinator and the State Relief and Recovery Team are clear. These documents should enable: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4175 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – supported by other organisations with a legislated responsibility for fuel management – plan for and increase the application of non-burning fuel management treatments including mechanical means. The annual fuel management report should include the non-burn component of fuel management treatment, track annual change, and provide a comparison to the previous three years. |
REC318-4170 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that responder agencies and Emergency Management Victoria review preparedness arrangements to ensure procedural documentation (including plans), recruitment, briefings and training are completed before significant seasonal events are likely to occur. Seasonal preparedness should culminate in attestations of assurance to confirm that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4066 | 2 - Emergency powers | The Australian Government should make provision, in legislation, for a declaration of a state of national emergency. The declaration should include the following components: |
REC317-4087 | 4 - Fire season preparation | State and territory governments, working with local governments and fire and emergency service agencies, should ensure that there are appropriate arrangements for roadside vegetation management that take into account, among other things: |
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
REC317-4076 | 12 - EM agency and authority | Australian, state and territory governments should develop an Australian-based and registered national aerial firefighting capability, to be tasked according to greatest national need. This capability should include: |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
REC317-4130 | 21 - Role of Commonwealth Government | The Australian Government should establish accountability and assurance mechanisms to promote continuous improvement and best practice in natural disaster arrangements. |
REC317-4108 | 4 - Fire season preparation | Australian, state and territory governments should review the assessment and approval processes relating to vegetation management, bushfire mitigation and hazard reduction to: |
REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
REC317-4107 | 4 - Fire season preparation | Public land managers should clearly convey and make available to the public their fuel load management strategies, including the rationale behind them, as well as report annually on the implementation and outcomes of those strategies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4027 | 12 - EM agency and authority | All organisations who have a role in the ECC should review their existing arrangements to ensure there is a sufficient cohort of staff to maintain a presence in the ECC at a level and with an imprimatur sufficient to make decisions and allocate resources and have access to senior executive levels if needed. |
REC316-4026 | 12 - EM agency and authority | The role, level, requirements and expectations of an ECC LO be clarified in the Emergency Plan and ECC Ops Sub-plan. |
REC316-4022 | 12 - EM agency and authority | That when determining their Management Executive, at a minimum the EC should consider appointing Director-General JACS and the PIC as standing members. |
REC316-4039 | 12 - EM agency and authority | Establish a Communications Working Group (CWG) with representatives from across key Directorates (CMTEDD, ESA, ACT Policing, Health, CHS, EPSDD for example) to review the CCIP and to further identify how the CCIP can be best implemented and utilised. The CWG should report its progress though SEMSOG and coordinate with other WG’s. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4016 | 12 - EM agency and authority | That the Emergency Plan be amended to include considerations for declaring a State of Alert or Emergency (and also wind back from these) and guidance as to what actions and decisions at a minimum should be taken as a consequence of such a declaration. |
REC316-4036 | 12 - EM agency and authority | Government give consideration to investment in professional specialities such as fire behaviour analysts, airbase managers, aerial firefighting technical specialists etc for the RFS. |
REC316-4015 | 12 - EM agency and authority | The working group should report to SEMSOG on progress. |
REC316-4031 | 12 - EM agency and authority | The ESA hold bi-lateral executive level meetings with the utility providers on a regular basis in consultation with other relevant Government stakeholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3834 | 12 - EM agency and authority | That, in order to ensure all firefighters understand how local situational awareness reflects (or may not reflect) the broader scale situation presented by a large/extreme bush fire and the implications this may have on asset protection and fire suppression strategies, the NSW RFS: |
REC315-3829 | 4 - Fire season preparation | That, in order to ensure outcomes-based roadside vegetation management to reduce roadside tree fall and grass ignitions in planning and preparing for bush fire, Transport for NSW, working with local government and NSW RFS, establish a consistent framework for roadside vegetation management that analyses road priority, utility, amenity, strategic value and risk. The framework should: |
REC315-3821 | 4 - Fire season preparation | That government agencies managing land (at all levels and through all agencies) be the best neighbours possible by considering their neighbours when undertaking activities related to bush fire preparation and having clear, two-way communication about these activities, with the aspiration that government landholders will be seen as highly desirable neighbours. |
REC315-3857 | 12 - EM agency and authority | That, in order to ensure timely payment and maintain positive ongoing supplier relationships during large-scale bush fires, the NSW RFS implements an automated logistics solution, informed by the outcomes of the Emergency Logistics Project. |
REC315-3846 | 12 - EM agency and authority | That, in order to maximise the efficiency and effectiveness of heavy plant used in dry fire fighting techniques, the NSW RFS expand and introduce the following in respect to heavy plant: |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3841 | 12 - EM agency and authority | That, in order to ensure suitably skilled and experienced personnel operate as Divisional Commanders during major fire incidents, Bush Fire Management Committees identify appropriate personnel as part of their plan of operations. |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3268 | 12 - EM agency and authority | Incorporate Farm Firefighting Units (FFUs) into the Australasian Inter Service Incident Management System (AIIMS) so that IMTs are aware of their presence on the fireground and their welfare and risks are understood. |
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2477 | 21 - Role of Commonwealth Government | The Department of Housing and Public Works should be included within Local Disaster Management Group evacuation centre planning and plans and assist with decision making around the relocation of evacuees from evacuation centres. |
REC309-2469 | 12 - EM agency and authority | Entities with disaster management responsibilities need to integrate the eight priorities identified within the Emergency Management Sector Adaptation Plan for Climate Change into their disaster management planning cycle. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2412 | 12 - EM agency and authority | Maintain independence of volunteer brigades as community-based organisations and clarify the status and role of volunteers within the chain of command. |
REC304-2411 | 12 - EM agency and authority | Create new seasonal paid positions to coordinate and support groups of volunteer brigades. |
REC304-2410 | 12 - EM agency and authority | Authorise Bushfires NT to establish volunteer bushfire brigades and to give authority to volunteer firefighters to take part in fire suppression and mitigation operations. |
REC304-2414 | 12 - EM agency and authority | Clarify and streamline the allocation of powers to Bushfires NT staff and volunteers involved in bushfire management operations, using a system of delegation through a chain of command similar to the arrangements described in the NT Fire and Emergency Act. |
REC304-2406 | 12 - EM agency and authority | Retain the Regional Bushfires Committees as regional planning and consultative bodies tasked with monitoring, reviewing and making recommendations on fire management in a Fire Control Region. |
REC304-2414 | 12 - EM agency and authority | Clarify and streamline the allocation of powers to Bushfires NT staff and volunteers involved in bushfire management operations, using a system of delegation through a chain of command similar to the arrangements described in the NT Fire and Emergency Act. |
REC304-2416 | 4 - Fire season preparation | Establish a capacity to prescribe bushfire management arrangements for individual properties based on bushfire risk assessment. |
REC304-2407 | 39 - Disaster Risk Management | Discontinue the automatic allocation of Fire Warden powers to Council and Committee members and substitute an option for members to be appointed as Fire Wardens. |
REC304-2413 | 12 - EM agency and authority | Authorise the Director of Bushfires NT to intervene in volunteer brigade affairs where necessary to maintain an effective fire management capacity in a brigade area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2401 | 12 - EM agency and authority | While the proposal to establish an integrated call and dispatch centre is being implemented, Fire and Rescue NSW should take steps to civilianise ComCen and maintain experienced senior officers from both agencies as supervisors similar to how the NSW Police Force and Ambulance Service of NSW operate |
REC302-2397 | 12 - EM agency and authority | Use the model and system in place at the Ambulance Service of NSW as a benchmark for call taking, dispatch and the provision of situational awareness when deploying resources. This will overcome the lack of a feedback loop in current bushfire operations |
REC302-2403 | 12 - EM agency and authority | Take steps to ensure that both fire commissioners are seeking opportunities to engender a culture in their respective organisations that seeks to attract and foster the volunteer ethos and experience |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
REC301-2391 | 12 - EM agency and authority | TFS, PWS and STT should jointly carry out work to identify acceptable shift lengths and patterns – including requirements for rest days – for all personnel working on emergency operations. Once these have been identified, systems should be put in place to ensure that HR rostering practices follow these fatigue management guidelines. And senior staff should lead by example and ensure that they, as well as the people working under them, take adequate rest breaks. |
REC301-2390 | 12 - EM agency and authority | TFS, PWS and STT should jointly reach a decision on whether a winch capable remote area firefighting capability should be maintained in Tasmania; which agency or agencies should be responsible for that program; and how a winch capable remote area firefighting capability can be safely trained and kept current, to include consideration of the availability of winching aircraft. If the decision is taken not to maintain this capability in the state, TFS, PWS and STT should identify how the gap in capability that this represents should be filled in future fire seasons. |
REC301-2389 | 12 - EM agency and authority | The proposed Tasmania State Air Desk should have a finance officer attached to its staff. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1348 | 4 - Fire season preparation | In keeping with the Victorian Bushfires Royal Commission’s findings and recommendations, human life has primacy in bushfire‑related regulations and it is important that this is maintained in the implementation of bushfire management overlays and relevant vegetation removal exemptions should reflect the primacy of human life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1335 | 12 - EM agency and authority | Explore alternative emergency management models including the alternative model proposed above to establish a South Australian Emergency Management Office and State Relief and Recovery Office within the South Australian Fire and Emergency Services Commission, to ensure that all the objects and guiding principles of the Emergency Management Act 2004, and State Emergency Management Plan are addressed efficiently and effectively. |
REC295-1325 | 12 - EM agency and authority | Review and reinstate the State Emergency Management Training Officer and State Emergency Management Planning Officer (capability development) positions to operate with a broad, strategic and leadership focus. |
REC295-1322 | 12 - EM agency and authority | Consider opportunities to identify synergies between the incident management systems used in SA being the, Australasian Interservice Incident Management System (AIIMS) and ICCS Plus. This might include joint training and exercising in roles that are common across both systems. |
REC295-1298 | 12 - EM agency and authority | That the State Emergency Service, in consultation with key stakeholders, identify and implement a robust system and procedures for prioritising, allocating and coordinating multiple tasks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
REC291-1241 | 12 - EM agency and authority | The State Emergency Management Committee, in consultation with Western Australian Farmers Federation, the Association of Bush Fire Brigades, the Contractors Association of WA, and the Forest Industries Federation of WA, to establish systems for the voluntary registration of: · farmer firefighting units; · contractor firefighting resources; and · forestry industry brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1216 | 12 - EM agency and authority | Resolve reoccurring issues with systems and processes |
REC290-1212 | 12 - EM agency and authority | Resourcing models appropriate to local needs, including fire risk and remoteness |
REC290-1208 | 12 - EM agency and authority | A unified and integrated fire sector across the whole fire hazard |
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
REC290-1217 | 12 - EM agency and authority | IAP formats and processes appropriate to the nature of the emergency response. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1382 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC280-1381 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC280-1394 | 12 - EM agency and authority | That the Minister for Police and Emergency Services examine the feasibility of relocating the NSW Rural Fire Service headquarters to a rural or regional location. |
REC280-1387 | 12 - EM agency and authority | That the NSW Rural Fire Service: |
REC280-1384 | 12 - EM agency and authority | That the NSW National Parks and Wildlife Service examine its staffing policy for periods of extreme and catastrophic weather conditions to ensure that sufficient staff are available on site on fire watch. |
REC280-1386 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
Rec-ID | Code | Recommendation |
---|---|---|
REC278-1224 | 21 - Role of Commonwealth Government | The committee recommends that the Australian Government recognise the need to enhance protection and conservation efforts in the Tasmanian Wilderness World Heritage Area by allocating increased funding: |
REC278-1223 | 21 - Role of Commonwealth Government | The committee recommends that the Australian Government commit to long-term funding for the the National Aerial Firefighting Centre of an amount that is at least equal to government's current contribution, rising in line with the Consumer Price Index |
REC278-1222 | 21 - Role of Commonwealth Government | The committee recommends that the Australian Government, in conjunction with state and territory governments, investigate a national remote area firefighting capability, to support Australian fire agencies. |
REC278-1220 | 21 - Role of Commonwealth Government | The committee recommends that the Australian Government: • recognise that climate change has increased fire conditions in south-eastern Australia and the risk to natural and cultural values in the Tasmanian Wilderness World Heritage Area; and • report annually to the World Heritage Committee on the state of conservation in the Tasmanian Wilderness World Heritage Area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC275-1173 | 12 - EM agency and authority | IGEM recommends that fire agencies review their documentation systems and information recording processes to ensure that all operational activities are captured, and to maintain the accuracy and relevance of all developed products. This includes the need to ensure that all significant points of reference entered into mapping products are geo-coded to facilitate accurate transfer of information from one mapping product to another. |
REC275-1172 | 12 - EM agency and authority | IGEM recommends that fire agencies review their resource allocation recording mechanisms and systems to ensure that an accurate reflection of resources deployed to an incident at any given time can be ascertained |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1137 | 12 - EM agency and authority | Review all current SACFS operational facilities (Group, ICC, RCC and SCC) to provide more effective communications, connectivity and resource management. |
REC273-1136 | 12 - EM agency and authority | Plan the establishment of one multi-agency Coordination Centre with sufficient capacity and capability to deal with all incidents in South Australia. |
REC273-1130 | 12 - EM agency and authority | Reviewing how Regional resources are managed and tracked and incorporate into COSO’s to ensure that there is complete situational awareness as to the location and tasking of CFS resources. |
REC273-1141 | 21 - Role of Commonwealth Government | SACFS and the BoM review current weather, fuel loads and curing rates to determine the most appropriate and accurate forecast is prepared, issued and validated against current conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1418 | 12 - EM agency and authority | Queensland Fire and Emergency Services should consider examining regulatory provisions to improve disaster management and business continuity planning for aged care providers. |
REC272-1414 | 12 - EM agency and authority | Queensland Fire and Emergency Services coordinate the development of an integrated risk based approach to disaster management planning for Queensland that is consistent with the Standard and applicable at all levels of the arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC270-1146 | 12 - EM agency and authority | Strengthens its oversight role as lead agency for mitigating Queensland's bushfire risk to acceptable levels by: · coordinating land managers' efforts to assess and mitigate bushfire risk · formalising the role of fire management groups to manage Queensland's fuel loads, including reporting planned and conducted hazard reduction burns and the effectiveness of hazard reduction burns · amending its bushfire mitigation planning to address prevention, preparedness, response and recovery and to manage Queensland's residual bushfire risk · developing and implementing a coordinated strategy to address arson, deterring would-be offenders and rehabilitating convicted offenders · working with local councils to develop and communicate local bushfire plans for communities located in high risk, bushfire-prone areas |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1153 | 4 - Fire season preparation | Planning for Access to Potentially Isolated Communities |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
REC265-1104 | 12 - EM agency and authority | DFES should increase and maintain urban interface bushfire skills and expertise. Appointments to senior roles within the agency should include people with experience and credibility in bushfire firefighting and management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1502 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
REC261-1499 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC261-1511 | 12 - EM agency and authority | That the Minister for Police and Emergency Services examine the feasibility of relocating the NSW Rural Fire Service headquarters to a rural or regional location. |
REC261-1498 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC261-1504 | 12 - EM agency and authority | That the NSW Rural Fire Service: |
REC261-1494 | 4 - Fire season preparation | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC261-1515 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service: |
REC261-1501 | 12 - EM agency and authority | That the NSW National Parks and Wildlife Service examine its staffing policy for periods of extreme and catastrophic weather conditions to ensure that sufficient staff are available on site on fire watch. |
REC261-1503 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1054 | 2 - Emergency powers | That the Rural Fire Service consider extending pre-emptive section 44 to whole of Castlereagh RFS/Warrumbungle Shire area. |
REC260-1071 | 4 - Fire season preparation | The NPWS to consider developing a land management policy that requires hazard reduction around identified assets within the Park and the clearing of fire trials within the Park before the bush fire season commences. Consideration should also be given to developing additional fire trails in the Park, bearing in mind the lack of available fire trails to the south of the John Renshaw Parkway in the park. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1589 | 12 - EM agency and authority | In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0931 | 4 - Fire season preparation | That a specific risk prevention and mitigation advisory body be established for the State Emergency Management Committee. |
REC247-0857 | 2 - Emergency powers | That the Tasmania Emergency Management Plan enable, and all organisations with a role in emergency management activate, emergency plans at lower threshold events to practice their arrangements and achieve a ‘hot start’ in escalating events. |
REC247-0856 | 2 - Emergency powers | That the Government reconsider the current position on emergency declarations in the Emergency Management Act 2006 and the Act is amended to provide: • a graduated scale of emergency declarations; • the ability to make a declaration when an emergency has occurred, is occurring or is about to occur; • the ability for the State Controller (or whatever the person in overall control of response and recovery operations is called) to make one or more declarations; • a declaration to enable access to all emergency powers. |
REC247-0935 | 4 - Fire season preparation | That the State Emergency Management Committee includes in its planning, the development of contingency emergency management plans for areas of high risk due to local conditions. |
REC247-0934 | 4 - Fire season preparation | That the State Fire Management Committee considers developing a structured, systemic and proactive bushfire hazard reduction program with municipal councils and Tasmania Fire Service; and advises the Government on any legislative or other changes required to implement such a program. |
REC247-0933 | 4 - Fire season preparation | That the Government considers whether a peak body should be established, with authority to effectively implement a bushfire mitigation plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0781 | 12 - EM agency and authority | TFS continue to develop and publish RFOC policy and procedures, ensuring that all partners who perform roles within the RFOC are included in the consultation and training. |
REC246-0783 | 12 - EM agency and authority | TFS review the restriction on interstate personnel filling positions such as Incident Controller and obtain definitive advice on the legal reasons for this. If immunity legislation is unclear then legislative change could be sought to ensure that the immunities enjoyed by Tasmanian incident controllers apply equally to personnel from interstate performing incident controller roles. |
REC246-0782 | 12 - EM agency and authority | That TFS develop a strategy to manage the workloads on career staff to reduce the risk of single point failures through spreading workloads and capability to ensure a level of redundancy and resilience in a number of critical portfolios. This should include deploying volunteer and retained personnel to maximise both its operational and support capacity during major and/or protracted fires and incidents, both in operational centres and in the field in command roles. Other sources of expertise should also be identified in advance of incidents occurring and called upon if necessary. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0986 | 12 - EM agency and authority | That the founding principle of the Rural Fire Service, that Brigades are formed on the principle of neighbour helping neighbour to collectively manage fire events, remains on of the foundation of Rural Fire Service Queensland. |
REC241-1038 | 12 - EM agency and authority | That District Inspectors retain the discretion to allocate gratuity to Fire Wardens for out of pocket expenses if required. |
REC241-0957 | 12 - EM agency and authority | That a strong emphasis be placed on the establishment and recruitment of PCYC emergency cadets. |
REC241-0993 | 12 - EM agency and authority | That wherever possible, for future appointments of Fire Wardens, where that Wardens’ district is totally covered a by Rural Fire Brigade, consideration should be given that the appointed Fire Warden is a Rural Brigade Member. |
REC241-0962 | 12 - EM agency and authority | That Rural Fire Service Queensland consider service delivery needs with a view to establishing boundary/ staff/budget changes according to State standards. |
REC241-1010 | 12 - EM agency and authority | That where a Brigade supports another community and this involves the use of any brigade equipment it shall be the decision of that brigade in relation to the deployment and use of their equipment and resources. |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
REC241-0975 | 12 - EM agency and authority | That employee selection panels for field staff positions only comprise three members and include a Rural Fire Service Queensland representative, a Rural Fire Brigades Association of Queensland representative and one representative from the District Fire Management Group. |
REC241-1037 | 12 - EM agency and authority | That Rural Fire Service Queensland and its staff be exempt from the Travel Management System. The Travel Management System does not work in the rural fire operation areas as it is not flexible in the rapid escalation of wild fire events or cater for volunteering timeframes. It has been proven to be inefficient and costly. |
REC241-0953 | 12 - EM agency and authority | That a separate area of responsibility be established to provide independent oversight and monitor disaster readiness across all hazards. |
REC241-0990 | 12 - EM agency and authority | Membership of the District Fire Management Group is at the discretion of the Chair of the District Fire Management Group, however members must have the necessary expertise and experience for the role and membership should include where applicable, the District Inspector - Rural Fire Service Queensland, a representative of relevant local governments and representatives of agencies responsible for parks and wildlife, transport and main roads, forestry and natural resources among other appropriate representatives. |
REC241-0961 | 12 - EM agency and authority | That staffing at Rural Fire Service Queensland District offices remain at current levels within establishment and, if needed, base staffing levels be increased. |
REC241-1008 | 12 - EM agency and authority | That the colour of Rural Fire Service Queensland Brigade operational vehicles remain yellow and that they retain the Rural Fire Service Queensland logo. |
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-0972 | 12 - EM agency and authority | That Rural Fire Service Queensland designate a position of Lands Procurement Officer to support volunteers by project managing the acquisition of land for Brigade sheds and their construction where required. |
REC241-1021 | 12 - EM agency and authority | That Brigades that do not have a truck and are currently classified as Rural conduct a self-determination to ascertain if they wish to be reclassified as a Primary Producer Brigade. |
REC241-0952 | 12 - EM agency and authority | That an operational organisation be established comprising of three streams – a. urban fire service; b. rural fire service; and c. the state emergency service. Each of the three organisations will be led by a Deputy Chief Officer, reporting to a Chief Officer. |
REC241-0989 | 12 - EM agency and authority | That the first tier comprise at least one District Fire Management Group in each Rural Fire Service Queensland District. The District Fire Management Group will be chaired by a person with the necessary expertise and experience, nominated by the community and appointed by Government. Chairs will hold the deciding vote in matters related to fire management at the local level. |
REC241-0960 | 12 - EM agency and authority | That Rural Fire Service Queensland District offices remain at least at their current number of 14, with consideration given by the Rural Fire Service Queensland to expanding the number of District offices by opening an office in the South Burnett, considering a new office in the southern Central Highlands, and the option of part time offices on a risk/need/growth basis, particularly in north-west Queensland. |
REC241-1007 | 12 - EM agency and authority | That the Rural Fire Service Queensland consider a less formal uniform which volunteers can better identify with, and that National rank markings be retained. |
REC241-0966 | 12 - EM agency and authority | That District offices be located in areas that enhance ease of access for out of town volunteers and the general public and also provide suitable parking, onsite storage and be suitable for operational use. |
REC241-1020 | 12 - EM agency and authority | That members of Village and Izone classified Brigades only be required to conduct a criminal history check when they first join a Brigade. Criminal history checks will no longer be required when a Member who has already undergone a criminal history check takes an office bearing role within a Brigade or changes Brigades. Criminal history checks are to still be conducted on Rural Fire Service volunteers undertaking interstate deployments. Members of other voluntary organisations in Queensland (e.g. State Emergency Service, Volunteer Marine Rescue) who wish to join the Rural Fire Service Queensland will not be required to undertake an additional criminal history check with an internal check to be conducted by the Department of Community Safety. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-0988 | 12 - EM agency and authority | That the planning system is to have a two tiered structure comprising District Fire Management Groups and linking to the State Disaster Management Group. |
REC241-0959 | 12 - EM agency and authority | That Rural Fire Service Queensland District offices report directly to the Deputy Chief Officer. |
REC241-1006 | 12 - EM agency and authority | That Brigades’ financial contributions to groups must be voluntary and approved by a recorded minute at a meeting of that brigade. |
REC241-0964 | 12 - EM agency and authority | That the position of Regional Manager Rural Operations be re-designated to Regional Co-ordinator in the North, Central and South-East regions to emphasise the supporting role the position will take. |
REC241-1019 | 12 - EM agency and authority | That a local committee consisting of Elders and community leaders be formed in remote and Indigenous communities to determine Brigade membership applications. |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-0987 | 12 - EM agency and authority | That to assist the Rural Fire Service Queensland and other agencies in managing wildfire risk, a planning system for wildfire management be established in legislation that complements the existing disaster management arrangements. |
REC241-0958 | 12 - EM agency and authority | That the Rural Operations division currently sitting within the Queensland Fire and Rescue Service become an autonomous unit called Rural Fire Service Queensland and be led by a Deputy Chief Officer. Structure and Leadership of the Rural Fire Service |
REC241-1005 | 12 - EM agency and authority | That fire groups can only be formed through the agreement of all brigades that will become a part of that group, and the management and operational procedures of the group must be approved by the contributing brigades. Local District Inspectors are to provide mentoring and support when brigades form a group. |
REC241-0963 | 12 - EM agency and authority | That there be three (3) RFSQ regions in Queensland - North, Central and South-East. |
REC241-1014 | 12 - EM agency and authority | That the Rural Fire Service Queensland should engage a private provider offsite and outside the Government firewall to establish an email address for each Brigade and Fire Warden. The email address would reflect the Brigade name and Fire Warden district. E.g.: GreenbankRFB@msn.com.au |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1624 | 12 - EM agency and authority | The Emergency Services Agency should: |
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
REC228-1627 | 12 - EM agency and authority | The Emergency Services Agency (ACT Rural Fire Service headquarters) should implement a system to provide assurance to the Chief Officer of the ACT Rural Fire Service that personnel and equipment readiness meets requirements. |
REC228-1626 | 12 - EM agency and authority | The Emergency Services Agency and the Territory and Municipal Services Directorate should clarify the timing of the requirement for meeting firefighter fitness requirements, as set out in ACT Rural Fire Service operating procedures and the Territory and Municipal Directorate’s Enterprise Agreement, and give priority to meeting that requirement. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0535 | 2 - Emergency powers | DFES or DEC (depending on land tenure) is mandated to take over control of emergency incidents from Local Government once they have been declared Level 2 incidents. WESTPLAN BUSHFIRE and legislation to be amended accordingly. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0520 | 12 - EM agency and authority | The Department of Environment and Conservation review the utility of its current regional model in terms of the capability of operational centres such as Kirup to service major fire activity on land proximate to the rural urban area (this recommendation should also be considered in the context of Recommendation 5). |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1816 | 21 - Role of Commonwealth Government | That the Department of Sustainability and Environment continue to invest in the auditing of Victoria’s levee systems, both public and private, so that the Victoria Flood Database contains reliable and up to date data, including information on levees’ location, height, condition and ongoing viability for flood protection. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0731 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directives it develops in relation to these matters. |
REC210-0696 | 21 - Role of Commonwealth Government | Carriers, councils and the Australian Communications and Media Authority should take into account the risk of flooding when considering the placement of telecommunications facilities. |
REC210-0730 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop clear directives about: • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the process for dealing with requests for assistance that exceed an SES unit’s capacity to respond them • the process for seeking extra support for an SES unit that has been overwhelmed by a disaster (whether by way of Emergency Management Queensland or the disaster management arrangements or both) • the role of SES liaison officers in communications with disaster managers about SES disaster operations • the role of incident controllers, and their teams, relative to those SES (or Emergency Management Queensland) personnel charged with the command of SES operations. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0729 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directive when it is developed. |
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0728 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop a directive that makes clear the authority of an officer of that agency to command a major SES operation. This could be expected to occur when a deployment of additional SES members is made to a region because the response needed is beyond the capacity of its local units. The directive should make clear the powers of the officer and his or her reporting responsibilities to disaster managers in these circumstances. Emergency Management Queensland must also ensure that any officer who assumes such a role has adequate training and skills in the conduct of disaster operations. |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0725 | 12 - EM agency and authority | The fire service should ensure that station officers are familiar with the procedure for contacting management when requesting the calling in of additional staff; and, in particular, that they have available to them the names and current telephone numbers of the officers to be contacted in the first instance, with alternative contact details in the event that those officers prove unavailable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1665 | 12 - EM agency and authority | Develop a long term forecast of volunteer requirements, by region, and then review the adequacy of volunteer operational grants, equipment and facilities to meet this forecast. |
REC209-1675 | 39 - Disaster Risk Management | PowerWater Corporation be consulted with the intention of establishing a Memorandum Of Understanding for the maintenance of PowerWater land for the purpose of coordinated fire reduction. |
REC209-1664 | 12 - EM agency and authority | Review Bushfires NT brigade boundaries to increase the catchment for possible volunteers and maximise the availability and allocation of equipment. |
REC209-1673 | 4 - Fire season preparation | That a trial be commissioned to assess the most effective means of road verge management, including regional variations, for future application across the Territory. |
REC209-1674 | 39 - Disaster Risk Management | That the concession holder of the rail corridor be approached to formalise a Memorandum of Understanding for the maintenance of the railway corridor for the purposes of fuel load reduction. |
REC209-1663 | 12 - EM agency and authority | Review Bushfires CRC initiatives as the basis for the implementation of a recruitment drive in the Territory. |
REC209-1672 | 4 - Fire season preparation | Annual property inspections assessing access and fuel loads are conducted in all peri urban areas. |
REC209-1667 | 39 - Disaster Risk Management | Prepare a formal proposal for the creation of pastoral/Indigenous Lands Fire Management Teams. |
REC209-1649 | 12 - EM agency and authority | Regular rotation of staff across other regions of the Territory to increase knowledge, skills and expertise that can be called upon to increase response effectiveness. |
REC209-1666 | 39 - Disaster Risk Management | Investigate the application and cost of the creation of District Coordination Officers to key high demand brigade districts. |
REC209-1668 | 12 - EM agency and authority | Maintain DNRETAS as the lead agency for all aspects of Bushfires NT’s role and maintain Bushfires NT as the lead organisation for both fire prevention and fire fighting operations in its specified districts and zones. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0295 | 12 - EM agency and authority | There would be benefit in progressively aligning the geographic boundaries of each of the agencies and seeking to co-locate their headquarters within those boundaries. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0501 | 2 - Emergency powers | The Minister for Emergency Services amend section 50 of the Emergency Management Act 2005 by June 2012 to allow the State Emergency Coordinator, as well as a hazard management agency, to make an emergency situation declaration. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-0389 | 12 - EM agency and authority | The Fire and Emergency Services Authority and local governments ensure that Community Emergency Service Managers are physically based in local government. |
REC200-0383 | 12 - EM agency and authority | The State Government restructure the Fire and Emergency Services Authority as a Department. 22 As part of this restructure, Emergency Management Western Australia should either be: 1. clearly separated from the fire and emergency services response function (see figure 2); or 2. moved to the Department of the Premier and Cabinet (see figures 3 and 4) or 3. moved to the Attorney-General’s department (see figures 3 and 5). |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
REC200-0381 | 2 - Emergency powers | The State Government amend section 50 of the Emergency Management Act 2005 to allow the Chair of the State Emergency Coordination Group to declare an emergency situation. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0444 | 2 - Emergency powers | the state, as a matter of urgency, develop a multi-agency Incident Control Team capability to be readily available for statewide deployment to establish incident control or to relieve functioning control structures. |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0235 | 12 - EM agency and authority | Consider the ‘secondment’ of staff into Information Section roles during the fire season along the lines of the seasonal Project Fire Fighters model |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0329 | 21 - Role of Commonwealth Government | The Fire Services Commissioner requests the Federal Government to revise the National SEWS Guidelines |
REC195-0320 | 12 - EM agency and authority | The Fire Services continue working towards a common and integrated information and communication platform to improve interoperability at state, regional and local levels. |
REC195-0334 | 4 - Fire season preparation | The Fire Services Commissioner leads a task force to: a. identify legislation, policies and guidelines that impact on vegetation management and recommend necessary changes b. develop a set of risk-based standards for vegetation management with respect to strategic firebreaks and the assets being protected c. integrate maintenance standards across all areas of responsibility and tenure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC192-1923 | 21 - Role of Commonwealth Government | The Committee recommends that Parliament establish a standing committee for natural disasters. The purpose of this committee would be to ensure that Government agencies and emergency services are fully prepared to deal with natural disasters and to provide an opportunity for Members of Parliament, as opposed to Cabinet, to have input into disaster management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0262 | 12 - EM agency and authority | that QFRS include consultation with rural fire brigades as mandatory when boundary changes are proposed. |
REC191-0271 | 12 - EM agency and authority | that QFRS should establish a Rural Fire Service division within QFRS with the aim of integrating and strengthening the relationship between the urban and rural fire services. |
REC191-0270 | 12 - EM agency and authority | that QFRS implement procedures to ensure that rural fire brigades receive written confirmation of the Commissioner’s approval after office bearer elections in compliance with section 81 of the Fire and Rescue Service Act 1990. |
REC191-0269 | 12 - EM agency and authority | that QFRS implement procedures to provide a clear grievance process which is available to rural fire brigade volunteers. |
REC191-0264 | 12 - EM agency and authority | that QFRS update its website to include the Rural Fire Service as part of its www.fire.qld.gov.au web presence. |
REC191-0263 | 12 - EM agency and authority | that QFRS investigate and implement an internal email system for rural fire brigades. |
REC191-0272 | 12 - EM agency and authority | that QFRS establish the position of Assistant Commissioner, Rural Fire Service to lead the proposed Rural Fire Service division within QFRS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC187-2946 | 21 - Role of Commonwealth Government | That a national agency sponsored by the Commonwealth Government be established to undertake national coordination of flood risk management and to operate the system of premium discounts and the flood risk reinsurance facility. The Agency would: |
REC187-2918 | 21 - Role of Commonwealth Government | That an agency sponsored by the Commonwealth Government be created to manage the national coordination of flood risk management and to operate a system of premium discounts and a flood risk reinsurance facility, supported by a funding guarantee from the Commonwealth. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0121 | 12 - EM agency and authority | A DEC fire management staff succession plan would minimise the loss of core fire management skills and experience in the future and provide a planned approach to development of prospective fire management staff. |
REC183-0106 | 12 - EM agency and authority | The DEC corporate statement should affirm a strong commitment to fire management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0128 | 12 - EM agency and authority | FESA establishes a process (and associated systems and policies) to mobilise staff to an incident, incorporating pre-formed multi-agency Incident Management Teams. The development of Incident Management Teams should align with the principles of seamless and integrated escalation of command and control arrangements, and be based on a whole of capability approach (people, organisations, systems, training, procedures etc.). |
REC182-0130 | 12 - EM agency and authority | FESA identifies and documents its information requirements for end-to-end information exchange and then assess the adequacy of current systems to meet these information requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0212 | 4 - Fire season preparation | VicRoads implement a systematic statewide program of bushfire risk assessment for all roads for which it is responsible, to ensure conformity with the obligations in s. 43 of the Country Fire Authority Act 1958 and with the objectives expressed in the VicRoads 1985 Code of Practice. |
REC181-0211 | 4 - Fire season preparation | The State and Commonwealth provide for municipal councils adequate guidance on resolving the competing tensions arising from the legislation affecting roadside clearing and, where necessary, amend environment protection legislation to facilitate annual bushfire-prevention activities by the appropriate agencies. |
REC181-0210 | 4 - Fire season preparation | The State amend the exemptions in clause 52.17-6 of the Victoria Planning Provisions to ensure that the provisions allow for a broad range of roadside works capable of reducing fire risk and provide specifically for a new exemption where the purpose of the works is to reduce bushfire risk. |
REC181-0186 | 21 - Role of Commonwealth Government | The Commonwealth, states and territories continue to pursue the National Action Plan to Reduce Bushfire Arson in Australia, giving priority to producing a nationally consistent framework for data collection and evaluating current and proposed programs in order to identify and share best-practice approaches. |
REC181-0192 | 4 - Fire season preparation | The Department of Sustainability and Environment develop and administer a collective offset solution for individual landholders who are permitted to remove native vegetation for the purpose of fire protection. |
REC181-0204 | 2 - Emergency powers | The State amend the Country Fire Authority Act 1958 to enable the Chief Officer to delegate the power to issue fire prevention notices. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3338 | 12 - EM agency and authority | Licensees and rig operators should be astute in ensuring that corporate systems and culture encourage rather than discourage raising of well control issues. For instance, do performance bonuses or rewards actually encourage or discourage reporting of issues? Is there a system in place to enable anonymous reporting of well control concerns? What whistleblower protections are in place? |
REC177-3371 | 21 - Role of Commonwealth Government | The Government should examine the scope for a single environment plan to meet the regulatory requirements of both the OPGGS Act and the EPBC Act. This could possibly be achieved by way of bilateral agreements and accreditation arrangements and/or legislative amendment. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3347 | 21 - Role of Commonwealth Government | The proposal of the Productivity Commission’s Research Report (Review of Regulatory Burden on the Upstream Petroleum (Oil and Gas) Sector, April 2009) to establish a NOPR should be pursued at a minimum. |
REC177-3358 | 21 - Role of Commonwealth Government | The body established to undertake a central coordination and facilitation role in the event of any future blowout in Commonwealth waters should undertake to make all relevant information publically available from one, authoritative and easy to access source. |
REC177-3337 | 12 - EM agency and authority | Supervision/oversight of well control operations (within licensees, rig operators and by regulators) must occur without assuming adherence to good oilfield practice. The opposite assumption should prevail: namely adherence to good oilfield practice may well be compromised by the pursuit of time and cost savings. |
REC177-3345 | 2 - Emergency powers | NOPSA’s prohibition powers should be extended such that a prohibition notice can be issued where a NOPSA Occupational Health and Safety Inspector believes, on reasonable grounds, that an activity is occurring or may occur at a facility involving an immediate threat to the health or safety of a person. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3346 | 21 - Role of Commonwealth Government | A single, independent regulatory body should be created, looking after safety as a primary objective, well integrity and environmental approvals. Industry policy and resource development and promotion activities should reside in government departments and not with the regulatory agency. The regulatory agency should be empowered (if that is necessary) to pass relevant petroleum information to government departments to assist them to perform the policy roles. |
REC177-3357 | 21 - Role of Commonwealth Government | In any future similar blowout or offshore emergency situation, the Minister appoint (through either a NOPR or the relevant Department) a senior public servant to establish and oversight a central coordinating body that will facilitate interaction between regulators, industry, AMSA and the owner/operator. Primary responsibility for stopping a blowout should remain with the owner/operator but should be subject to direction from the central coordinating body in consultation with stakeholders (including the owner/operator). |
REC177-3336 | 12 - EM agency and authority | Achievement and maintenance of well control should be written into the job responsibilities of key personnel, at every level up to and including CEOs. That is, a functional line of accountability for well control must exist up to, and including, CEOs. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3376 | 21 - Role of Commonwealth Government | In carrying out a review of PTTEPAA’s permit and licence, the Minister should have regard to this Report, particularly (i) the adverse findings set out in this Chapter; and (ii) the extent to which PTTEPAA has implemented the Action Plan submitted to the Inquiry, or otherwise addressed the matters canvassed in this Report. |
REC177-3274 | 21 - Role of Commonwealth Government | The Minister should appoint a senior policy adviser to investigate and report on the best means to implement the recommendations contained in this Chapter 3 of this report. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3351 | 21 - Role of Commonwealth Government | In the future, and in the interests of ensuring that all possible well control options are comprehensively pursued to exhaustion, decisions as to well control response options should be the result of collaboration between the regulator and the operator rather than leaving one party to make unilateral judgements as to the appropriateness of various well control operations. The regulator should provide transparent and contemporaneous explanations to the public of all well control options under consideration at any particular time. |
REC177-3336 | 12 - EM agency and authority | Achievement and maintenance of well control should be written into the job responsibilities of key personnel, at every level up to and including CEOs. That is, a functional line of accountability for well control must exist up to, and including, CEOs. |
REC177-3375 | 21 - Role of Commonwealth Government | For the purposes of that review, the Minister should issue a ‘show cause’ notice to PTTEPAA under s 276 of the OPGGS Act. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3349 | 21 - Role of Commonwealth Government | In the meantime, the Minister should: |
REC177-3372 | 21 - Role of Commonwealth Government | OSCPs should be endorsed by AMSA prior to regulatory approval to ensure that they align with the National Plan. Once field operations commence, the capability of operators should be assessed against their plans, and exercises conducted to ensure the plans remain effective. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3348 | 21 - Role of Commonwealth Government | Responsibility for well integrity should be moved to NOPSA (as also proposed by the Productivity Commission). |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0137 | 21 - Role of Commonwealth Government | The Commonwealth co-ordinate a standing national arson forum between fire and law enforcement agencies to be held every two years. |
REC176-0136 | 21 - Role of Commonwealth Government | The Commonwealth Government examine potential new arrangements for Commonwealth involvement in the development and implementation of a national policy for bushfire management. |
REC176-0140 | 4 - Fire season preparation | The Commonwealth seek agreement from the states and territories that would enable it to evaluate the adequacy of fuel reduction programs applied by public land management agencies in high bushfire risk areas, and audit their implementation against the program's stated objectives. |
REC176-0141 | 21 - Role of Commonwealth Government | The Commonwealth publish all fuel reduction plans and related audit findings on a national database. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0024 | 12 - EM agency and authority | Transport plans for BFB resources should be prepared by the Ground Support Unit in close liaison with FESA who will liaise with the home jurisdictions of the brigades. Moving personnel whilst leaving the equipment at the fire ground staging areas is preferred to moving equipment in and out with every shift. |
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0020 | 12 - EM agency and authority | The role of ‘BFB Task Force Liaison’ be defined and appropriately trained personnel be provided by the HMA (possibly from support brigades) to facilitate brigade movements on and off the fire ground. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
Rec-ID | Code | Recommendation |
---|---|---|
REC163-1939 | 2 - Emergency powers | That the Rural Fires Act 1997 be amended to provide to designated Fire Investigation Officers of the Rural Fire Service the power to enter any land upon which a bushfire has occurred for the purposes of investigation for a period of up to 24 hours after a fire has been declared out. |
REC163-1938 | 12 - EM agency and authority | That appropriate officers of the Rural Fire Service be granted the same powers as granted to officers of NSW Fire Brigades under section 19 of the Fire Brigades Act 1989. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1802 | 12 - EM agency and authority | That the South Australian Country Fire Service create as part of a Level 2 and 3 Incident Management Team Logistics Division an Officer whose function it is to seek out, locate and identify sources of water, be they on land or provided by carrier. |
REC153-1801 | 12 - EM agency and authority | That the South Australian Country Fire Service identify and impart minimum skills and competencies to members who fulfil the roles of the four core AIIMS functionaries of a Level 2 Incident Management Team. |
REC153-1800 | 12 - EM agency and authority | That the South Australian Country Fire Service utilise wherever possible the skills of paid, professional staff to perform the roles of Incident Controller and/or Planning Officer in Level 2 Incident Management Teams. |
REC153-1783 | 12 - EM agency and authority | That South Australian Country Fire Service create and develop the role of a Regional Public Warnings Officer as a member of the paid staff of the SACFS whose role it would be to identify the need for, and to deliver, timely bushfire warnings to the public during the course of a bushfire incident. |
REC153-1779 | 4 - Fire season preparation | That the South Australian Farmers’ Federation encourage its members and constituents to keep and maintain on rural land in proper working order machinery that is capable of removing, modifying or reducing cropping stubble at short notice in order to minimise or mitigate bushfire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3117 | 12 - EM agency and authority | QFRS ensure compliance with the brigade accountability requirements for funding received by rural fire brigades as specified in the Rural Fire Brigade Manual |
REC150-3123 | 12 - EM agency and authority | QFRS determine the performance information needed to support effective decision making . |
REC150-3116 | 12 - EM agency and authority | QFRS implement a brigade issues management process to capture, manage and report specific brigade issues. |
REC150-3121 | 12 - EM agency and authority | QFRS utilise performance information on brigade activity as a factor in determining brigade resource and funding needs. |
REC150-3114 | 12 - EM agency and authority | QFRS implement a process to review brigade plans and incorporate specific issues identified into forward planning at the area and regional levels. |
REC150-3120 | 12 - EM agency and authority | QFRS provide assistance to brigades in determining and budgeting for their resource needs. |
REC150-3113 | 12 - EM agency and authority | QFRS provide guidance and support to rural fire brigades in the development of their one year operational plan and three year management plan. |
REC150-3119 | 12 - EM agency and authority | QFRS implement a system to collate and analyse brigade funding information. |
REC150-3112 | 12 - EM agency and authority | Queensland Fire and Rescue Service (QFRS) implement a forward planning process specific to rural fire management as part of the QFRS strategic planning process, which involves regional and area offices and incorporates: |
REC150-3118 | 12 - EM agency and authority | QFRS review the financial accountability and audit requirements of the rural fire brigades to reflect their status as part of QFRS. |
REC150-3124 | 12 - EM agency and authority | QFRS establish a suitable process to reliably capture that information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3596 | 12 - EM agency and authority | CSC investigating possible change of location when contract for current location at Wendouree expires in 2008. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-1995 | 12 - EM agency and authority | That the Emergency Services Agency staff the Media Unit within its planning Section with profesisonal, experienced information officers skilled in dissemination of information and media management and liaison |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
REC126-1963 | 12 - EM agency and authority | That priority be given to ensuring that the ACT has an adequate resource of remote area firefighting teams consisting of personnel with high levels of fitness and training in remote fire suppression |
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
REC126-1949 | 12 - EM agency and authority | That the Emergency Services Agency be relocated into accommodation that is purpose-built and more sited to the agency’s operations than the current facility at Curtin |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3900 | 12 - EM agency and authority | That agencies integrate condition information into their asset management decision-making practices and use it as the basis for validating asset valuations and depreciation calculations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3783 | 4 - Fire season preparation | The Committee recommends that the government establish designated fire safety areas within native vegetation and at road intersections. |
REC122-3782 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities prepare a management plan that includes firebreaks and access tracks in the region, including the location of current breaks and access tracks and where breaks and tracks need to be established. |
REC122-3781 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities assess fire tracks and breaks to determine if firebreaks and access tracks need to be wider and/or native vegetation removed so that it does not impinge on firebreaks or tracks. |
REC122-3780 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities identify if: sufficient firebreaks and access track exist; they are strategically located; and they are being managed. |
REC122-3787 | 4 - Fire season preparation | The Committee recommends that the Native Vegetation Council provide landholders with assistance for applications for prescribed burning (via a guide, a proforma or staff). |
REC122-3785 | 4 - Fire season preparation | The Committee recommends that the government, via the CFS, coordinate the preparation and implementation of native vegetation management plans that incorporate management of fuel loads and includes a prescribed burning regime for the area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2334 | 12 - EM agency and authority | That the Fire Management Branch of DSE be prescribed as an ‘emergency service agency’ for the purposes of s21C (1)(a) of the Emergency Management Act 1986. |
REC104-2326 | 12 - EM agency and authority | That, as a matter of urgency, CFA and DSE: |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2248 | 12 - EM agency and authority | That Incident Control Centres and Municipal Emergency Co-ordination Centres be collocated, wherever practicable. |
REC104-2220 | 2 - Emergency powers | That CFA should not be given the power to direct Forest Industry Brigades to engage in fire prevention and suppression activities off their land and that decision should remain the responsibility of the plantation company. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2237 | 12 - EM agency and authority | That CFA continues to work with its Brigades to complete the integration of AIIMS-ICS with the Group Structure for full implementation by the 2004-2005 fire season. |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
REC104-2234 | 12 - EM agency and authority | That the fire agencies develop contingency plans in relation to access to water for firefighting, including where appropriate, the use of static, large volume water tanks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2136 | 4 - Fire season preparation | The Committee recommends that the Commonwealth through the National Heritage Trust assist the states and territories in the construction, maintenance and signage of fire trail networks. |
REC098-2140 | 12 - EM agency and authority | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments implements arrangements in which greater flexibility is devolved to local brigade captains in the |
REC098-2185 | 21 - Role of Commonwealth Government | The Committee recommends in acknowledgement of the expertise that the Commonwealth can bring to the Australasian Fire Authorities Council and of funding already supplied to the Council for the development of a National Aerial Firefighting Strategy, that the current status of Emergency Management Australia on AFAC as an associate member be upgraded to full membership and that full membership also be extended to the Department of Defence. |
REC098-2184 | 21 - Role of Commonwealth Government | The Committee recommends that the functions and administration of Emergency Management Australia be reviewed to develop an organisation that is proactive and involved in the development and implementation of national policy on emergency response. |
REC098-2168 | 2 - Emergency powers | The Committee recommends that the Commonwealth investigate, and where necessary, require the urgent enhancement of the provision of emergency power and telecommunications services for the purpose of |
REC098-2177 | 39 - Disaster Risk Management | The Committee recommends that state and territory governments be required to regularly perform risk assessments to the land within their jurisdictions to ensure that bushfire prone areas are accurately identified |
REC098-2150 | 12 - EM agency and authority | The Committee recommends that the Commonwealth seeks to ensure that the proposed Council of Australian Governments review of the bushfire management initiate with the states, as a priority, a review of the |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4163 | 12 - EM agency and authority | Effective planning, organisational and training capability be maintained at regional level and developed, as appropriate, for the future. [Reference paragraphs: 260 to 261] |
REC037-4162 | 12 - EM agency and authority | There be a close integration of the responsibilities of the Minister under the State Disasters Act and the State Disaster Plan, thereby strengthening overall counter—disaster management, direction and control. To this end, the organisational arrangements shown in Annexures “J” and “K” should be adopted. The main features of these are: |
REC037-4169 | 4 - Fire season preparation | Mitigation and preparedness be enhanced and maintained for the future. Some co—ordinating mechanism or system be introduced at State Government level for this purpose. [Reference paragraphs: 114 to 128] |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4150 | 12 - EM agency and authority | The Forests Department direct more staff to the planning and co-ordination of its bush fire control organisation so that emergency conditions can be met immediately by ample reserves of labour and equipment and that co-ordination between the Department, the local authority, sawmills and other sources of man-power and equipment in and around forestry districts is as complete as possible. This particularly includes co-operative protective burning around the boundaries of forest areas. |
REC019-4135 | 12 - EM agency and authority | The Bush Fires Board appoint a Standing Committee of about six of its members, all of whom are likely to be available at any time during the bush fire season to meet and take executive action as necessary. |
REC019-4147 | 12 - EM agency and authority | All local authorities form advisory committees of persons from bush fire brigades and of bush fire control officers to plan co-operation in effort and co-ordination between brigades, to group brigades under brigade group officers and to advise the local authority upon all matters of fire control, including the planning of the district firebreak layout and prosecuting for breaches of the Bush Fires Act. |
REC019-4134 | 12 - EM agency and authority | All members of the Board be selected for their interest in and experience and knowledge of matters directly associated with bush fire control and not merely as representatives of particular organisations, that the Chairman of the Board be appointed by the Governor instead of being an ex officio appointment of another forester, a member of the timber industry, a police officer and a person with a sound knowledge of weather and its effect upon fire behaviour. |
REC019-4141 | 12 - EM agency and authority | The relative seniority of bush fire control officers be determined with a view to appointing group leaders as chief bush fire control officers. The Shire Clerk should generally be a liaison bush fire control officer rather than a chief fire control officer. |
REC019-4159 | 12 - EM agency and authority | The State Emergency Service be used to meet any additional needs but that as far as possible, requests for assistance be directed in the first instance to the Bush Fires Board or at least referred to that Board by the State Emergency Service for advice before action is taken. |
REC019-4140 | 12 - EM agency and authority | Local authorities select bush fire control officers for their knowledge and experience of bush fires and their qualities of leadership and that as far as practicable, they be captains of bush fire brigades so that the person issuing the permit to burn has the responsibility of extinguishing the fire if it escapes. |
REC019-4155 | 12 - EM agency and authority | The management of all National Parks in the State be concentrated under one authority to ensure co-ordination in administration and protective measures. |
REC019-4138 | 12 - EM agency and authority | That care be exercised in recommending the application of emergency bush fire periods so that they will not be applied to districts where their application is unnecessary. |
REC019-4154 | 12 - EM agency and authority | A committee be formed and provided with the finance necessary to enable it to supplement the activities of the local bush fire brigades in districts in the far south-west of the State where ratable values are particularly low and the proportion of Crown lands high, and that the Forests Department be authorised to give approval for control burning of Crown lands throughout the State by bushfire brigades within two miles of a State Forest and that outside this distance the Bush Fires Board through its wardens have similar authority. |
REC019-4137 | 12 - EM agency and authority | Before the bush fire season starts, the Minister on the recommendation of the Board nominate a person and a deputy person who will be instructed to take charge of fire fighting operations in each district should a dangerous fire occur and render such an appointment advisable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3950 | 4 - Fire season preparation | It is recommended that on days of abnormal danger loads of briquettes be not kept in the station yard. The real danger, which transcends in gravity the danger of time destruction of loads of briquettes, is that the prevailing wind or a change of wind might carry showers of burning embers to the town, which is but the width of a road away, and thereby cause material damage in the town. It is further recommended that the yard and its surroundings be kept clear of scrub and growth; and that special provision be made for quelling fire which may break out in the deposits of inflammable dust which lie in time yard. |
REC016_3952 | 4 - Fire season preparation | It is recommended that the question of the future responsibility be made certain and that the body so made responsible keep the grounds of the hospital free from undergrowth and trees wherever their presence may be a possible source of future danger. |
REC016_3946 | 12 - EM agency and authority | It is recommended that it [The Fire Brigade] endeavour and be encouraged to add to its reserve of members, and that the reserves be fully and efficiently trained. Should fire on a wide, unbroken front attack the town, the brigade, if limited to its present numbers, could not be expected to be able to save the town. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3961 | 12 - EM agency and authority | It is recommended that each forestry officer should be stationed in one district for as long a time as is practicable consistent with justice to the officer. |
REC015_3958 | 12 - EM agency and authority | It is recommended that all members of the police force, members of brigades, municipal engineers and forest officers should be appointed as wardens. |
REC015_3957 | 12 - EM agency and authority | It is recommended that the functions of this authority should be primarily those of defining a general policy of prevention and suppression of bush fires and protection of life and property; of organizing and recruiting local brigades; of maintaining discipline of local brigades and over local fire authorities; and of acting independently, with or without such advice as it may care to take. |
REC015_3955 | 12 - EM agency and authority | The institution of a State Fire Authority is recommended. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3963 | 12 - EM agency and authority | The establishment of a Board, to be called "The Bush Fires Control Board" which shall operate in conjunction with the shire councils in connection with the prevention of bush fires and control of bush-fire organisations. |
REC013_3971 | 12 - EM agency and authority | To elect necessary officers. |
REC013_3970 | 12 - EM agency and authority | The Board may, at any time, require the Bush Fire Committees to report on the condition of their fire-fighting equipment, and on any other matter, which in their opinion, will tend to greater efficiency in their operations. |
REC013_3978 | 4 - Fire season preparation | Where possible to build stone or brick fireplaces for the use of travellers, teamsters, and drovers on the camping areas that are mostly used and where there is a risk of fire. |
REC013_3966 | 12 - EM agency and authority | Each member of the Board to act in an honorary capacity. |
REC013_3976 | 4 - Fire season preparation | To burn camping areas at suitable water and camping reserves. |
REC013_3965 | 12 - EM agency and authority | The Minister to have power to make regulations for the purpose of all proceedings of the Board, including the summoning and attendance of members, and the enforcement of orders of the Board. |
REC013_3964 | 12 - EM agency and authority | The Board shall consist of a Chairman and four other members, one member to be nominated each by the Graziers', Farmers and Settlers' and Agricultural Bureau Associations, one by the Fire Underwriters' Association, and one by the Government. |