REC327-4349 | 38 - Agency/Department Reporting | By December 2023, the Rural Fire Service should: develop performance measures to assess the performance and capabilities of the fleet in each RFS District by recording and publicly reporting on: fire response times and fire response outcomes; and, completions of fire hazard reduction works. |
REC327-4350 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: develop a fleet enhancement framework and strategy that is informed by an assessment of current fleet capability to respond to fire incidents, and research into the most appropriate technologies and appliances to address emerging and future fire risks across NSW. |
REC327-4345 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: review and improve processes for timely recording of fleet asset movements, locations, and maintenance status. |
REC327-4346 | 32 - Doctrine, standards, and reform | By December 2023, the Rural Fire Service should: establish a fleet maintenance framework to ensure regular update of District Service Agreements with local councils. |
REC327-4348 | 38 - Agency/Department Reporting | By December 2023, the Rural Fire Service should: report annually on fleet allocations to RFS Districts, and identify the ways in which fleet resources align with district-level fire risks |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4247 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends a collaborative review of firelines, tracks and trails on K’gari be undertaken by the Department of Environment and Science, in collaboration with the Locality Specific Area Fire Management Group and the Butchulla people, to ensure an adequate network is agreed by relevant stakeholders, and roles and responsibilities for maintenance are agreed and documented. |
REC322-4237 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science develop and implement a Wildfire Response Plan for Queensland Parks and Wildlife Service Coastal and Islands Region, to be included in the region’s Disaster Management Operations Plan. |
REC322-4232 | 11 - Evacuation and shelters | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to plan for the evacuation of K’gari due to bushfire. Once developed, the plan should be exercised and regularly reviewed. |
REC322-4250 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the Locality Specific Fire Management Group for K’gari meet at least twice per year, in person or virtually. |
REC322-4238 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science ensure that all Queensland Parks and Wildlife Service regions develop a Disaster Management Operations Plan based on a standardised format. The plans should include provision for annual review to ensure they remain contemporary, interoperable with relevant disaster management plans and aligned to the Department of Environment and Science Emergency Management Plan. |
REC322-4233 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science review the current description of Level 1, 2, and 3 bushfire incidents and the implied meaning of property in the Queensland Bushfire Plan. This review should identify and agree on clear criteria and decision points for the transfer of control and develop a standard process and templates. |
REC322-4241 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services consider expanding specialist Remote Area Firefighting Team capability to assist in responding to significant bushfire events which occur in rugged or inaccessible terrain. |
REC322-4234 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the Department of Environment and Science review its suite of operational doctrine to ensure arrangements for situational reporting and requests for assistance are aligned to recognised multi-agency practices used in disaster management. |
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
REC322-4227 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the membership of the K’gari Locality Specific Fire Management Group be expanded to include representatives of the Butchulla people, community associations from each township and tourism and business operators with interests on the island. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
REC322-4236 | 32 - Doctrine, standards, and reform | The Inspector-General Emergency Management recommends the arrangements and requirements for situational reporting when an incident is under the control of the Department of Environment and Science be detailed in the Queensland Bushfire Plan. These arrangements should also be outlined in relevant joint entity agreements and operational doctrine. |
REC322-4230 | 34 - Local knowledge | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services engages with land managers and other stakeholders on K’gari to source data to inform Predictive Services products. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4208 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) develops financial reporting to monitor fuel management costs and estimate future costs. |
REC321-4209 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) systemically documents and publicly reports reasons why it does not complete planned burns. |
REC321-4212 | 34 - Local knowledge | We recommend that DELWP increases its collaboration with Victorian Traditional Owner groups to facilitate the reintroduction of cultural burning and ensure effective support for these practices across all of its regions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4190 | 11 - Evacuation and shelters | Humanitarian relief: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions work with the Municipal Association of Victoria and councils to build contingencies into emergency relief centre planning to ensure places of shelter are inclusive, recognise diversity and are better placed to support all displaced people in circumstances of: |
REC319-4195 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, leads the development of a comprehensive, person-centred, trauma-informed recovery financial assistance system that establishes: |
REC319-4196 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, works with the emergency management sector to develop a recovery funding model that enables: |
REC319-4186 | 34 - Local knowledge | Supporting local recovery: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department work with councils and communities before, during and after emergencies to strengthen: |
REC319-4198 | 33 - Relief and recovery | Relief and recovery capability: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions works with the entity referred to in Recommendation 13, or otherwise responsible government department and/or Municipal Association of Victoria, councils and local relief and recovery organisations to provide centralised capability development opportunities to increase local capability and capacity to plan and deliver on their relief and recovery responsibilities: |
REC319-4187 | 33 - Relief and recovery | Recovery governance: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, work with councils, relevant recovery organisations and communities to develop clear roles and responsibilities for: |
REC319-4200 | 33 - Relief and recovery | Foundations of emergency management: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in consultation with the emergency management sector – establish policies and platforms to improve operational and personal information sharing between relief and recovery organisations. These policies and platforms should enable: |
REC319-4189 | 33 - Relief and recovery | Donated good: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4180 | 11 - Evacuation and shelters | The Inspector-General for Emergency Management recommends that Victoria Police – in collaboration with the community and the emergency management sector – reflect on events of the 2019–20 fire season to review and enhance evacuation plans and processes with consideration of: |
REC318-4177 | 38 - Agency/Department Reporting | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in conjunction with legislated fuel management organisations – develop a common set of objectives, metrics and reporting requirements for fuel management that form part of a compulsory regime that enables the Victorian Government to report publicly on a holistic fuel management program. The reporting requirements should: |
REC318-4173 | 32 - Doctrine, standards, and reform | The Inspector-General for Emergency Management recommends that in conjunction with Inquiry Recommendation 2, the State establish or assign responsibility to a single body or entity to lead and coordinate the implementation of evidence-based fuel management policy, practice and assurance and reporting on activities on both public and private land in Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4055 | 32 - Doctrine, standards, and reform | The Australian Government should revise the COMDISPLAN thresholds to provide that a request for Australian Government assistance, including Defence assistance, is able to be made by a state or territory government when: |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4119 | 33 - Relief and recovery | The Australian Government, through the mechanism of the proposed standing national recovery and resilience agency, should convene regular and ongoing national forums for charities, non-government organisations and volunteer groups, with a role in natural disaster recovery, with a view to continuous improvement of coordination of recovery support. |
REC317-4089 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4093 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review those plans, and update where appropriate, to provide for coordination between states and territories in cross border areas and to provide cross-border access to evacuation centres. |
REC317-4118 | 33 - Relief and recovery | Australian, state and territory governments should create a single national scheme for the regulation of charitable fundraising. |
REC317-4088 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4092 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review these plans, and update them where appropriate, to account for the existence and standard of any evacuation centres and safer places (however described) in the community, including: |
REC317-4072 | 32 - Doctrine, standards, and reform | The Australian Government should consider whether employment protections under the Fair Work Act 2009 (Cth) are sufficient to ensure that fire and emergency services volunteers will not be discriminated against, disadvantaged or dismissed for reasons associated with their volunteer service during natural disasters. |
REC317-4117 | 33 - Relief and recovery | State and territory governments should develop and implement efficient and effective arrangements to: |
REC317-4086 | 22 - Role of local Gvt | State and territory governments should review their arrangements for sharing resources between their local governments during natural disasters, including whether those arrangements: |
REC317-4127 | 33 - Relief and recovery | Australian, state and territory governments should incorporate the principle of ‘build back better’ more broadly into the Disaster Recovery Funding Arrangements. |
REC317-4091 | 11 - Evacuation and shelters | State and territory governments should provide further community education on the function and limitations of different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. This education should be nationally consistent. |
REC317-4064 | 32 - Doctrine, standards, and reform | Australian, state and territory governments should work together to develop consistent data standards to measure disaster impact. |
REC317-4116 | 33 - Relief and recovery | Governments should create and publish standing policy guidance on whether they will or will not assist to clean-up debris, including contaminated debris, resulting from natural hazards. |
REC317-4085 | 22 - Role of local Gvt | State and territory governments should take responsibility for the capability and capacity of local governments to which they have delegated their responsibilities in preparing for, responding to, and recovering from natural disasters, to ensure local governments are able to effectively discharge the responsibilities devolved to them. |
REC317-4126 | 33 - Relief and recovery | Australian, state and territory governments should expedite the development of pre-agreed recovery programs, including those that address social needs, such as legal assistance domestic violence, and also environmental recovery. |
REC317-4090 | 11 - Evacuation and shelters | State and territory governments should, as a priority, adopt nationally consistent terminology and functions for the different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. |
REC317-4104 | 33 - Relief and recovery | Australian, state and territory governments should refine arrangements to support localised planning and the delivery of appropriate mental health services following a natural disaster. |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4122 | 33 - Relief and recovery | Australian, state and territory and local governments should evaluate the effectiveness of existing financial assistance measures to inform the development of a suite of pre-effective pre-determined recovery supports. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4044 | 11 - Evacuation and shelters | A Relocation and Evacuation working group be established from stakeholder organisations to consider and develop an Evacuation and Relocations Sub- Plan. The Sub-Plan should consider the lessons learned this year and address principles, lead agency, WHoG coordination, trigger points etc. This could be the same working group formed for reviewing the Emergencies Act, Plan and sub-plans. |
REC316-4052 | 32 - Doctrine, standards, and reform | The ACT Emergencies Act 2004 be amended to clarify that the powers of the EC encompass the power to direct agencies and directorates to share personal information for the preservation of life and protection of Canberrans. |
REC316-4035 | 32 - Doctrine, standards, and reform | Review, refine and implement the joint ESA/EPSDD Arrangement for Fire Management in the ACT with the previous recommendation in mind. |
REC316-4051 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended so that the powers, including delegations, available to an EC be granted on their appointment and remain in place under the same section of the Act for the duration of their appointment rather than being drawn from different sections of the Act that are dependent on the existing alert state for the specified event. |
REC316-4025 | 32 - Doctrine, standards, and reform | The Emergency Plan and ECC Ops Plan be amended to better articulate the delivery of emergency management vs the delivery of the emergency plan. The Plan should facilitate principles for emergency management and clear role delineations whilst allowing flexibility in how the mechanisms are structured. |
REC316-4050 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended to allow for the provision for a Deputy Emergency Controller to be appointed, independent of the initial appointment of an EC. The powers and functions of this appointment to be contingent on the absence of the EC. |
REC316-4024 | 32 - Doctrine, standards, and reform | The Government consider amendments to the Emergencies Act to include provision for a Deputy ESA Commissioner. |
REC316-4049 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended to allow for the appointment of the EC to be made for a discretionary time period of up to 28 days with the requirement for a legislated review of the appointment to be removed. Alternatively, a period of review should fall within the Chief Ministers discretion for up to seven (7) days following appointment. |
REC316-4021 | 32 - Doctrine, standards, and reform | The Emergency Plan be amended to better reflect the intent of the Emergencies Act in the establishment of a Management Executive, separate to SEMSOG, on the appointment of an EC. It should describe the role of SEMSOG and the Management Executive as distinct in the emergency management architecture. |
REC316-4046 | 33 - Relief and recovery | Emergency Plan and Recovery sub-plans should be amended to better define recovery mechanisms and responsibilities, including hand over points to recovery authorities and community engagement for the delivery of long term recovery mechanisms. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3804 | 32 - Doctrine, standards, and reform | That the NSW RFS Commissioner consult with the Fire and Rescue NSW Commissioner and other emergency services to develop a protocol in the event that simultaneous emergency events necessitate the re-allocation of resources while a Section 44 declaration is in place. |
REC315-3844 | 32 - Doctrine, standards, and reform | That, in order to enhance fire fighting strategies in severe conditions, the NSW RFS implements the following in respect to backburning: |
REC315-3870 | 11 - Evacuation and shelters | That, in order to ensure the safety and wellbeing of vulnerable people during an evacuation, Resilience NSW: |
REC315-3820 | 32 - Doctrine, standards, and reform | That Government amend the Rural Fires Act 1997 so that all public land management agencies be required to forward complaints received about bush fire hazards to the Commissioner of the NSW RFS. As an interim measure, heads of agencies should commence this practice immediately. |
REC315-3814 | 11 - Evacuation and shelters | That the NSW RFS identifies remote bush fire prone areas that do not already have an indoor Neighbourhood Safer Place (NSP) and upgrades the relevant NSW RFS Stations to meet NSP guidelines. These stations would require adequate Asset Protection Zones and active/passive protection systems to provide short-term protection. |
REC315-3868 | 33 - Relief and recovery | That, in order to ensure people only need to tell their story once to access government agency support following an emergency, Resilience NSW and Service NSW jointly design an inclusive, person-centred approach to information collection at evacuation centres. This should be supported by an opt-in scheme enabling personal information to be shared between NSW government agencies, local councils and non-governmental organisations administering support services for disaster-affected people. |
REC315-3808 | 22 - Role of local Gvt | That, in order to strengthen the capability of local councils in future emergency events: |
REC315-3867 | 11 - Evacuation and shelters | That, in order to ensure evacuation centres are fit-for-purpose, Resilience NSW work with Local Emergency Management Committees (LEMCs) to: a) update the guidelines for LEMCs identifying evacuation centres to require a risk assessment of potential locations, which should include identifying alternate sources of power for use by evacuation centres and recording these appropriately |
REC315-3872 | 11 - Evacuation and shelters | That, in order to improve support for people evacuating with animals, the Department of Primary Industries: |
REC315-3805 | 32 - Doctrine, standards, and reform | That, to strengthen cross-agency accountability and deliver improved bush fire risk management outcomes: |
REC315-3866 | 11 - Evacuation and shelters | That, in order to ensure evacuation arrangements can be scaled up when needed, Resilience NSW: |
REC315-3871 | 11 - Evacuation and shelters | That, in order to ensure equitable access to evacuation centres and associated support services for people in border communities, Resilience NSW ensure cross-border access arrangements are reflected in evacuation centre management guidelines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3259 | 32 - Doctrine, standards, and reform | Implement previous review recommendations for bushfire management including those relating to the 2009 amendments to the Fire and Emergency Services Act 2005, State Bushfire Coordination Committee operation, State Bushfire Management Plan, as well as urgent completion of Codes of Practice for fuel hazard reduction on all land tenures, and redevelopment of Bushfire Management Area Plans accompanied by effective community engagement to build an understanding of risk. |
REC314-3269 | 32 - Doctrine, standards, and reform | Develop and practice procedures for the CFS, DEW and local governments to access and deploy heavy plant and machinery for fuel reduction operations both before and during bushfires. |
REC314-3266 | 14 - Incident Mgt Teams | Engage with the Australian Defence Force (ADF) once or twice a year to understand the capabilities that could potentially be deployed. Educate IMTs about how to deploy ADF assistance effectively and develop a streamlined ‘call out’ procedure. |
REC314-3265 | 14 - Incident Mgt Teams | Prepare to ‘scale up’ capability during major bushfire events with senior representatives (including BoM staff) in the SEC 24/7, ensure adequate facilities for IMTs, base camps (e.g. Humanihuts) and recovery centres. Consider the resource implications of providing firefighters to interstate operations. |
REC314-3260 | 32 - Doctrine, standards, and reform | Align risk assessment tools and processes to Risk Management Standard ISO 31000 and the National Emergency Risk Assessment Guidelines (NERAG) and communicate these on public-facing platforms. Make Bushfire Management Area Plans (BMAP) accountable for managing and reporting on region-specific risk and identifying critical infrastructure such as mobile phone towers as key risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
REC309-2479 | 34 - Local knowledge | Local groups should plan for and establish clear arrangements to effectively manage offers of assistance including the management of goods, services and volunteers. |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2456 | 22 - Role of local Gvt | A Local Government Association of Queensland representative should be included on the Crisis Communications Network to enhance the delivery of consistent information across and between levels of government. |
REC308-2455 | 32 - Doctrine, standards, and reform | The Queensland Offers of Assistance Policy, particularly for corporate donations, should be updated and exercised prior to the next season. |
REC308-2453 | 32 - Doctrine, standards, and reform | Business continuity planning should feature permanently in disaster management doctrine. |
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2441 | 32 - Doctrine, standards, and reform | Hazard-specific and disaster management guidelines and plans should explain the circumstances and process for hazard-specific activation of the disaster management arrangements in support of an incident. They should be relevant to local authorities and local and district groups, and used during events. |
REC307-2434 | 32 - Doctrine, standards, and reform | Given an increasing risk of intense fires, the framework of legislation relating to vegetation management, bushfire mitigation and preparation priorities should be re-assessed. The re-assessment should aim to enable more appropriate and flexible means at the local level for the reduction of intense fires. |
REC307-2432 | 32 - Doctrine, standards, and reform | Legislation at state and local level requiring landholders to reduce fire risk on their property should be actively applied |
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
REC307-2427 | 32 - Doctrine, standards, and reform | Wherever possible, the antecedents that will lead to catastrophic fire weather conditions existing for a particular area should be identified and documented within fire management plan relevant to the area. |
REC307-2443 | 32 - Doctrine, standards, and reform | Planning for response to bushfire risk should identify all stakeholders to be engaged in the response phase and their roles and responsibilities should be clearly documented. |
REC307-2426 | 32 - Doctrine, standards, and reform | Queensland's plans and arrangements for heatwave should be reviewed to provide for an intergrated multi-agency approach to their management. A single agency should lead and oversee this process. |
REC307-2442 | 32 - Doctrine, standards, and reform | Hazard-specific plans and guidelines should be published on external websites for access by relevant stakeholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2409 | 32 - Doctrine, standards, and reform | Formalise and clearly define the powers and duties of Bushfires NT personnel, including volunteers, thereby clarifying Bushfires NT’s role in bushfire management in the Northern Territory. |
REC304-2421 | 32 - Doctrine, standards, and reform | Include a detailed description of the role, responsibility and accountability of |
REC304-2408 | 32 - Doctrine, standards, and reform | Introduce clear Terms of Reference for the Bushfires Council and Regional Bushfires Committees, and introduce a requirement for the Minister to consider advice and recommendations from the Council. |
REC304-2420 | 32 - Doctrine, standards, and reform | Enshrine the broader fire management principles, including coordination, strategic planning, mitigation, monitoring and control within the Act. |
REC304-2418 | 32 - Doctrine, standards, and reform | Amend the object to provide for ‘The mitigation, management, and suppression of bushfires’. Definitions of these terms should be included in the Act, and should include clarification that bushfire suppression can include emergency response activities in certain circumstances |
REC304-2417 | 32 - Doctrine, standards, and reform | Amend the Act title to ‘Bushfires Management Act’. |
REC304-2415 | 32 - Doctrine, standards, and reform | Define formal bushfire management regimes for areas with different bushfire management requirements and define bushfire management responsibilities in those areas. One category will provide for areas that warrant provision of a wildfire response capacity, another will allow for the declaration of temporary fire management arrangements for the duration of identified high-risk circumstances. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2395 | 32 - Doctrine, standards, and reform | Remove those policies, guidelines, memoranda of understanding and committees that are made redundant as a result of adopting recommendation #2 while updating any remaining policies that are considered to still be relevant |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2387 | 32 - Doctrine, standards, and reform | TFS, PWS and STT agree an updated version of the Interagency Fire Management Protocol which maintains the principle that there will be one state-wide point of command for major unwanted fires burning in the State of Tasmania, explicitly recognises the right of each of TFS, PWS and STT to have their objectives prioritised in incident action planning and adequate resources applied to those objectives, and provides a mechanism for executive decision-makers from TFS, PWS and STT to come together and agree objectives and resourcing levels that will then be operationalised by whole-of-State control structures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1309 | 32 - Doctrine, standards, and reform | That members of Emergency Management Council ensure they are prepared to undertake their roles and responsibilities during emergency events, including establishing: a) contingencies for communication e.g. satellite phone b) access to relevant documents such as the State Emergency Management Plan, supporting plans, ministerial guidelines, agency plans and contacts in hard copy and/or portable device c) formalised arrangements for briefings (up and down), and d) arrangements for suitable representation e.g. relevant Chief Executive(s) or their deputy, at all Emergency Management Council meetings . |
REC295-1277 | 32 - Doctrine, standards, and reform | That the Department of Planning, Transport and Infrastructure review their Business Continuity Plan to: |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1289 | 32 - Doctrine, standards, and reform | That SA Police, emergency services, health facilities, utility providers and other key service providers, review their Business Continuity Plans giving consideration to factors such as: a) identification of: business critical needs; essential services power requirements; back-up power requirements for all facilities including State, regional and local facilities such as Police, SES, MFS and CFS stations; the need for any arrangements for back-up power to be included in contracts for design and or lease of Government premises b) contingencies for black system events and extended power outages c) regular back-up generator testing regime protocols, including testing under load and for long durations d) contingencies for communications when mobile, landline and/or radios are not operational e.g. satellite phones; and e) alternative State control centre facilities that are pre-identified, equipped and have procedures for moving to the alternative facility. |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1305 | 18 - Access to fire ground | That the annexure to the State Emergency Management Plan, ‘Traffic management during emergencies’, be updated to include: responsibilities and processes for road closures; and, Department of Planning, Transport and Infrastructure requirements in regards to provision of road closure information, notification of changes in road closure status and publishing of that information. |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
REC295-1323 | 32 - Doctrine, standards, and reform | Review and update the role, function, workload and focus of the groups/committees that contribute to incident management and emergency management capabilities including the State Emergency Management Training Committee, Interagency Incident Management Sub-Committee and the Central Exercise Writing Team. |
REC295-1287 | 32 - Doctrine, standards, and reform | That the glossary of terms in the State Emergency Management Plan be reviewed to ensure all relevant language is included. All agencies need to ensure the use of clear communication and accurate use of terminology, including in describing the status of critical services e.g. Triple Zero (000), SA Government Radio Network, electrical and water supplies and infrastructure. |
REC295-1333 | 32 - Doctrine, standards, and reform | Develop a State Relief and Recovery Plan as a distinct part of the State Emergency Management Plan which should include: a) potential locations for suitable facilities for relief and recovery centres which: are in locations safe from hazards such as flooding and bushfire; and, have appropriate access and suitable ablutions. b) formalisation of roles and capabilities of non-government organisations such as Red Cross |
REC295-1301 | 32 - Doctrine, standards, and reform | Establish an ‘Interstate Deployment Support Plan’ for incoming interstate resources. The plan should outline responsibilities and arrangements for this function. Consider including this plan into the State emergency management arrangements. |
REC295-1314 | 32 - Doctrine, standards, and reform | That an Emergency Management Assurance Framework be established as soon as possible to support the emergency management arrangements and the State Emergency Management Plan. Consider establishing an Inspector General Emergency Management department or position. |
REC295-1282 | 32 - Doctrine, standards, and reform | That the Office for Digital Government, in close partnership with telecommunications companies (e.g. Telstra, Optus, Vodaphone), develop a Control Agency Plan for Information and Communication Technology including mobile communications. The plan should consider: |
REC295-1332 | 32 - Doctrine, standards, and reform | Develop a Disaster Waste Management Plan to form part of the State Emergency Management Plan which describe participating agencies and responsibilities for various aspects of waste management during and after emergencies. |
REC295-1295 | 32 - Doctrine, standards, and reform | That resources be provided to support the implementation of recommendations in the South Australian Levee Bank Management Issues Paper (DEWNR, 2015) including: a) development of relevant policy; and b) identification of responsibilities in relation to levee management and flood mitigation |
REC295-1311 | 32 - Doctrine, standards, and reform | That the State Emergency Management Plan be reviewed and updated including: a) a better description of the responsibilities of Hazard Leaders Page xx b) establish a mechanism for a hazard leader to identify systemic failures in coordination of their hazard, with a clear process to raise those issues with SEMC and seek a remedy c) establish resilience as a key heading in the plan, with clearly documented strategies and responsibilities; and d) consider the Schar/Mulroney submission and taking a ‘fresh eyes’ approach |
REC295-1281 | 32 - Doctrine, standards, and reform | In order to increase resilience and public safety during emergencies, the State Emergency Management Committee should request the Australia and New Zealand Emergency Management Committee to place on the agenda, and consider establishing a national position, on redundancies for mobile communications (including phone tower back-up power) and the National Broadband Network. |
REC295-1331 | 32 - Doctrine, standards, and reform | Task South Australian Fire and Emergency Services Commission with further developing the Emergency Alerts capability across government agencies including to: a) establish and maintain a centralised training program for emergency alert initial and refresher training. b) establish a pool of endorsed Emergency Alert personnel from across government agencies to enable control agencies to assist each other with the emergency alert function during emergencies. c) develop supporting processes to ensure that the capability supports: emergencies involving any hazard; consistent issuing of alerts and warnings; consistent messages; and effective communication and notification of alerts issued to relevant internal and external stakeholders |
REC295-1292 | 32 - Doctrine, standards, and reform | That, giving consideration to the previous recommendation, the Flood |
REC295-1310 | 32 - Doctrine, standards, and reform | That additional guidance be provided in the State Emergency Management Plan regarding the activation, structure and operation of Zone Emergency Support Teams. This should include: a) the reporting relationship between the Zone Emergency Support Teams, the State Emergency Centre and the State Coordinator b) briefing requirements between the State Coordinator (or their representative) and the Zone Emergency Support Teams when the State Emergency Centre is activated c) responsibilities for provision of local public information; and d) the appointment of public information officers in Zone Emergency Support Teams (where there is no incident management team (established) to provide information to local communities |
REC295-1280 | 32 - Doctrine, standards, and reform | That a State Plan be developed for managing the consequences of a black system event or other major power outage. The plan should include: |
REC295-1330 | 32 - Doctrine, standards, and reform | Update the Public Information Functional Support Group Plan to include: a) standards, outputs, systems and processes required to be used by control agencies and the Public Information Functional Support Group during emergencies b) guidance on the public information cycle through the prevention, preparedness, response and recovery phases which includes the responsibilities and information requirements during different phases, and effective transition between phases c) establishing a public information intelligence cell within the Public Information Functional Service Group; and d) identifying tools or resources to monitor social media |
REC295-1290 | 32 - Doctrine, standards, and reform | Continue development of the Damage Assessment Support Plan to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1244 | 11 - Evacuation and shelters | The Department of Fire and Emergency Services to work with the Department of Planning and Local Governments to adopt a policy which enables Local Governments to identify, register and communicate, ‘Places of Bushfire Last Resort’ in settlements and townsites where the life risk from bushfire is very high or greater. |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
REC291-1247 | 32 - Doctrine, standards, and reform | The State Government to create a Rural Fire Service to enhance the capability for rural fire management and bushfire risk management at a State, regional and local level. The proposed Rural Fire Service will: · be established as a separate entity from the Department of Fire and Emergency Services or, alternatively, be established as a sub-department of the Department of Fire and Emergency Services; · have an independent budget; · be able to employ staff; · have a leadership structure which, to the greatest degree possible, is regionally based and runs the entity; · be led by a Chief Officer who reports to the responsible Minister on policy and administrative matters; and to the Commissioner for Fire and Emergency Services during operational and emergency response; · have responsibilities and powers relating to bushfire prevention, preparedness and response; and · operate collaboratively with the Department of Fire and Emergency Services, the Department of Parks and Wildlife, Local Government and volunteer Bush Fire Brigades. In creating the Rural Fire Service, the State Government to consider whether back office and corporate support services could be effectively provided by an existing Department, such as the Department of Fire and Emergency Services or the Department of Parks and Wildlife. The State Government to review the creation of the Rural Fire Service two years after its establishment, to assess whether its structure and operations are achieving the intended outcome. |
REC291-1238 | 32 - Doctrine, standards, and reform | The State Emergency Management Committee to adopt, across all hazards, the doctrine of: · the primacy of life; · the ‘Strategic Control Priorities’ (as documented by the Department of Fire and Emergency Services); and · community warnings that are timely, tailored and relevant. Agencies will reinforce amongst emergency management personnel the importance of this doctrine through briefings and intent statements. |
REC291-1246 | 18 - Access to fire ground | The State Emergency Management Committee to review the policy for traffic management at emergency incidents so it reflects national ‘best practice’. This includes the production and issuing of an aide-memoire to guide traffic management, emergency and incident management personnel. |
REC291-1245 | 18 - Access to fire ground | The Department of Fire and Emergency Services to issue a photo identification card to DFES members, members of Bush Fire Brigades, volunteer emergency services, Incident Management Teams, forestry industry brigade members and Networked Government Emergency Agency members. DFES also to consider temporary windscreen signage to identify vehicles carrying such personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1213 | 34 - Local knowledge | Structures to incorporate local knowledge and situational awareness into the fire response |
REC290-1211 | 32 - Doctrine, standards, and reform | Review of institutional arrangements in the fire sector |
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1200 | 32 - Doctrine, standards, and reform | The Committee finds that on the evidence presented, that the State Government should establish an independent Chair to govern the State Fire Commission and that this governance arrangement should be included in the reform of the governing legislation. |
REC288-1192 | 32 - Doctrine, standards, and reform | The Committee finds that on the evidence presented, that section 107 of the Fire Service Act should be amended to provide greater clarity in relation to discretionary spending by the Chief Officer or alternatively, the Act should be amended to include the authorisation for the State Fire Commission to directly fund the State Emergency Service. |
REC288-1191 | 32 - Doctrine, standards, and reform | The Committee finds that on the evidence presented, that a review and reform of the Fire Services Act 1979 is necessary. An investigation should be undertaken to assess how the legislation can be amended or replaced to best service the organisations subject to the Act and should be undertaken and completed within 12 months. The Fire Services Act 1979 must be reformed or replaced to allow for: (1) A centralised funding model for the State Emergency Services; (2) Streamlined approach to fire fighting between Tasmania Fire Service, Tasmania Parks and Wildlife Service, Forestry Tasmania and other relevant agencies; (3) Resources to be allocated according to the risk and not according to local government municipal boundaries; (4) The continuation of Tasmania having a singular fire service; (5) Clear reporting lines; (6) Improved governance structure; and, (7) Include the fire permit system and inter- agency protocols. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1182 | 32 - Doctrine, standards, and reform | The fire agencies consider how the Regional Fire Operations Centre (RFOC) as a concept adds value once a level 3 IMT is up and running in a region. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1203 | 22 - Role of local Gvt | Impact Assessment Data Sharing The Office of Emergency Management: · with the SEOCON, jointly provides further guidance to Regional Emergency Management Officers about their role in facilitating local council access to the Impact Assessment Data Base · with REMOs and the SEOCON jointly provides further information to local councils about Impact Assessment Data Sharing Arrangements and the data available through this mechanism · includes information about the Impact Assessment Data Sharing Arrangements in the Local Recovery Toolkit · develops a mechanism to allow local councils to have direct access to the collated impact data. |
REC281-1207 | 33 - Relief and recovery | Communicating in Recovery: The Office of Emergency Management: · considers the development of a communications and engagement strategy for major disaster events · progresses the development of the ‘Communicating In Recovery’ Guideline in the Local Recovery Toolkit. |
REC281-1206 | 33 - Relief and recovery | Transition from Response to Recovery: That Region Emergency Management Committees meet post event to: · consider available impact data · determine the need to establish a Recovery Committee · document the rationale for the decision · advise the Office of Emergency Management of the decision. |
REC281-1204 | 33 - Relief and recovery | Transition from Response to Recovery That the Office of Emergency Management, in consultation with the NSW Police Force Emergency Management Unit develops a template for handover of the Response to Recovery Phase of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1403 | 32 - Doctrine, standards, and reform | That the Ministry for Police and Emergency Services urgently review its policies for the provision of disaster welfare services to ensure that in the event of a bush fire emergency and the declaration of a fire under section 44 of the Rural Fires Act 1997, adequate funding and services, especially recovery centres and mental health services, are provided for an adequate length of time, with gradual transition to normal service delivery when those services are no longer required. |
REC280-1397 | 32 - Doctrine, standards, and reform | That the NSW National Parks and Wildlife Service adopt an interim fencing agreement in the immediate aftermath of a fire. This will enable emergency and interim works to commence, but features such as length, fencing components and site of the fence line are not binding. A final fencing agreement would be negotiated no earlier than six months following a major national park fire. |
REC280-1395 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service reassess the protection of pastoral assets during bush fires to ensure that priority for protection is not simply afforded to the homestead, and that land holders are, within reason, able to request which of their own assets are protected. |
REC280-1391 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service review its procedures, systems and infrastructure for notifying community members of bush fires, both when a fire has broken out and as it proceeds, to ensure the provision of timely and adequate information. |
REC280-1390 | 32 - Doctrine, standards, and reform | That the NSW Government consider enabling the default position during catastrophic and extreme fire danger periods to be the same as for section 44 fires, so that fire control centres have the same systems and resources ready to deploy should a fire break out. |
REC280-1389 | 32 - Doctrine, standards, and reform | That the NSW Government, as a matter of urgency, amend the Rural Fires Act 1997 to codify the current interim arrangements for command and notification requirements for class 1 and class 2 fires, which clarify that the NSW Rural Fire Service or Fire and Rescue NSW: |
Rec-ID | Code | Recommendation |
---|---|---|
REC278-1225 | 32 - Doctrine, standards, and reform | The committee recommends that the Australian and Tasmanian Governments: • develop options to increase co-operation to ensure that the Tasmanian Wilderness World Heritage Area is protected and conserved in line with Australia's obligations under the World Heritage Convention; and • work together to ensure strong provisions to protect the Tasmanian Wilderness World Heritage Area from bushfire risks are included in the Tasmanian Wilderness World Heritage Area Management Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1165 | 32 - Doctrine, standards, and reform | Clarify the role of the ROC and SOC and their reporting relationships: The ROC and SOC have important coordination roles under the State Emergency Management Arrangements to support both the incident and the broader region and state. Clarifying the role of the ROC and SOC, their reporting relationships, and how the command structures of other agencies are integrated, will have three main benefits: the ROC and SOC can perform their functions effectively • no inconsistencies, gaps or duplication in the activities of the IMT, ROC and SOC • transparency of incident management |
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC275-1174 | 32 - Doctrine, standards, and reform | IGEM recommends that fire agencies consider an earlier classification of Level 3 incident for fires that present significant complexity such as was evident in the Wye River – Jamieson Track event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1129 | 32 - Doctrine, standards, and reform | Incorporating ‘triggers’ within Chief Officers Standing Orders No. 17, which requires the escalation of the State Controller role to the rank of Assistant Chief Officer or greater, depending on the increased risk or activity. |
REC273-1142 | 18 - Access to fire ground | That SACFS consider the Traffic Management Procedures and guiding principles adopted in Tasmania as a model that could be implemented within SA. |
REC273-1128 | 32 - Doctrine, standards, and reform | Incorporate in operational doctrine the ability for the State Controller to determine the operational readiness levels of the state or regions based on either the predicted and/or actual risk and/or activity to some or all of the regions. |
REC273-1139 | 14 - Incident Mgt Teams | SACFS appoint the Regional Controller and/or Coordinator as the IC for any Level 3 incident occurring within their Region to provide better continuity and improved coordination. The position of the regional controller and/or coordinator could then be backfilled by a suitably qualified individual as required. |
REC273-1138 | 14 - Incident Mgt Teams | Review the communication and request procedures within SACFS to ensure that the most effective chain of command and line of communications are established between the Incident Management Team, region and state. |
REC273-1135 | 14 - Incident Mgt Teams | That SACFS conduct a review of SIMT with a view to increasing the number of teams from four to six, aligning them with each of the six regions within SA. |
REC273-1145 | 32 - Doctrine, standards, and reform | Review relevant Legislation associated Acts and Plans to establish a consistent approach to fire and emergency management to minimise duplication and risk of contradiction. That the Hazard and Functional area plans be amalgamated and establish a SA Bushfire Plan, under the SEMP, which clearly define role of SACFS. |
REC273-1133 | 32 - Doctrine, standards, and reform | That a complete review of current naming conventions of personnel and centres, in accordance with the outcomes of the Victorian Bushfire Royal Commission is undertaken, to ensure clarity around command, control and coordination within SA. |
REC273-1143 | 32 - Doctrine, standards, and reform | That SACFS in consultation with SAMFS consider adopting common terminology and capability requirements for strike teams being ‘4-5 appliances and a group officer’ in line with other jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
REC272-1417 | 32 - Doctrine, standards, and reform | That the following disaster management doctrine are reviewed and reissued to ensure consistency and improved guidance to local government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1156 | 33 - Relief and recovery | Streamlining NDRRA Grants Processes |
REC267-1155 | 33 - Relief and recovery | MP Recovery Reference Group |
REC267-1148 | 33 - Relief and recovery | Planning for Recovery Centres Recovery Centres are a proven means of providing support to affected communities. More comprehensive recovery planning is needed at local levels, including the identification of potential Recovery Centre sites in Local EM Plans to help facilitate streamlined establishment of the Centres in future events. Consideration should be given to developing a clear set of standard messaging regarding |
REC267-1163 | 33 - Relief and recovery | Corrections Volunteer Labour Teams |
REC267-1161 | 33 - Relief and recovery | VIP Visits |
REC267-1160 | 33 - Relief and recovery | Transition from Response to Recovery |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1122 | 18 - Access to fire ground | DFES, in consultation with bushfire volunteers should develop a procedure for the controlled entry and exit of volunteers to the fire ground |
REC265-1107 | 32 - Doctrine, standards, and reform | Standard Operating Procedure 1 (Mobilisation Zone 2, Perth Hills area) should be reviewed to ensure that appropriate escalation triggers and levels of operational readiness are in place for future periods when severe fire weather conditions are forecast. |
REC265-1121 | 18 - Access to fire ground | A Restricted Access Permit system for the entry/ re-entry of residents, based on the one developed for the Parkerville Stoneville Mt Helena Bushfire should be finalised. |
REC265-1127 | 33 - Relief and recovery | Consultation should be undertaken with agencies and organisations that are engaged in emergency welfare provision to identify more effective ways to provide a consistent message to the community that non-cash donations are not required. |
REC265-1100 | 32 - Doctrine, standards, and reform | The forthcoming review by SEMC of SEMP 4.4 Recovery Coordination and Westplan – Recovery Coordination and SEMP 4.1 Incident Management should include consideration of: |
REC265-1114 | 32 - Doctrine, standards, and reform | Procedures should be reviewed to address the risks associated with response aircraft all working from one forward operating base, including the need for a designated fire protection unit to be available in the event of an aircraftrelated fire or other emergency incident |
REC265-1126 | 33 - Relief and recovery | Development of a template contract for the clean-up of affected properties to speed-up the process; |
REC265-1113 | 32 - Doctrine, standards, and reform | The role of the Ground Controller should be reaffirmed in operational doctrine and reinforced in Incident Management Team training. During incidents involving aircraft the appointment of a Ground Controller should be confirmed by the Incident Controller |
REC265-1125 | 33 - Relief and recovery | Consultation with the Board of the Lord Mayor’s Distress Relief Fund and other disaster appeal organisers should be undertaken to determine the potential for software development to consolidate the application and approval process, including provision of templates and application forms; |
REC265-1110 | 32 - Doctrine, standards, and reform | Whenever a Bush Fires Act 1954 section 13 transfer of control is invoked, the Incident level of an event should also be reviewed and any changes documented. |
REC265-1124 | 32 - Doctrine, standards, and reform | EMP 4.4 and Westplan – Recovery Coordination should be amended to: clarify the wording around handing over control of the incident from the Controlling Agency to local government and the transition from response to recovery; include principles and criteria that will assist the Controlling Agency and local government to determine the best time to effect a hand over of control of the incident; make explicit the roles and responsibilities of the parties involved in the handover of control of the incident; specify the information required in the needs and impact assessments provided to local government by the Controlling Agency so that local government is given sufficient information to take control of incidents; clarify the roles, responsibilities and the title of the State Recovery Controller and ensure that the appropriate wording is reflected in Westplans and State Emergency Management Policies; Hazard Management Agencies, combat and support agencies and local governments need to fully inform themselves of the role of the State Recovery Controller and implement a more effective approach to communicating |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1080 | 32 - Doctrine, standards, and reform | The State develop and widely disseminate an integrated State Smoke Guide, to: • incorporate the proposed State Smoke Plan for the management of public health impacts from large scale, extended smoke events; • include updated Bushfre Smoke, carbon monoxide and PM protocols; and 2.5 • provide practical advice and support materials to employers, communities and individuals on how to minimise the harmful effects of smoke. |
REC264-1079 | 32 - Doctrine, standards, and reform | The State review and revise the Bushfre Smoke Protocol and the PM Health Protection Protocol, to: 2.5 • ensure both protocols are consistent with each other; and • ensure both protocols include assessment methods and trigger points for specifc responses. |
REC264-1078 | 32 - Doctrine, standards, and reform | The State review and revise the community carbon monoxide response protocol and the firefghter carbon monoxide response protocol, to: |
REC264-1077 | 32 - Doctrine, standards, and reform | The State take the lead in advocating for a national compliance standard for PM |
REC264-1088 | 32 - Doctrine, standards, and reform | GDF Suez adopt and apply the firefghter carbon monoxide response protocol. |
REC264-1075 | 32 - Doctrine, standards, and reform | The State: • bring forward the commencement date of s.16 of the Mineral Resources (Sustainable Development) Amendment Act 2014 (Vic), to facilitate the requirement that approved work plans specifcally address fre prevention, mitigation and suppression; and • acquire the expertise necessary to monitor and enforce compliance with fre risk measures adopted by the Victorian coal mining industry under both the mine licensing and occupational health and safety regimes. |
REC264-1084 | 32 - Doctrine, standards, and reform | GDF Suez revise its Emergency Response Plan, to: • require an increased state of readiness on days of Total Fire Ban; • require pre-establishment of an Emergency Command Centre; • require pre-positioning of an accredited Incident Controller as Emergency Commander; and • require any persons nominated as Emergency Commander to have incident controller accreditation and profciency in the use of the Australasian Inter-service Incident Management System. |
REC264-1074 | 32 - Doctrine, standards, and reform | The State enact legislation, to: • require Integrated Fire Management Planning; and • authorise the Emergency Management Commissioner to develop and implement regional and municipal fire management plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1512 | 32 - Doctrine, standards, and reform | That the NSW Rural Fire Service reassess the protection of pastoral assets during bush fires to ensure that priority for protection is not simply afforded to the homestead, and that land holders are, within reason, able to request which of their own assets are protected. |
REC261-1509 | 34 - Local knowledge | That the NSW Rural Fire Service, in order to ensure greater respect for volunteer fire fighters’ knowledge and experience in the management of fires: |
REC261-1506 | 32 - Doctrine, standards, and reform | That the NSW Government, as a matter of urgency, amend the Rural Fires Act 1997 to codify the current interim arrangements for command and notification requirements for class 1 and class 2 fires, which clarify that the NSW Rural Fire Service or Fire and Rescue NSW: |
REC261-1520 | 33 - Relief and recovery | That the Ministry for Police and Emergency Services urgently review its policies for the provision of disaster welfare services to ensure that in the event of a bush fire emergency and the declaration of a fire under section 44 of the Rural Fires Act 1997, adequate funding and services, especially recovery centres and mental health services, are provided for an adequate length of time, with gradual transition to normal service delivery when those services are no longer required. |
REC261-1516 | 32 - Doctrine, standards, and reform | That the NSW National Parks and Wildlife Service remove from its boundary fencing policy and standard contract the condition that requires adjoining land owners to maintain a fence that has been damaged by trees falling from national park land. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1056 | 32 - Doctrine, standards, and reform | That the Rural Fire Service and National Parks and Wildlife Service consider adopting the approach to fire classification suggested by Mr Conway that “classification and resourcing of the fire ground response and incident management capability should reflect the potential of the fire rather than observed fire behaviour. |
REC260-1069 | 32 - Doctrine, standards, and reform | That NPWS conduct a review of its hazard reduction policies to ensure all assets within and on the boundary of the Park are clearly identified and an adequate policy or management plan exists for the protection of all assets, including a procedure pursuant to which progress in meeting hazard reduction targets is regularly and comprehensively assessed. |
REC260-1055 | 34 - Local knowledge | That the Rural Fire Service together with other land managers develop a program whereby local stakeholders come together regularly (every 2 months during non-fire season and monthly during the fire season) to share intelligence and to consider hazard and incident management measures for implementation. |
REC260-1066 | 14 - Incident Mgt Teams | That during periods of ‘severe’ or worse fire conditions, that the National Parks and Wildlife Service consider adopting a posture of pre-emptive planning and deployment of incident management teams in national parks similar to the manner in which the Rural Fire Service does. |
REC260-1053 | 14 - Incident Mgt Teams | That in Class 3 fire-fighting operations, the Rural Fire Service consider including a fire behaviour analyst in the incident management team if feasible. |
REC260-1065 | 32 - Doctrine, standards, and reform | That the National Parks and Wildlife Service review its procedures for monitoring Class 1 fires occurring in ‘severe’ or worse fire conditions that cannot be reconnoitred at ground level adequately due to terrain or dangerous conditions, and consider including aerial surveillance (if reasonably practicable) as a standard procedure in such circumstances. |
REC260-1052 | 14 - Incident Mgt Teams | That the Rural Fire Service consider amending its fire prediction reports to include a checklist of significant factors that have not been able to be considered in the prediction model and a warning to be alert for them and seek intelligence on them from fire ground managers. |
REC260-1064 | 32 - Doctrine, standards, and reform | That the National Parks and Wildlife Service review its protocols for control of Class 1 fires under its control to ensure that incident controllers managing fires in ‘severe’ or worse fire conditions receive as much incident management planning support as is reasonably practicable in the circumstances. |
REC260-1061 | 18 - Access to fire ground | That the National Parks and Wildlife Service, in consultation with the relevant local Council(s), devise a policy that enables the John Renshaw Parkway to be closed at either end of the Warrumbungle National Park during a bush fire in such a way that its closure would not impede access by emergency services vehicles into the park. |
Rec-ID | Code | Recommendation |
---|---|---|
REC259-1043 | 33 - Relief and recovery | That a single victim registration form be designed, which captures all relevant details required for use by any support agency both in the Response Phase at Evacuation centres and during the Recovery Phase. That such documents when completed form part of a wider database which can be accessed by all relevant agencies |
REC259-1046 | 33 - Relief and recovery | That prior to the commencement of any major clean-up, firm policy be established and made known to the extent to which material removal will be the responsibility of the home owner, the Council or the State led recovery effort. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1554 | 32 - Doctrine, standards, and reform | All documents be reviewed to remove ambiguity and perceived inconsistencies. Marrangaroo Training Area Range Standing Orders be subject to further examination, with particular consideration of the bushfire mitigation strategies referred to in the Bushfire Management Plan 2011-2014 before amendments to Chapter 10 are made. the basis upon which Range Standing Orders might fix a cut-off point for live-firing exercises should depend on continued bushfire strategies. Range Standing orders and Marrangaroo Training Area Bushfire Management Plan be reviewed annually. if hazard reduction has not occurred or the fire trails degraded, Range Standing Orders should take into account of heightened risk. |
REC257-1543 | 32 - Doctrine, standards, and reform | Range Standing Orders be amended to include a direction that no Defence vehicle is to leave the administration area of Marrangaroo Training Area during a bushfire, except to leave Marrangaroo Training Area itself through the main gate, unless it is a properly equipped bushfire fighitng vehicle havig at least four wheel drive capabiliy and self-protection equipment. |
REC257-1553 | 32 - Doctrine, standards, and reform | On matters relating directly to safety or risk, or when live-firing may occur, where there is ambiguity or apparent inconsistency, the most conservative or restrctive order should be followed until formal clarification has been provided. |
REC257-1538 | 32 - Doctrine, standards, and reform | Commanding Officer Defence Explosive Ordnance Training School amend relevant instructions, both generally and specifically, so as to ensure that explosive ordnance used in training serials is logged in real time, in accordance with extant doctrine. |
REC257-1552 | 32 - Doctrine, standards, and reform | Authority be given to the regional Environmental Officer to close a range or impose live-firing restriction in addition to any set out in Range Standing Orders if circumstances so warrant. |
REC257-1537 | 32 - Doctrine, standards, and reform | Commanding Officer Defence Explosive Ordnance Training School review and enforce Standard Operating Procedures to ensure that appropriate explosive ordnance accounting and handling practices, in accordance with Defence doctrine, are adhered to during all training activities. |
REC257-1551 | 32 - Doctrine, standards, and reform | The use of Internal and External ranges at MTA for patrolling activities be prohibited. |
REC257-1550 | 32 - Doctrine, standards, and reform | Defence engage with both the Bureau of Meteorology and the Rural Fire Service to determine a more suitable index system. In the interim, Range Standing Orders be amended so that live-firing on the ranges on Marrangaroo Training Area not be permitted where the Forest Fire Danger Index for either the Central Ranges District or Greater Sydney Region is 12, it being the threshold for HIGH Fire Danger Rating or above. put another way, and in a practical sense, Range Standing Orders should, as an interim measure, require the Officer in Charge Practice and the Range Control Officer to consider the Forest Fire Danger Index for both Central Ranges District AND Greater Sydney Region on the day of any given serial. If either index is as 12 or above, live-firing should not be permitted. Any indication in Range Standing Orders or elsewhere that live-firing is permitted on Marrangaroo Training Area when the Fire Danger rating is HIGH should be rescinded. |
REC257-1555 | 14 - Incident Mgt Teams | The lines of responsibility be made clearer and some individual, perhaps the Regional Environmental Officer, or agency be given overarching responsibility to ensure recommended works related to bushfire mitigation on Defence Estate are carried out in accordance with the Bushfire Management Plan which the Manual for Fire Protection Engineering directs be prepared. |
REC257-1549 | 32 - Doctrine, standards, and reform | Marrangaroo Training Area Range Standing Orders should be reviewed to impose a requirement that the Officer in Charge of any live-firing practice ascertain and consider current weather parameters, temperature, humidity, wind strength and direction, registered at Mt Boyce immediately prior to any demolition serial. The setting of those parameters and their limits should be decided in consulation with the Bureau of Meteorology and Rural Fire Service and inserted into Range Standing Orders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
REC254-1584 | 32 - Doctrine, standards, and reform | DFES or DEC (depending on land tenure) is mandated to take over control of emergency incidents from Local Government once they have been declared Level 2 incidents. WESTPLAN BUSHFIRE and legislation to be amended accordingly. |
REC254-1580 | 32 - Doctrine, standards, and reform | Critical operational procedures such as ‘Red Flag Warnings’, on a common fireground need to be consistent across DFES, DEC and Local Government. In particular, the operational procedure of Red Flag Warnings needs to be adopted by all WA fire agencies. |
REC254-1588 | 32 - Doctrine, standards, and reform | WA fire agencies adopt a common set of standing orders, operational procedures, training and competencies for rural firefighting that are produced in hard copy, leading to integrated multi-agency training, IMTs, Regional and State coordination/control centres. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0877 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service reviews its approach to fire management operations at night, and develop and effectively implement unambiguous policy and operating procedures. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0862 | 14 - Incident Mgt Teams | That Tasmania Fire Service and its partner agencies establish a means of monitoring and reviewing the effectiveness of centralising the location of Incident Management Teams. |
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0912 | 32 - Doctrine, standards, and reform | That the State Fire Commission finalise its position on the Tasmania Bushfire Safety Policy without further delay. |
REC247-0870 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service considers adopting a primary tactic of an aggressive first attack on fires. |
REC247-0890 | 11 - Evacuation and shelters | That decisions to open Community Fire Refuges and evacuation centres be coordinated with Tasmania Police. |
REC247-0940 | 32 - Doctrine, standards, and reform | That the Government actively support the timely development and implementation of an ongoing Strategic Fuel Management Plan. |
REC247-0876 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service reviews its approach to blacking out and mopping up, including its policies, operating procedures and training. |
REC247-0901 | 11 - Evacuation and shelters | That evacuation centres and other centres have plans and arrangements for electrical power redundancy. |
REC247-0861 | 14 - Incident Mgt Teams | That Tasmania Fire Service examines options for developing and issuing fire management objectives and tactics from Incident Management Teams in a more timely way, including ‘quick’ plans. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0911 | 14 - Incident Mgt Teams | That emergency management plans specifically include processes and resources for effectively engaging with and using local communities, including volunteers |
REC247-0869 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service ensures that planning for active fires includes a proactive approach wherever possible. |
REC247-0889 | 11 - Evacuation and shelters | That Tasmania Police be identified as the lead agency on evacuations. |
REC247-0930 | 32 - Doctrine, standards, and reform | That the State Emergency Management Committee determine suitable risk management tools, such as the Bushfire Risk Assessment Model, and encourages their use in assessing bushfire risk in a consistent manner. |
REC247-0875 | 34 - Local knowledge | That Tasmania Fire Service reviews its integration of rural local knowledge and volunteer brigades into fire operations, develops and maintains appropriate strategies, and aims to be a best-practice fire service in this regard. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
REC247-0853 | 14 - Incident Mgt Teams | That the State Controller (or an alternate if they are not available) be expected to personally take an active role in controlling and coordinating response and recovery operations, depending on the nature and scale of the emergency, and until other identified arrangements for ongoing operations are established. |
REC247-0883 | 32 - Doctrine, standards, and reform | That Tasmania Police ensures planning for emergency operations includes a proactive approach wherever possible. |
REC247-0910 | 33 - Relief and recovery | That suitable facilities are established from which to effectively control and coordinate immediate recovery operations. |
REC247-0865 | 34 - Local knowledge | That Tasmania Fire Service reviews its position on using local experienced officers on the fire ground in the command model in a structured and systemic way. |
REC247-0888 | 11 - Evacuation and shelters | That arrangements are made and appropriate pre-planning occurs to effectively implement the policy on evacuation. |
REC247-0929 | 32 - Doctrine, standards, and reform | That the State Emergency Management Committee considers structuring the Tasmania Emergency Management Plan in a way that provides more specific guidance, commitment to and accountability for action to be taken. |
REC247-0874 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service reviews operational practices to ensure there is continuity of fire operations when fire suppression action is required. |
REC247-0898 | 32 - Doctrine, standards, and reform | That the State Special Emergency Plan–Recovery and the emergency management structure for recovery be reviewed. |
REC247-0852 | 32 - Doctrine, standards, and reform | That the role and expected duties of the State Controller be clearly defined in the Emergency Management Act 2006. |
REC247-0882 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service documents and publishes its operational policies and procedures so they are accessible to and suitable for operational personnel. |
REC247-0908 | 32 - Doctrine, standards, and reform | That the State Emergency Management Committee examine whether there are any legal issues associated with continuing recovery operations where the overarching emergency management arrangements have ceased. |
REC247-0864 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service reviews its position on fire ground management to determine whether a unified command model at the fire ground should be adopted. |
REC247-0887 | 11 - Evacuation and shelters | That qualifying the evacuation authority in section 47 of the Fire Service Act 1979 be considered — by exempting those people with a pecuniary interest in a property from a directed evacuation where it is reasonable for them to remain. |
REC247-0914 | 32 - Doctrine, standards, and reform | That the Tasmanian Emergency Management Plan includes a comprehensive all hazards communications policy and plan. |
REC247-0872 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service considers what adjustments may be necessary to the promotion and use of the Six Operational Priorities to ensure plans are suitable for the circumstances of each fire. |
REC247-0897 | 32 - Doctrine, standards, and reform | That a standing plan is developed to manage the transition from immediate recovery to medium and long-term recovery, and arrangements are made to ensure this plan can be effectively implemented in a timely way. |
REC247-0950 | 32 - Doctrine, standards, and reform | That resources are committed to developing and implementing approved reforms to the emergency management arrangements. |
REC247-0881 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service establishes sufficient resources and expertise to research, develop, implement and review its policies and operations. |
REC247-0907 | 33 - Relief and recovery | That the State Emergency Management Committee ensures that a program of debriefing on recovery issues is completed by all relevant agencies and organisations, and detailed plans and operating procedures are established ready for implementation. |
REC247-0863 | 34 - Local knowledge | That Tasmania Fire Service considers measures to bring local knowledge into Incident Management Team operations. |
REC247-0886 | 11 - Evacuation and shelters | That a state-level policy on evacuations be developed in the emergency management plans, including specific requirements for vulnerable people and guidelines for its implementation. |
REC247-0913 | 32 - Doctrine, standards, and reform | That the State Fire Commission structures its Tasmania Bushfire Safety Policy so policy outcomes are identifiable and progress in achieving outcomes can be evaluated. |
REC247-0871 | 32 - Doctrine, standards, and reform | That Tasmania Fire Service critically reviews the operation of the Six Operational Priorities to determine whether they are appropriate and effective. |
REC247-0896 | 33 - Relief and recovery | That the state level structural arrangements for managing recovery operations are reviewed. |
REC247-0949 | 32 - Doctrine, standards, and reform | That following any review, the Emergency Management Act 2006 be amended. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0780 | 32 - Doctrine, standards, and reform | TFS develop MOUs with interstate fire agencies and land management authorities to formalise agency to agency resource sharing/mutual aid protocols that ensure the effective deployment of interstate resources for all roles from fire ground to state control, and management of those resources within pre-established criteria. |
REC246-0779 | 32 - Doctrine, standards, and reform | TFS review all areas in which the SFOC has a role and ensure that robust policy and protocols are finalised to ensure that corporate knowledge is widely accessible and is not held solely by individuals. |
REC246-0778 | 32 - Doctrine, standards, and reform | TFS review the Inter-Agency Fire Management Protocol and the Terms of Reference (ToR) of the Multi-Agency Coordination Group (MAC), to ensure that the Inter-Agency Fire Management Protocol accurately reflects the role and functions of the State Fire Operations Centre (SFOC) and clearly establishes and communicates the role and functions of the MAC Group. |
REC246-0777 | 32 - Doctrine, standards, and reform | TFS finalise and sign off the State Fire Protection Plan (SFPP). All the documents named in the SFPP should be finalised and available to relevant stakeholders to support the SFPP. |
REC246-0776 | 32 - Doctrine, standards, and reform | All Tasmanian fire agencies seek to have the State Bushfire Policy finalised and signed-off at the required level of government. |
REC246-0786 | 14 - Incident Mgt Teams | TFS develop written guidelines for the use of IMTs about the use of evacuation in a bushfire context, and triggers for decision-making. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1031 | 32 - Doctrine, standards, and reform | That the State Government recognises the legal status of rural fire brigades as per Crown Law advice and addressed by Recommendations from this Review. |
REC241-1013 | 32 - Doctrine, standards, and reform | That Rural Fire Service Queensland undertake a risk management process for rural fire Brigade profiles across Queensland based on the principles in the Rural Fire Brigade Risk Management Guide, July 1999, and updated as necessary. |
REC241-1011 | 32 - Doctrine, standards, and reform | That the focus of Rural Fire Service Queensland will be the protection of life, property and the environment from the threat and impact of wildfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1611 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should specify preparation and approval requirements for bushfire operational plans, particularly those for lands in the Bushfire Abatement Zone. |
REC228-1608 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should review the operations of the Strategic Bushfire Management Plan Implementation Working Group to determine if it is the most appropriate mechanism for ‘monitoring the scope and effectiveness’ of the Strategic Bushfire Management Plan. If it is retained, ways to improve its effectiveness should be identified and implemented. |
REC228-1621 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should improve its management of the Community Fire Unit Program by: |
REC228-1607 | 32 - Doctrine, standards, and reform | The Justice and Community Safety Directorate, in managing future amendments to the Emergencies Act 2004, should propose amendments which require the Emergency Services Agency to maintain information on privately-owned assets of public interest that are vulnerable to bushfire without the need to include this information in the Strategic Bushfire Management Plan. |
REC228-1615 | 38 - Agency/Department Reporting | The Territory and Municipal Services Directorate, as part of its Bushfire Operations Plan monitoring and reporting, should assess and publicly report on cumulative progress against broader outcomes identified in the Regional Fire Management Plans and the Strategic Bushfire Management Plan. |
REC228-1606 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should comply with the Emergencies Act 2004 requirements for the Strategic Bushfire Management Plan by including in this Plan an explicit statement of all resources needed to meet the objectives of the Plan. |
REC228-1613 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should continue to work with National Land managers and develop a National Land bushfire management framework to address bushfire risks on National Land. |
REC228-1612 | 32 - Doctrine, standards, and reform | The Emergency Services Agency should develop a strategy for monitoring the development and implementation of all Government land managers’ operational plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0559 | 22 - Role of local Gvt | Early contact with the LG A is critical. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0593 | 22 - Role of local Gvt | Good Local Government planning and management facilitates community resilience. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0598 | 33 - Relief and recovery | When communities are grieving there is a need to provide special forms of support to affected residents. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0580 | 32 - Doctrine, standards, and reform | The role of district and local emergency management committees should be reviewed to ensure they are appropriately engaged in the active management of emergencies across the PPR R continuum |
REC226-0592 | 11 - Evacuation and shelters | Decisions on evacuations need to be made early enough for people to be fully informed, prepared and to move to a place of greater safety. Failure to conduct good planning can create situations where loss of life can occur |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0597 | 22 - Role of local Gvt | Given the prominent role played by the Shire in the management of welfare aspects in this emergency, there may be a need for state sponsored training for shire staff who are involved in implementing state emergency management policies and plans including how to deal with traumatised individuals. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0579 | 32 - Doctrine, standards, and reform | Legislative change may be needed to enable FES A to better manage fire- fighting resources across the state. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0596 | 33 - Relief and recovery | An early decision on relief funding enables timely responses. D CP should review their communication of relief arrangements to ensure that they are clear. |
REC226-0569 | 32 - Doctrine, standards, and reform | Section 13 arrangements need to be clarified across key agencies. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0595 | 33 - Relief and recovery | Shire experiences in managing these traumatic events should be captured and passed into emergency management procedures. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0561 | 34 - Local knowledge | Suitably experienced local representatives should be engaged to provide advice to the IMT in all Level 2 and Level 3 incidents at the earliest opportunity. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0594 | 33 - Relief and recovery | Procedures to resolve issues surrounding financial assistance need to be reviewed to ensure they are as smooth, fast and transparent as possible possible. Review and streamline current financial relief procedures. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0534 | 32 - Doctrine, standards, and reform | Once Recommendation 1 has been actioned, all agencies give greater priority to the promulgation of Red Flag warnings in order to enhance situational awareness on the fireground. |
REC225-0531 | 32 - Doctrine, standards, and reform | Critical operational procedures such as ‘Red Flag Warnings’, on a common fireground need to be consistent across DFES, DEC and Local Government. In particular, the operational procedure of Red Flag Warnings needs to be adopted by all WA fire agencies. |
REC225-0539 | 32 - Doctrine, standards, and reform | WA fire agencies adopt a common set of standing orders, operational procedures, training and competencies for rural firefighting that are produced in hard copy, leading to integrated multi-agency training, IMTs, Regional and State coordination/control centres. |
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC225-0536 | 32 - Doctrine, standards, and reform | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0519 | 34 - Local knowledge | The Department of Environment and Conservation review its practices and procedures in the undertaking of prescribed burns so as to fully utilise the skills available to it in a seamless way including but not limited to: · volunteer bushfire brigades, especially in regard to use as a source of local advice; and · staff of the Fire and Emergency Services Authority of Western Australia. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1659 | 32 - Doctrine, standards, and reform | Regional Fire Management Plans be reviewed for all regions prior to the start of each fire season. |
REC209-1645 | 14 - Incident Mgt Teams | Ensure that adequate administrative personnel are available within the incident control structure to provide administrative and knowledge management support for incident management. |
REC200-1693 | 22 - Role of local Gvt | The Fire and Emergency Services Authority and local governments ensure that the ability to: |
REC209-1678 | 32 - Doctrine, standards, and reform | That the Bushfires Act and Regulations be reviewed and modernised after the implementation of the recommendations of this review. |
REC209-1670 | 32 - Doctrine, standards, and reform | Bushfires NT create a bushfire management strategy and emergency response procedures framework including the criteria that define the escalation and response requirements for all incidents up to and including the establishment of an EOC, applicable for all regions across the Territory. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0293 | 34 - Local knowledge | Suitably experienced personnel with local knowledge should be connected to the Operations and Planning section in all Level 3 incidents in the vicinity of substantial settlements. |
REC203-0307 | 11 - Evacuation and shelters | When people are being moved away from their homes it’s important that they move to a place of greater safety and that their movement is relatively assured. |
REC203-0292 | 18 - Access to fire ground | There is a need for community education on how road-blocks and VCPs operate in the event of an emergency. |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0291 | 18 - Access to fire ground | Local knowledge should be accessed to inform the placement and operation of VCPs. |
REC203-0297 | 32 - Doctrine, standards, and reform | The role of district and local emergency management committees should be reviewed to ensure they are appropriately engaged in the active management of emergencies across the PPR R continuum |
REC203-0290 | 18 - Access to fire ground | VCPs are one of the instruments by which the Incident Controller manages the emergency. VCPs without communications cannot be fully effective in their role. Determine and implement an appropriate communications platform for emergency management |
REC203-0296 | 32 - Doctrine, standards, and reform | Legislative change may be needed to enable FES A to manage fire-fighting resources across the state. |
REC203-0289 | 18 - Access to fire ground | There needs to be a better appreciation of the role of Vehicle Control Points (VCPs) and how they are managed in bushfire emergencies by all key agencies and the community |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
REC203-0308 | 33 - Relief and recovery | Early resolution and clear communication of the financial and other support measures that will be available to affected residents is an important contributor to community resilience. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0502 | 32 - Doctrine, standards, and reform | The Minister for Environment bring to Parliament by June 2012 amendments to the Conservation and Land Management Act 1984 that reflect the use by the Department of Environment and Conservation of prescribed burns for both biodiversity conservation and community protection purposes. |
REC202-0499 | 32 - Doctrine, standards, and reform | The Minister for Emergency Services institute a thorough review by December 2012, including a comparison to other jurisdictions, of the risk analysis processes used by FESA, the Police and DEC to prepare them to protect the State from bushfires and other natural disasters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0259 | 11 - Evacuation and shelters | FESA seek legal and policing advice regarding the policy to leave residents who chose not to evacuate in a declared ‗dangerous area‘ after a bushfire. |
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0256 | 22 - Role of local Gvt | Noting existing legislative and policy arrangements, there is merit in considering options for the future management of Level 3 fires in Local Government areas. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1729 | 22 - Role of local Gvt | The Fire and Emergency Services Authority and local governments ensure that Community Emergency Service Managers are physically based in local government. |
REC200-0373 | 33 - Relief and recovery | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-0342 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. Local Government provide information to residents on any changes to the Australian Standard relating to tethering gas tanks and encourage property owners to take action to comply with the Standard. |
REC200-1695 | 22 - Role of local Gvt | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0354 | 22 - Role of local Gvt | Local governments consider increasing the number of green waste collections carried out each year to encourage a more proactive approach to property (and vegetation) maintenance by residents. |
REC200-1721 | 32 - Doctrine, standards, and reform | The State Government amend section 50 of the Emergency Management Act 2005 to allow the Chair of the State Emergency Coordination Group to declare an emergency situation. |
REC200-0369 | 18 - Access to fire ground | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
REC200-0341 | 32 - Doctrine, standards, and reform | The State Government give legislative effect to the Planning for Bush Fire Protection Guidelines. |
REC200-0382 | 32 - Doctrine, standards, and reform | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-1704 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-0353 | 22 - Role of local Gvt | The State Government give its full support to the Western Australian Local Government Association’s Send to Solve initiative. |
REC200-1720 | 32 - Doctrine, standards, and reform | The State Emergency Management Committee amend State Emergency Management Policy 4.1 (Operational Management) to: |
REC200-0367 | 22 - Role of local Gvt | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0339 | 32 - Doctrine, standards, and reform | Emergency Management Western Australia establish an inter-agency working group to continue the development of the new single emergency services Act. |
REC200-1683 | 22 - Role of local Gvt | Local Government recognise the work of the Gas Technical Regulatory Council and ensure any amendments to the Australian Standard are enforced. |
REC200-0380 | 32 - Doctrine, standards, and reform | The State Emergency Management Committee amend State Emergency Management Policy 4.1 (Operational Management) to: give clear and explicit direction about when and how an incident should be declared clearly articulate the actions to be taken clearly define accountabilities provide detailed criteria for elevating issues and engaging other agencies. |
REC200-1703 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority develop formal procedures for mandating the completion of Incident Action Plans, ensuring the documents are detailed and that they record critical decision making. |
REC200-0345 | 22 - Role of local Gvt | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-1715 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0375 | 22 - Role of local Gvt | Local governments institute a comprehensive program to assess fuel loads and bushfire preparedness on private properties. The program should give reference to the creation and maintenance of a Building Protection Zone, in line with FESA guidelines. This program should be implemented and managed under the Bush Fires Act 1954 in a manner similar to the fire break inspection program. |
REC200-1702 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority immediately comply with the provisions of WESTPLAN BUSHFIRE and formally declare incidents at their appropriate level and document and communicate those decisions in a similar way to the systems used by the Department of Environment and Conservation and the Western Australian Police. |
REC200-1714 | 11 - Evacuation and shelters | Hazard Management Agencies overseeing the response to incidents on the urban fringe select evacuation centres that are well within the urban environment and unlikely to be impacted by the incident. |
REC200-0363 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority develop formal procedures for mandating the completion of Incident Action Plans, ensuring the documents are detailed and that they record critical decision making. |
REC200-0374 | 11 - Evacuation and shelters | Hazard Management Agencies overseeing the response to incidents on the urban fringe select evacuation centres that are well within the urban environment and unlikely to be impacted by the incident. |
REC200-1696 | 32 - Doctrine, standards, and reform | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-1709 | 32 - Doctrine, standards, and reform | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
REC200-0362 | 32 - Doctrine, standards, and reform | The Fire and Emergency Services Authority immediately comply with the provisions of WESTPLAN BUSHFIRE and formally declare incidents at their appropriate level and document and communicate those decisions in a similar way to the systems used by the Department of Environment and Conservation and the Western Australian Police. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0238 | 34 - Local knowledge | Encourage ICCs to use local knowledge to review templates prior to release. |
REC196-0234 | 34 - Local knowledge | Ensure that local knowledge, local flavour and local language is used where possible in the development of all community bushfire warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0313 | 32 - Doctrine, standards, and reform | The Fire Services expedite programmed work on joint operational command and control, including standards, procedures and training |
REC195-0312 | 32 - Doctrine, standards, and reform | The Fire Services Commissioner ensures that joint fireground command and control, integration and escalation procedures are developed, particularly for ‘fastrunning’ fires |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
REC195-0311 | 32 - Doctrine, standards, and reform | The Fire Services ensure that agency specific operational procedures fully align with the arrangements. |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0225 | 22 - Role of local Gvt | Local government councils should move promptly to: adopt the Tasmania Fire Service Guidelines for Development in Bushfire Prone Areas of Tasmania give effect to the Department of Primary Industries, Parks, Water and Environment Neighbouring Developments and Fire Management Policy. |
REC193-0224 | 32 - Doctrine, standards, and reform | The State Fire Management Council work with all entities with responsibility for bushfire management to develop a state-wide position on performance indicators and promote that view nationally. |
REC193-0223 | 32 - Doctrine, standards, and reform | The State Fire Management Council support the further development of the Bushfire Risk Assessment Model with a view to it becoming the central information source for use by all entities with responsibility for fire management and mitigation. |
REC193-0222 | 22 - Role of local Gvt | The Local Government Association of Tasmania advocate, coordinate and support local councils’ input of bushfire risk assets data into the Bushfire Risk Assessment Model. |
REC193-0226 | 22 - Role of local Gvt | Local government councils should: strongly encourage owners to make improvements to construction or increase buffers in order to meet minimum safety standards implement programs to audit impacted properties and issue abatement notices where necessary monitor and maintain their reserves to ensure that adequate buffers to neighbouring buildings exist. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
REC183-0108 | 32 - Doctrine, standards, and reform | DEC should consider publishing a new reference document that describes policy, doctrine and key systems of work of the fire management system. This document would be a “brief case” or “back pack” reference and would be reviewed annually and issued to all senior staff and fire management personnel. |
REC183-0115 | 32 - Doctrine, standards, and reform | The Hazard Management Agency for bushfire has not been defined. Defining the HMA for bushfire should be addressed. |
REC183-0107 | 32 - Doctrine, standards, and reform | The DEC Fire Management Policy should be reviewed and updated. |
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
REC182-0123 | 32 - Doctrine, standards, and reform | FESA implements measures that will ensure unity and clarity of command. |
REC182-0135 | 33 - Relief and recovery | FESA revises its standard operating procedures to provide guidance on the format and timing of post-incident community meetings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0209 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment amend the Code of Practice for Fire Management on Public Land in order to achieve the following: ■ provide a clear statement of objectives, expressed as measurable outcomes; ■ include an explicit risk-analysis model for more objective and transparent resolution of competing objectives, where human life is the highest priority; ■ specify the characteristics of fire management zones—including burn size, percentage area burnt within the prescribed burn, and residual fuel loading; ■ adopt the use of the term ‘bushfire’ rather than ‘wildfire’. |
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
REC181-0162 | 32 - Doctrine, standards, and reform | The State consider either amending the Emergency Management Act 1986 or adopting a standing practice to require the Minister for Police and Emergency Services or the Chief Commissioner of Police to consult the Premier about the possibility of declaring a state of disaster for all of or any part of Victoria whenever the Minister or the Chief Commissioner of Police becomes aware of circumstances that make it a reasonable possibility that the criteria for making such a declaration will be satisfied. |
REC181-0164 | 32 - Doctrine, standards, and reform | The Victorian fire agencies amend the AIIMS framework before the 2010–11 fire season in order to do the following: ■ designate the Information Unit as a separate section reporting directly to the Incident Controller and require that the Information Unit contain a dedicated Public Information Officer whenever a full incident management team is required; ■ specify a set of functions in relation to which the Deputy Incident Controller for a level 3 incident will have oversight, which may be adjustable for a particular incident by agreement between the Incident Controller and the Deputy Incident Controller; ■ ensure that an individual with local knowledge is incorporated in an incident management team |
REC181-0202 | 22 - Role of local Gvt | The State develop and implement, in consultation with local government, a mechanism for sign-off by municipal councils of any permit conditions imposed under the Bushfire-prone Overlay and the regular assessment of landowners’ compliance with conditions. |
REC181-0153 | 22 - Role of local Gvt | The State establish mechanisms for helping municipal councils to undertake local planning that tailors bushfire safety options to the needs of individual communities. In doing this planning, councils should: ■ urgently develop for communities at risk of bushfire local plans that contain contingency options such as evacuation and shelter; ■ document in municipal emergency management plans and other relevant plans facilities where vulnerable people are likely to be situated—for example, aged care facilities, hospitals, schools and child care centres; ■ compile and maintain a list of vulnerable residents who need tailored advice of a recommendation to evacuate and provide this list to local police and anyone else with pre-arranged responsibility for helping vulnerable residents evacuate. |
REC181-0158 | 32 - Doctrine, standards, and reform | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require the following: ■ that at locations that attract preparedness levels A or B there be a full incident management team under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of code red fire danger and a core incident management team (eight personnel) under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of extreme fire danger; ■ that at locations that attract preparedness levels A or B there be a full incident management team under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of code red fire danger and a core incident management team (eight personnel) under the leadership of an accredited level 3 Incident Controller in position by 10.00 am on days of extreme fire danger. |
REC181-0169 | 18 - Access to fire ground | The Country Fire Authority provide to all CFA volunteers an identification card or similar to facilitate their passage through roadblocks established in accordance with the 2009 Guidelines for the Operation of Traffic Management Points during Wildfires. |
REC181-0195 | 22 - Role of local Gvt | The State press municipal councils—in particular, Murrindindi Shire Council—to urgently adopt a bushfire policy in their Local Planning Policy Framework and incorporate bushfire risk management in their planning policies and strategies for rebuilding communities such as Marysville, Kinglake and others affected by the January–February 2009 fires. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0181 | 22 - Role of local Gvt | Municipal councils include in their municipal fire prevention plans for areas of high bushfire risk provision for the identification of hazard trees and for notifying the responsible entities with a view to having the situation redressed. |
REC181-0161 | 32 - Doctrine, standards, and reform | The State consider amending the Emergency Management Act 1986 and the Emergency Management Manual Victoria in order to achieve the following: ■ remove the title of Coordinator in Chief of Emergency Management from the Minister for Police and Emergency Services; ■ clarify the function and powers of the Minister; ■ designate the Chief Commissioner of Police as Coordinator in Chief of Emergency Management, who would have primary responsibility for keeping the Minister informed during an emergency. |
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0213 | 32 - Doctrine, standards, and reform | The State enact legislation designed to achieve two specific ends: ■ appoint a Fire Commissioner as an independent statutory officer responsible to the Minister for Police and Emergency Services and as the senior operational firefighter in Victoria; ■ make the Chief Fire Officer of the Department of Sustainability and Environment a statutory appointment. The Fire Commissioner should have responsibility for the following: ■ promoting and directing reform aimed at increasing the operational capability, interoperability and resilience of Victoria’s fire services; ■ developing and building operational capacity to prepare for the days of highest bushfire risk and exercising control over level 3 fires as the permanent State Controller; ■ providing to government periodic advice on the metropolitan fire district boundary on the basis of triggers, frequency and criteria approved by government; ■ representing Victorian interests on operational matters in national committees. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0163 | 32 - Doctrine, standards, and reform | The State consider amending the Emergency Management Act 1986 to introduce a graded scale of emergency declarations short of a state of disaster. |
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0102 | 32 - Doctrine, standards, and reform | That further amendments be made to the Bush Fires Act 1954 be drafted to provide fire response agencies with the necessary authorisation and statutory protection to respond to a fire on private property, or land that Local Government, Department of Environment and Conservation (DEC) or FESA is responsible for, until such time as the responsible agency is able to attend and take control. The amendments to be drafted, in conjunction with the urgent progression of critical amendments as recommended by the Community Development and Justice Standing Committee. |
REC173-0100 | 32 - Doctrine, standards, and reform | The prioritising of the critical amendments to the Bush Fires Act 1954 recommended by the Community Development and Justice Standing Committee that relate to fire management, ie: a. Fire and Emergency Services Authority (FESA)‘s ability to assume control of a fire in specific circumstances b. Amendments to the definition of property c. Providing FESA with the authority to declare a total fire ban |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0011 | 18 - Access to fire ground | At Level 3 incidents the position of ‘Traffic Operations Officer’ –be established and filled by a WAPOL officer. A role description for this position is required and should be included in the “Guidelines for the Operations of Road Closures During Bushfires 2008”. This officer is to be supported by a suitably qualified officer from MRWA that is capable of developing Traffic Management Plans that address risk and are cognisant of considerations associated with road type, appropriate speed limitations, signage requirements, traffic volumes, detours for local traffic and heavy haulage etc. This role should report to the IC and have strong links to the Operations Section, Planning Section (particularly the Situation Unit) and the Information Unit. |
REC172-0017 | 18 - Access to fire ground | Information packs to be provided to road traffic personnel to assist with enquiries by public or provision to members of public and landholders who are defending homes/stock etc |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0039 | 18 - Access to fire ground | Dedicated information packages should be made available to personnel operating Vehicle Control Points at the shift briefing. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0016 | 18 - Access to fire ground | Full briefings of traffic management personnel should be provided prior to dispatch to work areas – why road closed, what their authority level is, level of current risk etc |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0038 | 34 - Local knowledge | The ISU should be provided with a person with local knowledge at Level 3 incidents. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0014 | 18 - Access to fire ground | The Interagency Guidelines for Road closure needs to be reviewed to incorporate a mechanism to identify bone-fide local landholders to facilitate their movement in and out of cordoned areas in sympathy with the Stay and Defend requirements. |
REC172-0003 | 32 - Doctrine, standards, and reform | All incidents where the HMA delegates the authority to manage suppression operations to another agency on its behalf, should be achieved via a written delegation setting out the scope, limitations and duration of the delegation. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0013 | 18 - Access to fire ground | In preparing traffic management plans consideration should be given to which VCP’s are critical and need to be resourced with uniformed Police Officers and which VCP’s can be manned with civilian contractors. |
REC172-0002 | 32 - Doctrine, standards, and reform | The Emergency Management Act 2005 is amended to provide a mechanism for one HMA to transfer responsibility to another HMA and ensure that both HMA’s are provided the powers and protection necessary under that Act. |
REC172-0021 | 32 - Doctrine, standards, and reform | Unassigned resources arriving at incidents should be encouraged to make themselves known and to undertake alternate duties. |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0012 | 18 - Access to fire ground | Main Roads Western Australia, Police and LGA’s be encouraged via State emergency arrangements to establish a distributed cache of “hard” road barriers for deployment to major incidents |
REC172-0001 | 32 - Doctrine, standards, and reform | The Emergency Management Regulations 2006 be urgently amended to determine a HMA(s) for bushfire. |
REC172-0018 | 32 - Doctrine, standards, and reform | The Interagency Guidelines need to be amended to reflect what is operationally possible with regard to risk management rather than what is required to achieve an absence of risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0070 | 32 - Doctrine, standards, and reform | That a review be conducted of DEC’s ability to manage major fires and consideration be given to increased direct involvement by FESA in fire management role in the case of major fires on reserves or on unallocated Crown lands. |
REC171-0068 | 32 - Doctrine, standards, and reform | That if the Bushfires Amendment Bill 2009 is to be enacted, procedures be put in place which would ensure that in the event of an escalating fire, FESA would receive sufficient information to make an informed judgment as to whether or not to take control of all operations. |
REC171-0067 | 14 - Incident Mgt Teams | That to the extent it has not already done so, DEC take action to ensure that in future cases relevant weather forecast information, particularly information as to significant wind changes, is promptly transmitted through the Incident Management Team and made available to persons with field operation responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3499 | 32 - Doctrine, standards, and reform | The Department of Primary Industries clearly document responsibilities within the Department to ensure better co-ordination of public information during emergencies. |
REC156-3510 | 32 - Doctrine, standards, and reform | Victoria’s emergency management arrangements as they relate to the Emergency Management Joint Public Information Committee be enhanced to include greater clarity of its operational role in the Emergency Management Manual Victoria. |
REC156-3498 | 32 - Doctrine, standards, and reform | The Department of Primary Industries, Department of Premier and Cabinet, and the Office of the Emergency Services Commissioner review and clarify energy sector emergency event trigger points for the activation of Central Government Response Committee. |
REC156-3508 | 32 - Doctrine, standards, and reform | The Australian Broadcast Corporation and Emergency Services Organisations redevelop the protocols for the use of the Memorandum of Understanding; and all relevant emergency services and ABC staff are trained in the use of the protocols. |
REC156-3492 | 22 - Role of local Gvt | The review of the municipal emergency management planning guidelines being led by the Office of the Emergency Services Commissioner clarify local governments’ role in community information about emergencies. |
REC156-3505 | 32 - Doctrine, standards, and reform | The Emergency Service Organisations and the Emergency Services Telecommunications Authority agree on the direct telephone numbers to be used for contacting the Emergency Services Telecommunications Authority in relation to emergency incidents. The Emergency Service Organisations need to ensure an effective process is in place to educate their personnel in relation to the use of these numbers. |
REC156-3489 | 32 - Doctrine, standards, and reform | The Department of Primary Industries responsibility for emergency management within the energy sector needs to be reinforced consistent with Recommendation 5. |
REC156-3504 | 32 - Doctrine, standards, and reform | The Emergency Services Telecommunications Authority develop a protocol to direct the suspension or cessation of scheduled telecommunication maintenance or testing to emergency alert systems during an emergency event. |
REC156-3513 | 32 - Doctrine, standards, and reform | The Department of Primary Industries in consultation with the energy sector develop and implement a Memorandum of Understanding or similar authorising instrument that provides a single contact for emergency |
REC156-3484 | 32 - Doctrine, standards, and reform | The Victoria State Emergency Service finalise its development of strategic emergency response management plans including severe weather and storm events. |
REC156-3501 | 32 - Doctrine, standards, and reform | The Country Fire Authority review their procedures regarding receipt of Triple Zero calls on the Brigade Spectrum Preset Conference including training material, testing procedures and interface back to the Emergency Services Telecommunications Authority Computer Aided Dispatch system. |
REC156-3511 | 32 - Doctrine, standards, and reform | The operational protocols of the Emergency Management Joint Public Information Committee be formally endorsed by the State Emergency Response Planning Committee and the Victorian Emergency Management |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3482 | 32 - Doctrine, standards, and reform | That the Victorian Government, and responsible agencies, expedite the implementation of the Integrated Fire Management Planning framework. |
REC155-3467 | 38 - Agency/Department Reporting | The Department of Sustainability and Environment should report its performance against the increased prescribed burning target in its annual report, which should also include the following details: |
REC155-3479 | 32 - Doctrine, standards, and reform | That a process of year round community engagement in the preparation of Fire Operations Plans be established. In addition a record of year round community engagement, as contained in the Gippsland Fire Operations Plan, should be a requirement of all Fire Operations Plans. |
REC155-3478 | 38 - Agency/Department Reporting | That all information pertaining to current and planned prescribed burns be published more prominently on the Department of Sustainability and Environment’s website, with a single prominent link to this material on the website homepage. |
REC155-3477 | 38 - Agency/Department Reporting | That the details of any variation or amendment of a Fire Operations Plan, including: the carrying forward or postponement of burns within the three-year period covered by a Fire Operations Plan; the carry over, removal or rescheduling of burns between past, present and future Fire Operations Plans; and the alteration of burn boundaries (including alterations of less than 25 per cent); should appear on the Department of Sustainability and Environment’s website at the time of the change and be included in the Fire Operations Plan for the following year. |
REC155-3476 | 38 - Agency/Department Reporting | That finalised Fire Operations Plans be made publicly available in their entirety (with the exception of any private information) on the Department of Sustainability and Environment’s website and in hard-copy, and that this requirement be clearly stated in future Codes of Practice. This should include the “district burns list”, or its future equivalents, and a map which shows the corresponding burns for each Fire District. Each map should be provided in a format which can be downloaded directly from the Department’s website without the need for further data manipulation by the user. An identical hardcopy version of the map for each Fire District should be also be available to members of the public on request and free of charge. |
REC155-3468 | 38 - Agency/Department Reporting | That the Department of Sustainability and Environment, Department of Primary Industries, Parks Victoria & VicForests separately cost, and report, annual expenditure on fuel reduction burning, ecological burning and regeneration burning in their Annual Reports. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1789 | 32 - Doctrine, standards, and reform | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service cause to be included among the SACFS’ Standard Operating Procedures (SOPs) a requirement that Incident |
REC153-1788 | 32 - Doctrine, standards, and reform | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service cause to be included among the SACFS’ Standard Operating Procedures (SOPs) a requirement that Incident |
REC153-1805 | 32 - Doctrine, standards, and reform | That the Minister for Emergency Services, the Minister for Environment, the Chief Officer of the CFS and the Native Vegetation Council, together develop a Code of Practice relating to the management of native vegetation as it affects bushfire prevention. |
REC153-1787 | 32 - Doctrine, standards, and reform | That the Minister for Emergency Services, the South Australian Country Fire Service, the South Australia Police and the South Australian Farmers’ Federation together continue to develop strategies to reduce the risk of harm to private firefighters and in particular: |
REC153-1799 | 14 - Incident Mgt Teams | That the South Australian Country Fire Service establish preplanned Level 2 Incident Management Teams in each Region for deployment to Level 2 incidents. |
REC153-1780 | 22 - Role of local Gvt | That the Minister for Local Government cause rural councils to appoint an Officer whose duties consist entirely of bushfire prevention, such Officer being required to become a trained, operative member of the South Australian Country Fire Service during the currency of his or her appointment. |
REC153-1791 | 14 - Incident Mgt Teams | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service consider the creation of a position within an Incident Management Team of a Landowner Liaison Officer the duties and responsibilities of whom is to establish contact with and liaise with the owner and/or occupiers of rural land on which a fire is situated. |
REC153-1774 | 32 - Doctrine, standards, and reform | That the Minister for Emergency Services, the Chief Officer of the South Australian Country Fire Service, the President of the Farmers’ Federation of South Australia and the Minister for Local Government, with a view to developing a Code of Practice, establish a body to investigate the impact of existing farming practices on bushfire risk and prevention. |
REC153-1790 | 32 - Doctrine, standards, and reform | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service cause to be included among the SACFS’ Standard Operating Procedures (SOPs) a requirement that Incident |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3115 | 32 - Doctrine, standards, and reform | QFRS establish a structured risk management process for rural fire management, which involves regional and area offices, to enhance decision making processes and ensure opportunities are maximised and losses are minimised. This process should be linked to forward planning and incorporate existing processes such as: |
REC150-3125 | 38 - Agency/Department Reporting | QFRS introduce a system to collate and analyse performance information for use in management reporting and to support effective decision making processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3536 | 32 - Doctrine, standards, and reform | The requirement for a rural council to establish a District Bushfire Prevention Committees under section 75 of the SA Fire and Emergency Services Act 2005 is removed. |
REC139-3541 | 32 - Doctrine, standards, and reform | Bushfire Management Committees will have the following functions: |
REC139-3546 | 22 - Role of local Gvt | Local Government to be maintained as an important component of bushfire management in South Australia because of the link with the community. |
REC139-3535 | 32 - Doctrine, standards, and reform | The requirement to establish Regional Bushfire Prevention Committees under section 73 of the SA Fire and Emergency Services Act 2005, is removed. |
REC139-3540 | 32 - Doctrine, standards, and reform | The State Bushfire Coordination Committee will have the following members with experience in bushfire management: |
REC139-3545 | 32 - Doctrine, standards, and reform | SA Country Fire Service to be responsible for Bushfire Management Plan preparation, analysis of future risks trends based on investigation and executive support to Bushfire Management Committees. |
REC139-3534 | 32 - Doctrine, standards, and reform | The SA Bushfire Prevention Advisory Committee established under section 71 of the SA Fire and Emergency Services Act 2005, is removed and replaced with the State Bushfire Coordination Committee. |
REC139-3539 | 32 - Doctrine, standards, and reform | The State Bushfire Coordination Committee will have the following functions: |
REC139-3544 | 32 - Doctrine, standards, and reform | The area of responsibility for Bushfire Management Committees will be established based on bushfire risk and the capacity of the area to cooperate and collaborate. |
REC139-3550 | 32 - Doctrine, standards, and reform | The State Bushfire Coordination Committee work with the Native Vegetation Council to develop more streamlined processes for the prescribed burning of native vegetation for hazard reduction. |
REC139-3538 | 32 - Doctrine, standards, and reform | The requirement to establish a Bushfire Management Committee is inserted into the SA Fire and Emergency Services Act 2005. |
REC139-3543 | 32 - Doctrine, standards, and reform | Bushfire Management Committees be given the appropriate powers under the SA Fire and Emergency Services Act 2005 to ensure that bushfire management strategies that have been identified in a Bushfire Management Plan or any other action to reduce bushfire risk, are completed by individuals, the community, agencies or organisations. |
REC139-3548 | 32 - Doctrine, standards, and reform | The current provisions for permit to light and maintain fire under Section 81 of the SA Fire and Emergency Services Act and Regulations 2005 to be reviewed for improvement with an accreditation for a self-regulation process. |
REC139-3537 | 32 - Doctrine, standards, and reform | The requirement for a rural council to appoint a suitably qualified Fire Prevention Officer under section 77 of the SA Fire and Emergency Services Act 2005 is removed. |
REC139-3542 | 32 - Doctrine, standards, and reform | Bushfire Management Committees will have the following members who reside and/or are employed/assigned in the area of responsibility, with experience in bushfire management: |
REC139-3547 | 32 - Doctrine, standards, and reform | The principle of developing Codes of Practice for Bushfire Management, referenced in the SA Fire and Emergency Services Act and Regulations 2005 be endorsed and further developed by the State Bushfire Coordination Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3523 | 38 - Agency/Department Reporting | This Report should be considered for publication so that the insights, data, conclusions and recommendations are available within Queensland and other jurisdictions to assist with disaster management issues in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3591 | 32 - Doctrine, standards, and reform | Joint development of templates for provision of core incident information by regional Incident Management Teams to CFA and DSE emergency coordination centres as basis for updates to the VBIL and other authorised information recipients |
REC132-3595 | 32 - Doctrine, standards, and reform | Development of framework document investigating future direction of VBIL including its role during incidents and its role in the transition from bushfire preparation to incident to bushfire recovery phases |
REC132-3592 | 32 - Doctrine, standards, and reform | Clarifying protocols for activating VBIL beyond normal working hours and for 24 hour activations |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1964 | 32 - Doctrine, standards, and reform | That all firefighting agencies adopt a policy and practice that all fires in remote areas of the ACT be responded to as quickly as possible, with vigorous and sustained efforts made to suppress the fires and not leave them unattended – especially at night – unless there are compelling reasons relating to firefighter safety or lack of resources |
REC126-1989 | 32 - Doctrine, standards, and reform | That formal protocols be developed and agreed with NSW authorities, so that a concerted effort that combines the resources of both NSW and the ACT can be brought to bear in the future - without impediment caused by lines on a map that make the ACT an island within the state of NSW |
REC126-1943 | 32 - Doctrine, standards, and reform | That the ACT’s Director of Public Prosecutions Act 1990 be amended by repealing s. 6(d) of the Act |
REC126-1962 | 32 - Doctrine, standards, and reform | That version 2 of the Strategic Bushfire Management Plan be completed and introduced without delay |
REC126-1978 | 32 - Doctrine, standards, and reform | That it be a matter of policy and practice that the relevant land management agency is responsible for the initial response to any fire or fires on the land under its care or management – within the overall operational response of the ACT Rural Fire Service |
REC126-1953 | 14 - Incident Mgt Teams | That appointments of personnel to functional positions within the incident management team be based solely on competence and experience and be made by the Chief of the ACT Rural Fire Service or, in the absence of that officer, the Deputy Chief of the ACT Rural Fire Service |
REC126-1966 | 32 - Doctrine, standards, and reform | That the Emergency Services Agency investigate and implement arrangements that will provide the capacity to use fire retardant in remote areas |
REC126-1946 | 32 - Doctrine, standards, and reform | That the ACT Government consider amending the Coroners Act 1997 to include what were ss. 56(1)(d) and 56(2)(c) of the 1956 Coroners Act |
REC126-1965 | 32 - Doctrine, standards, and reform | That helicopters be used wherever possible to facilitate the rapid deployment of remote area firefighting crews |
REC126-2008 | 34 - Local knowledge | That, if he is willing to participate, Mr John Lowe be made a member of the implementation taskforce to which I refer in recommendation 70 |
REC126-1945 | 32 - Doctrine, standards, and reform | That s. 47 of the ACT Coroners Act 1997 be expanded to explicitly state that an inquest and the inquiry are not adversarial in nature and are solely inquisitorial, with a view to establishing the truth |
REC126-1964 | 32 - Doctrine, standards, and reform | That remote area firefighting resources be deployed to a fire in a remote area as a matter of priority and in preference to the deployment of large tankers |
REC126-2007 | 34 - Local knowledge | That the views and concerns expressed by the ACT Sustainable Rural Lands Group be taken into account when implementing the recommendations in this report |
REC126-1944 | 32 - Doctrine, standards, and reform | That s. 59 of the ACT Coroners ACT 1997 be amended by deleting the words ‘by instrument’ in s. 59(1) and by deleting the words ‘by his or her instrument of appointment’ in s. 59(2)(b) |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3887 | 32 - Doctrine, standards, and reform | Give priority to the establishment of risk management processes across all stages of prescribed burning within the Department’s broader risk management strategy: |
REC124-3886 | 32 - Doctrine, standards, and reform | Clarify, strengthen and document roles, responsibilities and accountabilities of DSE and its partner organisations in the prescribed burning program: |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3784 | 34 - Local knowledge | The Committee recommends that the government provide authority to a single community representative body to authorise clearing of native vegetation for fire management. (The community representative body must incorporate the CFS, DEH, Native Vegetation Council and local council) |
REC122-3790 | 32 - Doctrine, standards, and reform | The Committee recommends that prescribed burning should only be undertaken by professionally trained personnel. |
REC122-3789 | 32 - Doctrine, standards, and reform | The Committee recommends that the native vegetation planning and approval process for prescribed burning be amended to allow flexibility for burning on optimum days. |
REC122-3788 | 32 - Doctrine, standards, and reform | The Committee recommends that the Native Vegetation Council have a consistent approach to prescribed burning on both public and private lands. |
REC122-3786 | 32 - Doctrine, standards, and reform | The Committee recommends that the Native Vegetation Act be amended to allow for prescribed burning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3903 | 32 - Doctrine, standards, and reform | Government should: establish emergency management legislation which clarifies State and local government responsibilities, and which rectifies the deficiencies in the State’s bushfire Emergency Management Plan, Westplan Wildfire. |
REC113-3902 | 14 - Incident Mgt Teams | Government should: establish a State-wide command structure across volunteer Bush Fire Brigades for fighting major bushfires, to more effectively manage the coordination of personnel and resources |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2229 | 32 - Doctrine, standards, and reform | That DSE and the Department of Primary Industries formalise an agreement by the 2003-2004 fire season documenting the policies, procedures and financial arrangements relating to the availability of Department of Primary Industries staff to be trained and released for fire prevention and suppression activities on public land. |
REC104-2252 | 32 - Doctrine, standards, and reform | That existing DSE and CFA regional co-ordination arrangements be reviewed and any changes, such as the continued use of Integrated Multi-Agency Co-ordination Centres, be reflected in the Victorian emergency management arrangements. |
REC104-2285 | 32 - Doctrine, standards, and reform | That, as a matter of urgency and in consultation with stakeholders, CFA and DSE develop and communicate clear guidelines on how and when privately owned firefighting equipment should be integrated into the fire response. |
REC104-2311 | 32 - Doctrine, standards, and reform | That all Departments, statutory authorities, utility providers and Local Governments be made aware of the need to develop contingency plans for recovery activities, and that such plans, and the associated public education and information strategies, are included in the Municipal Emergency Management Plans. |
REC104-2195 | 38 - Agency/Department Reporting | That the creation of buffers by chaining and then burning swaths of mallee be explicitly monitored for: |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2305 | 33 - Relief and recovery | That DPI actively promote as widely as possible within the community, the agricultural recovery service available during emergencies to ensure that all farmers are aware of the services provided. |
REC104-2324 | 32 - Doctrine, standards, and reform | That this group reports to the Minister for Police and Emergency Services on proposed legislative amendments to the Emergency Management Act 1986, the Country Fire Authority Act 1958 and any associated legislation by June 2004. |
REC104-2203 | 11 - Evacuation and shelters | That CFA further develops the information supporting the decision to stay or go, to incorporate a better understanding of both the likely consequences of leaving home at inappropriate times, and the conditions and |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2227 | 32 - Doctrine, standards, and reform | That the Municipal Fire Management Plan amendment includes appropriate provisions for the audit of the plans including: |
REC104-2251 | 11 - Evacuation and shelters | That Victoria Police ensure all police members understand the Victorian legislation in relation to evacuation, and that any decision to recommend evacuation remains with the Incident Controller. |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2310 | 33 - Relief and recovery | That recovery is recognised as commencing at the same time as response and that recovery planning and delivery is an integral part of the operations of the Municipal Emergency Co-ordination Centres. |
REC104-2194 | 38 - Agency/Department Reporting | That the success of current buffers in terms of assisting suppression operations be continually reviewed, evaluated and documented. |
REC104-2261 | 32 - Doctrine, standards, and reform | That the emergency management arrangements be amended to require Police Divisional Emergency Response Coordinators, in consultation with other response agencies, to establish and document procedures and structures at regional level in order to ensure there is: |
REC104-2304 | 22 - Role of local Gvt | That Municipal Emergency Resource Officers develop registers of volunteers willing and available to provide assistance and support during the response to, and recovery from, emergency incidents. |
REC104-2316 | 33 - Relief and recovery | That the State Emergency Recovery Committee explore opportunities to establish a 'one-stop shop’ approach wherever practicable following emergencies, including a single telephone number to connect a person to all agencies involved in the recovery process. |
REC104-2200 | 38 - Agency/Department Reporting | That DSE: |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2226 | 32 - Doctrine, standards, and reform | That the new Municipal Fire Management Plan is informed by the policy directions of the subcommittee of the Victoria Emergency Management Council. |
REC104-2246 | 34 - Local knowledge | That DSE undertake community consultation on policies relating to roads and access tracks on public land, particularly in respect to fire management. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2193 | 38 - Agency/Department Reporting | That if ‘link’ burns continue to be used, then on-site weather sequences and fuel conditions marking successful (‘within explicit prescription’) and unsuccessful burns be documented. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2290 | 38 - Agency/Department Reporting | That instances where demand for air support outstrips the supply of State Fleet Aircraft available are recorded. |
REC104-2314 | 33 - Relief and recovery | That DHS, in conjunction with Local Government, Government departments and the nongovernment sector, modify recovery planning at all levels to include a case management approach supported by an appropriate information system to be activated at the time of an emergency. |
REC104-2199 | 32 - Doctrine, standards, and reform | That evidence of the rekindling or otherwise of spring prescribed burns in forests be assembled and a model constructed and tested to see whether or not some days in spring could be used for prescribed burning in certain circumstances and places, especially in Zone 1. |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2309 | 32 - Doctrine, standards, and reform | That the Emergency Management Act 1986 be amended to include a provision that, on the recommendation of the Minister for Police and Emergency Services as Co-ordinator-in-Chief of Emergency Management, or of another Minister, the Premier establish a Ministerial Task Force to oversee recovery in situations of extreme natural disaster or other emergency events. |
REC104-2224 | 32 - Doctrine, standards, and reform | That the Country Fire Authority Act 1958 be amended to: |
REC104-2278 | 32 - Doctrine, standards, and reform | That DSE and CFA review the standards and protocols for documentation, including mapping, provided to fire line managers as part of their briefing notes, to ensure these are concise and appropriate. |
REC104-2236 | 32 - Doctrine, standards, and reform | That the Statewide Fire Control Priorities: |
REC104-2257 | 32 - Doctrine, standards, and reform | That the Emergency Management Act 1986 be amended to require the development of agreements that describe joint operational arrangements between emergency response agencies. |
REC104-2289 | 38 - Agency/Department Reporting | That the joint agencies introduce a system of performance measures for reporting the effectiveness of aircraft in firefighting operations. |
REC104-2313 | 33 - Relief and recovery | That Government review the emergency relief and financial assistance policy, and develop and communicate a predictable, consistent and equitable policy designed to assist the community to recover from emergencies, including natural disasters. |
REC104-2198 | 32 - Doctrine, standards, and reform | That an explicit formulation of the interactions between terrain, fuel, ignition pattern, time of day and weather be created to better define those days suited to prescribed burning. |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2307 | 33 - Relief and recovery | That the Victorian Government recommend to the Commonwealth Government that it reviews eligibility for those without employment who may or may not be engaged in an emergency response, and are unable to access the appropriate infrastructure to register for financial assistance. |
REC104-2330 | 32 - Doctrine, standards, and reform | That this unified system include recommendations for the appointment of one person or agency to be responsible for overall control of fire suppression activity in country Victoria, including for any legislative reform considered necessary. |
REC104-2222 | 22 - Role of local Gvt | That Municipal Councils: |
REC104-2276 | 32 - Doctrine, standards, and reform | That CFA and DSE jointly develop procedures to ensure that a more consistent strategic approach can be maintained at shift and tour of duty changes. |
REC104-2233 | 34 - Local knowledge | That communities, public land managers, Water Authorities and Catchment Management Authorities jointly identify and implement local and environmentally sound solutions to improve the availability of water for firefighting through the Municipal Fire Management Planning process. |
REC104-2253 | 32 - Doctrine, standards, and reform | That Victoria Police, CFA and DSE review the relationship between fire service regional co-ordination arrangements and Divisional Emergency Response Plans and that any changes be formalised in the emergency management arrangements. |
REC104-2288 | 32 - Doctrine, standards, and reform | That CFA develop protocols to integrate Ultra High Frequency and Citizen Band radios into their communication structures. |
REC104-2312 | 33 - Relief and recovery | That all agencies engaged in recovery participate in community briefings prior to and during emergency events, to ensure recovery issues are reinforced and communities are informed of the processes established to assist individuals – including matters that are not the responsibility of Victoria, such as Centrelink payments. |
REC104-2196 | 32 - Doctrine, standards, and reform | That, as a result of this monitoring, weather conditions for the safe conduct of burning in such operations should be defined. |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2306 | 33 - Relief and recovery | That VicRoads and Municipal Councils review procedures and processes to ensure that the identification and delivery of remedial works on State and Council roads following emergency events are as efficient as possible. |
REC104-2329 | 32 - Doctrine, standards, and reform | That CFA, DSE, MFESB and Victoria Police jointly develop a unified command and control system that better integrates with the State's emergency management arrangements, and that this be endorsed by the Victoria Emergency Management Council by July 2004. |
REC104-2219 | 32 - Doctrine, standards, and reform | That, following the review of Forest Industry Brigades, the Country Fire Authority Act 1958 be amended to ensure that the Forest Industry Brigades, which are acting in an approved manner, have the same powers and rights as other Brigades when attending fires on public land or interstate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2181 | 11 - Evacuation and shelters | The Committee recommends that the Australasian Fire Authorities Council’s suggested evacuation protocol be adopted by all of the Australian States and Territories. |
REC098-2149 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth work with the states and territories through the proposed Council of Australian Governments to review the response to bushfires to ensure that principles of fire prevention and rapid and effective initial attack are adopted and implemented by all rural fire authorities and public land managers |
REC098-2170 | 32 - Doctrine, standards, and reform | The Committee recommends that Emergency Management Australia request the Australasian Fire Authorities Council to: |
REC098-2141 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth through the National Heritage Trust, offer assistance to the states and the Australian Capital Territory to develop specific prescribed burning guides, at least |
REC098-2166 | 32 - Doctrine, standards, and reform | The Committee recommends that Emergency Management Australia work through the Australasian Fire Authorities Council to ensure that: |
REC098-2135 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments implements to a minimum national standard adequate access to all public lands including wilderness areas of national parks. |
REC098-2159 | 32 - Doctrine, standards, and reform | The Committee recommends that in changing the incident management systems as proposed in recommendation 23 above all bushfire agencies review concerns about difficulties in communicating operational information from the fire front to air operations. |
REC098-2187 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth require state and territory governments to have in place comprehensive bush fire management plans as a pre-requisite for accessing funding from the National Heritage Trust and like programs. |
REC098-2154 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek the adoption by all states and territories of multi-agency protocols and agreements for fire |
REC098-2186 | 38 - Agency/Department Reporting | The Committee recommends that the Department of Transport and Regional Services review its record keeping practices to show the type of emergency for which assistance is provided through the Natural Disaster |
REC098-2152 | 32 - Doctrine, standards, and reform | The Committee recommends that the Commonwealth, through the Council of Australian Governments and the Australasian Fire Authorities Council, initiate an overhaul of the incident management systems used |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4164 | 22 - Role of local Gvt | The role of local government in counter—disaster affairs be clearly defined and formalised by legislation. Local government authorities would then be fully aware of their responsibilities and of their entitlement to financial and other counter—disaster resources from State Government level. [Reference paragraphs: 232 to 233] |
REC037-4161 | 32 - Doctrine, standards, and reform | That separate counter—disaster systems be avoided by retaining counter—bushfire arrangements as part of the State’s total counter— disaster system. [Reference paragraph: 228] |
REC037-4168 | 32 - Doctrine, standards, and reform | The provisions of the State Disasters Act, 1983, be extended to cover the proposed policy and organisational amendments. (Reference paragraph: 286] |
REC037-4160 | 32 - Doctrine, standards, and reform | The current counter—bushfire concept be retained, with the proviso that it be kept under continuous review to ensure that all relevant future developments and techniques are effectively utilised. (Reference paragraphs: 88 to 90 and 257 to 259] |
REC037-4167 | 32 - Doctrine, standards, and reform | The definitions of command, control and co—ordination, as stated in the Australian Counter Disaster Handbook, be standardised throughout Victoria’s counter—disaster system. [Reference paragraphs: 106 to 111] |
REC037-4166 | 32 - Doctrine, standards, and reform | In the future development of Victoria’s counter—disaster capability, effective utilisation and management of resources be regarded as a major objective. |
REC037-4165 | 32 - Doctrine, standards, and reform | • Proposed amendments to the State Disaster Plan be formalised |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4136 | 34 - Local knowledge | The Bush Fires Board appoint a Regional Committee of Board members co-opt local members for each climatic region of the State to study the bush fire control problems of the region and advise the Board so that inter alia adequate attention may be given by the Board to co-ordinating the beginning and termination of the prohibited burning times in adjoining districts and to any advisable variations of these duties according to seasonal conditions each year. |
REC019-4157 | 18 - Access to fire ground | Local authorities and if necessary the Minister take active steps to enforce the removal of fire hazards from the vicinity of buildings in rural areas and that special attention be given to the removal of dead trees on the edges of pasture land and on firebreaks in timbered country. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3960 | 33 - Relief and recovery | It is recommended that the Forests Commission recognize and provide for the efficient exercise of three major functions, namely those of Commerce, Reclamation and Rehabilitation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3979 | 32 - Doctrine, standards, and reform | That burning off by "occupiers" on any lands be regulated by permit or by regulation. |
REC013_3968 | 22 - Role of local Gvt | Any number of persons, wishing to form a Bush Fire Brigade, may, by a majority vote of the ratepayers in the particular area, requisition the Shire Council to proclaim such area a Bush Fire Brigade area, and the Council may then impose, with the concurrence of a majority of such ratepayers, a special levy for the purpose of equipping such brigades and carrying out its neccessary functions. |
REC013_3967 | 22 - Role of local Gvt | Each Shire Council shall divide the lands within their respective shires into suitable areas for the formation of Bush Fire Brigades as requested. |