Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC327-4348 | 38 - Agency/Department Reporting | By December 2023, the Rural Fire Service should: report annually on fleet allocations to RFS Districts, and identify the ways in which fleet resources align with district-level fire risks |
REC327-4349 | 38 - Agency/Department Reporting | By December 2023, the Rural Fire Service should: develop performance measures to assess the performance and capabilities of the fleet in each RFS District by recording and publicly reporting on: fire response times and fire response outcomes; and, completions of fire hazard reduction works. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
REC322-4223 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the Department of Environment and Science implements the proposed treatments for fire identified in the Queensland Parks and Wildlife Service K’gari Compliance Strategy. |
REC322-4248 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the prescribed burn program for K’gari be developed by the Department of Environment and Science, in collaboration with the Locality Specific Fire Management Group and the Butchulla people, based on the principles of the National Position on Prescribed Burning. This program should incorporate a process for monitoring and evaluation of outcomes and integration of evolving fire management practices. |
REC322-4224 | 17 - Assets and technology | The Inspector-General Emergency Management recommends the Department of Environment and Science examines the utilisation of technology, in consultation with relevant stakeholders, to improve the collection of visitor numbers and movement data. This could include, for example, expanding the use of Automatic Number Plate Recognition technology to K’gari and examining the suitability of mobile phone check-in applications. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4208 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) develops financial reporting to monitor fuel management costs and estimate future costs. |
REC321-4217 | 5 - Hazard reduction burns | We recommend that DELWP in partnership with Country Fire Authority and Fire Rescue Victoria develops, implements and publicly reports on a holistic suite of performance metrics to demonstrate: - the impact that planned burning has on public and private land on bushfire risk - the impact that planned burning has on public and private land on ecosystem resilience - the impact that non-burn fuel management activities have on public and private land on bushfire risk - the impact that its activities at local and regional levels have on bushfire risk - the cost-effectiveness of its fuel management activities on public and private land. |
REC321-4209 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) systemically documents and publicly reports reasons why it does not complete planned burns. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4177 | 38 - Agency/Department Reporting | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in conjunction with legislated fuel management organisations – develop a common set of objectives, metrics and reporting requirements for fuel management that form part of a compulsory regime that enables the Victorian Government to report publicly on a holistic fuel management program. The reporting requirements should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3847 | 17 - Assets and technology | That, in order to ensure Australia’s fire fighting aerial capacity capitalises on existing assets and is made up of the right mix, Government: |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3817 | 5 - Hazard reduction burns | That Government, noting that hazard reduction targeted in proximity to assets is on balance more likely to provide help than hinder, should: |
REC315-3843 | 17 - Assets and technology | That, in order to improve early fire suppression, the NSW RFS trial initial aerial dispatch in areas of high bush fire risk. The trial should identify the most appropriate and cost-effective mix of aircraft, and any associated infrastructure improvements that would be required. |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3816 | 5 - Hazard reduction burns | That Government re-commit to the current, regionally based approach to planning and coordinating hazard reduction activities across all tenures through Bush Fire Management Committees but ensure that it is actually being implemented at a high-level of quality across NSW. Getting it to a high-level of quality requires: |
REC315-3837 | 17 - Assets and technology | That, in order to improve firefighter safety, Government fire authorities: |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3836 | 17 - Assets and technology | That, in order to ensure frontline personnel have appropriate personal protective clothing during bush fires: |
REC315-3849 | 17 - Assets and technology | That, in order to enhance NSW’s fire fighting capacity, Government trial aerial fire fighting at night in the 2020-21 season with a view to full implementation if successful. |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3815 | 17 - Assets and technology | That, in order to equip NSW RFS with comprehensive information on all structures and assets at risk of bush fire, Government ensures that: |
REC315-3848 | 17 - Assets and technology | That, in order to enhance NSW’s ability to improve situational awareness, Government expand FRNSW’s Remotely Piloted Aerial Systems (RPAS) capability (both capital assets and trained operators) to major regional centres and ensure the NSW RFS and other NSW government agencies can access this capability as required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3266 | 14 - Incident Mgt Teams | Engage with the Australian Defence Force (ADF) once or twice a year to understand the capabilities that could potentially be deployed. Educate IMTs about how to deploy ADF assistance effectively and develop a streamlined ‘call out’ procedure. |
REC314-3270 | 17 - Assets and technology | Review the use of aviation assets including facilities to operate them given the increased pressure from extended fire seasons on northern and southern hemisphere resources. Review line scanning capability with a view to providing real time data to the IMTs on where fires are burning using aviation assets as an intelligence tool rather than just a fire suppression capability. |
REC314-3265 | 14 - Incident Mgt Teams | Prepare to ‘scale up’ capability during major bushfire events with senior representatives (including BoM staff) in the SEC 24/7, ensure adequate facilities for IMTs, base camps (e.g. Humanihuts) and recovery centres. Consider the resource implications of providing firefighters to interstate operations. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2402 | 17 - Assets and technology | Explore better options for call and dispatch, telecommunications and information sharing capability across the emergency management portfolio including the adoption of a multi-agency emergency management operations complex |
REC302-2398 | 17 - Assets and technology | As a matter of priority commence the roll out of AVL capability for the Rural Fire Service fleet, completing as much work as possible before the 2018/19 bushfire season, capitalising where necessary on current and future work undertaken with the NSW Government Radio Network to ensure both officer safety and situational awareness |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1278 | 20 - Role of police | That SA Police develop an evacuation plan for the Adelaide Central Business District (CBD) which includes: |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1307 | 20 - Role of police | That, as with earthquake, SA Police be designated the Control Agency under the State Emergency Management Plan for black system events or other major power outages. |
REC295-1304 | 20 - Role of police | That SA Police, as the control agency for search and rescue, and State Emergency Service who have the responsibility for providing search and rescue services under the State Emergency Management Plan, develop a swiftwater rescue capability plan that describes key swiftwater risk locations, roles and responsibilities of emergency services, State swiftwater resources and dispatch arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
REC290-1219 | 17 - Assets and technology | Live resource tracking system that can be used by all response agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1198 | 17 - Assets and technology | The Committee finds that on the evidence presented, that the Government should undertake a review of how firefighting equipment and gear in Tasmania can be better standardised with interstate equipment and gear to improve cross-jurisdiction resource utilisation. |
REC288-1195 | 5 - Hazard reduction burns | The Committee finds that on the evidence presented, that the Fuel Reduction Burn Program should be maintained and have its budget directly funded to ensure that the program continues and does not hinder other services or programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1377 | 5 - Hazard reduction burns | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC280-1376 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC280-1375 | 5 - Hazard reduction burns | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
REC280-1378 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: -improve accountability in relation to the implementation of bush fire risk management plans as a means of delivering more hazard reduction. |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1139 | 14 - Incident Mgt Teams | SACFS appoint the Regional Controller and/or Coordinator as the IC for any Level 3 incident occurring within their Region to provide better continuity and improved coordination. The position of the regional controller and/or coordinator could then be backfilled by a suitably qualified individual as required. |
REC273-1138 | 14 - Incident Mgt Teams | Review the communication and request procedures within SACFS to ensure that the most effective chain of command and line of communications are established between the Incident Management Team, region and state. |
REC273-1135 | 14 - Incident Mgt Teams | That SACFS conduct a review of SIMT with a view to increasing the number of teams from four to six, aligning them with each of the six regions within SA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1123 | 17 - Assets and technology | Every effort should be made to enhance the ability of communications personnel to cope with fast moving and time critical fire events by providing and maintaining: ongoing extensive communications training; advanced vehicle capability for clear communication within areas of radio coverage dead spots; ability to receive Air intelligence live streaming; map production facilities; deployment of multiple Incident Control Vehicles when required; all Incident Control Vehicles with access to DFES Information Technology Systems. |
REC265-1117 | 17 - Assets and technology | Automatic Vehicle Location technology should be adopted to enable a better appreciation of the deployment and location of appliances at an incident, in order to increase situational awareness |
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1116 | 17 - Assets and technology | Procedures should be established to monitor the use of heavy plant during a bushfire incident, including the tasking of support appliances. Procedures should provide for the appointment of a dedicated Machinery Supervisor as prescribed within the Australasian Interservice Incident Management System. |
REC265-1112 | 17 - Assets and technology | Radio infrastructure in the Perth Hills should be reviewed to assess whether it is practicable for radio and/or mobile phone coverage to be improved to achieve better coverage across the area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1513 | 17 - Assets and technology | That the Minister for Police and Emergency Services review the communications technologies used by the NSW Rural Fire Service, Fire and Rescue NSW, the NSW National Parks and Wildlife Service and Forestry NSW during fire fighting operations, to ensure that systems are standardised and effective. Within this context, the potential value of satellite phone technology should be investigated. |
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC261-1495 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: |
REC261-1493 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1052 | 14 - Incident Mgt Teams | That the Rural Fire Service consider amending its fire prediction reports to include a checklist of significant factors that have not been able to be considered in the prediction model and a warning to be alert for them and seek intelligence on them from fire ground managers. |
REC260-1070 | 5 - Hazard reduction burns | The NPWS conduct a review of its prescribed burns program to ensure, as far as reasonably practicable, that all necessary managerial approvals for a prescribed burn are provided as promptly as possible. |
REC260-1066 | 14 - Incident Mgt Teams | That during periods of ‘severe’ or worse fire conditions, that the National Parks and Wildlife Service consider adopting a posture of pre-emptive planning and deployment of incident management teams in national parks similar to the manner in which the Rural Fire Service does. |
REC260-1063 | 5 - Hazard reduction burns | That the National Parks and Wildlife Service consider reviewing its guidelines and protocols in respect of hazard reduction planning and burning-off operations in the light of the evidence from experts witnesses in these proceedings that the incidence of, and intensity of, major fires is increasing and in the light of expert evidence given in these proceedings concerning the dangers of vorticity-driven lateral spread. |
REC260-1053 | 14 - Incident Mgt Teams | That in Class 3 fire-fighting operations, the Rural Fire Service consider including a fire behaviour analyst in the incident management team if feasible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1541 | 17 - Assets and technology | A Stryker unit, or an upgraded firefighting unit, be present at the range sentry point, remain manned and ready to deploy during range activites, with its driver in direct radio contact with the Range Safety Officer. Upon the range being declared clear by the Safety Officer inspecting the range after a demolition serial, the firefighting unit must proceed forward to the range wile the periphery of the range continues to be inspected by the Safety Officer, and remain on the range until the Safety officer declares that the area is clear of fire or that it is otherwise appropriate for the fireghting unit to leave the range area. |
REC257-1544 | 17 - Assets and technology | Defence should not procure any firefighting vehicle for Marrangaroo Training Area without first consulting relevant personnel within the Rural Fire Service on an appropriate type of vehicle, and obtaining training for the personnel proposed to use it. Alternatively, Defence should explore contracted firefighitng support during periods of live-fire on Marrangaroo Training Area. |
REC257-1542 | 17 - Assets and technology | Firefighitng capability at Marrangaroo Training Area be upgraded so that Australian Defence Force members are not placed in situations of unacceptable risk. Specifically, those participating in range practices must have access to a firefighting vehicle close by and easily deployed, and capable of throwing a large quantity of water an appreciable distance into areas adjacent to the ranges, should a fire occur. |
REC257-1555 | 14 - Incident Mgt Teams | The lines of responsibility be made clearer and some individual, perhaps the Regional Environmental Officer, or agency be given overarching responsibility to ensure recommended works related to bushfire mitigation on Defence Estate are carried out in accordance with the Bushfire Management Plan which the Manual for Fire Protection Engineering directs be prepared. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1582 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0938 | 5 - Hazard reduction burns | That Tasmania Fire Service or another suitable agency provides information to the community which shows, in simple form, the legislation applicable to approvals for lighting fires on private property and the various relationships between that legislation. |
REC247-0880 | 17 - Assets and technology | That bushfire agencies develop, implement and maintain air operations procedures. |
REC247-0879 | 17 - Assets and technology | That bushfire agencies develop procedures for the automatic activation of aircraft to fires at pre-determined trigger points on high fire risk days. |
REC247-0911 | 14 - Incident Mgt Teams | That emergency management plans specifically include processes and resources for effectively engaging with and using local communities, including volunteers |
REC247-0947 | 20 - Role of police | That Tasmania Police develops and implements a program for examining emergency management arrangements and facilities in Australia. |
REC247-0878 | 17 - Assets and technology | That bushfire agencies evaluate the use and effectiveness of fixed wing water bombing aircraft. |
REC247-0894 | 17 - Assets and technology | That the police and other emergency service organisations discuss their resource issues for emergency operations with the Government. |
REC247-0862 | 14 - Incident Mgt Teams | That Tasmania Fire Service and its partner agencies establish a means of monitoring and reviewing the effectiveness of centralising the location of Incident Management Teams. |
REC247-0946 | 20 - Role of police | That Tasmania Police establishes a section within its structure with responsibility for developing and maintaining contemporary expertise in emergency management, progressing innovation, assisting organisational change initiatives and supporting its responsibilities in state emergency management arrangements. |
REC247-0855 | 17 - Assets and technology | That a structure and facilities be established for the State Controller or other person managing multi-agency response and recovery operations. |
REC247-0893 | 17 - Assets and technology | That further options to appropriately supplement the resources available for emergency management operations be examined. |
REC247-0861 | 14 - Incident Mgt Teams | That Tasmania Fire Service examines options for developing and issuing fire management objectives and tactics from Incident Management Teams in a more timely way, including ‘quick’ plans. |
REC247-0945 | 20 - Role of police | That Tasmania Police conducts a review to ensure emergency management is treated as a priority and a core function throughout the organisation, including the development of contemporary capabilities, and is supported by an appropriate culture. |
REC247-0939 | 5 - Hazard reduction burns | That Tasmania Fire Service conducts a review of the fire permit system in the Fire Service Act 1979, and implements change to improve the efficiency and effectiveness of the system by: • considering whether it is appropriate to authorise persons or organisations to conduct fuel reduction burning during a permit period • providing a better match between the period, area and fire risk • maintaining a timely and efficient process for issuing permits • naming the period in a way that draws attention to bushfire risk • establishing a reporting and accountability process. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0892 | 17 - Assets and technology | That a review be conducted of the resource capacity and capability to provide effective and efficient emergency operations, including approved improvements. |
REC247-0853 | 14 - Incident Mgt Teams | That the State Controller (or an alternate if they are not available) be expected to personally take an active role in controlling and coordinating response and recovery operations, depending on the nature and scale of the emergency, and until other identified arrangements for ongoing operations are established. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0786 | 14 - Incident Mgt Teams | TFS develop written guidelines for the use of IMTs about the use of evacuation in a bushfire context, and triggers for decision-making. |
REC246-0784 | 17 - Assets and technology | Recommendation 9 TFS should review the capacity of its Fire Information Line to handle very large scale events, and explore additional options for a surge capability for the Fire Information Line. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1027 | 17 - Assets and technology | That Rural Fire Service Queensland, in consultation with Primary Producer Brigade volunteers, redesign and reconfigure slip-on units to bring the total cost below the level required for asset registration. The redesign should allow for the foam system to be optional. |
REC241-1042 | 17 - Assets and technology | The issue of red and blue lights for RFSQ and SES vehicles be further pursued by the Department of Community Safety |
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-0973 | 17 - Assets and technology | That all land on which rural fire brigade sheds are located be re-evaluated to formalise enforceable lease agreements. |
REC241-1026 | 17 - Assets and technology | That the Rural Fire Service Queensland catalogue accurately reflects the range of equipment available. |
REC241-1039 | 17 - Assets and technology | That the State Government supply and logistics for Personal Protective Equipment and other equipment be urgently reviewed with a focus on timely and cost effective delivery to volunteer members. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-0970 | 17 - Assets and technology | That RFSQ retain responsibility for Air Operations and re-evaluate avenues for cost recovery when aircraft are used by other agencies. The coordination of incendiary tasking to support mitigation should sit with the RFSQ in coordination with other agencies |
REC241-1025 | 17 - Assets and technology | That an ‘Options Paper’ be developed by District Inspectors on the suitability and supply of PPE and equipment to volunteers for their district. |
REC241-1036 | 17 - Assets and technology | That each District Inspector prepare a report on vehicles required over the next ten years based on current age of fleet. |
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-1024 | 17 - Assets and technology | That the Rural Fire Service Queensland revoke its current 20 year maximum age policy on volunteer Brigade vehicles to allow Brigades wanting to retain their vehicle to do so, providing the vehicle has an annual mechanical certificate. A 30 year maximum age policy for vehicles will replace the 20 year policy. |
REC241-1029 | 17 - Assets and technology | That a policy be developed around the ownership, insurance and safe use and operation of All Terrain Vehicle 4WD vehicles by brigades for fire fighting purposes. |
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-1012 | 17 - Assets and technology | Use of private aircraft to be at the discretion of District Inspector or Incident Control and reimbursement of fuel to be authorised accordingly. |
REC241-1028 | 17 - Assets and technology | That vehicles are fit for the purpose and the Brigade locality for which they are intended. A group of two volunteers, in conjunction with the Rural Fire Brigades Association Queensland, should be charged with reviewing current models and providing Recommendations on vehicle suitability. |
REC241-1009 | 17 - Assets and technology | That the reflective livery on Rural Fire Service Queensland staff vehicles be kept to a minimum of a light bar and affixed Rural Fire Service Queensland logo. These vehicles are to be appropriate to the task and location. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1615 | 38 - Agency/Department Reporting | The Territory and Municipal Services Directorate, as part of its Bushfire Operations Plan monitoring and reporting, should assess and publicly report on cumulative progress against broader outcomes identified in the Regional Fire Management Plans and the Strategic Bushfire Management Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0583 | 17 - Assets and technology | The state should converge on a single communications platform for all emergency management and support agencies. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0582 | 17 - Assets and technology | The state should progressively align on a shared platform, such as WebEOC, to establish a COP [Common Operating Picture or Platform?]. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC225-0533 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1645 | 14 - Incident Mgt Teams | Ensure that adequate administrative personnel are available within the incident control structure to provide administrative and knowledge management support for incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0506 | 17 - Assets and technology | The Minister for Emergency Services ensure that FESA has the funds to implement the installation and use of WebEOC for use during the 2011-12 bushfire season and immediately put in place common protocols with the Police and DEC to record significant events during a bushfire. |
REC202-0496 | 17 - Assets and technology | The Minister for Emergency Services ensure that a whole-of-government equipment register of the firefighting equipment held by FESA, DEC and local government authorities is in place for the 2012-13 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
REC201-0249 | 17 - Assets and technology | FRS fire appliance allocation and training needs to be reviewed to enhance offensive bushfire capability within the metropolitan area. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0378 | 17 - Assets and technology | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-0368 | 20 - Role of police | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
REC200-0365 | 17 - Assets and technology | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA’s own policy of ‘Use of Private Vehicles in Fires’. |
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
REC200-0364 | 17 - Assets and technology | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-0388 | 17 - Assets and technology | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-0387 | 17 - Assets and technology | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the Recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0336 | 20 - Role of police | Victoria Police, under the auspice of the Regional Emergency Response Plan, lead a task force to ensure that the Princes Highway is treated as an asset of significance and an appropriate risk-based approach is adopted to minimise the impact of fire. This approach is to be integrated into regional and municipal fire management plan |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0227 | 5 - Hazard reduction burns | Local government councils implement a zoning approach to fuel management as recommended by COAG 2004. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
REC183-0119 | 17 - Assets and technology | The development of a three year aerial firefighting strategy for W.A. would ensure optimal development of a joint air capability. |
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
REC183-0120 | 17 - Assets and technology | Maintaining the DEC fleet of tankers, bulldozers and low loaders is crucial to DEC’s fire management and control capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
REC182-0134 | 17 - Assets and technology | FESA reviews its air reconnaissance capability and determines if multiple multi-sensor air reconnaissance aircraft or unmanned aerial vehicles are required for managing concurrent and/or complex incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0206 | 5 - Hazard reduction burns | The State fund and commit to implementing a long-term program of prescribed burning based on an annual rolling target of 5 per cent minimum of public land. |
REC181-0170 | 17 - Assets and technology | The Country Fire Authority and the Department of Sustainability and Environment amend their policies on aerial preparedness and standby arrangements, their dispatch protocols and the management of aircraft in order to do the following: ■ require that at locations that attract the risk assessment or preparedness level A on code red days all personnel needed for air operations must be on standby by 10.00 am; ■ establish a system that enables the dispatch of aircraft to fires in high-risk areas without requiring a request from an Incident Controller or the State Duty Officer. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0185 | 20 - Role of police | Victoria Police continue to pursue a coordinated statewide approach to arson prevention and regularly review its approach to ensure that it contains the following elements: ■ high-level commitment from senior police; ■ a research program aimed at refining arson prevention and detection strategies; ■ centralised coordination that includes comprehensive training, periodic evaluation of arson prevention strategies and programs, and promotion of best-practice prevention approaches; ■ a requirement that all fire-prone police service areas have arson prevention plans and programs, according to their level of risk. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0160 | 20 - Role of police | The State clarify whether, during major fires, Victoria Police should discharge its coordination functions from the State Emergency Response Coordination Centre or from the State Control Centre. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0207 | 5 - Hazard reduction burns | The Department of Sustainability and Environment report annually on prescribed burning outcomes in a manner that meets public accountability objectives, including publishing details of targets, area burnt, funds expended on the program, and impacts on biodiversity. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0171 | 17 - Assets and technology | The State, in conjunction with Emergency Management Australia and the Department of Defence, develop an agreement that allows Commonwealth aerial resources that are suitable for firefighting and support activities to be incorporated in preparedness plans and used on days of high fire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0147 | 5 - Hazard reduction burns | The Commonwealth encourages further research into prescribed burning and its effectiveness and into alternative bushfire mitigation approaches through improved bushfire risk understanding at the asset level. |
REC176-0150 | 17 - Assets and technology | The committee recommends that the Commonwealth co-ordinate a national approach to the pooling of ground fire fighting resources across agencies and jurisdictions to maximise the efficiency of their use. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0028 | 17 - Assets and technology | Ensure the S61 helicopter has all appropriate channels for water bombing operations throughout the State by including this requirement on a pre-deployment checklist. |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0026 | 17 - Assets and technology | At large incidents a communications bus should be provided for the use by Air Ops and a designated work space should be provided for the Air Ops management group. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0025 | 17 - Assets and technology | Suppression resources should be ordered and mobilised as 2 truck Strike Teams with a STL and consistently deployed to the fire ground as a unit. |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0019 | 17 - Assets and technology | A centralised, regional, multi-agency resource coordination and tracking system/facility be established to accommodate and coordinate the movement of resources from all agencies within and between regions. |
REC172-0047 | 17 - Assets and technology | There is an established need to develop mobile accommodation and accommodation facility support solutions that allows an acceptable standard of accommodation to be provided to fire fighters in close proximity to the incident. |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0029 | 17 - Assets and technology | Provide a photocopier in the Mobile Communications Facility or the mobile equipment cache that is capable of large volume production of collated documents. |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0069 | 17 - Assets and technology | That in any consideration being given to the allocation of responsibility for control of operations in respect of major fires, consideration be given to the availability of technology and other resources, particularly when particular skills are required to make best use of such technology or resources. |
REC171-0067 | 14 - Incident Mgt Teams | That to the extent it has not already done so, DEC take action to ensure that in future cases relevant weather forecast information, particularly information as to significant wind changes, is promptly transmitted through the Incident Management Team and made available to persons with field operation responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3477 | 38 - Agency/Department Reporting | That the details of any variation or amendment of a Fire Operations Plan, including: the carrying forward or postponement of burns within the three-year period covered by a Fire Operations Plan; the carry over, removal or rescheduling of burns between past, present and future Fire Operations Plans; and the alteration of burn boundaries (including alterations of less than 25 per cent); should appear on the Department of Sustainability and Environment’s website at the time of the change and be included in the Fire Operations Plan for the following year. |
REC155-3476 | 38 - Agency/Department Reporting | That finalised Fire Operations Plans be made publicly available in their entirety (with the exception of any private information) on the Department of Sustainability and Environment’s website and in hard-copy, and that this requirement be clearly stated in future Codes of Practice. This should include the “district burns list”, or its future equivalents, and a map which shows the corresponding burns for each Fire District. Each map should be provided in a format which can be downloaded directly from the Department’s website without the need for further data manipulation by the user. An identical hardcopy version of the map for each Fire District should be also be available to members of the public on request and free of charge. |
REC155-3468 | 38 - Agency/Department Reporting | That the Department of Sustainability and Environment, Department of Primary Industries, Parks Victoria & VicForests separately cost, and report, annual expenditure on fuel reduction burning, ecological burning and regeneration burning in their Annual Reports. |
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
REC155-3467 | 38 - Agency/Department Reporting | The Department of Sustainability and Environment should report its performance against the increased prescribed burning target in its annual report, which should also include the following details: |
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
REC155-3478 | 38 - Agency/Department Reporting | That all information pertaining to current and planned prescribed burns be published more prominently on the Department of Sustainability and Environment’s website, with a single prominent link to this material on the website homepage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1803 | 17 - Assets and technology | That the Minister for Emergency Services give further consideration to acquiring a firefighting helicopter to be permanently or primarily stationed in South Australia. |
REC153-1799 | 14 - Incident Mgt Teams | That the South Australian Country Fire Service establish preplanned Level 2 Incident Management Teams in each Region for deployment to Level 2 incidents. |
REC153-1777 | 5 - Hazard reduction burns | That the Minister for Emergency Services and the Minister for Local Government consider the enactment of legislation that would empower Local Government to require the owners or occupiers of rural land to create fire breaks on the land of a kind that Local Government may determine and/or to require the removal of flammable materials from the land, as measures for preventing the outbreak of a bushfire, or for preventing the spread or extension of a bushfire. |
REC153-1791 | 14 - Incident Mgt Teams | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service consider the creation of a position within an Incident Management Team of a Landowner Liaison Officer the duties and responsibilities of whom is to establish contact with and liaise with the owner and/or occupiers of rural land on which a fire is situated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3125 | 38 - Agency/Department Reporting | QFRS introduce a system to collate and analyse performance information for use in management reporting and to support effective decision making processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3523 | 38 - Agency/Department Reporting | This Report should be considered for publication so that the insights, data, conclusions and recommendations are available within Queensland and other jurisdictions to assist with disaster management issues in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-1953 | 14 - Incident Mgt Teams | That appointments of personnel to functional positions within the incident management team be based solely on competence and experience and be made by the Chief of the ACT Rural Fire Service or, in the absence of that officer, the Deputy Chief of the ACT Rural Fire Service |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3884 | 5 - Hazard reduction burns | Develop new prescriptions for prescribed burning to accommodate local conditions in those areas where standard prescriptions are assessed to be inappropriate: |
REC124-3885 | 5 - Hazard reduction burns | Align policies and processes, within the year round 365 day focus on fire management, to provide consistency in the approach to fire regardless of its origins,- that is fuel reduction burning, regeneration and ecological burning or unplanned fire; |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
REC113-3902 | 14 - Incident Mgt Teams | Government should: establish a State-wide command structure across volunteer Bush Fire Brigades for fighting major bushfires, to more effectively manage the coordination of personnel and resources |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2193 | 38 - Agency/Department Reporting | That if ‘link’ burns continue to be used, then on-site weather sequences and fuel conditions marking successful (‘within explicit prescription’) and unsuccessful burns be documented. |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2290 | 38 - Agency/Department Reporting | That instances where demand for air support outstrips the supply of State Fleet Aircraft available are recorded. |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2289 | 38 - Agency/Department Reporting | That the joint agencies introduce a system of performance measures for reporting the effectiveness of aircraft in firefighting operations. |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2200 | 38 - Agency/Department Reporting | That DSE: |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2286 | 17 - Assets and technology | That CFA, having regard to terrain, continue to review the mix of firefighting appliances currently in service. In particular, consideration should be given to the number and distribution of smaller ‘slip-on’ type equipment. |
REC104-2195 | 38 - Agency/Department Reporting | That the creation of buffers by chaining and then burning swaths of mallee be explicitly monitored for: |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2194 | 38 - Agency/Department Reporting | That the success of current buffers in terms of assisting suppression operations be continually reviewed, evaluated and documented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2186 | 38 - Agency/Department Reporting | The Committee recommends that the Department of Transport and Regional Services review its record keeping practices to show the type of emergency for which assistance is provided through the Natural Disaster |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2139 | 17 - Assets and technology | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments initiate consideration of the relaxation of restrictions on the movement of fire fighting equipment |
REC098-2142 | 5 - Hazard reduction burns | The Committee recommends that the Commonwealth seek to ensure that the Council of Australian Governments seek agreement from the states and territories on the optimisation and implementation of prescribed burning targets and programs to a degree that is recognised as adequate for the protection of life, property and the environment. The prescribed burning programs should include strategic evaluation of fuel management at the regional level and the results of annual fuel management in each state should be publicly reported and audited. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4153 | 17 - Assets and technology | No opportunity be lost by the Forests Department to improve the efficiency of their fire fighting gangs, radio and other equipment in the light of the latest practical and scientific developments. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3949 | 17 - Assets and technology | It is recommended that the A.R.P. dams or earth tanks be kept filled during possible danger periods. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3975 | 5 - Hazard reduction burns | To burn, where necessary, at least 33 feet where there is a risk of fire, on the outside of the railway fence, in conjunction with the railway employees. |