REC327-4347 | 36 - Volunteers | By December 2023, the Rural Fire Service should: develop a strategy to ensure that local brigade volunteers are adequate in numbers and appropriately trained to operate fleet appliances in the RFS Districts where they are required. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4315 | 36 - Volunteers | The Community First Responders Program: That, to better coordinate community efforts to save life and property during a disaster, Government create a ‘Community First Responders Program’, funding appropriate community equipment and training, particularly in high-risk catchments along the east coast of NSW. This training would be delivered by combat and/or other appropriate government agencies. This program could support and empower community led initiatives such as disaster response, evacuation centres and the provision of services such as psychological first aid. |
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4265 | 34 - Local knowledge | That the NSW Government work with First Nations peoples to support Aboriginal organisations in their capacity to operate and respond in times of natural disasters. |
REC323-4275 | 34 - Local knowledge | That the NSW Government, in partnership with community groups, including First Nations groups, develop initiatives to build community resilience, particularly in regions at high risk of future natural disaster events. |
REC323-4276 | 34 - Local knowledge | That the NSW Government ensure that community groups, both existing and emerging, including First Nations groups, are well integrated into disaster recovery, by incorporating them into state recovery plans and engaging with them in between and in the lead up to natural disasters. |
REC323-4287 | 34 - Local knowledge | That the NSW State Emergency Service, in partnership with the Bureau of Meteorology, investigate ways in which local communities and local media with local knowledge can play a stronger role in flood predictions and warnings. |
REC323-4264 | 34 - Local knowledge | That the NSW Government work in partnership with key Aboriginal stakeholders, including the Jali Local Aboriginal Land Council, to prioritise the rebuild of Cabbage Tree Island, and ensure a safe and resourced evacuation plan is in place. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4227 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the membership of the K’gari Locality Specific Fire Management Group be expanded to include representatives of the Butchulla people, community associations from each township and tourism and business operators with interests on the island. |
REC322-4230 | 34 - Local knowledge | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services engages with land managers and other stakeholders on K’gari to source data to inform Predictive Services products. |
REC322-4235 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science review the resourcing model to ensure surge capacity is available to support incident management functions during response operations. This includes processes to request assistance from other departments and entities with responsibilities for fire and incident management. |
REC322-4250 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the Locality Specific Fire Management Group for K’gari meet at least twice per year, in person or virtually. |
REC322-4243 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science identify opportunities to increase Queensland Parks and Wildlife Service’s capability in incident management and multi-agency fire response, through exercising plans and procedures in collaboration with other stakeholders, including disaster and fire management groups at all levels. |
REC322-4245 | 14 - Incident Mgt Teams | The Inspector-General Emergency Management recommends the Department of Environment and Science establish pre-determined financial delegations and authority for Queensland Parks and Wildlife Service Incident Controllers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4212 | 34 - Local knowledge | We recommend that DELWP increases its collaboration with Victorian Traditional Owner groups to facilitate the reintroduction of cultural burning and ensure effective support for these practices across all of its regions. |
REC321-4216 | 13 - Mapping and data quality | We recommend that DELWP enhances bushfire modelling by: - exploring multiple bushfire modelling tools to lower the uncertainty and limitations associated with using a single modelling tool - applying more detailed fire-severity data - validating and updating fuel accumulation curves - establishing and regularly updating an archive of well-documented fire events and using this to systematically test it against a broad range of burning and fuel conditions - establishing and implementing processes to routinely review and update its underlying datasets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4197 | 36 - Volunteers | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department develop and resource an ongoing strategy to coordinate spontaneous volunteers that can be activated before, during or after emergencies. |
REC319-4186 | 34 - Local knowledge | Supporting local recovery: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department work with councils and communities before, during and after emergencies to strengthen: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4183 | 13 - Mapping and data quality | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in consultation with relevant agencies – develop a system to manage personnel and asset deployments to all tiers of incident management to meet the needs of the emergency and support the health and wellbeing of personnel. Where appropriate and within occupational health and safety requirements, this may include: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4065 | 13 - Mapping and data quality | Australian, state and territory governments should continue to develop a greater capacity to collect and share standardised and comprehensive natural disaster impact data. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4060 | 13 - Mapping and data quality | Australian, state and territory governments should create common information platforms and share technologies to enable collaboration in the production, analysis, access, and exchange of information, data and knowledge about climate and disaster risks. |
REC317-4109 | 13 - Mapping and data quality | Australian, state and territory governments should develop consistent processes for the classification, recording and sharing of fuel load data. |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4059 | 13 - Mapping and data quality | Australian, state and territory governments should prioritise the implementation of harmonised data governance and national data standards. |
REC317-4106 | 13 - Mapping and data quality | Australian, state and territory governments should ensure greater consistency and collaboration in the collation, storage, access and provision of data on the distribution and conservation status of Australian flora and fauna. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4105 | 13 - Mapping and data quality | Australian, state and territory governments should agree to: |
REC317-4068 | 13 - Mapping and data quality | Australian, state and territory governments should establish a national register of fire and emergency services personnel, equipment and aerial assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3800 | 13 - Mapping and data quality | That the NSW Government, along with other Australian governments, ask AFAC to establish a national bush fire database. This database would enable: |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3819 | 13 - Mapping and data quality | That, as part of the spatial technology acceleration program, Government support deployment of remote sensing and picture processing technologies to monitor and audit how well Asset Protection Zones and defendable space are being maintained, especially around towns. |
REC315-3801 | 13 - Mapping and data quality | That, in order to improve capability to detect ignitions and monitor accurately all fire edge intensity and progression automatically across the State in near real time, Government establish a spatial technology acceleration program to maximise the information available from the various remote sensing technologies currently in use and to plan for inclusion of new remote sensing systems that can sense precisely and rapidly through heavy smoke, cloud, fog and dust. This will require work within the State and with partners nationally and internationally. |
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3265 | 14 - Incident Mgt Teams | Prepare to ‘scale up’ capability during major bushfire events with senior representatives (including BoM staff) in the SEC 24/7, ensure adequate facilities for IMTs, base camps (e.g. Humanihuts) and recovery centres. Consider the resource implications of providing firefighters to interstate operations. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3266 | 14 - Incident Mgt Teams | Engage with the Australian Defence Force (ADF) once or twice a year to understand the capabilities that could potentially be deployed. Educate IMTs about how to deploy ADF assistance effectively and develop a streamlined ‘call out’ procedure. |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2479 | 34 - Local knowledge | Local groups should plan for and establish clear arrangements to effectively manage offers of assistance including the management of goods, services and volunteers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2437 | 13 - Mapping and data quality | The ability to share, analyse, interrogate and display information from disparate entities should be progressed as a matter of some urgency. |
REC307-2446 | 14 - Incident Mgt Teams | Coordinated arrangements for liaison officer deployment should be considered and documented by disaster management groups across the full spectrum of risk identified for their area of responsibility, and not rely on a singular inflexible approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2384 | 36 - Volunteers | TFS should pursue the creation of a cadre of volunteer remote area firefighters. In doing so the TFS should not consider itself limited to upskilling of current volunteer brigade members, but should carry out a cost benefit analysis of creating one or more remote area firefighting units based in urban areas, in order to tap into the potential of those members of the urban-based Tasmanian community who may have advanced knowledge and skills relating to navigation and survival in wilderness areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1345 | 36 - Volunteers | That issues of animal welfare be given a higher practical priority in the planned burning process on the ground, including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1254 | 13 - Mapping and data quality | That Government: |
REC297-1265 | 13 - Mapping and data quality | That BoM and the Flood Warning Consultative Committee, in consultation with gauge owners, review flood gauges and develop a program to update data used to support hydrologic modelling. This should include reviewing gauge maintenance before and after floods. |
REC297-1253 | 13 - Mapping and data quality | That agencies undertaking flood studies adopt a standardised approach, based on Australia Handbook 7, maintain public ownership of underlying data sets to support future modelling, and ensure open access to these studies. |
REC297-1263 | 13 - Mapping and data quality | Subject to funding, that the Flood Warning Consultative Committee investigates the hydrological matters and advice received during this Review and detailed in this Report in Sections 4.1.9 and 4.1.11. |
REC297-1252 | 13 - Mapping and data quality | That SES uploads current flood studies and plans to the Common Operating Platform as a flood plan layer and that councils, subject to resolving licence restrictions, arrange to have appropriate access. |
REC297-1262 | 13 - Mapping and data quality | That the Flood Warning Consultative Committee considers the merits of delineating the Ouse River as a separate catchment from the Derwent River Basin. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1305 | 18 - Access to fire ground | That the annexure to the State Emergency Management Plan, ‘Traffic management during emergencies’, be updated to include: responsibilities and processes for road closures; and, Department of Planning, Transport and Infrastructure requirements in regards to provision of road closure information, notification of changes in road closure status and publishing of that information. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1246 | 18 - Access to fire ground | The State Emergency Management Committee to review the policy for traffic management at emergency incidents so it reflects national ‘best practice’. This includes the production and issuing of an aide-memoire to guide traffic management, emergency and incident management personnel. |
REC291-1240 | 14 - Incident Mgt Teams | The Departments of Parks and Wildlife and Fire and Emergency Services to adopt the policy that all bushfire Level 3 Incident Management Teams in the Perth Hills and the South West will be integrated and pre-formed from the start of the 2016/17 fire season with substantial involvement of both the Departments of Parks and Wildlife and Fire and Emergency Services personnel on all teams. |
REC291-1245 | 18 - Access to fire ground | The Department of Fire and Emergency Services to issue a photo identification card to DFES members, members of Bush Fire Brigades, volunteer emergency services, Incident Management Teams, forestry industry brigade members and Networked Government Emergency Agency members. DFES also to consider temporary windscreen signage to identify vehicles carrying such personnel. |
REC291-1239 | 14 - Incident Mgt Teams | The State Government to establish an arrangement to develop a ‘network’ of Western Australian State Government agency personnel who can be called upon for bushfire and emergency incident management capability within Western Australia. The arrangement will be led by the State Emergency Management Committee and modelled on systems used by the Department of Parks and Wildlife. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1213 | 34 - Local knowledge | Structures to incorporate local knowledge and situational awareness into the fire response |
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1199 | 36 - Volunteers | The Committee finds that on the evidence presented, that volunteer firefighters are at risk of being undervalued and underrated and that the Government should use best endeavours to ensure the full acknowledgement and recognition of these services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1202 | 13 - Mapping and data quality | Impact Assessment Data Collection: The Office of Emergency Management continues to progress the Impact Assessment Data Collection Project and: · incorporate recovery schema in Rapid Impact Assessments · review procedures for collection of Rapid Impact Assessment Data · review and combine current templates into one, single template for Impact Assessment Reports that is used by all agencies · further develop Impact Assessment Guidelines for agency personnel undertaking impact assessments |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1393 | 36 - Volunteers | That the NSW Rural Fire Service formally recognise the Volunteer Fire Fighters Association as a legitimate advocacy organisation representing volunteer bush fire fighters, and duly consult with it on policy and operational matters. |
REC280-1380 | 13 - Mapping and data quality | That the NSW Rural Fire Service investigate mechanisms to enhance the predictability of megafires and how this information is communicated easily to the public. |
REC280-1392 | 36 - Volunteers | That the NSW Rural Fire Service, in order to ensure greater respect for volunteer fire fighters’ knowledge and experience in the management of fires: |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1139 | 14 - Incident Mgt Teams | SACFS appoint the Regional Controller and/or Coordinator as the IC for any Level 3 incident occurring within their Region to provide better continuity and improved coordination. The position of the regional controller and/or coordinator could then be backfilled by a suitably qualified individual as required. |
REC273-1138 | 14 - Incident Mgt Teams | Review the communication and request procedures within SACFS to ensure that the most effective chain of command and line of communications are established between the Incident Management Team, region and state. |
REC273-1135 | 14 - Incident Mgt Teams | That SACFS conduct a review of SIMT with a view to increasing the number of teams from four to six, aligning them with each of the six regions within SA. |
REC273-1142 | 18 - Access to fire ground | That SACFS consider the Traffic Management Procedures and guiding principles adopted in Tasmania as a model that could be implemented within SA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1533 | 14 - Incident Mgt Teams | State Disaster Coordination Centre considers requesting a representative from critical infrastructure owners be present as a liaison officer in the State Disaster Coordination Centre during activations for events that may impact on their assets. |
REC271-1526 | 13 - Mapping and data quality | In accordance with recommendations of the BMT WBM report, the Banana Shire Council, SunWater, and the Bureau of Meteorology, under the stewardship of the Department of Natural Resources and Mines, jointly identify the requirements for a suitable gauge network for the Callide Valley to allow meaningful and timely flood warnings. The review should identify key stakeholders, examine potential funding sources and include a cost benefit analysis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1152 | 13 - Mapping and data quality | Impact Assessment Data Sharing Project |
REC267-1154 | 36 - Volunteers | Coordination of Volunteer Support |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1122 | 18 - Access to fire ground | DFES, in consultation with bushfire volunteers should develop a procedure for the controlled entry and exit of volunteers to the fire ground |
REC265-1121 | 18 - Access to fire ground | A Restricted Access Permit system for the entry/ re-entry of residents, based on the one developed for the Parkerville Stoneville Mt Helena Bushfire should be finalised. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
REC264-1076 | 13 - Mapping and data quality | The State equip itself to undertake rapid air quality monitoring in any location in Victoria, to: • collect all relevant data, including data on PM , carbon monoxide and ozone; and 2.5 • ensure this data is used to inform decision-making within 24 hours of the incident occurring. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1510 | 36 - Volunteers | That the NSW Rural Fire Service formally recognise the Volunteer Fire Fighters Association as a legitimate advocacy organisation representing volunteer bush fire fighters, and duly consult with it on policy and operational matters. |
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC261-1509 | 34 - Local knowledge | That the NSW Rural Fire Service, in order to ensure greater respect for volunteer fire fighters’ knowledge and experience in the management of fires: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1053 | 14 - Incident Mgt Teams | That in Class 3 fire-fighting operations, the Rural Fire Service consider including a fire behaviour analyst in the incident management team if feasible. |
REC260-1061 | 18 - Access to fire ground | That the National Parks and Wildlife Service, in consultation with the relevant local Council(s), devise a policy that enables the John Renshaw Parkway to be closed at either end of the Warrumbungle National Park during a bush fire in such a way that its closure would not impede access by emergency services vehicles into the park. |
REC260-1055 | 34 - Local knowledge | That the Rural Fire Service together with other land managers develop a program whereby local stakeholders come together regularly (every 2 months during non-fire season and monthly during the fire season) to share intelligence and to consider hazard and incident management measures for implementation. |
REC260-1052 | 14 - Incident Mgt Teams | That the Rural Fire Service consider amending its fire prediction reports to include a checklist of significant factors that have not been able to be considered in the prediction model and a warning to be alert for them and seek intelligence on them from fire ground managers. |
REC260-1050 | 13 - Mapping and data quality | Alternatively, I recommend that the RFS consider developing such capacity to deploy weather balloons itself, in conjunction with mobile weather stations, for this purpose. |
REC260-1049 | 13 - Mapping and data quality | That the Rural Fire Service consider proposing an arrangement with the Bureau of Meteorology to deploy weather balloons specifically for the purpose of assessing atmospheric instability during periods of severe to catastrophic fire danger in locations most likely to be severely affected, for example, areas in which a very high C-Haines index reading is registered and local fires have been identified. |
REC260-1066 | 14 - Incident Mgt Teams | That during periods of ‘severe’ or worse fire conditions, that the National Parks and Wildlife Service consider adopting a posture of pre-emptive planning and deployment of incident management teams in national parks similar to the manner in which the Rural Fire Service does. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1555 | 14 - Incident Mgt Teams | The lines of responsibility be made clearer and some individual, perhaps the Regional Environmental Officer, or agency be given overarching responsibility to ensure recommended works related to bushfire mitigation on Defence Estate are carried out in accordance with the Bushfire Management Plan which the Manual for Fire Protection Engineering directs be prepared. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0853 | 14 - Incident Mgt Teams | That the State Controller (or an alternate if they are not available) be expected to personally take an active role in controlling and coordinating response and recovery operations, depending on the nature and scale of the emergency, and until other identified arrangements for ongoing operations are established. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0906 | 18 - Access to fire ground | That emergency management plans recognise the need to provide priority access to areas of emergency operations for critical infrastructure providers. |
REC247-0911 | 14 - Incident Mgt Teams | That emergency management plans specifically include processes and resources for effectively engaging with and using local communities, including volunteers |
REC247-0875 | 34 - Local knowledge | That Tasmania Fire Service reviews its integration of rural local knowledge and volunteer brigades into fire operations, develops and maintains appropriate strategies, and aims to be a best-practice fire service in this regard. |
REC247-0899 | 18 - Access to fire ground | That appropriate plans are made to mobilise resources quickly to re-open roads affected by emergencies. |
REC247-0860 | 13 - Mapping and data quality | That Tasmania Fire Service establishes suitable systems and practices for recording fire management objectives and tactics. |
REC247-0862 | 14 - Incident Mgt Teams | That Tasmania Fire Service and its partner agencies establish a means of monitoring and reviewing the effectiveness of centralising the location of Incident Management Teams. |
REC247-0865 | 34 - Local knowledge | That Tasmania Fire Service reviews its position on using local experienced officers on the fire ground in the command model in a structured and systemic way. |
REC247-0885 | 18 - Access to fire ground | That arrangements are made for and appropriate pre-planning occurs to effectively implement the policy on road closures and traffic management. |
REC247-0851 | 13 - Mapping and data quality | That if a sound business case is developed, the Emergency Information Management and Sharing Project be supported. |
REC247-0861 | 14 - Incident Mgt Teams | That Tasmania Fire Service examines options for developing and issuing fire management objectives and tactics from Incident Management Teams in a more timely way, including ‘quick’ plans. |
REC247-0863 | 34 - Local knowledge | That Tasmania Fire Service considers measures to bring local knowledge into Incident Management Team operations. |
REC247-0884 | 18 - Access to fire ground | That Tasmania Police reviews its Emergency Traffic Management Points policy; and develops a multi-agency policy in the emergency management plans for road closures and traffic management, including clarity in decision making, coordination and sufficient operational flexibility. |
REC247-0850 | 13 - Mapping and data quality | That police and other emergency service agencies establish and maintain effective recording systems for emergency operations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0785 | 13 - Mapping and data quality | TFS should take steps to obtain cell transmission coverage maps for LBS-based EA messages and take note of the need for training of staff to ensure that messages are drafted carefully and appropriately so as to take cell transmission coverage into account. |
REC246-0786 | 14 - Incident Mgt Teams | TFS develop written guidelines for the use of IMTs about the use of evacuation in a bushfire context, and triggers for decision-making. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1003 | 13 - Mapping and data quality | The Manager of the Geographic Information Systems unit conduct an audit of the Firecom mapping system to ensure that rural Brigade and road addressing is up to date. |
REC241-0978 | 36 - Volunteers | That in recognition of their commitment to the community volunteers employed by the State Government should be released to assist as volunteers for up to five (5) days per year in appropriately identified emergency operations. |
REC241-1002 | 13 - Mapping and data quality | That the Rural Fire Service Queensland upgrades its subscription to technology for the Brigade Mapping Toolset to make it available to all Brigades who want it. |
REC241-0955 | 36 - Volunteers | That corporate support, such as administration and finance, to volunteer services be shared to enable a closer working relationship between the services. |
REC241-0971 | 13 - Mapping and data quality | That the RFSQ central office undertake a review of Firecom procedures in relation to Rural Fire Service callouts. Each Rural Fire Service Queensland district office should also undertake a review of the Firecom data sets/callout information for their district to establish call out protocols are correct. |
REC241-1040 | 36 - Volunteers | That RFSQ review local SAP function and delegation to enable effective and timely support for volunteers. |
REC241-1023 | 13 - Mapping and data quality | That Rural Fire Service Queensland develops a simple data collection system to record the activities of brigades. |
REC241-1017 | 36 - Volunteers | That each District office establish and maintain a register of suitably qualified Australasian Inter-service Incident Management System trained volunteers who are prepared to undertake the management of operations and provide these to the District Fire Management Group. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0799 | 18 - Access to fire ground | Develop and implement a program of cost-effective road improvement works that can enhance flood evacuation capacity in the short-medium term. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0561 | 34 - Local knowledge | Suitably experienced local representatives should be engaged to provide advice to the IMT in all Level 2 and Level 3 incidents at the earliest opportunity. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0576 | 13 - Mapping and data quality | Better maps are required for urban/rural interface fires |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0547 | 13 - Mapping and data quality | Fuel loads on private property need to be identified and included in understanding fire behaviour in determine the contribution they make to the burn risk assessment. |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0546 | 13 - Mapping and data quality | Maps prepared for prescribed burns should address the fuel type and burn history of the burn area as well as surrounding areas. Predicted rates of spread under prescribed and other conditions should recognise the complexity of coastal heathlands. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1630 | 13 - Mapping and data quality | The Minister for Emergency Services ensure that a Statewide fuel load database that includes data from Western Power, the Department of Fire and Emergency Services and the Department of Environment and Conservation be established before the 2013-14 bushfire season. |
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0519 | 34 - Local knowledge | The Department of Environment and Conservation review its practices and procedures in the undertaking of prescribed burns so as to fully utilise the skills available to it in a seamless way including but not limited to: · volunteer bushfire brigades, especially in regard to use as a source of local advice; and · staff of the Fire and Emergency Services Authority of Western Australia. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0683 | 13 - Mapping and data quality | All councils should, resources allowing, map the overland flow paths of their urban areas. |
REC210-0665 | 13 - Mapping and data quality | Councils should make their flood and overland flow maps and models available to applicants for development approvals, and to consultants engaged by applicants. |
REC210-0755 | 13 - Mapping and data quality | CS Energy should supplement physical monitoring of Splityard Creek Dam with visual monitoring by installing surveillance cameras or similar devices. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0664 | 13 - Mapping and data quality | Councils should, resources allowing, maintain flood maps and overland flow path maps for use in development assessment. For urban areas these maps should be based on hydraulic modelling; the model should be designed to allow it to be easily updated as new information (such as information about further development) becomes available. |
REC210-0746 | 13 - Mapping and data quality | Seqwater should consider engaging a technical writer to develop completely new manuals after the operational strategies for Wivenhoe, Somerset and North Pine dams are set by the Queensland Government. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1645 | 14 - Incident Mgt Teams | Ensure that adequate administrative personnel are available within the incident control structure to provide administrative and knowledge management support for incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
REC203-0293 | 34 - Local knowledge | Suitably experienced personnel with local knowledge should be connected to the Operations and Planning section in all Level 3 incidents in the vicinity of substantial settlements. |
REC203-0292 | 18 - Access to fire ground | There is a need for community education on how road-blocks and VCPs operate in the event of an emergency. |
REC203-0291 | 18 - Access to fire ground | Local knowledge should be accessed to inform the placement and operation of VCPs. |
REC203-0290 | 18 - Access to fire ground | VCPs are one of the instruments by which the Incident Controller manages the emergency. VCPs without communications cannot be fully effective in their role. Determine and implement an appropriate communications platform for emergency management |
REC203-0289 | 18 - Access to fire ground | There needs to be a better appreciation of the role of Vehicle Control Points (VCPs) and how they are managed in bushfire emergencies by all key agencies and the community |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0507 | 13 - Mapping and data quality | The Minister for Emergency Services, with advice from the Interagency Bushfire Management Committee Fuel Load Management sub-committee, report to Parliament by May 2012 on the estimated cost of developing one fuel load information system across all lands in Western Australia, no matter who manages it. This system’s information should be readily accessible and easily understood by all stakeholders, including the public. |
REC202-0509 | 36 - Volunteers | The Minister for Emergency Services and the Minister for Environment develop by December 2012 a Volunteer Charter that recognises the important work undertaken by the State’s volunteer bushfire and emergency services personnel. |
REC202-0508 | 36 - Volunteers | The Minister for Emergency Services and the Minister for Local Government review and report to Parliament by May 2012 on ways in which the State’s volunteer firefighters and rescue workers can be more effectively managed and valued. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0251 | 14 - Incident Mgt Teams | All responding crews and the incident command appointments should adopt a ‘Size Up‘ reporting format. |
REC201-0248 | 14 - Incident Mgt Teams | To provide Level 3 IC‘s (and FESA) with a level of confidence and to maintain currency across the pool of accredited IC‘s, regular exercising of IC‘s and Level 3 IMT‘s is required. |
REC201-0258 | 14 - Incident Mgt Teams | FESA should review the size of the existing pre-formed IMT to include additional Information and Planning officers and increased resourcing of scribes and management support for all Level 3 incidents. |
REC201-0255 | 14 - Incident Mgt Teams | FESA and DEC need to appoint accredited Level 3 IC‘s based on experience, competency and currency. |
REC201-0254 | 14 - Incident Mgt Teams | FESA should continue to develop with DEC and Local Government a number of rostered pre-formed IMT‘s available throughout the fire season, regardless of predicted weather. |
REC201-0253 | 14 - Incident Mgt Teams | Review the command function of the MROC for Level 3 incidents when the SOC is activated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0369 | 18 - Access to fire ground | The Western Australian Police and the Fire and Emergency Services Authority jointly examine the Traffic Management System developed in response to the 2009 Victorian bushfires and seek its adaptation to use in WA with additional attention to the access and egress by bona fide residents to areas that are evacuated. |
REC200-1706 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
REC200-0359 | 13 - Mapping and data quality | The State Government ensure that the continued development of the Fire and Emergency Service Authority’s Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-0358 | 13 - Mapping and data quality | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. The system should enable public access to allow members of the community to access information about the fuel load in a given locality. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0355 | 13 - Mapping and data quality | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-0352 | 13 - Mapping and data quality | The Fire and Emergency Services Authority and local governments ensure that the ability to: measure and map fuel loads maintain fuel load databases draw up prescriptions for, and oversee controlled burns are included as key competencies in any future recruitment of Chief Bushfire Control Officers and Community and Emergency Services Managers. |
REC200-0391 | 14 - Incident Mgt Teams | The Interagency Bushfire Management Committee develop a consistent program of education, training (including media), testing and review of Level 3 Incident Controllers. This should include provision for a formal review of the performance of individual Level 3 Incident Controllers after every incident. |
REC200-0366 | 14 - Incident Mgt Teams | The Fire and Emergency Services Authority and the Department of Environment and Conservation ensure that their Incident Controllers identify critical infrastructure as part of their initial assessment and preparation of Incident Action Plans when attending major incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
REC199-0422 | 36 - Volunteers | the state establish a process for volunteer community member accreditation to allow volunteers to provide flood information to the control agency during a flood event. This process should establish a base competency standard and provide appropriate emergency management and Australasian Inter-service Incident Management System training to accredited community volunteers. |
REC199-0429 | 13 - Mapping and data quality | the state take into account any outcomes from the Commonwealth Government’s flood mapping reviews in the continual development of the Victorian flood database and to incorporate into the database flood data currently held by Melbourne Water. |
REC199-0420 | 13 - Mapping and data quality | the state establish standards for flood mapping to ensure they are kept contemporary and meet the purposes of landuse risk planning and emergency response. In doing so, maps should extend where appropriate to include Probable Maximum Flood, over a range of Annual Exceedence Probability levels and be explicitly linked to a stream gauge. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0417 | 13 - Mapping and data quality | the state ensure that regional and local flood plans incorporate all available flood mapping and intelligence, including assessments of levees and flood consequence information. |
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0408 | 13 - Mapping and data quality | the state, in consultation with Bureau of Meteorology and Melbourne Water, take the necessary action to ensure that all flood warnings issued are linked to the geographical location of the gauge the data was derived from. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0238 | 34 - Local knowledge | Encourage ICCs to use local knowledge to review templates prior to release. |
REC196-0234 | 34 - Local knowledge | Ensure that local knowledge, local flavour and local language is used where possible in the development of all community bushfire warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0330 | 13 - Mapping and data quality | The Fire Services develop a program that enables all communication mediums, including social media and agency websites, to be monitored in real time to provide quality assurance for outgoing messages and additional sources of information and intelligence relating to an emergency |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0265 | 13 - Mapping and data quality | that QFRS undertake a thorough review of Firecom’s systems, including data integrity and dispatch procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0114 | 14 - Incident Mgt Teams | Higher level DEC guidance to Level 3 Incident Controllers could be improved by introducing a more explicit and robust process of questioning, engagement, monitoring and oversight of Level 3 Incident Controllers. |
REC183-0113 | 14 - Incident Mgt Teams | A summary Incident Action Plan could allow the Incident Controller to more quickly appreciate the situation and articulate a plan early in an incident. |
REC183-0112 | 14 - Incident Mgt Teams | DEC’s incident management capability could be enhanced by: – Appointing a Deputy Incident Controller for every Level 3 IMT. – Establishing a fast response “short” IMT capability for each Level 3 IMT. – Establish clear triggers to initiate sending in a “short” IMT to a fire. – Including FESA officers in pre-formed Level 3 IMT’s. – Establishing additional pre-formed Level 3 IMT’s with FESA. – Where appropriate, appointing a local Bush Fire Brigade officer as Deputy Operations Officer. |
REC183-0111 | 14 - Incident Mgt Teams | Conducting a pre-fire season exercise for each Pre-Formed Incident Management Team could be used to “re-accrediting” each team on an annual basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0131 | 14 - Incident Mgt Teams | FESA establishes a dedicated intelligence function in Incident Management Teams for major bushfires and ensure this function is appropriately supported with threat based tools and systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0208 | 13 - Mapping and data quality | The Department of Sustainability and Environment significantly upgrade its program of long-term data collection to monitor and model the effects of its prescribed burning programs and of bushfires on biodiversity in Victoria. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0193 | 13 - Mapping and data quality | The Department of Sustainability and Environment conduct biodiversity mapping identifying flora, fauna and any threatened species throughout Victoria and make the results publicly available. The format used should be compatible with that used for Bushfire-prone Area mapping. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0187 | 13 - Mapping and data quality | The State identify a central point of responsibility for and expertise in mapping bushfire risk to: ■ review urgently the mapping criteria at present used by the Country Fire Authority to map the Wildfire Management Overlay, to ensure that the mapping used to determine building and planning controls is based on the best available science and takes account of all relevant aspects of bushfire risk; ■ map and designate Bushfire-prone Areas for the purposes of planning and building controls, in consultation with municipal councils and fire agencies; ■ finalise the alignment of site-assessment methods for planning and building purposes, taking into account bushfire risk to human safety as well as to property. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0166 | 13 - Mapping and data quality | The Country Fire Authority and the Department of Sustainability and Environment improve mapping support in the following ways: ■ DSE providing mapping data free of charge to emergency response agencies; ■ greatly increasing the CFA’s ‘write’ access to FireMap for incident management team staff; ■ establishing a joint DSE–CFA training program to ensure that mapping officers in level 2 and 3 incident management teams are fully trained in using FireMap, including in producing fire prediction maps; ■ requiring before the 2010–11 fire season that FireMap be used for joint incidents. |
REC181-0169 | 18 - Access to fire ground | The Country Fire Authority provide to all CFA volunteers an identification card or similar to facilitate their passage through roadblocks established in accordance with the 2009 Guidelines for the Operation of Traffic Management Points during Wildfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0016 | 18 - Access to fire ground | Full briefings of traffic management personnel should be provided prior to dispatch to work areas – why road closed, what their authority level is, level of current risk etc |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0038 | 34 - Local knowledge | The ISU should be provided with a person with local knowledge at Level 3 incidents. |
REC172-0027 | 13 - Mapping and data quality | Add an ‘Aviation’ map to the standard set of incident maps. The standard for this map will need to be developed by subject matter experts from the Air Ops group. |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0014 | 18 - Access to fire ground | The Interagency Guidelines for Road closure needs to be reviewed to incorporate a mechanism to identify bone-fide local landholders to facilitate their movement in and out of cordoned areas in sympathy with the Stay and Defend requirements. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0013 | 18 - Access to fire ground | In preparing traffic management plans consideration should be given to which VCP’s are critical and need to be resourced with uniformed Police Officers and which VCP’s can be manned with civilian contractors. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0012 | 18 - Access to fire ground | Main Roads Western Australia, Police and LGA’s be encouraged via State emergency arrangements to establish a distributed cache of “hard” road barriers for deployment to major incidents |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0039 | 18 - Access to fire ground | Dedicated information packages should be made available to personnel operating Vehicle Control Points at the shift briefing. |
REC172-0011 | 18 - Access to fire ground | At Level 3 incidents the position of ‘Traffic Operations Officer’ –be established and filled by a WAPOL officer. A role description for this position is required and should be included in the “Guidelines for the Operations of Road Closures During Bushfires 2008”. This officer is to be supported by a suitably qualified officer from MRWA that is capable of developing Traffic Management Plans that address risk and are cognisant of considerations associated with road type, appropriate speed limitations, signage requirements, traffic volumes, detours for local traffic and heavy haulage etc. This role should report to the IC and have strong links to the Operations Section, Planning Section (particularly the Situation Unit) and the Information Unit. |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0017 | 18 - Access to fire ground | Information packs to be provided to road traffic personnel to assist with enquiries by public or provision to members of public and landholders who are defending homes/stock etc |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0067 | 14 - Incident Mgt Teams | That to the extent it has not already done so, DEC take action to ensure that in future cases relevant weather forecast information, particularly information as to significant wind changes, is promptly transmitted through the Incident Management Team and made available to persons with field operation responsibility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1799 | 14 - Incident Mgt Teams | That the South Australian Country Fire Service establish preplanned Level 2 Incident Management Teams in each Region for deployment to Level 2 incidents. |
REC153-1791 | 14 - Incident Mgt Teams | That the Minister for Emergency Services and the Chief Officer of the South Australian Country Fire Service consider the creation of a position within an Incident Management Team of a Landowner Liaison Officer the duties and responsibilities of whom is to establish contact with and liaise with the owner and/or occupiers of rural land on which a fire is situated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1960 | 13 - Mapping and data quality | That an appropriate geographic information systems capability be maintained to enable the production of fire-specific maps as the need arises and that personnel from the Emergency Services Agency and other agencies be trained in the operation of map production systems, so that 9maps can be modified to include fire-specific information as required |
REC126-2007 | 34 - Local knowledge | That the views and concerns expressed by the ACT Sustainable Rural Lands Group be taken into account when implementing the recommendations in this report |
REC126-1959 | 13 - Mapping and data quality | That the Emergency Services Agency introduce a program with land management agencies in the ACT to ensure that maps of all public and private land in the ACT are subjected to regular review and amendment as required. Maps of a scale sufficient to facilitate fire management operations should be available in printed form and maintained on an electronic database capable of modification to add relevant features during a firefighting operation |
REC126-1953 | 14 - Incident Mgt Teams | That appointments of personnel to functional positions within the incident management team be based solely on competence and experience and be made by the Chief of the ACT Rural Fire Service or, in the absence of that officer, the Deputy Chief of the ACT Rural Fire Service |
REC126-2008 | 34 - Local knowledge | That, if he is willing to participate, Mr John Lowe be made a member of the implementation taskforce to which I refer in recommendation 70 |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3784 | 34 - Local knowledge | The Committee recommends that the government provide authority to a single community representative body to authorise clearing of native vegetation for fire management. (The community representative body must incorporate the CFS, DEH, Native Vegetation Council and local council) |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3902 | 14 - Incident Mgt Teams | Government should: establish a State-wide command structure across volunteer Bush Fire Brigades for fighting major bushfires, to more effectively manage the coordination of personnel and resources |
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
REC104-2328 | 36 - Volunteers | That CFA, VICSES and other volunteer-based emergency service organisations develop proposals in support of the strategies for sustainable volunteerism, and that the State Government advocate these initiatives to the Federal Government. |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2191 | 13 - Mapping and data quality | That DSE and CFA, recognising that the Bureau of Meteorology does not routinely store all variables required to produce the calculations and indices necessary for research and planning into fire occurrence and behaviour, develop appropriate systems to ensure that such current and historical information is readily available and accessible. |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2190 | 13 - Mapping and data quality | That DSE institute additional routine data storage and analysis to supplement current climate records with at least daily 3 pm values for the Grassland and Forest Fire Danger Index, and Keetch-Byram Drought Index, for selected high quality stations representing a cross-section of environments throughout Victoria. |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2246 | 34 - Local knowledge | That DSE undertake community consultation on policies relating to roads and access tracks on public land, particularly in respect to fire management. |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2320 | 13 - Mapping and data quality | That Government acknowledge the importance of spatial information as a key element of planning, operations and program evaluation, and support the Geospatial Emergency Information Network as a means of ensuring integrated and co-ordinated information management on a whole-ofGovernment basis. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2233 | 34 - Local knowledge | That communities, public land managers, Water Authorities and Catchment Management Authorities jointly identify and implement local and environmentally sound solutions to improve the availability of water for firefighting through the Municipal Fire Management Planning process. |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2319 | 13 - Mapping and data quality | That all emergency service agencies, CFA and DSE in particular, give greater priority to information management – especially the collection, maintenance and quality control of base data sets necessary for planning, operations and program evaluation. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2202 | 13 - Mapping and data quality | That DSE and CFA map all unplanned fires greater than four hectares on public and private land in order to further develop an understanding of the risk to rural Victoria from unplanned fires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
REC098-2173 | 36 - Volunteers | The Committee suggests that registered volunteer fire fighters be exempt from paying Fire Levy tax to help offset some of the expense they incur during active duty. The exemption could be for a period of 12 months |
REC098-2156 | 36 - Volunteers | The Committee recommends that: |
REC098-2162 | 13 - Mapping and data quality | The Committee recommends that the 1:100,000 national mapping program be accelerated to achieve an average life of no greater than 10 years with priority given to those areas most susceptible to national disasters. |
REC098-2161 | 13 - Mapping and data quality | The Committee recommends that Emergency Management Australia be required to participate in the development and delivery of spatial information systems as part of a national approach to emergency planning and management data. The first priority in policy development and of systems should be related to bushfire hazards. |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2160 | 13 - Mapping and data quality | The Committee recommends that Geoscience Australia take responsibility, in conjunction with Emergency Management Australia, for developing a national spatial data policy to coordinate the development of data systems, the collection of data and the sharing of data between all the emergency response agencies across Australia, and that both agencies participate in the development and delivery of spatial information |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4157 | 18 - Access to fire ground | Local authorities and if necessary the Minister take active steps to enforce the removal of fire hazards from the vicinity of buildings in rural areas and that special attention be given to the removal of dead trees on the edges of pasture land and on firebreaks in timbered country. |
REC019-4136 | 34 - Local knowledge | The Bush Fires Board appoint a Regional Committee of Board members co-opt local members for each climatic region of the State to study the bush fire control problems of the region and advise the Board so that inter alia adequate attention may be given by the Board to co-ordinating the beginning and termination of the prohibited burning times in adjoining districts and to any advisable variations of these duties according to seasonal conditions each year. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |