REC327-4348 | 38 - Agency/Department Reporting | By December 2023, the Rural Fire Service should: report annually on fleet allocations to RFS Districts, and identify the ways in which fleet resources align with district-level fire risks |
REC327-4349 | 38 - Agency/Department Reporting | By December 2023, the Rural Fire Service should: develop performance measures to assess the performance and capabilities of the fleet in each RFS District by recording and publicly reporting on: fire response times and fire response outcomes; and, completions of fire hazard reduction works. |
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4339 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends that Queensland Fire and Emergency Services review and update the State Disaster Risk Report, including re-evaluating the risk of flooding by all types. Queensland Fire and Emergency Services should publish the updated State Disaster Risk Report by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4222 | 4 - Fire season preparation | The Inspector-General Emergency Management recommends the Department of Environment and Science undertake a review of campfire locations on K’gari, including all relevant signage on and off the island, maps and visitor permit information, to promote a consistent message about lighting campfires on K’gari. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4208 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) develops financial reporting to monitor fuel management costs and estimate future costs. |
REC321-4209 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) systemically documents and publicly reports reasons why it does not complete planned burns. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4204 | 4 - Fire season preparation | We recommend that DEWLP and CFA (in consultation with FRV) in partnership with councils, provide advice to government in line with the Safer Together: A new approach to reducing the risk of bushfire in Victoria policy on options to better resource the assessment of risk on private land, its treatment and activities to enforce compliance of land owners with risk-reduction treatments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4175 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – supported by other organisations with a legislated responsibility for fuel management – plan for and increase the application of non-burning fuel management treatments including mechanical means. The annual fuel management report should include the non-burn component of fuel management treatment, track annual change, and provide a comparison to the previous three years. |
REC318-4170 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that responder agencies and Emergency Management Victoria review preparedness arrangements to ensure procedural documentation (including plans), recruitment, briefings and training are completed before significant seasonal events are likely to occur. Seasonal preparedness should culminate in attestations of assurance to confirm that: |
REC318-4177 | 38 - Agency/Department Reporting | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in conjunction with legislated fuel management organisations – develop a common set of objectives, metrics and reporting requirements for fuel management that form part of a compulsory regime that enables the Victorian Government to report publicly on a holistic fuel management program. The reporting requirements should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4107 | 4 - Fire season preparation | Public land managers should clearly convey and make available to the public their fuel load management strategies, including the rationale behind them, as well as report annually on the implementation and outcomes of those strategies. |
REC317-4087 | 4 - Fire season preparation | State and territory governments, working with local governments and fire and emergency service agencies, should ensure that there are appropriate arrangements for roadside vegetation management that take into account, among other things: |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4108 | 4 - Fire season preparation | Australian, state and territory governments should review the assessment and approval processes relating to vegetation management, bushfire mitigation and hazard reduction to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3829 | 4 - Fire season preparation | That, in order to ensure outcomes-based roadside vegetation management to reduce roadside tree fall and grass ignitions in planning and preparing for bush fire, Transport for NSW, working with local government and NSW RFS, establish a consistent framework for roadside vegetation management that analyses road priority, utility, amenity, strategic value and risk. The framework should: |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3821 | 4 - Fire season preparation | That government agencies managing land (at all levels and through all agencies) be the best neighbours possible by considering their neighbours when undertaking activities related to bush fire preparation and having clear, two-way communication about these activities, with the aspiration that government landholders will be seen as highly desirable neighbours. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2512 | 38 - Agency/Department Reporting | Documenting results and recommendations from disaster recovery tests. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2416 | 4 - Fire season preparation | Establish a capacity to prescribe bushfire management arrangements for individual properties based on bushfire risk assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4012 | 38 - Agency/Department Reporting | Complete sets of daily-report books should be provided, and kept in the mine or office, to be overlooked by the Inspector during his periodical visits. |
REC002-4013 | 19 - Offences | Infringement of the regulations by either party should be followed by a summary form of justice, instituted before two Magistrates. |
REC002-4002 | 19 - Offences | Where safety-lamps are necessary - gas being present for (say) one month after being found in dangerous quantity - they should be securely locked by a man duly appointed, and tampering with them must be punishable by a simple and inexpensive process of law. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1337 | 19 - Offences | The Government should: |
REC299-1348 | 4 - Fire season preparation | In keeping with the Victorian Bushfires Royal Commission’s findings and recommendations, human life has primacy in bushfire‑related regulations and it is important that this is maintained in the implementation of bushfire management overlays and relevant vegetation removal exemptions should reflect the primacy of human life. |
REC299-1338 | 19 - Offences | The Government introduce an amendment to the Country Fire Authority Act 1958 or other instruments which imposes significant penalties and strengthens enforcement, including via infringement notices, for offences against Total Fire Ban requirements before the 2017‑2018 fire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2339 | 19 - Offences | I recommend that the Law, Crime and Community Safety Council develop a mechanism to ensure that all information on criminal history (including bail) that is relevant to the investigation and prosecution of criminal offences is readily accessible to police and prosecutors across all Australian jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-1436 | 4 - Fire season preparation | Continue the development and implementation of community level Bushfire Mitigation Plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC285-2525 | 38 - Agency/Department Reporting | The report recommends that Ambulance Tasmania outline what KPIs are measured and provide targets or benchmarks to define what is good or poor performance. |
REC285-2518 | 38 - Agency/Department Reporting | The report recommends that regional summary reports of clinical reviews be standardised to facilitate review and comparison across regions. |
REC285-2517 | 38 - Agency/Department Reporting | The report recommends that Ambulance Tasmania collects data to allow regular and meaningful comparison of clinical outcomes at the regional level, to better allocate resources and to rapidly identify problems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1386 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC280-1382 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC280-1381 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1153 | 4 - Fire season preparation | Planning for Access to Potentially Isolated Communities |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1498 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC261-1494 | 4 - Fire season preparation | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC261-1515 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service: |
REC261-1503 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC261-1502 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
REC261-1499 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1071 | 4 - Fire season preparation | The NPWS to consider developing a land management policy that requires hazard reduction around identified assets within the Park and the clearing of fire trials within the Park before the bush fire season commences. Consideration should also be given to developing additional fire trails in the Park, bearing in mind the lack of available fire trails to the south of the John Renshaw Parkway in the park. |
Rec-ID | Code | Recommendation |
---|---|---|
REC255-1579 | 38 - Agency/Department Reporting | The ANAO recommends that the Department of Defence take steps to strengthen the priority afforded by Defence units to meeting these reporting requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2566 | 38 - Agency/Department Reporting | Western Australia Health should require service providers to report more comprehensive performance data using additional cost and clinical indicators |
REC252-2565 | 38 - Agency/Department Reporting | Western Australia Health should include in contracts minimum standards for emergency and secondary ambulance services and effective mechanisms to monitor these |
REC252-2571 | 38 - Agency/Department Reporting | St John Ambulance should develop quantitative performance targets for community paramedics and report these to Western Australia Health |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0935 | 4 - Fire season preparation | That the State Emergency Management Committee includes in its planning, the development of contingency emergency management plans for areas of high risk due to local conditions. |
REC247-0937 | 19 - Offences | That the legislation and enforcement arrangements are reviewed to ensure there are suitable offences and penalties, investigation and enforcement capabilities, and a rigorous approach is taken to breaches of the law. |
REC247-0934 | 4 - Fire season preparation | That the State Fire Management Committee considers developing a structured, systemic and proactive bushfire hazard reduction program with municipal councils and Tasmania Fire Service; and advises the Government on any legislative or other changes required to implement such a program. |
REC247-0933 | 4 - Fire season preparation | That the Government considers whether a peak body should be established, with authority to effectively implement a bushfire mitigation plan. |
REC247-0931 | 4 - Fire season preparation | That a specific risk prevention and mitigation advisory body be established for the State Emergency Management Committee. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0847 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2649 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2653 | 38 - Agency/Department Reporting | That the Department of Health publicly reports a comprehensive suite of performance information, including: |
REC240-2652 | 38 - Agency/Department Reporting | That the Department of Health enhances management reporting processes over complaints by recording the number and nature of complaints, following up outstanding complaints formally and reporting complaints data to executive management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2674 | 38 - Agency/Department Reporting | That Queensland Corrective Service continues to develop its proposed recidivism index as a priority, including place and program based measures. |
REC239-2773 | 38 - Agency/Department Reporting | That should the Mobile Strategy in its current form be approved by government the CEO Portfolio Business and the Deputy Commissioner Operations: |
REC239-2673 | 38 - Agency/Department Reporting | That Queensland Corrective Service, in consultation with key partners in the criminal justice and social services sectors, develops specific performance indicators focused on efficiencies and customer/stakeholder outcomes across the criminal justice system. |
REC239-2772 | 38 - Agency/Department Reporting | That the roll-out of the mobile service program business case mentioned earlier |
REC239-2771 | 38 - Agency/Department Reporting | That the Queensland Police Service Commissioner addresses the situation regarding statistical reporting. The Commissioner, in collaboration with the Chief Executive Officer Portfolio Business and the Queensland Fire and Rescue Service Commissioner should also examine the opportunity to acquire the services of a qualified and experienced Chief Information Officer or Chief Digital Officer in line with other Queensland and Australian government agencies. |
REC239-2767 | 38 - Agency/Department Reporting | Recommendation: That the CEO Portfolio Business collaborates with the two portfolio Commissioners to: |
REC239-2684 | 38 - Agency/Department Reporting | The Chief Executive Officer Portfolio Business establishes a set of performance indicators to provide a transparent process for government to monitor its performance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2808 | 38 - Agency/Department Reporting | The committee recommends that in relation to mandatory and confidential reporting, the default position should be that no identifying details should be provided or disclosed. However, if there is a clear risk to safety then the ATSB, CASA and industry representatives should develop a process that contains appropriate checks and balances. |
REC236-2800 | 38 - Agency/Department Reporting | The committee recommends that where a safety action has not been completed before a report being issued that a recommendation should be made. If it has been completed the report should include details of the action, who was involved and how it was resolved. |
REC236-2799 | 38 - Agency/Department Reporting | The committee recommends that the ATSB prepare and release publicly a list of all its identified safety issues and the actions which are being taken or have been taken to address them. The ATSB should indicate its progress in monitoring the actions every 6 months and report every 12 months to Parliament. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2813 | 38 - Agency/Department Reporting | To strengthen its oversight of Queensland reconstruction progress, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce: |
REC234-2810 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Australian Government Reconstruction Inspectorate and the National Disaster Recovery Taskforce seek to maximise the benefits from their value for money review activities by obtaining more timely and comprehensive information on project progress and completion from the Queensland Reconstruction Authority, to enable the preliminary value for money assessments to be finalised based on the scope and cost of works that were actually delivered (rather than estimates). |
Rec-ID | Code | Recommendation |
---|---|---|
REC231-2830 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Department of Regional Australia, Local Government, Arts and Sport improve its monitoring of the delivery of the Natural Disaster Recovery Work Plans for Queensland and Victoria by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
REC228-1615 | 38 - Agency/Department Reporting | The Territory and Municipal Services Directorate, as part of its Bushfire Operations Plan monitoring and reporting, should assess and publicly report on cumulative progress against broader outcomes identified in the Regional Fire Management Plans and the Strategic Bushfire Management Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1853 | 38 - Agency/Department Reporting | The Ministers for Emergency Services, Environment and Police ensure their departments include in their annual reports the expenditure they have incurred on preparing their staff for critical incidents, and for managing their response to these incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC221-2860 | 19 - Offences | Housing should ensure it has sound systems, processes and controls in place that minimise the opportunity for fraud and gives it the best chance of detecting it by: |
REC221-2862 | 38 - Agency/Department Reporting | Housing should use risk based analysis of its tenant and property information, job order data and quality assurance results to better inform target setting for KPIs, job order controls, and the sampling used for completed work inspections before and after payment. This analysis should synthesise information from all sources and include a risk assessment of tenants and properties, as well as consideration of the various types of maintenance work being done (emergency, priority and routine, and planned maintenance). |
REC221-2861 | 38 - Agency/Department Reporting | Housing should further develop its Head Contractor key performance indicators to include quality, cost and tenant satisfaction. Currently performance reporting is focused entirely on timeliness indicators. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0681 | 19 - Offences | Councils and distributor-retailers should agree to protocols for the exchange of information about suspected illegal connections, the steps being taken to investigate them or the basis for concluding that no investigation is required, and the results of any investigations or enforcement actions. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1673 | 4 - Fire season preparation | That a trial be commissioned to assess the most effective means of road verge management, including regional variations, for future application across the Territory. |
REC209-1676 | 19 - Offences | Increase the emphasis on the issuing of infringement notices to reinforce the responsibilities of landholder’s in the management of bushfires in the Territory. |
REC209-1672 | 4 - Fire season preparation | Annual property inspections assessing access and fuel loads are conducted in all peri urban areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1912 | 38 - Agency/Department Reporting | The Board of Tourism WA should take action to ensure that it reviews the quality of Board papers that are submitted to it by the executive of Tourism WA. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0334 | 4 - Fire season preparation | The Fire Services Commissioner leads a task force to: a. identify legislation, policies and guidelines that impact on vegetation management and recommend necessary changes b. develop a set of risk-based standards for vegetation management with respect to strategic firebreaks and the assets being protected c. integrate maintenance standards across all areas of responsibility and tenure. |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1929 | 38 - Agency/Department Reporting | That the Queensland Reconstruction Authority consider extending the suite of internal performance indicators being used as the Authority matures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0212 | 4 - Fire season preparation | VicRoads implement a systematic statewide program of bushfire risk assessment for all roads for which it is responsible, to ensure conformity with the obligations in s. 43 of the Country Fire Authority Act 1958 and with the objectives expressed in the VicRoads 1985 Code of Practice. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0211 | 4 - Fire season preparation | The State and Commonwealth provide for municipal councils adequate guidance on resolving the competing tensions arising from the legislation affecting roadside clearing and, where necessary, amend environment protection legislation to facilitate annual bushfire-prevention activities by the appropriate agencies. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0210 | 4 - Fire season preparation | The State amend the exemptions in clause 52.17-6 of the Victoria Planning Provisions to ensure that the provisions allow for a broad range of roadside works capable of reducing fire risk and provide specifically for a new exemption where the purpose of the works is to reduce bushfire risk. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0192 | 4 - Fire season preparation | The Department of Sustainability and Environment develop and administer a collective offset solution for individual landholders who are permitted to remove native vegetation for the purpose of fire protection. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2977 | 38 - Agency/Department Reporting | The Department of Human Services should create evaluation guidelines for recovery operations, including links to planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3287 | 38 - Agency/Department Reporting | Licensees should be subject to an express obligation to inform regulators of problems which arise in the course of installing barriers, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. |
REC177-3290 | 38 - Agency/Department Reporting | The successful installation of every barrier should be the subject of written verification within and between licensees and rig operators; and should be the subject of explicit reporting to the relevant regulator(s). |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0140 | 4 - Fire season preparation | The Commonwealth seek agreement from the states and territories that would enable it to evaluate the adequacy of fuel reduction programs applied by public land management agencies in high bushfire risk areas, and audit their implementation against the program's stated objectives. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0105 | 19 - Offences | That the Department of the Attorney General, in consultation with FESA and Western Australia Police (WAPOL), consider options for legislative amendments to extend criminal liability to all damage, injury or death directly caused by arson. |
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
Rec-ID | Code | Recommendation |
---|---|---|
REC169-2997 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet and Victoria Police, in consultation with departments, should standardise reporting on training exercises conducted under Part 6 of the Act and the CIP framework to promote greater consistency and to enable better identification of lessons learned and continuous improvement. |
REC169-2989 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet should lead the development of a performance management framework for measuring, monitoring and reporting on the implementation of Part 6 of the Act and the CIP framework. The framework should include key indicators, targets and reporting arrangements for assessing the extent to which departments, agencies and industry have fulfilled their obligations, as well as measures for monitoring achievement of joint objectives. |
REC169-2998 | 38 - Agency/Department Reporting | Reports on the training exercises should be retained in an appropriately secured central repository so that consolidated results of the exercises can be drawn together effectively. |
Rec-ID | Code | Recommendation |
---|---|---|
REC163-1936 | 19 - Offences | The prescribed penalty notice penalty amount for section 66(7) of the Rural Fires Act 1997 be increased to $1,100. |
REC163-1935 | 19 - Offences | The prescribed penalty notice penalty amount for section 99(6) of the Rural Fires Act 1997 be increased to $1,100. |
REC163-1934 | 19 - Offences | The prescribed penalty notice penalty amount for section 100(2) of the Rural Fires Act 1997 be increased to $1,100. |
REC163-1941 | 19 - Offences | A working group be established to consider methods of preventing criminal firestarting. |
REC163-1940 | 19 - Offences | That legislation be prepared by the Criminal Law Review Division of the Attorney General’s Department allowing designated officers of the Rural Fire Service to apply for a warrant in certain circumstances. |
REC163-1937 | 19 - Offences | That the Attorney General’s Department’s Crime Prevention Division consider the causes of, and any solution to, the high number of juveniles involved in causing bushfires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC160-3045 | 38 - Agency/Department Reporting | The ANAO recommends that Centrelink: |
REC160-3044 | 38 - Agency/Department Reporting | The ANAO recommends that the Business Continuity, Crisis Management and Security Sub committee: |
REC160-3042 | 38 - Agency/Department Reporting | In order to identify key business processes and provide for the regular comparative assessment of Maximum Allowable Outage periods (MAOs), the ANAO recommends that Centrelink: |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3047 | 38 - Agency/Department Reporting | ACTAS should develop a comprehensive performance management framework that includes key performance indicators and targets aligned to its service delivery activities, to help inform management and stakeholders of its performance. |
REC159-3062 | 38 - Agency/Department Reporting | ACTAS should develop a set of standards to measure and monitor patient satisfaction, so that improvements to the service can be made, based on patient satisfaction information. |
REC159-3059 | 38 - Agency/Department Reporting | ACTAS should establish a clinical information database that: |
REC159-3055 | 38 - Agency/Department Reporting | ACTAS should implement systems to enable the accurate collection and measurement of non-emergency ambulance service bookings to facilitate monitoring of performance and the provision of accurate advice to Government. |
REC159-3050 | 38 - Agency/Department Reporting | ACTAS should log all emergency calls on CAD to document non-ambulance dispatch decisions, and to provide more complete data on demand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3429 | 38 - Agency/Department Reporting | That the nominated marine safety authority is required to ensure that incident notification and data recording requirements for Victorian commercial ports are consistent and adhered to. |
REC158-3428 | 38 - Agency/Department Reporting | That the nominated marine safety authority, in consultation with the Emergency Services Commissioner and senior emergency services personnel, is responsible for monitoring the implementation and auditing against appropriate performance standards, risk management guidelines and good practice guidelines. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3468 | 38 - Agency/Department Reporting | That the Department of Sustainability and Environment, Department of Primary Industries, Parks Victoria & VicForests separately cost, and report, annual expenditure on fuel reduction burning, ecological burning and regeneration burning in their Annual Reports. |
REC155-3467 | 38 - Agency/Department Reporting | The Department of Sustainability and Environment should report its performance against the increased prescribed burning target in its annual report, which should also include the following details: |
REC155-3478 | 38 - Agency/Department Reporting | That all information pertaining to current and planned prescribed burns be published more prominently on the Department of Sustainability and Environment’s website, with a single prominent link to this material on the website homepage. |
REC155-3477 | 38 - Agency/Department Reporting | That the details of any variation or amendment of a Fire Operations Plan, including: the carrying forward or postponement of burns within the three-year period covered by a Fire Operations Plan; the carry over, removal or rescheduling of burns between past, present and future Fire Operations Plans; and the alteration of burn boundaries (including alterations of less than 25 per cent); should appear on the Department of Sustainability and Environment’s website at the time of the change and be included in the Fire Operations Plan for the following year. |
REC155-3476 | 38 - Agency/Department Reporting | That finalised Fire Operations Plans be made publicly available in their entirety (with the exception of any private information) on the Department of Sustainability and Environment’s website and in hard-copy, and that this requirement be clearly stated in future Codes of Practice. This should include the “district burns list”, or its future equivalents, and a map which shows the corresponding burns for each Fire District. Each map should be provided in a format which can be downloaded directly from the Department’s website without the need for further data manipulation by the user. An identical hardcopy version of the map for each Fire District should be also be available to members of the public on request and free of charge. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1779 | 4 - Fire season preparation | That the South Australian Farmers’ Federation encourage its members and constituents to keep and maintain on rural land in proper working order machinery that is capable of removing, modifying or reducing cropping stubble at short notice in order to minimise or mitigate bushfire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3092 | 19 - Offences | Expiation fees be reviewed so as to be consistent with the seriousness of the offences. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3125 | 38 - Agency/Department Reporting | QFRS introduce a system to collate and analyse performance information for use in management reporting and to support effective decision making processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3138 | 38 - Agency/Department Reporting | The current KPI measures used by the Regulator and industry need to be reassessed and the performance indicators need to be related to the risk profiles of the industry. The industry needs to develop the indicators, which need to be agreed and measured by the industry in discussion with other stakeholders. The KPI's selected should be published in comparison with the worldwide offshore industry and with other industries. NOPSA should continue discussions with Australian Safety and Compensation Council (ASCC) with a view to adopting their goals. |
REC149-3142 | 19 - Offences | NOPSA should use encouragement as the primary tool of enforcing compliance provided willingness to improve is exhibited by the players. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3178 | 38 - Agency/Department Reporting | That the officer responsible for the importation of horses prepare a report to the Executive Director of AQIS that: |
REC148-3149 | 38 - Agency/Department Reporting | That there be established the position of Inspector General of Horse Importation, the duties of that position being: |
Rec-ID | Code | Recommendation |
---|---|---|
REC147-3186 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that, in order to assist management decision making and to inform Parliament about performance, Emergency Management Australia (EMA) develop and report appropriate measures for its key emergency management activities and outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3574 | 38 - Agency/Department Reporting | Formation of a subcommittee of the DHHS Tasmanian Medical Retrieval Services Committee to identify risk exposures, system problems and potential solutions. The subcommittee should review data, problem cases, system issues and generate a risk register. Meetings should occur at least quarterly. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3523 | 38 - Agency/Department Reporting | This Report should be considered for publication so that the insights, data, conclusions and recommendations are available within Queensland and other jurisdictions to assist with disaster management issues in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3625 | 38 - Agency/Department Reporting | We recommend that NSW Health continue with its good work and establish a performance management framework with targets and indicators to assess progress in preparing for infectious disease emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3601 | 38 - Agency/Department Reporting | That, as a matter of principle, the NSW Government provide public reports on the lessons learned from emergency exercises which it manages or in which it participates. If necessary, such reports should exclude material which might jeopardise security. |
REC128-3619 | 38 - Agency/Department Reporting | That the Department of Primary Industries should ensure the roles and capacities of Rural Lands Protection Boards and industry are effectively monitored to enable assessment of the effectiveness of animal health programs. |
REC128-3605 | 38 - Agency/Department Reporting | That the Department of Primary Industries make every effort to meet its targets for the TSE program and encourage public and private sector veterinarians across the State to submit samples. The Department should include reports on its performance against these targets in annual reports. |
REC128-3602 | 38 - Agency/Department Reporting | That the Department’s performance against tactical and strategic benchmarks be regularly reported in annual reports or animal and plant health emergency evaluation reports and compared to other jurisdictions where possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3783 | 4 - Fire season preparation | The Committee recommends that the government establish designated fire safety areas within native vegetation and at road intersections. |
REC122-3782 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities prepare a management plan that includes firebreaks and access tracks in the region, including the location of current breaks and access tracks and where breaks and tracks need to be established. |
REC122-3781 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities assess fire tracks and breaks to determine if firebreaks and access tracks need to be wider and/or native vegetation removed so that it does not impinge on firebreaks or tracks. |
REC122-3780 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities identify if: sufficient firebreaks and access track exist; they are strategically located; and they are being managed. |
REC122-3787 | 4 - Fire season preparation | The Committee recommends that the Native Vegetation Council provide landholders with assistance for applications for prescribed burning (via a guide, a proforma or staff). |
REC122-3785 | 4 - Fire season preparation | The Committee recommends that the government, via the CFS, coordinate the preparation and implementation of native vegetation management plans that incorporate management of fuel loads and includes a prescribed burning regime for the area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3722 | 38 - Agency/Department Reporting | The ATSB should deliver any report of any such rail accident which it investigates to the Board of any rail organisation involved in the accident, ITSRR and the Minister for Transport Services. |
REC121-3776 | 38 - Agency/Department Reporting | The Minister for Transport Services should retain, independently of ITSRR, safety auditors to provide a report to the Minister confirming or qualifying the contents of each such ITSRR quarterly report. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3712 | 38 - Agency/Department Reporting | RailCorp and ITSRR should co-operate with national programs for the collection, collation, trend analysis and dissemination of safety critical information. |
REC121-3775 | 38 - Agency/Department Reporting | The Minister for Transport Services must table in Parliament, each such quarterly report by ITSRR. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
REC121-3697 | 38 - Agency/Department Reporting | All train drivers’ defects reports should be entered by RailCorp into a computerised record and tracked to finalisation. |
REC121-3774 | 38 - Agency/Department Reporting | The ITSRR must provide a quarterly report to the Minister for Transport Services on the progress made by RailCorp in implementing these recommendations, including: |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3729 | 38 - Agency/Department Reporting | All reports of the Chief Investigator of OTSI should be delivered, upon completion and without being reviewed, to ITSRR and the Minister for Transport Services. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3723 | 38 - Agency/Department Reporting | All ATSB accident investigation reports should be made public. |
Rec-ID | Code | Recommendation |
---|---|---|
REC119-3648 | 38 - Agency/Department Reporting | It is recommended that providers supply data to the Board: |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3633 | 38 - Agency/Department Reporting | The ANAO recommends that, to provide better information to contribute to strategic assessments, decisions and reporting, the Attorney-General’s Department, with input and guidance from the Department of the Prime Minister and Cabinet: |
REC117-3641 | 38 - Agency/Department Reporting | The ANAO recommends that, to ensure the outcomes of evaluations are effectively used to enhance the national counter-terrorism arrangements, the Attorney-General’s Department and the Department of the Prime Minister and Cabinet take appropriate measures to ensure: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2194 | 38 - Agency/Department Reporting | That the success of current buffers in terms of assisting suppression operations be continually reviewed, evaluated and documented. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2193 | 38 - Agency/Department Reporting | That if ‘link’ burns continue to be used, then on-site weather sequences and fuel conditions marking successful (‘within explicit prescription’) and unsuccessful burns be documented. |
REC104-2290 | 38 - Agency/Department Reporting | That instances where demand for air support outstrips the supply of State Fleet Aircraft available are recorded. |
REC104-2289 | 38 - Agency/Department Reporting | That the joint agencies introduce a system of performance measures for reporting the effectiveness of aircraft in firefighting operations. |
REC104-2200 | 38 - Agency/Department Reporting | That DSE: |
REC104-2195 | 38 - Agency/Department Reporting | That the creation of buffers by chaining and then burning swaths of mallee be explicitly monitored for: |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2186 | 38 - Agency/Department Reporting | The Committee recommends that the Department of Transport and Regional Services review its record keeping practices to show the type of emergency for which assistance is provided through the Natural Disaster |
REC098-2136 | 4 - Fire season preparation | The Committee recommends that the Commonwealth through the National Heritage Trust assist the states and territories in the construction, maintenance and signage of fire trail networks. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3246 | 38 - Agency/Department Reporting | The Committee recommends that performance monitoring standards be established, reviewed and maintained through a common reporting system by the Minister for Police and Emergency Services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4169 | 4 - Fire season preparation | Mitigation and preparedness be enhanced and maintained for the future. Some co—ordinating mechanism or system be introduced at State Government level for this purpose. [Reference paragraphs: 114 to 128] |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4139 | 19 - Offences | Local authorities prosecute in all cases of deliberate breaches of the provisions of the Bush Fires Act and thay failing this the Bush Fires Board take appropriate action to initiate such prosecutions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3952 | 4 - Fire season preparation | It is recommended that the question of the future responsibility be made certain and that the body so made responsible keep the grounds of the hospital free from undergrowth and trees wherever their presence may be a possible source of future danger. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3950 | 4 - Fire season preparation | It is recommended that on days of abnormal danger loads of briquettes be not kept in the station yard. The real danger, which transcends in gravity the danger of time destruction of loads of briquettes, is that the prevailing wind or a change of wind might carry showers of burning embers to the town, which is but the width of a road away, and thereby cause material damage in the town. It is further recommended that the yard and its surroundings be kept clear of scrub and growth; and that special provision be made for quelling fire which may break out in the deposits of inflammable dust which lie in time yard. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3983 | 19 - Offences | To prohibit persons throwing lighted cigarettes, cigars and tobacco among any straw, stubble, grass or herbage during the months of September to March in any Bush Fire area, under a penalty not exceeding $10. |
REC013_3982 | 19 - Offences | To prohibit persons taking into a harvest field or through any grass or bush lands any motor, tractor, harvester, &c., which is not supplied with an approved fire extinguisher or without the exhaust being properly fitted and protected, under a penalty not exceeding $50. |
REC013_3978 | 4 - Fire season preparation | Where possible to build stone or brick fireplaces for the use of travellers, teamsters, and drovers on the camping areas that are mostly used and where there is a risk of fire. |
REC013_3976 | 4 - Fire season preparation | To burn camping areas at suitable water and camping reserves. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3998 | 19 - Offences | That a by-law be made forbidding, under a heavy penalty, any persons travelling in such trains to throw lighted tobacco, cigars, cigarettes, pipe ashes, matches, or other inflammable matter on the railway line or right-of-way, or in any part of a railway carriage except the receptacles duly provided for the purpose. |
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |