Rec-ID | Code | Recommendation |
---|---|---|
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4219 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends should a Queensland Government Action Plan be considered, clarity about the intent of the recommendations be sought from the Inspector-General Emergency Management to assist in informing this process. |
REC322-4220 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science monitor the progress of relevant improvement activities resulting from the K’gari (Fraser Island) Bushfire Review, through their respective lessons management programs. |
REC322-4240 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the next review of the Queensland State Disaster Management Plan examines and provides guidance in respect to the application of Queensland’s disaster management arrangements to support hazard specific events such as bushfire. |
REC322-4246 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the Interagency Protocol for Fire Management be reviewed by all relevant entities, including representatives of the Butchulla people, and be updated as a matter of priority. Entities responsible for the protocol should implement a process for regular review and evaluation of its effectiveness. This review process should be conducted after a major bushfire event, or to reflect any material change to applicable legislation and policy. It should also consider pre-arranged approvals and a range of agreed fiscal protocols between the agencies. |
REC322-4252 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services regularly review and evaluate the effectiveness of the Queensland Bushfire Plan with land managers and stakeholders, including disaster management groups. A review should occur in line with any material change to the Queensland State Disaster Management Plan, the Disaster Management Act 2003, the Prevention Preparedness Response and Recovery Guideline, or after major bushfire events, to ensure appropriate alignment and currency. |
REC322-4218 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends this report be returned to the IGEM to monitor, evaluate and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4216 | 13 - Mapping and data quality | We recommend that DELWP enhances bushfire modelling by: - exploring multiple bushfire modelling tools to lower the uncertainty and limitations associated with using a single modelling tool - applying more detailed fire-severity data - validating and updating fuel accumulation curves - establishing and regularly updating an archive of well-documented fire events and using this to systematically test it against a broad range of burning and fuel conditions - establishing and implementing processes to routinely review and update its underlying datasets. |
REC321-4207 | 25 - Inquiry, audit, lessons management and after action review | We recommend that DELWP reviews its target for the number of fuel hazard assessments conducted and ensures that this measure is evidence based, accurately reflects regional performance, and that the department monitors and reports on each region’s performance against it. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4182 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in partnership with agencies engaged in state, regional and incident control centres: |
REC318-4181 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in collaboration with the emergency management sector and as part of the emergency management planning reforms: |
REC318-4183 | 13 - Mapping and data quality | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in consultation with relevant agencies – develop a system to manage personnel and asset deployments to all tiers of incident management to meet the needs of the emergency and support the health and wellbeing of personnel. Where appropriate and within occupational health and safety requirements, this may include: |
REC318-4178 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in collaboration with the Country Fire Authority and local government – undertake a review of the current residual risk target to ensure that it remains contemporary in terms of its designated percentage value. The review should: |
REC318-4171 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the State review (and where necessary amend) legislation including but not limited to the Country Fire Authority Act 1958, Forest Act 1958 and Local Government Act 2020 to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4102 | 25 - Inquiry, audit, lessons management and after action review | Australian, state and territory governments should review Australian Medical Assistance Team capabilities and procedures and develop necessary training, exercising and other arrangements to build capacity for domestic deployments. |
REC317-4105 | 13 - Mapping and data quality | Australian, state and territory governments should agree to: |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
REC317-4074 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should review the content of the Defence Assistance to the Civil Community manual to ensure consistency of language and application with a revised COMDISPLAN. |
REC317-4068 | 13 - Mapping and data quality | Australian, state and territory governments should establish a national register of fire and emergency services personnel, equipment and aerial assets. |
REC317-4066 | 2 - Emergency powers | The Australian Government should make provision, in legislation, for a declaration of a state of national emergency. The declaration should include the following components: |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
REC317-4065 | 13 - Mapping and data quality | Australian, state and territory governments should continue to develop a greater capacity to collect and share standardised and comprehensive natural disaster impact data. |
REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
REC317-4060 | 13 - Mapping and data quality | Australian, state and territory governments should create common information platforms and share technologies to enable collaboration in the production, analysis, access, and exchange of information, data and knowledge about climate and disaster risks. |
REC317-4109 | 13 - Mapping and data quality | Australian, state and territory governments should develop consistent processes for the classification, recording and sharing of fuel load data. |
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4059 | 13 - Mapping and data quality | Australian, state and territory governments should prioritise the implementation of harmonised data governance and national data standards. |
REC317-4106 | 13 - Mapping and data quality | Australian, state and territory governments should ensure greater consistency and collaboration in the collation, storage, access and provision of data on the distribution and conservation status of Australian flora and fauna. |
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3858 | 25 - Inquiry, audit, lessons management and after action review | That, in order to improve cross-agency communication and coordination during bush fires, the NSW RFS review Fire Control Centres (FCCs) in areas that were heavily affected by fire. The results should be combined with the Emergency Operations Centre (EOC) Facilities Review to identify areas that would benefit from a purpose-built FCC, enabling co-location with the EOC. |
REC315-3812 | 25 - Inquiry, audit, lessons management and after action review | That Government commit to: |
REC315-3840 | 29 - Operational Health and Safety | That, in order to ensure firefighter sustenance is of sufficient volume and quality, the NSW RFS reviews food standards and procedures in consultation with volunteers. The review should include catering service standards, including food safety, as well as the viability of sourcing commercial contracts and providing 12-hour food packs to firefighters. |
REC315-3819 | 13 - Mapping and data quality | That, as part of the spatial technology acceleration program, Government support deployment of remote sensing and picture processing technologies to monitor and audit how well Asset Protection Zones and defendable space are being maintained, especially around towns. |
REC315-3798 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure recommendations accepted by the Government are implemented in a timely and transparent manner, Government establish a central accountability mechanism to track implementation of recommendations from bush fire-related reviews and inquiries and consider expanding this to other policy areas. |
REC315-3839 | 29 - Operational Health and Safety | That, to ensure firefighters can access mental health support through GPs, Government work with the Commonwealth Government to: |
REC315-3873 | 25 - Inquiry, audit, lessons management and after action review | That Resilience NSW review existing functional area arrangements to ensure they are closely aligned to agencies responsible for direct service delivery. |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3801 | 13 - Mapping and data quality | That, in order to improve capability to detect ignitions and monitor accurately all fire edge intensity and progression automatically across the State in near real time, Government establish a spatial technology acceleration program to maximise the information available from the various remote sensing technologies currently in use and to plan for inclusion of new remote sensing systems that can sense precisely and rapidly through heavy smoke, cloud, fog and dust. This will require work within the State and with partners nationally and internationally. |
REC315-3838 | 29 - Operational Health and Safety | That, in order to ensure all NSW RFS members can access the mental health support they need, the NSW RFS expands in-house mental health support for members. |
REC315-3860 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure the guiding principles and approval processes are contemporary, streamlined and more flexible, the NSW and Commonwealth Governments review the Defence Assistance to the Civil Community (DACC) arrangements. This review should include the circumstances in which the State can request Commonwealth assistance, and the level of information provided by the ADF to the State on available resources and capabilities. |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3800 | 13 - Mapping and data quality | That the NSW Government, along with other Australian governments, ask AFAC to establish a national bush fire database. This database would enable: |
REC315-3859 | 25 - Inquiry, audit, lessons management and after action review | That, in order to ensure State Emergency Operations Centre (SEOC) interoperability during all natural disasters, Resilience NSW review the current SEOC arrangements and location including responsibilities for ongoing resourcing and maintenance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
REC307-2437 | 13 - Mapping and data quality | The ability to share, analyse, interrogate and display information from disparate entities should be progressed as a matter of some urgency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2407 | 39 - Disaster Risk Management | Discontinue the automatic allocation of Fire Warden powers to Council and Committee members and substitute an option for members to be appointed as Fire Wardens. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
REC301-2385 | 25 - Inquiry, audit, lessons management and after action review | TFS should initiate a policy review (seeking support from government as appropriate) to clearly identify what body or agency is responsible for planning, carrying out and enforcing fuel management on private property at a township level. If current arrangements are unclear or ineffective, TFS should request government to consider making this a statutory responsibility of TFS and provide any additional funding required to support this function. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1344 | 25 - Inquiry, audit, lessons management and after action review | That a review of the cross‑tenure approach be undertaken to determine its effectiveness and to address issues that arise in fire prevention on private and public land. |
REC299-1343 | 25 - Inquiry, audit, lessons management and after action review | That the Government conduct a review of fire prevention |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1263 | 13 - Mapping and data quality | Subject to funding, that the Flood Warning Consultative Committee investigates the hydrological matters and advice received during this Review and detailed in this Report in Sections 4.1.9 and 4.1.11. |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1262 | 13 - Mapping and data quality | That the Flood Warning Consultative Committee considers the merits of delineating the Ouse River as a separate catchment from the Derwent River Basin. |
REC297-1254 | 13 - Mapping and data quality | That Government: |
REC297-1253 | 13 - Mapping and data quality | That agencies undertaking flood studies adopt a standardised approach, based on Australia Handbook 7, maintain public ownership of underlying data sets to support future modelling, and ensure open access to these studies. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1252 | 13 - Mapping and data quality | That SES uploads current flood studies and plans to the Common Operating Platform as a flood plan layer and that councils, subject to resolving licence restrictions, arrange to have appropriate access. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1265 | 13 - Mapping and data quality | That BoM and the Flood Warning Consultative Committee, in consultation with gauge owners, review flood gauges and develop a program to update data used to support hydrologic modelling. This should include reviewing gauge maintenance before and after floods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1249 | 25 - Inquiry, audit, lessons management and after action review | The Department of the Premier and Cabinet to conduct an independent review of the current arrangement for the management and distribution of the Emergency Services Levy. The review will have the specific purpose of: · seeking input from key entities including the Departments of Treasury, Finance, Fire and Emergency Services, Lands, and Parks and Wildlife, WA Local Government Association, and the Office of Bushfire Risk Management. · ensuring the arrangement has the flexibility and agility to deal with emerging bushfire risk priorities. · establishing a budget process that enables a shift in investment towards prevention, mitigation and building community resilience and capability. |
REC291-1233 | 25 - Inquiry, audit, lessons management and after action review | The State Government to explore options for streamlining the functions and the independence of the State Emergency Management Committee Secretariat and the Office of Bushfire Risk Management with a view to including an inspectorate function, and appointing a person who is dedicated to that role. The purpose is to provide assurance and reporting, and to inquire into, monitor and report transparently on emergency management standards, preparedness, capability, service delivery and investment performance outcomes. Within two years of the establishment of this arrangement the State Government to review and assess whether it is meeting the desired outcomes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1185 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies take steps at a national level to share learnings from the 2016 fires about the administration of interstate assistance and support the codifcation of the workings, structure and reporting lines of an Interstate and International Liaison Unit for future complex deployments within Australia and New Zealand. |
REC287-1188 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies commission a review into the efectiveness of aerial firefghting in the 2016 fires, in order to better understand and to document for future reference the cost-efectiveness of specifc fire suppression strategies and tactics in different vegetation types. The Review should include a comparative analysis of fire suppression options whether aerial or ground-based. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1396 | 25 - Inquiry, audit, lessons management and after action review | That the Minister for Police and Emergency Services review the communications technologies used by the NSW Rural Fire Service, Fire and Rescue NSW, the NSW National Parks and Wildlife Service and Forestry NSW during fire fighting operations, to ensure that systems are standardised and effective. Within this context, the potential value of satellite phone technology should be investigated. |
REC280-1388 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service: |
REC280-1380 | 13 - Mapping and data quality | That the NSW Rural Fire Service investigate mechanisms to enhance the predictability of megafires and how this information is communicated easily to the public. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1526 | 13 - Mapping and data quality | In accordance with recommendations of the BMT WBM report, the Banana Shire Council, SunWater, and the Bureau of Meteorology, under the stewardship of the Department of Natural Resources and Mines, jointly identify the requirements for a suitable gauge network for the Callide Valley to allow meaningful and timely flood warnings. The review should identify key stakeholders, examine potential funding sources and include a cost benefit analysis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1102 | 25 - Inquiry, audit, lessons management and after action review | SEMC Secretariat Community Emergency Management Officers should work with the Shire to document the Shire of Mundaring’s learnings from the Parkerville Stoneville Mt Helena fire with a view to sharing this with other local authorities particularly those facing similar situations in order to extend the range of tools available to assist local governments to understand their roles and responsibilities in future emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1076 | 13 - Mapping and data quality | The State equip itself to undertake rapid air quality monitoring in any location in Victoria, to: • collect all relevant data, including data on PM , carbon monoxide and ozone; and 2.5 • ensure this data is used to inform decision-making within 24 hours of the incident occurring. |
REC264-1087 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • practice and ensures that, by taking a risk management approach, it is suitable for fire prevention, mitigation and suppression in all parts of the Hazelwood mine; and review its ‘Mine Fire Service Policy and Code of Practice’ so that it refects industry best • work plan for the Hazelwood mine. incorporate the revised ‘Mine Fire Service Policy and Code of Practice’ into the approved |
REC264-1086 | 25 - Inquiry, audit, lessons management and after action review | GDF Suez: • consequences of fire in the worked out areas of the Hazelwood mine, and an assessment of the most effective fre protection for the exposed coal surfaces; conduct, assisted by an independent consultant, a risk assessment of the likelihood and • controls are in place to eliminate or reduce the risk of fre; and prepare an implementation plan that ensures the most effective and reasonably practicable • implement the plan |
REC264-1072 | 25 - Inquiry, audit, lessons management and after action review | The State empower and require the Auditor-General or another appropriate agency, to: • oversee the implementation of these recommendations and the commitments made by the State and GDF Suez during this Inquiry; and • report publicly every year for the next three years on the progress made in implementing recommendations and commitments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1508 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service review its procedures, systems and infrastructure for notifying community members of bush fires, both when a fire has broken out and as it proceeds, to ensure the provision of timely and adequate information. |
REC261-1505 | 25 - Inquiry, audit, lessons management and after action review | That the NSW Rural Fire Service: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1054 | 2 - Emergency powers | That the Rural Fire Service consider extending pre-emptive section 44 to whole of Castlereagh RFS/Warrumbungle Shire area. |
REC260-1050 | 13 - Mapping and data quality | Alternatively, I recommend that the RFS consider developing such capacity to deploy weather balloons itself, in conjunction with mobile weather stations, for this purpose. |
REC260-1049 | 13 - Mapping and data quality | That the Rural Fire Service consider proposing an arrangement with the Bureau of Meteorology to deploy weather balloons specifically for the purpose of assessing atmospheric instability during periods of severe to catastrophic fire danger in locations most likely to be severely affected, for example, areas in which a very high C-Haines index reading is registered and local fires have been identified. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1548 | 25 - Inquiry, audit, lessons management and after action review | The Regional Director-Defence Support-Northern NSW, make contact with Deputy Commissioner ~~~~~ Director of Operational Services Rural Fire Service, to arrange a headquarters driven bipartite review of the events of 16 October 2013 with a review to mitigation of future fire events generally, and with specific reference to: |
REC257-1546 | 25 - Inquiry, audit, lessons management and after action review | Defence undertake a review of its ability to respond to a fire within Marrangaroo Training Area, whether bushfire or structural. The underlying assumption should be that the only response available to fight a fire within Marrangaroo Training Area will be provided by Defence. Further, such response must occur while a fire is in its initial stages. A review must either acknowledge the risk of fire occurring in th future, or upgrade Defence's firefighting capability at Marrangaroo Training Area. |
REC257-1539 | 25 - Inquiry, audit, lessons management and after action review | Defence Security Authority conduct an investigation into the whereabouts of items of anaccounted explosive ordnance issued to Defence Explosive Ordnance Training School Exercise Marrangaroo. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0909 | 25 - Inquiry, audit, lessons management and after action review | That the plans for social recovery be reviewed, and plans and procedures are established ready for implementation. |
REC247-0951 | 25 - Inquiry, audit, lessons management and after action review | That an independent means of monitoring and reporting on the implementation of approved recommendations is established. |
REC247-0903 | 25 - Inquiry, audit, lessons management and after action review | That the role of Red Cross in emergency management plans and procedures for the activation of Red Cross be reviewed. |
REC247-0941 | 25 - Inquiry, audit, lessons management and after action review | That the Strategic Fuel Management Plan includes measurable targets and they are actively monitored and reported on to the community. |
REC247-0860 | 13 - Mapping and data quality | That Tasmania Fire Service establishes suitable systems and practices for recording fire management objectives and tactics. |
REC247-0857 | 2 - Emergency powers | That the Tasmania Emergency Management Plan enable, and all organisations with a role in emergency management activate, emergency plans at lower threshold events to practice their arrangements and achieve a ‘hot start’ in escalating events. |
REC247-0873 | 25 - Inquiry, audit, lessons management and after action review | If it is considered more information is required on action to suppress the fires in Dunalley and why fire operations did not continue, the Department of Justice should conduct an independent examination of this matter. |
REC247-0927 | 25 - Inquiry, audit, lessons management and after action review | That an accountability process be established for managing improvement in the emergency management arrangements, including annual State of Readiness Reports by relevant departments and agencies and on the overall emergency management arrangements. |
REC247-0851 | 13 - Mapping and data quality | That if a sound business case is developed, the Emergency Information Management and Sharing Project be supported. |
REC247-0856 | 2 - Emergency powers | That the Government reconsider the current position on emergency declarations in the Emergency Management Act 2006 and the Act is amended to provide: • a graduated scale of emergency declarations; • the ability to make a declaration when an emergency has occurred, is occurring or is about to occur; • the ability for the State Controller (or whatever the person in overall control of response and recovery operations is called) to make one or more declarations; • a declaration to enable access to all emergency powers. |
REC247-0926 | 25 - Inquiry, audit, lessons management and after action review | That membership of the State Emergency Management Committee, and other processes to link in appropriate agencies and organisations to emergency management, be included in the recommended review of the emergency management arrangements. |
REC247-0850 | 13 - Mapping and data quality | That police and other emergency service agencies establish and maintain effective recording systems for emergency operations. |
REC247-0923 | 25 - Inquiry, audit, lessons management and after action review | That a process be established for the timely implementation of approved recommendations from the 2009 Victorian Bushfires Royal Commission. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0788 | 25 - Inquiry, audit, lessons management and after action review | TFS seek to address the following outstanding items from the recommendations of the Victorian Bushfires Royal Commission. § 45 out of 53 Community Bushfire Response Plans for “at risk” communities have been finalized. The remaining eight should be completed as a priority action. § That TFS progress the development of Community Bushfire Mitigation Plans for the 53 at risk communities, possibly as an action for reactivated Fire Management Area Committees. § TFS, together with other ESOs and local government, should develop a common comprehensive approach to the option of planned evacuation from dangerous or potentially dangerous areas to safer areas and eventual return. § TFS should include factors for consideration for evacuation during a bushfire into their training doctrine for Incident Controllers. § The IAP Template and its application be reinforced as an important operational requirement for IMT’s during the 2013-14 pre-season briefing program. 10 § That TFS review their use of IRMS to ascertain if either its full potential is not being realized through a lack of operator training or it is in fact not providing the required functionality and there is a need to research an improved resource management system which enhances interoperability. § The TFS Publication: Guidelines for Development in Bushfire Prone Areas of Tasmania http://www.fire.tas.gov.au/userfiles/stuartp/file/Publications/BushDeve… s2012.pdf requires an update to reflect the provisions of Planning Directive #5 Bushfire-Prone Areas Code. |
REC246-0785 | 13 - Mapping and data quality | TFS should take steps to obtain cell transmission coverage maps for LBS-based EA messages and take note of the need for training of staff to ensure that messages are drafted carefully and appropriately so as to take cell transmission coverage into account. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1015 | 29 - Operational Health and Safety | That the First Officer or Brigade Officer retain the ability to seek assistance from any person whose services are available at the fire. Any person appointed to provide this assistance should be protected under relevant Workplace Health and Safety and Workcover legislation. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-1002 | 13 - Mapping and data quality | That the Rural Fire Service Queensland upgrades its subscription to technology for the Brigade Mapping Toolset to make it available to all Brigades who want it. |
REC241-0965 | 29 - Operational Health and Safety | That the number of Bushfire Safety Officer positions be, over time, increased so that one BSO operates out of each District office. |
REC241-0971 | 13 - Mapping and data quality | That the RFSQ central office undertake a review of Firecom procedures in relation to Rural Fire Service callouts. Each Rural Fire Service Queensland district office should also undertake a review of the Firecom data sets/callout information for their district to establish call out protocols are correct. |
REC241-1023 | 13 - Mapping and data quality | That Rural Fire Service Queensland develops a simple data collection system to record the activities of brigades. |
REC241-1022 | 29 - Operational Health and Safety | That Rural Fire Service Queensland in consultation with the Rural Fire Brigades Association Queensland will undertake a full review of the medical and health protocols to support the new Volunteer organisation. |
REC241-1003 | 13 - Mapping and data quality | The Manager of the Geographic Information Systems unit conduct an audit of the Firecom mapping system to ensure that rural Brigade and road addressing is up to date. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2827 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, conduct a comprehensive national audit and mapping exercise to: |
REC232-2815 | 25 - Inquiry, audit, lessons management and after action review | The Department of Health and Ageing review the existing evidence base to evaluate the cost-effectiveness of its policy to use heat scanners at ports of entry as a measure to mitigate the risk of infectious disease importation. |
REC232-2828 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, commission an independent review to assess the case for establishing a national centre for communicable disease control in Australia. The review should outline the role of a national centre and how it might be structured to build on and enhance existing systems. It should examine different models, considering a range of options for location, governance and staffing. The review should incorporate a cost-benefit analysis for each of the models presented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1620 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the Territory and Municipal Services Directorate, should review the Farm FireWise Program, including: |
REC228-1614 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the ACT Bushfire Council, should conduct a review of the ACT Bushfire Council against its recently developed terms of reference (July 2013) within two years. |
REC228-1609 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency should undertake audits to meet the requirements in the Strategic Bushfire Management Plan for the preparation, sharing and publication of annual progress reports. Annual progress reports should be made available to the ACT Bushfire Council. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0547 | 13 - Mapping and data quality | Fuel loads on private property need to be identified and included in understanding fire behaviour in determine the contribution they make to the burn risk assessment. |
REC226-0546 | 13 - Mapping and data quality | Maps prepared for prescribed burns should address the fuel type and burn history of the burn area as well as surrounding areas. Predicted rates of spread under prescribed and other conditions should recognise the complexity of coastal heathlands. |
REC226-0576 | 13 - Mapping and data quality | Better maps are required for urban/rural interface fires |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0540 | 25 - Inquiry, audit, lessons management and after action review | : In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
REC225-0535 | 2 - Emergency powers | DFES or DEC (depending on land tenure) is mandated to take over control of emergency incidents from Local Government once they have been declared Level 2 incidents. WESTPLAN BUSHFIRE and legislation to be amended accordingly. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1630 | 13 - Mapping and data quality | The Minister for Emergency Services ensure that a Statewide fuel load database that includes data from Western Power, the Department of Fire and Emergency Services and the Department of Environment and Conservation be established before the 2013-14 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0523 | 25 - Inquiry, audit, lessons management and after action review | The Government consider enacting legislation to facilitate the review of all future major incidents, including but not limited to fire, earthquake, storm and marine inundation, and the emergency response to them. |
REC223-0522 | 25 - Inquiry, audit, lessons management and after action review | The response operation to the Margaret River bushfire in November 2011 be the subject of a review with independent oversight. |
REC223-0516 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Conservation review its implementation of the findings of the Ferguson Review conducted in 2010. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0755 | 13 - Mapping and data quality | CS Energy should supplement physical monitoring of Splityard Creek Dam with visual monitoring by installing surveillance cameras or similar devices. |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0746 | 13 - Mapping and data quality | Seqwater should consider engaging a technical writer to develop completely new manuals after the operational strategies for Wivenhoe, Somerset and North Pine dams are set by the Queensland Government. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0683 | 13 - Mapping and data quality | All councils should, resources allowing, map the overland flow paths of their urban areas. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0665 | 13 - Mapping and data quality | Councils should make their flood and overland flow maps and models available to applicants for development approvals, and to consultants engaged by applicants. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0664 | 13 - Mapping and data quality | Councils should, resources allowing, maintain flood maps and overland flow path maps for use in development assessment. For urban areas these maps should be based on hydraulic modelling; the model should be designed to allow it to be easily updated as new information (such as information about further development) becomes available. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1667 | 39 - Disaster Risk Management | Prepare a formal proposal for the creation of pastoral/Indigenous Lands Fire Management Teams. |
REC209-1666 | 39 - Disaster Risk Management | Investigate the application and cost of the creation of District Coordination Officers to key high demand brigade districts. |
REC209-1643 | 25 - Inquiry, audit, lessons management and after action review | An evaluation be conducted into the integration of the appropriate elements of the South Australian Country Fire Service “Crimson” networking system into Bushfires NT ICT. |
REC209-1675 | 39 - Disaster Risk Management | PowerWater Corporation be consulted with the intention of establishing a Memorandum Of Understanding for the maintenance of PowerWater land for the purpose of coordinated fire reduction. |
REC209-1674 | 39 - Disaster Risk Management | That the concession holder of the rail corridor be approached to formalise a Memorandum of Understanding for the maintenance of the railway corridor for the purposes of fuel load reduction. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0497 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Local Government have urgent discussions with the Western Australian Local Government Association (WALGA) as to why they are not supporting the full Recommendations addressed to local government in the Keelty Report. The Minister ensure that by May 2012 WALGA and its member councils have the resources to fully implement theimplementation of the Recommendations. |
REC202-0495 | 25 - Inquiry, audit, lessons management and after action review | At the conclusion to the 2011-12 bushfire season, the Minister for Emergency Services institute a thorough review of the operations of FESA, the Police and DEC in protecting the State from bushfires and other natural disasters, with a primary focus on: · staffing levels; · equipment levels and coordination; and · training needs. The Minister report to Parliament by June 2012 on any changes that need to be made to the current departmental structures to optimise the State’s preparedness for the 2012-13 bushfire season. |
REC202-0507 | 13 - Mapping and data quality | The Minister for Emergency Services, with advice from the Interagency Bushfire Management Committee Fuel Load Management sub-committee, report to Parliament by May 2012 on the estimated cost of developing one fuel load information system across all lands in Western Australia, no matter who manages it. This system’s information should be readily accessible and easily understood by all stakeholders, including the public. |
REC202-0493 | 25 - Inquiry, audit, lessons management and after action review | The Minister for Emergency Services report to Parliament every six months on the progress made in completing all of the outstanding Recommendations of the Keelty Report. |
REC202-0501 | 2 - Emergency powers | The Minister for Emergency Services amend section 50 of the Emergency Management Act 2005 by June 2012 to allow the State Emergency Coordinator, as well as a hazard management agency, to make an emergency situation declaration. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0257 | 29 - Operational Health and Safety | FESA needs to place greater priority on the appointment of Safety Advisors to Level 3 incidents as is reflected in WESTPLAN Bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0352 | 13 - Mapping and data quality | The Fire and Emergency Services Authority and local governments ensure that the ability to: measure and map fuel loads maintain fuel load databases draw up prescriptions for, and oversee controlled burns are included as key competencies in any future recruitment of Chief Bushfire Control Officers and Community and Emergency Services Managers. |
REC200-0384 | 25 - Inquiry, audit, lessons management and after action review | Emergency Management Western Australia develop mechanisms to calculate the estimated total cost of a fire to the community. |
REC200-1701 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. |
REC200-0361 | 25 - Inquiry, audit, lessons management and after action review | The Fire and Emergency Services Authority convene a facilitated debriefing session between the families who remained behind to protect their properties, and the incident controllers. This session should include open discussion and explain the decisions of all parties – including how the incident controllers determined priorities, and why residents chose not follow their advice to evacuate. The learning outcomes should be promulgated across all agencies and incorporated in future level 3 incident controller training programs. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-0359 | 13 - Mapping and data quality | The State Government ensure that the continued development of the Fire and Emergency Service Authority’s Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-1705 | 29 - Operational Health and Safety | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA‟s own policy of „Use of Private Vehicles in Fires‟ |
REC200-0358 | 13 - Mapping and data quality | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. The system should enable public access to allow members of the community to access information about the fuel load in a given locality. |
REC200-0355 | 13 - Mapping and data quality | The Western Australian Local Government Association explore the feasibility of local governments utilising aerial and satellite imagery to monitor firebreaks and fuel loads on private property. |
REC200-0392 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry’s Recommendations in two years. |
REC200-0381 | 2 - Emergency powers | The State Government amend section 50 of the Emergency Management Act 2005 to allow the Chair of the State Emergency Coordination Group to declare an emergency situation. |
REC200-1732 | 25 - Inquiry, audit, lessons management and after action review | The State Government review implementation of the Special Inquiry's recommendations in two years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0417 | 13 - Mapping and data quality | the state ensure that regional and local flood plans incorporate all available flood mapping and intelligence, including assessments of levees and flood consequence information. |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0408 | 13 - Mapping and data quality | the state, in consultation with Bureau of Meteorology and Melbourne Water, take the necessary action to ensure that all flood warnings issued are linked to the geographical location of the gauge the data was derived from. |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0429 | 13 - Mapping and data quality | the state take into account any outcomes from the Commonwealth Government’s flood mapping reviews in the continual development of the Victorian flood database and to incorporate into the database flood data currently held by Melbourne Water. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0444 | 2 - Emergency powers | the state, as a matter of urgency, develop a multi-agency Incident Control Team capability to be readily available for statewide deployment to establish incident control or to relieve functioning control structures. |
REC199-0420 | 13 - Mapping and data quality | the state establish standards for flood mapping to ensure they are kept contemporary and meet the purposes of landuse risk planning and emergency response. In doing so, maps should extend where appropriate to include Probable Maximum Flood, over a range of Annual Exceedence Probability levels and be explicitly linked to a stream gauge. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0330 | 13 - Mapping and data quality | The Fire Services develop a program that enables all communication mediums, including social media and agency websites, to be monitored in real time to provide quality assurance for outgoing messages and additional sources of information and intelligence relating to an emergency |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0265 | 13 - Mapping and data quality | that QFRS undertake a thorough review of Firecom’s systems, including data integrity and dispatch procedures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0133 | 29 - Operational Health and Safety | FESA reviews its approach to safety and safety culture. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0204 | 2 - Emergency powers | The State amend the Country Fire Authority Act 1958 to enable the Chief Officer to delegate the power to issue fire prevention notices. |
REC181-0166 | 13 - Mapping and data quality | The Country Fire Authority and the Department of Sustainability and Environment improve mapping support in the following ways: ■ DSE providing mapping data free of charge to emergency response agencies; ■ greatly increasing the CFA’s ‘write’ access to FireMap for incident management team staff; ■ establishing a joint DSE–CFA training program to ensure that mapping officers in level 2 and 3 incident management teams are fully trained in using FireMap, including in producing fire prediction maps; ■ requiring before the 2010–11 fire season that FireMap be used for joint incidents. |
REC181-0217 | 25 - Inquiry, audit, lessons management and after action review | The State consider the development of legislation for the conduct of inquiries in Victoria —in particular, the conduct of royal commissions. |
REC181-0208 | 13 - Mapping and data quality | The Department of Sustainability and Environment significantly upgrade its program of long-term data collection to monitor and model the effects of its prescribed burning programs and of bushfires on biodiversity in Victoria. |
REC181-0216 | 25 - Inquiry, audit, lessons management and after action review | The State appoint an independent monitor or the Victorian Auditor-General to assess progress with implementing the Commission’s recommendations and report to the Parliament and the people of Victoria by 31 July 2012. |
REC181-0176 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment adopt the title ‘safety officer’ (as opposed to ‘safety adviser’) and require without exception that a safety officer be appointed to every level 3 incident management team. |
REC181-0193 | 13 - Mapping and data quality | The Department of Sustainability and Environment conduct biodiversity mapping identifying flora, fauna and any threatened species throughout Victoria and make the results publicly available. The format used should be compatible with that used for Bushfire-prone Area mapping. |
REC181-0174 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures for investigating safety incidents and ‘near-misses’ to ensure that all dangerous incidents, including back-burns, are fully investigated and that all relevant people are consulted and informed of the results. |
REC181-0187 | 13 - Mapping and data quality | The State identify a central point of responsibility for and expertise in mapping bushfire risk to: ■ review urgently the mapping criteria at present used by the Country Fire Authority to map the Wildfire Management Overlay, to ensure that the mapping used to determine building and planning controls is based on the best available science and takes account of all relevant aspects of bushfire risk; ■ map and designate Bushfire-prone Areas for the purposes of planning and building controls, in consultation with municipal councils and fire agencies; ■ finalise the alignment of site-assessment methods for planning and building purposes, taking into account bushfire risk to human safety as well as to property. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3345 | 2 - Emergency powers | NOPSA’s prohibition powers should be extended such that a prohibition notice can be issued where a NOPSA Occupational Health and Safety Inspector believes, on reasonable grounds, that an activity is occurring or may occur at a facility involving an immediate threat to the health or safety of a person. |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0030 | 29 - Operational Health and Safety | A strategically located Staging Area serviced with check in/out personnel should be considered as early as possible at incidents involving an extended attack. |
REC172-0027 | 13 - Mapping and data quality | Add an ‘Aviation’ map to the standard set of incident maps. The standard for this map will need to be developed by subject matter experts from the Air Ops group. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
Rec-ID | Code | Recommendation |
---|---|---|
REC163-1939 | 2 - Emergency powers | That the Rural Fires Act 1997 be amended to provide to designated Fire Investigation Officers of the Rural Fire Service the power to enter any land upon which a bushfire has occurred for the purposes of investigation for a period of up to 24 hours after a fire has been declared out. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3466 | 25 - Inquiry, audit, lessons management and after action review | A comprehensive review of the effectiveness of the increased prescribed burning target in meeting ecological and bushfire suppression needs should be conducted every three years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC154-3463 | 13 - Mapping and data quality | Biosecurity Victoria should enhance controls to provide assurance regarding data integrity. This process should include: |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3122 | 29 - Operational Health and Safety | QFRS implement a system to monitor the condition and safety of brigade buildings and equipment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3175 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to review, at least once every two years, the operating procedures to ensure that they adequately identify and manage the risk of entry and spread of equine influenza associated with the importation of horses into Australia. The outcome of each such review should be the subject of a written report and recommendations to the person responsible for the importation of horses and the Executive Director of AQIS. A determination should then be made as to whether any, and if so what, changes should be made to the operating procedures. |
REC148-3170 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to conduct within six months, an inspection and review of the process of horse importation from the time horses arrive in Australia until the completion of their post-arrival quarantine in order to: |
REC148-3167 | 25 - Inquiry, audit, lessons management and after action review | That the facilities at Eastern Creek and Spotswood Quarantine Stations be reviewed by AQIS in consultation with experts in biosecurity and interested parties including state and territory governments, import agents, veterinarians, farriers, operators of private quarantine stations, and representatives of horse owners, horse racing organisations and equestrian organisations. There should in any event be constructed without delay, an adequate supply of hygienic, modern showering facilities and places of entry and exit to the stations and the horse sections of them that can be supervised and monitored continually. There should also be provided at those stations as soon as is practicable suitable means of electronic surveillance, including closed-circuit television; a secure place to store chemicals, drugs, instruments and equipment for use by people attending the quarantined horses, and a set of horse stalls and yards separate from the main stalls and yards to enable isolation of horses suffering from contagious or infectious diseases. These reviews should also consider the desirability of separate areas in quarantine stations to hold horses forming part of a single quarantine intake but that have been imported from different regions or have undergone pre-export quarantine in different places. The reviews should be carried out without delay, and the two quarantine stations should be upgraded in accordance with the recommendations of the reviews. |
REC148-3154 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia or another qualified body to inspect and review the activities and events that occur from the time horses enter pre-export quarantine until the time they arrive at an airport in Australia, in order to identify any biosecurity risks and recommend any necessary changes to import conditions or other requirements. This inspection and review shall be performed without delay for each country or region from which horses are imported to Australia, and it should take account of my other recommendations and comments in this report. |
REC148-3182 | 25 - Inquiry, audit, lessons management and after action review | That Biosecurity Australia review that formal import risk analysis at least once every two years to take into account any relevant developments in scientific knowledge—specifically testing methods, vaccines, vaccination procedures and other matters that affect biosecurity. Reports on the reviews should be provided to the officer responsible for the importation of horses and should contain recommendations for any necessary changes to policies for importation. |
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3598 | 25 - Inquiry, audit, lessons management and after action review | That the Department of Primary Industries incorporates reviews of plans and operating procedures as a result of emergency incidents and exercises and ensures that there is adequate commitment from all participants in the review process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-2011 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the recommendations of the seven reviews of the Emergency Services Bureau carried out before the McLeod inquiry and ensure implementation of any of those recommendations that remain relevant but have not been implemented |
REC126-1960 | 13 - Mapping and data quality | That an appropriate geographic information systems capability be maintained to enable the production of fire-specific maps as the need arises and that personnel from the Emergency Services Agency and other agencies be trained in the operation of map production systems, so that 9maps can be modified to include fire-specific information as required |
REC126-2010 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the extent to which the recommendations in the McLeod report have been implemented in order to ensure implementation of those not yet implemented |
REC126-1959 | 13 - Mapping and data quality | That the Emergency Services Agency introduce a program with land management agencies in the ACT to ensure that maps of all public and private land in the ACT are subjected to regular review and amendment as required. Maps of a scale sufficient to facilitate fire management operations should be available in printed form and maintained on an electronic database capable of modification to add relevant features during a firefighting operation |
REC126-1952 | 25 - Inquiry, audit, lessons management and after action review | That regular periodic reviews be undertaken of changes made to the operational and management arrangements for dealing with wildfires and other emergencies in the ACT, to ensure that those arrangements continue to comply with the Australian Inter-Agency Incident Management System Incident Control System |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1947 | 25 - Inquiry, audit, lessons management and after action review | That the ACT Government commission a review of coroners’ jurisdiction in order to determine whether that jurisdiction ought to be limited or expanded and, if so, to what extend |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3926 | 13 - Mapping and data quality | That DPI upgrades the Crop Health Services diagnostic database so that it alerts PSB and PIRVIC to the receipt of samples from nearby areas with similar symptoms and can be linked to other PIRVIC diagnostic databases. |
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
REC112-3925 | 13 - Mapping and data quality | That DPI establishes a system to ensure the security of all samples at all times, but particularly during their handling and transport. |
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2281 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA work cooperatively to review the management and application of bulldozers in fire suppression operations to ensure that they are used effectively, appropriately and are adequately supervised. |
REC104-2191 | 13 - Mapping and data quality | That DSE and CFA, recognising that the Bureau of Meteorology does not routinely store all variables required to produce the calculations and indices necessary for research and planning into fire occurrence and behaviour, develop appropriate systems to ensure that such current and historical information is readily available and accessible. |
REC104-2332 | 25 - Inquiry, audit, lessons management and after action review | That the Review of emergency operations centres by the Departments of Premier and Cabinet and Treasury and Finance and the Office of the Emergency Services Commissioner: |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
REC104-2270 | 29 - Operational Health and Safety | That DSE and CFA continue to stress firefighter safety as their highest priority for incident managers and fire ground supervisors |
REC104-2277 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review methods of gathering and processing fire information to ensure all methods are pursued to greatest effect. |
REC104-2190 | 13 - Mapping and data quality | That DSE institute additional routine data storage and analysis to supplement current climate records with at least daily 3 pm values for the Grassland and Forest Fire Danger Index, and Keetch-Byram Drought Index, for selected high quality stations representing a cross-section of environments throughout Victoria. |
REC104-2293 | 25 - Inquiry, audit, lessons management and after action review | That aviation contractors be required to submit a copy of their annual independent regulatory compliance audit prepared for Civil Aviation Safety Authority to the State Aircraft Unit. |
REC104-2228 | 25 - Inquiry, audit, lessons management and after action review | That the Government identifies an appropriate body, or bodies, to undertake the audit of the Municipal Fire Management Plans. |
REC104-2292 | 25 - Inquiry, audit, lessons management and after action review | That a systematic performance audit of State Aircraft Fleet contractors be conducted jointly by agency and SAU personnel. |
REC104-2320 | 13 - Mapping and data quality | That Government acknowledge the importance of spatial information as a key element of planning, operations and program evaluation, and support the Geospatial Emergency Information Network as a means of ensuring integrated and co-ordinated information management on a whole-ofGovernment basis. |
REC104-2197 | 25 - Inquiry, audit, lessons management and after action review | That a review of the fuel management zones be implemented with a view to reducing the number of zones so as to focus clearly on (i) asset protection (especially at the Public/Private land interface), and (ii) ecological burns. |
REC104-2220 | 2 - Emergency powers | That CFA should not be given the power to direct Forest Industry Brigades to engage in fire prevention and suppression activities off their land and that decision should remain the responsibility of the plantation company. |
REC104-2284 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review the management of personnel deployed ensuring that: |
REC104-2319 | 13 - Mapping and data quality | That all emergency service agencies, CFA and DSE in particular, give greater priority to information management – especially the collection, maintenance and quality control of base data sets necessary for planning, operations and program evaluation. |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2282 | 25 - Inquiry, audit, lessons management and after action review | That quality control or performance assessments are routinely completed post fire season, to ensure that contractors who have not performed to an agreed standard are not re-engaged for the consequential rehabilitation works. |
REC104-2202 | 13 - Mapping and data quality | That DSE and CFA map all unplanned fires greater than four hectares on public and private land in order to further develop an understanding of the risk to rural Victoria from unplanned fires. |
REC104-2333 | 25 - Inquiry, audit, lessons management and after action review | That in doing so, this Review must consult with the agencies mentioned above, and others such as VICSES and the Departments of Human Services and Primary Industries. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2177 | 39 - Disaster Risk Management | The Committee recommends that state and territory governments be required to regularly perform risk assessments to the land within their jurisdictions to ensure that bushfire prone areas are accurately identified |
REC098-2151 | 29 - Operational Health and Safety | The Committee recommends that the Commonwealth Attorney-General engage the Commonwealth, states and territories in a review of occupational health and safety legislation as it affects the proper and effective functioning of bush fire services. |
REC098-2162 | 13 - Mapping and data quality | The Committee recommends that the 1:100,000 national mapping program be accelerated to achieve an average life of no greater than 10 years with priority given to those areas most susceptible to national disasters. |
REC098-2161 | 13 - Mapping and data quality | The Committee recommends that Emergency Management Australia be required to participate in the development and delivery of spatial information systems as part of a national approach to emergency planning and management data. The first priority in policy development and of systems should be related to bushfire hazards. |
REC098-2155 | 25 - Inquiry, audit, lessons management and after action review | The Committee recommends that Emergency Management Australia initiate a process involving Australasian Fire Authorities Council and the Australian Assembly of Volunteer Fire Brigades Association to review |
REC098-2160 | 13 - Mapping and data quality | The Committee recommends that Geoscience Australia take responsibility, in conjunction with Emergency Management Australia, for developing a national spatial data policy to coordinate the development of data systems, the collection of data and the sharing of data between all the emergency response agencies across Australia, and that both agencies participate in the development and delivery of spatial information |
REC098-2168 | 2 - Emergency powers | The Committee recommends that the Commonwealth investigate, and where necessary, require the urgent enhancement of the provision of emergency power and telecommunications services for the purpose of |