REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4339 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends that Queensland Fire and Emergency Services review and update the State Disaster Risk Report, including re-evaluating the risk of flooding by all types. Queensland Fire and Emergency Services should publish the updated State Disaster Risk Report by 1 November 2023. |
REC325-4328 | 9 - Community education | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services establish a community education program by 1 November 2023 that complements the implementation of the Australian Warning System. An evaluation process should be incorporated into the program to determine effectiveness. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
REC325-4330 | 38 - Agency/Department Reporting | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services review the Queensland Emergency Alert Manual – M.1.174 in its entirety by 1 November 2023. The manual should specifically address the authorising environment, legislative obligations and the capability and complexities of the Emergency Alert system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4221 | 9 - Community education | The Inspector-General Emergency Management recommends Department of Environment and Science implement an awareness and engagement strategy aimed at deterring the lighting of campfires to encourage behavioural change amongst visitors. |
REC322-4242 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends the Department of Environment and Science review the format and delivery of Queensland Parks and Wildlife Service annual fire refresher training to include a scenario-based exercise. |
REC322-4223 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the Department of Environment and Science implements the proposed treatments for fire identified in the Queensland Parks and Wildlife Service K’gari Compliance Strategy. |
REC322-4248 | 5 - Hazard reduction burns | The Inspector-General Emergency Management recommends the prescribed burn program for K’gari be developed by the Department of Environment and Science, in collaboration with the Locality Specific Fire Management Group and the Butchulla people, based on the principles of the National Position on Prescribed Burning. This program should incorporate a process for monitoring and evaluation of outcomes and integration of evolving fire management practices. |
REC322-4249 | 9 - Community education | The Inspector-General Emergency Management recommends all Area Fire Management Groups in Queensland make their Bushfire Risk Mitigation Plans, bushfire risk mapping and methodology easily understood and available to the community. All public plans should be dated to ensure currency and incorporate mechanisms for community feedback. |
REC322-4224 | 17 - Assets and technology | The Inspector-General Emergency Management recommends the Department of Environment and Science examines the utilisation of technology, in consultation with relevant stakeholders, to improve the collection of visitor numbers and movement data. This could include, for example, expanding the use of Automatic Number Plate Recognition technology to K’gari and examining the suitability of mobile phone check-in applications. |
REC322-4251 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services facilitate an annual state level exercise of the Queensland Bushfire Plan that includes all relevant stakeholders and land managers. The exercise should focus on roles, responsibilities, interagency arrangements and handover arrangements between agencies and land managers. |
REC322-4226 | 9 - Community education | The Inspector-General Emergency Management recommends the Bushfire Risk Mitigation Plan for Fraser Coast Area Fire Management Group include a schedule of planned engagement activities, or a community engagement sub-plan outlining these activities, and be publicly available. |
REC322-4222 | 4 - Fire season preparation | The Inspector-General Emergency Management recommends the Department of Environment and Science undertake a review of campfire locations on K’gari, including all relevant signage on and off the island, maps and visitor permit information, to promote a consistent message about lighting campfires on K’gari. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4214 | 1 - Land-use and building regs | We recommend that DELWP determines which elements of different regional planning approaches are the most effective and implements these across the state. |
REC321-4204 | 4 - Fire season preparation | We recommend that DEWLP and CFA (in consultation with FRV) in partnership with councils, provide advice to government in line with the Safer Together: A new approach to reducing the risk of bushfire in Victoria policy on options to better resource the assessment of risk on private land, its treatment and activities to enforce compliance of land owners with risk-reduction treatments. |
REC321-4215 | 1 - Land-use and building regs | We recommend that DELWP develops more holistic bushfire-management planning that focuses on the best mix of risk treatments rather than planned burning alone. |
REC321-4208 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) develops financial reporting to monitor fuel management costs and estimate future costs. |
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4217 | 5 - Hazard reduction burns | We recommend that DELWP in partnership with Country Fire Authority and Fire Rescue Victoria develops, implements and publicly reports on a holistic suite of performance metrics to demonstrate: - the impact that planned burning has on public and private land on bushfire risk - the impact that planned burning has on public and private land on ecosystem resilience - the impact that non-burn fuel management activities have on public and private land on bushfire risk - the impact that its activities at local and regional levels have on bushfire risk - the cost-effectiveness of its fuel management activities on public and private land. |
REC321-4209 | 38 - Agency/Department Reporting | We recommend that DEWLP and CFA (in consultation with FRV) systemically documents and publicly reports reasons why it does not complete planned burns. |
REC321-4211 | 1 - Land-use and building regs | We recommend that CFA (in consultation with FRV) improves planning on private land to ensure risk assessments and plans are conducted consistently across public and private land to address state-wide bushfire risk based on where and how they can most effectively reduce risk. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
REC321-4203 | 9 - Community education | We recommend that DELWP provides advice to government, in consultation with Country Fire Authority, Fire Rescue Victoria and councils, on options to improve owner and occupier awareness of and accountability for bushfire management overlay planning controls (see Section 4.3). |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4193 | 9 - Community education | Public communications: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department, coordinate ongoing education campaigns to increase public awareness of community roles and responsibilities during periods of emergency relief and recovery. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4186 | 9 - Community education | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in collaboration with the emergency management sector – develops and implements processes to ensure greater dissemination and improved understanding of information for all Victorians, and visitors to Victoria in an emergency event. This should consider but not be exclusive to individuals who: |
REC318-4177 | 38 - Agency/Department Reporting | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in conjunction with legislated fuel management organisations – develop a common set of objectives, metrics and reporting requirements for fuel management that form part of a compulsory regime that enables the Victorian Government to report publicly on a holistic fuel management program. The reporting requirements should: |
REC318-4175 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – supported by other organisations with a legislated responsibility for fuel management – plan for and increase the application of non-burning fuel management treatments including mechanical means. The annual fuel management report should include the non-burn component of fuel management treatment, track annual change, and provide a comparison to the previous three years. |
REC318-4174 | 9 - Community education | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – with support from all legislated fuel management organisations for public and private land – lead a community engagement process to improve the Victorian community’s understanding of: |
REC318-4170 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that responder agencies and Emergency Management Victoria review preparedness arrangements to ensure procedural documentation (including plans), recruitment, briefings and training are completed before significant seasonal events are likely to occur. Seasonal preparedness should culminate in attestations of assurance to confirm that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4028 | 41 - Emergency Management exercises | Any changes to the ECC structure and role be exercised both within ESA and across a WHoG exercise and testing program. |
REC316-4040 | 41 - Emergency Management exercises | The PICC be exercised in conjunction with any and all Emergency Plan exercises to test and refine strengthened arrangements. |
REC316-4023 | 41 - Emergency Management exercises | An opportunity to exercise and test the formation and functioning of a Management Executive through desktop and/or limited scenario-based exercises be provided. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
REC316-4032 | 41 - Emergency Management exercises | Concurrent and/or non–standard emergencies such as energy supply impacts be included in future exercise programs. |
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4041 | 9 - Community education | The ESA Community Education and Engagement program be adapted to include an expanded role for RFS volunteers and include a wider set of stakeholders who are more vulnerable to the impact of bushfire. A plan would require wider involvement across stakeholder organisations such as Directorates who have existing relationships with vulnerable groups. |
Rec-ID | Code | Recommendation |
---|---|---|
REC312-2506 | 9 - Community education | The chairpersons of disaster management groups within the Townsville Disaster District, supported by the Queensland Police Service, Queensland Fire and Emergency Services and the Queensland Reconstruction Authority develop a district action plan based on the capability enhancement strategy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2502 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, Sunwater develop and deliver a sustainable long-term communication strategy on the community safety issues and |
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2501 | 9 - Community education | To enable the community to make informed choices about disaster management, and act on them, a joint Sunwater/council community engagement program be conducted to prepare the community downstream from Paradise Dam for events in the 2019/2020 storm and cyclone season, including the possibility of a Paradise Dam failure. |
REC311-2489 | 9 - Community education | To enable the community to have a shared understanding of risks and enhance community engagement, flood scenarios in Emergency Action Plans be published, and in a format that can be utilised by public mapping systems. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2500 | 9 - Community education | To enable the community to make informed choices about disaster management, Bundaberg and North Burnett regional councils and Sunwater undertake a community-informed audible test of the Paradise Dam siren. |
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2503 | 9 - Community education | To enable the casual/itinerant worker and tourism sector, including those who do not have English as a first language, to make informed choices about disaster management, community engagement and communication strategies about Paradise Dam and floods in the Burnett river system be tailored to this sector. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2482 | 9 - Community education | Practical guidance on what community-led recovery means, and how it can be best implemented should be captured and shared with all who have responsibility for it. This should be done to help individuals and communities to take the lead in recovery and so that community-led recovery becomes the norm following disasters and other events. |
REC310-2487 | 39 - Disaster Risk Management | The state’s arrangements for disaster management, including recovery, are articulated in the Disaster Management Act (2003), the Queensland Reconstruction Authority Act (2011), the State Disaster Management Plan and the Queensland Recovery Plan. To enable state-level arrangements to better support community-led recovery and to improve Queensland’s recovery governance |
REC310-2486 | 9 - Community education | State arrangements for on-the-ground support to recovering local governments should be in line with Queensland’s disaster management arrangements, and ensure the best balance between local relationships, suitable capability and sufficient capacity. |
REC310-2483 | 9 - Community education | 09-Community education/engagement/preparedness |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
REC309-2467 | 9 - Community education | Further work be undertaken to develop effective public flood risk messaging and community education materials that are easy to understand and tested with the community to ensure flood risk is understood. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
REC308-2466 | 41 - Emergency Management exercises | Exercising should focus on vertical integration and include all levels of the system. A strategic program of exercises should be developed and implemented. |
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
REC308-2461 | 24 - Govt responsibility | A strategy should be developed between the key tourism and transport operators, and local and state government. It should address the arrival of visitors and tourists after a disaster, and should ensure that their arrival matches communities’ needs for recovery and return to normal business. The Department of Tourism, Major Events, Small Business and the Commonwealth Games should monitor its implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2433 | 24 - Govt responsibility | To make planned burning and land clearing easier to understand and implement for landholders, a single point of contact for all bushfire mitigation inquiries and permits should be established. |
REC307-2448 | 9 - Community education | Targeted education about the short- and long-term effects of chemical suppressants should reach those likely to be exposed to them before aerial chemical suppressants are used in Queensland again. |
REC307-2431 | 9 - Community education | Area Fire Management Groups should share seasonal risk information with local groups and actively and appropriately contribute to disaster management planning. |
REC307-2447 | 9 - Community education | Clear public messaging regarding risks (if any) from the use of suppressants, including to 'organic' producers, should be developed and socialised before the next fire season and be readily available for dissemination when needed. |
REC307-2430 | 9 - Community education | All Area Fire Management Groups should adopt and be guided by a good neighbour policy. |
REC307-2444 | 41 - Emergency Management exercises | All disaster management groups should run an exercise that has full involvement of a hazard-specific primary agency in the next 12 months and regularly thereafter. |
REC307-2429 | 9 - Community education | A good neighbour policy such as that of the Queensland Parks and Wildlife Service, setting out clear expectations, be developed to guide all landholders. |
REC307-2439 | 9 - Community education | Education on bushfires should include information about: |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1348 | 4 - Fire season preparation | In keeping with the Victorian Bushfires Royal Commission’s findings and recommendations, human life has primacy in bushfire‑related regulations and it is important that this is maintained in the implementation of bushfire management overlays and relevant vegetation removal exemptions should reflect the primacy of human life. |
REC299-1347 | 5 - Hazard reduction burns | In order to manage a reduced time window available to undertake the current types of planned burns, alternative methods, including the indigenous mosaic ‘cool’ burns, should be examined and trialled as they may extend the period in which planned burns can be undertaken while reducing overall risk and fuel loads. |
REC299-1341 | 5 - Hazard reduction burns | That in conjunction with a risk‑based approach, a minimum hectare target is also maintained that can be measured and compared. This minimum target should not be below the 5% target established by the Victorian Bushfire Royal Commission. |
Rec-ID | Code | Recommendation |
---|---|---|
REC294-1364 | 24 - Govt responsibility | The Chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services recommend implementing the Mackay District Improvement Strategy (refer to page 53 of the inquiry). |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1248 | 24 - Govt responsibility | The State Emergency Management Committee to establish a State Bushfire Coordinating Committee as a sub-committee of SEMC. The State Bushfire Coordinating Committee will be chaired by the Director of the Office of Bushfire Risk Management and will have the primary responsibility to: · develop a State Bushfire Management Policy and a set of long term bushfire risk management objectives; · provide a forum for key bushfire risk management stakeholder agencies; · advise the SEMC on matters pertaining to bushfire, in particular, to report against the investment in, and achievement of the bushfire risk management objectives; · provide advice and support to the proposed Chief Officer of the Rural Fire Service on bushfire risk management matters; and · report to SEMC and to the community on bushfire risk management matters on at least an annual basis. |
REC291-1237 | 5 - Hazard reduction burns | The Department of Fire and Emergency Services, utilising the Office of Bushfire Risk Management, to develop a simplified and fast track hazard reduction burn (and other fuel mitigation techniques) planning and approval process to ensure the timely conduct of township and asset protection burns by Bush Fire Brigades and individual property owners. The process is to be agile and adaptable for the range of stakeholders which may participate in low risk, small scale, low complexity burn planning and approvals. |
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
REC291-1235 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to continue emphasis on landscape hazard reduction burning with the annual objective of treating 140,000 hectares per annum in Land Management Zone C. In combination with Recommendation 2 (above) the strategic objective will be that a fuel age of less than six years will be maintained across 45% of the landscape on State Forest, National Parks and other Parks and Wildlife managed lands in the South West and Perth Hills. This will address the current backlog (created from under achievements of the recent two decades of burn programs) by the end of the 2020-2021 burning season (i.e. within the next 5 years). |
REC291-1234 | 5 - Hazard reduction burns | The Department of Parks and Wildlife to plan for the highest priority hazard reduction burning effort around settlements and critical assets in the South West and Perth Hills. The annual objective is to treat a total of 60,000 hectares of priority hazard reduction per annum, comprising 20,000 hectares per annum of Land Management Zone A and 40,000 hectares per year of Land Management Zone B. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
REC290-1219 | 17 - Assets and technology | Live resource tracking system that can be used by all response agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1416 | 24 - Govt responsibility | A state-wide strategy, including a common definition, is developed for identifying and engaging vulnerable people in emergencies. |
REC272-1420 | 24 - Govt responsibility | The Department of Housing and Public Works should consider preparing an annual communique to asset owners of, and local governments with access to public cyclone shelters, outlining the maintenance and certification process and pre-season status. |
REC272-1418 | 24 - Govt responsibility | A state-wide engagement strategy is coordinated to ensure community messaging is consistent across all levels of Queensland’s disaster management arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1524 | 9 - Community education | SunWater provide downstream residents with easily understood information regarding operation of the dam, and the impacts that various outflows may have for them, in accordance with mapping prepared for the Emergency Action Plan. This information should be complementary to any information from the Banana Shire Council. |
REC271-1523 | 9 - Community education | Banana Shire Council coordinates the development of a strategy to significantly enhance public education regarding local disaster management arrangements within the Banana Shire, focusing on key identified risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC270-1147 | 9 - Community education | improves engagement with communities to prepare for and respond to bushfires by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC268-1432 | 9 - Community education | Queensland Fire and Emergency Services should consider developing and implementing mechanisms, such as face-to-face forums, for disaster management practitioners to share knowledge, contemporary research findings and document good practice about warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1117 | 17 - Assets and technology | Automatic Vehicle Location technology should be adopted to enable a better appreciation of the deployment and location of appliances at an incident, in order to increase situational awareness |
REC265-1116 | 17 - Assets and technology | Procedures should be established to monitor the use of heavy plant during a bushfire incident, including the tasking of support appliances. Procedures should provide for the appointment of a dedicated Machinery Supervisor as prescribed within the Australasian Interservice Incident Management System. |
REC265-1112 | 17 - Assets and technology | Radio infrastructure in the Perth Hills should be reviewed to assess whether it is practicable for radio and/or mobile phone coverage to be improved to achieve better coverage across the area. |
REC265-1123 | 17 - Assets and technology | Every effort should be made to enhance the ability of communications personnel to cope with fast moving and time critical fire events by providing and maintaining: ongoing extensive communications training; advanced vehicle capability for clear communication within areas of radio coverage dead spots; ability to receive Air intelligence live streaming; map production facilities; deployment of multiple Incident Control Vehicles when required; all Incident Control Vehicles with access to DFES Information Technology Systems. |
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
REC265-1120 | 9 - Community education | DFES should prepare a Standard Operating Procedure for the conduct of community meetings, and have available the appropriate audio visual and other equipment, to ensure that such meetings are able to fulfil their function in providing information and direction |
REC265-1101 | 9 - Community education | Staff and consultants skilled in community engagement practice should be specifically included in bushfire risk management planning and preparedness building programs undertaken by State agencies and/or local government. |
REC265-1119 | 24 - Govt responsibility | Relevant policies and Westplans should be amended to require that full consultation occurs between the Controlling Agency and the Department for Child Protection and Family Support regarding the location of the evacuation centre(s) in a bushfire incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
REC264-1083 | 9 - Community education | The State, led by Emergency Management Victoria, develop a community engagement model for emergency management to ensure all State agencies and local governments engage with communities and already identifed trusted networks as an integral component of emergency management planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1582 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
Rec-ID | Code | Recommendation |
---|---|---|
REC252-2571 | 38 - Agency/Department Reporting | St John Ambulance should develop quantitative performance targets for community paramedics and report these to Western Australia Health |
REC252-2566 | 38 - Agency/Department Reporting | Western Australia Health should require service providers to report more comprehensive performance data using additional cost and clinical indicators |
REC252-2565 | 38 - Agency/Department Reporting | Western Australia Health should include in contracts minimum standards for emergency and secondary ambulance services and effective mechanisms to monitor these |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-1012 | 17 - Assets and technology | Use of private aircraft to be at the discretion of District Inspector or Incident Control and reimbursement of fuel to be authorised accordingly. |
REC241-0979 | 24 - Govt responsibility | That the Queensland Government liaise with the Federal Government with a view to securing incentives for employers that recognise loss of income and employee time for emergency operations. |
REC241-1028 | 17 - Assets and technology | That vehicles are fit for the purpose and the Brigade locality for which they are intended. A group of two volunteers, in conjunction with the Rural Fire Brigades Association Queensland, should be charged with reviewing current models and providing Recommendations on vehicle suitability. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-1009 | 17 - Assets and technology | That the reflective livery on Rural Fire Service Queensland staff vehicles be kept to a minimum of a light bar and affixed Rural Fire Service Queensland logo. These vehicles are to be appropriate to the task and location. |
REC241-0973 | 17 - Assets and technology | That all land on which rural fire brigade sheds are located be re-evaluated to formalise enforceable lease agreements. |
REC241-1027 | 17 - Assets and technology | That Rural Fire Service Queensland, in consultation with Primary Producer Brigade volunteers, redesign and reconfigure slip-on units to bring the total cost below the level required for asset registration. The redesign should allow for the foam system to be optional. |
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-1042 | 17 - Assets and technology | The issue of red and blue lights for RFSQ and SES vehicles be further pursued by the Department of Community Safety |
REC241-1001 | 24 - Govt responsibility | That the extent of forest and plantation fuel load fire risk in South East Queensland requires a designated government resources fire team to manage this risk and proactively conduct fuel mitigation burning; and provide a wildfire response to government land. |
REC241-0970 | 17 - Assets and technology | That RFSQ retain responsibility for Air Operations and re-evaluate avenues for cost recovery when aircraft are used by other agencies. The coordination of incendiary tasking to support mitigation should sit with the RFSQ in coordination with other agencies |
REC241-1026 | 17 - Assets and technology | That the Rural Fire Service Queensland catalogue accurately reflects the range of equipment available. |
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-1039 | 17 - Assets and technology | That the State Government supply and logistics for Personal Protective Equipment and other equipment be urgently reviewed with a focus on timely and cost effective delivery to volunteer members. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1025 | 17 - Assets and technology | That an ‘Options Paper’ be developed by District Inspectors on the suitability and supply of PPE and equipment to volunteers for their district. |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
REC241-1036 | 17 - Assets and technology | That each District Inspector prepare a report on vehicles required over the next ten years based on current age of fleet. |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-0954 | 24 - Govt responsibility | That a Ministerial Advisory Council be established to inform the Minister of matters relating to Rural Fire Service and SES volunteers. |
REC241-1024 | 17 - Assets and technology | That the Rural Fire Service Queensland revoke its current 20 year maximum age policy on volunteer Brigade vehicles to allow Brigades wanting to retain their vehicle to do so, providing the vehicle has an annual mechanical certificate. A 30 year maximum age policy for vehicles will replace the 20 year policy. |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
REC241-1029 | 17 - Assets and technology | That a policy be developed around the ownership, insurance and safe use and operation of All Terrain Vehicle 4WD vehicles by brigades for fire fighting purposes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC240-2653 | 38 - Agency/Department Reporting | That the Department of Health publicly reports a comprehensive suite of performance information, including: |
REC240-2652 | 38 - Agency/Department Reporting | That the Department of Health enhances management reporting processes over complaints by recording the number and nature of complaints, following up outstanding complaints formally and reporting complaints data to executive management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2674 | 38 - Agency/Department Reporting | That Queensland Corrective Service continues to develop its proposed recidivism index as a priority, including place and program based measures. |
REC239-2687 | 24 - Govt responsibility | That funding, staffing and responsibility associated with administration of the NDRP be transferred from Emergency Management Queensland to the Department of Local Government, Community Recovery and Resilience. |
REC239-2767 | 38 - Agency/Department Reporting | Recommendation: That the CEO Portfolio Business collaborates with the two portfolio Commissioners to: |
REC239-2701 | 24 - Govt responsibility | That the Inspector General Emergency Management provide continuing advice to Government on the level of interoperability in disaster management arrangements, as well as the level of interoperability being achieved within the new portfolio. |
REC239-2772 | 38 - Agency/Department Reporting | That the roll-out of the mobile service program business case mentioned earlier |
REC239-2659 | 9 - Community education | That Queensland Health continues to recognise and foster the important contributions of Local Ambulance Committees to supporting effective community focused ambulance services across the State. |
REC239-2721 | 24 - Govt responsibility | That the Chief Executive Officer Portfolio Business collaborate with the two portfolio Commissioners to: |
REC239-2782 | 24 - Govt responsibility | That transparency of the Ministerial direction be achieved through publishing and monitoring for effectiveness. |
REC239-2673 | 38 - Agency/Department Reporting | That Queensland Corrective Service, in consultation with key partners in the criminal justice and social services sectors, develops specific performance indicators focused on efficiencies and customer/stakeholder outcomes across the criminal justice system. |
REC239-2686 | 24 - Govt responsibility | That primacy of control should rest with the State Disaster Coordinator. This position should, by default, be the Deputy Commissioner, Regional Operations, Queensland Police Service. |
REC239-2759 | 24 - Govt responsibility | That the new Chief Executive Officer Portfolio Business be accountable for delivering the reformed Communications Centre arrangement by the 2017–18 financial year in time for the Commonwealth Games of 2018. |
REC239-2700 | 24 - Govt responsibility | That the position of Inspector General Emergency Management (in addition to some of the responsibilities of the chief executive officer under the current Disaster Management Act 2003) will: |
REC239-2771 | 38 - Agency/Department Reporting | That the Queensland Police Service Commissioner addresses the situation regarding statistical reporting. The Commissioner, in collaboration with the Chief Executive Officer Portfolio Business and the Queensland Fire and Rescue Service Commissioner should also examine the opportunity to acquire the services of a qualified and experienced Chief Information Officer or Chief Digital Officer in line with other Queensland and Australian government agencies. |
REC239-2657 | 24 - Govt responsibility | That negotiation takes place between Queensland Health and the Queensland Ambulance Service to determine the broad governance requirements of any such arrangements. |
REC239-2712 | 24 - Govt responsibility | That Emergency Management Queensland be integrated with the current Queensland Fire and Rescue to become the Department of Fire and Emergency Services. |
REC239-2778 | 17 - Assets and technology | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative ANPR models should form part of the design architecture considerations. |
REC239-2664 | 17 - Assets and technology | That Queensland Corrective Service should increase the use of technology as an alternative to court appearances and ensure the provision of appropriate number and level of facilities under its control. |
REC239-2685 | 24 - Govt responsibility | That primacy of control for disaster operations remains with the Queensland Police Service and be reinforced. |
REC239-2699 | 24 - Govt responsibility | That the Minister establish a public sector office to be headed by an Inspector General of Emergency Management. The Inspector General of Emergency Management will be responsible for most of the functions listed under part 16A of the current Disaster Management Act 2003. |
REC239-2770 | 9 - Community education | That the efficiency review of the Queensland Police Service develop options for better management of community expectations and divesting the organisation of historical practices. |
REC239-2655 | 24 - Govt responsibility | That the Queensland Ambulance Service is transferred to Queensland Health by a machinery-of-Government change as soon as is practicable and that the Commissioner report directly to the Director General Queensland Health. |
REC239-2711 | 39 - Disaster Risk Management | That the Inspector General Emergency Management be empowered to provide an assurance to Government that the disaster management system is both appropriate and capable of dealing with complex events. |
REC239-2775 | 17 - Assets and technology | That efforts by the courts, the Director of Public Prosecutions, the legal profession, Queensland Corrective Services and the Queensland Police Service to adopt technology for court processes should be supported through Government funding in so far as they create efficiencies, result in lower costs and produce better human rights outcomes. |
REC239-2662 | 24 - Govt responsibility | That responsibility for prisoner transport and non-managerial roles within the larger watch-houses is transferred to Queensland Corrective Service. |
REC239-2684 | 38 - Agency/Department Reporting | The Chief Executive Officer Portfolio Business establishes a set of performance indicators to provide a transparent process for government to monitor its performance. |
REC239-2749 | 24 - Govt responsibility | That the Prostitution Licensing Authority be moved to the Department of Justice and Attorney General Office of Fair Trading. |
REC239-2692 | 39 - Disaster Risk Management | That the Queensland Police Service Disaster Management Unit is to be permanently located at the State Disaster Coordination Centre to work on a day to day basis with the proposed new Department of Fire and Emergency Services. |
REC239-2769 | 9 - Community education | That the Chief Executive Officer portfolio business and Commissioner of Police in line with the government’s open data policy consider introducing an improved social media style forum for interaction with the community and stakeholders across the portfolio. |
REC239-2709 | 17 - Assets and technology | That the information and communication technology solution being developed to provide situational awareness, decision support, event management and that logs critical decisions receives urgent attention to ensure timely completion. |
REC239-2774 | 39 - Disaster Risk Management | Those final determinations of disaster management districts include consultation with the Local Government Association Queensland, the Queensland Fire and Rescue Service and other Government departments. |
REC239-2661 | 24 - Govt responsibility | That Queensland Corrective Service remains a separate program within the Department of Justice and Attorney-General so that while opportunities for improved services and efficacy can be realised, there is a clear separation from the youth justice services. |
REC239-2679 | 24 - Govt responsibility | To remove the Queensland Ambulance Service and Queensland Corrective Services from the Department of Community Safety—we recommend that it be renamed the Department of Fire and Emergency Services and be led by a Commissioner. |
REC239-2732 | 24 - Govt responsibility | There be a formation of an Office of Portfolio Business, providing support and governance across a range of corporate functions, which are essential to the delivery of frontline services. The Review team considers that the functions of the Operations Business and Strategy Directorate should become part of that Office and that any exception should be carefully considered by those charged with implementation of approved recommendations. |
REC239-2678 | 24 - Govt responsibility | That probation and parole should continue to work together with the Queensland Police Service to reduce the risk of reoffending and reduce crime. |
REC239-2691 | 39 - Disaster Risk Management | That the Commissioners of Police and the Queensland Fire and Rescue Service review the current district disaster boundaries as a matter of urgency in-line with the findings and recommendations of the Auditor–General’s report into the Queensland disaster management system. |
REC239-2768 | 9 - Community education | Recommendation: That: |
REC239-2708 | 24 - Govt responsibility | That the role of the Inspector General Emergency Management not extend to conducting reviews on behalf of agencies and that the role consider the effectiveness of all agencies and how their work contributes to a whole of Government response. |
REC239-2773 | 38 - Agency/Department Reporting | That should the Mobile Strategy in its current form be approved by government the CEO Portfolio Business and the Deputy Commissioner Operations: |
REC239-2660 | 24 - Govt responsibility | That Queensland Corrective Services be transferred to the Department of Justice and Attorney-General by a machinery-of-Government change as soon as is practicable. |
REC239-2723 | 1 - Land-use and building regs | That the Queensland Fire and Rescue Service examine alternative contractual arrangements with building owners which would reduce the need for physical attendance at alarm activations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1615 | 38 - Agency/Department Reporting | The Territory and Municipal Services Directorate, as part of its Bushfire Operations Plan monitoring and reporting, should assess and publicly report on cumulative progress against broader outcomes identified in the Regional Fire Management Plans and the Strategic Bushfire Management Plan. |
REC228-1610 | 24 - Govt responsibility | The Emergency Services Agency should annually review fire management zones and the Territory and Municipal Services Directorate should subsequently update the Regional Fire Management Plans. |
REC228-1605 | 24 - Govt responsibility | The Justice and Community Safety Directorate should continue to review its strategic and accountability indicators and the Territory and Municipal Services Directorate should commence a review of its strategic and accountability indicators. The directorates should consult to develop complementary measures which better assess their bushfire management activities. |
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
REC228-1619 | 1 - Land-use and building regs | The Territory and Municipal Services Directorate, in consultation with the Emergency Services Agency, should improve its management of Land Management Agreements, with respect to rural leaseholders’ fire management responsibilities, by: |
REC228-1618 | 24 - Govt responsibility | The Emergency Services Agency, the Environment and Sustainable Development Directorate and the Territory and Municipal Services Directorate should strengthen across-Government delivery of major projects in the Strategic Bushfire Management Plan and Regional Fire Management Plans by collectively: |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2850 | 17 - Assets and technology | I recommend that the AFP be provided with a search and rescue vessel which is suitable to the specific conditions of Christmas Island. I further recommend that steps be taken to ensure that if for any reason the search and rescue vessel is not available, there is a replacement vessel on Christmas Island capable of providing an emergency response in difficult sea conditions. |
REC227-2848 | 17 - Assets and technology | I recommend that the AFP take steps to determine whether access can be obtained to the National Search and Rescue Council endorsed SARMAP program covering the Australian Search and Rescue Region as well as adjoining tiles for Indonesia. Steps should be taken to ensure that if possible coverage would include high traffic areas where SIEVs enter the Australian Search and Rescue region allowing timely search and rescue plans to be drawn up for any potential incidents. |
REC227-2846 | 17 - Assets and technology | I recommend that Border Protection Command continues to examine ways of improving its surveillance capability around Christmas Island so that the risk of SIEVs arriving undetected is reduced. |
REC227-2859 | 17 - Assets and technology | I recommend that the issue of RHIB jet intake protection be allocated a high priority and that there be ongoing investigation of possible solutions to reduce the problem. |
REC227-2851 | 17 - Assets and technology | I recommend that consideration should be given to acquiring two personal water craft for deployment by appropriately trained and equipped staff of the AFP or the VMRS or both on Christmas Island. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
REC226-0583 | 17 - Assets and technology | The state should converge on a single communications platform for all emergency management and support agencies. |
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0582 | 17 - Assets and technology | The state should progressively align on a shared platform, such as WebEOC, to establish a COP [Common Operating Picture or Platform?]. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0581 | 24 - Govt responsibility | Increased acceptance of mutual obligations will be fundamental to the management of fire risk across the state |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
REC226-0571 | 24 - Govt responsibility | A review of the manner in which resourcing is conducted across all agencies needs to occur with a review identifying the best manner to ensure all agencies adapt to the same process. |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0568 | 24 - Govt responsibility | State-wide all agency reporting should be established to facilitate the interactions of emergency management agencies, support agencies and governments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0533 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1631 | 24 - Govt responsibility | The State Government prepare a strategy before the 2013-14 bushfire season on how the main firefighting agencies should deal with a drier South West region where fewer prescribed burns can be completed each year. |
REC224-1629 | 24 - Govt responsibility | The Minister for Emergency Services must ensure that future post-incident analyses are completed and made public within eight weeks of a natural disaster. |
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0521 | 9 - Community education | The Department of Environment and Conservation develop and implement a strategy to better inform the community about the complexities and decisions surrounding prescribed burns when they are undertaken in the rural urban area. |
REC223-0515 | 5 - Hazard reduction burns | The Department of Environment and Conservation urgently undertake a review of its risk management practices as they relate to prescribed burns including but not limited to: *reviewing risk management practices to ensure that they are in accordance with AS/NZS ISO 31000:2009; * finalising and implementing the new complexity model developed in house by the DEC; * considering a broader set of parameters of risk by conducting an environmental scan or similar tool for areas under consideration for a prescribed burn; *updating the prescribed fire plans to reflect the broader risk considerations discovered through environmental scanning; *better informing the risk considerations by updating the ‘Red Book’ to reflect current research on burning in coastal heath; and * reconsidering the utility of the ‘Red Flag Burn’ notification on files and either adopting it as a policy across the State or removing it as a consideration. |
REC223-0514 | 5 - Hazard reduction burns | The Department of Environment and Conservation review its current policies and operational guidelines in particular by: * strengthening the governance of operations by ensuring the Guidelines are relevant and practical; * ensuring the processes that are implemented for prescribed burns are: (a) value adding to the decisions and approvals required (b) informed by substantive input (c) focussed on outcome rather than process; *completing the draft management plan for the Leeuwin-Naturaliste Capes Area Parks and Reserves in accordance with the provisions of the Conservation and Land Management Act 1989; * exploring the possibility of automating and streamlining the various processes for formulating a prescription for prescribed burns for ease of access and updating; and * clarifying the guidance provided to decision makers as to the ‘edging’ and security of prescribed burns. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1853 | 38 - Agency/Department Reporting | The Ministers for Emergency Services, Environment and Police ensure their departments include in their annual reports the expenditure they have incurred on preparing their staff for critical incidents, and for managing their response to these incidents. |
REC222-1861 | 41 - Emergency Management exercises | The Ministers for Health, Emergency Services, Environment and Police provide additional funds to their agencies so that a detailed exercise is held on a regular basis based on a disaster that will create the worst outcome for the State. |
Rec-ID | Code | Recommendation |
---|---|---|
REC221-2862 | 38 - Agency/Department Reporting | Housing should use risk based analysis of its tenant and property information, job order data and quality assurance results to better inform target setting for KPIs, job order controls, and the sampling used for completed work inspections before and after payment. This analysis should synthesise information from all sources and include a risk assessment of tenants and properties, as well as consideration of the various types of maintenance work being done (emergency, priority and routine, and planned maintenance). |
REC221-2861 | 38 - Agency/Department Reporting | Housing should further develop its Head Contractor key performance indicators to include quality, cost and tenant satisfaction. Currently performance reporting is focused entirely on timeliness indicators. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2865 | 9 - Community education | Management of community expectations: further development of tools that would allow the community to more easily |
REC216-2864 | 9 - Community education | Management of community expectations: continued community education. |
REC216-2863 | 9 - Community education | Management of community expectations: better understanding of what different groups within a community expect. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1880 | 24 - Govt responsibility | Regulators can help to achieve improved outcomes by involving fire services in the planning and licensing processes |
REC215-1877 | 39 - Disaster Risk Management | Regulators can help to achieve improved outcomes by considering the issues identified by this review |
REC215-1876 | 39 - Disaster Risk Management | Fire services can improve outcomes by initiating discussions with landfill operators about fire management planning and emphasising the critical importance of water supplies and early intervention |
REC215-1875 | 1 - Land-use and building regs | Fire services can improve outcomes by seeking input to decisions about siting, design and fire water systems as part of the planning and licensing processes |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0682 | 1 - Land-use and building regs | The Department of Environment and Resource Management should review the Queensland Urban Drainage Manual to determine whether it requires updating or improvement, in particular, to reflect the current law and to take into account insights gained from the 2010/2011 floods. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0614 | 9 - Community education | Councils and the Queensland Government should display on their websites all flood mapping they have commissioned or adopted. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0631 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0654 | 1 - Land-use and building regs | The Queensland Government should consider drafting assessment criteria to be included in the model flood planning controls which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the applicable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms) • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0691 | 1 - Land-use and building regs | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0637 | 1 - Land-use and building regs | The Queensland Government should consider amending the Urban Land Development Authority Act 2007, the South Bank Corporation Act 1989, the State Development and Public Works Organisation Act 1971 insofar as it governs state development areas, and other legislation which establishes alternative planning systems that operate independently of the Sustainable Planning Act 2009, to require that: • any planning scheme, interim or otherwise, appropriately reflects any state planning policy with respect to flood • flood risk be considered in the assessment of any development application. |
REC210-0660 | 1 - Land-use and building regs | There should be a consistent process for the determination of applications to build levees. That process should include: • consulting landholders who may be affected by the proposed levee • obtaining or commissioning appropriate hydrological and hydraulic studies to assess the impacts of the proposed levee. |
REC210-0697 | 1 - Land-use and building regs | Queensland Rail and QR National should continue to investigate opportunities for increasing the flood resilience of their networks, including raising the height of critical equipment. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0624 | 1 - Land-use and building regs | The Queensland Government should ensure that the circumstances in which the Department of Community Safety is to consult the Department of Environment and Resource Management about a planning scheme’s flood modelling and flood mapping are clear. |
REC210-0644 | 1 - Land-use and building regs | The Queensland Government should ensure that the criteria under the Environmental Protection Act 1994 that apply to the assessment of development applications for material change of use for environmentally relevant activities include consideration of the risk of flooding at the site on which the activity is proposed to occur. |
REC210-0673 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirements about utilities and sanitary drains (Performance Requirement P2 and P3) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot. |
REC210-0680 | 9 - Community education | Queensland Urban Utilities, and other distributor-retailers and councils, that have identified a practice of stormwater drains being connected to sewerage infrastructure, should conduct a program of education to raise public awareness that this practice is illegal and impedes the operation of the sewerage infrastructure. |
REC210-0613 | 1 - Land-use and building regs | Councils should ensure that areas for which there has been no assessment of the likelihood of flooding are indicated on a map and that, as part of the development assessment process for these, there is at least some enquiry into whether a site proposed for development could be subject to flooding. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0629 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a requirement that councils have a flood overlay map in their planning schemes. The map should identify the areas of the council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0652 | 1 - Land-use and building regs | The Queensland Government should review the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003 to consider whether the design and construction standards should be made more stringent than the existing standards. |
REC210-0690 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require critical infrastructure in assessable substation developments is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0636 | 1 - Land-use and building regs | The Queensland Government should consider allowing councils to amend a planning scheme to update existing flood mapping information by way of the minor amendment process, provided that adequate public consultation has occurred. |
REC210-0659 | 1 - Land-use and building regs | The Queensland Government should consult with councils to formulate a definition of ‘levee’ to identify what should be regulated. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0623 | 1 - Land-use and building regs | The Department of Community Safety should put in place administrative arrangements which ensure it can readily ascertain whether its comments are being reflected in council planning schemes. If the Department of Community Safety becomes aware that its comments are not being adequately addressed, it should take steps to follow this up with the Department of Local Government and Planning. |
REC210-0642 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require the impact of flood on commercial property to be minimised. |
REC210-0672 | 1 - Land-use and building regs | The proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, should be amended so that the performance requirement relating to building design and construction (Performance Requirement P1) for building on a lot will only be triggered where the council has: • designated part of its area as a natural hazard management area (flood) under section 13 of the Building Regulation 2006, and • either: – declared a height to be the expected flood level under section 13 of the Building Regulation 2006, or – adopted a highest recorded flood level for the lot, and • either: – declared a velocity to be the expected maximum velocity of flood water for the area in which the lot is located, or – designated the area in which the lot is located an inactive flow or backwater area. |
REC210-0677 | 1 - Land-use and building regs | Authorities responsible for the management of sewerage infrastructure should conduct a review of their existing infrastructure to identify electrical infrastructure that may be vulnerable to inundation and perform risk and cost/benefit assessments to determine if it should be relocated to a higher level. |
REC210-0612 | 1 - Land-use and building regs | For non-urban areas or areas where limited development is expected to occur councils should consider, on a risk basis, what level of information about flood risk is required for the area, and undertake the highest ranked of the following options which is appropriate to that need and within the capacities (financial and technical) of the council: a. a map showing ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. a map showing the extent of floods of a range of likelihoods (at least three) c. a flood map based on historic flood levels that have been subjected to a flood frequency analysis to estimate the annual exceedance probability of the selected historical flood d. a historic flood map without flood frequency analysis e. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay as a way to determine those areas for which further flood studies are required, or f. the Queensland Reconstruction Authority Interim Floodplain Assessment Overlay (preferably refined using local flood information) as a trigger for development assessment. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0628 | 1 - Land-use and building regs | The Queensland Government should draft model flood planning controls, using a similar format and structure to that in the Queensland Planning Provisions, that councils can adapt for local conditions. The Queensland Government should require these controls to be reflected in new planning schemes. This may be achieved by including the controls in either: • a state planning policy dealing with flood, with an accompanying amendment to the Sustainable Planning Act 2009, or • the Queensland Planning Provisions. The Queensland Government should consult councils to determine which of the two state planning instruments is the more appropriate to include the model flood planning controls. |
REC210-0649 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters. |
REC210-0689 | 9 - Community education | Councils should conduct education campaigns directed to ensuring that all residents and property owners in areas identified as being at risk of backflow flooding are aware of the circumstances in which backflow flooding can occur, the hazard it presents and what should be done if it occurs. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0617 | 1 - Land-use and building regs | The Queensland Government should consider implementing a mechanism by which prospective purchasers of property are alerted to the issue of flood risk. To that end, the Queensland Government should consider consulting the Real Estate Institute of Queensland and the Law Society of Queensland as to the appropriateness of amending standard contract conditions so as to include a ‘subject to flood search’ condition, or other means of achieving the same objective. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0635 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to expressly provide either a power to remake or a power to extend a temporary local planning instrument containing interim flood regulation for a further limited period. The power to remake or extend should: a. permit the modification of the temporary local planning instrument to the extent required to ensure its provisions remain relevant, having regard to any requirement that may have been introduced or any information that may have become available while the original temporary local planning instrument was in force b. be contingent on the Minister’s being satisfied that the circumstances listed in section 105 of the Sustainable Planning Act continue to exist and that there are proper grounds for the failure to make a permanent scheme amendment while the original temporary local planning instrument was in force. |
REC210-0658 | 1 - Land-use and building regs | The Queensland Government should consult with councils to determine an effective method for the regulation of the construction of levees in Queensland. In particular, the Queensland Government should consider: • requiring a development permit for the construction of a levee by designating levees as assessable development in the Sustainable Planning Regulation 2009, or • requiring, by way of a state planning policy or mandatory provision in the Queensland Planning Provisions, that councils nominate the construction of a levee as assessable development in their planning schemes. |
REC210-0694 | 1 - Land-use and building regs | The Queensland Government should consider whether there should be a legislative requirement that customer dedicated assets be built at or above the applicable defined flood level and if so, the Queensland Government should consider which legislation should contain such a requirement. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0622 | 1 - Land-use and building regs | If, as part of a state interest review process, the Department of Local Government and Planning decides that no condition should be imposed requiring a council’s proposed planning scheme to incorporate the effect of the Department of Community Safety’s comments about State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide, it should advise the Department of Community Safety of the reasons for its decision. |
REC210-0640 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0666 | 1 - Land-use and building regs | The Queensland Government should draft a model planning scheme policy to be included in the model flood planning controls that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0611 | 1 - Land-use and building regs | For urban areas or areas where development is expected to occur: a. councils with the requisite resources should develop a flood map which shows ‘zones of risk’ (at least three) derived from information about the likelihood and behaviour of flooding b. councils without the requisite resources to produce a flood behaviour map should develop a flood map which shows the extent of floods of a range of likelihoods (at least three). |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0627 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Act 2009 to require that consideration be given to the risk of flooding in the preparation or revision of a regional plan. |
REC210-0647 | 1 - Land-use and building regs | The Department of Environment and Resource Management should ensure that, when applications for a material change of use for an environmentally relevant activity are approved by the department, the details of those activities, including their nature and location, are provided to the council within whose area the activity will be conducted. |
REC210-0676 | 1 - Land-use and building regs | Authorities responsible for the construction of sewerage infrastructure should, when embarking on new works, undertake risk and cost/benefit assessments to determine the level at which electrical infrastructure that may be vulnerable to inundation should be placed. |
REC210-0685 | 1 - Land-use and building regs | In assessing and determining development applications for material change of use in areas susceptible to flood, councils should consider whether the new developments locate essential services infrastructure above basement level, or, alternatively, whether essential services infrastructure located at basement level can be constructed so that it can continue to function during a flood. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0616 | 1 - Land-use and building regs | Councils that do not currently do so should consider offering an online database which allows the public to conduct a search on a parcel of land to find development approvals relevant to that parcel of land. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0634 | 1 - Land-use and building regs | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include in their planning schemes a planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as a part of the development application, or • for development proposed on land where potential for flooding is unknown requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information to allow an assessment of the flood risk. |
REC210-0657 | 1 - Land-use and building regs | Levees should be regulated. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0621 | 1 - Land-use and building regs | The Queensland Government should: a. narrow the definition of ‘development commitment’ in State Planning Policy 1/03: Mitigating the Adverse Impacts of Flood, Bushfire and Landslide to ensure more development applications are assessed for compatibility with flood, and b. investigate whether the compensation provisions of the Sustainable Planning Act 2009 act as a deterrent to the inclusion of flood controls in a planning scheme and consider whether they ought be amended. |
REC210-0639 | 1 - Land-use and building regs | The Queensland Government should consider extending the application of a state planning policy dealing with flood to the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood. |
REC210-0662 | 1 - Land-use and building regs | The Queensland Government should draft assessment criteria to be included in the model flood planning controls that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0604 | 9 - Community education | By reference to the order of priority determined in accordance with recommendation 2.5, the Queensland Government and councils should together ensure that the council responsible for each urban area in Queensland has access to current flood study information. This will include determining: a. a process or processes by which the flood studies will be completed, including the involvement of the Queensland Government and relevant councils b. how, and from whom, the necessary technical and financial resources will be obtained c. a reasonable timeframe by which all flood studies required will be completed. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0626 | 1 - Land-use and building regs | Councils should consider using the limited development (constrained land) zone in their planning schemes for areas that have a very high flood risk. |
REC210-0646 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend the template assessment report used to assess applications for a material change of use for environmentally relevant activities so that it prompts departmental officers to give specific consideration, as part of the assessment process, to the risk of flooding at the site where the activity is proposed to occur. |
REC210-0675 | 1 - Land-use and building regs | The Queensland Government should consider including in the criteria in the Queensland Plumbing and Wastewater Code a requirement that the risk of leakage from private on-site sewerage systems during floods be minimised. |
REC210-0684 | 1 - Land-use and building regs | Councils should consider amending their planning schemes to include provisions directed to consideration of the flood resilience of basements as a factor in determining the appropriateness of a material change of use. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0615 | 9 - Community education | Flood maps, and property specific flooding information intended for use by the general public, should be readily interpretable and should, where necessary, be accompanied by a comprehensible explanatory note. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0633 | 1 - Land-use and building regs | The Queensland Government should include in the model flood planning controls a model planning scheme policy that: • for development proposed on land susceptible to flooding, outlines what additional information an applicant should provide to the assessment manager as part of the development application, or • for development proposed on land where the potential for flooding is unknown, requires an applicant to provide: – as part of the development application, information to enable an assessment of whether the subject land is susceptible to flooding, and – upon a determination the subject land is susceptible to flooding, more detailed information, to allow an assessment of the flood risk. |
REC210-0656 | 1 - Land-use and building regs | The Queensland Government should consider amending the Sustainable Planning Regulation 2009 so that operational work or plumbing or drainage work (including maintenance and repair work) carried out by or on behalf of a public sector entity authorised under a state law to carry out the work is not exempt development under the Sustainable Planning Act 2009 if the development has the potential to reduce floodplain storage. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0638 | 1 - Land-use and building regs | The Coordinator-General should amend the guideline for preparing an ‘initial advice statement’ for a significant project under the State Development and Public Works Organisation Act 1971 so that it specifically requires an applicant to consider and provide information about the project’s flood risk. |
REC210-0661 | 1 - Land-use and building regs | There should be a common set of considerations in the decision whether to approve an application to build a levee, including: • the impacts of the proposed levee on the catchment as a whole • the benefits of the proposed levee to the individual or entity applying to build the levee and to any nearby community as a whole • any adverse impacts on other landholders, including the risk of levee failure • the implications of the proposed levee for land planning and emergency management procedures • whether any structural, land planning or emergency management measures can be taken to mitigate the adverse impacts of the proposed levee. |
REC210-0603 | 9 - Community education | The Queensland Government, in consultation with councils, should determine which urban areas in Queensland do not have access to flood information from a current flood study. The Queensland Government should rank those areas in order of priority in accordance with their need for updated flood information by reference to factors including: a. population b. sophistication of land use planning and emergency management measures already in place in those areas c. currency of any flood risk information available to the council d. approximate frequency of damaging floods in the area according to the historical record |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0625 | 1 - Land-use and building regs | The Queensland Government should change Temporary State Planning Policy 2/11: Planning for stronger more resilient floodplains to remove the possibility of councils’ using the interim floodplain assessment overlay mapping and Model Code as part of a permanent amendment to their existing planning scheme or as part of a new planning scheme. |
REC210-0645 | 1 - Land-use and building regs | The Department of Environment and Resource Management should amend its information sheet about applications for a material change of use for environmentally relevant activities so that applicants are prompted to include information (if any) about the risk of flooding at the site where the activity is proposed to occur. |
REC210-0674 | 1 - Land-use and building regs | The Queensland Government should consider amending the ‘Limitation’ section of the proposed new part of the Queensland Development Code, Mandatory Part 3.5 ‘Construction of buildings in flood hazard areas’, to allow for the possible application of ‘acceptable solution A1’ to a building located on a lot if: • it is reasonable to expect the part of the lot on which the building work is proposed to be subjected to a maximum velocity of less than 1.5 metres per second, or • the part of the lot on which the building work is proposed is located in an inactive flow or backwater area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1919 | 1 - Land-use and building regs | Tourism WA must give specific regard as to whether land use approvals need to be sought, particularly from Department of Regional Development and Lands, when conducting due diligence for event sponsorship proposals that require sign off by both departments. |
REC204-1918 | 1 - Land-use and building regs | Department of Regional Development and Lands and Department of Environment and Conservation should consider how their respective land use approval processes can incorporate the input of Local Emergency Management Committees (LEMCs) as part of risk assessments for high risk events and adventure sport activities. |
REC204-1915 | 24 - Govt responsibility | The Department of Regional Development and Lands should ensure that event organisers and government agencies responsible for sponsoring and approving events have a greater level of awareness about the requirements of section 91 licences under the Land Administration Act 1977 (WA). |
REC204-1912 | 38 - Agency/Department Reporting | The Board of Tourism WA should take action to ensure that it reviews the quality of Board papers that are submitted to it by the executive of Tourism WA. |
REC204-1911 | 24 - Govt responsibility | As part of the review of its due diligence processes, Tourism WA should ensure that: |
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0498 | 24 - Govt responsibility | The Minister for Planning report to Parliament by May 2012 on the urgent actions undertaken by the Department of Planning and the Western Australian Planning Commission (WAPC) to transfer responsibility for declaring bushfire prone areas to the WAPC. |
REC202-0511 | 9 - Community education | The Minister for Emergency Services commission an independent report to Parliament by June 2012 on the best practices in other jurisdictions to increase the rate of residents likely to be effected by a bushfire who properly prepare their properties before the bushfire season. |
REC202-0496 | 17 - Assets and technology | The Minister for Emergency Services ensure that a whole-of-government equipment register of the firefighting equipment held by FESA, DEC and local government authorities is in place for the 2012-13 bushfire season. |
REC202-0510 | 9 - Community education | The Minister for Emergency Services and the Minister for Local Government provide additional resources to FESA, DEC and WALGA in the 2012-13 Budget to improve the Western Australian community’s knowledge of bushfire safety and to allow these agencies to involve the public in their exercises. |
REC202-0506 | 17 - Assets and technology | The Minister for Emergency Services ensure that FESA has the funds to implement the installation and use of WebEOC for use during the 2011-12 bushfire season and immediately put in place common protocols with the Police and DEC to record significant events during a bushfire. |
REC202-0503 | 24 - Govt responsibility | The Minister for Police and Emergency Services and the Minister for the Environment report to Parliament by December each year as to the state of readiness of the main State Government agencies tasked with fighting bushfires. |
REC202-0500 | 24 - Govt responsibility | In implementing the Keelty Report’s Recommendation 42, the Ministers for Emergency Services and Environment jointly report to Parliament by May 2012 on the likely impacts on, and implications for, the future bushfire operations of the State Government of the drying climate in the State’s South West region. |
REC202-0512 | 9 - Community education | The Minister for Emergency Services commission an independent report to Parliament by June 2012 on an assessment of the success of FESA’s Total Fire Ban community education campaign in improving the community’s knowledge on this issue. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0249 | 17 - Assets and technology | FRS fire appliance allocation and training needs to be reviewed to enhance offensive bushfire capability within the metropolitan area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1694 | 24 - Govt responsibility | The State Government give its full support to the Western Australian Local Government Association's Send to Solve initiative. |
REC200-0365 | 17 - Assets and technology | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA’s own policy of ‘Use of Private Vehicles in Fires’. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-0387 | 17 - Assets and technology | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the Recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-0346 | 1 - Land-use and building regs | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-1685 | 9 - Community education | The Fire and Emergency Services Authority (FESA) review its distribution of information material, including Prepare. Act. Survive. FESA should also consider including the community in pre-season exercising, in consultation with the Department for Child Protection and local governments. |
REC200-1723 | 24 - Govt responsibility | The State Government restructure the Fire and Emergency Services Authority as a Department. As part of this restructure, Emergency Management Western Australia should either |
REC200-0351 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: Reducing fuel load Improving inter-operability A mutual understanding of the fire fighting techniques of each agency. |
REC200-1692 | 5 - Hazard reduction burns | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments take proactive steps to conduct their prescribed burning programs as joint exercises. This will give effect to: |
REC200-1707 | 1 - Land-use and building regs | Main Roads Western Australia undertake more frequent examinations of its bridges located in areas prone to bushfire and ensure that the risk posed to loss of infrastructure in a fire is understood by local authorities. |
REC200-0379 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-0344 | 9 - Community education | The Fire and Emergency Services Authority (FESA) review its distribution of information material, including Prepare. Act. Survive. FESA should also consider including the community in pre-season exercising, in consultation with the Department for Child Protection and local governments. |
REC200-1684 | 9 - Community education | The Fire and Emergency Services Authority, in partnership with local governments, conduct more focused pre-season bushfire education, which emphasises: |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-0350 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth’s urban/rural interface to compliment DEC’s existing landscape-scale program. |
REC200-1691 | 5 - Hazard reduction burns | The State Government consider resourcing the Department of Environment and Conservation and local governments to develop and administer a comprehensive prescribed burning program in Perth‟s urban/rural interface to compliment DEC's existing landscape-scale program. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-0378 | 17 - Assets and technology | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-0343 | 9 - Community education | The Fire and Emergency Services Authority, in partnership with local governments, conduct more focused pre-season bushfire education, which emphasises: Water supply is not guaranteed during a bushfire Power supply is not guaranteed during a bushfire Saving life will be a priority over saving property so expect to be evacuated Once evacuated, access to affected areas may not be possible for several days Water ‘bombing’ by aircraft cannot be guaranteed in bushfire SMS warnings are advice only and may not be timely. |
REC200-1682 | 24 - Govt responsibility | The State Government give legislative effect to the Planning for Bush Fire Protection Guidelines. |
REC200-1719 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-0349 | 9 - Community education | The Fire and Emergency Services Authority work in partnership with Main Roads Western Australia and local governments to develop and implement a comprehensive strategy for the use of mobile variable message boards to alert the community to the declaration of a total fire ban and what it means. |
REC200-1688 | 9 - Community education | The Department of Education oversee the provision of bushfire education in schools that are located in bushfire prone areas, ensuring that all schools in these areas incorporate key bushfire messages in their curriculum. |
REC200-1728 | 24 - Govt responsibility | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-0364 | 17 - Assets and technology | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-1699 | 24 - Govt responsibility | The State Government ensure that the continued development of the Fire and Emergency Service Authority's Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost-effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-0377 | 1 - Land-use and building regs | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-0340 | 1 - Land-use and building regs | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-1681 | 24 - Govt responsibility | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-1717 | 24 - Govt responsibility | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-0348 | 9 - Community education | The Fire and Emergency Services Authority consider alternative wording to Total Fire Ban that ensures people gain a more complete understanding of what actions are prohibited. |
REC200-1687 | 9 - Community education | The Fire and Emergency Services Authority work in partnership with the Real Estate Institute of Western Australia to develop a package of information for new residents moving into bushfire prone areas, and a process to ensure this information is provided through real estate agents. |
REC200-1727 | 24 - Govt responsibility | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-0376 | 1 - Land-use and building regs | State and locals governments: a) recognise that regardless of future declarations of bushfire prone areas, the existing planning and building problems in the Perth Hills related to bushfire risk will persist; b) urge residents in these areas to retrofit their homes and evaporative air conditioners in compliance with AS 3959 - 2009; c) examine options to retrospectively bring these areas into compliance with Planning for Bushfire Protection Guidelines. |
REC200-1716 | 24 - Govt responsibility | State and locals governments: |
REC200-0388 | 17 - Assets and technology | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-0347 | 9 - Community education | The Department of Education oversee the provision of bushfire education in schools that are located in bushfire prone areas, ensuring that all schools in these areas incorporate key bushfire messages in their curriculum. |
REC200-1686 | 9 - Community education | Local governments continue to include information on bushfire risk and preparedness with rates notices. |
REC200-1726 | 41 - Emergency Management exercises | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. |
REC200-0356 | 5 - Hazard reduction burns | The State Government reaffirm its 2009 decision to approve DEC exercising greater flexibility in managing smoke within national guidelines, in order to achieve its prescribed burn program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0430 | 9 - Community education | the state undertake a community education program to inform households of their respective flood risk. This may include information on rate notices of heights of houses above flood level and educating people about flash flooding. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0483 | 9 - Community education | the state ensure: • where external assistance is provided to Victoria during emergencies, communities are advised of the specific purpose of that assistance, through media and other information channels; and • all agencies provide incident management personnel with information regarding the arrangements for tasking Australian Defence Force resources and that this advice is reinforced during emergencies where Australian Defence Force support is provided. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0431 | 9 - Community education | the state allocate core funding for the ongoing delivery of the ‘FloodSafe’ program to flood prone communities across Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC197-1741 | 9 - Community education | A. The CFA further develop community education programs to specifically engage culturally and linguistically diverse (CALD) communities to address the importance of ethnic diversity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0230 | 9 - Community education | Explain the meaning of ‘timely, relevant and tailored’ community bushfire warnings through training and meetings particularly of Information Section staff and Incident Controllers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0334 | 4 - Fire season preparation | The Fire Services Commissioner leads a task force to: a. identify legislation, policies and guidelines that impact on vegetation management and recommend necessary changes b. develop a set of risk-based standards for vegetation management with respect to strategic firebreaks and the assets being protected c. integrate maintenance standards across all areas of responsibility and tenure. |
REC195-0333 | 9 - Community education | The Fire Services identify opportunities for the community to learn about, engage with and influence local emergency management planning. |
REC195-0332 | 9 - Community education | The Fire Services, in consultation with the community, develop a methodology for measuring community preparedness. They should also develop tailored education and information sharing opportunities to improve community understanding of bushfire risk, mitigation and preparedness. |
REC195-0337 | 9 - Community education | DSE enhance community engagement programs in East Gippsland to ensure that local communities are more informed about the complexities and interdependencies of prescribed burning and encourage local input. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0267 | 9 - Community education | that the Deputy Premier, Attorney-General, Minister for Local Government and Special Minister of State establish with local government a communication strategy to inform all residents about their fire prevention responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1929 | 38 - Agency/Department Reporting | That the Queensland Reconstruction Authority consider extending the suite of internal performance indicators being used as the Authority matures. |
REC190-1928 | 24 - Govt responsibility | That the Queensland Reconstruction Authority finalise the value for money policies and procedures, particularly those that take into account the role and responsibilities of the external service providers. |
REC190-1927 | 24 - Govt responsibility | That the Queensland Reconstruction Authority agree on and finalise the work plan and attach it as a Schedule to the Agreement as required in section 15 of the Agreement. |
REC190-1926 | 24 - Govt responsibility | That the Queensland Reconstruction Authority clarify and communicate the roles of the Lines of Reconstruction sub-committees to the Chairs of each committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0120 | 17 - Assets and technology | Maintaining the DEC fleet of tankers, bulldozers and low loaders is crucial to DEC’s fire management and control capability. |
REC183-0119 | 17 - Assets and technology | The development of a three year aerial firefighting strategy for W.A. would ensure optimal development of a joint air capability. |
REC183-0109 | 1 - Land-use and building regs | It is sensible that, in considering planning development proposals on land adjacent to the DEC estate, that development authorities invite comment from DEC on the fire management consequences of development proposals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0127 | 9 - Community education | FESA strengthens its planning process to ensure learnings are incorporated and communicated, levels of preparedness are linked to threat analyses and public awareness and education activities are sustained. |
REC182-0126 | 9 - Community education | FESA promotes a whole-of-community approach, involving FESA, Local Governments and the community, in fire prevention functions, activities and planning. |
REC182-0132 | 9 - Community education | FESA implements an education and awareness campaign to promote the purpose and utility of community information systems. |
REC182-0134 | 17 - Assets and technology | FESA reviews its air reconnaissance capability and determines if multiple multi-sensor air reconnaissance aircraft or unmanned aerial vehicles are required for managing concurrent and/or complex incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0192 | 4 - Fire season preparation | The Department of Sustainability and Environment develop and administer a collective offset solution for individual landholders who are permitted to remove native vegetation for the purpose of fire protection. |
REC181-0199 | 1 - Land-use and building regs | The State modify its adoption of the Building Code of Australia for the following purposes: ■ to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ to apply bushfire construction provisions to non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities; ■ other than in exceptional circumstances, to apply a minimum AS 3959-2009 construction level of BAL-12.5 to all new buildings and extensions in bushfire-prone areas. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0206 | 5 - Hazard reduction burns | The State fund and commit to implementing a long-term program of prescribed burning based on an annual rolling target of 5 per cent minimum of public land. |
REC181-0191 | 1 - Land-use and building regs | The State: ■ amend the Victoria Planning Provisions to require that, when assessing a permit to remove native vegetation around an existing dwelling, the responsible authority and the Department of Sustainability and Environment, as referral authority, take into account fire hazard and give weight to fire protection purposes; ■ develop guidelines for determining the maximum level of native vegetation removal for bushfire risk mitigation, beyond which level the application would be rejected. |
REC181-0198 | 1 - Land-use and building regs | The Australian Building Codes Board do the following: ■ amend the performance requirements in the Building Code of Australia to ensure that they incorporate reducing the risk of ignition from ember attack; ■ work with Standards Australia to effect expeditious continuing review and development of AS 3959, Construction of Buildings in Bushfire-prone Areas, and other bushfire-related standards referred to in the Building Code of Australia; ■ negotiate with Standards Australia and SAI Global Ltd an arrangement for free online access to AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, the other Australian standards referred to in AS 3959-2009, and any other bushfire-related Australian standards referred to in the Building Code of Australia; ■ amend the Building Code of Australia to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ include in the Building Code of Australia bushfire construction provisions for non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities. |
REC181-0205 | 1 - Land-use and building regs | The State initiate the development of education and training options to improve understanding of bushfire risk management in the building and planning regimes by: ■ providing regular training and guidance material to planning and building practitioners; ■ providing regular training and guidance material to planning and building practitioners. |
REC181-0157 | 9 - Community education | The Commonwealth lead an initiative through the Ministerial Council for Police and Emergency Management, facilitated by Emergency Management Australia, to develop a national bushfire awareness campaign. |
REC181-0190 | 1 - Land-use and building regs | The Country Fire Authority amend its guidelines for assessing permit applications for dwellings, nondwellings and subdivisions in the Bushfire-prone Overlay in order to accommodate the amendments to the Wildfire Management Overlay that are implemented as a result of recommendation 39 and make the guidelines available to municipal councils and the public. The revised guidelines should do the following: ■ substantially restrict new developments and subdivisions in those areas of highest risk in the Bushfire-prone Overlay; ■ set out the CFA’s guidelines for assessing permit applications for dwellings, non-dwellings and subdivisions—including the minimum defendable space requirements for different risk levels; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ emphasise the need for enduring permit conditions—in particular, conditions for the creation and maintenance of minimum defendable space to be maintained for the life of the development. |
REC181-0212 | 4 - Fire season preparation | VicRoads implement a systematic statewide program of bushfire risk assessment for all roads for which it is responsible, to ensure conformity with the obligations in s. 43 of the Country Fire Authority Act 1958 and with the objectives expressed in the VicRoads 1985 Code of Practice. |
REC181-0197 | 1 - Land-use and building regs | Standards Australia do the following: ■ amend the objective of AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, to ensure that it incorporates reducing the risk of ignition from ember attack; ■ review, and amend as appropriate, the testing methods prescribed in its standards for Tests on Elements of Construction for Buildings Exposed to Simulated Bushfire Attack (AS 1530.8.1 and AS 1530.8.2) to ensure that, so far as is possible, the methods provide a reliable predictor of the performance of construction elements under bushfire conditions. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0203 | 1 - Land-use and building regs | The State amend s. 32 of the Sale of Land Act 1962 to require that a vendor’s statement include whether the land is in a designated Bushfire-prone Area, a statement about the standard (if any) to which the dwelling was constructed, the bushfire attack level assessment at the time of construction (where relevant) and a current bushfire attack level assessment of the site of the dwelling. |
REC181-0156 | 9 - Community education | Victoria lead an initiative of the Ministerial Council for Education, Early Childhood Development and Youth Affairs to ensure that the national curriculum incorporates the history of bushfire in Australia and that existing curriculum areas such as geography, science and environmental studies include elements of bushfire education. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0189 | 1 - Land-use and building regs | The State amend the Victoria Planning Provisions relating to bushfire to ensure that the provisions give priority to the protection of human life, adopt a clear objective of substantially restricting development in the areas of highest bushfire risk—giving due consideration to biodiversity conservation—and provide clear guidance for decision makers. The amendments should take account of the conclusions reached by the Commission and do the following: ■ outline the State’s objectives for managing bushfire risk through land-use planning in an amended state planning policy for bushfire, as set out in clause 15.07 of the Victoria Planning Provisions; ■ allow municipal councils to include a minimum lot size for use of land for a dwelling, both with and without a permit, in a schedule to each of the Rural Living Zone, Green Wedge Zone, Green Wedge A Zone, Rural Conservation Zone, Farming Zone and Rural Activity Zone; ■ amend clause 44.06 of the Victoria Planning Provisions to provide a comprehensive Bushfire-prone Overlay provision. |
REC181-0211 | 4 - Fire season preparation | The State and Commonwealth provide for municipal councils adequate guidance on resolving the competing tensions arising from the legislation affecting roadside clearing and, where necessary, amend environment protection legislation to facilitate annual bushfire-prevention activities by the appropriate agencies. |
REC181-0196 | 1 - Land-use and building regs | The State develop and implement a retreat and resettlement strategy for existing developments in areas of unacceptably high bushfire risk, including a scheme for non-compulsory acquisition by the State of land in these areas. |
REC181-0201 | 9 - Community education | The Victorian Building Commission, in conjunction with the Country Fire Authority, develop, publish and provide to the community and industry information about ways in which existing buildings in bushfire-prone areas can be modified to incorporate bushfire safety measures. |
REC181-0152 | 9 - Community education | The State revise the approach to community bushfire safety education in order to: ■ ensure that its publications and educational materials reflect the revised bushfire safety policy; ■ equip all fire agency personnel with the information needed to effectively communicate the policy to the public as required; ■ ensure that in content and delivery the program is flexible enough to engage individuals, households and communities and to accommodate their needs and circumstances; ■ regularly evaluate the effectiveness of community education programs and amend them as necessary. |
REC181-0171 | 17 - Assets and technology | The State, in conjunction with Emergency Management Australia and the Department of Defence, develop an agreement that allows Commonwealth aerial resources that are suitable for firefighting and support activities to be incorporated in preparedness plans and used on days of high fire risk. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0188 | 1 - Land-use and building regs | The State implement a regional settlement policy that: ■ takes account of the management of bushfire risk, including that associated with small, undeveloped rural lots; ■ includes a process for responding to bushfire risk at the planning stage for new urban developments in regional cities, the process being similar to that used for new developments in Melbourne’s Urban Growth Zone. |
REC181-0210 | 4 - Fire season preparation | The State amend the exemptions in clause 52.17-6 of the Victoria Planning Provisions to ensure that the provisions allow for a broad range of roadside works capable of reducing fire risk and provide specifically for a new exemption where the purpose of the works is to reduce bushfire risk. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0194 | 9 - Community education | The Country Fire Authority produce for community guidance material on fire-resistant landscape and garden design, including a list of fire-resistant species. |
REC181-0200 | 1 - Land-use and building regs | Standards Australia move expeditiously to develop a standard for bushfire sprinklers and sprayers. |
REC181-0170 | 17 - Assets and technology | The Country Fire Authority and the Department of Sustainability and Environment amend their policies on aerial preparedness and standby arrangements, their dispatch protocols and the management of aircraft in order to do the following: ■ require that at locations that attract the risk assessment or preparedness level A on code red days all personnel needed for air operations must be on standby by 10.00 am; ■ establish a system that enables the dispatch of aircraft to fires in high-risk areas without requiring a request from an Incident Controller or the State Duty Officer. |
REC181-0207 | 5 - Hazard reduction burns | The Department of Sustainability and Environment report annually on prescribed burning outcomes in a manner that meets public accountability objectives, including publishing details of targets, area burnt, funds expended on the program, and impacts on biodiversity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2977 | 38 - Agency/Department Reporting | The Department of Human Services should create evaluation guidelines for recovery operations, including links to planning. |
REC179-2976 | 41 - Emergency Management exercises | The Department of Human Services should regularly test recovery plans with partner agencies. |
REC179-2983 | 24 - Govt responsibility | The Department of Human Services should work with the State Emergency Recovery Planning Committee, regions, and other partners to facilitate understanding and ownership of roles and responsibilities for common recovery services. |
REC179-2980 | 24 - Govt responsibility | The Department of Human Services should work with regions and partner agencies at the state level to create consistent, streamlined impact assessment processes and systems. |
REC179-2979 | 24 - Govt responsibility | The Department of Human Services should communicate strategic priorities to achieve state and regional level alignment in building recovery capacity and capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0104 | 1 - Land-use and building regs | That FESA assess the cost and other implications of proposed changes to bushfire prone zone declarations which would allow the whole State to be declared bushfire prone. |
REC173-0103 | 24 - Govt responsibility | That the Minister for Emergency Services consider the appointment of the Chief Executive Officer, Department of Environment and Conservation as a member of the State Emergency Management Committee. |
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0047 | 17 - Assets and technology | There is an established need to develop mobile accommodation and accommodation facility support solutions that allows an acceptable standard of accommodation to be provided to fire fighters in close proximity to the incident. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0019 | 17 - Assets and technology | A centralised, regional, multi-agency resource coordination and tracking system/facility be established to accommodate and coordinate the movement of resources from all agencies within and between regions. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0028 | 17 - Assets and technology | Ensure the S61 helicopter has all appropriate channels for water bombing operations throughout the State by including this requirement on a pre-deployment checklist. |
REC172-0029 | 17 - Assets and technology | Provide a photocopier in the Mobile Communications Facility or the mobile equipment cache that is capable of large volume production of collated documents. |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
REC172-0026 | 17 - Assets and technology | At large incidents a communications bus should be provided for the use by Air Ops and a designated work space should be provided for the Air Ops management group. |
REC172-0025 | 17 - Assets and technology | Suppression resources should be ordered and mobilised as 2 truck Strike Teams with a STL and consistently deployed to the fire ground as a unit. |
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0069 | 17 - Assets and technology | That in any consideration being given to the allocation of responsibility for control of operations in respect of major fires, consideration be given to the availability of technology and other resources, particularly when particular skills are required to make best use of such technology or resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0049 | 24 - Govt responsibility | SEMC and EM WA should: formally and regularly assess which hazards the state should prepare for |
REC170-0050 | 24 - Govt responsibility | SEMC and EM WA should: assess the state’s level of preparedness at least annually, identifying gaps and significant risks |
Rec-ID | Code | Recommendation |
---|---|---|
REC169-2991 | 24 - Govt responsibility | The Department of Premier and Cabinet should provide definitive guidance on identifying essential services for declaration to better inform relevant departments in discharging their responsibilities under Part 6 of the Act. |
REC169-2997 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet and Victoria Police, in consultation with departments, should standardise reporting on training exercises conducted under Part 6 of the Act and the CIP framework to promote greater consistency and to enable better identification of lessons learned and continuous improvement. |
REC169-2990 | 24 - Govt responsibility | The Department of Premier and Cabinet should clarify the roles and responsibilities of departments and agencies under Part 6 of the Act and CIP framework to reduce confusion and gaps. |
REC169-2995 | 24 - Govt responsibility | The Department of Premier and Cabinet, in consultation with Victoria Police, should develop clear guidance to distinguish between declared essential services and critical infrastructure to assist departments, Victoria Police and industry in implementing Part 6 of the Act and the CIP framework more effectively. |
REC169-2989 | 38 - Agency/Department Reporting | The Department of Premier and Cabinet should lead the development of a performance management framework for measuring, monitoring and reporting on the implementation of Part 6 of the Act and the CIP framework. The framework should include key indicators, targets and reporting arrangements for assessing the extent to which departments, agencies and industry have fulfilled their obligations, as well as measures for monitoring achievement of joint objectives. |
REC169-2994 | 24 - Govt responsibility | Representatives of lead departments should obtain necessary security clearances so appropriate officers can access information relevant to their sectors. |
REC169-2993 | 24 - Govt responsibility | The Department of Premier and Cabinet should clarify the requirements in relation to establishing Security and Continuity Networks in designated sectors, so that there is a shared understanding of those requirements. |
REC169-2992 | 24 - Govt responsibility | The Department of Premier and Cabinet should identify risks arising from the joined-up nature of the approach to protecting essential services and critical infrastructure, and to assist departments and agencies to develop associated risk management arrangements at the whole-of-government level. |
REC169-2998 | 38 - Agency/Department Reporting | Reports on the training exercises should be retained in an appropriately secured central repository so that consolidated results of the exercises can be drawn together effectively. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0097 | 24 - Govt responsibility | Revised governance arrangements be implemented involving Disaster Management Groups at the three levels supported by EMQ as outlined in this report to achieve continuous improvement in the Disaster Management arrangements in the State. A new provision in Section 5 emphasise the discretion available to all involved in the Disaster Management system to take action to prevent impending loss of life even if contrary to the agreed arrangements. |
REC165-0098 | 24 - Govt responsibility | The SDMG take into account key improvement initiatives and change processes suggested when deciding on an effective implementation strategy for agreed recommendations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC159-3059 | 38 - Agency/Department Reporting | ACTAS should establish a clinical information database that: |
REC159-3055 | 38 - Agency/Department Reporting | ACTAS should implement systems to enable the accurate collection and measurement of non-emergency ambulance service bookings to facilitate monitoring of performance and the provision of accurate advice to Government. |
REC159-3050 | 38 - Agency/Department Reporting | ACTAS should log all emergency calls on CAD to document non-ambulance dispatch decisions, and to provide more complete data on demand. |
REC159-3062 | 38 - Agency/Department Reporting | ACTAS should develop a set of standards to measure and monitor patient satisfaction, so that improvements to the service can be made, based on patient satisfaction information. |
REC159-3047 | 38 - Agency/Department Reporting | ACTAS should develop a comprehensive performance management framework that includes key performance indicators and targets aligned to its service delivery activities, to help inform management and stakeholders of its performance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3430 | 17 - Assets and technology | That the nominated marine safety authority is responsible for development of a declared asset system and is required to ensure that port/channel managers utilise and maintain the declared asset system. |
REC158-3454 | 24 - Govt responsibility | That the Department of Transport ensures that key stakeholders are engaged during the implementation of the approved Review recommendations. |
REC158-3429 | 38 - Agency/Department Reporting | That the nominated marine safety authority is required to ensure that incident notification and data recording requirements for Victorian commercial ports are consistent and adhered to. |
REC158-3448 | 24 - Govt responsibility | That the Director of Marine Safety works with the Australian Maritime Safety Authority to ensure that State and port emergency arrangements interface appropriately with the National Maritime Emergency Response Arrangements. |
REC158-3428 | 38 - Agency/Department Reporting | That the nominated marine safety authority, in consultation with the Emergency Services Commissioner and senior emergency services personnel, is responsible for monitoring the implementation and auditing against appropriate performance standards, risk management guidelines and good practice guidelines. |
REC158-3433 | 24 - Govt responsibility | That Harbour Masters are employed by a government body and remain geographically located at the port. |
REC158-3432 | 17 - Assets and technology | That port/channel managers are required to ensure, through service agreements, licensing, direct acquisition or other means as appropriate, the availability of the critical Level 1declared assets. |
REC158-3431 | 17 - Assets and technology | That port/channel managers are required to identify in the declared asset system (in conjunction with the emergency services) critical Level 1 declared assets and other Level 2 declared assets, that may be required in support of a marine emergency within the port, and that identified resource availability, accessibility and call out time is recorded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3517 | 9 - Community education | The Victoria State Emergency Service work with the electricity distribution businesses, Department of Primary Industries and Energy Safe Victoria to develop and implement a joint community education program for public safety during and after storms and power outages. |
REC156-3486 | 24 - Govt responsibility | The emergency management arrangements include the development of partnerships between the public and private sectors, in particular the involvement of government departments and essential services. |
REC156-3514 | 24 - Govt responsibility | The State Government endorse the establishment of the Victorian Emergency Information Line and it is developed with appropriate protocols to ensure linkages and information flows to the energy sector. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3490 | 24 - Govt responsibility | The Department of Human Services improve its communication with councils to enhance delivery of recovery services. |
REC156-3518 | 24 - Govt responsibility | The Department of Premier and Cabinet, the Office of the Emergency Services Commissioner and other relevant departments conduct further work to determine the need for a power to appoint a coordinator of essential services restoration. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3467 | 38 - Agency/Department Reporting | The Department of Sustainability and Environment should report its performance against the increased prescribed burning target in its annual report, which should also include the following details: |
REC155-3476 | 38 - Agency/Department Reporting | That finalised Fire Operations Plans be made publicly available in their entirety (with the exception of any private information) on the Department of Sustainability and Environment’s website and in hard-copy, and that this requirement be clearly stated in future Codes of Practice. This should include the “district burns list”, or its future equivalents, and a map which shows the corresponding burns for each Fire District. Each map should be provided in a format which can be downloaded directly from the Department’s website without the need for further data manipulation by the user. An identical hardcopy version of the map for each Fire District should be also be available to members of the public on request and free of charge. |
REC155-3465 | 5 - Hazard reduction burns | That in order to enhance the protection of community and ecological assets, the Department of Sustainability and Environment increase its annual prescribed burning target from 130,000 hectares to 385,000 hectares. This should be treated as a rolling target, with any shortfalls to be made up in subsequent years. |
REC155-3475 | 9 - Community education | That in relation to Fire Operations Plans, the Department Sustainability and Environment extends the number of community meetings during the public consultation period to a minimum of one meeting for each Fire District, with the possibility of repeat visits to particular areas. |
REC155-3483 | 9 - Community education | That the Department of Sustainability and Environment and its partner agencies continue to develop a proactive approach to engagement with the local and wider media to achieve continuous improvement in the standard of community information and education. |
REC155-3464 | 5 - Hazard reduction burns | That the Department of Sustainability and Environment implement remote sensing imagery as a routine part of its pre-burn and post-burn assessment process for prescribed burning. Maps of every prescribed burn should be produced in a similar format to those used in Western Australia, indicating the boundary of each burn and the varying fire intensities achieved within the burn area. The boundaries of all Fuel Management Zones within each burn should also be indicated. |
REC155-3474 | 24 - Govt responsibility | That the Victorian Government consider all available means, consistent with conservation values, for substantially increasing the access of apiarists to the public land estate. |
REC155-3480 | 1 - Land-use and building regs | That the Integrated Fire Management Planning framework establish zones in the interface between public and private land in which bushfire risk management is the shared responsibility of the Victorian Government and private landholders. |
REC155-3473 | 24 - Govt responsibility | That the Victorian Government expedite the implementation of its 2006 election commitment to provide four wheel drive clubs with access to management vehicle only tracks. |
REC155-3478 | 38 - Agency/Department Reporting | That all information pertaining to current and planned prescribed burns be published more prominently on the Department of Sustainability and Environment’s website, with a single prominent link to this material on the website homepage. |
REC155-3468 | 38 - Agency/Department Reporting | That the Department of Sustainability and Environment, Department of Primary Industries, Parks Victoria & VicForests separately cost, and report, annual expenditure on fuel reduction burning, ecological burning and regeneration burning in their Annual Reports. |
REC155-3477 | 38 - Agency/Department Reporting | That the details of any variation or amendment of a Fire Operations Plan, including: the carrying forward or postponement of burns within the three-year period covered by a Fire Operations Plan; the carry over, removal or rescheduling of burns between past, present and future Fire Operations Plans; and the alteration of burn boundaries (including alterations of less than 25 per cent); should appear on the Department of Sustainability and Environment’s website at the time of the change and be included in the Fire Operations Plan for the following year. |
Rec-ID | Code | Recommendation |
---|---|---|
REC154-3459 | 41 - Emergency Management exercises | To improve response preparedness, DPI should clearly link the selection of simulation exercises to the risk management framework to target coverage of high risks. |
REC154-3462 | 41 - Emergency Management exercises | DPI should formalise the approach and framework for evaluating simulation exercises and response to Emergency Animal Disease incidents with guidelines to define the nature of the review process. This should include: |
REC154-3461 | 24 - Govt responsibility | DPI should develop an Memorandum of Understanding (MOU) with the Department of Human Services that capitalises on and strengthens the current good working relationship to support joint forward planning and risk management and mitigates against relationship failure in the event of leadership change. The MOU should clarify: |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3125 | 38 - Agency/Department Reporting | QFRS introduce a system to collate and analyse performance information for use in management reporting and to support effective decision making processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3393 | 1 - Land-use and building regs | The Committee recommends that the responsibility for land management issues lie within a single portfolio, specifically the Minister for Territory and Municipal Services. |
REC144-3384 | 41 - Emergency Management exercises | The Committee recommends that the ESA develop a schedule of proposed exercises as a five year rolling plan, in order that all the elements of emergency services are able to be tested over that time and in differing |
REC144-3390 | 24 - Govt responsibility | If the ACT Government decides to proceed with the site as the emergency services headquarters, that it accord a high priority to the finalisation of the site preparations for the ESA at Fairbairn as a matter of urgency. |
REC144-3399 | 9 - Community education | The Committee recommends that the Emergency Services Agency post all its publications, which are not internal working documents or otherwise confidential, on its website. |
REC144-3382 | 24 - Govt responsibility | The Committee recommends that responsibility for oversighting the progress of the implementation of agreed recommendations of the Coroner be undertaken by a truly independent body and not by the Bushfire Council. |
REC144-3389 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government make a public announcement about the future accommodation plans for the Emergency Services Agency and its component parts so that both the ESA and the ACT public are informed about current proposals and timeframes. |
REC144-3398 | 9 - Community education | The Committee recommends that the Emergency Services Agency update its website to accommodate, at a minimum, a publications menu item and a search function. |
REC144-3388 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government re-investigate the suitability of the Fairbairn site as a proposed centralised accommodation facility for emergency services. |
REC144-3397 | 9 - Community education | The Committee recommends that the ACT Government investigate the Victorian Community Fireguard model with a view to implementing a similar scheme in the ACT to enhance community preparedness for and ability to respond to bushfire emergencies. |
REC144-3386 | 24 - Govt responsibility | The Committee considers that the ACT Government should table in the ACT Legislative Assembly the cost-benefit analysis and business plan for Fairbairn as a central site for emergency services in the ACT. |
REC144-3396 | 9 - Community education | The Committee recommends that information in relation to proposed fuel load activity and controlled burning should be disseminated to the community and in an accessible format. |
REC144-3385 | 41 - Emergency Management exercises | The Committee recommends that the ESA hold discussions with NSW with a view to developing a joint exercise program with the NSW Rural Fire Service on an ongoing basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3580 | 17 - Assets and technology | That FESA investigate the use of new technologies such as Voice over Internet Protocol (VoIP) for supplementing the dissemination of WANDRA information in cases where landlines have been disrupted. |
REC143-3579 | 9 - Community education | That FESA develop comprehensive internet-based information including but not limited to detail of WANDRA objectives, assistance measures, administering agencies, eligibility criteria (where applicable) and application forms. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3529 | 24 - Govt responsibility | The Queensland Government should consider the endorsement of transitional arrangements proposed in this report, in order to ensure as far as possible the smooth completion of the recovery and the ultimate return to government operations as usual in the cyclone-affected area. |
REC136-3525 | 24 - Govt responsibility | In any future disaster of comparable proportions, consideration should be given to the co-location of the Building Coordination Centre and the principal One Stop Shop. |
REC136-3523 | 38 - Agency/Department Reporting | This Report should be considered for publication so that the insights, data, conclusions and recommendations are available within Queensland and other jurisdictions to assist with disaster management issues in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-2005 | 9 - Community education | That community education programs include unambiguous information that at times of unusually high water demand there might be a drop in or loss of water pressure and it might be appropriate for residents who intend to remain and fight a fire to have auxilary water pumps or booster pumps |
REC126-1942 | 24 - Govt responsibility | That the ACT Attorney-General and the ACT Government - in consulation with the Chief Justice of the ACT and the ACT Chief Magistrate - take legislative action that would have the effect of funds being directly appropriated annually to the courts, preferable along the lines of the Commonwealth model as it applies to the High Court of Australia, the Federal Court of Australia, the Family Court of Australia and the Federal Magistrates Court. Alternatively, the funds could be appropriated in accordance with the South Australian model, which has a seperate Courts Administartion Authority. |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |
REC126-1996 | 9 - Community education | That the Emergency Services Agency develop a clear policy for disseminating information to the public and the media in times of emergency and that, as required, that policy incorporate advance door-knocking of homes in the area affected, as well as regular broadcasts by local radio and television stations and regular updates on the relevant website - be that Canberra Connect or a different ACT government website - as well as the Emergency Services Agency's website |
REC126-1976 | 24 - Govt responsibility | That the Emergency Services Agency have authority over the land management agencies and other landholders in order to implement preparedness and prevention measures – including fuel-reduction works where there are failures in compliance |
REC126-2003 | 9 - Community education | That the community be made aware of the risk presented by heavy loads of garden fuels and certain types of vegetation around their houses and take active, regular measures to reduce that risk |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1962 | 24 - Govt responsibility | That, because of the small jurisdiction of the ACT (equivalent to one fire district in NSW) the ACT Government consider all possible options for the provision of fire services to the ACT, among them: |
REC126-1993 | 9 - Community education | That consulations and negotiations occur between the Emergncy Services Agency and the NSW Rural Fire Service to ensure that fire risk and safety messages to the community are coordinated. Maximum use should be made of television and radio announcements throughout the ACT and southern NSW, consistent with NSW timetables for targeted programs in conjunction with the United Firefighters Union ACT Branch and volunteer fire brigade representative. The Emergency Services Agency should consider using ACT Fire Brigade staff and ACT Rural Fire Service volunteers to talk to groups in the community on request, thus furthering face-to-face community education in high-risk suburban areas of the ACT |
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-2002 | 1 - Land-use and building regs | That consideration be given when building to the positioning of outbuildings around residential structures such that their potential impact on the main structure is reduced |
REC126-1985 | 24 - Govt responsibility | That the Emergency Services Agency, with the suport of the ACT Government, seek to establish with the NSW Department of Environment and Conservation and the NSW Rural Fire Service a protocol that will provide for the establishment of a joint incident management team as part of unified control arrangements based on adoption of the following principles: |
REC126-2012 | 24 - Govt responsibility | If they are willing and available to participate, that the taskforce's membership include Mr Phil Cheney, Mr Tony Bartlett, Mr Val Jeffery and Mr John Lowe |
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
REC126-1992 | 9 - Community education | That implementation of the Bushfire Wise Program continue and include a letterbox drop of the updated Bushfire Information Booklet |
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
REC126-2001 | 9 - Community education | That community education programs provide information about fire behaviour, urban design principles that contribute to a specific level of risk, and the benefits of fitting basic ember protection materials in areas at risk from bushfire |
REC126-1984 | 24 - Govt responsibility | That the Emergency Services Agency, with the support of the ACT Government, develop a single, new memorandum of understanding with the NSW Department of Environment and Conservation and the NSW Rural Fire Service, providing for liaison and joint operations as soon as it becomes apparent to whichever jurisdiction is managing a fire that the fire will probably affect the other jurisdiction. Joint operations should not be limited to when an incident occurs on both sides of the border, as is the current arrangement |
REC126-2009 | 24 - Govt responsibility | That a taskforce be established to give effect to the recommendations in this report |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-1991 | 9 - Community education | That the Emergency Services Agency establish annual targets for the introduction of community education programs and provide resources to conduct regular independent assessments of the level of community preparedness engendered as a result of the programs |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
REC126-2000 | 1 - Land-use and building regs | That the ACT Government consider taking measures to implement the provisions of Australian Standard 3959, Construction of Buildings in Bushfire Prone Areas, for the ACT urban area |
REC126-1979 | 24 - Govt responsibility | That the policy and practice just recommended be the subject of a memorandum of understanding between the Emergency Services Agency and the Department of Territory and Municipal Services (previously the Department of Urban Services) or other relevant department or agency, so as to ensure that the land management agency on whose land a fire starts has responsibility to respond immediately to that fire in accordance with the applicable standards for weight of response. Further, the land management agency should be responsible for efforts to suppress fire until such time as it becomes clear that the suppression task is beyond capacity of the agency, at which point the ACT Rural Fire Service should assume direct responsibility for coordinating the ongoing response |
REC126-2006 | 24 - Govt responsibility | I recommend that, as appropriate, the ACT cooperate with the Commonwealth in the implementation of the committee's recommendations and, in particular, give careful consideration to adoption of the following recommendations: |
REC126-1948 | 24 - Govt responsibility | That the Emergency Services Agency be removed from the Department of Justice and Community Safety and transformed into an independent statutory authority reporting directly to the responsible Minister. Note in this regard that Mr McLeod made a similar recommendation, and I endorse it unequivocally. Placing the agency within a government department puts unnecessary layers of bureaucracy between the agency and the responsible Minister, and the bureaucrats concerned usually have no special knowledge of or experience in emergency management, regardless of their seniority in the bureaucracy |
REC126-1990 | 9 - Community education | That the Emergency Services Agency take measures to ensure that the community regularly receives up-to-date information on the risks of bushfires |
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-1999 | 9 - Community education | That the Canberra Urban Development Working Group referred to in Mr Peter Dunn's letter consider the report prepared by Mr Leonard and note particularly that the community awareness information currently available to householders in connection with measures they can take to better protect their homes from bushfires does not refer to the potential of wooden fences, conifers and outbuildings to contribute greatly to fire spread, particularly in suburban areas. Also noteworthy is Mr Leonard's evidence that the linear sitting of homes on house blocks in Canberra seems to be an important factor contributing to house-to-house fire spread and that this should be avoided in future developments on the urban fringe |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3885 | 5 - Hazard reduction burns | Align policies and processes, within the year round 365 day focus on fire management, to provide consistency in the approach to fire regardless of its origins,- that is fuel reduction burning, regeneration and ecological burning or unplanned fire; |
REC124-3884 | 5 - Hazard reduction burns | Develop new prescriptions for prescribed burning to accommodate local conditions in those areas where standard prescriptions are assessed to be inappropriate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3882 | 41 - Emergency Management exercises | The Office of the Emergency Services Commissioner convene a working group of key emergency services and emergency management agencies to develop a flow chart based on scenario testing, to support decision making and the assessment of response requirements to medical, hazardous materials and CBR emergencies including their transition from one type to another. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3921 | 17 - Assets and technology | That the recommendations of the 2000 DPI report into the reference collection’s storage facility be implemented, to secure the collection in a purpose-built facility. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3936 | 24 - Govt responsibility | To enhance the governance of the Queensland disaster management system, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services ensure that — |
REC111-3935 | 24 - Govt responsibility | To provide the strategic leadership and governance required to implement the Disaster Management Act 2003, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable governance framework for disaster management which includes the establishment of — |
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2286 | 17 - Assets and technology | That CFA, having regard to terrain, continue to review the mix of firefighting appliances currently in service. In particular, consideration should be given to the number and distribution of smaller ‘slip-on’ type equipment. |
REC104-2210 | 9 - Community education | That CFA reports to the Minister for Police and Emergency Services on recommended solutions and implementation strategies for isolated small communities by June 2004. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2192 | 24 - Govt responsibility | That, according to available scientific evidence, a decision regarding cattle grazing in the High Country should not be based on the argument that ‘grazing prevents blazing.’ |
REC104-2247 | 24 - Govt responsibility | That an appropriately resourced, national aerial firefighting strategy is urgently required, and that the Victorian Government make representations to the Commonwealth to support the Australasian Fire Authorities Council recommendations |
REC104-2204 | 9 - Community education | That the three fire agencies (CFA, DSE and MFESB) develop and implement a joint Statewide fire awareness education and information program aimed at encouraging a higher degree of personal and household self-reliance. |
REC104-2268 | 9 - Community education | That CFA and DSE include agreed Fire Control Priorities in community awareness and education material provided to the community before each fire season. |
REC104-2209 | 9 - Community education | That CFA, in conjunction with isolated small communities, develop and promote a suite of appropriate fire readiness and fire management strategies to meet their needs. |
REC104-2214 | 9 - Community education | That CFA, recognising the value of the Community Fireguard Group program, undertake a review by June 2004 to identify opportunities to further develop the program to ensure its continuing appropriateness in preparing communities for fire into the future. |
REC104-2315 | 24 - Govt responsibility | That the Privacy Commissioner be asked for advice in the development of this model. |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
REC104-2239 | 24 - Govt responsibility | That any local level agreements developed to address geographically specific risks or issues must be consistent with State-level arrangements. |
REC104-2335 | 41 - Emergency Management exercises | That the fire agencies develop a program to significantly increase the amount of joint training and exercises undertaken. |
REC104-2200 | 38 - Agency/Department Reporting | That DSE: |
REC104-2256 | 24 - Govt responsibility | That the State Emergency Operations Centre develop and maintain strong and close links with the State Emergency Response Coordination Centre, if collocation is not possible. |
REC104-2208 | 9 - Community education | That CFA and MFESB encourage householders to review their fire safety plan annually. |
REC104-2213 | 9 - Community education | That CFA provides technical advice to Community Fireguard Groups in the selection and purchase of appropriate equipment and protective clothing for use on their own land. |
REC104-2303 | 24 - Govt responsibility | That Interstate Agreements prepared by the fire agencies be reviewed to include protocols for the joint release of consistent and appropriate information relating to fires burning across State borders. |
REC104-2232 | 24 - Govt responsibility | That Government in the development of its statewide water policy includes appropriate consideration of access to water for firefighting. |
REC104-2331 | 24 - Govt responsibility | That a State Emergency Operations Centre be established to replace the existing separate fire agency centres. This could, if necessary, be initially confined to being a State Fire Operations Centre as recommended in Chapter 18, Part D. |
REC104-2195 | 38 - Agency/Department Reporting | That the creation of buffers by chaining and then burning swaths of mallee be explicitly monitored for: |
REC104-2255 | 24 - Govt responsibility | That the options of collocating the State Emergency Response Coordination Centre with the new State Emergency Operations Centre |
REC104-2207 | 9 - Community education | That the Coordinator-in-Chief of Emergency Management directs that all emergency management agencies review, by June 2004, terminology and language in current communication and public education material to ensure it is clear, easily understood and consistent, particularly with regard to fire. |
REC104-2290 | 38 - Agency/Department Reporting | That instances where demand for air support outstrips the supply of State Fleet Aircraft available are recorded. |
REC104-2212 | 9 - Community education | That Community Fireguard Group co-ordinators’ names are supplied to their local municipality for the 2003-2004 fire season, and are updated annually for use in information exchange should a Municipal Emergency Co-ordination Centre or Incident Control Centre be established. |
REC104-2230 | 24 - Govt responsibility | That DSE investigates whether such agreements should exist with other government Departments and agencies, particularly those with officers located in rural Victoria who may be involved in fire response and support operations in the future, based on their expertise and experience. |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2194 | 38 - Agency/Department Reporting | That the success of current buffers in terms of assisting suppression operations be continually reviewed, evaluated and documented. |
REC104-2254 | 24 - Govt responsibility | That a single state-of-the-art all hazards State Emergency Operations Centre be established for Victoria. This could, if necessary, be implemented in stages, initially incorporating DSE, CFA, MFESB and the State Aircraft Unit. |
REC104-2206 | 9 - Community education | That CFA and MFESB: |
REC104-2289 | 38 - Agency/Department Reporting | That the joint agencies introduce a system of performance measures for reporting the effectiveness of aircraft in firefighting operations. |
REC104-2211 | 9 - Community education | That CFA clarifies and restates the roles and function of existing Community Fireguard Groups (including their relationship to the Municipal Fire Prevention Plan) to members, co-ordinators, Incident Controllers and Municipal Emergency Resource Officers, prior to the 2003-2004 fire season. |
REC104-2225 | 24 - Govt responsibility | That the Victoria Emergency Management Council establish a sub-committee by June 2004 to ensure an all-agency and appropriate industries’ policy framework is developed and agreed in respect to the planning for fire prevention, mitigation and suppression. |
REC104-2321 | 24 - Govt responsibility | That Government confirms that the Model of Fire Cover/Fire Safety Victoria strategy should be a seamless model for the whole of the State and include both private and public land. |
REC104-2193 | 38 - Agency/Department Reporting | That if ‘link’ burns continue to be used, then on-site weather sequences and fuel conditions marking successful (‘within explicit prescription’) and unsuccessful burns be documented. |
REC104-2250 | 41 - Emergency Management exercises | That DSE and CFA work in cooperation with the Municipal Emergency Response Coordinators to develop and conduct joint exercises that practise the skills and test procedures for operations of the Municipal Emergency Coordination Centre, Municipal Recovery Centre and Incident Control Centres. |
REC104-2205 | 9 - Community education | That CFA should remain the lead agency in delivering the community education and information program to rural Victoria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3246 | 38 - Agency/Department Reporting | The Committee recommends that performance monitoring standards be established, reviewed and maintained through a common reporting system by the Minister for Police and Emergency Services. |
REC061-3408 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3242 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3257 | 9 - Community education | The Committee recommends that the FireVision concept used by the Metropolitan Fire Brigades Board be extended through the Directorate of School Education's Interactive Television Program to all emergency services and in particular to rural fire and emergency services. |
REC061-3422 | 9 - Community education | The Committee recommends that the FireVision concept used by the Metropolitan Fire Brigades Board be extended through the Directorate of School Education's Interactive Television Program to all emergency services and in particular to rural fire and emergency services. |
REC061-3250 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |
REC061-3415 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4153 | 17 - Assets and technology | No opportunity be lost by the Forests Department to improve the efficiency of their fire fighting gangs, radio and other equipment in the light of the latest practical and scientific developments. |
REC019-4133 | 9 - Community education | The Bush Fires Board take a more active part in enlightening the public generally and the local communities in particular to their responsibilites on fire control. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3949 | 17 - Assets and technology | It is recommended that the A.R.P. dams or earth tanks be kept filled during possible danger periods. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
REC016_3952 | 4 - Fire season preparation | It is recommended that the question of the future responsibility be made certain and that the body so made responsible keep the grounds of the hospital free from undergrowth and trees wherever their presence may be a possible source of future danger. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3950 | 4 - Fire season preparation | It is recommended that on days of abnormal danger loads of briquettes be not kept in the station yard. The real danger, which transcends in gravity the danger of time destruction of loads of briquettes, is that the prevailing wind or a change of wind might carry showers of burning embers to the town, which is but the width of a road away, and thereby cause material damage in the town. It is further recommended that the yard and its surroundings be kept clear of scrub and growth; and that special provision be made for quelling fire which may break out in the deposits of inflammable dust which lie in time yard. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3956 | 24 - Govt responsibility | It is strongly recommended that no public department of possible combination of public departments interested in forests should be permitted to gain control of this authority. |
REC015_3954 | 24 - Govt responsibility | It is recommended that each public department or body which may now or hereafter control forest areas be allowed to pursue its own policy of fire prevention and suppression. As each such body is responsible directly or indirectly to Parliament it must be allowed to carry its responsibility in its own manner. It is strongly recommended that no such department be given authority over any other body in matters relating to fire prevention or suppression. If it is ultimately shown that a department is unfit to discharge the duty involved other measures may be taken. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
REC004-3996 | 17 - Assets and technology | That the standard pattern of cinder arrester be affixed to the ash-pans in all locomotives during the summer months. |
REC004-3994 | 17 - Assets and technology | That the Railway Department, while gradually reducing the number of different types of locomotives, should steadily keep in view the adoption of English and American railway practice, by providing engines with larger boilers, fire boxers, and smoke-boxes, and with wide blast-pipes, in order to insure ample steaming power with a minimum of forced draught. |
REC004-3992 | 17 - Assets and technology | That the use of a spark-arrester and cinder-arrester by the Railway Department shall not constitute a defence to an action for damage caused by fire escaping from a locomotive, unless the Department proves that such spark-arrester and cinder-arrester were in a thoroughly efficient condition when the fire took place. |