Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC326-4340 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: documents all key decisions and approvals in line with record keeping obligations. |
REC326-4341 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures regular monitoring is in place as part of funding deeds. |
REC326-4342 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures staff declare conflicts of interest prior to the commencement of a grants stream, and that these conflicts of interest are recorded and managed. |
REC326-4343 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: ensures a communications plan is in place, including the communication of guidelines to potential applicants. |
REC326-4344 | 24 - Govt responsibility | To promote integrity and transparency, the Department of Regional NSW should ensure that for all future grant programs it: establishes and follows guidelines that align with relevant good practice guidance including accountabilities, key assessment steps and clear assessment criteria. |
Rec-ID | Code | Recommendation |
---|---|---|
REC325-4322 | 24 - Govt responsibility | The Inspector-General of Emergency Management recommends the Dam Safety Regulator review the Emergency Action Plan for Referable Dam Guideline with particular regard to the distinction between the process required by a flood event as compared to a dam failure event by 1 November 2023. The Emergency Action Plan for Referable Dam Guideline review will be informed by a discussion, facilitated by the Dam Safety Regulator, between dam owner Seqwater, the Brisbane City Council Flood Information Centre, the Brisbane Local Disaster Management Group and the Brisbane District Disaster Management Group. The purpose of the facilitation is to achieve inter-agency understanding of warning and notification responsibilities. The reviewed Emergency Action Plan for Referable Dam Guideline should be published, promoted and shared via a stakeholder engagement exercise with Queensland’s referable dam owners, disaster management stakeholders including local disaster management groups and district disaster management group. |
REC325-4331 | 41 - Emergency Management exercises | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services conduct annual exercises with every local disaster management group and district disaster management group to confirm the process for developing, approving and issuing of an Emergency Alert, including the use of pre-formatted polygons and messages. Upon completion of the initial statewide exercise, Queensland Fire and Emergency Services will furnish an exercise evaluation report to the Office of the Inspector-General of Emergency Management by 1 November 2023. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4273 | 33 - Relief and recovery | That the NSW Government overhaul the way in which it conducts its grants process as it frustrated applicants and further traumatised them by repeatedly re-interviewing them and making them prove that they were flooded. |
REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
REC323-4277 | 33 - Relief and recovery | That the NSW Government develop a more proactive, rapid response to manage animal welfare following natural disasters which includes improved collaboration and communication with local veterinarians and animal welfare organisations. |
REC323-4262 | 33 - Relief and recovery | That the NSW Government provide an increased level of targeted support to flood affected communities contending with widespread mould. |
REC323-4269 | 33 - Relief and recovery | That the NSW Government address the mental health needs of local communities following the February-March 2022 floods by: • embedding within state emergency and recovery plans a strategy that provides surge capacity for mental health and social workers by: • prioritising funding for community groups that are currently providing social and mental health support to their local communities • ensuring all flood-impacted communities receive the mental health support they need to fully recover. |
REC323-4289 | 33 - Relief and recovery | That the NSW Government ensure that all emergency and recovery plans, including state plans, local emergency management plans and functional area plans, are reviewed and updated regularly and provide clarity on the role of non-government partners. |
REC323-4271 | 33 - Relief and recovery | That Service NSW establish teams of assessors that can be on the ground to assess and approve grant applications. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4242 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends the Department of Environment and Science review the format and delivery of Queensland Parks and Wildlife Service annual fire refresher training to include a scenario-based exercise. |
REC322-4251 | 41 - Emergency Management exercises | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services facilitate an annual state level exercise of the Queensland Bushfire Plan that includes all relevant stakeholders and land managers. The exercise should focus on roles, responsibilities, interagency arrangements and handover arrangements between agencies and land managers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4198 | 33 - Relief and recovery | Relief and recovery capability: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions works with the entity referred to in Recommendation 13, or otherwise responsible government department and/or Municipal Association of Victoria, councils and local relief and recovery organisations to provide centralised capability development opportunities to increase local capability and capacity to plan and deliver on their relief and recovery responsibilities: |
REC319-4189 | 33 - Relief and recovery | Donated good: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department: |
REC319-4200 | 33 - Relief and recovery | Foundations of emergency management: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in consultation with the emergency management sector – establish policies and platforms to improve operational and personal information sharing between relief and recovery organisations. These policies and platforms should enable: |
REC319-4195 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, leads the development of a comprehensive, person-centred, trauma-informed recovery financial assistance system that establishes: |
REC319-4196 | 33 - Relief and recovery | Relief and recovery funding: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, works with the emergency management sector to develop a recovery funding model that enables: |
REC319-4187 | 33 - Relief and recovery | Recovery governance: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department, work with councils, relevant recovery organisations and communities to develop clear roles and responsibilities for: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4184 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria collaborate with the emergency management sector to develop a capacity model that considers current and future: |
REC318-4179 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in accepting that emergency management is a ‘shared responsibility’ - collaborate with the emergency management sector and community to: |
REC318-4185 | 15 - Inter-service cooperation | The Inspector-General for Emergency Management recommends that Emergency Management Victoria works with the emergency management sector and relevant emergency management entities in New South Wales and South Australia to identify and address key cross border operational and resource management issues. This engagement should aim to enhance interoperability and maximise the capability and capacity of agencies to work together during emergencies along Victoria’s borders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4054 | 24 - Govt responsibility | Australian, state and territory governments should establish an authoritative advisory body to consolidate advice on strategic policy and relevant operational considerations for ministers in relation to natural disasters. |
REC317-4121 | 41 - Emergency Management exercises | Australian, state and territory governments should work together to develop a program for national level recovery exercises, building on the work currently underway through the Community Outcomes and Recovery Subcommittee of the Australia-New Zealand Emergency Management Committee. |
REC317-4116 | 33 - Relief and recovery | Governments should create and publish standing policy guidance on whether they will or will not assist to clean-up debris, including contaminated debris, resulting from natural hazards. |
REC317-4078 | 24 - Govt responsibility | Australian, state and territory governments should adopt procurement and contracting strategies that support and develop a broader Australian-based sovereign aerial firefighting industry. |
REC317-4063 | 23 - Climate Change | Australian, state and territory governments should produce downscaled climate |
REC317-4126 | 33 - Relief and recovery | Australian, state and territory governments should expedite the development of pre-agreed recovery programs, including those that address social needs, such as legal assistance domestic violence, and also environmental recovery. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4053 | 24 - Govt responsibility | Australian, state and territory governments should restructure and reinvigorate ministerial forums with a view to enabling timely and informed strategic decision-making in respect of: |
REC317-4071 | 41 - Emergency Management exercises | Australian, state and territory governments should conduct multi-agency, national-level exercises, not limited to cross-border jurisdictions. These exercises should, at a minimum: |
REC317-4104 | 33 - Relief and recovery | Australian, state and territory governments should refine arrangements to support localised planning and the delivery of appropriate mental health services following a natural disaster. |
REC317-4073 | 24 - Govt responsibility | State and territory governments should take steps to ensure that there is better interaction, planning and ongoing understanding of Australian Defence Force capabilities and processes by state and territory fire and emergency service agencies and local governments. |
REC317-4122 | 33 - Relief and recovery | Australian, state and territory and local governments should evaluate the effectiveness of existing financial assistance measures to inform the development of a suite of pre-effective pre-determined recovery supports. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4069 | 24 - Govt responsibility | State and territory governments should update and implement the National Framework to Improve Government Radio Communications Interoperability, or otherwise agree a new strategy, to achieve interoperable communications across jurisdictions. |
REC317-4131 | 24 - Govt responsibility | Each state and territory government should establish an independent accountability and assurance mechanism to promote continuous improvement and best practice in natural disaster arrangements. |
REC317-4119 | 33 - Relief and recovery | The Australian Government, through the mechanism of the proposed standing national recovery and resilience agency, should convene regular and ongoing national forums for charities, non-government organisations and volunteer groups, with a role in natural disaster recovery, with a view to continuous improvement of coordination of recovery support. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4058 | 24 - Govt responsibility | The Australian Government should enhance national preparedness for, and response to, natural disasters, building on the responsibilities of Emergency Management Australia, to include facilitating resource sharing decisions of governments and stress testing national disaster plans. |
REC317-4118 | 33 - Relief and recovery | Australian, state and territory governments should create a single national scheme for the regulation of charitable fundraising. |
REC317-4123 | 24 - Govt responsibility | Australian, state and territory governments should ensure that personal information of individuals affected by a natural disaster is able to be appropriately shared between all levels of government, agencies, insurers, charities and organisations delivering recovery services, taking account of all necessary safeguards to ensure the sharing is only for recovery purposes. |
REC317-4056 | 24 - Govt responsibility | Australian Government agencies should work together across all phases of disaster management. |
REC317-4117 | 33 - Relief and recovery | State and territory governments should develop and implement efficient and effective arrangements to: |
REC317-4101 | 24 - Govt responsibility | Australian, state and territory governments should develop national air quality forecasting capabilities, which include broad coverage of population centres and apply to smoke and other airborne pollutants, such as dust and pollen, to predict plume behaviour. |
REC317-4127 | 33 - Relief and recovery | Australian, state and territory governments should incorporate the principle of ‘build back better’ more broadly into the Disaster Recovery Funding Arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4023 | 41 - Emergency Management exercises | An opportunity to exercise and test the formation and functioning of a Management Executive through desktop and/or limited scenario-based exercises be provided. |
REC316-4017 | 15 - Inter-service cooperation | The working group (Rec 1) should include relevant stakeholders deciding collectively what the declaration might mean for such things as sub and supporting plans and the relevant community messages and calls to action. |
REC316-4040 | 41 - Emergency Management exercises | The PICC be exercised in conjunction with any and all Emergency Plan exercises to test and refine strengthened arrangements. |
REC316-4043 | 15 - Inter-service cooperation | NDIA be engaged in regard to information sharing in emergencies as part of the above actions. |
REC316-4032 | 41 - Emergency Management exercises | Concurrent and/or non–standard emergencies such as energy supply impacts be included in future exercise programs. |
REC316-4046 | 33 - Relief and recovery | Emergency Plan and Recovery sub-plans should be amended to better define recovery mechanisms and responsibilities, including hand over points to recovery authorities and community engagement for the delivery of long term recovery mechanisms. |
REC316-4034 | 15 - Inter-service cooperation | Efforts be increased to build trust, confidence and a common operating picture across PCS and RFS and seek mechanisms that identifies RFS and PCS as equitable partners in delivery of fire management across the territory. |
REC316-4028 | 41 - Emergency Management exercises | Any changes to the ECC structure and role be exercised both within ESA and across a WHoG exercise and testing program. |
REC316-4019 | 15 - Inter-service cooperation | In collaboration with other jurisdictions the ACT share the learnings for this bushfire event and work to officially embedded values officers and RRATs as key elements of bushfire response. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3856 | 10 - Infrastructure | That, in order to improve response times to Triple Zero calls, the NSW RFS implements the integrated dispatch system before the 2020-21 fire season commences. |
REC315-3842 | 24 - Govt responsibility | That, in order to prioritise early suppression and keep fires small: |
REC315-3868 | 33 - Relief and recovery | That, in order to ensure people only need to tell their story once to access government agency support following an emergency, Resilience NSW and Service NSW jointly design an inclusive, person-centred approach to information collection at evacuation centres. This should be supported by an opt-in scheme enabling personal information to be shared between NSW government agencies, local councils and non-governmental organisations administering support services for disaster-affected people. |
REC315-3851 | 10 - Infrastructure | That, to ensure mobile generators are sourced and distributed on a priority basis during natural disasters, the EUSFAC work with the NSW Telco Authority, relevant NSW government agencies and commercial stakeholders to develop a mobile asset deployment strategy. The strategy should reduce duplication in purchasing, maintaining and housing mobile generators and improve agility in deployment. |
REC315-3835 | 15 - Inter-service cooperation | That, in order to ensure the safety of local landholders on firegrounds, the NSW RFS emphasises the importance of local landholders using protective clothing while fire fighting as part of the RFS’ ‘Farm Fire Unit Integration’ priority for 2020-21. |
REC315-3810 | 24 - Govt responsibility | That, to ensure updated resource-sharing arrangements are in place, the NSW and Victorian Governments progress and finalise a multi-agency Memorandum of Understanding before the 2020-21 fire season commences. |
REC315-3827 | 10 - Infrastructure | That, in order to minimise communication outages and extend basic communication coverage during bush fires, the NSW Government work directly, or together with other Australian governments and/or their relevant power and telecommunications regulatory, policy and market bodies, to: |
REC315-3826 | 10 - Infrastructure | That, in order to maximise the protection of critical infrastructure in a bush fire, Australian governments revise the regulatory framework for the provision to government authorities of information about all critical infrastructure (public and private) including a possible change to compel the owners of critical assets to provide all needed metadata, updated annually, for appropriate planning, preparation and response for bush fire. This would include information about location, ownership, access, details of service the infrastructure supports, and fire treatments of building and surrounding zones. |
REC315-3806 | 15 - Inter-service cooperation | That the NSW RFS work with AFAC to analyse the impact of changing fire seasons on inter- jurisdictional resource sharing agreements, both domestic and international, and determine any flow-on effects for NSW fire fighting personnel capacity. |
REC315-3863 | 15 - Inter-service cooperation | That, in order to provide real-time information on evacuation doorknocking during emergency events, Government explore a shared data gateway for NSW agencies based on the NSW State Emergency Service Collector app and a common mapping and analytics platform. |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3261 | 24 - Govt responsibility | Consider amending the Fire and Emergency Services Act 2005 to align SAFECOM Board operations with accepted governance standards with the Minister appointing an Independent Chair of the SAFECOM Board. The SAFECOM Chief Executive (CE) should report to the Board and maintain SAFECOM’s role at the direction of the Board. Alternatively, SAFECOM could be abolished, moving to a model of a Department of Fire and Emergency Services where the departmental head reports to the Minister but the value proposition of any such machinery of government change would need to be thoroughly examined. |
Rec-ID | Code | Recommendation |
---|---|---|
REC313-2513 | 33 - Relief and recovery | Assessing the availability and skillsets of the resources needed to respond to a major disaster recovery event. |
REC313-2509 | 33 - Relief and recovery | Developing detailed recovery procedures. |
REC313-2516 | 33 - Relief and recovery | Documenting disaster recovery risks in agency risk registers, along with controls and treatment plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2493 | 41 - Emergency Management exercises | To increase shared understanding of risks and enhance capability integration and collaborative planning, both Local Disaster Management Group (LDMG) participate in the exercising of the Paradise Dam Emergency Action Plan. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2488 | 33 - Relief and recovery | The basic capacity needs of each functional recovery group and how this can be scaled up should be identified. Plans for functional recovery groups should reflect this in clear statements for every level of the system, for all relevant entities about their required function, role and responsibilities during recovery. |
REC310-2485 | 33 - Relief and recovery | Recovery plans at all levels should include transition arrangements. They should be implemented during recovery. The arrangements should: |
REC310-2484 | 33 - Relief and recovery | There remains a need to maximise the effect of all offers of assistance to recovering communities. This recommendation presents an opportunity to resolve any outstanding aspects of Recommendation 4 and Actions in Response from the Cyclone Debbie Review Action Plan: |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2468 | 33 - Relief and recovery | State Government agencies with key roles and responsibilities around disaster recovery provide increased support in the development of recovery at the local level (pre-event). |
REC309-2475 | 15 - Inter-service cooperation | Greater emphasis be placed on pre-planned and pre-determined arrangements between the Australian Defence Force and State and local agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2461 | 24 - Govt responsibility | A strategy should be developed between the key tourism and transport operators, and local and state government. It should address the arrival of visitors and tourists after a disaster, and should ensure that their arrival matches communities’ needs for recovery and return to normal business. The Department of Tourism, Major Events, Small Business and the Commonwealth Games should monitor its implementation. |
REC308-2466 | 41 - Emergency Management exercises | Exercising should focus on vertical integration and include all levels of the system. A strategic program of exercises should be developed and implemented. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2433 | 24 - Govt responsibility | To make planned burning and land clearing easier to understand and implement for landholders, a single point of contact for all bushfire mitigation inquiries and permits should be established. |
REC307-2444 | 41 - Emergency Management exercises | All disaster management groups should run an exercise that has full involvement of a hazard-specific primary agency in the next 12 months and regularly thereafter. |
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2425 | 24 - Govt responsibility | We recommend that the Department of Natural Resources and Mines and the four councils work together to effectively and economically regulate levee banks. |
REC306-2422 | 24 - Govt responsibility | We recommend that, in the absence of stand-alone catchment management authorities, the Department of Infrastructure, Local Government and Planning fulfil its obligation under the State Disaster Management Plan to drive the enhancement of flood resilience in the four catchments by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2405 | 24 - Govt responsibility | Retain the Bushfires Council as a Ministerial advisory body. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2393 | 15 - Inter-service cooperation | In recognising the success of the work of both the volunteer based Rural Fire Service and the full time Fire and Rescue NSW (FRNSW) members in joint operations – both agencies should be represented at major briefings or press conferences to reinforce successful integrated collaborative efforts rather than individual agency achievements |
REC302-2399 | 24 - Govt responsibility | Implement a fully integrated civilianised single call and dispatch centre, that includes a redundancy option outside the Sydney CBD, which will adopt an agnostic approach to deploy the quickest most suitable resource to an emergency. Such a centre should be managed by either a non uniformed public servant staffed organisation like the Office for Emergency Management, or the NSW Police Force |
REC302-2400 | 15 - Inter-service cooperation | Until a single call centre is developed, continue deployments of a senior RFS officer to Fire and Rescue NSW ComCen on a 24/7 day basis. This arrangement should determine the quickest most suitable resource and who is ‘in charge’ of an incident |
REC302-2396 | 15 - Inter-service cooperation | The Commissioners of Fire and Rescue NSW (FRNSW) and the RFS issue an instruction to FRNSW ComCen that while AVL capability is being made available to the RFS vehicle fleet, no offers of assistance by one agency to the other in combatting a fire is rejected or delayed if what is being offered is appropriate |
REC302-2394 | 15 - Inter-service cooperation | Take immediate steps to eliminate fire boundaries for call and dispatch purposes to create an agnostic approach to the threat of fires from both a departmental and organisational perspective |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2388 | 15 - Inter-service cooperation | TFS, PWS and STT should establish a State Air Desk, to be staffed by specialist staff year-round, with responsibility for managing both preparatory and contractual issues out of season as well as aircraft management when fires or other emergency events are occurring. |
REC301-2386 | 15 - Inter-service cooperation | TFS, PWS and STT should work with government and each other to continue to pursue a whole-of-state fuel management and burning program that encompasses all land tenures, meets the range of outcomes required by the state (township protection, risk reduction and landscape-scale burns) and is inclusive of private landholders and local communities as well as all fire agencies. |
REC301-2383 | 15 - Inter-service cooperation | Tasmanian Fire Service (TFS), Tasmanian Parks and Wildlife Service (PWS) and Sustainable Timber Tasmania (STT) initiate a discussion among their Australasian peers about good practice around managing new fire starts in remote terrain, to include issues around identification, predictive analysis, risk management and suppression activities. The outcome should be a document which allows for benchmarking to accepted good practice across Australasia, from which Tasmanian fire agencies can develop protocols against which the management of future events can be tested. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4007 | 40 - Equipment and consumables | A measure of safety may be found in the use of high explosives combined with wet tamping, or, still better, water cartridges, instead of powder under any of its modifications. Encouragement ought also to be given to the use of patent multiple wedges and applicances of a like nature, for supplanting the use of explosives. Under all circumstances and conditions some provision should be adopted for compelling workmen to thoroughly undercut, shear, or nick, and generally to work the coal as directed by the Manager. |
REC002-4005 | 40 - Equipment and consumables | Where safety-lamps are used the lock should be of such a character as to prevent any workman opening it. If the "Protector" type of lamp be employed the necessity for a lock is the less necessary, as the unscrewing of this type of lamp extinguishes the light. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1312 | 24 - Govt responsibility | That the Department of Education and Child Development be included as a member of State Emergency Management Council and represented in the State Emergency Centre. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1308 | 24 - Govt responsibility | That the Department of the Premier and Cabinet revise the ministerial documents relating to emergency management. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1291 | 24 - Govt responsibility | That the Flood Reform Task Group, as proposed by the Department |
REC295-1319 | 24 - Govt responsibility | That a single emergency service multi-agency control centre be established with sufficient capacity and capability to deal with all types of emergency incidents in SA. Also consider Police and State Emergency Centre. |
REC295-1288 | 24 - Govt responsibility | That Attorney General’s Department explore options to overcome fatigue and welfare issues of SAGRN staff associated with emergency events of extended duration. |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1318 | 24 - Govt responsibility | That the recommendation made following the Pinery bushfire, ‘to review control facilities at State, region and incident level’, be expanded to include all emergency services facilities that will be utilised for major incidents other than bushfire e.g. flood and earthquake and to also be extended into metropolitan areas, and implemented. |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
REC295-1316 | 24 - Govt responsibility | That the position of Deputy Director, Office for Digital Government is dedicated to the Office for Digital Government; and that people throughout DPC are identified and trained to perform appropriate roles within the State Crisis Centre |
Rec-ID | Code | Recommendation |
---|---|---|
REC294-1364 | 24 - Govt responsibility | The Chairpersons of disaster management groups within the Mackay Disaster District, supported by the Queensland Police Service and Queensland Fire and Emergency Services recommend implementing the Mackay District Improvement Strategy (refer to page 53 of the inquiry). |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2380 | 24 - Govt responsibility | I recommend that the New South Wales Police Force, in conjunction with NSW Health, establish a Fixated Threat Assessment Centre to identify and gather information about fixated persons, assess the risks they pose, and attempt to mitigate such risks through early intervention. |
REC292-2379 | 24 - Govt responsibility | I recommend that the Premier of New South Wales consider whether the Privacy and Personal Information Protection Act 1998 and the Health Records and Information Privacy Act 2002 should be amended to ensure that there is appropriate access to health related information available to ASIO (consistent with recommendation 12 of the report of the Martin Place Siege Joint Commonwealth—New South Wales review) |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1248 | 24 - Govt responsibility | The State Emergency Management Committee to establish a State Bushfire Coordinating Committee as a sub-committee of SEMC. The State Bushfire Coordinating Committee will be chaired by the Director of the Office of Bushfire Risk Management and will have the primary responsibility to: · develop a State Bushfire Management Policy and a set of long term bushfire risk management objectives; · provide a forum for key bushfire risk management stakeholder agencies; · advise the SEMC on matters pertaining to bushfire, in particular, to report against the investment in, and achievement of the bushfire risk management objectives; · provide advice and support to the proposed Chief Officer of the Rural Fire Service on bushfire risk management matters; and · report to SEMC and to the community on bushfire risk management matters on at least an annual basis. |
REC291-1242 | 15 - Inter-service cooperation | The Departments of Fire and Emergency Services and Parks and Wildlife to investigate and adopt an emergency services resource management system that will enable the registration, tasking, tracking, management and coordination of emergency management personnel, vehicles, plant and aircraft. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1210 | 15 - Inter-service cooperation | Co‐designed arrangements that support a unified response to fire |
REC290-1209 | 15 - Inter-service cooperation | Coordinated and targeted mitigation of fire risk |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1180 | 15 - Inter-service cooperation | The Tasmanian fire agencies consider the development of fire operational guidelines to avoid long-term environmental impacts such as: • • • strategies and tactics that will minimise the impact of fire management activities conditions under which earthmoving equipment and fire chemicals may be used information on seasonal conditions and the times of year when various strategies and tactics should be applied, and fuel management strategies. |
REC287-1184 | 24 - Govt responsibility | The Tasmanian fire agencies think more broadly about how staff who are already employed by Government could support the management of future emergencies. |
REC287-1179 | 15 - Inter-service cooperation | The Tasmanian fire agencies develop a joint multi-agency Fire Preparedness Matrix to guide decision-making in response to severe fire weather conditions or capacity issues. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2019 | 24 - Govt responsibility | Assess water supply resilience in the case of an interruption. |
REC286-2053 | 40 - Equipment and consumables | Personal protective equipment (masks, gowns, gloves, goggles) – enhance stocktake methods. |
REC286-2067 | 24 - Govt responsibility | Improve integration of health information systems. |
REC286-2082 | 41 - Emergency Management exercises | Undertake inter-agency severe storm exercises. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2021 | 40 - Equipment and consumables | Review temporary bridge stockpile for adequacy (DSG). |
REC286-2063 | 24 - Govt responsibility | Review Tas Govt interoperability arrangements. |
REC286-2061 | 41 - Emergency Management exercises | Review and exercise the Tasmanian Mass Vaccination Plan. |
REC286-1467 | 15 - Inter-service cooperation | Review the allocation of responsibilities for earthquake risk management. |
REC286-1464 | 41 - Emergency Management exercises | Exercise time-critical decision making processes within the context of an earthquake scenario. |
REC286-2059 | 24 - Govt responsibility | Enhance business continuity planning by the Tasmanian Health Service. |
REC286-2039 | 41 - Emergency Management exercises | Nuance the exercises for flood / dam-break / debris flow to incorporate consideration. |
REC286-1465 | 15 - Inter-service cooperation | Improve the coordination and delivery of the National seismic monitoring program. |
REC286-2078 | 15 - Inter-service cooperation | Review interagency information sharing arrangements. |
REC286-1445 | 41 - Emergency Management exercises | Develop, implement, review and exercise inter-agency community evacuation and recovery plans across the State. |
REC286-2058 | 24 - Govt responsibility | Clarify the relationship between the DHHS and THS in the establishment of flu services. |
REC286-2025 | 41 - Emergency Management exercises | Exercise heatwave arrangements with a focus on the public administration sector and management of vulnerable people |
REC286-2069 | 24 - Govt responsibility | Implement a database management approach for notifiable disease record systems. |
REC286-2014 | 15 - Inter-service cooperation | Integrate non-government entities into emergency response and recovery arrangements. |
REC286-2033 | 24 - Govt responsibility | Incorporate heatwave surge response planning into business continuity planning. |
REC286-2054 | 40 - Equipment and consumables | Personal protective equipment (masks, gowns, gloves, goggles) – review supply/distribution arrangements. |
REC286-2068 | 24 - Govt responsibility | Develop a disaster client record system. |
REC286-2087 | 41 - Emergency Management exercises | Develop and exercise Severe Storm Emergency Management Plan. |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1207 | 33 - Relief and recovery | Communicating in Recovery: The Office of Emergency Management: · considers the development of a communications and engagement strategy for major disaster events · progresses the development of the ‘Communicating In Recovery’ Guideline in the Local Recovery Toolkit. |
REC281-1206 | 33 - Relief and recovery | Transition from Response to Recovery: That Region Emergency Management Committees meet post event to: · consider available impact data · determine the need to establish a Recovery Committee · document the rationale for the decision · advise the Office of Emergency Management of the decision. |
REC281-1204 | 33 - Relief and recovery | Transition from Response to Recovery That the Office of Emergency Management, in consultation with the NSW Police Force Emergency Management Unit develops a template for handover of the Response to Recovery Phase of an emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC274-1404 | 15 - Inter-service cooperation | That the Department of Health & Human Services and the Department of Justice & Regulation, in consultation with their portfolio emergency service agencies that have response time measures, determine relevant targets for these. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1131 | 15 - Inter-service cooperation | That the Emergency Management Australia’s ‘Arrangements for Interstate Assistance (Fire and Emergency Services)’ be applied to all future requests for assistance by the SACFS, SAMFS and SASES. |
REC273-1132 | 15 - Inter-service cooperation | Noting the implementation of Common Incident Command and Control System (CICCS) in SA that fire and emergency services together with police (including through AFAC and ANZPAA), continue to liaise regarding the development of a national incident management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1416 | 24 - Govt responsibility | A state-wide strategy, including a common definition, is developed for identifying and engaging vulnerable people in emergencies. |
REC272-1420 | 24 - Govt responsibility | The Department of Housing and Public Works should consider preparing an annual communique to asset owners of, and local governments with access to public cyclone shelters, outlining the maintenance and certification process and pre-season status. |
REC272-1418 | 24 - Govt responsibility | A state-wide engagement strategy is coordinated to ensure community messaging is consistent across all levels of Queensland’s disaster management arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1156 | 33 - Relief and recovery | Streamlining NDRRA Grants Processes |
REC267-1155 | 33 - Relief and recovery | MP Recovery Reference Group |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1148 | 33 - Relief and recovery | Planning for Recovery Centres Recovery Centres are a proven means of providing support to affected communities. More comprehensive recovery planning is needed at local levels, including the identification of potential Recovery Centre sites in Local EM Plans to help facilitate streamlined establishment of the Centres in future events. Consideration should be given to developing a clear set of standard messaging regarding |
REC267-1163 | 33 - Relief and recovery | Corrections Volunteer Labour Teams |
REC267-1151 | 24 - Govt responsibility | Government Communications Coordination |
REC267-1161 | 33 - Relief and recovery | VIP Visits |
REC267-1149 | 15 - Inter-service cooperation | PES External Surge Program The success of the PES External Surge Program and the willingness of participants to deploy at short notice to support the recovery effort is commendable, as is the readiness of their supervisors to release them from their duties to enable deployment. The Program, supported by an appropriate training program, is one that should be sustained as part of the whole of Government recovery readiness effort. |
REC267-1160 | 33 - Relief and recovery | Transition from Response to Recovery |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1125 | 33 - Relief and recovery | Consultation with the Board of the Lord Mayor’s Distress Relief Fund and other disaster appeal organisers should be undertaken to determine the potential for software development to consolidate the application and approval process, including provision of templates and application forms; |
REC265-1111 | 15 - Inter-service cooperation | All agencies engaged in bushfire response should develop expeditious procedures for the mobilisation of resources in support of other agencies. See discussion in Section 7.1. |
REC265-1106 | 15 - Inter-service cooperation | In addition to regular meetings of the DFES/DPaW Interagency Bushfire Management Committee, the two organisations should use joint exercises to identify agreed firefighting approaches for common or likely scenarios. |
REC265-1127 | 33 - Relief and recovery | Consultation should be undertaken with agencies and organisations that are engaged in emergency welfare provision to identify more effective ways to provide a consistent message to the community that non-cash donations are not required. |
REC265-1105 | 15 - Inter-service cooperation | The Executive Teams of both DFES and DPaW should meet quarterly to review and agree joint improvements relating to issues of interoperability, complementarity and the alignment of firefighting doctrine. The establishment of a unified command in joint State Operations Centre, Regional Operations Centre and Incident Management Teams should be pursued as an overarching goal. |
REC265-1126 | 33 - Relief and recovery | Development of a template contract for the clean-up of affected properties to speed-up the process; |
REC265-1119 | 24 - Govt responsibility | Relevant policies and Westplans should be amended to require that full consultation occurs between the Controlling Agency and the Department for Child Protection and Family Support regarding the location of the evacuation centre(s) in a bushfire incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1073 | 15 - Inter-service cooperation | The State establish, for any future incident, integrated incident management teams with GDF Suez and other Victorian essential industry providers, to: • essential industry providers; and require that emergency services personnel work with GDF Suez and other appropriate • implement the Australasian Inter-service Incident Management System. |
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1095 | 15 - Inter-service cooperation | CFA and VICSES should: explore further opportunities to collaborate with each other. |
Rec-ID | Code | Recommendation |
---|---|---|
REC262-1489 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority reclassifies its State Emergency Communications Centres as critical national infrastructure. |
REC262-1482 | 15 - Inter-service cooperation | That Emergency Management Victoria be responsible for facilitating the interoperability of all organisations involved in emergency response, including the Emergency Services Telecommunications Authority and Ambulance Victoria. |
REC262-1490 | 10 - Infrastructure | That the Emergency Services Telecommunications Authority critically reviews: |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1520 | 33 - Relief and recovery | That the Ministry for Police and Emergency Services urgently review its policies for the provision of disaster welfare services to ensure that in the event of a bush fire emergency and the declaration of a fire under section 44 of the Rural Fires Act 1997, adequate funding and services, especially recovery centres and mental health services, are provided for an adequate length of time, with gradual transition to normal service delivery when those services are no longer required. |
REC261-1507 | 24 - Govt responsibility | That the NSW Government consider enabling the default position during catastrophic and extreme fire danger periods to be the same as for section 44 fires, so that fire control centres have the same systems and resources ready to deploy should a fire break out. |
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1067 | 15 - Inter-service cooperation | That as part of the adoption of such a posture in ‘severe’ or worse fire conditions, the National Parks and Wildlife Service consider alerting, at an early stage, all relevant persons and organisations, such as shire councils, heavy plant operators, the local RFS captains, Fire & Rescue NSW and other emergency services, that it is doing so, and that their assistance may be required at short notice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC259-1046 | 33 - Relief and recovery | That prior to the commencement of any major clean-up, firm policy be established and made known to the extent to which material removal will be the responsibility of the home owner, the Council or the State led recovery effort. |
REC259-1043 | 33 - Relief and recovery | That a single victim registration form be designed, which captures all relevant details required for use by any support agency both in the Response Phase at Evacuation centres and during the Recovery Phase. That such documents when completed form part of a wider database which can be accessed by all relevant agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2526 | 24 - Govt responsibility | The Australian Government develops the State Safety Program into a strategic plan for Australia’s aviation safety system, under the leadership of the Aviation Policy Group, and uses it as the foundation for rationalising and improving coordination mechanisms. |
REC258-2559 | 15 - Inter-service cooperation | The Civil Aviation Safety Authority’s Director of Aviation Safety meet with industry sector leaders to jointly develop a plan for renewing a collaborative and effective Standards Consultative Committee. |
REC258-2561 | 24 - Govt responsibility | The Australian Government amends regulations so that background checks and the requirement to hold an Aviation Security Identification Card are only required for unescorted access to Security Restricted Areas, not for general airside access. This approach would align with international practice. |
REC258-2530 | 24 - Govt responsibility | The Australian Government appoints an additional Australian Transport Safety Bureau Commissioner with aviation operational and safety management experience. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1547 | 15 - Inter-service cooperation | The Marrangaroo Training Area Regional Environmental Officer confer with the local Rural Fire Service at least annually and determine a hazard reduction regime capable of implementation. It is furter recommended all ranges be reviewed in relation to the same issue, that is, that personnel involved in the management of each range under Defence control be directed to confer with local firefighting authorities on at least an annual basis to assess hazard reduction responses to be pursued for that range in subsequent years. |
REC257-1545 | 15 - Inter-service cooperation | Range Control Officer Marrangaroo Training Area liase with the local Rural Fire Service units to develop a map indicating the areas of the range likely to contain unexploded ordnance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1566 | 24 - Govt responsibility | State and territory governments should prioritise and accelerate implementation of the Enhancing Disaster Resilience in the Built Environment Roadmap, including reviewing the regulatory components of vendor disclosure statements. The Land Use Planning and Building Codes Taskforce should be tasked to identify and consider options for regular, low-cost dissemination of hazard information to households by governments and insurers. |
REC256-1561 | 24 - Govt responsibility | State and territory governments should be required to report on the following accountability requirements: |
REC256-1575 | 24 - Govt responsibility | State and territory governments should develop benchmark prices for the reconstruction of essential public assets and submit these to the Australian Government for approval within one year. In developing these prices, they should consult with local governments and relevant experts, and draw on asset management plans. The prices should be reviewed and updated over time. |
REC256-1571 | 24 - Govt responsibility | State and territory taxes and levies on general insurance should be phased out and replaced with less distortionary taxes. |
REC256-1568 | 24 - Govt responsibility | State governments, where they have not already done so, should provide local governments with statutory protection from liability for releasing natural hazard information and making changes to local planning schemes where such actions have been taken ‘in good faith’ and in accordance with state planning policy and legislation. |
REC256-1567 | 24 - Govt responsibility | State and territory governments should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1586 | 15 - Inter-service cooperation | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0794 | 24 - Govt responsibility | Rural Finance Corporation (Department of Treasury and Finance) and Regional Development Victoria should coordinate any future disaster relief and recovery programs for businesses. |
REC250-0793 | 24 - Govt responsibility | The Department of Premier and Cabinet should develop clear guidelines for departments in designing community disaster relief and recovery programs. |
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0896 | 33 - Relief and recovery | That the state level structural arrangements for managing recovery operations are reviewed. |
REC247-0910 | 33 - Relief and recovery | That suitable facilities are established from which to effectively control and coordinate immediate recovery operations. |
REC247-0928 | 24 - Govt responsibility | That the Government take into account demographic change in its assessment of the consequences of climate change on emergency events. |
REC247-0948 | 15 - Inter-service cooperation | That the Department of Justice conduct an independent review to develop a suitable model for integrated and interoperable emergency management arrangements in Tasmania. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0907 | 33 - Relief and recovery | That the State Emergency Management Committee ensures that a program of debriefing on recovery issues is completed by all relevant agencies and organisations, and detailed plans and operating procedures are established ready for implementation. |
REC247-0854 | 15 - Inter-service cooperation | That in multi-agency response and recovery operations, arrangements be made so it is unambiguous who is in charge of these operations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2598 | 24 - Govt responsibility | That government considers the establishment of a separate unit to implement and operate a Whole of Government network if existing stakeholders fail to make significant progress toward an agreed Whole of Government solution. |
REC245-2596 | 24 - Govt responsibility | That the Whole of Government project’s objectives should include meeting entity requirements and the consultant be asked to reevaluate the revised set of objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0836 | 24 - Govt responsibility | That the Government explore as a matter of priority the transitioning to St John Ambulance SA Ltd providing non-emergency ambulance carriage services in South Australia, and be appropriately funded for doing so. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2638 | 24 - Govt responsibility | That the Government explore as a matter of priority the transitioning to St John Ambulance SA Ltd providing non-emergency ambulance carriage services in South Australia, and be appropriately funded for doing so. |
REC242-2646 | 24 - Govt responsibility | That the State Government give high priority to liaising with interstate and Federal processes, and offer to take a lead, on changing the climatic and fire rating arrangements to ensure these match the conditions that can create dangerous bushfire conditions at short notice. |
REC242-2639 | 24 - Govt responsibility | That the Government’s Workers Rehabilitation and Compensation (SAMFS Firefighters) Amendment Bill be amended to include Country Fire Service firefighters alongside Metropolitan Fire Service firefighters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1001 | 24 - Govt responsibility | That the extent of forest and plantation fuel load fire risk in South East Queensland requires a designated government resources fire team to manage this risk and proactively conduct fuel mitigation burning; and provide a wildfire response to government land. |
REC241-0979 | 24 - Govt responsibility | That the Queensland Government liaise with the Federal Government with a view to securing incentives for employers that recognise loss of income and employee time for emergency operations. |
REC241-0954 | 24 - Govt responsibility | That a Ministerial Advisory Council be established to inform the Minister of matters relating to Rural Fire Service and SES volunteers. |
REC241-1004 | 15 - Inter-service cooperation | That a memorandum of understanding be developed between RFSQ and other organisations with fire fighting capacity at state level, to establish operational procedures when these organisations may be required for a joint response roles. Specifically, the intent will be: Vegetation Fire in a Rural Area: The Rural Fire Brigade in that area (boundary) is in charge and is the first Brigade called by Firecom. Structural Fire in a Rural Area: Firecom calls the Urban Brigade first and they control the incident. Local Rural Fire Brigade must also be notified by Firecom at the same time. Vegetation Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. At their discretion they may call Rural Fire Brigades for assistance. Structural Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2661 | 24 - Govt responsibility | That Queensland Corrective Service remains a separate program within the Department of Justice and Attorney-General so that while opportunities for improved services and efficacy can be realised, there is a clear separation from the youth justice services. |
REC239-2782 | 24 - Govt responsibility | That transparency of the Ministerial direction be achieved through publishing and monitoring for effectiveness. |
REC239-2686 | 24 - Govt responsibility | That primacy of control should rest with the State Disaster Coordinator. This position should, by default, be the Deputy Commissioner, Regional Operations, Queensland Police Service. |
REC239-2708 | 24 - Govt responsibility | That the role of the Inspector General Emergency Management not extend to conducting reviews on behalf of agencies and that the role consider the effectiveness of all agencies and how their work contributes to a whole of Government response. |
REC239-2660 | 24 - Govt responsibility | That Queensland Corrective Services be transferred to the Department of Justice and Attorney-General by a machinery-of-Government change as soon as is practicable. |
REC239-2759 | 24 - Govt responsibility | That the new Chief Executive Officer Portfolio Business be accountable for delivering the reformed Communications Centre arrangement by the 2017–18 financial year in time for the Commonwealth Games of 2018. |
REC239-2762 | 15 - Inter-service cooperation | That the Chief Executive Officer Portfolio Business in consultation with the Police Commissioner and the Commissioner Fire & Emergency Services should provide the direction for future information and communication technology strategies and acquisitions. |
REC239-2685 | 24 - Govt responsibility | That primacy of control for disaster operations remains with the Queensland Police Service and be reinforced. |
REC239-2701 | 24 - Govt responsibility | That the Inspector General Emergency Management provide continuing advice to Government on the level of interoperability in disaster management arrangements, as well as the level of interoperability being achieved within the new portfolio. |
REC239-2657 | 24 - Govt responsibility | That negotiation takes place between Queensland Health and the Queensland Ambulance Service to determine the broad governance requirements of any such arrangements. |
REC239-2749 | 24 - Govt responsibility | That the Prostitution Licensing Authority be moved to the Department of Justice and Attorney General Office of Fair Trading. |
REC239-2761 | 15 - Inter-service cooperation | That systems development in the Queensland Police Service capitalises on the advances made by the Queensland Fire and Rescue Service in recent years. |
REC239-2679 | 24 - Govt responsibility | To remove the Queensland Ambulance Service and Queensland Corrective Services from the Department of Community Safety—we recommend that it be renamed the Department of Fire and Emergency Services and be led by a Commissioner. |
REC239-2700 | 24 - Govt responsibility | That the position of Inspector General Emergency Management (in addition to some of the responsibilities of the chief executive officer under the current Disaster Management Act 2003) will: |
REC239-2655 | 24 - Govt responsibility | That the Queensland Ambulance Service is transferred to Queensland Health by a machinery-of-Government change as soon as is practicable and that the Commissioner report directly to the Director General Queensland Health. |
REC239-2732 | 24 - Govt responsibility | There be a formation of an Office of Portfolio Business, providing support and governance across a range of corporate functions, which are essential to the delivery of frontline services. The Review team considers that the functions of the Operations Business and Strategy Directorate should become part of that Office and that any exception should be carefully considered by those charged with implementation of approved recommendations. |
REC239-2703 | 15 - Inter-service cooperation | That the protocols developed by the Queensland Police Service and SES for operations define the respective roles and responsibilities as well as recognise the varying capabilities of SES units across the State. |
REC239-2678 | 24 - Govt responsibility | That probation and parole should continue to work together with the Queensland Police Service to reduce the risk of reoffending and reduce crime. |
REC239-2699 | 24 - Govt responsibility | That the Minister establish a public sector office to be headed by an Inspector General of Emergency Management. The Inspector General of Emergency Management will be responsible for most of the functions listed under part 16A of the current Disaster Management Act 2003. |
REC239-2721 | 24 - Govt responsibility | That the Chief Executive Officer Portfolio Business collaborate with the two portfolio Commissioners to: |
REC239-2694 | 15 - Inter-service cooperation | That Queensland enters into a similar arrangement with Bureau of Meteorology to have an experienced forecaster seconded to Kedron State Disaster Coordination Centre for at least the duration of fire and storm seasons. |
REC239-2662 | 24 - Govt responsibility | That responsibility for prisoner transport and non-managerial roles within the larger watch-houses is transferred to Queensland Corrective Service. |
REC239-2687 | 24 - Govt responsibility | That funding, staffing and responsibility associated with administration of the NDRP be transferred from Emergency Management Queensland to the Department of Local Government, Community Recovery and Resilience. |
REC239-2712 | 24 - Govt responsibility | That Emergency Management Queensland be integrated with the current Queensland Fire and Rescue to become the Department of Fire and Emergency Services. |
REC239-2667 | 15 - Inter-service cooperation | That Queensland Corrective Service, the Queensland Police Service and Queensland Health should work together to develop a position that enables prisoners to have timely access to their prescribed medication despite travel between facilities and without the need for costly re-prescription. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0806 | 33 - Relief and recovery | Review the adequacy of current arrangements for infrastructure reconstruction following a major flood event in the Hawkesbury-Nepean Valley. |
REC238-0805 | 33 - Relief and recovery | Develop a Hawkesbury-Nepean Flood Recovery Plan, which identifies strategies and arrangement for recovery from severe floods in the Hawkesbury-Nepean Valley. |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1596 | 24 - Govt responsibility | Department of Broadband, Communications and the Digital Economy to review the content of the Government’s digital business website at www.digitalbusiness.gov.au and liaise with the Department of Industry, Innovation, Climate Change, Science, Research and Tertiary Education, which manages the www.business.gov.au, to ensure these business advice sites provide appropriate information regarding business continuity planning in the event of telecommunications outages. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2824 | 41 - Emergency Management exercises | The Australian Department of Health and Ageing consult with members of the general public or representatives of health consumers in the pandemic planning process, including in pandemic exercises designed to test the ability of government to respond to a pandemic event. Consumer involvement should include testing the ability of any communication strategy designed to inform and engage consumers about a pandemic event. |
REC232-2822 | 41 - Emergency Management exercises | The Australian Government test Australia’s ability to respond to a widespread outbreak of infectious disease other than influenza, by undertaking a pandemic exercise across the relevant Commonwealth, state and territory government agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC230-2831 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate 20 MHz of contiguous spectrum in the 700 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2833 | 10 - Infrastructure | If recommendation 1 is not supported by the Australian Government, the committee recommends that the Minister for Broadband, Communications and the Digital Economy issue a Ministerial Direction to the Australian Communications and Media Authority to allocate as a minimum requirement, 20 MHz in the 800 MHz band for the purposes of a public safety mobile broadband network. |
REC230-2832 | 10 - Infrastructure | The committee recommends that the Minister for Broadband, Communications and the Digital Economy take appropriate measures to secure, for public service agencies, priority access to an additional 10 MHz of spectrum in the 700 MHz band for public safety purposes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2845 | 24 - Govt responsibility | The committee recommends that the Commonwealth government works with state and territory governments to continue to implement the recommendations of the Productivity Commission report, where possible, to improve coordination in relation to climate change adaptation. |
REC229-2844 | 15 - Inter-service cooperation | The committee recommends that Australian governments specifically address issues of compatibility and capacity to facilitate the most effective interoperability of emergency service organisations and their key personnel, especially for fire services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1605 | 24 - Govt responsibility | The Justice and Community Safety Directorate should continue to review its strategic and accountability indicators and the Territory and Municipal Services Directorate should commence a review of its strategic and accountability indicators. The directorates should consult to develop complementary measures which better assess their bushfire management activities. |
REC228-1623 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should develop and routinely review a strategic bushfire capability for the ACT. The contribution of ACT Fire and Rescue (including the Community Fire Units) and the ACT Rural Fire Service (including Parks Brigade) should be explicitly stated. |
REC228-1622 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should continue to improve working arrangements between the ACT Rural Fire Service Parks Brigade and the ACT Rural Fire Service headquarters, by: |
REC228-1618 | 24 - Govt responsibility | The Emergency Services Agency, the Environment and Sustainable Development Directorate and the Territory and Municipal Services Directorate should strengthen across-Government delivery of major projects in the Strategic Bushfire Management Plan and Regional Fire Management Plans by collectively: |
REC228-1610 | 24 - Govt responsibility | The Emergency Services Agency should annually review fire management zones and the Territory and Municipal Services Directorate should subsequently update the Regional Fire Management Plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2847 | 15 - Inter-service cooperation | I recommend that Border Protection Command implement a surveillance strategy, possibly with the assistance of other Commonwealth authorities and organisations on the island such as the AFP, which heightens its coverage at times when the weather and sea conditions are rough. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0568 | 24 - Govt responsibility | State-wide all agency reporting should be established to facilitate the interactions of emergency management agencies, support agencies and governments. |
REC226-0548 | 15 - Inter-service cooperation | Inter-agency cooperation to manage fire precincts in a tenure-blind fashion is necessary for effective fire suppression. |
REC226-0596 | 33 - Relief and recovery | An early decision on relief funding enables timely responses. D CP should review their communication of relief arrangements to ensure that they are clear. |
REC226-0595 | 33 - Relief and recovery | Shire experiences in managing these traumatic events should be captured and passed into emergency management procedures. |
REC226-0594 | 33 - Relief and recovery | Procedures to resolve issues surrounding financial assistance need to be reviewed to ensure they are as smooth, fast and transparent as possible possible. Review and streamline current financial relief procedures. |
REC226-0581 | 24 - Govt responsibility | Increased acceptance of mutual obligations will be fundamental to the management of fire risk across the state |
REC226-0578 | 15 - Inter-service cooperation | There would be benefit in progressively aligning the geographic boundaries of each of the agencies and seeking to co-locate their headquarters within those boundaries. |
REC226-0571 | 24 - Govt responsibility | A review of the manner in which resourcing is conducted across all agencies needs to occur with a review identifying the best manner to ensure all agencies adapt to the same process. |
REC226-0560 | 15 - Inter-service cooperation | There would be value in progressively aligning the geographical boundaries of emergency management agencies and co-locating where possible within regions and districts. |
REC226-0598 | 33 - Relief and recovery | When communities are grieving there is a need to provide special forms of support to affected residents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC224-1631 | 24 - Govt responsibility | The State Government prepare a strategy before the 2013-14 bushfire season on how the main firefighting agencies should deal with a drier South West region where fewer prescribed burns can be completed each year. |
REC224-1629 | 24 - Govt responsibility | The Minister for Emergency Services must ensure that future post-incident analyses are completed and made public within eight weeks of a natural disaster. |
REC224-1634 | 10 - Infrastructure | The Minister for Emergency Services should urgently review the technical issues with the Western Australia Emergency Radio Network program that is forcing the State’s firefighters to revert to their older radio networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1861 | 41 - Emergency Management exercises | The Ministers for Health, Emergency Services, Environment and Police provide additional funds to their agencies so that a detailed exercise is held on a regular basis based on a disaster that will create the worst outcome for the State. |
REC222-1857 | 15 - Inter-service cooperation | The Ministers for Health, Police, and Emergency Services ensure that the Western Australia Police, the Fire and Emergency Services Authority and St John Ambulance establish a formal platform to share their knowledge and experience in delivering programs to their staff and volunteers to address issues of stress from disasters and critical incidents, as is done in other Australian jurisdictions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1880 | 24 - Govt responsibility | Regulators can help to achieve improved outcomes by involving fire services in the planning and licensing processes |
REC215-1874 | 15 - Inter-service cooperation | Fire services can improve outcomes by working with EPA as the regulator and licensing authority to achieve improved compliance with the required outcomes specified in the BPEM guidelines |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1639 | 40 - Equipment and consumables | An equipment replacement schedule for all Bushfires NT equipment be developed. |
REC209-1654 | 24 - Govt responsibility | That the Director Bushfires NT NOT be appointed as a member of Council. |
REC209-1644 | 41 - Emergency Management exercises | A regular program that tests fire based incidents of command, control and coordination of operational procedures using scenario planning, training simulations and coordination of emergency responses between NTFRS, NTES and NT Police be instituted. |
REC209-1638 | 40 - Equipment and consumables | The Assets and Equipment Register be reviewed prior to each fire season. |
REC209-1637 | 40 - Equipment and consumables | Implement maintenance schedules for all common assets and shared equipment. |
REC209-1671 | 15 - Inter-service cooperation | That Bushfires NT, NTFRS, DLP, Weeds Branch, Parks and Wildlife, the Natural Resources Management Board, Biodiversity staff and representatives of the Volunteer Fire Brigades get together, at least annually, to coordinate planning efforts for peri-urban areas. |
REC209-1636 | 40 - Equipment and consumables | Update the Asset and Equipment Register for all assets and equipment. |
REC209-1669 | 15 - Inter-service cooperation | Conduct an information sharing and planning exercise between Bushfires NT and NTFRS to explore the current boundaries and the overlaps in the peri-urban areas between the NTFRS ERA and the Bushfires NT areas of responsibility for all major centres in the NT. |
REC209-1635 | 40 - Equipment and consumables | Conduct a stocktake of all assets and equipment in all regions for Bushfires NT and Volunteer Brigades. |
REC209-1640 | 40 - Equipment and consumables | Conduct a stocktake of all PPE and implement a top up program to bring all PPE to a fully operational standard. |
REC209-1660 | 24 - Govt responsibility | Better alignment between divisions within DNRETAS be achieved through the development of an integrated strategy that addresses the combined objectives of weed management, land management, carbon farming and biodiversity management using fire across the Territory. |
REC209-1651 | 15 - Inter-service cooperation | Review the membership of the Bushfires Council, and the composition of Regional Committees to ensure that the Council and Committees have representational stakeholders. |
Rec-ID | Code | Recommendation |
---|---|---|
REC206-1884 | 24 - Govt responsibility | The Committee recommends that the Australian Parliament pass the Insurance Contracts Amendment Bill 2011 and ensure its enactment by 1 July 2012. The Committee further recommends that the standard definition of ‘flood’ be included in the definition of Standard Cover in the Insurance Contracts Regulations 1985. |
REC206-1888 | 24 - Govt responsibility | The Committee recommends that the Australian Government empower the Australian Securities and Investments Commission to regulate claims handling and settlement of financial service providers. This can be achieved by the Treasurer introducing legislation by 1 July 2012 to give effect to the measures contained in Schedule 1, Part 1 of the lapsed Insurance Contracts Amendment Bill 2010, so that breaches of the duty of utmost good faith in relation to claims handling constitute a breach of the Insurance Contracts Act. |
REC206-1885 | 24 - Govt responsibility | The Committee recommends that the Australian Government introduce legislative changes required to remove the exemption for general insurers to unfair contract terms laws, and ensure its enactment by the end of 2012. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1904 | 24 - Govt responsibility | State and territory taxes and levies on general insurance constitute a barrier to effective adaptation to climate change. State and territory governments should phase out these taxes and replace them with less distortionary taxes. |
REC205-1899 | 24 - Govt responsibility | Local governments’ uncertainty about their legal liability is a barrier to effective climate change adaptation. State governments should clarify the legal liability of councils with respect to climate change adaptation matters and the processes required to manage that liability. |
REC205-1898 | 24 - Govt responsibility | To help clarify roles and responsibilities of local government for climate change adaptation, the state and Northern Territory governments should publish and maintain a comprehensive list of laws that delegate regulatory roles to local governments. This would assist both state and local governments to assess whether local governments have the capacity to discharge their roles effectively. |
REC205-1896 | 24 - Govt responsibility | Australian governments should implement policies that help the community deal with the current climate by improving the flexibility of the economy. This would also build adaptive capacity to deal with future climate change. This includes reforms to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1914 | 15 - Inter-service cooperation | FESA, WA Police and St John Ambulance establish a uniform protocol for handling multiple agency emergency responses that does not involve callers having to make multiple calls to 000. |
REC204-1915 | 24 - Govt responsibility | The Department of Regional Development and Lands should ensure that event organisers and government agencies responsible for sponsoring and approving events have a greater level of awareness about the requirements of section 91 licences under the Land Administration Act 1977 (WA). |
REC204-1911 | 24 - Govt responsibility | As part of the review of its due diligence processes, Tourism WA should ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0298 | 15 - Inter-service cooperation | The state should progressively align on a shared platform, such as WebEO C , to establish a Common Operating Picture (COP). |
REC203-0288 | 15 - Inter-service cooperation | The State Duty Officer from DEC and the State Duty Director, FES A need to confer whenever a Level 2 or 3 incident is declared to satisfy themselves that they have appropriate incident management structures and resources across the state are at an appropriate level of preparedness. |
REC203-0287 | 15 - Inter-service cooperation | On a regional basis there would be value in closer working relationship between DEC crews and VBFBs to build mutual trust and confidence. This could be done by opportunity engagement of VBFBs in DEC fire management or through exercises. |
REC203-0301 | 15 - Inter-service cooperation | Early in an incident, close and effective liaison needs to be established with local government agencies. |
REC203-0308 | 33 - Relief and recovery | Early resolution and clear communication of the financial and other support measures that will be available to affected residents is an important contributor to community resilience. |
REC203-0299 | 15 - Inter-service cooperation | The state should converge on a single communications platform for all emergency management and support agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0503 | 24 - Govt responsibility | The Minister for Police and Emergency Services and the Minister for the Environment report to Parliament by December each year as to the state of readiness of the main State Government agencies tasked with fighting bushfires. |
REC202-0504 | 15 - Inter-service cooperation | The Minister for Emergency Services ensure that the annual budget of FESA contains the funds it requires to coordinate an annual multi-agency bushfire field exercise, alongside other desktop exercises, to be held in different regions of the State each year. The outcomes of this field exercise should be included in the proposed annual Ministerial statement to Parliament on bushfire readiness before each season. |
REC202-0500 | 24 - Govt responsibility | In implementing the Keelty Report’s Recommendation 42, the Ministers for Emergency Services and Environment jointly report to Parliament by May 2012 on the likely impacts on, and implications for, the future bushfire operations of the State Government of the drying climate in the State’s South West region. |
REC202-0498 | 24 - Govt responsibility | The Minister for Planning report to Parliament by May 2012 on the urgent actions undertaken by the Department of Planning and the Western Australian Planning Commission (WAPC) to transfer responsibility for declaring bushfire prone areas to the WAPC. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0260 | 15 - Inter-service cooperation | There are a range of opportunities identified from reviewing the three fires that will improve coordination between FESA and DEC, requiring limited resources, potentially generating some efficiencies and reflecting a joint, tenure blind approach to fire management in WA. The MIR acknowledges the progress made through the IBMC in these matters and notes these measures will require ongoing strong leadership. These include: · Clarification and consistent application of the Zone 2 and 2A mobilisation protocols; · Duplicating available information on websites; · Establishing a single State air desk and cross-utilising Air Attack Supervisors; · Completing common training for the conduct of public meetings;· Coordinating IMT training and exercises; · Operating joint IMT‘s during interface fires; FESA utilising the DEC mobile ICC when suitable ICPs are not available; · FESA engaging in daily weather teleconferences with DEC; Engaging a permanent BoM officer to support a common FESA and DEC SOC; · Developing a common ‗Tool Box‘ of forms and operational procedures for fire response; · Developing common jurisdictional arrangements to accommodate interstate support; · Developing a joint FESA/DEC SOC at the new (FESA) Emergency Services facility at Cockburn; · Adopting common and transparent Level 3 IC accreditation · Using a single mapping capability across both agencies and · Using common naming conventions for fires. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0379 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-1726 | 41 - Emergency Management exercises | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. |
REC200-1708 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Western Australian Police ensure they receive all necessary legal clarification in relation to Bushfire Responsibilities of Police Officers – Powers Used in Assisting Fire Authorities in Responding to Bushfires, to be promulgated across FESA and WAPOL. |
REC200-1728 | 24 - Govt responsibility | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-1699 | 24 - Govt responsibility | The State Government ensure that the continued development of the Fire and Emergency Service Authority's Integrated Bushfire Risk Management System is dependent on an independent comparative assessment of its functionality and cost-effectiveness against the Spatial Support System used by the Department of Environment and Conservation. |
REC200-1680 | 15 - Inter-service cooperation | Emergency Management Western Australia establish an inter-agency working group to continue the development of the new single emergency services Act. |
REC200-1727 | 24 - Govt responsibility | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-1712 | 10 - Infrastructure | FESA and local governments jointly review radio communications capability prior to the 2011/12 bushfire season with a view to improving the current delivery of service to firefighters. |
REC200-1694 | 24 - Govt responsibility | The State Government give its full support to the Western Australian Local Government Association's Send to Solve initiative. |
REC200-1679 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-1723 | 24 - Govt responsibility | The State Government restructure the Fire and Emergency Services Authority as a Department. As part of this restructure, Emergency Management Western Australia should either |
REC200-1682 | 24 - Govt responsibility | The State Government give legislative effect to the Planning for Bush Fire Protection Guidelines. |
REC200-1719 | 24 - Govt responsibility | The State Government recognise the projected changes in climate and potential impact on future fire events. |
REC200-0373 | 33 - Relief and recovery | The Department for Child Protection, the Western Australian Police and the Fire and Emergency Services Authority develop improved arrangements for communicating the loss of home and possessions to persons gathered at evacuation centres with a view to increasing privacy. |
REC200-0386 | 15 - Inter-service cooperation | Emergency service agencies undertake more consultation and joint exercising involving the Fire and Emergency Services Authority, the Department of Environment, the Western Australian Police, the Department for Child Protection, local governments and volunteers – including Volunteer Bush Fire Brigades. This should include field exercises which test: Evacuation centres Critical infrastructure (including at the local level) Traffic management, including road blocks. Consideration should also be given to involving the community in exercising (see Recommendation 7) and using prescribed burns as exercises (see Recommendation 14) More detailed planning for exercises should be included in a revised WESTPLANBUSHFIRE to be endorsed by the State Emergency Management Committee. |
REC200-1681 | 24 - Govt responsibility | The State Government transfer responsibility for declaring bushfire prone areas from local government to the Western Australian Planning Commission. The Western Australian Planning Commission should urgently assess those areas that should be declared bushfire prone. |
REC200-1717 | 24 - Govt responsibility | The State Government mandate that the title deeds for relevant properties be amended to indicate if the property is in a declared bushfire prone area. |
REC200-0338 | 15 - Inter-service cooperation | The Fire and Emergency Services Authority and the Department of Environment and Conservation develop and finalise their Memorandum of Understanding and commit to working in partnership. |
REC200-1716 | 24 - Govt responsibility | State and locals governments: |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0466 | 24 - Govt responsibility | the Departments of Health and Human Services finalise the definition of ‘vulnerable person’ and the list of facility types where vulnerable people are located and ensure that the definition and associated policy(ies) are applicable across ‘all hazards’. |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0465 | 24 - Govt responsibility | the state undertake major reform of Victoria’s emergency management arrangements to bring about an effective ‘all hazards, all agencies’ approach, incorporating: • clarity of command and control in all emergencies • common operating platforms, including communications and information technology • interoperability between all agencies • regular joint training and exercising by all agencies • the development and implementation of performance standards for each emergency management agency • the development and maintenance of effective planning arrangements at all levels of emergency management • a meaningful monitoring and audit regime for designated standards and planning requirements; and • an effective accountability mechanism to support the maintenance of legislative and other agency obligations. |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0455 | 24 - Govt responsibility | the state conduct an ‘all hazards’ needs analysis to determine requirements for level 3 Incident Control Centres with a focus on ‘all hazards’ and multi-agency capability. Following this analysis, the state take steps to ensure the availability of sufficient and functional level 3 Incident Control Centres across the state with an ‘all hazards’ and multi-agency capability |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0451 | 15 - Inter-service cooperation | the state ensure, as a matter of priority, that the State Control Centre is able to function as a fit for purpose, multi-agency emergency management centre. Necessary works to achieve this outcome should have an overarching focus on the implementation of common agency systems and processes to the fullest extent possible. |
REC199-0406 | 24 - Govt responsibility | the state expand the Regional Water Monitoring Partnerships model to include all flood warning gauges. |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0400 | 24 - Govt responsibility | The state take the necessary measures to clarify roles, responsibilities and cost-sharing arrangements for flood warning systems, including tasking state and regional bodies to be responsible for the flood warning system. This will require engaging with the commonwealth to amend the 2001 arrangements, updating the 1998 floodplain management strategy accordingly and continuing to support commonwealth initiatives designed to improve flood mapping standards and associated issues. |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0481 | 24 - Govt responsibility | the state (consistent with recommendation 46) develop a model for determining the capability and capacity of departments and agencies with roles and responsibilities in large scale or protracted emergencies. The issues of capability and capacity should be addressed at all levels of emergency management planning. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2903 | 15 - Inter-service cooperation | The CFA works with MFB to ensure that the MFB control unit is available for responding to large fires and multi-agency incidents in fringe CFA areas |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0327 | 15 - Inter-service cooperation | The Fire Services Commissioner ensures that the inter-relationship between Information Sections at all levels is understood. |
REC195-0318 | 15 - Inter-service cooperation | The Fire Services develop a joint protocol for each Fire Service to notify the other of fires reported from fire towers |
REC195-0309 | 15 - Inter-service cooperation | The Fire Services, and other emergency management agencies, use the Tostaree fire as a scenario exercise to improve understanding of fast-running fires and enhance interoperability and control strategies |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
Rec-ID | Code | Recommendation |
---|---|---|
REC190-1928 | 24 - Govt responsibility | That the Queensland Reconstruction Authority finalise the value for money policies and procedures, particularly those that take into account the role and responsibilities of the external service providers. |
REC190-1927 | 24 - Govt responsibility | That the Queensland Reconstruction Authority agree on and finalise the work plan and attach it as a Schedule to the Agreement as required in section 15 of the Agreement. |
REC190-1926 | 24 - Govt responsibility | That the Queensland Reconstruction Authority clarify and communicate the roles of the Lines of Reconstruction sub-committees to the Chairs of each committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC188-2917 | 33 - Relief and recovery | The committee recommends that relevant Commonwealth agencies continue to monitor the wellbeing of their personnel and that counselling and support services should be provided for as long as necessary. |
REC188-2916 | 33 - Relief and recovery | The committee recommends that the Department of Regional Australia and DIAC liaise with the Christmas Island community to explore options for a permanent memorial to be erected on the island, at a site of the residents' choosing, for the victims of the tragedy. |
REC188-2915 | 33 - Relief and recovery | The committee recommends that Department of Immigration and Citizenship (DIAC) and its relevant contractors continue to monitor the wellbeing of the survivors and that counselling and support services should be provided for as long as is necessary. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0118 | 15 - Inter-service cooperation | A Memorandum of Understanding signed by the Chief Executives of DEC and FESA would be a valuable statement of joint commitment between the two agencies. |
REC183-0117 | 15 - Inter-service cooperation | The Interagency Bushfire Management Committee and its sub-committees are the logical central platform for developing and strengthening future joint bushfire strategies and common systems of work between bushfire management agencies in Western Australia. |
REC183-0116 | 15 - Inter-service cooperation | Triggers and a process for transfer of command and control from DEC to FESA should be developed and documented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0135 | 33 - Relief and recovery | FESA revises its standard operating procedures to provide guidance on the format and timing of post-incident community meetings. |
REC182-0129 | 15 - Inter-service cooperation | FESA maintains inter-agency relationships and arrangements, and develops formalised arrangements across the entire emergency management cycle for joint activities such as training, exercises and procedure development. |
REC182-0125 | 15 - Inter-service cooperation | FESA, in partnership with other agencies and the community, develops Western Australia’s urban interface fire fighting capability and capacity. |
REC182-0124 | 15 - Inter-service cooperation | FESA and DEC take a whole of capability approach to joint operations, including developing joint doctrine that provides a common and articulated understanding of roles and responsibilities, resources and capabilities |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0172 | 15 - Inter-service cooperation | The Country Fire Authority and the Department of Sustainability and Environment standardise their operating systems and information and communications technologies with the aim of achieving greater efficiency and interoperability between agencies. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
Rec-ID | Code | Recommendation |
---|---|---|
REC179-2976 | 41 - Emergency Management exercises | The Department of Human Services should regularly test recovery plans with partner agencies. |
REC179-2983 | 24 - Govt responsibility | The Department of Human Services should work with the State Emergency Recovery Planning Committee, regions, and other partners to facilitate understanding and ownership of roles and responsibilities for common recovery services. |
REC179-2980 | 24 - Govt responsibility | The Department of Human Services should work with regions and partner agencies at the state level to create consistent, streamlined impact assessment processes and systems. |
REC179-2979 | 24 - Govt responsibility | The Department of Human Services should communicate strategic priorities to achieve state and regional level alignment in building recovery capacity and capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0139 | 10 - Infrastructure | Subject to the findings of the Productivity Commission, the Commonwealth examine options for the funding of replacement of power infrastructure that presents an unacceptable bushfire risk. |
REC176-0138 | 10 - Infrastructure | The Productivity Commission undertake an examination of bushfire risk from ageing power infrastructure, including an assessment of replacement costs and likely suppression costs from bushfires caused by defective infrastructure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0103 | 24 - Govt responsibility | That the Minister for Emergency Services consider the appointment of the Chief Executive Officer, Department of Environment and Conservation as a member of the State Emergency Management Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0022 | 15 - Inter-service cooperation | The declaration of a potential Level 3 incident should be notified to FESA who can facilitate an early warning to CFCO’s in the Shire and surrounding LGA’s. |
Rec-ID | Code | Recommendation |
---|---|---|
REC170-0058 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure that all agencies can access other agencies’ operations centres when needed and that the procedures to do so are documented |
REC170-0050 | 24 - Govt responsibility | SEMC and EM WA should: assess the state’s level of preparedness at least annually, identifying gaps and significant risks |
REC170-0049 | 24 - Govt responsibility | SEMC and EM WA should: formally and regularly assess which hazards the state should prepare for |
REC170-0059 | 15 - Inter-service cooperation | SEMC and EM WA should: ensure all agencies use the same approach to managing incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC169-2990 | 24 - Govt responsibility | The Department of Premier and Cabinet should clarify the roles and responsibilities of departments and agencies under Part 6 of the Act and CIP framework to reduce confusion and gaps. |
REC169-2995 | 24 - Govt responsibility | The Department of Premier and Cabinet, in consultation with Victoria Police, should develop clear guidance to distinguish between declared essential services and critical infrastructure to assist departments, Victoria Police and industry in implementing Part 6 of the Act and the CIP framework more effectively. |
REC169-2994 | 24 - Govt responsibility | Representatives of lead departments should obtain necessary security clearances so appropriate officers can access information relevant to their sectors. |
REC169-2993 | 24 - Govt responsibility | The Department of Premier and Cabinet should clarify the requirements in relation to establishing Security and Continuity Networks in designated sectors, so that there is a shared understanding of those requirements. |
REC169-2992 | 24 - Govt responsibility | The Department of Premier and Cabinet should identify risks arising from the joined-up nature of the approach to protecting essential services and critical infrastructure, and to assist departments and agencies to develop associated risk management arrangements at the whole-of-government level. |
REC169-2991 | 24 - Govt responsibility | The Department of Premier and Cabinet should provide definitive guidance on identifying essential services for declaration to better inform relevant departments in discharging their responsibilities under Part 6 of the Act. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3007 | 15 - Inter-service cooperation | That Tasmania Fire Service implement Recommendation 5 above; and that Aurora continue to co-operate with that Service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0096 | 15 - Inter-service cooperation | The Department of Community Safety and Councils develop MOUs to reflect the genuine partnership that exists in present arrangements including an emphasis on the use of the agreed State disaster arrangements to task and deploy SES units following State/Local consultation. |
REC165-0097 | 24 - Govt responsibility | Revised governance arrangements be implemented involving Disaster Management Groups at the three levels supported by EMQ as outlined in this report to achieve continuous improvement in the Disaster Management arrangements in the State. A new provision in Section 5 emphasise the discretion available to all involved in the Disaster Management system to take action to prevent impending loss of life even if contrary to the agreed arrangements. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
REC165-0098 | 24 - Govt responsibility | The SDMG take into account key improvement initiatives and change processes suggested when deciding on an effective implementation strategy for agreed recommendations. |
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3035 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources liaise with Ministers with environmental and planning responsibilities, and if necessary Council of Australian Governments, to ensure that environmental requirements for oil and gas projects are not imposed subsequent to safety assessments and do not increase the risk of major accident events. |
REC161-3028 | 24 - Govt responsibility | That Ministerial Council on Mineral and Petroleum Resources continue to support a duty of care safety case regime for best practice offshore petroleum industry regulation augmented to include regulation of integrity. Since the safety case is at the centre of the duty of care co-regulatory regime, we consider that the requirement for the implementation of the safety case at facilities involved in the exploitation of petroleum resources should be provided for within the Offshore Petroleum and Greenhouse Gas Storage Act 2006 itself. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3448 | 24 - Govt responsibility | That the Director of Marine Safety works with the Australian Maritime Safety Authority to ensure that State and port emergency arrangements interface appropriately with the National Maritime Emergency Response Arrangements. |
REC158-3433 | 24 - Govt responsibility | That Harbour Masters are employed by a government body and remain geographically located at the port. |
REC158-3447 | 15 - Inter-service cooperation | That emergency services are required to work directly with port/channel managers and the nominated marine safety authority to ensure that a training and exercise regime is established to enable emergency services personnel to develop and maintain the skills and knowledge relevant to marine emergency management. |
REC158-3446 | 15 - Inter-service cooperation | That emergency services are required to work directly with port/channel managers and the nominated marine safety authority to identify and ensure availability of marine resources necessary for emergency services to meet their statutory obligations in responding to marine emergencies (this recommendation should be read in conjunction with recommendation 26 & 27). |
REC158-3445 | 15 - Inter-service cooperation | That emergency services are required to work directly with ports and the nominated marine safety authority when ports are preparing marine emergency response arrangements. |
REC158-3454 | 24 - Govt responsibility | That the Department of Transport ensures that key stakeholders are engaged during the implementation of the approved Review recommendations. |
REC158-3444 | 15 - Inter-service cooperation | That the Office of the Emergency Services Commissioner ensures that an emergency services multi-agency working group is established to develop a specialist marine emergency response capability for Victoria based on the multi-agency Urban Search and Rescue (USAR) model. The specialist personnel should be required to have: |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3486 | 24 - Govt responsibility | The emergency management arrangements include the development of partnerships between the public and private sectors, in particular the involvement of government departments and essential services. |
REC156-3485 | 15 - Inter-service cooperation | The integrated Emergency Coordination Centre be utilised during all significant multi-agency or multi-incident events with effective liaison with the State Emergency Response Coordinator. |
REC156-3518 | 24 - Govt responsibility | The Department of Premier and Cabinet, the Office of the Emergency Services Commissioner and other relevant departments conduct further work to determine the need for a power to appoint a coordinator of essential services restoration. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3514 | 24 - Govt responsibility | The State Government endorse the establishment of the Victorian Emergency Information Line and it is developed with appropriate protocols to ensure linkages and information flows to the energy sector. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3490 | 24 - Govt responsibility | The Department of Human Services improve its communication with councils to enhance delivery of recovery services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3474 | 24 - Govt responsibility | That the Victorian Government consider all available means, consistent with conservation values, for substantially increasing the access of apiarists to the public land estate. |
REC155-3473 | 24 - Govt responsibility | That the Victorian Government expedite the implementation of its 2006 election commitment to provide four wheel drive clubs with access to management vehicle only tracks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC154-3462 | 41 - Emergency Management exercises | DPI should formalise the approach and framework for evaluating simulation exercises and response to Emergency Animal Disease incidents with guidelines to define the nature of the review process. This should include: |
REC154-3459 | 41 - Emergency Management exercises | To improve response preparedness, DPI should clearly link the selection of simulation exercises to the risk management framework to target coverage of high risks. |
REC154-3461 | 24 - Govt responsibility | DPI should develop an Memorandum of Understanding (MOU) with the Department of Human Services that capitalises on and strengthens the current good working relationship to support joint forward planning and risk management and mitigates against relationship failure in the event of leadership change. The MOU should clarify: |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1806 | 40 - Equipment and consumables | That the Minister for Emergency Services and the Minister for Local Government cause local council plant and equipment that is suitable for use in bushfire fighting be fitted with radios connected to the Government Radio Network. |
Rec-ID | Code | Recommendation |
---|---|---|
REC152-3401 | 15 - Inter-service cooperation | The streamlining correspondence to Emergency Service Agencies |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3095 | 24 - Govt responsibility | SAFECOM re-evaluate and determine a more meaningful definition of fire districts. |
REC151-3071 | 24 - Govt responsibility | The comprehensive prevention, preparedness, response and recovery (PPRR) approach to the management of bushfires as recommended by the Ministerial Review of Bushfire Management in South Australia is supported: its implementation should consider issues raised by councils and should also be considerate of the recommendations of the Wangary Coronial Inquest. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3224 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3223 | 24 - Govt responsibility | The Committee recommends that the Australian Government urgently commission a detailed climate change vulnerability assessment for Kakadu National Park, in consultation with the park’s traditional owners and other stakeholders and drawing on the results of the ‘first pass’ National Coastal Vulnerability Assessment of the park. This assessment should specifically focus on the vulnerability of Kakadu’s freshwater wetland systems to saltwater intrusion. A key outcome of the assessment should be the development of a Climate Change Action Plan for Kakadu National Park, with coordinated input from the Australian Government and Northern Territory Government, Indigenous land owners, researchers and other stakeholders. |
REC145-3239 | 24 - Govt responsibility | The Committee recommends that the Australian Government establish a National Coastal Advisory Council to: |
REC145-3221 | 24 - Govt responsibility | The Committee recommends that the Australian Government, in considering its response to the Independent Review of the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act), take into account concerns about the EPBC Act and coastal zone management raised as part of this inquiry—in particular, the need to address the cumulative impacts of coastal development. This could be achieved by numerous means, including: |
REC145-3237 | 24 - Govt responsibility | The Committee recommends that the Australian Government, in cooperation with state, territory and local governments, and in consultation with coastal stakeholders, develop an Intergovernmental Agreement on the Coastal Zone to be endorsed by the Council of Australian Governments. The intergovernmental agreement should: |
REC145-3219 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3230 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
REC145-3217 | 24 - Govt responsibility | The Committee recommends that the Australian Government, through the Council of Australian Governments process, examine the establishment of a system of national coastal zone environmental accounts, employing the model developed by the South East Queensland Healthy Waterways Partnership. |
REC145-3226 | 24 - Govt responsibility | The Committee recommends that the Australian Government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3389 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government make a public announcement about the future accommodation plans for the Emergency Services Agency and its component parts so that both the ESA and the ACT public are informed about current proposals and timeframes. |
REC144-3388 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government re-investigate the suitability of the Fairbairn site as a proposed centralised accommodation facility for emergency services. |
REC144-3386 | 24 - Govt responsibility | The Committee considers that the ACT Government should table in the ACT Legislative Assembly the cost-benefit analysis and business plan for Fairbairn as a central site for emergency services in the ACT. |
REC144-3395 | 15 - Inter-service cooperation | The Committee recommends that the ACT Emergency Services and the Rural Fire Service in particular institute regular meetings with the NSW Rural Fire Service and other appropriate authorities, such as environment |
REC144-3382 | 24 - Govt responsibility | The Committee recommends that responsibility for oversighting the progress of the implementation of agreed recommendations of the Coroner be undertaken by a truly independent body and not by the Bushfire Council. |
REC144-3385 | 41 - Emergency Management exercises | The Committee recommends that the ESA hold discussions with NSW with a view to developing a joint exercise program with the NSW Rural Fire Service on an ongoing basis. |
REC144-3384 | 41 - Emergency Management exercises | The Committee recommends that the ESA develop a schedule of proposed exercises as a five year rolling plan, in order that all the elements of emergency services are able to be tested over that time and in differing |
REC144-3390 | 24 - Govt responsibility | If the ACT Government decides to proceed with the site as the emergency services headquarters, that it accord a high priority to the finalisation of the site preparations for the ESA at Fairbairn as a matter of urgency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3588 | 33 - Relief and recovery | That, in line with recommendations contained in the 2004 Report to the Council of Australian Governments, greater flexibility should be introduced to WANDRA to enable damaged infrastructure to be upgraded to a more resilient standard where that is both feasible and cost-effective. |
REC143-3585 | 33 - Relief and recovery | That the Professional Assistance Grant is formally extended by WANDRA to include non rural businesses and that it be made available to assist with the clean up of disaster related damage to farms and businesses. (The Committee recognises that the amendments to WANDRA as of March 2007 address this recommendation). |
REC143-3583 | 33 - Relief and recovery | That the newly proposed index linked limits for Personal Hardship and Distress Relief Payments as outlined in the paper “National Disaster Relief Arrangements - An Analysis and Recommendations for Personal Hardship Distress Measures” be accepted by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3575 | 24 - Govt responsibility | The preferred model for the Tasmanian Medical Retrieval Services is to have TMRS and NETS staff based in RHH. The fixed wing would remain based in Launceston (for the present) with the helicopter to remain based in Hobart. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3529 | 24 - Govt responsibility | The Queensland Government should consider the endorsement of transitional arrangements proposed in this report, in order to ensure as far as possible the smooth completion of the recovery and the ultimate return to government operations as usual in the cyclone-affected area. |
REC136-3525 | 24 - Govt responsibility | In any future disaster of comparable proportions, consideration should be given to the co-location of the Building Coordination Centre and the principal One Stop Shop. |
Rec-ID | Code | Recommendation |
---|---|---|
REC132-3597 | 15 - Inter-service cooperation | Investigate engaging with other agencies involved in emergency management including SES, VicRoads, VicPolice, OESC and DHS to establish a single united emergency information line for Victoria that can be used to provide information to the public from all agencies involved. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3623 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and apply the lessons learnt from Exercise Cumpston to further improve preparedness for major infectious disease emergencies. |
REC129-3628 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test the capability of its contact tracing system to deal with a public health emergency. |
REC129-3627 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test its surveillance systems for early detection of infectious diseases. |
REC129-3624 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and formally establish and oversight a comprehensive program of training, testing and evaluation of plans at the state, area and facility level. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3606 | 24 - Govt responsibility | That the Department of Primary Industries address the forthcoming potential shortage of veterinary pathologists and agronomists within its testing facilities by positive recruitment actions over the next five years such as offering scholarships or training existing professional staff to develop skills in pathology. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1956 | 15 - Inter-service cooperation | That courses and programs be conducted to increase the level of Incident Control System training and augment the expertise of people who are likely to perform functions in an incident management team |
REC126-1979 | 24 - Govt responsibility | That the policy and practice just recommended be the subject of a memorandum of understanding between the Emergency Services Agency and the Department of Territory and Municipal Services (previously the Department of Urban Services) or other relevant department or agency, so as to ensure that the land management agency on whose land a fire starts has responsibility to respond immediately to that fire in accordance with the applicable standards for weight of response. Further, the land management agency should be responsible for efforts to suppress fire until such time as it becomes clear that the suppression task is beyond capacity of the agency, at which point the ACT Rural Fire Service should assume direct responsibility for coordinating the ongoing response |
REC126-2012 | 24 - Govt responsibility | If they are willing and available to participate, that the taskforce's membership include Mr Phil Cheney, Mr Tony Bartlett, Mr Val Jeffery and Mr John Lowe |
REC126-1954 | 15 - Inter-service cooperation | That senior officers of the Emergency Services Agency give greater recognition to the skills, knowledge and experience of people from other agencies – particularly the land management agencies – as well as rural residents and private individuals and use these people in roles commensurate with their skills and experience |
REC126-1976 | 24 - Govt responsibility | That the Emergency Services Agency have authority over the land management agencies and other landholders in order to implement preparedness and prevention measures – including fuel-reduction works where there are failures in compliance |
REC126-2009 | 24 - Govt responsibility | That a taskforce be established to give effect to the recommendations in this report |
REC126-1967 | 40 - Equipment and consumables | That the Emergency Services Agency give priority to ensuring it has guaranteed access to an adequate number and type of bulldozers, as well as experienced operators, during the fire season, for immediate deployment as required |
REC126-1962 | 24 - Govt responsibility | That, because of the small jurisdiction of the ACT (equivalent to one fire district in NSW) the ACT Government consider all possible options for the provision of fire services to the ACT, among them: |
REC126-2006 | 24 - Govt responsibility | I recommend that, as appropriate, the ACT cooperate with the Commonwealth in the implementation of the committee's recommendations and, in particular, give careful consideration to adoption of the following recommendations: |
REC126-1948 | 24 - Govt responsibility | That the Emergency Services Agency be removed from the Department of Justice and Community Safety and transformed into an independent statutory authority reporting directly to the responsible Minister. Note in this regard that Mr McLeod made a similar recommendation, and I endorse it unequivocally. Placing the agency within a government department puts unnecessary layers of bureaucracy between the agency and the responsible Minister, and the bureaucrats concerned usually have no special knowledge of or experience in emergency management, regardless of their seniority in the bureaucracy |
REC126-1985 | 24 - Govt responsibility | That the Emergency Services Agency, with the suport of the ACT Government, seek to establish with the NSW Department of Environment and Conservation and the NSW Rural Fire Service a protocol that will provide for the establishment of a joint incident management team as part of unified control arrangements based on adoption of the following principles: |
REC126-1981 | 15 - Inter-service cooperation | That senior officers in the Australian Federal Police and the Emergency Services Agency maintain regular and meaningful contact during fire emergencies, to ensure full dissemination of information and thus facilitate the making of good operational decisions |
REC126-1942 | 24 - Govt responsibility | That the ACT Attorney-General and the ACT Government - in consulation with the Chief Justice of the ACT and the ACT Chief Magistrate - take legislative action that would have the effect of funds being directly appropriated annually to the courts, preferable along the lines of the Commonwealth model as it applies to the High Court of Australia, the Federal Court of Australia, the Family Court of Australia and the Federal Magistrates Court. Alternatively, the funds could be appropriated in accordance with the South Australian model, which has a seperate Courts Administartion Authority. |
REC126-1984 | 24 - Govt responsibility | That the Emergency Services Agency, with the support of the ACT Government, develop a single, new memorandum of understanding with the NSW Department of Environment and Conservation and the NSW Rural Fire Service, providing for liaison and joint operations as soon as it becomes apparent to whichever jurisdiction is managing a fire that the fire will probably affect the other jurisdiction. Joint operations should not be limited to when an incident occurs on both sides of the border, as is the current arrangement |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3891 | 15 - Inter-service cooperation | That Melbourne Water and councils explore opportunities for working collaboratively to address the management of flooding risks with a view to optimising the efficient and effective use of their flood mitigation resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3889 | 15 - Inter-service cooperation | Develop a component of the DSE Workforce Strategy to build organisational capacity and sustainability of the prescribed burning program across the networked emergency organisation: |
REC124-3883 | 15 - Inter-service cooperation | Integrate information management systems relating to the prescribed burning program to provide consistency across the networked emergency organisation: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3882 | 41 - Emergency Management exercises | The Office of the Emergency Services Commissioner convene a working group of key emergency services and emergency management agencies to develop a flow chart based on scenario testing, to support decision making and the assessment of response requirements to medical, hazardous materials and CBR emergencies including their transition from one type to another. |
REC123-3876 | 15 - Inter-service cooperation | Metropolitan Fire Brigade and Aviation Rescue Fire Fighting service review and enhance the existing mutual response Memorandum of Agreement to provide more timely notification and therefore immediate access to appropriate resources to respond to emergencies. |
REC123-3875 | 15 - Inter-service cooperation | Melbourne Airport Emergency Planning Committee review the Airport Emergency Plan to ensure the capabilities of agencies are adequately documented and understood by all stakeholders, and that all agencies including airlines are represented at the appropriate organisational level on the Airport Emergency Planning Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3779 | 24 - Govt responsibility | The Committee recommends that relevant government departments implement an ongoing management program for the eradication of feral pests and weeds. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
Rec-ID | Code | Recommendation |
---|---|---|
REC117-3636 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in conjunction with the National Counter-Terrorism Committee’s exercise management advisers, explore options for the incorporation of more contemporary and varied testing and training aids in the National Capability Development Exercise Programme. |
REC117-3634 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter- Terrorism Committee, pursue the adoption of a more strategic approach to determining the National Capability Development Exercise Programme so that: |
REC117-3639 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the National Counter-Terrorism Committee, strengthens the reporting on the National Capability Development Exercise Programme through: |
REC117-3635 | 15 - Inter-service cooperation | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, seek to create systematic mechanisms for better targeting and evaluating inter- agency coordination within the National Capability Development Exercise Programme and continuous improvement cycle. |
REC117-3638 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee: |
REC117-3637 | 41 - Emergency Management exercises | The ANAO recommends that the Attorney-General’s Department, in consultation with the Department of the Prime Minister and Cabinet and the National Counter-Terrorism Committee, pursue a more strategic and systematic approach to the measurement of performance via the National Capability Development Exercise Programme by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2117 | 33 - Relief and recovery | The Working Group recommends that potential shortfalls in the capacity to deal with large numbers of unprotected children and other special needs groups in a catastrophic event be referred to the Disaster Recovery Sub Committee of Community Services Ministers’ Advisory Council (CSMAC) for consideration and report back. |
REC116-2109 | 24 - Govt responsibility | The Working Group recommends that participants in the exercises designed to test continuity of executive government plans and procedures should be the office holders themselves. |
REC116-2103 | 33 - Relief and recovery | The Working Group recommends that jurisdictions plan for the logistics of supply and delivery of meals to large numbers of homebound persons in an attempt to identify possible ways of resolving existing shortcomings. |
REC116-2108 | 24 - Govt responsibility | The Working Group recommends that all States/Territories and the Australian Government should regularly (annually) test their continuity of executive government plans and contingencies. |
REC116-2098 | 15 - Inter-service cooperation | The Working Group recommends that Emergency Management Australia (EMA) facilitate national discussions into the capability of States/Territories to ensure thorough collaborative systems and plans for inter-jurisdictional resource interoperability exist, and where this has not already occurred at State/Territory level and appropriate agencies, committees or government departments can be identified, they should be tasked with progressing specific issues in the following areas: |
REC116-2126 | 24 - Govt responsibility | The Working Group recommends the Australian Emergency Management Committee note that: |
REC116-2105 | 24 - Govt responsibility | The Working Group recommends that the adequacy of existing national mortuary capability to meet the likely demands of a catastrophic disaster be assessed by State/Territory Coroners. This assessment should also consider the need for a mobile mortuary capability and involve discussions with the Australian Federal Police. |
REC116-2129 | 41 - Emergency Management exercises | The Working Group recommends that Emergency Management Australia and the jurisdictions through the AEMC develop a three year rolling national exercise strategy aimed at testing the response and recovery aspects of large scale disasters. |
REC116-2125 | 24 - Govt responsibility | The Working group recommends that the Australian Government take a leadership role with regard to addressing the national capability issues identified within this review. Further, that the States/Territories recognise and accept the collaborative nature of developing national capability and commit through engagement and consultation to assisting the Australian Government in this task. |
REC116-2115 | 41 - Emergency Management exercises | The Working Group recommends that the results of the scenario modeling be presented to the Australian Emergency Management Committee (AEMC) upon completion, and that AEMC form Sub Working Groups of State/Territory emergency management representatives as appropriate to be tasked with considering response and recovery capability (both state/territory and national) against the identified consequences. |
REC116-2122 | 33 - Relief and recovery | The Working Group recommends that States/Territories consider their ability to house large numbers of domestic pets, and where necessary, develop plans and arrangements that facilitate this need. |
REC116-2123 | 24 - Govt responsibility | The Working Group recommends that the Australian Government consider developing an overarching whole of government disaster plan that clearly articulates authority, roles and responsibilities of agencies, inter-departmental committees and key officials, to link the range of existing Australian Government disaster plans. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2120 | 33 - Relief and recovery | The Working Group recommends that the National Recovery Coordinators Group considers the issue of emergency relief centres in the context of catastrophic disaster with a view to assisting jurisdictions to plan for the need to accommodate thousands of people following a disaster. |
REC116-2118 | 24 - Govt responsibility | The Working Group recommends that State/Territory Recovery Committees review their membership to ensure that it is reflective of community needs, including representation from the Insurance Disaster Response Organisation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3906 | 10 - Infrastructure | Firefighting organisations should: resolve existing telecommunication problems and work with other emergency service organisations to establish compatible telecommunications systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3933 | 15 - Inter-service cooperation | That DPI formalises agreements between divisions and groups that allow staff to be involved in incursion responses and reflects this requirement in individual duty statements. |
REC112-3920 | 15 - Inter-service cooperation | That better use be made of Primary Industries Research Victoria's (PIRVIC) facilities by strengthening links with relevant groups of expertise, such as the Forest Science Centre. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3936 | 24 - Govt responsibility | To enhance the governance of the Queensland disaster management system, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services ensure that — |
REC111-3935 | 24 - Govt responsibility | To provide the strategic leadership and governance required to implement the Disaster Management Act 2003, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable governance framework for disaster management which includes the establishment of — |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2192 | 24 - Govt responsibility | That, according to available scientific evidence, a decision regarding cattle grazing in the High Country should not be based on the argument that ‘grazing prevents blazing.’ |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2323 | 15 - Inter-service cooperation | That CFA, DSE, MFESB, VICSES, Victoria Police and OESC, in consultation with the Municipal Association of Victoria, consult on the proposal to combine Municipal Councils’ current responsibilities for the development of an emergency management plan/committee, as required by the Emergency Management Act 1986 and a fire prevention plan/committee as required by the Country Fire Authority Act 1958. |
REC104-2247 | 24 - Govt responsibility | That an appropriately resourced, national aerial firefighting strategy is urgently required, and that the Victorian Government make representations to the Commonwealth to support the Australasian Fire Authorities Council recommendations |
REC104-2335 | 41 - Emergency Management exercises | That the fire agencies develop a program to significantly increase the amount of joint training and exercises undertaken. |
REC104-2315 | 24 - Govt responsibility | That the Privacy Commissioner be asked for advice in the development of this model. |
REC104-2307 | 33 - Relief and recovery | That the Victorian Government recommend to the Commonwealth Government that it reviews eligibility for those without employment who may or may not be engaged in an emergency response, and are unable to access the appropriate infrastructure to register for financial assistance. |
REC104-2238 | 15 - Inter-service cooperation | That the Victorian fire agencies negotiate with their counterparts in New South Wales and South Australia to put in place agreements for mutual aid and the development of cross border strategy for the management of fires burning in the vicinity of, or across, State borders, and these agreements are reviewed annually. |
REC104-2316 | 33 - Relief and recovery | That the State Emergency Recovery Committee explore opportunities to establish a 'one-stop shop’ approach wherever practicable following emergencies, including a single telephone number to connect a person to all agencies involved in the recovery process. |
REC104-2322 | 15 - Inter-service cooperation | That DSE commits appropriate resources to work with OESC in developing the bushfire component of the model. |
REC104-2239 | 24 - Govt responsibility | That any local level agreements developed to address geographically specific risks or issues must be consistent with State-level arrangements. |
REC104-2250 | 41 - Emergency Management exercises | That DSE and CFA work in cooperation with the Municipal Emergency Response Coordinators to develop and conduct joint exercises that practise the skills and test procedures for operations of the Municipal Emergency Coordination Centre, Municipal Recovery Centre and Incident Control Centres. |
REC104-2303 | 24 - Govt responsibility | That Interstate Agreements prepared by the fire agencies be reviewed to include protocols for the joint release of consistent and appropriate information relating to fires burning across State borders. |
REC104-2306 | 33 - Relief and recovery | That VicRoads and Municipal Councils review procedures and processes to ensure that the identification and delivery of remedial works on State and Council roads following emergency events are as efficient as possible. |
REC104-2314 | 33 - Relief and recovery | That DHS, in conjunction with Local Government, Government departments and the nongovernment sector, modify recovery planning at all levels to include a case management approach supported by an appropriate information system to be activated at the time of an emergency. |
REC104-2295 | 15 - Inter-service cooperation | That more emphasis should be given to communication and discussion in regard to State Aircraft Unit’s roles, responsibilities, practices and procedures. |
REC104-2232 | 24 - Govt responsibility | That Government in the development of its statewide water policy includes appropriate consideration of access to water for firefighting. |
REC104-2256 | 24 - Govt responsibility | That the State Emergency Operations Centre develop and maintain strong and close links with the State Emergency Response Coordination Centre, if collocation is not possible. |
REC104-2305 | 33 - Relief and recovery | That DPI actively promote as widely as possible within the community, the agricultural recovery service available during emergencies to ensure that all farmers are aware of the services provided. |
REC104-2313 | 33 - Relief and recovery | That Government review the emergency relief and financial assistance policy, and develop and communicate a predictable, consistent and equitable policy designed to assist the community to recover from emergencies, including natural disasters. |
REC104-2283 | 15 - Inter-service cooperation | That DSE, CFA, MFESB and VICSES work cooperatively to establish a common system for resource tracking during major fires and incidents. |
REC104-2230 | 24 - Govt responsibility | That DSE investigates whether such agreements should exist with other government Departments and agencies, particularly those with officers located in rural Victoria who may be involved in fire response and support operations in the future, based on their expertise and experience. |
REC104-2255 | 24 - Govt responsibility | That the options of collocating the State Emergency Response Coordination Centre with the new State Emergency Operations Centre |
REC104-2331 | 24 - Govt responsibility | That a State Emergency Operations Centre be established to replace the existing separate fire agency centres. This could, if necessary, be initially confined to being a State Fire Operations Centre as recommended in Chapter 18, Part D. |
REC104-2312 | 33 - Relief and recovery | That all agencies engaged in recovery participate in community briefings prior to and during emergency events, to ensure recovery issues are reinforced and communities are informed of the processes established to assist individuals – including matters that are not the responsibility of Victoria, such as Centrelink payments. |
REC104-2266 | 15 - Inter-service cooperation | That DSE and CFA review their joint planning for Incident Control Centres to ensure that, wherever safe and practicable, those Centres are located close to the fire area. |
REC104-2225 | 24 - Govt responsibility | That the Victoria Emergency Management Council establish a sub-committee by June 2004 to ensure an all-agency and appropriate industries’ policy framework is developed and agreed in respect to the planning for fire prevention, mitigation and suppression. |
REC104-2336 | 15 - Inter-service cooperation | That OESC work with the fire agencies in developing implementation strategies for recommendations agreed by Government. |
REC104-2254 | 24 - Govt responsibility | That a single state-of-the-art all hazards State Emergency Operations Centre be established for Victoria. This could, if necessary, be implemented in stages, initially incorporating DSE, CFA, MFESB and the State Aircraft Unit. |
REC104-2321 | 24 - Govt responsibility | That Government confirms that the Model of Fire Cover/Fire Safety Victoria strategy should be a seamless model for the whole of the State and include both private and public land. |
REC104-2310 | 33 - Relief and recovery | That recovery is recognised as commencing at the same time as response and that recovery planning and delivery is an integral part of the operations of the Municipal Emergency Co-ordination Centres. |
REC104-2265 | 15 - Inter-service cooperation | That in the review of Incident Control Centre locations, DSE and CFA give due consideration to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2131 | 24 - Govt responsibility | The Committee recommends that the Commonwealth through the Council of Australian Governments ensure that states and territories have adequate controls to ensure that local governments implement required fuel management standards on private property and land under their control. |
REC098-2167 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority, in conjunction with the respective state and territory governments, ensure the survivability of essential communication installations during fire incidents by strategic fuel management around the assets. |
REC098-2163 | 10 - Infrastructure | The Committee recommends that Emergency Management Australia and the Australian Communications Authority jointly with the Australasian Fire Authorities Council: |
REC098-2138 | 10 - Infrastructure | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve to increase water access points for bushfire fighting on public land to the minimum national standard. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3413 | 15 - Inter-service cooperation | The Committee recommends to the Minister for Police and Emergency Services that a joint communications and dispatch facility be established under the Minister's control to implement the following minimum services to the Victoria Police and the emergency services: |
REC061-3242 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3415 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |
REC061-3408 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3248 | 15 - Inter-service cooperation | The Committee recommends to the Minister for Police and Emergency Services that a joint communications and dispatch facility be established under the Minister's control to implement the following minimum services to the Victoria Police and the emergency services: |
REC061-3250 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3953 | 15 - Inter-service cooperation | It is therefore recommended that the State Electricity Commission should be advised by someone whose profession it is to consider and devise methods of forest fire protection and suppression; that he should collaborate with others to devise a general scheme of organized protection of the undertaking and township of Yallourn; and that above all, he should have direct access to the Commissioners themselves, lest his advice should lose something of its strength and reality in its journey through the “proper channels” of the Commission’s organization. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3947 | 15 - Inter-service cooperation | It is recommended that the services of this body [Air Raids Precautions Body] be used in future if to do so be thought desirable. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3956 | 24 - Govt responsibility | It is strongly recommended that no public department of possible combination of public departments interested in forests should be permitted to gain control of this authority. |
REC015_3954 | 24 - Govt responsibility | It is recommended that each public department or body which may now or hereafter control forest areas be allowed to pursue its own policy of fire prevention and suppression. As each such body is responsible directly or indirectly to Parliament it must be allowed to carry its responsibility in its own manner. It is strongly recommended that no such department be given authority over any other body in matters relating to fire prevention or suppression. If it is ultimately shown that a department is unfit to discharge the duty involved other measures may be taken. |
REC015_3960 | 33 - Relief and recovery | It is recommended that the Forests Commission recognize and provide for the efficient exercise of three major functions, namely those of Commerce, Reclamation and Rehabilitation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3973 | 40 - Equipment and consumables | To arrange for uniform water facilities, where possible, by having large taps attached to elevated tanks, suitable approaches made to dams for filling carts, and convienient gates to approach same. |
REC013_3972 | 40 - Equipment and consumables | To recommend to shire councils the purchase of fire carts and necessary equipment for fire fighting. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3988 | 40 - Equipment and consumables | The Commission recommends that buckets of sand or other apparatus for extinguishing fire be kept in any chamber where high powered electricity is used. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3997 | 40 - Equipment and consumables | That suitable metal receptacles be fitted under the spittoons of all smoking compartments of country trains, to receive pipe ashes, lighted tobacco, cigars, cigarettes, matches, or other inflammable matter used by smokers. |
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4104 | 33 - Relief and recovery | Australian, state and territory governments should refine arrangements to support localised planning and the delivery of appropriate mental health services following a natural disaster. |