Rec-ID | Code | Recommendation |
---|---|---|
REC325-4326 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends Queensland Fire and Emergency Services lead an inter-agency IT system assessment with Queensland Police Service and local governments to identify disaster management systems currently in use and develop options to enhance connectivity and interoperability between systems. Outputs to be considered include, but are not limited to, consideration of requests for assistance (RFA) and the production of situation reports. |
REC325-4327 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends all local governments that offer an opt-in system develop strategies to increase the number of subscribers who elect to use this service. As part of the annual disaster management plan assessment process for the period 2023–2025, the Office of the Inspector-General of Emergency Management will request information from the relevant local disaster management groups to highlight and share innovative practices that have led to an increase in subscription levels for opt-in services. |
REC325-4338 | 17 - Assets and technology | The Inspector-General of Emergency Management recommends the Queensland Reconstruction Authority and the Bureau of Meteorology investigate options for the consolidation of ownership, renewed capital and maintenance in the flood warning network in consultation with flood warning infrastructure asset owners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4294 | 34 - Local knowledge | Environment: That, to maximise protection for the environment in and around floodplains, Government, working with local communities especially Indigenous communities, the NSWRA, other agencies and local councils ensure Indigenous voices are well heard in land use planning and natural resource management by: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4278 | 11 - Evacuation and shelters | That the NSW Government ensure that the current review of evacuation centres considers the role, accreditation and support of community evacuation centres, with the outcomes of this review to be made public and incorporated into the update of state emergency plans. |
REC323-4259 | 3 - Biodiversity | That the NSW Government provide immediate support to the Hawkesbury City Council to remediate the riverbank erosion affecting Cornwallis Road, Cornwallis without any further delay. |
REC323-4256 | 17 - Assets and technology | That the NSW Government work with relevant agencies and local landowners to find ways to improve the management of drainage channels including looking for recommendations to reduce red and green tape. |
REC323-4264 | 34 - Local knowledge | That the NSW Government work in partnership with key Aboriginal stakeholders, including the Jali Local Aboriginal Land Council, to prioritise the rebuild of Cabbage Tree Island, and ensure a safe and resourced evacuation plan is in place. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
REC323-4260 | 3 - Biodiversity | That the NSW Government invest in the restoration of the Wilsons and Richmond Rivers to include riparian restoration, water quality and river health improvement. |
REC323-4263 | 17 - Assets and technology | That the NSW Government prioritise support for the full restoration of sewage treatment facilities on the Richmond River, for the benefit of communities in the Northern Rivers region. |
REC323-4265 | 34 - Local knowledge | That the NSW Government work with First Nations peoples to support Aboriginal organisations in their capacity to operate and respond in times of natural disasters. |
REC323-4268 | 11 - Evacuation and shelters | That the NSW Government accelerate its caravan program and ensure it is made available as an option to all displaced residents from the February-March 2022 floods. |
REC323-4275 | 34 - Local knowledge | That the NSW Government, in partnership with community groups, including First Nations groups, develop initiatives to build community resilience, particularly in regions at high risk of future natural disaster events. |
REC323-4285 | 17 - Assets and technology | That the NSW Government, in consultation with telecommunication providers and satellite communication providers, investigate ways to minimise the complete loss of telecommunication services in natural disasters, including: |
REC323-4274 | 11 - Evacuation and shelters | That the NSW Government establish a standing workforce from within the public service to staff evacuation and recovery centres, with this workforce to be trained ahead of time and mobilised as soon as a natural disaster occurs. |
REC323-4276 | 34 - Local knowledge | That the NSW Government ensure that community groups, both existing and emerging, including First Nations groups, are well integrated into disaster recovery, by incorporating them into state recovery plans and engaging with them in between and in the lead up to natural disasters. |
REC323-4286 | 17 - Assets and technology | That the NSW Government advocate through the National Cabinet for the Bureau of Meteorology to review its rain data infrastructure and flood modelling tools, to ensure forecasting locations, rain and flood gauges and other infrastructure are appropriately placed, maintained and updated. |
REC323-4287 | 34 - Local knowledge | That the NSW State Emergency Service, in partnership with the Bureau of Meteorology, investigate ways in which local communities and local media with local knowledge can play a stronger role in flood predictions and warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4224 | 17 - Assets and technology | The Inspector-General Emergency Management recommends the Department of Environment and Science examines the utilisation of technology, in consultation with relevant stakeholders, to improve the collection of visitor numbers and movement data. This could include, for example, expanding the use of Automatic Number Plate Recognition technology to K’gari and examining the suitability of mobile phone check-in applications. |
REC322-4222 | 4 - Fire season preparation | The Inspector-General Emergency Management recommends the Department of Environment and Science undertake a review of campfire locations on K’gari, including all relevant signage on and off the island, maps and visitor permit information, to promote a consistent message about lighting campfires on K’gari. |
REC322-4232 | 11 - Evacuation and shelters | The Inspector-General Emergency Management recommends the Maryborough District Disaster Management Group works with the Fraser Coast Local Disaster Management Group to plan for the evacuation of K’gari due to bushfire. Once developed, the plan should be exercised and regularly reviewed. |
REC322-4227 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the membership of the K’gari Locality Specific Fire Management Group be expanded to include representatives of the Butchulla people, community associations from each township and tourism and business operators with interests on the island. |
REC322-4230 | 34 - Local knowledge | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services engages with land managers and other stakeholders on K’gari to source data to inform Predictive Services products. |
REC322-4250 | 34 - Local knowledge | The Inspector-General Emergency Management recommends the Locality Specific Fire Management Group for K’gari meet at least twice per year, in person or virtually. |
Rec-ID | Code | Recommendation |
---|---|---|
REC321-4212 | 34 - Local knowledge | We recommend that DELWP increases its collaboration with Victorian Traditional Owner groups to facilitate the reintroduction of cultural burning and ensure effective support for these practices across all of its regions. |
REC321-4204 | 4 - Fire season preparation | We recommend that DEWLP and CFA (in consultation with FRV) in partnership with councils, provide advice to government in line with the Safer Together: A new approach to reducing the risk of bushfire in Victoria policy on options to better resource the assessment of risk on private land, its treatment and activities to enforce compliance of land owners with risk-reduction treatments. |
REC321-4206 | 3 - Biodiversity | We recommend that DELWP conducts more effective ecosystem resilience monitoring by: - setting a target for regions on the quantity of ecosystem resilience monitoring assessments that they should complete annually - setting an outcomes-level target that defines desirable values for key ecosystem resilience metrics - reporting publicly against all of the metrics in its Measuring Ecosystem Resilience in Strategic Bushfire Management Planning policy in its fuel management reports. |
REC321-4210 | 3 - Biodiversity | We recommend that CFA (in consultation with FRV) improves its values checks by providing ongoing state-wide support to regional vegetation management officers and leveraging any relevant systems or capabilities from DELWP to conduct values checks through guidance, training and ongoing funding. |
REC321-4213 | 3 - Biodiversity | We recommend that DELWP improves the effectiveness, consistency and transparency of its environmental and cultural values checks by: - finalising its review of operational values checking processes and committing to an implementation plan - clarifying and formalising principles and procedures, making them publicly available where possible - improving capability and capacity among staff responsible for carrying out values checks, for example through training - developing a long-term program of work and investment to improve the quality, consistency and comprehensiveness of underlying datasets - increasing alignment in regard to values checks between agencies carrying out fuel management. |
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4186 | 34 - Local knowledge | Supporting local recovery: The Inspector-General for Emergency Management recommends that the entity referred to in Recommendation 13, or otherwise responsible government department work with councils and communities before, during and after emergencies to strengthen: |
REC319-4190 | 11 - Evacuation and shelters | Humanitarian relief: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions work with the Municipal Association of Victoria and councils to build contingencies into emergency relief centre planning to ensure places of shelter are inclusive, recognise diversity and are better placed to support all displaced people in circumstances of: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4175 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – supported by other organisations with a legislated responsibility for fuel management – plan for and increase the application of non-burning fuel management treatments including mechanical means. The annual fuel management report should include the non-burn component of fuel management treatment, track annual change, and provide a comparison to the previous three years. |
REC318-4180 | 11 - Evacuation and shelters | The Inspector-General for Emergency Management recommends that Victoria Police – in collaboration with the community and the emergency management sector – reflect on events of the 2019–20 fire season to review and enhance evacuation plans and processes with consideration of: |
REC318-4170 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that responder agencies and Emergency Management Victoria review preparedness arrangements to ensure procedural documentation (including plans), recruitment, briefings and training are completed before significant seasonal events are likely to occur. Seasonal preparedness should culminate in attestations of assurance to confirm that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4088 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4092 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review these plans, and update them where appropriate, to account for the existence and standard of any evacuation centres and safer places (however described) in the community, including: |
REC317-4107 | 4 - Fire season preparation | Public land managers should clearly convey and make available to the public their fuel load management strategies, including the rationale behind them, as well as report annually on the implementation and outcomes of those strategies. |
REC317-4079 | 39 - Disaster Risk Management | Australian, state and territory governments, in consultation with local governments and the private sector, should review supply chain risks, and consider options to ensure supply of essential goods in times of natural disasters. |
REC317-4091 | 11 - Evacuation and shelters | State and territory governments should provide further community education on the function and limitations of different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. This education should be nationally consistent. |
REC317-4087 | 4 - Fire season preparation | State and territory governments, working with local governments and fire and emergency service agencies, should ensure that there are appropriate arrangements for roadside vegetation management that take into account, among other things: |
REC317-4067 | 39 - Disaster Risk Management | State and territory governments should have a structured process to regularly assess the capacity and capability requirements of fire and emergency services, in light of both current and future natural disaster risk. |
REC317-4090 | 11 - Evacuation and shelters | State and territory governments should, as a priority, adopt nationally consistent terminology and functions for the different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. |
REC317-4062 | 39 - Disaster Risk Management | The National Disaster Risk Information Services Capability should include tools and systems to support operational and strategic decision making, including integrated climate and disaster risk scenarios tailored to various needs of relevant industry sectors and end users. |
REC317-4061 | 39 - Disaster Risk Management | Australian, state and territory governments should support the implementation of the National Disaster Risk Information Services Capability and aligned climate adaptation initiatives. |
REC317-4089 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4057 | 39 - Disaster Risk Management | The Australian Government should establish a standing entity that will enhance national natural disaster resilience and recovery, focused on long-term disaster risk reduction. |
REC317-4093 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review those plans, and update where appropriate, to provide for coordination between states and territories in cross border areas and to provide cross-border access to evacuation centres. |
REC317-4108 | 4 - Fire season preparation | Australian, state and territory governments should review the assessment and approval processes relating to vegetation management, bushfire mitigation and hazard reduction to: |
REC317-4103 | 39 - Disaster Risk Management | Australian, state and territory governments should develop arrangements that facilitate greater inclusion of primary healthcare providers in disaster management, including: representation on relevant disaster committees and plans and providing training, education and other supports. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4030 | 17 - Assets and technology | Continue to explore options in the short term to improve the functionality and relationship with NSW RFS ‘Fires Near Me’ with respect to ACT specific information before the 2020-21 bushfire season. |
REC316-4029 | 17 - Assets and technology | ACT Government continues to develop the concept for an ACT specific emergency app whilst also using national coordination mechanisms to support an affordable nationally standard all-hazards mobile app. |
REC316-4044 | 11 - Evacuation and shelters | A Relocation and Evacuation working group be established from stakeholder organisations to consider and develop an Evacuation and Relocations Sub- Plan. The Sub-Plan should consider the lessons learned this year and address principles, lead agency, WHoG coordination, trigger points etc. This could be the same working group formed for reviewing the Emergencies Act, Plan and sub-plans. |
REC316-4037 | 17 - Assets and technology | Consideration be given to developing alternate website contingency in the event of a critical failure and an assurance review across all community facing Government websites. |
Rec-ID | Code | Recommendation |
---|---|---|
REC315-3870 | 11 - Evacuation and shelters | That, in order to ensure the safety and wellbeing of vulnerable people during an evacuation, Resilience NSW: |
REC315-3847 | 17 - Assets and technology | That, in order to ensure Australia’s fire fighting aerial capacity capitalises on existing assets and is made up of the right mix, Government: |
REC315-3840 | 29 - Operational Health and Safety | That, in order to ensure firefighter sustenance is of sufficient volume and quality, the NSW RFS reviews food standards and procedures in consultation with volunteers. The review should include catering service standards, including food safety, as well as the viability of sourcing commercial contracts and providing 12-hour food packs to firefighters. |
REC315-3867 | 11 - Evacuation and shelters | That, in order to ensure evacuation centres are fit-for-purpose, Resilience NSW work with Local Emergency Management Committees (LEMCs) to: a) update the guidelines for LEMCs identifying evacuation centres to require a risk assessment of potential locations, which should include identifying alternate sources of power for use by evacuation centres and recording these appropriately |
REC315-3843 | 17 - Assets and technology | That, in order to improve early fire suppression, the NSW RFS trial initial aerial dispatch in areas of high bush fire risk. The trial should identify the most appropriate and cost-effective mix of aircraft, and any associated infrastructure improvements that would be required. |
REC315-3839 | 29 - Operational Health and Safety | That, to ensure firefighters can access mental health support through GPs, Government work with the Commonwealth Government to: |
REC315-3866 | 11 - Evacuation and shelters | That, in order to ensure evacuation arrangements can be scaled up when needed, Resilience NSW: |
REC315-3829 | 4 - Fire season preparation | That, in order to ensure outcomes-based roadside vegetation management to reduce roadside tree fall and grass ignitions in planning and preparing for bush fire, Transport for NSW, working with local government and NSW RFS, establish a consistent framework for roadside vegetation management that analyses road priority, utility, amenity, strategic value and risk. The framework should: |
REC315-3837 | 17 - Assets and technology | That, in order to improve firefighter safety, Government fire authorities: |
REC315-3838 | 29 - Operational Health and Safety | That, in order to ensure all NSW RFS members can access the mental health support they need, the NSW RFS expands in-house mental health support for members. |
REC315-3814 | 11 - Evacuation and shelters | That the NSW RFS identifies remote bush fire prone areas that do not already have an indoor Neighbourhood Safer Place (NSP) and upgrades the relevant NSW RFS Stations to meet NSP guidelines. These stations would require adequate Asset Protection Zones and active/passive protection systems to provide short-term protection. |
REC315-3821 | 4 - Fire season preparation | That government agencies managing land (at all levels and through all agencies) be the best neighbours possible by considering their neighbours when undertaking activities related to bush fire preparation and having clear, two-way communication about these activities, with the aspiration that government landholders will be seen as highly desirable neighbours. |
REC315-3830 | 39 - Disaster Risk Management | That as a matter of urgency, in order to accelerate and finalise a State-wide strategic fire trail network, the NSW RFS Commissioner and Bush Fire Coordinating Committee (BFCC): |
REC315-3836 | 17 - Assets and technology | That, in order to ensure frontline personnel have appropriate personal protective clothing during bush fires: |
REC315-3872 | 11 - Evacuation and shelters | That, in order to improve support for people evacuating with animals, the Department of Primary Industries: |
REC315-3849 | 17 - Assets and technology | That, in order to enhance NSW’s fire fighting capacity, Government trial aerial fire fighting at night in the 2020-21 season with a view to full implementation if successful. |
REC315-3850 | 3 - Biodiversity | That Government develop and implement a policy on injured wildlife response, rescue and rehabilitation including: |
REC315-3825 | 39 - Disaster Risk Management | That Government, acknowledging that a strategic approach to planning for bush fire will take time, and in order to protect, prepare and build resilience into existing communities better, should immediately: |
REC315-3815 | 17 - Assets and technology | That, in order to equip NSW RFS with comprehensive information on all structures and assets at risk of bush fire, Government ensures that: |
REC315-3871 | 11 - Evacuation and shelters | That, in order to ensure equitable access to evacuation centres and associated support services for people in border communities, Resilience NSW ensure cross-border access arrangements are reflected in evacuation centre management guidelines. |
REC315-3848 | 17 - Assets and technology | That, in order to enhance NSW’s ability to improve situational awareness, Government expand FRNSW’s Remotely Piloted Aerial Systems (RPAS) capability (both capital assets and trained operators) to major regional centres and ensure the NSW RFS and other NSW government agencies can access this capability as required. |
REC315-3833 | 3 - Biodiversity | That Government invest in long-term ecosystem and land management monitoring, modelling, forecasting, research and evaluation, and harness citizen science in this effort. This will include, among other things: |
Rec-ID | Code | Recommendation |
---|---|---|
REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
REC314-3270 | 17 - Assets and technology | Review the use of aviation assets including facilities to operate them given the increased pressure from extended fire seasons on northern and southern hemisphere resources. Review line scanning capability with a view to providing real time data to the IMTs on where fires are burning using aviation assets as an intelligence tool rather than just a fire suppression capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2490 | 39 - Disaster Risk Management | To enable entities to have a shared understanding of forecast information for dam failure events during a flood, including flood wave travel time, speed and height, Emergency Action Plans contain protocols and responsibilities of relevant stakeholders for these aspects. |
REC311-2499 | 39 - Disaster Risk Management | To ensure enhanced capability integration and enable timely community messaging Bundaberg LDMG in consultation with Sunwater develop additional Emergency Alerts and associated polygons for a Paradise Dam failure and load these on to the disaster management portal. |
REC311-2498 | 39 - Disaster Risk Management | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg DDMG use the QERMF process to determine if dam failure for Paradise Dam should be reported as a residual risk in this instance due to known changes in the risk profile to: |
REC311-2497 | 39 - Disaster Risk Management | To increase shared understanding of risks, ensure the coordination of plans and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg District Disaster Management Plan (DDMP). |
REC311-2492 | 39 - Disaster Risk Management | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the North Burnett Local Disaster Management Plan (LDMP). |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2487 | 39 - Disaster Risk Management | The state’s arrangements for disaster management, including recovery, are articulated in the Disaster Management Act (2003), the Queensland Reconstruction Authority Act (2011), the State Disaster Management Plan and the Queensland Recovery Plan. To enable state-level arrangements to better support community-led recovery and to improve Queensland’s recovery governance |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2479 | 34 - Local knowledge | Local groups should plan for and establish clear arrangements to effectively manage offers of assistance including the management of goods, services and volunteers. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2465 | 29 - Operational Health and Safety | Fatigue management strategies and guidance should be improved to ensure sustainable staffing practices are incorporated into disaster management planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2436 | 39 - Disaster Risk Management | The outputs of these capabilities should be shared and actively inform the disaster management sector, including response operations and the creation of warnings and public messaging. |
REC307-2428 | 39 - Disaster Risk Management | The future risk of bushfires to Queensland communities should be re-evaluated as part of the 2020 State Risk Assessment in light of recent and emerging science, events and lessons. |
Rec-ID | Code | Recommendation |
---|---|---|
REC304-2407 | 39 - Disaster Risk Management | Discontinue the automatic allocation of Fire Warden powers to Council and Committee members and substitute an option for members to be appointed as Fire Wardens. |
REC304-2416 | 4 - Fire season preparation | Establish a capacity to prescribe bushfire management arrangements for individual properties based on bushfire risk assessment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2402 | 17 - Assets and technology | Explore better options for call and dispatch, telecommunications and information sharing capability across the emergency management portfolio including the adoption of a multi-agency emergency management operations complex |
REC302-2398 | 17 - Assets and technology | As a matter of priority commence the roll out of AVL capability for the Rural Fire Service fleet, completing as much work as possible before the 2018/19 bushfire season, capitalising where necessary on current and future work undertaken with the NSW Government Radio Network to ensure both officer safety and situational awareness |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC299-1348 | 4 - Fire season preparation | In keeping with the Victorian Bushfires Royal Commission’s findings and recommendations, human life has primacy in bushfire‑related regulations and it is important that this is maintained in the implementation of bushfire management overlays and relevant vegetation removal exemptions should reflect the primacy of human life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2348 | 17 - Assets and technology | I recommend that if it has not already done so, the New South Wales Police Force acquires the audio surveillance technology that in similar circumstances would allow a device to be monitored in the Police Forward Command Post and/or the Police Operations Centre and that the organisation ensures that its capacity in this regard keeps pace with technological advances in the area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC291-1244 | 11 - Evacuation and shelters | The Department of Fire and Emergency Services to work with the Department of Planning and Local Governments to adopt a policy which enables Local Governments to identify, register and communicate, ‘Places of Bushfire Last Resort’ in settlements and townsites where the life risk from bushfire is very high or greater. |
REC291-1236 | 4 - Fire season preparation | The Departments of Parks and Wildlife and Fire and Emergency Services to develop options for the expansion of the ‘Bushfire Mitigation Grant Scheme’ 20 January 2016 Waroona Fire Special Inquiry utilising both State and Commonwealth Government funding to enable the implementation of hazard reduction works identified through the Bushfire Risk Management Planning process. This will target hazard reduction projects on land owned by private landholders in rural-urban interface areas, critical infrastructure protection, local government land, roadsides and land managed by utilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1219 | 17 - Assets and technology | Live resource tracking system that can be used by all response agencies |
REC290-1215 | 4 - Fire season preparation | Appropriate and scalable resourcing models for remote locations |
REC290-1213 | 34 - Local knowledge | Structures to incorporate local knowledge and situational awareness into the fire response |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1198 | 17 - Assets and technology | The Committee finds that on the evidence presented, that the Government should undertake a review of how firefighting equipment and gear in Tasmania can be better standardised with interstate equipment and gear to improve cross-jurisdiction resource utilisation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2081 | 39 - Disaster Risk Management | Engage with industry bodies to explore opportunities to better understand and manage risks. |
REC286-1447 | 39 - Disaster Risk Management | Assess vulnerability of ecosystems and species to coastal inundation. |
REC286-1461 | 39 - Disaster Risk Management | Review all hazards response and recovery plans to ensure they address likely earthquake consequences. |
REC286-2066 | 39 - Disaster Risk Management | Advocate for an National Notifiable Diseases Database. |
REC286-2026 | 11 - Evacuation and shelters | Identify facilities that can be used as cool spaces during heatwaves and establish linkages between operators and emergency management organisations |
REC286-1455 | 39 - Disaster Risk Management | Assess options for managed coastal retreat. |
REC286-2071 | 29 - Operational Health and Safety | Implement a social marking program to promote improved respiratory etiquette and hygiene. |
REC286-1478 | 39 - Disaster Risk Management | Review environmental risks associated with hazardous uses within flood prone areas. |
REC286-2056 | 39 - Disaster Risk Management | Review Ambulance Tasmania surge capacity. |
REC286-1436 | 4 - Fire season preparation | Continue the development and implementation of community level Bushfire Mitigation Plans. |
REC286-1452 | 39 - Disaster Risk Management | Improve understanding of the allocation of ownership across government, business and individuals. |
REC286-2055 | 29 - Operational Health and Safety | Personal protective equipment (masks, gowns, gloves, goggles) – review fit-testing vs fit-checking. |
REC286-1469 | 39 - Disaster Risk Management | Actively manage riparian vegetation to manage flood dynamics. |
REC286-2049 | 39 - Disaster Risk Management | Pro-actively manage landslide areas. |
REC286-1472 | 11 - Evacuation and shelters | Develop flood evacuation plans for at risk communities. |
REC286-1450 | 39 - Disaster Risk Management | Improve the understanding of the vulnerability of critical infrastructure. |
REC286-1468 | 39 - Disaster Risk Management | Identify and anlalyse the location of critical infrastructure within defined flood areas. |
REC286-2017 | 39 - Disaster Risk Management | Improve maintenance of flood mitigation infrastructure. |
REC286-2089 | 39 - Disaster Risk Management | Identify and analyse statewide storm hazard risk. |
REC286-1454 | 11 - Evacuation and shelters | Review coastal inundation evacuation and response plans. |
REC286-1448 | 39 - Disaster Risk Management | Utilise coastal mapping to assess need for coastal defences. |
REC286-1463 | 39 - Disaster Risk Management | Develop enablers and capacity for Tasmanian earthquake risk owners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1381 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC280-1386 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC280-1382 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1153 | 4 - Fire season preparation | Planning for Access to Potentially Isolated Communities |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1123 | 17 - Assets and technology | Every effort should be made to enhance the ability of communications personnel to cope with fast moving and time critical fire events by providing and maintaining: ongoing extensive communications training; advanced vehicle capability for clear communication within areas of radio coverage dead spots; ability to receive Air intelligence live streaming; map production facilities; deployment of multiple Incident Control Vehicles when required; all Incident Control Vehicles with access to DFES Information Technology Systems. |
REC265-1117 | 17 - Assets and technology | Automatic Vehicle Location technology should be adopted to enable a better appreciation of the deployment and location of appliances at an incident, in order to increase situational awareness |
REC265-1116 | 17 - Assets and technology | Procedures should be established to monitor the use of heavy plant during a bushfire incident, including the tasking of support appliances. Procedures should provide for the appointment of a dedicated Machinery Supervisor as prescribed within the Australasian Interservice Incident Management System. |
REC265-1112 | 17 - Assets and technology | Radio infrastructure in the Perth Hills should be reviewed to assess whether it is practicable for radio and/or mobile phone coverage to be improved to achieve better coverage across the area. |
REC265-1108 | 4 - Fire season preparation | Appropriately equipped Incident Control Centres should be identified and/or established throughout the Perth Hills to meet the requirements of a fully resourced Incident Management Team in future bushfire events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1092 | 29 - Operational Health and Safety | CFA and VICSES should: implement risk management processes within regions, districts, brigades and units to understand and manage the local risks associated with their volunteer workforces |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1498 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC261-1513 | 17 - Assets and technology | That the Minister for Police and Emergency Services review the communications technologies used by the NSW Rural Fire Service, Fire and Rescue NSW, the NSW National Parks and Wildlife Service and Forestry NSW during fire fighting operations, to ensure that systems are standardised and effective. Within this context, the potential value of satellite phone technology should be investigated. |
REC261-1494 | 4 - Fire season preparation | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC261-1515 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service: |
REC261-1503 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC261-1509 | 34 - Local knowledge | That the NSW Rural Fire Service, in order to ensure greater respect for volunteer fire fighters’ knowledge and experience in the management of fires: |
REC261-1502 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
REC261-1499 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC260-1071 | 4 - Fire season preparation | The NPWS to consider developing a land management policy that requires hazard reduction around identified assets within the Park and the clearing of fire trials within the Park before the bush fire season commences. Consideration should also be given to developing additional fire trails in the Park, bearing in mind the lack of available fire trails to the south of the John Renshaw Parkway in the park. |
REC260-1055 | 34 - Local knowledge | That the Rural Fire Service together with other land managers develop a program whereby local stakeholders come together regularly (every 2 months during non-fire season and monthly during the fire season) to share intelligence and to consider hazard and incident management measures for implementation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2548 | 17 - Assets and technology | The Civil Aviation Safety Authority shares the risk assessment outputs of Sky Sentinel, its computerised risk assessment system, with the applicable authorisation holder. |
REC258-2560 | 29 - Operational Health and Safety | The Civil Aviation Safety Authority devolve to Designated Aviation Medical Examiners the ability to renew aviation medical certificates (for Classes 1, 2, and 3) where the applicant meets the required standard at the time of the medical examination. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1541 | 17 - Assets and technology | A Stryker unit, or an upgraded firefighting unit, be present at the range sentry point, remain manned and ready to deploy during range activites, with its driver in direct radio contact with the Range Safety Officer. Upon the range being declared clear by the Safety Officer inspecting the range after a demolition serial, the firefighting unit must proceed forward to the range wile the periphery of the range continues to be inspected by the Safety Officer, and remain on the range until the Safety officer declares that the area is clear of fire or that it is otherwise appropriate for the fireghting unit to leave the range area. |
REC257-1544 | 17 - Assets and technology | Defence should not procure any firefighting vehicle for Marrangaroo Training Area without first consulting relevant personnel within the Rural Fire Service on an appropriate type of vehicle, and obtaining training for the personnel proposed to use it. Alternatively, Defence should explore contracted firefighitng support during periods of live-fire on Marrangaroo Training Area. |
REC257-1542 | 17 - Assets and technology | Firefighitng capability at Marrangaroo Training Area be upgraded so that Australian Defence Force members are not placed in situations of unacceptable risk. Specifically, those participating in range practices must have access to a firefighting vehicle close by and easily deployed, and capable of throwing a large quantity of water an appreciable distance into areas adjacent to the ranges, should a fire occur. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1582 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0875 | 34 - Local knowledge | That Tasmania Fire Service reviews its integration of rural local knowledge and volunteer brigades into fire operations, develops and maintains appropriate strategies, and aims to be a best-practice fire service in this regard. |
REC247-0886 | 11 - Evacuation and shelters | That a state-level policy on evacuations be developed in the emergency management plans, including specific requirements for vulnerable people and guidelines for its implementation. |
REC247-0880 | 17 - Assets and technology | That bushfire agencies develop, implement and maintain air operations procedures. |
REC247-0901 | 11 - Evacuation and shelters | That evacuation centres and other centres have plans and arrangements for electrical power redundancy. |
REC247-0935 | 4 - Fire season preparation | That the State Emergency Management Committee includes in its planning, the development of contingency emergency management plans for areas of high risk due to local conditions. |
REC247-0865 | 34 - Local knowledge | That Tasmania Fire Service reviews its position on using local experienced officers on the fire ground in the command model in a structured and systemic way. |
REC247-0879 | 17 - Assets and technology | That bushfire agencies develop procedures for the automatic activation of aircraft to fires at pre-determined trigger points on high fire risk days. |
REC247-0890 | 11 - Evacuation and shelters | That decisions to open Community Fire Refuges and evacuation centres be coordinated with Tasmania Police. |
REC247-0934 | 4 - Fire season preparation | That the State Fire Management Committee considers developing a structured, systemic and proactive bushfire hazard reduction program with municipal councils and Tasmania Fire Service; and advises the Government on any legislative or other changes required to implement such a program. |
REC247-0863 | 34 - Local knowledge | That Tasmania Fire Service considers measures to bring local knowledge into Incident Management Team operations. |
REC247-0878 | 17 - Assets and technology | That bushfire agencies evaluate the use and effectiveness of fixed wing water bombing aircraft. |
REC247-0889 | 11 - Evacuation and shelters | That Tasmania Police be identified as the lead agency on evacuations. |
REC247-0894 | 17 - Assets and technology | That the police and other emergency service organisations discuss their resource issues for emergency operations with the Government. |
REC247-0933 | 4 - Fire season preparation | That the Government considers whether a peak body should be established, with authority to effectively implement a bushfire mitigation plan. |
REC247-0855 | 17 - Assets and technology | That a structure and facilities be established for the State Controller or other person managing multi-agency response and recovery operations. |
REC247-0888 | 11 - Evacuation and shelters | That arrangements are made and appropriate pre-planning occurs to effectively implement the policy on evacuation. |
REC247-0893 | 17 - Assets and technology | That further options to appropriately supplement the resources available for emergency management operations be examined. |
REC247-0931 | 4 - Fire season preparation | That a specific risk prevention and mitigation advisory body be established for the State Emergency Management Committee. |
REC247-0887 | 11 - Evacuation and shelters | That qualifying the evacuation authority in section 47 of the Fire Service Act 1979 be considered — by exempting those people with a pecuniary interest in a property from a directed evacuation where it is reasonable for them to remain. |
REC247-0892 | 17 - Assets and technology | That a review be conducted of the resource capacity and capability to provide effective and efficient emergency operations, including approved improvements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0784 | 17 - Assets and technology | Recommendation 9 TFS should review the capacity of its Fire Information Line to handle very large scale events, and explore additional options for a surge capability for the Fire Information Line. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2593 | 17 - Assets and technology | That network managers develop and document strategic plans for the management of their radio networks. |
REC245-2591 | 17 - Assets and technology | That until the outcome of the Whole of Government project is complete (and interoperability is achieved), emergency services should investigate and implement methods for further improving interoperability. |
REC245-2597 | 17 - Assets and technology | That the project team become independent from any of the entities involved in the Whole of Government network. |
REC245-2595 | 17 - Assets and technology | That stakeholders involved with the Whole of Government radio project re-engage positively to ensure a solution to the current impasse is achieved in the best interests of the stakeholders and the State as a whole. |
REC245-2594 | 17 - Assets and technology | That the network managers produce business cases for all major upgrades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC243-0847 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
REC243-0846 | 17 - Assets and technology | That the Government adequately fund Community Safety and Emergency Services budgets so that fire-bombing aircraft are available on call for rapid deployment throughout Autumn and Spring at short notice to bomb fires at the earliest and safest possible opportunity. |
REC243-0848 | 17 - Assets and technology | That the Government resume funding for the helicopter surveillance service rather than by fixed-wing aircraft along Adelaide, South Coast and other high-risk coastlines during summer recreational periods for monitoring shark and other rescue situations, to bring the State back into line with interstate best practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC242-2649 | 4 - Fire season preparation | That the obligation (following the passage of the Fire and Emergency Services (Review) Amendment Bill 2009) for Chief Fire Officers (CFS & MFS) to require State agencies to clean up fire risk on their land, and to make similar requests to Commonwealth agencies, be strongly implemented. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1009 | 17 - Assets and technology | That the reflective livery on Rural Fire Service Queensland staff vehicles be kept to a minimum of a light bar and affixed Rural Fire Service Queensland logo. These vehicles are to be appropriate to the task and location. |
REC241-1027 | 17 - Assets and technology | That Rural Fire Service Queensland, in consultation with Primary Producer Brigade volunteers, redesign and reconfigure slip-on units to bring the total cost below the level required for asset registration. The redesign should allow for the foam system to be optional. |
REC241-0968 | 4 - Fire season preparation | That a Mitigation Officer position be created to assist the District offices and District Fire Management Groups (refer to Recommendations 40 to 46) in developing their fire management plans and to ensure mitigation work is being conducted. |
REC241-1042 | 17 - Assets and technology | The issue of red and blue lights for RFSQ and SES vehicles be further pursued by the Department of Community Safety |
REC241-1022 | 29 - Operational Health and Safety | That Rural Fire Service Queensland in consultation with the Rural Fire Brigades Association Queensland will undertake a full review of the medical and health protocols to support the new Volunteer organisation. |
REC241-0973 | 17 - Assets and technology | That all land on which rural fire brigade sheds are located be re-evaluated to formalise enforceable lease agreements. |
REC241-1026 | 17 - Assets and technology | That the Rural Fire Service Queensland catalogue accurately reflects the range of equipment available. |
REC241-1039 | 17 - Assets and technology | That the State Government supply and logistics for Personal Protective Equipment and other equipment be urgently reviewed with a focus on timely and cost effective delivery to volunteer members. |
REC241-1000 | 4 - Fire season preparation | That the provisions of the Vegetation Management Act 1999 should be clarified to ensure that effective and accessible firebreaks or fire control lines are established in order that assets can be protected. The decision on the construction of these firebreaks and fire control lines is to be made by the landowner in conjunctions with the local Rural Fire Brigade or Fire Warden |
REC241-1015 | 29 - Operational Health and Safety | That the First Officer or Brigade Officer retain the ability to seek assistance from any person whose services are available at the fire. Any person appointed to provide this assistance should be protected under relevant Workplace Health and Safety and Workcover legislation. |
REC241-0970 | 17 - Assets and technology | That RFSQ retain responsibility for Air Operations and re-evaluate avenues for cost recovery when aircraft are used by other agencies. The coordination of incendiary tasking to support mitigation should sit with the RFSQ in coordination with other agencies |
REC241-1025 | 17 - Assets and technology | That an ‘Options Paper’ be developed by District Inspectors on the suitability and supply of PPE and equipment to volunteers for their district. |
REC241-1036 | 17 - Assets and technology | That each District Inspector prepare a report on vehicles required over the next ten years based on current age of fleet. |
REC241-0998 | 4 - Fire season preparation | That Rural Fire Service Queensland instigates a hazard mitigation operational period, (E.G. Operation Cold Burn), at suitable times each year as appropriate by area. |
REC241-0965 | 29 - Operational Health and Safety | That the number of Bushfire Safety Officer positions be, over time, increased so that one BSO operates out of each District office. |
REC241-1024 | 17 - Assets and technology | That the Rural Fire Service Queensland revoke its current 20 year maximum age policy on volunteer Brigade vehicles to allow Brigades wanting to retain their vehicle to do so, providing the vehicle has an annual mechanical certificate. A 30 year maximum age policy for vehicles will replace the 20 year policy. |
REC241-1029 | 17 - Assets and technology | That a policy be developed around the ownership, insurance and safe use and operation of All Terrain Vehicle 4WD vehicles by brigades for fire fighting purposes. |
REC241-0992 | 4 - Fire season preparation | That District Inspectors be responsible for consultation with Fire Wardens during the development of District fire management plans. |
REC241-1012 | 17 - Assets and technology | Use of private aircraft to be at the discretion of District Inspector or Incident Control and reimbursement of fuel to be authorised accordingly. |
REC241-1028 | 17 - Assets and technology | That vehicles are fit for the purpose and the Brigade locality for which they are intended. A group of two volunteers, in conjunction with the Rural Fire Brigades Association Queensland, should be charged with reviewing current models and providing Recommendations on vehicle suitability. |
REC241-0991 | 4 - Fire season preparation | That annual planning be undertaken at each level that addresses hazard actions across all disaster management phases (ie: prevention, preparation, response and recovery), with a focus on vegetation and land management. This planning is to be consistent with the hazard- specific planning envisaged under the Queensland Disaster Management Arrangements and be supported by guidelines to be developed and issued by Rural Fire Service Queensland. District plans are to be approved by the Director- General or equivalent for the Department of Community Safety and will inform a State Wildfire Management Plan to be approved by the State Disaster Management Group. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2709 | 17 - Assets and technology | That the information and communication technology solution being developed to provide situational awareness, decision support, event management and that logs critical decisions receives urgent attention to ensure timely completion. |
REC239-2774 | 39 - Disaster Risk Management | Those final determinations of disaster management districts include consultation with the Local Government Association Queensland, the Queensland Fire and Rescue Service and other Government departments. |
REC239-2737 | 29 - Operational Health and Safety | That the workplace health and safety reporting system be reviewed to facilitate ease of reporting. |
REC239-2664 | 17 - Assets and technology | That Queensland Corrective Service should increase the use of technology as an alternative to court appearances and ensure the provision of appropriate number and level of facilities under its control. |
REC239-2711 | 39 - Disaster Risk Management | That the Inspector General Emergency Management be empowered to provide an assurance to Government that the disaster management system is both appropriate and capable of dealing with complex events. |
REC239-2778 | 17 - Assets and technology | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative ANPR models should form part of the design architecture considerations. |
REC239-2692 | 39 - Disaster Risk Management | That the Queensland Police Service Disaster Management Unit is to be permanently located at the State Disaster Coordination Centre to work on a day to day basis with the proposed new Department of Fire and Emergency Services. |
REC239-2775 | 17 - Assets and technology | That efforts by the courts, the Director of Public Prosecutions, the legal profession, Queensland Corrective Services and the Queensland Police Service to adopt technology for court processes should be supported through Government funding in so far as they create efficiencies, result in lower costs and produce better human rights outcomes. |
REC239-2781 | 34 - Local knowledge | That the current provisions enabling there to be a Ministerial Direction be maintained and actioned as the Minister sees fit. |
REC239-2691 | 39 - Disaster Risk Management | That the Commissioners of Police and the Queensland Fire and Rescue Service review the current district disaster boundaries as a matter of urgency in-line with the findings and recommendations of the Auditor–General’s report into the Queensland disaster management system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2840 | 39 - Disaster Risk Management | The committee recommends relevant authorities work with community service organisations in both planning responses to and responding to extreme weather events, in particular those organisations that provide vital services to vulnerable groups. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1625 | 4 - Fire season preparation | The Emergency Services Agency and the Territory and Municipal Services Directorate should improve information capture and sharing by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2851 | 17 - Assets and technology | I recommend that consideration should be given to acquiring two personal water craft for deployment by appropriately trained and equipped staff of the AFP or the VMRS or both on Christmas Island. |
REC227-2850 | 17 - Assets and technology | I recommend that the AFP be provided with a search and rescue vessel which is suitable to the specific conditions of Christmas Island. I further recommend that steps be taken to ensure that if for any reason the search and rescue vessel is not available, there is a replacement vessel on Christmas Island capable of providing an emergency response in difficult sea conditions. |
REC227-2848 | 17 - Assets and technology | I recommend that the AFP take steps to determine whether access can be obtained to the National Search and Rescue Council endorsed SARMAP program covering the Australian Search and Rescue Region as well as adjoining tiles for Indonesia. Steps should be taken to ensure that if possible coverage would include high traffic areas where SIEVs enter the Australian Search and Rescue region allowing timely search and rescue plans to be drawn up for any potential incidents. |
REC227-2846 | 17 - Assets and technology | I recommend that Border Protection Command continues to examine ways of improving its surveillance capability around Christmas Island so that the risk of SIEVs arriving undetected is reduced. |
REC227-2859 | 17 - Assets and technology | I recommend that the issue of RHIB jet intake protection be allocated a high priority and that there be ongoing investigation of possible solutions to reduce the problem. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0583 | 17 - Assets and technology | The state should converge on a single communications platform for all emergency management and support agencies. |
REC226-0549 | 4 - Fire season preparation | All forms of fuel modification should be available to fire managers. |
REC226-0582 | 17 - Assets and technology | The state should progressively align on a shared platform, such as WebEOC, to establish a COP [Common Operating Picture or Platform?]. |
REC226-0541 | 4 - Fire season preparation | Experienced forecasters and fire behaviour experts should be embedded in DEC at least at a state level to ensure that fire risks are properly understood by decision makers. |
REC226-0592 | 11 - Evacuation and shelters | Decisions on evacuations need to be made early enough for people to be fully informed, prepared and to move to a place of greater safety. Failure to conduct good planning can create situations where loss of life can occur |
REC226-0561 | 34 - Local knowledge | Suitably experienced local representatives should be engaged to provide advice to the IMT in all Level 2 and Level 3 incidents at the earliest opportunity. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0533 | 17 - Assets and technology | As a minimum requirement, all vehicles entering the fireground must be fitted with an accessible fire blanket – one per person in each vehicle plus roll down, in-cab, radiant heat shields. |
Rec-ID | Code | Recommendation |
---|---|---|
REC223-0519 | 34 - Local knowledge | The Department of Environment and Conservation review its practices and procedures in the undertaking of prescribed burns so as to fully utilise the skills available to it in a seamless way including but not limited to: · volunteer bushfire brigades, especially in regard to use as a source of local advice; and · staff of the Fire and Emergency Services Authority of Western Australia. |
Rec-ID | Code | Recommendation |
---|---|---|
REC222-1852 | 29 - Operational Health and Safety | The Minister for Health immediately establish the road trauma counselling service to be funded by the Road Trauma Trust Account. |
REC222-1850 | 29 - Operational Health and Safety | The Ministers for Emergency Services, Environment and Police ensure that their departments develop as a high priority a computer system for tracking their staff and the number of traumatic events they have attended over a particular period. |
REC222-1849 | 29 - Operational Health and Safety | Departmental chief executives of the Western Australia Police, Department of Environment and Conservation and the Fire and Emergency Services Authority should be made personally responsible for the psychological health (as a result of critical incident trauma) of their staff and volunteers. This obligation should be reflected in their performance agreements. |
REC222-1848 | 29 - Operational Health and Safety | The Western Australian Government amend current State occupational health and safety legislation so that it includes a definition for ‘health’ that includes psychological health. |
REC222-1859 | 29 - Operational Health and Safety | The Attorney General and the Ministers for Health and Mental Health fund their departments to establish a peer support program by the end of 2013 for their staff undertaking stressful tasks during a disaster or critical incident. |
REC222-1858 | 29 - Operational Health and Safety | The Ministers for Environment, Police, Child Protection and Emergency Services fund additional chaplaincy services, particularly for staff and volunteers based in rural and regional Western Australia. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1877 | 39 - Disaster Risk Management | Regulators can help to achieve improved outcomes by considering the issues identified by this review |
REC215-1876 | 39 - Disaster Risk Management | Fire services can improve outcomes by initiating discussions with landfill operators about fire management planning and emphasising the critical importance of water supplies and early intervention |
Rec-ID | Code | Recommendation |
---|---|---|
REC209-1667 | 39 - Disaster Risk Management | Prepare a formal proposal for the creation of pastoral/Indigenous Lands Fire Management Teams. |
REC209-1666 | 39 - Disaster Risk Management | Investigate the application and cost of the creation of District Coordination Officers to key high demand brigade districts. |
REC209-1675 | 39 - Disaster Risk Management | PowerWater Corporation be consulted with the intention of establishing a Memorandum Of Understanding for the maintenance of PowerWater land for the purpose of coordinated fire reduction. |
REC209-1673 | 4 - Fire season preparation | That a trial be commissioned to assess the most effective means of road verge management, including regional variations, for future application across the Territory. |
REC209-1674 | 39 - Disaster Risk Management | That the concession holder of the rail corridor be approached to formalise a Memorandum of Understanding for the maintenance of the railway corridor for the purposes of fuel load reduction. |
REC209-1672 | 4 - Fire season preparation | Annual property inspections assessing access and fuel loads are conducted in all peri urban areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2881 | 17 - Assets and technology | Extend ICT governance arrangements to all applications and subject in-house development to rigorous approval processes. |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0307 | 11 - Evacuation and shelters | When people are being moved away from their homes it’s important that they move to a place of greater safety and that their movement is relatively assured. |
REC203-0293 | 34 - Local knowledge | Suitably experienced personnel with local knowledge should be connected to the Operations and Planning section in all Level 3 incidents in the vicinity of substantial settlements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC202-0496 | 17 - Assets and technology | The Minister for Emergency Services ensure that a whole-of-government equipment register of the firefighting equipment held by FESA, DEC and local government authorities is in place for the 2012-13 bushfire season. |
REC202-0506 | 17 - Assets and technology | The Minister for Emergency Services ensure that FESA has the funds to implement the installation and use of WebEOC for use during the 2011-12 bushfire season and immediately put in place common protocols with the Police and DEC to record significant events during a bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC201-0249 | 17 - Assets and technology | FRS fire appliance allocation and training needs to be reviewed to enhance offensive bushfire capability within the metropolitan area. |
REC201-0259 | 11 - Evacuation and shelters | FESA seek legal and policing advice regarding the policy to leave residents who chose not to evacuate in a declared ‗dangerous area‘ after a bushfire. |
REC201-0257 | 29 - Operational Health and Safety | FESA needs to place greater priority on the appointment of Safety Advisors to Level 3 incidents as is reflected in WESTPLAN Bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-0388 | 17 - Assets and technology | The Water Corporation immediately review the outstanding orders for hydrant repairs and develop strategies to reduce the backlog. |
REC200-1722 | 39 - Disaster Risk Management | Emergency Management Western Australia and the State Emergency Management Committee amend WESTPLAN-BUSHFIRE to require State Emergency Coordination Group meetings to be held at the State Coordination Centre in West Leederville. |
REC200-0387 | 17 - Assets and technology | The State Government transfer responsibility for the installation, removal, maintenance of fire hydrants to the Water Corporation, in accordance with the Recommendations of the 2006 CDJSC Inquiry into Fire and Emergency Services Legislation. |
REC200-1698 | 39 - Disaster Risk Management | The Fire and Emergency Services Authority, the Department of Environment and Conservation and local governments jointly develop a single, integrated system for fuel load assessment and management. |
REC200-1714 | 11 - Evacuation and shelters | Hazard Management Agencies overseeing the response to incidents on the urban fringe select evacuation centres that are well within the urban environment and unlikely to be impacted by the incident. |
REC200-0378 | 17 - Assets and technology | Western Power and the Water Corporation continue to work collaboratively to assess options to better protect the power supply to water pumping stations in bushfire prone areas. |
REC200-1700 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: |
REC200-0365 | 17 - Assets and technology | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA’s own policy of ‘Use of Private Vehicles in Fires’. |
REC200-1705 | 29 - Operational Health and Safety | The Fire and Emergency Services Authority (FESA) review its program to decommission vehicles and ensure that when such vehicles are offered during an incident that FESA staff adhere to FESA‟s own policy of „Use of Private Vehicles in Fires‟ |
REC200-0364 | 17 - Assets and technology | The Fire and Emergency Services Authority review its use of the Australian Interagency Incident Management System to ensure that the most appropriate resources (including aerial resources) are used to respond to an incident. If resources are rejected during an incident either through the decision making process or other grounds, the reason for the decision should be documented. |
REC200-0374 | 11 - Evacuation and shelters | Hazard Management Agencies overseeing the response to incidents on the urban fringe select evacuation centres that are well within the urban environment and unlikely to be impacted by the incident. |
REC200-0360 | 4 - Fire season preparation | The Interagency Bushfire Management committee develop and oversee a work program to: conduct site specific assessments to assess current fuel loads assess, analyse and prioritise bushfire risk on land within and adjacent to communities develop a three year rolling mitigation works program with annual implementation and review. This work should commence independently of any decision on the most effective online integrated system. All data collected should be uploaded to the SLIP. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0492 | 34 - Local knowledge | the state comprehensively pursue the objective of achieving (where possible) the priority outcomes of the National Strategy for Disaster Resilience and the imperative of shared responsibility, in particular by: • requiring that local knowledge is considered as a critical component of all phases of emergency management • involving local communities in the development and ownership of community resilience plans based on an ‘all hazards’ approach and tailored for the specific needs of each community • encouraging local communities to form resilience committees to develop and administer community resilience plans • nominating Victoria Police as the lead agency in initiating the strategy to develop community resilience committees; and • requiring emergency service agencies to consult and engage with local community resilience committees in the preparation, planning, response and recovery phases of emergency management. |
REC199-0452 | 17 - Assets and technology | the state ensure that any new systems and equipment purchased by state emergency management agencies are interoperable with other relevant agencies to the fullest extent possible. This should involve the state establishing a procurement gateway process with input from the Emergency Services Commissioner. |
REC199-0421 | 34 - Local knowledge | the state take the necessary measures to require that local knowledge is considered in flood risk planning, including verification of flood maps and flood response plans. |
REC199-0410 | 17 - Assets and technology | the state take the necessary measures to upgrade existing manual stream and rain gauges and ensure that all future gauges provide a seamless transfer of data from the gauges to the Bureau of Meteorology. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0238 | 34 - Local knowledge | Encourage ICCs to use local knowledge to review templates prior to release. |
REC196-0234 | 34 - Local knowledge | Ensure that local knowledge, local flavour and local language is used where possible in the development of all community bushfire warnings. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0334 | 4 - Fire season preparation | The Fire Services Commissioner leads a task force to: a. identify legislation, policies and guidelines that impact on vegetation management and recommend necessary changes b. develop a set of risk-based standards for vegetation management with respect to strategic firebreaks and the assets being protected c. integrate maintenance standards across all areas of responsibility and tenure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2907 | 29 - Operational Health and Safety | a) For the purposes of designing and implementing its regulatory activities, National Offshore Petroleum Safety Authority (NOPSA) should continue to identify priority hazards and risks and their underlying causes, in consultation with the NOPSA Advisory Board and stakeholders (see Theme 9, Stakeholder engagement). |
REC189-2912 | 29 - Operational Health and Safety | The review team recommend that the safety case system be strengthened by including provisions for a design notification scheme along the lines of that under the British Offshore Safety Case Regulations. |
REC189-2911 | 29 - Operational Health and Safety | The review team recommend that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC186-0395 | 17 - Assets and technology | The committee further recommends that any allocation of broadband spectrum to emergency service organisations (ESOs) for PPDR must be provided on the basis of interoperability amongst Australian ESOs and with ESO counterparts overseas. |
REC186-0394 | 17 - Assets and technology | The committee recommends the Commonwealth Government allocate sufficient spectrum for dedicated broadband public protection and disaster relief (PPDR) radiocommunications in Australia. |
REC186-0393 | 17 - Assets and technology | The committee recommends that interoperability of narrowband voice radiocommunications between federal, state and territory emergency service organisations is achieved as soon as practicable and that all services attending major incidents be compelled to maintain a common emergency communications platform to ensure seamless real time communication from and to the Incident Controller. |
Rec-ID | Code | Recommendation |
---|---|---|
REC183-0120 | 17 - Assets and technology | Maintaining the DEC fleet of tankers, bulldozers and low loaders is crucial to DEC’s fire management and control capability. |
REC183-0119 | 17 - Assets and technology | The development of a three year aerial firefighting strategy for W.A. would ensure optimal development of a joint air capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC182-0133 | 29 - Operational Health and Safety | FESA reviews its approach to safety and safety culture. |
REC182-0134 | 17 - Assets and technology | FESA reviews its air reconnaissance capability and determines if multiple multi-sensor air reconnaissance aircraft or unmanned aerial vehicles are required for managing concurrent and/or complex incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0171 | 17 - Assets and technology | The State, in conjunction with Emergency Management Australia and the Department of Defence, develop an agreement that allows Commonwealth aerial resources that are suitable for firefighting and support activities to be incorporated in preparedness plans and used on days of high fire risk. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0212 | 4 - Fire season preparation | VicRoads implement a systematic statewide program of bushfire risk assessment for all roads for which it is responsible, to ensure conformity with the obligations in s. 43 of the Country Fire Authority Act 1958 and with the objectives expressed in the VicRoads 1985 Code of Practice. |
REC181-0170 | 17 - Assets and technology | The Country Fire Authority and the Department of Sustainability and Environment amend their policies on aerial preparedness and standby arrangements, their dispatch protocols and the management of aircraft in order to do the following: ■ require that at locations that attract the risk assessment or preparedness level A on code red days all personnel needed for air operations must be on standby by 10.00 am; ■ establish a system that enables the dispatch of aircraft to fires in high-risk areas without requiring a request from an Incident Controller or the State Duty Officer. |
REC181-0211 | 4 - Fire season preparation | The State and Commonwealth provide for municipal councils adequate guidance on resolving the competing tensions arising from the legislation affecting roadside clearing and, where necessary, amend environment protection legislation to facilitate annual bushfire-prevention activities by the appropriate agencies. |
REC181-0210 | 4 - Fire season preparation | The State amend the exemptions in clause 52.17-6 of the Victoria Planning Provisions to ensure that the provisions allow for a broad range of roadside works capable of reducing fire risk and provide specifically for a new exemption where the purpose of the works is to reduce bushfire risk. |
REC181-0176 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment adopt the title ‘safety officer’ (as opposed to ‘safety adviser’) and require without exception that a safety officer be appointed to every level 3 incident management team. |
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
REC181-0192 | 4 - Fire season preparation | The Department of Sustainability and Environment develop and administer a collective offset solution for individual landholders who are permitted to remove native vegetation for the purpose of fire protection. |
REC181-0174 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures for investigating safety incidents and ‘near-misses’ to ensure that all dangerous incidents, including back-burns, are fully investigated and that all relevant people are consulted and informed of the results. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0150 | 17 - Assets and technology | The committee recommends that the Commonwealth co-ordinate a national approach to the pooling of ground fire fighting resources across agencies and jurisdictions to maximise the efficiency of their use. |
REC176-0140 | 4 - Fire season preparation | The Commonwealth seek agreement from the states and territories that would enable it to evaluate the adequacy of fuel reduction programs applied by public land management agencies in high bushfire risk areas, and audit their implementation against the program's stated objectives. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0101 | 4 - Fire season preparation | The prioritisation, by the State Emergency Management Committee (SEMC), of bushfire preparedness activities including updating WESTPLAN - BUSHFIRE and coordinating bushfire exercises prior to the 2009/10 bushfire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0019 | 17 - Assets and technology | A centralised, regional, multi-agency resource coordination and tracking system/facility be established to accommodate and coordinate the movement of resources from all agencies within and between regions. |
REC172-0028 | 17 - Assets and technology | Ensure the S61 helicopter has all appropriate channels for water bombing operations throughout the State by including this requirement on a pre-deployment checklist. |
REC172-0029 | 17 - Assets and technology | Provide a photocopier in the Mobile Communications Facility or the mobile equipment cache that is capable of large volume production of collated documents. |
REC172-0030 | 29 - Operational Health and Safety | A strategically located Staging Area serviced with check in/out personnel should be considered as early as possible at incidents involving an extended attack. |
REC172-0026 | 17 - Assets and technology | At large incidents a communications bus should be provided for the use by Air Ops and a designated work space should be provided for the Air Ops management group. |
REC172-0048 | 4 - Fire season preparation | A standard for signage at fire incidents be developed and caches of this equipment be established at DEC and Local Govt facilitates to enable its rapid and effective deployment by Ground Support Unit at fires. |
REC172-0047 | 17 - Assets and technology | There is an established need to develop mobile accommodation and accommodation facility support solutions that allows an acceptable standard of accommodation to be provided to fire fighters in close proximity to the incident. |
REC172-0025 | 17 - Assets and technology | Suppression resources should be ordered and mobilised as 2 truck Strike Teams with a STL and consistently deployed to the fire ground as a unit. |
REC172-0046 | 4 - Fire season preparation | Perishable food should be ‘stamped’ with an expiry date. |
REC172-0038 | 34 - Local knowledge | The ISU should be provided with a person with local knowledge at Level 3 incidents. |
REC172-0045 | 4 - Fire season preparation | Food storage should be a design consideration in all fire ground appliances |
REC172-0044 | 4 - Fire season preparation | Pre-season arrangements to provide high quality food should be encouraged in all emergency management plans |
Rec-ID | Code | Recommendation |
---|---|---|
REC171-0069 | 17 - Assets and technology | That in any consideration being given to the allocation of responsibility for control of operations in respect of major fires, consideration be given to the availability of technology and other resources, particularly when particular skills are required to make best use of such technology or resources. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3004 | 17 - Assets and technology | That the Tasmania Fire Service consider improvements in radio units installed in breathing apparatus: |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0095 | 11 - Evacuation and shelters | Planning and consultation be undertaken by EMQ with all levels of the Disaster Management system to ensure that necessary risk-based disaster evacuation plans are prepared at Local, District and State levels, supported by necessary community education and preparedness programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3432 | 17 - Assets and technology | That port/channel managers are required to ensure, through service agreements, licensing, direct acquisition or other means as appropriate, the availability of the critical Level 1declared assets. |
REC158-3431 | 17 - Assets and technology | That port/channel managers are required to identify in the declared asset system (in conjunction with the emergency services) critical Level 1 declared assets and other Level 2 declared assets, that may be required in support of a marine emergency within the port, and that identified resource availability, accessibility and call out time is recorded. |
REC158-3430 | 17 - Assets and technology | That the nominated marine safety authority is responsible for development of a declared asset system and is required to ensure that port/channel managers utilise and maintain the declared asset system. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1803 | 17 - Assets and technology | That the Minister for Emergency Services give further consideration to acquiring a firefighting helicopter to be permanently or primarily stationed in South Australia. |
REC153-1779 | 4 - Fire season preparation | That the South Australian Farmers’ Federation encourage its members and constituents to keep and maintain on rural land in proper working order machinery that is capable of removing, modifying or reducing cropping stubble at short notice in order to minimise or mitigate bushfire risk. |
Rec-ID | Code | Recommendation |
---|---|---|
REC150-3122 | 29 - Operational Health and Safety | QFRS implement a system to monitor the condition and safety of brigade buildings and equipment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3135 | 29 - Operational Health and Safety | The initial acceptance of a new facility Safety Case should be in conjunction with inspection of a facility upon commencement of operations. |
REC149-3128 | 29 - Operational Health and Safety | National Offshore Petroleum Safety Authority (NOPSA) should develop guidelines in consultation with stakeholders to provide clarity and consistency to the process which ultimately will result in better safety outcomes. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3147 | 29 - Operational Health and Safety | As all stakeholders have responsibility for safe outcomes, decisions regarding target subjects for safety promotion need to have the support of all stakeholders including NOPSA and the workforce. Industry, which ultimately has the responsibility for managing risk as well as funding the promotion, should take a leadership role in implementation. |
REC149-3144 | 29 - Operational Health and Safety | The Safety Case proponent should be allowed some flexibility to involve appropriate experience matched with the proposed workforce competencies to enable the Safety Case to be developed with value adding processes. Subsequent to the hiring of the workforce Final Government Response Offshore Petroleum Safety Regulation Inquiry and 2008 Review of NOPSA Operational Activities and preferably before the commencement of operations a review of the Safety Case should take place with the new workforce to ensure they understand the accepted Safety Case, its risks and Safety Management Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3209 | 39 - Disaster Risk Management | The Committee notes that major initiatives relating to climate change adaptation risk assessment and infrastructure are currently in progress. Given that much of Australia’s infrastructure is in the coastal zone and the particular threats facing the coastal zone from climate change, involving significant socioeconomic costs, the Committee recommends that the Australian Government ensure there is a comprehensive national assessment of coastal infrastructure vulnerability to inundation from sea level rise and extreme sea level events. |
REC145-3220 | 3 - Biodiversity | The Committee recommends that, in seeking to expand the area protected within Australia’s National Reserve System (NRS) under the Caring for our Country program, the Australian Government focus on high biodiversity coastal habitat, including more effective off-reserve coastal zone conservation and expanded coastal reserves that provide larger buffer zones. In undertaking this initiative, the Australian Government should continue to work with state/territory and local governments, Indigenous groups, conservation organisations, private landholders and other stakeholders to ensure that these protected areas are added to the NRS in a timely manner. |
REC145-3203 | 39 - Disaster Risk Management | The Committee recommends that: |
REC145-3205 | 17 - Assets and technology | The Committee recommends that, following the completion of the ‘first pass’ National Coastal Vulnerability Assessment, the Australian Government consider the resourcing and financing of second and third pass assessments, in conjunction with state, territory and local government authorities. |
REC145-3227 | 39 - Disaster Risk Management | The Committee recommends that coastal based Natural Resource Management bodies seeking funding under the Caring for our Country program have coastal and marine priorities, as well as coastal zone management principles integrated in their management plans. |
REC145-3210 | 39 - Disaster Risk Management | The Committee recommends that the Department of Climate Change, in collaboration with the Queensland Government, CSIRO and Indigenous communities in the Torres Strait, undertake a major study into the vulnerability of the Torres Strait to the impacts of climate change and provide assistance in the development of an adaptation plan. |
REC145-3225 | 3 - Biodiversity | The Committee recommends that the Australian Government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC143-3580 | 17 - Assets and technology | That FESA investigate the use of new technologies such as Voice over Internet Protocol (VoIP) for supplementing the dissemination of WANDRA information in cases where landlines have been disrupted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3563 | 17 - Assets and technology | An additional secure emergency oxygen supply source to be located in the BK 117 helicopter. An internal supply is preferred. |
REC140-3561 | 17 - Assets and technology | Development of a helipad at Mersey Hospital. |
REC140-3560 | 17 - Assets and technology | RHH requires a helipad. Plans to rebuild RHH must include a helipad at its earliest stage of conception. |
REC140-3559 | 17 - Assets and technology | A service level agreement is negotiated with the Police department that will cover access, tasking, price, equipment and staffing. This will enable a more strategic use of the helicopter. |
REC140-3565 | 17 - Assets and technology | The TMRS medical equipment inventory requires an overhaul. The TMRS medical equipment should be located with the TMRS team. |
REC140-3556 | 17 - Assets and technology | The use of hospital transport vehicles to support retrieval operations be investigated. |
REC140-3564 | 17 - Assets and technology | The medical equipment used in retrieval and air ambulance duties undertaken by helicopter and fixed wing must be standardised. |
Rec-ID | Code | Recommendation |
---|---|---|
REC139-3551 | 39 - Disaster Risk Management | The SA Country Fire Service to analyse the Coroner’s Report into the Wangary Bushfire 2005, and consider the relevant recommendations from this report in the implementation of the Ministerial Bushfire Management Review recommendations. |
REC139-3549 | 39 - Disaster Risk Management | The SA Country Fire Service investigates the establishment of a Minister’s Bushfire Risk Management Reward Scheme. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3600 | 34 - Local knowledge | The Department of Primary Industries continue to consult local community about emergency planning and sites for disposal to retain confidence in the event of a genuine emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-2008 | 34 - Local knowledge | That, if he is willing to participate, Mr John Lowe be made a member of the implementation taskforce to which I refer in recommendation 70 |
REC126-2007 | 34 - Local knowledge | That the views and concerns expressed by the ACT Sustainable Rural Lands Group be taken into account when implementing the recommendations in this report |
REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
Rec-ID | Code | Recommendation |
---|---|---|
REC122-3785 | 4 - Fire season preparation | The Committee recommends that the government, via the CFS, coordinate the preparation and implementation of native vegetation management plans that incorporate management of fuel loads and includes a prescribed burning regime for the area. |
REC122-3795 | 3 - Biodiversity | The Committee recommends that the government assess the impact on fauna movement prior to managing native vegetation. |
REC122-3783 | 4 - Fire season preparation | The Committee recommends that the government establish designated fire safety areas within native vegetation and at road intersections. |
REC122-3794 | 3 - Biodiversity | The Committee recommends that when preparing the plan for fire management (including identifying where and when to undertake prescribed burning, firebreaks and fire access tracks) consideration must be given to the impact on local fauna. |
REC122-3784 | 34 - Local knowledge | The Committee recommends that the government provide authority to a single community representative body to authorise clearing of native vegetation for fire management. (The community representative body must incorporate the CFS, DEH, Native Vegetation Council and local council) |
REC122-3782 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities prepare a management plan that includes firebreaks and access tracks in the region, including the location of current breaks and access tracks and where breaks and tracks need to be established. |
REC122-3793 | 3 - Biodiversity | The committee recommends that the government actively manage native vegetation for fuel loads, weeds and pests. |
REC122-3781 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities assess fire tracks and breaks to determine if firebreaks and access tracks need to be wider and/or native vegetation removed so that it does not impinge on firebreaks or tracks. |
REC122-3792 | 3 - Biodiversity | The Committee recommends that, after a fire, as much vegetation as feasible be retained to minimise soil erosion from wind and first rains. |
REC122-3780 | 4 - Fire season preparation | The Committee recommends that the government in cooperation with local authorities identify if: sufficient firebreaks and access track exist; they are strategically located; and they are being managed. |
REC122-3787 | 4 - Fire season preparation | The Committee recommends that the Native Vegetation Council provide landholders with assistance for applications for prescribed burning (via a guide, a proforma or staff). |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3737 | 29 - Operational Health and Safety | There must be a minimum of two independent methods of self-initiated emergency escape for passengers from all trains at all times. |
REC121-3682 | 29 - Operational Health and Safety | All new rolling stock should be designed to be compatible with at least level 2 automatic train protection discussed in chapter 7 of this report. |
REC121-3743 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must have the external emergency door release clearly marked with the words “Emergency Door Release”. |
REC121-3711 | 29 - Operational Health and Safety | The ITSRR should establish an electronic document control system to enable effective and reliable information to be gathered for monitoring the safety of the New South Wales rail system. |
REC121-3755 | 29 - Operational Health and Safety | The RailCorp Board should require a full review of the safety competence of RailCorp managers to ensure that each has the ability to bring about those safety reforms recommended in this report which are applicable to his or her position. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3735 | 29 - Operational Health and Safety | Risk assessments of occupational health and safety issues by RailCorp should include an analysis of broader public safety risks and not be confined to narrow occupational health and safety issues. |
REC121-3681 | 29 - Operational Health and Safety | RailCorp should progressively implement, within a reasonable time, level 2 automatic train protection with the features identified in chapter 8 of this report. |
REC121-3741 | 29 - Operational Health and Safety | The operation of the train doors should have an override facility whereby the train driver or the guard can override an internal passenger emergency door release system if the door release is interfered with when there is no emergency. There should be an alarm, together with an intercom, in the train guard’s compartment so that, if a passenger attempts to initiate an emergency door release, there is an appropriate delay during which time an alarm sounds in the train guard’s compartment and the guard can then, after first attempting to speak via the intercom to the person concerned, if necessary, override the door release, and make an appropriate announcement over the intercom system in the train. |
REC121-3709 | 29 - Operational Health and Safety | RailCorp should provide access to electronic versions of safety documentation for all operational staff at their workplace. |
REC121-3754 | 29 - Operational Health and Safety | The RailCorp Board should ensure that RailCorp has an adequate and integrated safety management system, including adequate systems for risk assessment, clearly defined safety responsibilities and accountabilities for persons holding management positions, and specific performance criteria against which evaluations can be made of safety performance and accountability for safety performance of all managers. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3734 | 29 - Operational Health and Safety | RailCorp should integrate its management of occupational health and safety into its overall safety management. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3680 | 29 - Operational Health and Safety | All trains must be fitted with a minimum of two independent engineering defences to minimise the risk of derailment or collision in the event of train driver incapacitation. |
REC121-3740 | 29 - Operational Health and Safety | The internal passenger emergency door release should be fitted with a facility which prevents it from operating unless the train is stationary. |
REC121-3707 | 29 - Operational Health and Safety | The safety document management system should provide for the distribution of electronic versions of safety documentation to relevant staff. |
REC121-3749 | 29 - Operational Health and Safety | All new rolling stock must be designed with an area of the roof through which emergency services personnel can access a rail car without encountering wiring or other equipment. That access point must be clearly marked with words such as “emergency services cut here”. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3733 | 29 - Operational Health and Safety | RailCorp’s approach to occupational health and safety should be proactive and involve the systematic analysis of all current hazards, risks and controls and an assessment of their adequacy to reduce the risk of injury to, or death of, employees to an acceptable level. |
REC121-3739 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must be fitted with external emergency door releases which do not require any special key or other equipment to operate. |
REC121-3706 | 29 - Operational Health and Safety | RailCorp should establish a comprehensive safety document management system. |
REC121-3748 | 29 - Operational Health and Safety | All new rail cars must have appropriate signage and lighting identifying escape routes in the case of emergency. |
REC121-3732 | 29 - Operational Health and Safety | If ITSRR accepts such a plan as an appropriate response to the existing weak safety culture, ITSRR should approve it and monitor the effectiveness of the plan. |
REC121-3764 | 29 - Operational Health and Safety | The ITSRR should not grant accreditation to any rail organisation unless it has an integrated safety management system in accordance with any safety management system regulation and the guidelines published from time to time by ITSRR. |
REC121-3738 | 29 - Operational Health and Safety | All passenger trains must be fitted with an internal passenger emergency door release. |
REC121-3702 | 29 - Operational Health and Safety | Random alcohol testing should be continued. |
REC121-3747 | 29 - Operational Health and Safety | All trains should have windows available through which passengers can escape. |
REC121-3731 | 29 - Operational Health and Safety | RailCorp should develop a plan to be submitted to ITSRR to address the deficiencies in the safety culture of RailCorp, including: |
REC121-3759 | 29 - Operational Health and Safety | A Safety Reform Program Director (hereafter referred to as SRPD), reporting directly to the Chief Executive of RailCorp, should be retained to manage, as head of a Safety Reform Program Office, any safety reform program being undertaken by RailCorp. The SRPD should work with the Chief Executive and senior management to ensure the implementation of an integrated safety management system and the cultural change required. The SRPD must have qualifications suitable for recognition by the Australian Institute of Project Management as a master program director. He or she should report to and be under the control of the Chief Executive, to ensure that the accountability of the Chief Executive is not reduced. The SRPD should co-ordinate and integrate any existing rail safety reform programs and, in consultation with and with the authority of the Chief Executive he or she should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
Rec-ID | Code | Recommendation |
---|---|---|
REC113-3904 | 39 - Disaster Risk Management | FESA should: in addition to its current initiatives, develop and implement structured programs (with clearly identified objectives, target groups and time lines for achievement) aimed at: |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3921 | 17 - Assets and technology | That the recommendations of the 2000 DPI report into the reference collection’s storage facility be implemented, to secure the collection in a purpose-built facility. |
REC112-3928 | 3 - Biodiversity | That DPI formalises agreements within the Regional Services and Agriculture Division to ensure that plant health information is included in extension programs. |
REC112-3911 | 3 - Biodiversity | That DPI develops a consistent process to identify, assess and prioritise potential plant pest and disease threats, and aligns it with prioritisation processes used at the national level by Plant Health Australia. |
Rec-ID | Code | Recommendation |
---|---|---|
REC111-3941 | 39 - Disaster Risk Management | That the State Disaster Management Group supported by the Department of Emergency Services ensures that State-wide a robust disaster risk management process is established that includes the aggregation of relevant information from local, district, functional and threat specific plans to develop a hazard risk profile for Queensland. |
REC111-3940 | 39 - Disaster Risk Management | To enhance disaster risk management planning processes, it is recommended that the State Disaster Management Group supported by the Department of Emergency Services develop a suitable performance management system to ensure local, district, functional and threat specific Disaster Management Plans are — |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2246 | 34 - Local knowledge | That DSE undertake community consultation on policies relating to roads and access tracks on public land, particularly in respect to fire management. |
REC104-2233 | 34 - Local knowledge | That communities, public land managers, Water Authorities and Catchment Management Authorities jointly identify and implement local and environmentally sound solutions to improve the availability of water for firefighting through the Municipal Fire Management Planning process. |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2251 | 11 - Evacuation and shelters | That Victoria Police ensure all police members understand the Victorian legislation in relation to evacuation, and that any decision to recommend evacuation remains with the Incident Controller. |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
REC104-2203 | 11 - Evacuation and shelters | That CFA further develops the information supporting the decision to stay or go, to incorporate a better understanding of both the likely consequences of leaving home at inappropriate times, and the conditions and |
REC104-2286 | 17 - Assets and technology | That CFA, having regard to terrain, continue to review the mix of firefighting appliances currently in service. In particular, consideration should be given to the number and distribution of smaller ‘slip-on’ type equipment. |
REC104-2270 | 29 - Operational Health and Safety | That DSE and CFA continue to stress firefighter safety as their highest priority for incident managers and fire ground supervisors |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2177 | 39 - Disaster Risk Management | The Committee recommends that state and territory governments be required to regularly perform risk assessments to the land within their jurisdictions to ensure that bushfire prone areas are accurately identified |
REC098-2181 | 11 - Evacuation and shelters | The Committee recommends that the Australasian Fire Authorities Council’s suggested evacuation protocol be adopted by all of the Australian States and Territories. |
REC098-2139 | 17 - Assets and technology | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments initiate consideration of the relaxation of restrictions on the movement of fire fighting equipment |
REC098-2151 | 29 - Operational Health and Safety | The Committee recommends that the Commonwealth Attorney-General engage the Commonwealth, states and territories in a review of occupational health and safety legislation as it affects the proper and effective functioning of bush fire services. |
REC098-2148 | 3 - Biodiversity | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments develop a mechanism that ensures that appropriate measures are taken by public and private land |
REC098-2136 | 4 - Fire season preparation | The Committee recommends that the Commonwealth through the National Heritage Trust assist the states and territories in the construction, maintenance and signage of fire trail networks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC037-4169 | 4 - Fire season preparation | Mitigation and preparedness be enhanced and maintained for the future. Some co—ordinating mechanism or system be introduced at State Government level for this purpose. [Reference paragraphs: 114 to 128] |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4136 | 34 - Local knowledge | The Bush Fires Board appoint a Regional Committee of Board members co-opt local members for each climatic region of the State to study the bush fire control problems of the region and advise the Board so that inter alia adequate attention may be given by the Board to co-ordinating the beginning and termination of the prohibited burning times in adjoining districts and to any advisable variations of these duties according to seasonal conditions each year. |
REC019-4153 | 17 - Assets and technology | No opportunity be lost by the Forests Department to improve the efficiency of their fire fighting gangs, radio and other equipment in the light of the latest practical and scientific developments. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3952 | 4 - Fire season preparation | It is recommended that the question of the future responsibility be made certain and that the body so made responsible keep the grounds of the hospital free from undergrowth and trees wherever their presence may be a possible source of future danger. |
REC016_3950 | 4 - Fire season preparation | It is recommended that on days of abnormal danger loads of briquettes be not kept in the station yard. The real danger, which transcends in gravity the danger of time destruction of loads of briquettes, is that the prevailing wind or a change of wind might carry showers of burning embers to the town, which is but the width of a road away, and thereby cause material damage in the town. It is further recommended that the yard and its surroundings be kept clear of scrub and growth; and that special provision be made for quelling fire which may break out in the deposits of inflammable dust which lie in time yard. |
REC016_3949 | 17 - Assets and technology | It is recommended that the A.R.P. dams or earth tanks be kept filled during possible danger periods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3981 | 3 - Biodiversity | To prohibit the preparation of baits for the destruction of rabbits and other noxious animals in which stick phosphorus is used at the time of mixing on any farm, pastoral or grazing area. |
REC013_3978 | 4 - Fire season preparation | Where possible to build stone or brick fireplaces for the use of travellers, teamsters, and drovers on the camping areas that are mostly used and where there is a risk of fire. |
REC013_3976 | 4 - Fire season preparation | To burn camping areas at suitable water and camping reserves. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3992 | 17 - Assets and technology | That the use of a spark-arrester and cinder-arrester by the Railway Department shall not constitute a defence to an action for damage caused by fire escaping from a locomotive, unless the Department proves that such spark-arrester and cinder-arrester were in a thoroughly efficient condition when the fire took place. |
REC004-3996 | 17 - Assets and technology | That the standard pattern of cinder arrester be affixed to the ash-pans in all locomotives during the summer months. |
REC004-3994 | 17 - Assets and technology | That the Railway Department, while gradually reducing the number of different types of locomotives, should steadily keep in view the adoption of English and American railway practice, by providing engines with larger boilers, fire boxers, and smoke-boxes, and with wide blast-pipes, in order to insure ample steaming power with a minimum of forced draught. |